[go: up one dir, main page]

CN109537578A - A kind of elongated degree shock insulation campshed shockproof structure that intensively drills - Google Patents

A kind of elongated degree shock insulation campshed shockproof structure that intensively drills Download PDF

Info

Publication number
CN109537578A
CN109537578A CN201910030059.8A CN201910030059A CN109537578A CN 109537578 A CN109537578 A CN 109537578A CN 201910030059 A CN201910030059 A CN 201910030059A CN 109537578 A CN109537578 A CN 109537578A
Authority
CN
China
Prior art keywords
seismic
campshed
shock insulation
length
variable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910030059.8A
Other languages
Chinese (zh)
Inventor
罗文俊
贺斯进
徐长节
黄大维
童立红
杨鹏奇
蒋峻楠
程龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Jiaotong University
Original Assignee
East China Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Jiaotong University filed Critical East China Jiaotong University
Priority to CN201910030059.8A priority Critical patent/CN109537578A/en
Publication of CN109537578A publication Critical patent/CN109537578A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/08Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against transmission of vibrations or movements in the foundation soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention discloses a kind of elongated degree shock insulation campshed shockproof structures that intensively drills; it is characterized in that the shockproof structure includes the row shock insulation campshed in the soil body being embedded between focus and shock insulation protection target; the horizontal layout of the shock insulation campshed uses intensive bore mode; the intensive bore mode refers to that pitch-row is not more than stake diameter, and each single pile length in the shock insulation campshed is in inverse relation at a distance from away from the focus.The invention has the advantages that saving material and project cost by the way that the single pile length of shock insulation campshed is arranged at a distance from away from focus not only to have ensure that the isolating affection of shock insulation campshed, but also reduce project amount in inverse relation;And waterproof material has been filled in the stake holes at the top of shock insulation campshed, and be aided with gutter and drained, it avoids surface water injection and reduces its isolating affection.

Description

A kind of elongated degree shock insulation campshed shockproof structure that intensively drills
Technical field
The present invention relates to isolation construction technology fields, and in particular to a kind of shockproof knot of elongated degree shock insulation campshed that intensively drills Structure.
Background technique
With economic fast development, the construction of means of transportation in city, the underground structures such as highway and rail traffic in city The various artificial vibration pollutions such as the construction process and above ground structure demolition blasting of object are increasingly frequent, and brought influence is increasingly Obviously, close to buildings, precision instrument and equipment and people's lives are influenced increasingly severe.Vibration is classified as in the world One of " seven big public hazards ".Directly or indirectly caused buildings or structures body is damaged for concussion of blasting.When nearby there is machine manufacture in quick-fried area When equipment, particularly industrial control equipment and precision instrument, concussion of blasting will cause shadow to these equipment, the normal use of instrument It rings, or even equipment, instrument can be destroyed.
In city in engineering construction, big compacting, deep basal pit or tunnel excavation and heavy-duty machinery construction activities shake through soil Earth travels at Adjacent Buildings basis, causes the vibration responding of building, thus the people to life and work between floors It is interfered with generating, or even causes the damage of building, and then threaten the globality and safety of building.Concussion of blasting for The safety such as neighbouring historical relic, side slope, pipeline and normal use seriously affect generation, easily cause cracking, damage, unstability, failure etc. Accident causes the uneasiness of periphery crowd and discomfort, must be subject to strict control thus.The shake generated in explosion and engineering construction It moves in the influence process of surrounding, there are focus, route of transmission, site condition and the protection big influence factors of target four.It cuts off, cut Weak or shielding vibration propagation, excavates every the technical measures such as (subtracting) shake ditch and setting shock insulation campshed, vibration energy is controlled in peace It is effective and feasible one of measure within full standard.How while ensuring isolating affection, reduce construction isolation structure at It originally is the problem that those skilled in the art face.
Summary of the invention
According to the deficiencies of the prior art described above, It is an object of the present invention to provide a kind of elongated degree shock insulations that intensively drills Campshed shockproof structure,.
The object of the invention realization is completed by following technical scheme:
One kind intensively drills elongated degree shock insulation campshed shockproof structure, it is characterised in that the shockproof structure include be embedded in focus and Shock insulation protects the row shock insulation campshed in the soil body between target, and the horizontal layout of the shock insulation campshed is using intensive drilling side Formula, the intensive bore mode refer to pitch-row no more than stake diameter, each single pile length in the shock insulation campshed with away from the shake The distance in source is in inverse relation.
Stake holes depth between the vibration isolation campshed stake top and ground is 0.3-0.7m, is filled with waterproof material in the stake holes Material.
Be covered with impermeable material above the waterproof material, the impermeable material cover height 30cm above ground level with Form the gradient.
The shockproof structure further includes the draining that shock insulation campshed two sides are opened in along the shock insulation campshed arragement direction Ditch.
The depth in the gutter fills depth less than the waterproof material.
The gradient in the gutter is not less than 0.5%, and its terminal is connect with reservoir or drainage pipeline.
The shock insulation campshed is preformed rigid concrete-pile.
The shock insulation campshed is provided at least two rows of stress relief holes in the side soil body of focus.
The plan-position of the stress relief hole is arranged using blossom type.
Moso bamboo cage is filled in the stress relief hole.
The invention has the advantages that (1) is by being arranged to the single pile length of shock insulation campshed at a distance from away from focus in inverse ratio Relationship, not only ensure that the isolating affection of shock insulation campshed, but also reduce project amount, save material and project cost;(2) shock insulation campshed Waterproof material has been filled in the stake holes at top, and has been aided with gutter and is drained, and is avoided surface water injection and is reduced its shock insulation Effect.
Detailed description of the invention
Fig. 1 is the schematic top plan view of shockproof structure in the present invention;
Fig. 2 is the diagrammatic cross-section of shockproof structure in the present invention;
Fig. 3 is the elevational schematic view of shockproof structure in the present invention.
Specific embodiment
Feature of the invention and other correlated characteristics are described in further detail by embodiment below in conjunction with attached drawing, with Convenient for the understanding of technical staff of the same trade:
Such as Fig. 1-3, label 1-6 is respectively as follows: focus 1, shock insulation protection target 2, shock insulation campshed 3, gutter 4, stress release in figure Hole 5, waterproof material 6.
Embodiment: as shown in Figure 1-3, the present embodiment is more particularly to a kind of shockproof knot of elongated degree shock insulation campshed that intensively drills Structure, the shockproof structure is by protecting the shock insulation campshed 3 that setting length changes between target 2 in focus 1 and shock insulation, so that ensuring While isolating affection, reduce the project amount of isolation structure.
As shown in Figure 1-3, the elongated degree shock insulation campshed shockproof structure of intensively drilling in the present embodiment includes being arranged in focus 1 The shock insulation campshed 3 in the soil body between shock insulation protection target 2, specifically, shock insulation campshed 3 is arranged in focus 1 and shock insulation is protected On the vertical line of both targets 2 line, arrangement range, which should cover, is unsatisfactory for shotfiring safety permission distance or discontented foot protection The section of targeted security administrative distance simultaneously preferably extends outwardly;The horizontal layout of shock insulation campshed 3 uses intensive bore mode, i.e. pitch-row No more than stake diameter, its isolating affection is can be improved in setting in this way;The stake top of shock insulation campshed 3 is apart from ground a certain distance, i.e. stake holes Depth it is longer than shock insulation campshed 3, this in the present embodiment section distance is chosen for 0.5m;The single pile length of shock insulation campshed 3 is in variation shape, Specifically, the single pile length of shock insulation campshed 3 at a distance from away from focus 1 be in inverse relation, it may be assumed that in shock insulation campshed 3 with 1 distance of focus Closer single pile length is longer, and shorter apart from remoter single pile length with focus 1, and shock insulation campshed 3 is rendered as in the present embodiment Length successively decrease from its middle part to both ends are stepped, due to the damping action of the soil body, shock wave during diffusive transport, Intensity is gradually reduced with the increase of propagation distance, therefore with the increase of single pile and 1 distance of focus in shock insulation campshed 3, single Pile length can gradually shorten, such to design the isolating affection that not only can guarantee shock insulation campshed 3, but also shock insulation row can be greatly reduced The construction material and project amount of stake 3 reduce engineering cost.
As shown in figure 1-3, the shock insulation campshed 3 in the present embodiment uses prefabricated rigid concrete shock insulation stake, strong concrete Degree grade is C50, it is ensured that it is with good isolating affection.
As shown in Figure 1-3, having filled waterproof material 6, waterproof material in stake holes between the stake top and ground of shock insulation campshed 3 Material 6 can prevent from avoiding being stored with water in stake holes and influencing its isolating affection in the surface water (such as rainfall etc.) directly injection stake holes; It is also covered with impermeable material in the top of waterproof material 6, and keeps the impermeable material of covering above ground level about 30cm makes it form certain gradient with ground, so that further preventing the surface water from flowing into influences its isolating affection in stake holes, this Impermeable material specifically selects clay in embodiment;It is anti-to further enhance it that waterproof cloth can also be added at the place of eating dishes without rice or wine of stake holes Aqueous energy.
As shown in Figure 1-3, being respectively excavated with a gutter on the arragement direction of 3 liang of lateral edge shock insulation campsheds 3 of shock insulation campshed 4, it moves towards substantially orthogonal with the slope surface contour of 3 position of shock insulation campshed;The depth in gutter 4 is less than waterproof material 6 Depth is filled, thus avoid the water in gutter 4 from penetrating into stake holes, and the gradient in gutter 4 is not less than 0.5%, terminal It is connected to reservoir or drainage pipeline, so as to which the surface water at shock insulation campshed 3 is drained to other places, the surface water is avoided to seep Enter the isolating affection of stake holes and its ambient influence shock insulation campshed 3;Gutter 4 should carry out erosion control measure, for example can be laid with turf Or it with cubic meter of stone lining cutting, is washed away with coping with possible heavy rain.
As shown in Figure 1-3, being additionally provided at least two rows of stress releases in the side soil body of the shock insulation campshed 3 close to focus 1 The plan-position in hole 5, stress relief hole 5 is arranged using blossom type, and it is filled be connected and fixed structure with moso bamboo and stirrup At moso bamboo cage, stress relief hole 2 can reduce the soil body extrusion stress of the construction activities stroke such as piling, strong rammer, further increase The isolating affection of strong shockproof structure, and moso bamboo acquisition is convenient, low in cost, can reduce construction cost.
As shown in Figure 1-3, the Specific construction process of the elongated degree shock insulation campshed shockproof structure that intensively drills in the present embodiment The following steps are included:
(1) focus side is disposed adjacent to by blossom type and opens up at least two rows of stress relief holes 5, and place in stress relief hole 5 Woven moso bamboo cage;
(2) it intensively being drilled on the vertical line of both focus 1 and shock insulation protection target 2 line, i.e., pitch-row is not more than stake diameter, Depending on the distance between bore position and focus and shock insulation protection target 2 are as needed, it should not generally be placed in low-lying place, stake holes Depth from it is intermediate to two sides in it is symmetrical it is ladder-like successively decrease, and the depth of stake holes prefabricated concrete more inbuilt than correspondence The length depth 50cm of stake, reserves the space for filling waterproof material 6;
(3) by the concrete-pile embedment stake holes of corresponding length, the stake holes of stake top and ground formation 0.5cm distance makes concrete Stake is formed from intermediate to both ends in symmetrical ladder-like;
(4) waterproof material 6 is filled in the stake holes between stake top and ground, then covers impermeable material on waterproof material 6, is made Eminence is in ground about 30cm to form the gradient after covering;
(5) respectively construct a gutter 4 in the extending direction of the two lateral edge shock insulation campsheds 3 of shock insulation campshed 3, trend substantially with slope Face contour is orthogonal, and ensures its gradient not less than 0.5%, and the terminal in gutter 4 is connected to reservoir or drainage pipeline, does Good erosion control measure (turfing or cubic meter of stone lining cutting).
It is temporary preventive measure by shockproof structure in this present embodiment, it is to be blasted to wait the engineering construction for generating strenuous vibration It can not handle after the completion or directly be embedded to underground.
The beneficial effect of the present embodiment is: (1) by being arranged to the single pile length of shock insulation campshed at a distance from away from focus In inverse relation, the isolating affection of shock insulation campshed not only ensure that, but also reduced project amount, save material and project cost;(2) every Waterproof material has been filled in stake holes at the top of shake campshed, and has been aided with gutter and is drained, surface water injection has been avoided and reduces Its isolating affection.

Claims (10)

1.一种密集钻孔变长度隔震排桩防震结构,其特征在于所述防震结构包括埋设于震源与隔震保护目标之间的土体中的一排隔震排桩,所述隔震排桩的平面布置采用密集钻孔方式,所述的密集钻孔方式是指孔距不大于桩径,所述隔震排桩中的各单桩长度与距所述震源的距离呈反比关系。1. a densely drilled variable-length seismic-isolating pile-piling anti-vibration structure, characterized in that the anti-vibration structure comprises a row of seismic-isolating piles embedded in the soil between the seismic source and the seismic-isolation protection target, and the seismic-isolating piles are The plane layout of the pile row adopts the dense drilling method, the dense drilling method means that the hole spacing is not greater than the pile diameter, and the length of each single pile in the seismic isolation pile row is inversely proportional to the distance from the earthquake source. 2.根据权利要求1所述的一种密集钻孔变长度隔震排桩防震结构,其特征在于所述隔振排桩桩顶与地面之间的桩孔深度为0.3-0.7m,所述桩孔内填充有防水材料。2. A kind of intensive drilling variable-length seismic-isolating pile-arranging anti-vibration structure according to claim 1, characterized in that the depth of the pile hole between the top of the vibration-isolating pile and the ground is 0.3-0.7 m, and the The pile hole is filled with waterproof material. 3.根据权利要求2所述的一种密集钻孔变长度隔震排桩防震结构,其特征在于所述防水材料上方覆盖有不透水材料,所述不透水材料覆盖高度高出地面30cm以形成坡度。3. A kind of densely drilled variable-length seismic-isolating pile-arresting structure according to claim 2, characterized in that the waterproof material is covered with an impermeable material, and the covering height of the impermeable material is 30cm higher than the ground to form a structure. slope. 4.根据权利要求2所述的一种密集钻孔变长度隔震排桩防震结构,其特征在于所述防震结构还包括沿所述隔震排桩排布方向开设于所述隔震排桩两侧的排水沟。4 . The seismic structure for densely drilled variable-length seismic isolation piles according to claim 2 , characterized in that the seismic structure further comprises a structure arranged on the seismic isolation piles along the layout direction of the seismic isolation piles. 5 . Gutters on both sides. 5.根据权利要求4所述的一种密集钻孔变长度隔震排桩防震结构,其特征在于所述排水沟的深度小于所述防水材料的填筑深度。5 . The seismic structure for densely drilled variable-length seismic isolation piles according to claim 4 , wherein the depth of the drainage ditch is less than the filling depth of the waterproof material. 6 . 6.根据权利要求4所述的一种密集钻孔变长度隔震排桩防震结构,其特征在于所述排水沟的坡度不小于0.5%,且其终端与蓄水池或排水管道连接。6 . The seismic structure for densely drilled variable-length seismic isolation piles according to claim 4 , wherein the slope of the drainage ditch is not less than 0.5%, and its terminal is connected to a reservoir or a drainage pipe. 7 . 7.根据权利要求1所述的一种密集钻孔变长度隔震排桩防震结构,其特征在于所述隔震排桩为预制刚性混凝土桩。7 . The seismic structure for densely drilled variable-length seismic isolation piles according to claim 1 , wherein the seismic isolation piles are prefabricated rigid concrete piles. 8 . 8.根据权利要求1所述的一种密集钻孔变长度隔震排桩防震结构,其特征在于所述隔震排桩靠近震源的一侧土体中设置有至少两排应力释放孔。8 . The seismic structure for densely drilled variable-length seismic isolation piles according to claim 1 , characterized in that at least two rows of stress relief holes are provided in the soil body on one side of the seismic isolation piles close to the earthquake source. 9 . 9.根据权利要求8所述的一种密集钻孔变长度隔震排桩防震结构,其特征在于所述应力释放孔的平面位置采用梅花型布置。9 . The seismic structure for densely drilled variable-length seismic isolation piles according to claim 8 , wherein the plane positions of the stress relief holes are arranged in a plum-shaped arrangement. 10 . 10.根据权利要求9所述的一种密集钻孔变长度隔震排桩防震结构,其特征在于所述应力释放孔内填充有毛竹笼。10 . The seismic structure for densely drilled variable-length seismic isolation piles according to claim 9 , wherein the stress release holes are filled with bamboo cages. 11 .
CN201910030059.8A 2019-01-14 2019-01-14 A kind of elongated degree shock insulation campshed shockproof structure that intensively drills Pending CN109537578A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910030059.8A CN109537578A (en) 2019-01-14 2019-01-14 A kind of elongated degree shock insulation campshed shockproof structure that intensively drills

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910030059.8A CN109537578A (en) 2019-01-14 2019-01-14 A kind of elongated degree shock insulation campshed shockproof structure that intensively drills

Publications (1)

Publication Number Publication Date
CN109537578A true CN109537578A (en) 2019-03-29

Family

ID=65835178

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910030059.8A Pending CN109537578A (en) 2019-01-14 2019-01-14 A kind of elongated degree shock insulation campshed shockproof structure that intensively drills

Country Status (1)

Country Link
CN (1) CN109537578A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112392074A (en) * 2020-12-03 2021-02-23 西南交通大学 Anti-vibration structure based on phononic crystal theory
CN114482040A (en) * 2022-04-06 2022-05-13 许昌学院 Local landslide control methods in mines

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291042A (en) * 1999-04-08 2000-10-17 Yokohama Rubber Co Ltd:The Earthquake proofing improved ground
JP2012031665A (en) * 2010-07-30 2012-02-16 Shimizu Corp Vibration isolation wall
CN202644589U (en) * 2011-12-29 2013-01-02 标力建设集团有限公司 Soft soil geology pre-stress tube pile static pressing anti-soil-squeezing structure
CN203320532U (en) * 2013-04-28 2013-12-04 中南大学 Protection device of nearby pile foundation close to deep foundation pit
CN106988350A (en) * 2017-04-27 2017-07-28 北京市市政工程设计研究总院有限公司 A kind of intensive drilling anti-explosion shock structure of back-up sand vibration isolation campshed
CN206396775U (en) * 2016-11-24 2017-08-11 贵州开磷建设集团有限公司 A kind of masonry house concrete filled steel tube pillar support shock insulating foundation structure
CN108442417A (en) * 2018-04-25 2018-08-24 华东交通大学 Shock insulation ditch with compaction grouting and varying depth
CN209493937U (en) * 2019-01-14 2019-10-15 华东交通大学 An anti-seismic structure of densely drilled and variable-length seismic-isolation pile rows

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291042A (en) * 1999-04-08 2000-10-17 Yokohama Rubber Co Ltd:The Earthquake proofing improved ground
JP2012031665A (en) * 2010-07-30 2012-02-16 Shimizu Corp Vibration isolation wall
CN202644589U (en) * 2011-12-29 2013-01-02 标力建设集团有限公司 Soft soil geology pre-stress tube pile static pressing anti-soil-squeezing structure
CN203320532U (en) * 2013-04-28 2013-12-04 中南大学 Protection device of nearby pile foundation close to deep foundation pit
CN206396775U (en) * 2016-11-24 2017-08-11 贵州开磷建设集团有限公司 A kind of masonry house concrete filled steel tube pillar support shock insulating foundation structure
CN106988350A (en) * 2017-04-27 2017-07-28 北京市市政工程设计研究总院有限公司 A kind of intensive drilling anti-explosion shock structure of back-up sand vibration isolation campshed
CN108442417A (en) * 2018-04-25 2018-08-24 华东交通大学 Shock insulation ditch with compaction grouting and varying depth
CN209493937U (en) * 2019-01-14 2019-10-15 华东交通大学 An anti-seismic structure of densely drilled and variable-length seismic-isolation pile rows

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112392074A (en) * 2020-12-03 2021-02-23 西南交通大学 Anti-vibration structure based on phononic crystal theory
CN114482040A (en) * 2022-04-06 2022-05-13 许昌学院 Local landslide control methods in mines

Similar Documents

Publication Publication Date Title
CN102966108B (en) Construction method of deep foundation pit close to building and adopting underground structure as internal support
CN111101540B (en) Construction method for passing existing electric power tunnel on open cut tunnel
CN203361033U (en) Protective device for intercepting falling rocks of through cut
CN102071607A (en) Railroad bed repair method without affecting existing running conditions
CN112281877B (en) Cutting high slope construction method
CN111560957B (en) Shield receiving well foundation pit excavation and supporting non-dewatering construction method
CN107083771A (en) A kind of drilling construction method of artificial digging pile
CN108222060A (en) High-speed railway, highway pile foundation joist buttress type pallet subgrade support retainer structure
CN109537578A (en) A kind of elongated degree shock insulation campshed shockproof structure that intensively drills
CN207143981U (en) 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN106480889A (en) A kind of Pile of Deep Foundation Pit method of reinforcement design
CN112832802A (en) Large-bottom plate supporting structure and method for asymmetric pressure
CN110284505A (en) Construction method of mountain foundation pit
CN209066468U (en) A kind of base pit dewatering device
CN111235990A (en) Cutting slope toe beam plate type reinforcing structure and construction method
CN109610505A (en) A method of constructing a foundation pit above a tunnel
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall
CN209493937U (en) An anti-seismic structure of densely drilled and variable-length seismic-isolation pile rows
CN111424685A (en) Deep water falling hole processing structure and method for backfilling foundation in large karst depression
RU121275U1 (en) REINFORCED GROUND-CEMENT WALL FOR PROTECTION OF BUILDINGS AND STRUCTURES FROM THE DIGGED NEAR THE CROWDED
CN110939142A (en) Roadbed structure for side slope
KR101169437B1 (en) The installation structure and construction method using a trough
CN109750568A (en) A kind of road structure and its construction method with pile foundation bent cap
CN212612517U (en) Micro steel pipe pile composite supporting structure for deep foundation pit in limited space
CN212405178U (en) Deep water falling hole processing structure of backfill foundation in large karst depression

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination