CN109403575A - Shingle nail integrated installation assembly and wall surface decorating method - Google Patents
Shingle nail integrated installation assembly and wall surface decorating method Download PDFInfo
- Publication number
- CN109403575A CN109403575A CN201810859178.XA CN201810859178A CN109403575A CN 109403575 A CN109403575 A CN 109403575A CN 201810859178 A CN201810859178 A CN 201810859178A CN 109403575 A CN109403575 A CN 109403575A
- Authority
- CN
- China
- Prior art keywords
- wall
- shingle nail
- shingle
- inner corner
- corner trim
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0801—Separate fastening elements
- E04F13/0803—Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0801—Separate fastening elements
- E04F13/0803—Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
- E04F13/081—Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0889—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements characterised by the joints between neighbouring elements, e.g. with joint fillings or with tongue and groove connections
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0889—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements characterised by the joints between neighbouring elements, e.g. with joint fillings or with tongue and groove connections
- E04F13/0898—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements characterised by the joints between neighbouring elements, e.g. with joint fillings or with tongue and groove connections with sealing elements between coverings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Finishing Walls (AREA)
Abstract
The invention discloses a kind of shingle nail integrated installation assembly and wall surface decorating method, shingle nail integrated installation assembly includes: multiple shingle nails, and multiple shingle nails are arranged successively along wall extending direction, and the surface of shingle nail is provided with decorative layer;Device is flushed, device is flushed and is arranged between two adjacent shingle nails and is used to connect two adjacent shingle nails, two shingle nails are fixed by flushing device with wall;The wall inner corner trim of wall is arranged in inner corner trim mounting assembly, inner corner trim mounting assembly, and the shingle nail positioned at wall inner corner trim two sides is fixed by inner corner trim mounting assembly with wall;The wall external corner of wall is arranged in external corner fixing piece, external corner fixing piece, and the shingle nail positioned at wall external corner two sides is fixed by external corner fixing piece with wall.The present invention provides a kind of shingle nail integrated installation assembly and wall surface decorating method, it can be achieved that shingle nail and wall quick assembling, decorating wall improve industrialized level.
Description
Technical field
The present invention relates to indoor wall finishings, fill more particularly, to a kind of shingle nail integrated installation assembly and metope
Decorations method.
Background technique
Wall decoration is the key area of the interior space decorations of building, and wall decoration can protect wall, is increased
The robustness and durability of strong wall, extend the service life of wall.
In existing wall decoration fitment process, especially toilet or kitchen etc. are related in the space with water, it is necessary first to
Pre- water-proofing treatment is carried out to wall, decorative layer is installed on pre- waterproof base, extends the construction time, improves decoration cost.
Decorative layer mainly based on ceramic tile, stone material paving, ceramic tile, stone material paving mode be broadly divided into wet combining and cladding two kinds of shapes
Formula.Wherein, wet combining on ceramic tile or stone material mainly by being arranged cement mortar or tile binding material, to realize the stickup with wall
It is fixed;It is cladding mainly by using cladding component, ceramic tile or stone material are fixed on the wall.What above two method was primarily present
Problem is as follows: wet combining work progress is longer, construction professional standards are higher and quality control difficulty is larger, construction environment pollution etc.
Adverse effect;Cladding component wasting space is larger, levelling in installation process to adjust relatively complicated, single ceramic tile cladding easily broken etc.
Unfavorable condition.Waterproofing step can be omitted as decorative layer come decorated wall surface using shingle nail, saved money laborsaving.Shingle nail can basis
Specific construction space is previously-completed production, realizes assembly after entering construction space, can using shingle nail decorating wall
Installation effectiveness is improved, construction cost is saved.But existing cladding component is not particularly suited for the installation of shingle nail.
Therefore, it is necessary to a kind of shingle nail integrated installation assembly and wall surface decorating methods, to solve the above problems.
Summary of the invention
In view of this, it is an object of the invention to propose a kind of shingle nail integrated installation assembly and wall surface decorating method,
Shingle nail integrated installation assembly can realize shingle nail and wall quick assembling, by shingle nail treat the wall in installation space into
Luggage decorations, can simplify work progress, shorten the construction period, avoid generating more rubbish at the construction field (site), avoid floor,
The positions such as doorframe are easy to leave a trace, and improve industrialized level.
Based on a kind of above-mentioned purpose shingle nail integrated installation assembly provided by the invention, comprising:
Multiple shingle nails, multiple shingle nails are arranged successively along wall extending direction, the surface setting of the shingle nail
There is decorative layer;
Device is flushed, the device that flushes is arranged between two adjacent shingle nails and for connecting two adjacent institutes
Shingle nail is stated, two shingle nails flush device described in and fix with wall;
The wall inner corner trim of the wall is arranged in inner corner trim mounting assembly, the inner corner trim mounting assembly, is located at the wall inner corner trim two
The shingle nail of side is fixed by the inner corner trim mounting assembly with the wall;
The wall external corner of the wall is arranged in external corner fixing piece, the external corner fixing piece, positioned at wall external corner two sides
The shingle nail is fixed by the external corner fixing piece with the wall.
Preferably, the device that flushes includes: shingle nail connector, and adjacent two are arranged in the shingle nail connector
Between the shingle nail, and for connecting two adjacent shingle nails;
Shingle nail fixing piece, the shingle nail connector are connect with the shingle nail fixing piece, the shingle nail fixing piece
It is connect for realizing the shingle nail connector with the leveling keel of two adjacent shingle nails;
Caulking strip is flushed, the caulking strip that flushes is for sealing the gap between two adjacent shingle nails.
Preferably, the inner corner trim mounting assembly includes:
Inner corner trim plug-in unit, the inner corner trim plug-in unit include the first mounting plate and the second peace extended from first mounting plate
Loading board is provided with mounting groove on first mounting plate, is provided with insertion end on second mounting plate;
Inner corner trim vertical keel, the inner corner trim vertical keel include the first limited wall and extend from first limited wall
The second limited wall, the first mounting groove and the second installation are respectively arranged on first limited wall and second limited wall
Slot;The junction of first limited wall and second limited wall is provided with mounting base, the mounting base and first limit
The inserting groove for being used cooperatively with the insertion end of the inner corner trim plug-in unit, wall yin are provided on the parallel the first side wall of position wall
First shingle nail at angle is connected in the mounting base by the first mounting plate of the inner corner trim plug-in unit;Second limited wall with
Second mounting plate of the inner corner trim plug-in unit can clamp the second shingle nail of the wall inner corner trim, and the mounting base and described the
The parallel second sidewall of one limited wall is abutted with the end face of second shingle nail.
Preferably, the inner corner trim mounting assembly further include: inner corner trim caulking strip, the inner corner trim caulking strip include support portion and set
Set the sealing and guide part in the support portion opposite end, the height of the support portion be greater than the height of the guide part and
Less than the height of the sealing, the guide part is for guiding the support portion to enter first shingle nail and described second
In gap between shingle nail, the sealing is for sealing the gap.
Furthermore it is preferred that the external corner fixing piece includes mounting rod, the first protrusion, the second protrusion, the first fixation wall and the
Two fixation walls, first protrusion and second protrusion are separately positioned on the opposite sides of the body of rod of the mounting rod, described
First fixation wall and second fixation wall are separately positioned in the first end of the body of rod, first protrusion and described first
The extending direction of both fixation walls is parallel, and second protrusion is parallel with the extending direction of both second fixation walls, described
The second end of mounting rod is for being connected in the gap between first shingle nail and second shingle nail.
The present invention also provides a kind of wall surface decorating methods, use such as above-mentioned shingle nail integrated installation assembly, comprising:
(1) multiple shingle nails are sequentially distributed along wall extending direction;
(2) inner corner trim mounting assembly, the inner corner trim mounting assembly are installed on the outside of the first side end of multiple shingle nails
Support and limit be located at the first side end the shingle nail, and will be located at the first side end the shingle nail free end with
The wall is fixed;
(3) it will flush on the wall that device is fixed between two adjacent shingle nails, two adjacent institutes
It states shingle nail to flush device by described and be connected as one, and flushes device by described and fixed with the wall;
(4) repetition step (3), will up to installing the wall inner corner trim of the wall or/and the shingle nail of wall external corner two sides
Inner corner trim mounting assembly or/and external corner fixing piece are fixed on the wall inner corner trim or/and the wall external corner, are located at the wall inner corner trim
Or/and the shingle nail of wall external corner two sides by the inner corner trim mounting assembly or/and the external corner fixing piece with it is described
Wall is fixed;
(5) step (4) are repeated until the shingle nail of the second side end of multiple shingle nails is positioned at, more
The inner corner trim mounting assembly, the inner corner trim mounting assembly support and limit position are installed on the outside of the second side end of a shingle nail
The shingle nail in the second side end, and the free end for being located at the shingle nail of the second side end is consolidated with the wall
It is fixed.
Preferably, in step (3) further include:
(3a) shingle nail connector is arranged between two adjacent shingle nails, passes through the shingle nail connector
Two adjacent shingle nails are connected, and multiple shingle nails are connected as one;
Multiple leveling keel are separately fixed on the adjacent corresponding wall in the shingle nail junction by (3b), by metope
Plate fixing piece is connect with the leveling keel of two adjacent shingle nails, and the shingle nail connector is consolidated with the shingle nail
Determine part connection;
(3c) will be flushed in the gap that caulking strip is installed between two adjacent shingle nails.
Preferably, in step (4) further include:
(4a) will be respectively connected with adjusting foot, the first limited wall on the first mounting groove and the second mounting groove of inner corner trim vertical keel
Pass through the adjusting foot respectively with the second limited wall to abut with the two sides wall of wall inner corner trim;
The insertion end of inner corner trim plug-in unit is plugged on the inserting groove of the inner corner trim vertical keel by (4b), by the inner corner trim plug-in unit
The first mounting plate abutted with second limited wall, the second mounting plate of the inner corner trim plug-in unit and the inner corner trim vertical keel
The first side wall of mounting base abuts;
The adjacent both sides of the face of first shingle nail are connected to first mounting plate and described second by (4c) respectively
On mounting plate, and it is fixed on the second mounting plate;Second shingle nail is inserted into first limited wall and second peace
It is fixed between loading board.
Preferably, in step (4c) further include:
By the guide part guiding support of inner corner trim caulking strip be inserted into first mounting plate and second shingle nail it
Between gap in, provide support by the support portion for second shingle nail;The sealing of the inner corner trim caulking strip is for close
Seal the gap between first shingle nail and second shingle nail.
Preferably, in step (4) further include: (4d) mounting rod of external corner fixing piece is arranged in first shingle nail
In gap between second shingle nail, the first protrusion of the external corner fixing piece and the second protrusion are plugged on institute respectively
In the through-hole for stating the first shingle nail and second shingle nail, by the first fixation wall and the second fixation wall of the external corner fixing piece
It abuts and is fixed on first shingle nail and second shingle nail respectively.
From the above it can be seen that shingle nail integrated installation assembly provided by the invention and wall surface decorating method, with
The prior art is compared, and is had the advantage that the easy installation that can realize shingle nail using above-mentioned shingle nail integrated installation assembly, is mentioned
High speed of application, while avoiding generation environment pollution or decoration garbage.Shingle nail and wall quick assembling can be achieved, can simplify and apply
Work process shortens the construction period, avoids generating more rubbish at the construction field (site), avoids being easy in positions such as floor, doorframes
It leaves a trace, improves industrialized level.Moreover, shingle nail integrated installation assembly occupies little space, easy to assembly quick, positioning is quasi-
Really, flatness is high, good decorating effect, leakproofness and good waterproof performance.
Detailed description of the invention
By the way that embodiment is described with reference to the accompanying drawing, features described above of the invention and technological merit will become
More understands and be readily appreciated that.
Fig. 1 is the schematic diagram of shingle nail integrated installation assembly in the specific embodiment of the invention.
Fig. 2 is the schematic diagram of the shingle nail of shingle nail integrated installation assembly shown in FIG. 1.
Fig. 3 is the partial enlargement diagram in the portion A of shingle nail integrated installation assembly shown in FIG. 1.
Fig. 4 is the schematic diagram of the shingle nail connector of shingle nail integrated installation assembly shown in Fig. 3.
Fig. 5 is the schematic diagram of the shingle nail fixing piece of shingle nail integrated installation assembly shown in Fig. 3.
Fig. 6 is the schematic diagram for flushing caulking strip of shingle nail integrated installation assembly shown in Fig. 3.
Fig. 7 is the partial enlargement diagram in the portion B of shingle nail integrated installation assembly shown in FIG. 1.
Fig. 8 is the schematic diagram of the inner corner trim vertical keel of shingle nail integrated installation assembly shown in Fig. 7.
Fig. 9 is the schematic diagram of the inner corner trim plug-in unit of shingle nail integrated installation assembly shown in Fig. 7.
Figure 10 is the schematic diagram of the inner corner trim caulking strip of shingle nail integrated installation assembly shown in Fig. 7.
Figure 11 is the partial enlargement diagram in the portion C of shingle nail integrated installation assembly shown in FIG. 1.
Figure 12 is the schematic diagram of the wall external corner of shingle nail integrated installation assembly shown in FIG. 1.
Figure 13 is the schematic diagram of another wall external corner for shingle nail integrated installation assembly.
Wherein appended drawing reference:
10: flushing caulking strip;11: pedestal;12: strut;13: sealing bar;
20: shingle nail connector;21: interconnecting piece;211: bottom plate;212: first partition;
213: second partition;214: the first mounting walls;215: the second mounting walls;
22: the first mounting portions;221: third partition;222: the four partitions;
223: the first connecting plates;224: the first retention beads;23: the second mounting portions;
231: the five partitions;232: the six partitions;233: the second connecting plates;
234: the second retention beads;30: shingle nail fixing piece;31: holding tank;
32: the first limit plates;33: the second limit plates;34: connecting plate;35: positioning plate;
36: partition;40: shingle nail;410: substrate;411: top surface;412: bottom surface;
413: through-hole;414: decorative layer;420: mounting portion;421: protrusion;422: limiting card;
423: groove;424: opening;425: lightening hole;41: the first shingle nails;
42: the second shingle nails;43: adjusting foot fixing piece;44: gap;45 adjust foot;
50: external corner fixing piece;51: mounting rod;52: the first protrusions;53: the second protrusions;
54: the first fixation walls;55: the second fixation walls;50 ': external corner fixing piece;
51 ': segmentation mounting rod;52 ': the first closure protrusions;53 ': the second closure protrusions;
60: inner corner trim plug-in unit;61: insertion end;62: the first mounting plates;63: the second mounting plates;
70: inner corner trim caulking strip;71: support portion;72: guide part;73: sealing;
74: bent area;80: inner corner trim vertical keel;81: the first limited walls;
82: the second limited walls;83: mounting base;84: inserting groove;85: the first mounting grooves;
86: the second mounting grooves;87: loss of weight through-hole;88: adjusting grooves.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, below in conjunction with specific embodiment, and reference
Attached drawing, the present invention is described in more detail.Wherein identical components are presented with like reference characters.It needs to illustrate
It is that word "front", "rear" used in the following description, "left", "right", "up" and "down" refer to the direction in attached drawing.It uses
Word "inner" and "outside" refer respectively to the direction towards or away from geometric center of specific component.
Fig. 1 is the schematic diagram of shingle nail integrated installation assembly in the specific embodiment of the invention.As shown in Figure 1, shingle nail collection
Include multiple shingle nails 40 at installation assembly, flush device, inner corner trim mounting assembly and external corner fixing piece 50.
Multiple shingle nails 40 are arranged successively along wall extending direction, and the surface of shingle nail 40 is provided with decorative layer 414;It flushes
Device is arranged between two adjacent shingle nails 40 and for connecting two adjacent shingle nails 40, and two shingle nails 40 pass through
Device is flushed to fix with wall;The wall inner corner trim of wall is arranged in inner corner trim mounting assembly, and the shingle nail 40 positioned at wall inner corner trim two sides is logical
Inner corner trim mounting assembly is crossed to fix with wall;The wall external corner of wall, the metope positioned at wall external corner two sides is arranged in external corner fixing piece 50
Plate 40 is fixed by external corner fixing piece 50 with wall.
When multiple shingle nails 40 are arranged successively along wall extending direction, from one end of wall assembly shingle nail, positioned at end
The free end of the shingle nail in portion can be fixed on the wall by inner corner trim mounting assembly;For straight metope, adjacent shingle nail it
Between be fixed on the wall by flushing device;The shingle nail of wall inner corner trim two sides is installed on wall by inner corner trim mounting assembly, wall
The shingle nail of external corner two sides is installed on wall by external corner fixing piece 50, and the free end positioned at the shingle nail of end side is logical
Inner corner trim mounting assembly is crossed to be fixed on the wall.The easy installation of shingle nail can be realized using above-mentioned shingle nail integrated installation assembly,
Speed of application is improved, while avoiding generation environment pollution or decoration garbage;Shingle nail and wall quick assembling can be achieved, can simplify
Work progress shortens the construction period, avoids generating more rubbish at the construction field (site), avoids holding in positions such as floor, doorframes
It easily leaves a trace, improves industrialized level.
Fig. 2 is the schematic diagram of the shingle nail of shingle nail integrated installation assembly shown in FIG. 1.As shown in Fig. 2, shingle nail includes
Substrate 410 and mounting portion 420.
Preferably, shingle nail includes substrate 410 and the mounting portion 420 that at least one end of substrate 410 is arranged in, decorative layer 414
It is arranged on substrate 410, identical with 410 extending direction of substrate raised 421, raised 421 and substrate is provided on mounting portion 420
Be arranged fluted 423 between 410, protrusion 421 towards being provided with limiting card 422 on the side wall surface of groove 423, protrusion 421 with
The opening 424 being used to support is provided between end face of the mounting portion 420 far from 410 side of substrate.The decorative layer of substrate 410
414 towards external setting, and so as to decorating wall, mounting portion 420 cooperates with device is flushed, to complete adjacent shingle nail 40
Splicing assembling.The interconnecting piece for flushing device is arranged between two adjacent shingle nails, and the by flushing device first installation
Portion and the second mounting portion respectively with the mounting portion card of two shingle nails 40 and connection, wherein adjacent two are arranged in interconnecting piece
In gap between shingle nail 40, opening 424 provides a supporting role for interconnecting piece, and interconnecting piece is sealed gap;First peace
The slot of the close interconnecting piece of both dress portion and the second mounting portion respectively with the protrusion 421 of two shingle nails 40 card and connect, and
It is limited by limiting card 422;The slot of the separate interconnecting piece of both first mounting portion, the second mounting portion is inserted into two respectively
In the groove 423 of shingle nail 40, groove is sealed.Using above-mentioned shingle nail with flush device card and connect in succession, it is convenient for disassembly and assembly,
Limiting card provides limit, to realize close connection, improves the integraty of shingle nail peace connection device, while improving integral sealing
Property and waterproof performance.
In the present embodiment, shingle nail 40 includes one or two mounting portion 420, when multiple shingle nails 40 are arranged successively,
The substrate 410 of the shingle nail 40 at both ends is provided with a mounting portion 420, the substrate of the shingle nail 40 between both ends
There are two mounting portions 420 for 410 settings.
To simplify apparatus structure, it is preferable that substrate 410 is provided with relatively parallel top surface 411 and bottom surface in the width direction
412, it is connected between top surface 411 and bottom surface 412 by side wall, decorative layer 414 is arranged on the top surface 411 of substrate 410;Protrusion
421 are arranged on top surface 411, and extend to 412 side of bottom surface, and it is perforative logical that multiple through-thickness are provided on substrate 410
Hole 413, multiple through-holes 413 are spaced apart along the length direction of substrate 410.Bottom surface 412 is arranged towards wall, 411 conduct of top surface
Decorative cover is arranged in parallel towards external setting, top surface 411 and bottom surface 412, reduces installation difficulty, while helping to provide straight
Decorative cover improves aesthetics;Decorative layer can be integrated on substrate 410 by modes such as stickups, in order to provide better decoration effect
Fruit.Protrusion 421 is extended from top surface 411 to bottom surface 412, is hidden between wall and top surface 411 to flush device, is avoided influencing
The aesthetics of shingle nail 40;Through-hole 413 can reduce by 40 weight of shingle nail, reduce installation difficulty.Decorative layer 414 can pass through stickup etc.
Mode is integrated on substrate 410, in order to provide better decorative effect.
In the present embodiment, the bottom surface 412 of substrate 410 and the junction of side wall are provided with guide surface (not identifying), are oriented to
Face from bottom surface 412 to side wall towards move closer to 423 side of groove extend.By be arranged guide surface can reduce flush device with
The installation difficulty of mounting portion 420 conveniently flushes in the slot insertion groove of device.
In the present embodiment, multiple lightening holes 425 being spaced apart are provided on mounting portion 420.By the way that lightening hole is arranged
425 can reduce the weight of shingle nail 40.
In the present embodiment, the bearing height of the bearing height and substrate 410 of protrusion 421, which maintains an equal level, is arranged.Protrusion 421 and base
The bearing height of plate 410 maintains an equal level, and to keep substrate 410 and the bearing height having the same of mounting portion 420, it is difficult to reduce installation
Degree, provides concordant decorative cover.
In the present embodiment, the free end of protrusion 421 is guide end, the width of guide end towards protrusion 421 from the distant to the near
In gradually increasing.By the way that guide end is arranged in protrusion 421, the installation difficulty for flushing device and protrusion 421 can be reduced, is conveniently put down
The slot of connection device is set in protrusion 421.
In the present embodiment, the width of limiting card 422 is in and first increases to reduce afterwards from the notch of groove 423 to slot bottom.Limit
Male cooperation on card 422 and the socket sidewalls for flushing device uses, when the slot for flushing device is set in protrusion 421, limit
Position card 422 first passes through curved surface from narrow to wide and provides guiding role, then by providing position-limiting action to narrow curved surface by wide, both side
Just limiting card 422 and device quick assembling is flushed, while position-limiting action is provided, avoid flushing device play back and forth.
To improve support strength, at the same with flush the shape of device to being adapted to, in the present embodiment, be open 424 support
Between face and the top surface 411 of substrate 410 vertical range be greater than groove 423 slot bottom and the top surface 411 of substrate 410 between it is vertical away from
From.Opening 424 provides relatively high bearing height, the lightening hole 425 between opening 424 and top surface 411 relative to groove 423
Area be greater than the area of lightening hole 425 between groove 423 and top surface 411.
In the present embodiment, substrate 410 is an integral molding structure with mounting portion 420.Using integrated formed structure, Ke Yijian
Change manufacturing process, improves the structural strength of shingle nail fixing piece 30.
Fig. 3 is the partial enlargement diagram in the portion A of shingle nail integrated installation assembly shown in FIG. 1.As shown in figure 3, flushing
Device includes: shingle nail connector 20, shingle nail fixing piece 30 and flushes caulking strip 10.
Preferably, device is flushed to include: shingle nail connector 20, shingle nail fixing piece 30 and flush caulking strip 10;Metope
Plate connector 20 is arranged between two adjacent shingle nails 10, and for connecting two adjacent shingle nails 10;Shingle nail connects
Fitting 20 is connect with shingle nail fixing piece 30, and shingle nail fixing piece 30 is for realizing shingle nail connector 20 and two adjacent walls
The adjusting foot fixing piece 43 of panel 10 connects, and is provided on regulating part fixing piece 43 and adjusts foot 45, for improving the smooth of wall
Degree;Caulking strip 10 is flushed for sealing the gap 44 between two adjacent shingle nails 40.Shingle nail connector 20 for realizing
Adjacent the first shingle nail 41 and the second shingle nail 42 flushes, and shingle nail connector 20 is connect with shingle nail fixing piece 30, wall
Faceplate fastener 30 is connect with the adjusting foot fixing piece 43 of shingle nail, so as to the first shingle nail 41 and the second metope after flushing
Plate 42 is fixed on the wall.Caulking strip 10 will be flushed to be inserted into the gap 44 between the first shingle nail 41 and the second shingle nail 42,
Steam dust etc. is avoided to enter in gap 44, the above-mentioned device that flushes for shingle nail can be realized the quick of adjacent shingle nail
Assembly, stability is good, improves waterproof performance;Traditional gap filling process is saved simultaneously, is simplified construction process, is avoided pollution operation
Environment.
Fig. 4 is the schematic diagram of the shingle nail connector of shingle nail integrated installation assembly shown in Fig. 3.As shown in figure 4, metope
Plate connector 20 includes interconnecting piece 21, the first mounting portion 22 and the second mounting portion 23.
Preferably, shingle nail connector 20 includes interconnecting piece 21 and the first mounting portion that 21 opposite sides of interconnecting piece is arranged in
22 and second mounting portion 23, the first mounting portion 22 and the second mounting portion 23 be respectively used to that two adjacent shingle nails are installed, connect
Portion 21 is arranged in the gap 44 between two adjacent shingle nails, and for connecting with shingle nail fixing piece 30.Interconnecting piece 21
It is arranged in the gap of two adjacent shingle nails, is used for sealing off gap, the first mounting portion 22 and the second mounting portion 23 are used respectively
In installing the first shingle nail 41 and the second shingle nail 42, so that the first shingle nail 41 is connected with the second shingle nail 42 by shingle nail
Part 20 is connected as one, and the adjusting foot 45 of tune section foot fixing piece 43 and tune section foot fixing piece 43 is then installed by interconnecting piece
On.Shingle nail connector 20 is stably connected with for realizing adjacent shingle nail, realizes quick assembling, shortens assembly time, simplifies
Assembly process.
To simplify apparatus structure, good sealing effect is provided to the gap of adjacent shingle nail, in the present embodiment, even
Socket part 20 includes bottom plate 211 and from 211 opposite end of bottom plate to the ipsilateral first partition 212 extended and second partition 213, bottom
Plate 211, first partition 212 and second partition 213 are enclosed the first card slot, and the first card slot passes through first partition 212 and second
Partition 213 is abutted with two shingle nails respectively, and first partition 212 and second partition 213 each extend to the outside in gap 44, and two
Extend the first mounting wall 214 and the second mounting wall 215 to the notch side far from the first card slot in the free end of person.When first
When the substrate of 42 the two of shingle nail 41 and the second shingle nail abuts, there are gap 44 between the protrusion of the two, interconnecting piece is inserted into
In gap 44, wherein bottom plate 211 is connected on substrate, first partition 212 and second partition 213 respectively with the first shingle nail 41
Protrusion side wall and the second shingle nail 42 protrusion side wall abut against, the first card slot blind 44, the first mounting wall 214
It is plugged in the holding tank of shingle nail fixing piece 30 respectively with the second mounting wall 215, realizes shingle nail connector 20 and shingle nail
The connection of fixing piece 30.The alternative traditional caulking process of interconnecting piece shortens the construction time, while avoiding pollution operating environment.
To increase integraty, bonding strength is improved, in the present embodiment, first partition 212 is towards the first shingle nail 41
On surface and second partition 213 is towards being provided with protrusion on the surface of the second shingle nail 42.First partition 212 and second every
Protrusion on plate 213 can produce deformation when being squeezed by the first shingle nail 41 and the second shingle nail 42, convex to restore deformation
It rises and is closely connected on the first shingle nail 41 and the second shingle nail 42, Lai Tigao bonding strength.
In the present embodiment, the notch of raised width towards the first card slot is in and first increases to reduce afterwards from the distant to the near, protrusion
Width close to slot bottom side is lower, it is possible to provide guiding role facilitates the second card slot/the 4th card slot to be set in the first shingle nail
In the protrusion of 41/ second shingle nail 42.
To reduce assembly difficulty, in the present embodiment, the free end of 215 the two of the first mounting wall 214 and the second mounting wall
Be guide end, the width of guide end towards the first card slot be from the distant to the near in gradually increase.Appearance is provided on shingle nail fixing piece
The free end of first mounting wall 214 and the second mounting wall 215 is disposed as guide end, passed through by slot of receiving to reduce assembly difficulty
Reduce the width of guide end, enters holding tank to facilitate.
To simplify apparatus structure, in the present embodiment, the first mounting portion 22 includes setting gradually and opening direction is identical
Second card slot and third card slot, the second card slot and third card slot be respectively used to a shingle nail in adjacent with two protrusion and
Groove card and connection;Second mounting portion 23 includes setting gradually and identical 4th card slot of opening direction and the 5th card slot, and the 4th
Card slot and the 5th card slot are respectively used to raised and groove card and the connection of another shingle nail in adjacent with two.To realize the
The close connection of one mounting portion 22 and the first shingle nail 41, by the second card slot and third card slot respectively with protrusion and groove card and
Connection, the second card slot form card with the male cooperation of the first shingle nail 41 and connect, easy disassembly;Third card slot and the first metope
The groove of plate 41 cooperatively forms card and connection, increases the leakproofness of the first shingle nail 41.To realize the second mounting portion 23 and second
The close connection of shingle nail 42, by the 4th card slot and the 5th card slot respectively with protrusion and groove card and connection, the 4th card slot and
The male cooperation of second shingle nail 42 forms card and connection, easy disassembly;The cooperation of the groove of 5th card slot and the second shingle nail 42
Card and connection are formed, the leakproofness of the second shingle nail 42 is increased.
To further enhance integraty, connectivity and leakproofness, while simplifying apparatus structure, in the present embodiment, along the
One mounting wall, 214 extending direction interval and it is relatively set with third partition 221 and the 4th partition 222, third partition 221, first
Mounting wall 214 and first partition 213 are enclosed the second card slot;4th partition 222 passes through the first connecting plate 223 and third partition
221 connections, and it is enclosed third card slot.Second card slot forms integral structure by the first mounting wall 214 and interconnecting piece 21, the
Three card slots form integral structure by the first connecting plate 223 and the second card slot, i.e. the first mounting portion 22 is integrated with interconnecting piece 21
Structure, Lai Tigao integraty, the first mounting portion 22 pass through the second card slot and third the card slot protrusion with the first shingle nail 41 respectively
It is connected with groove, Lai Zengqiang connectivity and leakproofness.
In the present embodiment, third partition 221 extends from the middle part of the first mounting wall 214 to the first card slot slot bottom side,
Third partition 221 is arranged in parallel with first partition 212, and third partition 221, the first mounting wall 214 and first partition 213 enclose shape
At the second card slot;Extend the first connecting plate 223, the first connecting plate 223 to far from the second card slot side from third partition 221
It is arranged in parallel with the first mounting wall 214, and there is gap between the two, the free end of the first connecting plate 223 is to far from the first peace
The 4th partition 222 is extended in the direction of dress wall 214, and the 4th partition 222 is arranged in parallel with third partition 221, the 4th partition 222,
First connecting plate 223 is connect with third partition 221 is enclosed third card slot.
For the bonding strength for improving the first mounting portion and the first shingle nail, in the present embodiment, the freedom of third partition 221
End is provided with the first retention bead 224, and the first retention bead 224 makes with the limiting card cooperation in the protrusion of the first shingle nail 41
With.First retention bead 224 limits mutually with the limiting card in the protrusion of the first shingle nail 41, avoids the first shingle nail 41
Play back and forth in two draw-in groove improves stability.
To further enhance integraty, connectivity and leakproofness, while simplifying apparatus structure, in the present embodiment, along the
Two mounting walls, 215 extending direction interval and it is relatively set with the 5th partition 231 and the 6th partition 232, the 5th partition 231, second
Mounting wall 215 and second partition 213 are enclosed the 4th card slot;6th partition 232 passes through the second connecting plate 233 and the 5th partition
231 connections, and it is enclosed the 5th card slot.4th card slot forms integral structure by the second mounting wall 215 and interconnecting piece 21, the
Five card slots form integral structure by the second connecting plate 233 and the 4th card slot, i.e. the second mounting portion 23 is integrated with interconnecting piece 21
Structure, Lai Tigao integraty, the second mounting portion 23 pass through the 4th card slot and the 5th the card slot protrusion with the second shingle nail 42 respectively
It is connected with groove, Lai Zengqiang connectivity and leakproofness.
In the present embodiment, the 5th partition 231 extends from the middle part of the second mounting wall 215 to the first card slot slot bottom side,
Second mounting wall 215 is arranged in parallel with second partition 213, and the 5th partition 231, the second mounting wall 215 and first partition 213 enclose
Form the 4th card slot;Extend the second connecting plate 233, the second connecting plate to far from the 4th card slot side from the 5th partition 231
233 are arranged in parallel with the second mounting wall 215, and there is gap between the two, and the free end of the second connecting plate 233 is to far from second
The 6th partition 232 is extended in the direction of mounting wall 215, and the 6th partition 232 is arranged in parallel with the 5th partition 231, the 5th partition
231, the second connecting plate 233 is connect with the 5th partition 231 is enclosed the 5th card slot.
For the bonding strength for improving the second mounting portion and the second shingle nail, in the present embodiment, the freedom of the 5th partition 231
End is provided with the second retention bead 234, and the second retention bead 234 makes with the limiting card cooperation in the protrusion of the second shingle nail 42
With.Second retention bead 234 limits mutually with the limiting card in the protrusion of the second shingle nail 42, avoids the second shingle nail 42
Play back and forth in four card slots improves stability.
In the present embodiment, metope connector 20 is symmetrical structure, 23 the two of first connecting portion 22 and second connecting portion
Cross section is in that nearly m type, first connecting portion 22 and second connecting portion 23 are symmetrical in mirror surface along the axis of interconnecting piece 21.
Fig. 5 is the schematic diagram of the shingle nail fixing piece of shingle nail integrated installation assembly shown in Fig. 3.As shown in figure 5, metope
Plate fixing piece 30 includes connecting plate 34, holding tank 31, the first limit plate 32 and the second limit plate 33.
Shingle nail fixing piece 30 include connecting plate 34, holding tank 31 and be arranged in holding tank 31 notch opposite sides the
One limit plate 32 and the second limit plate 33, the first limit plate 32 and the second limit plate 33 extend into notch;Connecting plate 34 with
The slot bottom of holding tank 31, which maintains an equal level, to be arranged, at least one mounting groove (not identifying) is provided on connecting plate 34, and fixing piece can be through peace
Tankage and by shingle nail fixing piece 30 be fixed to adjustment keel 43 on.
The mounting wall of shingle nail connector 20 is pluggable to be arrived in accommodation groove 31, and the first limit plate 32 and the second limit plate 33 are
It is used to support mounting wall, and mounting wall is limited in accommodation groove 31, the slot bottom and connecting plate 34 of accommodation groove 31 are and tune
It saves foot fixing piece 43 and abuts connection, fixing piece runs through mounting groove, and shingle nail fixing piece 30 is fixed on and adjusts foot fixing piece 43
And it adjusts on foot 45.It is used cooperatively using above-mentioned shingle nail fixing piece with shingle nail connector, realizes shingle nail and leveling dragon
The connection of bone, avoids damage to the integrality of shingle nail connector, and operating space is big, it can be achieved that quick assembling.
In the present embodiment, holding tank include mounting plate and from mounting plate opposite end to the first side wall of ipsilateral extension
And second sidewall, mounting plate, the first side wall and second sidewall are enclosed holding tank;The free end of the first side wall and second sidewall
Extend the first limit plate 32 and the second limit plate 33 into notch, the first limit plate 32 and the second limit plate 33 with installation
Plate is arranged in parallel.
In the present embodiment, shingle nail fixing piece 30 further include: positioning plate 35, positioning plate 35 is from the first limit plate 32 to remote
Notch side from holding tank 31 extends, and positioning plate 35, the first limit plate 32 and the second limit plate 33 maintain an equal level and be arranged.Metope
When plate fixing piece 30 and shingle nail connector 20 cooperate, positioning plate 35 can be abutted with shingle nail, be used to support and limit shingle nail,
Shingle nail play is avoided, realizes accurate and quick assembling.
When shingle nail fixing piece 30 and shingle nail connector 20 cooperate, positioning plate 35 can be abutted with shingle nail, be used to support
With limit shingle nail, shingle nail play is avoided, realizes accurate and quick assembling;In general, the mounting wall packet of shingle nail connector 20
The first mounting wall and the second mounting wall are included, the first mounting wall extends round about with the second mounting wall, to realize metope connection
Part and wall surface fixture are stably connected with, and the first mounting wall and the second mounting wall of shingle nail connector 20 can be plugged into respectively
In one accommodation groove and the second accommodation groove, the first limit plate 32 and the second limit plate 33 are used to support mounting wall, and by mounting wall
It is limited in accommodation groove 31, the slot bottom and connecting plate 34 of accommodation groove 31 abut connection, fixing piece with adjusting foot fixing piece 43
Through mounting groove, and shingle nail fixing piece 30 is fixed on and adjusts foot fixing piece 43 and adjusts on foot 45.Using above-mentioned metope
Plate fixing piece is used cooperatively with shingle nail connector, is realized shingle nail and is leveled the connection of keel, and shingle nail connection is avoided damage to
The integrality of part, operating space are big, it can be achieved that quick assembling.
In the present embodiment, positioning plate 35 is an integral molding structure with the first limit plate 32.It, can using integrated formed structure
To simplify manufacturing process, the structural strength of shingle nail fixing piece 30 is improved.
In general, the mounting wall of shingle nail connector includes the first mounting wall and the second mounting wall, the first mounting wall and second
Mounting wall extends round about, to realize being stably connected with for metope connector and wall surface fixture, it is preferable that holding tank 31
Slot bottom is provided with the partition 36 extended to notch side, and holding tank 31 is divided into the first holding tank and second and accommodated by partition 36
Slot.First holding tank and the second holding tank carry out limited support to the first mounting wall and the second mounting wall respectively, so as to metope company
Fitting is stably connected with wall surface fixture realization.
In the present embodiment, partition 36, part mounting plate (mounting plate in 36 left side of partition), the first side wall and the first limit
Plate 32 is enclosed the first holding tank, and the first holding tank is for accommodating the first mounting wall, the opposite end difference of the first mounting wall
It is connected on partition 36 and the first side wall;Partition 36, part mounting plate (mounting plate on 36 right side of partition), second sidewall and second
Limit plate 33 is enclosed the second holding tank, and the second accommodation groove is for accommodating the second mounting wall, the opposite end of the second mounting wall
It is connected in partition 36 and second sidewall respectively.
In the present embodiment, the free end of the first limit plate 32 and the second limit plate 33 is provided with to 31 slot bottom of holding tank
The retention bead that side extends.To avoid shingle nail connector 20 from deviating from from holding tank 31, in the first limit plate 32 and the second limit
Retention bead is arranged in the free end of position plate 33, and retention bead is connected on the mounting wall of shingle nail connector 20, mounting plate and limit
Position protrusion clamps mounting wall simultaneously and is limited.
In the present embodiment, mounting groove extends along the width direction of connecting plate 34, and penetrates through opposite the two of connecting plate 34
Hold end face.Mounting groove penetrates through the opposite end end face of connecting plate 34, so that connecting plate 34 can be bent along mounting groove, to adjust
The height of connecting plate 34 improves flexibility to be applicable in different installation spaces.The shape of mounting groove may include a variety of, be square
Just connecting plate 34 is turned up, and in the present embodiment, the width of mounting groove is in be gradually reduced from notch to slot bottom.
In the present embodiment, the mounting hole for accommodating fixing piece is provided on connecting plate 34, mounting hole penetrates through mounting groove
Setting.Fixing piece can be hidden in mounting groove or mounting hole, facilitated connecting plate 34 and adjusted foot fixing piece 43 and adjust foot 45
Connection, adjusting foot 45 has buffer function, can absorb the fluctuating on wall, so that the decorative cover of shingle nail keeps straight, keeps away
Exempt from the aesthetics of influence shingle nail.
In the present embodiment, connecting plate 34 and the slot bottom of mounting groove 31 are an integral molding structure.Using integrated formed structure,
It can simplify manufacturing process, improve the structural strength of shingle nail fixing piece 30.
To reduce weight, reduction production cost, while meeting durability requirements, in the present embodiment, shingle nail fixing piece
30 are made by aluminum alloy materials or plastic material.Aluminum alloy materials have the advantages that intensity is high, plasticity is good, weight is low etc., fit
For making shingle nail fixing piece 30.For the service life for extending shingle nail fixing piece 30, it is solid that anti-corrosion layer is coated on shingle nail
The surface for determining part 30 avoids water mist etc. from corroding shingle nail fixing piece 30;Moreover, being provided on shingle nail fixing piece 30 corrosion-resistant
Layer, keeps 30 surface of shingle nail fixing piece smooth, the obvious shortcomings such as pore-free, scar, burr, spot, corrosion, Lai Tigao shingle nail
The aesthetics and user satisfaction of fixing piece 30.
Fig. 6 is the schematic diagram for flushing caulking strip of shingle nail integrated installation assembly shown in Fig. 3.As shown in fig. 6, flushing embedding
Stitching item 10 includes pedestal, strut 12 and sealing bar 13.
Preferably, the strut 12 that caulking strip 10 includes pedestal 11 and extends from pedestal 11 is flushed, strut 12 is along length side
To multiple sealing bars 13 are arranged at intervals with, sealing bar 13 is used to seal the gap between two adjacent shingle nails.It will flush embedding
Stitch the gap 44 that item 10 is inserted between the first shingle nail 41 and the second shingle nail 42, the bottom face of pedestal 11 and the first shingle nail
41, the second shingle nail 42 concordantly setting, the opposite sides wall surface of pedestal 11 respectively with the first shingle nail 41 and the second shingle nail 42
It abuts, strut 12 is extended vertically upwards from the top end face of pedestal 11, and strut 12 is that multiple sealing bars 13 provide a supporting role, multiple
Sealing bar 13 generates deformation when being squeezed by the first shingle nail 41 and the second shingle nail 42, to restore deformation, is closely connected to
On first shingle nail 41 and the second shingle nail 42, for sealing the gap 44 between the first shingle nail 41 and the second shingle nail 42;
It avoids steam dust etc. to enter in gap 44 simultaneously, improves the waterproof performance for flushing device;Traditional gap filling is saved simultaneously
Process simplifies construction process, avoids pollution operating environment.
In the present embodiment, strut 12 includes the body of rod and guide end, and sealing bar 13 is arranged along the length direction interval of the body of rod,
Guide end is connect by the body of rod with pedestal 11, and the width of guide end is in gradually increase towards pedestal 11 from the distant to the near.Guide end tool
There is the width of gradual change, the difficulty in gap 44 is entered for reducing the body of rod and pedestal 11, by the sealing that multilayer is arranged on the body of rod
Bar 13, it is multi-sealed to be provided for gap 44, improve leakproofness.
To avoid sealing bar from being broken when being squeezed, in the present embodiment, the junction of sealing bar 13 and the body of rod
It is provided with rounding off.By rounding off, the intensity for flushing caulking strip is improved, increases the one of sealing bar 13 and strut 11
Property.
In the present embodiment, the width of pedestal 11 is in be gradually reduced towards strut 12 from the distant to the near.To improve bonding strength,
It is connected between pedestal 11 and strut 12 using grading profile.The width of the bottom face of pedestal 11 is greater than the width of the body of rod, so as to base
Seat 11 provides stable support for strut 12 and sealing bar 13.The minimum widith phase of the width of the body of rod of strut 12 and pedestal 11
Together.
To improve leakproofness, in the present embodiment, the free end of sealing bar 13 extends towards close to 11 side of pedestal.Sealing
Bar 13 is tilted towards the extension of pedestal 11, makes to flush caulking strip 10 with stronger deformability, to improve leakproofness.
To further increase leakproofness, in the present embodiment, strut 12 is circumferentially arranged, and there are two sealing bars 13, and two close
The axisymmetrical that bar 13 is sealed along strut 12 is distributed.Sealing bar 13 is symmetricly set on the two sides of 12 axis of strut, two sealing bars 13
When being squeezed by the first shingle nail 41 and the second shingle nail 42, deflection is identical, keeps center of gravity constant.
In the present embodiment, there are six sealing bars 13 for setting on strut 12, symmetrical two-by-two, formation triple seal, and three
Resealing is spaced apart along the extending direction of strut 12.Triple seal is followed successively by lower seal, middle part from pedestal 11 to guide end
Sealing and top seal, middle part sealing and the distance between lower seal be less than be located between middle part sealing and top seal away from
From.
Be to improve to the leakproofness in gap, in the present embodiment, two sealing bars 13 being circumferentially arranged along strut 12 from
It is greater than the width of pedestal 11 by the distance between end.The opposite sides of pedestal 11 respectively with the first shingle nail 41 and the second shingle nail
42 abut, and the distance of the free end of two sealing bars 13 is greater than the width of pedestal 11, when flushing in 10 inserted into gap 44 of caulking strip,
First shingle nail 41 and the second shingle nail 42 squeeze sealing bar 13, bring it about deformation, and to restore deformation, sealing bar 13 is closely
It is fitted on the first shingle nail 41 and the second shingle nail 42, to improve leakproofness.
In the present embodiment, strut 12 is made using hard plastic;Pedestal 11 and sealing bar 13 are all made of flexible modeling
Material is made.It flushes caulking strip 10 to be made using the soft or hard bond material of PVC, strut 12 is made using hard plastic, is made
It provides the support of higher-strength for sealing bar 13;Pedestal 11 and sealing bar 13 are made using flexiplast, flexiplast makes
Pedestal 11 and sealing bar 13 can carry out deformation, to provide better seal effect for gap 44.
In the present embodiment, caulking strip 10 is flushed to be an integral molding structure.Using integrated formed structure, production can simplify
Process improves the structural strength for flushing caulking strip 10.
Fig. 7 is the partial enlargement diagram in the portion B of shingle nail integrated installation assembly shown in FIG. 1.Fig. 8 is shown in Fig. 7
The schematic diagram of the vertical dragon of the inner corner trim of shingle nail integrated installation assembly.Fig. 9 is the inner corner trim of shingle nail integrated installation assembly shown in Fig. 7
The schematic diagram of plug-in unit.Figure 10 is the schematic diagram of the inner corner trim caulking strip of shingle nail integrated installation assembly shown in Fig. 7.Such as Fig. 7 to figure
Shown in 10, inner corner trim mounting assembly includes: inner corner trim vertical keel 80 and inner corner trim plug-in unit 60.
Inner corner trim plug-in unit 30 includes the first mounting plate 32 and the second mounting plate 33 for extending from the first mounting plate 32, and first
It is provided with mounting groove on mounting plate 32, is provided with insertion end 31 on the second mounting plate 33;
Inner corner trim vertical keel 80 includes the first limited wall 81 and the second limited wall 82 extended from the first limited wall 81,
The first mounting groove 85 and the second mounting groove 86 are respectively arranged on first limited wall 81 and the second limited wall 82;First limited wall 81
The junction of second limited wall 82 is provided with mounting base 83, is set on the first side wall parallel with the first limited wall 81 of mounting base 83
It is equipped with the inserting groove 84 being used cooperatively for the insertion end 31 with inner corner trim plug-in unit 30, the first shingle nail 41 of wall inner corner trim passes through inner corner trim
First mounting plate 32 of plug-in unit 30 is connected in mounting base 83;Second mounting plate 33 of the second limited wall 82 and inner corner trim plug-in unit 30 can
Second shingle nail 42 of gripper wall inner corner trim, and the second sidewall and the second shingle nail 42 that mounting base 83 is parallel with the second limited wall 82
End face abut.
First limited wall 81 of inner corner trim centre keel 10 and the second limited wall 82 are abutted with the two sides wall of wall inner corner trim respectively,
The insertion end 31 of inner corner trim plug-in unit 30 is inserted into inserting groove 84, the first mounting plate 32 is abutted with the second limited wall 82, the second peace
Loading board 33 is abutted with the first side wall of mounting base 83;The adjacent both sides of the face of first shingle nail 41 are connected to the first mounting plate 32
With the second mounting plate 33, and it is fixed by fixing piece;Second shingle nail 42 is inserted into the first limited wall 81 and the second installation
Between plate 33, to realize the fixation to the first shingle nail 41 and the second shingle nail 42, insertion end can retreat in inserting groove 84,
It adjusts the installation site of the second shingle nail 42, to absorb installation error, improves installation accuracy.Using above-mentioned inner corner trim centre keel
The quick assembling and accurate positioning of the first shingle nail and the second shingle nail at wall inner corner trim can be achieved, reduce installation difficulty, improve peace
Precision is filled, guarantees installation quality.
In the present embodiment, inserting groove 84 is disposed with gripping section and expansion segment from slot bottom to notch, and gripping section is used for
Clamping limit inner corner trim plug-in unit 30, expansion segment are connected to by notch with outside.Expansion segment is used to reduce the insertion end of inner corner trim plug-in unit 30
Resistance when 31 installation, gripping section is for clamping insertion end 31 to realize fixation, to improve assembling speed, it is difficult to reduce assembly
Degree.
To further decrease assembly difficulty, in the present embodiment, the notch of inserting groove 84 is provided with guide surface, guide surface
Diameter is in be gradually reduced towards slot bottom from the distant to the near.Insertion end 31 can be rapidly inserted into grafting under the guiding function of guide surface
In slot 84, to realize quick assembling.
In the present embodiment, it is arranged jagged in the second sidewall of mounting base 83, notch is towards 81 side of the first limited wall
Extend to form adjusting grooves 88.By the way that adjusting grooves 88 are arranged, deformation space is provided for mounting base 83, increases the change of mounting base 83
Shape ability, to absorb the installation error of the second shingle nail 42.
In the present embodiment, be provided with loss of weight through-hole 87 in mounting base 83, loss of weight through-hole 87 towards the first mounting groove 85 and/
Or second mounting groove 86 hole wall on be provided with stiffening plate.Loss of weight through-hole 87 can reduce the weight of inner corner trim vertical keel, meet light
The requirement of quantization;Loss of weight through-hole 87 is that mounting base 83 provides deformation space, to absorb the first shingle nail 41 and the second shingle nail
42 installation error realizes accurate installation.Stiffening plate is set on hole wall, the first limited wall 81 and the second limited wall 82 can be improved
Intensity, so as to for adjust foot 50 support is provided.
For the installation difficulty for reducing shingle nail and inner corner trim vertical keel, in the present embodiment, the first limited wall 81 and/or the
The free end of both two limited walls 82 is guide end, and the width of guide end is in gradually to subtract away from mounting base 83 from the near to the distant
It is small.First shingle nail 41 and the second shingle nail 42 can quickly be connected to inner corner trim vertical keel 80 under the guiding function of guide surface
On, to realize quick assembling.
In the present embodiment, inner corner trim vertical keel further include: the first waterproof adhesive tape, the setting of the first waterproof adhesive tape is in the first limit
Position wall 81 and/or the second limited wall 82 towards on 13 1 side surface of mounting wall, the first waterproof adhesive tape along the first limited wall 81 and/
Or second limited wall 82 length direction extend.First waterproof adhesive tape is used to improve the waterproof performance of inner corner trim vertical keel 80, leads to
The area for increasing the first waterproof adhesive tape is crossed, can further improve waterproof performance.
Preferably, inner corner trim installation assembly further include: inner corner trim caulking strip 70, inner corner trim caulking strip 70 include support portion 71 and setting
In the sealing 73 and guide part 72 of 71 opposite end of support portion, 71 height of support portion are greater than the height of guide part 72 and are less than
The height of sealing 73, guide part 72 enter the seam between the first shingle nail 41 and the second shingle nail 20 for guiding support 71
In gap, sealing 73 is used for sealing off gap.
There are gap between first shingle nail 41 and the second shingle nail 42, the guide part 72 of inner corner trim caulking strip 70 guides support
Portion 71 enters in the gap between the second mounting plate 33 and the second shingle nail 42, is that the second shingle nail 21 provides branch by support portion 71
Support effect;Sealing 73 is used to seal the gap between the first shingle nail 41 and the second shingle nail 42;Steam dust is avoided simultaneously
Deng entering in gap 44, the waterproof performance of inner corner trim installation assembly is improved, while saving traditional gap filling process, simplifies construction
Process.Inner corner trim caulking strip 70 can reinforce inner corner trim vertical keel 80 to the fixed effect of the first shingle nail 41 and the second shingle nail 42;
And for sealing the gap 44 between the first shingle nail 41 and the second shingle nail 42, relatively closed space is provided.
In the present embodiment, the insertion end 61 of inner corner trim plug-in unit 60 is used cooperatively with the inserting groove 84 of inner corner trim vertical keel 80,
And it can be moved along the depth direction of inserting groove 84;Be provided on first limited wall 81 and/or the second limited wall 82 at least one
One mounting groove 85 and/or the second mounting groove 86, fixing piece can be through the first mounting groove 85 and/or the second mounting grooves 86 and by inner corner trim
Plug-in unit 60 is fixed to predeterminated position.
Inner corner trim plug-in unit 60 is inserted into inserting groove 84 by insertion end 61, depth direction of the inner corner trim plug-in unit 60 to inserting groove 84
Extended, when the gap between the first shingle nail 41 and the second shingle nail 42 is larger, the second shingle nail 42 can not be connected to slotting
When access slot 84, position of the insertion end 61 in inserting groove 84 is adjusted, exits insertion end 61 on a small quantity, extends inserting groove 84 in outside
Length, to effectively absorb error.Inner corner trim plug-in unit 60 can reduce by 42 installation difficulty of the first shingle nail 41 and the second shingle nail,
The assembly difficulty of inner corner trim installation assembly is reduced, work progress is simplified, saves the set-up time.
In the present embodiment, insertion end 61 is provided with guide portion far from a side end face of the first mounting plate 62.It guide portion can
To reduce the difficulty that insertion end 61 enters inserting groove 84, the assembly difficulty of inner corner trim installation assembly is reduced, can be saved the set-up time.
The implementation of guide portion includes a variety of, for example, guide portion is inclined-plane, smooth curved surface or is inclined-plane and curved surface knot
The mode of conjunction.In the present embodiment, the width of insertion end 61 is in and first gradually increases to protect afterwards from guide portion towards the first mounting plate 62
It holds constant.
In the present embodiment, insertion end 61 is hollow structure.Hollow structure is that insertion end 61 provides deformation space, works as insertion
When end 61 is squeezed, it is conveniently inserted into inserting groove 84, installation difficulty can be reduced;After insertion, for restore deformation, insertion end 61 with
The inner wall of inserting groove 84 abuts, to further increase the bonding strength that insertion end 61 is inserting groove 84.
In the present embodiment, inner corner trim plug-in unit uses integrated formed structure, can simplify manufacturing process, improves inner corner trim plug-in unit 60
Structural strength.
To reduce weight, reduce production cost, while meeting durability requirements, in the present embodiment, inner corner trim plug-in unit 60 by
Aluminum alloy materials or plastic material are made.Aluminum alloy materials have the advantages that intensity is high, plasticity is good, weight is low etc., are suitable for
Make inner corner trim plug-in unit 60.For the service life for extending inner corner trim plug-in unit 60, anti-corrosion layer is coated on the surface of inner corner trim plug-in unit 60, avoids
Water mist etc. corrodes inner corner trim plug-in unit 60;Moreover, being provided with anti-corrosion layer on inner corner trim plug-in unit 60, keep 60 surface of inner corner trim plug-in unit smooth,
The obvious shortcomings such as pore-free, scar, burr, spot, corrosion, the aesthetics and user satisfaction of Lai Tigao inner corner trim plug-in unit 60.
Inner corner trim caulking strip 70 is fitted and connected for realizing the vertical dragon 80 of inner corner trim and the second shingle nail 42, to further increase
It is bonded effect, in the present embodiment, the bottom end end face of sealing 73, support portion 71 and guide part 72, which maintains an equal level, to be arranged, and upwards
Extend.Sealing 73 is abutted by top end face with the first shingle nail 41, and support portion 71 supports inner corner trim vertical by top end face
Keel 80, guide part 72 provide guiding role by the setting of top end slope;Sealing 73, support portion 71 and guide part 72 are equal
Connection is abutted with the second shingle nail 42 by bottom end end face, when the bottom end end face of sealing 73, support portion 71 and guide part 72 is held
When flat setting, three can realize with the second shingle nail 42 and preferably be fitted and connected, to be the first shingle nail 41 and the second metope
Plate 42 provides better supporting role.
In the present embodiment, sealing 73 is provided with round and smooth mistake towards between a side surface and support portion 71 for support portion 71
It crosses.By setting rounding off, it can be achieved that inner corner trim caulking strip 70 and shingle nail fit closely, further increase support strength with
Leakproofness.
In the present embodiment, sealing 73 is provided with bent area 74 backwards to a side surface of support portion 71.Sealing 73 is used
Gap 44 between the first shingle nail 41 of sealing and the second shingle nail 42;When sealing 73 is installed in gap 44, by
The extruding of first shingle nail 41 and the second shingle nail 42, sealing 73 generates deformation by bent area 74, to be fitted tightly over
On first shingle nail 41 and the second shingle nail 42, to improve the leakproofness to gap 44.
In the present embodiment, the bending angle that bent area 74 is formed is obtuse angle.Obtuse angle makes bent area 74 have biggish change
Shape space, while when being squeezed, the top and bottom end of bent area 74 can be closely adhered to the first shingle nail 41 and
On two shingle nails 42, Lai Tigao leakproofness.
The implementation of guide part 72 includes a variety of, for example, guide part 72 is inclined-plane, smooth curved surface or is inclined-plane and song
The mode that face combines.Preferably, the height of guide part 72 is in gradually increase towards support portion 71 from the distant to the near.
In the present embodiment, support portion 71 and guide part 72 are all made of hard plastic and are made;Sealing 73 is using soft
Property plastic production forms.Inner corner trim caulking strip 70 is made using the soft or hard bond material of PVC, makes support portion using hard plastic
71 and guide part 72, so that its inner corner trim vertical keel 80 is provided the support of higher-strength;Sealing 73 is made using flexiplast,
Flexiplast makes sealing 73 that can carry out deformation, to provide better seal effect for gap 44.
Support portion 71 and guide part 72 are made using identical material, in the present embodiment, support portion 71 and guiding
Portion 72 is an integral molding structure.Using integrated formed structure, manufacturing process can simplify, the structure for improving inner corner trim caulking strip 70 is strong
Degree.
Figure 11 is the partial enlargement diagram in the portion C of shingle nail integrated installation assembly shown in FIG. 1.Figure 12 is shown in Fig. 1
Shingle nail integrated installation assembly wall external corner schematic diagram.As is illustrated by figs. 11 and 12, external corner fixing piece 50 includes mounting rod
51, the first protrusion 52, the second protrusion 53, the first fixation wall 54 and the second fixation wall 55.
External corner fixing piece 50 is fixed including mounting rod 51, the first protrusion 52, the second protrusion 53, the first fixation wall 54 and second
Wall 55, the first protrusion 52 and the second protrusion 53 are separately positioned on the opposite sides of the body of rod of mounting rod 51,54 He of the first fixation wall
Second fixation wall 55 is separately positioned in the first end of the body of rod, and the extending direction of 54 the two of the first protrusion 52 and the first fixation wall is flat
Row, the second protrusion 53 is parallel with the extending direction of both the second fixation walls 55, and the second end of mounting rod 51 is for being connected to first
In gap between shingle nail 41 and the second shingle nail 42.
First fixation wall 54 and the second fixation wall 55 abut respectively and are fixed on the first shingle nail 41 and the second shingle nail 42
On, so that the first shingle nail 41 and the second shingle nail 42 are connected as one by external corner fixing piece 50, the first raised 52 Hes
Second protrusion 53 is plugged on respectively in the through-hole of the first shingle nail 41 and the second shingle nail 42, increases by the first shingle nail 41 and second
The connective stability of shingle nail 42 and external corner fixing piece 50;The setting of mounting rod 51 the first shingle nail 41 and the second shingle nail 42 it
Between gap in, the leakproofness between the first shingle nail 41 and the second shingle nail 42 can be enhanced.It is used using above-mentioned external corner fixing piece
In the quick assembling and accurate positioning of realizing the first shingle nail and the second shingle nail at wall external corner, installation difficulty is reduced, improves peace
Precision is filled, guarantees installation quality.
In general, the first shingle nail and the second shingle nail use identical wall board structure, to improve stability, in this implementation
In example, the first protrusion 52 and the second protrusion 53 are distributed along the middle line of the body of rod in mirror symmetry;First fixation wall 54 and second is fixed
Wall 55 is distributed along the middle line of the body of rod in mirror symmetry.External corner fixing piece 50 uses mirror symmetry distributed architecture, and stable structure is the
One shingle nail 41 and the second shingle nail 42 provide stable support.
In general, the side walls of wall external corner are mutually perpendicular to, to realize accurate fixation of the shingle nail at wall external corner, in this reality
It applies in example, the extending direction of 53 the two of the first protrusion 52 and the second protrusion intersects vertically;First fixation wall 54 and the second fixation wall
Both 55 intersect vertically.By the way that the extending direction of external corner fixing piece 50 is arranged, to ensure that shingle nail is parallel with the wall of wall external corner,
To realize accurate installation.
It is installed for convenience of fixation wall and shingle nail, reduces assembly difficulty, improve assembling speed, in the present embodiment, first
Be provided with mounting hole in fixation wall 54 and/or the second fixation wall 55, fixing piece is inserted into mounting hole, by the first fixation wall 54 and/
Or second fixation wall 55 be fixed on the first shingle nail 41 and/or the second shingle nail 42 of wall external corner.By the first fixation wall 54 and/
Or second fixation wall 55 be connected on the first shingle nail 41 and/or the second shingle nail 42 respectively, by fixing piece be inserted into mounting hole in,
And run through the first shingle nail 41 and/or the second shingle nail 42, quickly to fix.
In the present embodiment, mounting hole is provided in the first fixation wall 54 and the second fixation wall 55;Fixing piece include but
It is not limited to screw.
For simplify apparatus structure, in the present embodiment, first protrusion 52 include the first support plate and the first guide plate, first
Support plate extends out from the body of rod, and parallel with 41 direction of the first shingle nail of wall external corner;The free end of first support plate extends
First guide plate out, the first guide plate may be guided the first support plate and enter in the groove of the first shingle nail 41;First guide plate
Free end is provided with the first flange.First guide plate guides the first support plate and the first flange to enter the through-hole of the first shingle nail 41
Interior, to reduce the assembly difficulty of the first protrusion 52, the first support plate is that the decorative layer of the first shingle nail 41 provides a supporting role;The
One flange is used to increase the support strength of the first support plate, so that the first protrusion 52 can provide for the first shingle nail 41 stablizes branch
Support.
To increase stability of strutting system, in the present embodiment, a side surface of the first support plate towards wall external corner is provided with the
One rough layer, the first rough layer extend along the length direction of the first support plate.First rough layer can increase by first protrusion 52 with
Frictional force between first shingle nail 41, to increase connective stability.
To be further simplified apparatus structure, in the present embodiment, the second protrusion 53 includes the second support plate and the second guiding
Plate, the second support plate extend out from the body of rod, and parallel with 42 direction of the second shingle nail of wall external corner;The freedom of second support plate
The second guide plate is extended at end, and the second guide plate may be guided the second support plate and enter in the groove of the second shingle nail 42;Second leads
The free end of plate is provided with the second flange.Second guide plate guides the second support plate and the second flange to enter the second shingle nail 42
Through-hole in, to reduce the assembly difficulty of the second protrusion 53, the second support plate provides support for the decorative layer of the second shingle nail 42
Effect;Second flange is used to increase the support strength of the second support plate, so that the second protrusion 53 can provide for the second shingle nail 42
Stablize support.
To further increase stability of strutting system, in the present embodiment, a side surface of the second support plate towards wall external corner is set
It is equipped with the second rough layer, the second rough layer extends along the length direction of the second support plate.It is convex that second rough layer can increase by second
53 and the second frictional force between shingle nail 42 are played, to increase connective stability.
To further increase installation accuracy, in the present embodiment, the extension side of both the first support plate and second support plate
To supporting angle is formed, supporting angle is identical as the angle of wall external corner.By the way that the angle of support plate is arranged, can be provided for shingle nail
The support force parallel with wall, to increase stability of strutting system.
In addition, in the present embodiment, adhered layer, the first rough layer are provided on the first rough layer and/or the second rough layer
And/or second rough layer connect with the first shingle nail and/or the second shingle nail by adhered layer.It, can be with by the way that adhered layer is arranged
Increase bonding strength between the first protrusion 52 and the second protrusion 53 and the first shingle nail 41 and the second shingle nail 42, increases one
Property.
Figure 13 is the schematic diagram of another wall external corner for shingle nail integrated installation assembly.As shown in figure 13, external corner is fixed
Difference between 50 ' of part and external corner fixing piece 50 is: segmentation 51 ' of mounting rod, the first closure 52 ' of protrusion and the second closure protrusion
The structure of 53 ' is different.
First closure 52 ' of protrusion and the difference of the first protrusion 52 are that the first flange is extended to be connected with segmentation 51 ' of mounting rod
It connects, forms relatively closed structure, further increase support strength.
Second closure 53 ' of protrusion and the difference of the second protrusion 53 are that the second flange is extended to be connected with segmentation 51 ' of mounting rod
It connects, forms relatively closed structure, and the first flange is connect with the second flange, so that the first support plate, the first guide plate, first
Flange, the second support plate, the second directing plate and the second flange are enclosed the cavity of closure, further increase support strength.
The difference of segmentation 51 ' of mounting rod and mounting rod 51 exists, and mounting rod 51 is structure as a whole, and segmentation 51 ' of mounting rod is two
A spaced first rod segment and the second rod segment, the first end of the first rod segment is the first end of mounting rod 51, for being mounted on
In gap between first shingle nail 41 and the second shingle nail 42;The second end of first rod segment and the first support plate, the second support
Plate connection;The first end of second rod segment is connect with the first flange, the second flange, and the second end of the second rod segment is the of mounting rod 51
Two ends are connect with the junction of the first fixation wall 54 and the second fixation wall 55.
The use process of shingle nail integrated installation assembly is described further below.
When installing shingle nail 40, the top surface 411 of substrate 410 is provided with decorative layer 414, and bottom surface 412 is arranged towards wall,
The interconnecting piece for flushing device is arranged in the gap between two adjacent shingle nails 40, and opening 424 provides support for interconnecting piece
Effect, interconnecting piece are sealed gap;The slot of the close interconnecting piece of both first mounting portion and the second mounting portion respectively with
The card of protrusion 421 of two shingle nails 40 and connection, and limited by limiting card 422;Both first, second mounting portions it is remote
Slot from interconnecting piece is inserted into respectively in the groove 423 of two shingle nails 40, is sealed to groove 423.
When installing shingle nail connector 20, shingle nail fixing piece 30 is abutted with foot fixing piece 43 is adjusted, passes through bolt
Shingle nail fixing piece 30 is fixed on and adjusts foot fixing piece 43 and adjusts on foot 45.Shingle nail connector 20 is passed through into the first installation
Wall 214 and the second mounting wall 215 are connect with shingle nail fixing piece 30.The protrusion and groove of first shingle nail 41 are plugged on respectively
In second card slot and third card slot, the limiting card in the protrusion of the first retention bead 224 and the first shingle nail 41 cooperates, to incite somebody to action
First shingle nail 41 is fixed on the first mounting portion 22;The protrusion and groove of second shingle nail 42 are plugged on the 4th card slot respectively
In the 5th card slot, the limiting card in the protrusion of the second retention bead 234 and the second shingle nail 42 cooperates, by the second shingle nail
42 are fixed on the second mounting portion 23;First card slot is arranged between the first shingle nail 41 and the second shingle nail 42 in gap 44.
When installing shingle nail fixing piece 30, the first shingle nail 41 and the second shingle nail 42 are separately mounted to metope connector
On 20, the first mounting wall and the second mounting wall of shingle nail connector 20 are inserted respectively into the first accommodation groove and the second accommodation groove
Interior, the opposite end of the first mounting wall is connected to respectively on partition 36 and the first side wall, the opposite end difference of the second mounting wall
It is connected in partition 36 and second sidewall;First limit plate 32 and the second limit plate 33 are respectively the first mounting wall and the second installation
Wall provides a supporting role, the first limit plate 32 and the second limit plate 33 be on retention bead limit the first mounting wall and respectively
Two mounting walls are connected on the mounting plate of 36 two sides of partition.Positioning plate 35 is that the first shingle nail 41 provides positioning action, fixing piece
Through the mounting hole of connecting plate 34, shingle nail fixing piece 30 is fixed on leveling keel 43 and regulating part 45.
When installation flushes caulking strip 10, caulking strip 10 will be flushed and be inserted between the first shingle nail 41 and the second shingle nail 42
Gap 44, the concordant setting of the bottom face of pedestal 11 and the first shingle nail 41, the second shingle nail 42, the two lateral walls of pedestal 11
Face is abutted with the first shingle nail 41 and the second shingle nail 42 respectively, and strut 12 is extended vertically upwards from the top end face of pedestal 11, branch
Bar 12 is that multiple sealing bars 13 provide a supporting role, and there are six sealing bars 13 for setting on strut 12, symmetrical two-by-two, forms three
Resealing, triple seal are spaced apart along the extending direction of strut 12.Two sealing bars 13 of every resealing are by the first wall
Panel 41 and the second shingle nail 42 generate deformation when squeezing, and to restore deformation, are closely connected to the first shingle nail 41 and the second wall
On panel 42, for sealing the gap 44 between the first shingle nail 41 and the second shingle nail 42.
When installing inner corner trim mounting assembly, by the first limited wall 81 of inner corner trim centre keel 80 and the second limited wall 82 respectively with
The two sides wall of wall inner corner trim abuts, and is connected separately on the first mounting groove 85 and the second mounting groove 86 and adjusts foot fixing piece 43, adjusts
Section foot 45, which is fixed on, to be adjusted on foot fixing piece 43, and is abutted with metope, for realizing the first limited wall 81 and the second limited wall 82
Straight assembly on wall;The second waterproof adhesive tape is pasted in the insertion end 61 of inner corner trim plug-in unit 60, insertion end 61 is inserted into
In inserting groove 84, the first mounting plate 63 is abutted with the second limited wall 82, and the second mounting plate 63 and the first side wall of mounting base 83 support
It connects;The adjacent both sides of the face of first shingle nail 41 are connected to the first mounting plate 62 and the second mounting plate 63, and pass through fixing piece
It is fixed;In the first waterproof of side surface mount towards mounting base 83 of the first limited wall 81 and/or the second limited wall 82
Adhesive tape, the second shingle nail 42 are inserted between the first limited wall 81 and the second mounting plate 63, to realize to the first shingle nail 41
With the fixation of the second shingle nail 42, insertion end 61 can retreat in inserting groove 84, to adjust the installation site of the second shingle nail 22.
When installing external corner fixing piece 50, the first rough layer and of the first support plate is respectively adhered in two adhered layers
On second rough layer of two support plates, the first protrusion 52 and the second drawing by the first guide plate and the second guide plate of protrusion 53
It leads, is plugged in the through-hole of the first shingle nail 41 and the second shingle nail 42 respectively, so that the first support plate and the first flange difference
It is connected on the hole wall of the opposite sides of the through-hole of the first shingle nail 41, so that the second support plate and the second flange are connected to respectively
On the hole wall of the opposite sides of the through-hole of second shingle nail 42, the first end of mounting rod 51 is inserted into the first shingle nail 41 and
In gap between two shingle nails 42, the first fixation wall 54 and the second fixation wall 55 are connected to the first shingle nail 41 and second respectively
On shingle nail 42, two screws are inserted into respectively in the mounting hole of the first fixation wall 54 and the second fixation wall 55, it is fixed by first
Wall 54 and the second fixation wall 55 are separately fixed on the first shingle nail 41 and the second shingle nail 42, so that the first shingle nail 41 and
Two shingle nails 42 are connected as one by external corner fixing piece 50.
The present invention also provides a kind of wall surface decorating methods, use such as above-mentioned shingle nail integrated installation assembly, comprising: (1)
Multiple shingle nails 40 are sequentially distributed along wall extending direction;(2) yin is installed on the outside of the first side end of multiple shingle nails 40
Angle mounting assembly, the support of inner corner trim mounting assembly and limit are located at the shingle nail of the first side end, and will be located at the first side end
The free end of shingle nail is fixed with wall;(3) it will flush on the wall that device is fixed between two adjacent shingle nails 40, phase
Two adjacent shingle nails 40 are connected as one by flushing device, and are fixed by flushing device with wall;(4) it repeats to walk
Suddenly (3) are until the wall inner corner trim of installation wall or/and the shingle nail 40 of wall external corner two sides, inner corner trim mounting assembly or/and external corner are consolidated
Determine part 50 to be fixed on wall inner corner trim or/and wall external corner, the shingle nail 40 positioned at wall inner corner trim or/and wall external corner two sides is pacified by inner corner trim
Arrangement or/and external corner fixing piece 50 are fixed with wall;(5) step (4) are repeated until being positioned at the of multiple shingle nails 40
The shingle nail 40 of two side ends installs inner corner trim mounting assembly, inner corner trim installation group on the outside of the second side end of multiple shingle nails 40
Part support and limit are located at the shingle nail 40 of the second side end, and will be located at free end and the wall of the shingle nail 40 of the second side end
Body is fixed.Wall decoration is carried out using above-mentioned shingle nail integrated installation assembly, it can be achieved that the easy of shingle nail is installed, raising is constructed
Speed, while avoiding generation environment pollution or decoration garbage;Shingle nail and wall quick assembling can be achieved, can simplify and construct
Journey shortens the construction period, avoids generating more rubbish at the construction field (site), avoids being easy to leave in positions such as floor, doorframes
Trace improves industrialized level.
Preferably, in step (3) further include: two adjacent shingle nails 40 are arranged in shingle nail connector 20 by (3a)
Between, two adjacent shingle nails 40 are connected by shingle nail connector 20, and multiple shingle nails 40 are connected as one;
Multiple leveling keel are separately fixed on the adjacent corresponding wall in 40 junction of shingle nail by (3b), by shingle nail fixing piece 30
It is connect with the leveling keel of two adjacent shingle nails 40, shingle nail connector 20 is connect with shingle nail fixing piece 30;(3c)
It will flush in the gap 44 that caulking strip 10 is installed between two adjacent shingle nails 40.It can be realized using the above-mentioned device that flushes
The quick assembling of adjacent shingle nail, stability is good, improves waterproof performance;Traditional gap filling process is saved simultaneously, and simplification is applied
Work process, avoids pollution operating environment.
Preferably, in step (4) further include: (4a) installs the first mounting groove 85 and second of inner corner trim vertical keel 80
It is respectively connected on slot 86 and adjusts foot 45, the first limited wall 81 and the second limited wall 82 are respectively by adjusting the two of foot 45 and wall inner corner trim
Side wall body abuts;The insertion end 61 of inner corner trim plug-in unit 60 is plugged on the inserting groove 84 of inner corner trim vertical keel 80 by (4b), by inner corner trim
First mounting plate 62 of plug-in unit 60 is abutted with the second limited wall 82, the second mounting plate 63 and inner corner trim vertical keel of inner corner trim plug-in unit 60
The first side wall of 80 mounting base 83 abuts;The adjacent both sides of the face of first shingle nail 41 are connected to the first installation by (4c) respectively
On plate 62 and the second mounting plate 63, and it is fixed on the second mounting plate 63;By the first limited wall 81 of the second shingle nail 42 insertion with
It is fixed between second mounting plate 63.First shingle nail and the second metope at wall inner corner trim can be realized using above-mentioned inner corner trim centre keel
The quick assembling of plate and accurate positioning reduce installation difficulty, improve installation accuracy, guarantee installation quality.
Preferably, in step (4c) further include: be inserted by 72 guiding support 71 of guide part of inner corner trim caulking strip 70
It is that the second shingle nail 42 provides support by support portion 71 in gap between first mounting plate 62 and the second shingle nail 42;Inner corner trim
The sealing 73 of caulking strip 70 is used to seal the gap 44 between the first shingle nail 41 and the second shingle nail 42.Inner corner trim caulking strip 70
It avoids steam dust etc. from entering in gap 44, improves the waterproof performance of inner corner trim installation assembly, while saving traditional gap filling
Process simplifies construction process.
Preferably, in step (4) further include: (4d) mounting rod 51 of external corner fixing piece 50 is arranged in the first shingle nail
41 and the second gap 44 between shingle nail 42 in, the first protrusion 52 of external corner fixing piece 50 and the second protrusion 53 are distinguished into grafting
In the through-hole of the first shingle nail 41 and the second shingle nail 42, by the first fixation wall 54 of external corner fixing piece 50 and the second fixation wall
55 abut respectively and are fixed on the first shingle nail 41 and the second shingle nail 42.Using above-mentioned external corner fixing piece for realizing wall sun
The quick assembling and accurate positioning of first shingle nail and the second shingle nail at angle reduce installation difficulty, improve installation accuracy, guarantee
Installation quality.
From the description above with practice it is found that shingle nail integrated installation assembly provided by the invention and wall decoration side
Method has the advantage that the easy peace that shingle nail can be realized using above-mentioned shingle nail integrated installation assembly compared with prior art
Dress improves speed of application, while avoiding generation environment pollution or decoration garbage.Shingle nail and wall quick assembling can be achieved, it can
Simplify work progress, shorten the construction period, avoids generating more rubbish at the construction field (site), avoid on floor, doorframe equipotential
It sets and is easy to leave a trace, improve industrialized level.Moreover, shingle nail integrated installation assembly occupies little space, it is easy to assembly quick,
Accurate positioning, flatness is high, good decorating effect, leakproofness and good waterproof performance.
It should be understood by those ordinary skilled in the art that: the above is only a specific embodiment of the present invention, and
It is not used in the limitation present invention, all any modification, equivalent substitution, improvement and etc. within purport of the invention, done should all include
Within protection scope of the present invention.
Claims (10)
1. a kind of shingle nail integrated installation assembly characterized by comprising
Multiple shingle nails, multiple shingle nails are arranged successively along wall extending direction, and the surface of the shingle nail is provided with dress
Adorn layer;
Device is flushed, the device that flushes is arranged between two adjacent shingle nails and for connecting two adjacent walls
Panel, two shingle nails flush device described in and fix with wall;
The wall inner corner trim of the wall is arranged in inner corner trim mounting assembly, the inner corner trim mounting assembly, positioned at wall inner corner trim two sides
The shingle nail is fixed by the inner corner trim mounting assembly with the wall;
The wall external corner of the wall is arranged in external corner fixing piece, the external corner fixing piece, described in wall external corner two sides
Shingle nail is fixed by the external corner fixing piece with the wall.
2. shingle nail integrated installation assembly according to claim 1, which is characterized in that the device that flushes includes:
Shingle nail connector, the shingle nail connector are arranged between two adjacent shingle nails, and for connecting phase
Two adjacent shingle nails;
Shingle nail fixing piece, the shingle nail connector are connect with the shingle nail fixing piece, and the shingle nail fixing piece is used for
Realize that the shingle nail connector and the leveling keel of two adjacent shingle nails are connect;
Caulking strip is flushed, the caulking strip that flushes is for sealing the gap between two adjacent shingle nails.
3. shingle nail integrated installation assembly according to claim 1 or 2, which is characterized in that the inner corner trim mounting assembly packet
It includes:
Inner corner trim plug-in unit, the inner corner trim plug-in unit include the first mounting plate and the second installation extended from first mounting plate
Plate is provided with mounting groove on first mounting plate, is provided with insertion end on second mounting plate;
Inner corner trim vertical keel, the inner corner trim vertical keel include the first limited wall and extend from first limited wall
The first mounting groove and the second mounting groove are respectively arranged on two limited walls, first limited wall and second limited wall;Institute
The junction for stating the first limited wall and second limited wall is provided with mounting base, and the mounting base and first limited wall are flat
It is provided with the inserting groove for being used cooperatively with the insertion end of the inner corner trim plug-in unit on capable the first side wall, the of wall inner corner trim
One shingle nail is connected in the mounting base by the first mounting plate of the inner corner trim plug-in unit;Second limited wall and the yin
Second mounting plate of angle plug-in unit can clamp the second shingle nail of the wall inner corner trim, and the mounting base and first limit
The parallel second sidewall of wall is abutted with the end face of second shingle nail.
4. shingle nail integrated installation assembly according to any one of claims 1 to 3, which is characterized in that the inner corner trim installation
Component further include:
Inner corner trim caulking strip, the inner corner trim caulking strip include support portion and the sealing that the support portion opposite end is arranged in and lead
To portion, the height of the support portion is greater than the height of the guide part and is less than the height of the sealing, and the guide part is used
In guiding the support portion to enter in the gap between first shingle nail and second shingle nail, the sealing is used for
Seal the gap.
5. shingle nail integrated installation assembly according to any one of claims 1 to 3, which is characterized in that the external corner is fixed
Part includes mounting rod, the first protrusion, the second protrusion, the first fixation wall and the second fixation wall, first protrusion and described second
Protrusion is separately positioned on the opposite sides of the body of rod of the mounting rod, and first fixation wall and second fixation wall are set respectively
It sets in the first end of the body of rod, first protrusion is parallel with the extending direction of both first fixation walls, and described the
Two protrusions are parallel with the extending direction of both second fixation walls, and the second end of the mounting rod is for being connected to described first
In gap between shingle nail and second shingle nail.
6. a kind of wall surface decorating method, which is characterized in that by using shingle nail collection such as described in any one of claim 1 to 5
At installation assembly, comprising:
(1) multiple shingle nails are sequentially distributed along wall extending direction;
(2) inner corner trim mounting assembly, the inner corner trim mounting assembly support are installed on the outside of the first side end of multiple shingle nails
With limit be located at the first side end the shingle nail, and will be located at the first side end the shingle nail free end with it is described
Wall is fixed;
(3) it will flush on the wall that device is fixed between two adjacent shingle nails, two adjacent walls
Panel flushes device described in and is connected as one, and flushes device described in and fix with the wall;
(4) step (3) are repeated until the wall inner corner trim of the wall or/and the shingle nail of wall external corner two sides are installed, by inner corner trim
Mounting assembly or/and external corner fixing piece are fixed on the wall inner corner trim or/and the wall external corner, be located at the wall inner corner trim or/and
The shingle nail of wall external corner two sides is solid by the inner corner trim mounting assembly or/and the external corner fixing piece and the wall
It is fixed;
(5) step (4) are repeated until the shingle nail of the second side end of multiple shingle nails is positioned at, in multiple institutes
It states and the inner corner trim mounting assembly is installed on the outside of the second side end of shingle nail, the inner corner trim mounting assembly support and limit are located at the
The shingle nail of two side ends, and the free end for being located at the shingle nail of the second side end is fixed with the wall.
7. wall surface decorating method according to claim 6, which is characterized in that in step (3) further include:
(3a) shingle nail connector is arranged between two adjacent shingle nails, is connected by the shingle nail connector
Two adjacent shingle nails, and multiple shingle nails are connected as one;
Multiple leveling keel are separately fixed on the adjacent corresponding wall in the shingle nail junction by (3b), and shingle nail is consolidated
Determine part to connect with the leveling keel of two adjacent shingle nails, by the shingle nail connector and the shingle nail fixing piece
Connection;
(3c) will be flushed in the gap that caulking strip is installed between two adjacent shingle nails.
8. wall surface decorating method according to claim 6 or 7, which is characterized in that in step (4) further include:
(4a) will be respectively connected with adjusting foot, the first limited wall and on the first mounting groove and the second mounting groove of inner corner trim vertical keel
Two limited walls pass through the adjusting foot respectively and abut with the two sides wall of wall inner corner trim;
The insertion end of inner corner trim plug-in unit is plugged on the inserting groove of the inner corner trim vertical keel by (4b), by the of the inner corner trim plug-in unit
One mounting plate is abutted with second limited wall, the installation of the second mounting plate of the inner corner trim plug-in unit and the inner corner trim vertical keel
The first side wall of seat abuts;
The adjacent both sides of the face of first shingle nail are connected to first mounting plate and second installation by (4c) respectively
On plate, and it is fixed on the second mounting plate;Second shingle nail is inserted into first limited wall and second mounting plate
Between be fixed.
9. wall surface decorating method according to claim 8, which is characterized in that in step (4c) further include:
By inner corner trim caulking strip through being inserted between first mounting plate and second shingle nail, and seal first shingle nail
Gap between second shingle nail.
10. wall surface decorating method according to claim 6 or 7, which is characterized in that further include:
(5) mounting rod of external corner fixing piece is arranged in the gap between first shingle nail and second shingle nail,
First protrusion of the external corner fixing piece and the second protrusion are plugged on first shingle nail and second shingle nail respectively
Through-hole in, the first fixation wall of the external corner fixing piece and the second fixation wall are abutted respectively and are fixed on first metope
On plate and second shingle nail.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810859178.XA CN109403575B (en) | 2018-07-31 | 2018-07-31 | Wall panel integrated installation assembly and wall decoration method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810859178.XA CN109403575B (en) | 2018-07-31 | 2018-07-31 | Wall panel integrated installation assembly and wall decoration method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109403575A true CN109403575A (en) | 2019-03-01 |
CN109403575B CN109403575B (en) | 2024-04-19 |
Family
ID=65463484
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810859178.XA Active CN109403575B (en) | 2018-07-31 | 2018-07-31 | Wall panel integrated installation assembly and wall decoration method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109403575B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110042994A (en) * | 2019-04-22 | 2019-07-23 | 浙江亚厦装饰股份有限公司 | A kind of quick levelling adjustment structure and inner corner trim integrated morphology |
CN110259017A (en) * | 2019-07-01 | 2019-09-20 | 浙江亚厦装饰股份有限公司 | Shingle nail installation assembly and its installation method |
CN110805220A (en) * | 2019-12-03 | 2020-02-18 | 浙江亚厦装饰股份有限公司 | Shingle assembly and method of installation |
CN111173221A (en) * | 2020-01-08 | 2020-05-19 | 佛山市鹏宇整装卫浴科技有限公司 | Concealed connecting wall panel and its composed wall, decoration structure and installation method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205330047U (en) * | 2015-12-30 | 2016-06-22 | 浙江亚厦装饰股份有限公司 | Wall frame reentrant corner joint system |
CN108049583A (en) * | 2017-12-30 | 2018-05-18 | 浙江亚厦装饰股份有限公司 | Corner brace, which is fixed, receives side member, prefabricated ceramic tile external corner and its installation method |
CN108308966A (en) * | 2017-12-30 | 2018-07-24 | 浙江亚厦装饰股份有限公司 | A kind of silver mirror mounting assembly and its installation method |
CN211114550U (en) * | 2018-07-31 | 2020-07-28 | 浙江亚厦装饰股份有限公司 | Integrated installation assembly of shingle nail |
-
2018
- 2018-07-31 CN CN201810859178.XA patent/CN109403575B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205330047U (en) * | 2015-12-30 | 2016-06-22 | 浙江亚厦装饰股份有限公司 | Wall frame reentrant corner joint system |
CN108049583A (en) * | 2017-12-30 | 2018-05-18 | 浙江亚厦装饰股份有限公司 | Corner brace, which is fixed, receives side member, prefabricated ceramic tile external corner and its installation method |
CN108308966A (en) * | 2017-12-30 | 2018-07-24 | 浙江亚厦装饰股份有限公司 | A kind of silver mirror mounting assembly and its installation method |
CN211114550U (en) * | 2018-07-31 | 2020-07-28 | 浙江亚厦装饰股份有限公司 | Integrated installation assembly of shingle nail |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110042994A (en) * | 2019-04-22 | 2019-07-23 | 浙江亚厦装饰股份有限公司 | A kind of quick levelling adjustment structure and inner corner trim integrated morphology |
CN110042994B (en) * | 2019-04-22 | 2024-05-14 | 浙江亚厦装饰股份有限公司 | Quick leveling adjusting structure and internal corner integrated structure |
CN110259017A (en) * | 2019-07-01 | 2019-09-20 | 浙江亚厦装饰股份有限公司 | Shingle nail installation assembly and its installation method |
CN110259017B (en) * | 2019-07-01 | 2024-09-17 | 浙江亚厦装饰股份有限公司 | Wall panel installation assembly and installation method thereof |
CN110805220A (en) * | 2019-12-03 | 2020-02-18 | 浙江亚厦装饰股份有限公司 | Shingle assembly and method of installation |
CN111173221A (en) * | 2020-01-08 | 2020-05-19 | 佛山市鹏宇整装卫浴科技有限公司 | Concealed connecting wall panel and its composed wall, decoration structure and installation method |
CN111173221B (en) * | 2020-01-08 | 2025-02-07 | 池州市千润宇信息技术有限公司 | Hidden connection wall panel and wall body, decoration structure and installation method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN109403575B (en) | 2024-04-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109356350A (en) | Shingle nail integrated installation assembly and wall surface decorating method | |
CN109403575A (en) | Shingle nail integrated installation assembly and wall surface decorating method | |
CN108952053A (en) | Shingle nail installation assembly and its installation method | |
AU2002240860B2 (en) | Wall boards or panel boards for use in interior construction and dry construction | |
CN108049590B (en) | Modularization metope and trailing | |
CN109497807B (en) | Curtain box structure, curtain box system and assembly method of curtain box system | |
CN113530131B (en) | Assembled kitchen wall surface fast-assembling assembly and installation method thereof | |
CN210177866U (en) | Wall keel | |
CN113404240B (en) | Wallboard mounting structure for wallboard corner and mounting method thereof | |
CN209837533U (en) | Fine setting flat fast-assembling wallboard reentrant corner mounting structure | |
CN109057249A (en) | Inner corner trim installation assembly and its installation method | |
CN212336485U (en) | Cellular board staggered-layer lap-joint section bar | |
CN218268931U (en) | Multifunctional inclined plane lamp closing-in section bar | |
CN216076085U (en) | Assembled wall leveling structure | |
CN210177867U (en) | Soil style of calligraphy wall fossil fragments | |
CN214740748U (en) | Invisible door frame matched with leveling wallboard | |
CN214462186U (en) | Suspended ceiling modeling structure | |
CN214302640U (en) | Decorate interior wallboard cell structure and assembled wallboard system | |
CN215631243U (en) | Assembled aluminum alloy wallboard mounting system | |
CN210177868U (en) | Open-word type wall fossil fragments | |
CN210622192U (en) | Decorative board secretly adorns connecting strip and decorative board secretly adorns structure | |
CN211058218U (en) | Aluminum profile mounting keel frame for laying wall porcelain plate | |
CN207332617U (en) | A kind of doorframe structure | |
CN211114550U (en) | Integrated installation assembly of shingle nail | |
CN113216550A (en) | Suspended wood veneer structure and mounting method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |