[go: up one dir, main page]

CN109371805A - A long-span multi-tower suspension cable system bridge and its construction method - Google Patents

A long-span multi-tower suspension cable system bridge and its construction method Download PDF

Info

Publication number
CN109371805A
CN109371805A CN201811352763.7A CN201811352763A CN109371805A CN 109371805 A CN109371805 A CN 109371805A CN 201811352763 A CN201811352763 A CN 201811352763A CN 109371805 A CN109371805 A CN 109371805A
Authority
CN
China
Prior art keywords
bridge
cable
suspension
multitower
large span
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811352763.7A
Other languages
Chinese (zh)
Inventor
张清华
程震宇
林飞
李俊
袁道云
郭亚文
卜之
卜一之
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Original Assignee
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University filed Critical Southwest Jiaotong University
Priority to CN201811352763.7A priority Critical patent/CN109371805A/en
Publication of CN109371805A publication Critical patent/CN109371805A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/02Suspension bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及桥梁,特别涉及一种大跨度多塔悬索体系桥梁及其施工方法,包括至少三座桥塔和两端连接桥塔的主梁,桥塔之间通过悬索组件相连,主梁从中部向两端依次为中段、过渡段和头段,位于中间位置的桥塔上端设置有抗滑移鞍座结构,桥梁的主缆为不间断的一整条,该主缆经过抗滑移鞍座结构将至少三座桥塔的上端串联;头段通过多根斜拉索与该头段相邻的桥塔连接;中段通过主缆上悬吊的多根悬索连接该主缆;过渡段通过斜拉索与桥塔连接,通过悬索与主缆连接;多根斜拉索、多根悬索和主缆组成悬索组件。采用本桥梁的斜拉悬索协作体系不仅相比于单跨桥梁跨径更长,还能有效解决目前跨径虽大但横向稳定性不足的悬索桥问题。

The invention relates to bridges, in particular to a large-span multi-tower suspension system bridge and a construction method thereof, comprising at least three bridge towers and main beams connecting the bridge towers at both ends, the bridge towers are connected by suspension components, and the main beams From the middle to the two ends are the middle section, the transition section and the head section in order. The upper end of the bridge tower at the middle position is provided with an anti-slip saddle structure. The main cable of the bridge is an uninterrupted whole. The saddle structure connects the upper ends of at least three bridge towers in series; the head section is connected to the adjacent bridge towers of the head section through a plurality of stay cables; the middle section is connected to the main cable through a plurality of suspension cables suspended on the main cable; the transition section is connected by The stay cable is connected with the bridge tower, and connected with the main cable through the suspension cable; a plurality of stay cables, a plurality of suspension cables and the main cable form a suspension cable assembly. Compared with the single-span bridge, the cable-stayed suspension cable coordination system of the bridge is not only longer in span, but also can effectively solve the problem of the current suspension bridge with large span but insufficient lateral stability.

Description

A kind of large span multitower cable-cabin structure bridge and its construction method
Technical field
The present invention relates to bridge, in particular to a kind of large span multitower cable-cabin structure bridge and its construction method.
Background technique
As economic fast development and social are constantly progressive, people are continuously increased the demand in traffic, more next More Longspan Bridges is built in gorge over strait or crosses on broad waters.Currently, cable-stayed bridge and multi-span suspension bridges are Long spans Two kinds of bridge types that bridge considers at first.There are maximum cantilever states when CONSTRUCTION OF CABLE-STAYED BRIDGE, if across footpath is excessive, girder root is in nearly tower Place can there is a phenomenon where lateral deflection unstabilitys;The main push-towing rope and girder steel using amount of suspension bridge are larger, and with multi-span suspension bridges across footpath Increase, including king-tower, main push-towing rope, the main members scale of construction such as anchorage and basis further increase, middle tower rigidity further increases, mistake High cost and complicated construction technology become the principal element of limitation multi-span suspension bridges development.
Summary of the invention
The purpose of the present invention is to provide a kind of good large span multitower cable-cabin structure bridge of stability and its construction method, It is solved the above problems with expectation.
To achieve the goals above, the present invention provides a kind of large span multitower cable-cabin structure bridges, including at least three Bridge tower connects the girder of bridge tower with both ends, is connected between bridge tower by suspension cable component, above-mentioned girder is followed successively by from middle part to both ends Middle section, changeover portion and head section, centrally located bridge tower upper end are provided with resistant slide saddle structure, and the main push-towing rope of above-mentioned bridge is Continual one is whole, which connects the upper end of above-mentioned at least three bridge towers by above-mentioned resistant slide saddle structure;
The bridge tower connection adjacent with the head section by multiple skew cables of above-mentioned head section;
Above-mentioned middle section connects the main push-towing rope by the more suspension cables suspended in midair on main push-towing rope;
Above-mentioned changeover portion is connect by suspension cable with bridge tower, is connect by suspension cable with main push-towing rope;
Above-mentioned multiple skew cables, more suspension cables and main push-towing rope form above-mentioned suspension cable component.
By using above-mentioned large span multitower cable-cabin structure bridge, the span ability of bridge, largest span can increase It can reach 1000 meters to 1500 meters.In the prior art, longer span ability is such as realized, it, can be using current when poising bridge type The maximum suspension bridge of across footpath, it is not only longer compared to single span span of bridge using the oblique pull suspension cable co-operative system of this bridge, moreover it is possible to Though effectively solving the problems, such as that current across footpath is big but the insufficient suspension bridge of lateral stability.
It is further that the length of above-mentioned interlude is the 3/10~2/5 of main beam length, based on the length of above-mentioned changeover portion The 1/10~3/20 of beam length.
It is further that the length of above-mentioned interlude is the 1/3 of main beam length, the length of above-mentioned changeover portion is main beam length 1/8.
It is further that above-mentioned girder is arranged with the auxiliary pier for being used to support the girder, so that this large span multitower is outstanding Cable system bridge stability is more preferable.
It is further that above-mentioned auxiliary pier is set to a kind of both ends of above-mentioned large span multitower cable-cabin structure bridge.
It is further, positioned at a kind of number of the above-mentioned auxiliary pier of any end of large span multitower cable-cabin structure bridge It is at least two.
It is further that on above-mentioned changeover portion, anchor point of the above-mentioned suspension cable on girder and above-mentioned suspension cable are in girder On anchor point be same anchorage point.
It is further to be respectively arranged with the anchorage positioned at bank positioned at the both ends of above-mentioned bridge, make anchorage so simultaneously It also serves as end bay bridge pier.
As another aspect of the present invention, the present invention also provides a kind of large span multitower cable-cabin structure bridge construction sides Method, for building above-mentioned large span multitower cable-cabin structure bridge, comprising the following steps:
Step 1: carrying out the construction of pile foundation and three bridge towers being arranged successively;
Step 2: symmetrical construction head section sets up suspension cable, and one skew cables of every erection are both needed to carry out cable force adjustment;
Step 3: setting up main push-towing rope;
Step 4: setting up changeover portion, set up suspension cable and suspension cable, while carrying out the adjustment of Suo Li;It is symmetrical to set up interlude, Set up suspension cable;
Step 5: completing appurtenant work and deck paving, reach bridge completion state.
By this construction method, more efficiently above-mentioned large span multitower cable-cabin structure bridge can be built.
It is further above-mentioned erection Construction of Transition Section method are as follows: head section has just connect paragraph by paragraph, and changeover portion and head section are cut with scissors paragraph by paragraph It connects, realizes that beam section has just connect by ballast after closure, then tensioning changeover portion suspension cable.
The present invention is described further with reference to the accompanying drawings and detailed description.The additional aspect of the present invention and excellent Point will be set forth in part in the description, and partially will become apparent from the description below.Or practice through the invention It solves.
Detailed description of the invention
The attached drawing for constituting a part of the invention is used to assist the understanding of the present invention, content provided in attached drawing and its Related explanation can be used for explaining the present invention in the present invention, but not constitute an undue limitation on the present invention.In the accompanying drawings:
Fig. 1 is the schematic diagram of a kind of large span multitower cable-cabin structure bridge and its construction method for illustrating embodiment;
Marked in the figure: 1- bridge tower, 2- girder, 2a- head section, 2b- changeover portion, the middle section 2c-, 3- main push-towing rope, 4- suspension cable, 5- are outstanding Rope, 6- auxiliary pier, 7- anchorage.
Specific embodiment
Clear, complete explanation is carried out to the present invention with reference to the accompanying drawing.Those of ordinary skill in the art are being based on these The present invention will be realized in the case where explanation.Before in conjunction with attached drawing, the present invention will be described, of particular note is that:
The technical solution provided in each section including following the description and technical characteristic in the present invention are not rushing In the case where prominent, these technical solutions and technical characteristic be can be combined with each other.
In addition, the embodiment of the present invention being related in following the description is generally only the embodiment of a branch of the invention, and The embodiment being not all of.Therefore, based on the embodiments of the present invention, those of ordinary skill in the art are not making creativeness Every other embodiment obtained, should fall within the scope of the present invention under the premise of labour.
About term in the present invention and unit.Term in description and claims of this specification and related part " comprising " and its any deformation, it is intended that cover and non-exclusive include.
Such as Fig. 1, a kind of large span multitower cable-cabin structure bridge connects the girder 2 of bridge tower 1 including three bridge towers 1 with both ends, Two are formed across structure, is connected between bridge tower 1 by suspension cable component, above-mentioned girder 2 is followed successively by middle section 2c, transition from middle part to both ends Section 2b and head section 2a, centrally located 1 upper end of bridge tower are provided with resistant slide saddle structure, and the main push-towing rope 3 of above-mentioned bridge is not Intermittent one is whole, which connects the upper end of above-mentioned three bridge towers 1 by above-mentioned resistant slide saddle structure;
Above-mentioned head section 2a is connected by the bridge tower 1 adjacent with head section 2a of multiple skew cables 4;
Above-mentioned middle section 2c connects the main push-towing rope 3 by the more suspension cables 5 suspended in midair on main push-towing rope 3;
Above-mentioned changeover portion 2b is connect by suspension cable 4 with bridge tower 1, is connect by suspension cable 5 with main push-towing rope 3;
Above-mentioned multiple skew cables 4, more suspension cables 5 and main push-towing rope 3 form above-mentioned suspension cable component.
By using above-mentioned large span multitower cable-cabin structure bridge, the span ability of bridge, largest span can increase It can reach 1000 meters to 1500 meters.In the prior art, longer span ability is such as realized, it, can be using current when poising bridge type The maximum suspension bridge of across footpath, using the not only longer compared to single span span of bridge of this bridge, moreover it is possible to effectively solve current across footpath Though the big but insufficient suspension bridge problem of lateral stability;By the way that the above-mentioned changeover portion 2b for being all connected with suspension cable 5, suspension cable 4 is arranged, have Effect improves the overall stability of bridge, this large span multitower cable-cabin structure bridge also significantly reduces 1 height of bridge tower, bridge tower 1 The part that cost accounting is most heavy in bed rearrangement bridge, this bridge type compared to same span suspension bridge, because introducing suspension cable 4, It can effectively reduce 1 height of bridge tower, reduce bridge cost.
The above-mentioned resistant slide saddle structure of the present invention is a kind of resistant slide structure of applicant's innovation and creation, including is equipped with and holds The cable saddle of cable slot, above-mentioned main push-towing rope 3 include top cable and bottom cable, are set to and hold in cable slot saddle, that is, hold in cable slot and have two Bar hawser (top cable, bottom cable form main push-towing rope 3), pushes up and is equipped at intervals with dumbbell shape friction plate structure, the top of friction plate between cable and bottom cable Face and the strand arragement construction of top cable are mutually agreed with, and the bottom surface of above-mentioned friction plate is mutually agreed with the strand arragement construction of bottom cable.Pass through Top cable and bottom cable guarantee the rigidity and equilibrant force of this large span multitower cable-cabin structure bridge, then pass through dumbbell shape friction on the basis of this Hardened structure increases rubbing surface, so that the frictional force between top cable, bottom cable and cable saddle greatly increases, is disposed at large span 1 upper end of bridge tower in multitower cable-cabin structure bridge middle position, improves the resistant slide safety of middle position bridge tower 1.
The length of above-mentioned interlude is the 3/10~2/5 of 2 length of girder, and the length of above-mentioned changeover portion 2b is 2 length of girder 1/10~3/20.For this bridge of large span, middle section 2c is more appropriate the 3/10~2/5 of 2 length of girder, accounts for Than too small, then head section 2a is too long, when construction during, the maximum cantilever end of head section 2a is too long, and difficulty of construction is excessive;Accounting mistake Greatly, then middle tower effect is excessively significant.
For this bridge of large span, 1/10~3/20 more appropriate, accounting mistake that changeover portion 2b accounts for 2 length of girder Small, entire bridge is not longitudinally rigid excessively gentle along bridge, if accounting is excessive, construction complexity increases.
Here the length for being preferably interlude is the 1/3 of 2 length of girder, and the length of changeover portion 2b is 2 length of girder 1/8, alternatively, the length of interlude is the 3/10 of 2 length of girder, the length of changeover portion 2b is the 1/10 of 2 length of girder, alternatively, The length of interlude is the 2/5 of 2 length of girder, and the length of changeover portion 2b is the 1/10 of 2 length of girder.
Above-mentioned girder 2 is arranged with the auxiliary pier 6 for being used to support the girder 2, and auxiliary pier 6 is set to a kind of above-mentioned large span The both ends of multitower cable-cabin structure bridge.So that this large span multitower cable-cabin structure bridge stability is more preferable.Positioned at a kind of large span The number of the above-mentioned auxiliary pier 6 of any end of multitower cable-cabin structure bridge two.It is dynamic in structure after end bay adds auxiliary pier 6 On mechanics, powerful effect of contraction has been played to the vibration of girder 2.When analyzing this large span multitower cable-cabin structure bridge force-bearing, Be contemplated that three kinds of different structural systems, i.e., longitudinal floating system, tower beam support system and tower beam consolidation system, to this greatly across Degree multitower cable-cabin structure bridge can obtain after doing structural dynamical model, and auxiliary pier 6 has lateral confinement effect to girder 2, and single order is horizontal Curved frequency is affected by auxiliary pier 6;Frequency perpendicular for single order and single order turn round frequency, when auxiliary pier 6 from scratch when, frequency values Amplification very little.After i.e. end bay adds auxiliary pier 6, the static(al) and dynamic property of cooperation this large span multitower cable-cabin structure bridge can be improved Energy.
On above-mentioned changeover portion 2b, above-mentioned suspension cable 4 is in the anchor point and anchor of the above-mentioned suspension cable 5 on girder 2 on girder 2 Solid point mutually staggers, and to improve the rigidity of this large span multitower cable-cabin structure bridge, while facilitating construction.
It is respectively arranged with the anchorage 7 positioned at bank positioned at the both ends of above-mentioned bridge, anchorage 7 is made to also serve as end bay in this way Bridge pier.
As another aspect of the present invention, the present invention also provides a kind of large span multitower cable-cabin structure bridge construction sides Method, for building above-mentioned large span multitower cable-cabin structure bridge, comprising the following steps:
Step 1: carrying out the construction of pile foundation and three bridge towers 1 being arranged successively;
Step 2: symmetrical construction head section 2a sets up suspension cable 4, and one skew cables 4 of every erection are both needed to carry out cable force adjustment;
Step 3: setting up main push-towing rope 3;
Step 4: setting up changeover portion 2b, set up suspension cable 4 and suspension cable 5, while carrying out the adjustment of Suo Li;Symmetrical erection is intermediate Section sets up suspension cable 5;
Step 5, appurtenant work and deck paving are completed, bridge completion state is reached.
By this construction method, more efficiently above-mentioned large span multitower cable-cabin structure bridge can be built.
Changeover portion suspension cable, suspension cable 5 installation initial internal force can influence each other, join the two sections of a bridge, etc position and closure measure equally exist Kinds of schemes, these factors can all cause the variation of structural internal force state in work progress, to influence the smooth installation of beam section. So using construction method below:
Changeover portion 2b is set up, sets up suspension cable 4 and suspension cable 5, while carrying out the adjustment of Suo Li;It is symmetrical to set up interlude, frame If 5 construction method of suspension cable are as follows: head section 2a has just connect paragraph by paragraph, and changeover portion 2b and head section 2a are hinged paragraph by paragraph, is realized after closure by ballast Beam section just connects, then tensioning changeover portion 2b suspension cable 4.When setting up girder 2, the internal force variation of girder 2 can maintain lesser Level, the articulated connection between beam section can effectively control 2 internal force of girder in work progress;And tensioning is needed for suspension cable 5, lead to The form for crossing the 5 gradation tensioning of suspension cable 4 and suspension cable, can equally improve the internal force status of girder 2 to a certain extent.
In addition, the 2 internal force variable quantity of girder of closure section is smaller, and the difference between different schemes is also smaller, join the two sections of a bridge, etc ballast and Ballast measure can guarantee that the smooth of beam section just connects before just connecing.
Just connect by head end, just connect after changeover portion 2b and the piecewise hinged, closure of middle section 2c by ballast realization beam section paragraph by paragraph, The arrangement and method for construction of tensioning changeover portion 2b suspension cable 4 again can effectively control the internal force status of structure in work progress, and the program Suspension cable 5 be not necessarily to tensioning, equipment can be saved on certain procedures, shortened the construction period.
Certainly, when selecting the mode of tensioning suspension cable 5 to carry out beam section erection, it can choose reasonable system transform in practice Scheme, to guarantee that suspension cable 4 and suspension cable 5 have enough Strength Safety deposits in work progress.
Related content of the invention is illustrated above.Those of ordinary skill in the art are in the feelings illustrated based on these The present invention will be realized under condition.Based on above content of the invention, those of ordinary skill in the art are not making creativeness Every other embodiment obtained, should fall within the scope of the present invention under the premise of labour.

Claims (10)

1. a kind of large span multitower cable-cabin structure bridge, connect the girder of bridge tower with both ends including at least three bridge towers, bridge tower it Between by suspension cable component be connected, the girder is followed successively by middle section, changeover portion and head section from middle part to both ends, which is characterized in that position The bridge tower upper end in middle position is provided with resistant slide saddle structure, the main push-towing rope of the bridge is continual one whole, master Cable connects the upper end of at least three bridge towers by the resistant slide saddle structure;
The head section bridge tower connection adjacent with the head section by multiple skew cables;
The middle section connects the main push-towing rope by the more suspension cables suspended in midair on main push-towing rope;
The changeover portion is connect by suspension cable with bridge tower, is connect by suspension cable with main push-towing rope;
The multiple skew cables, more suspension cables and main push-towing rope form the suspension cable component.
2. a kind of large span multitower cable-cabin structure bridge as described in claim 1, which is characterized in that the length of the interlude It is the 3/10~2/5 of main beam length, the length of the changeover portion is the 1/10~3/20 of main beam length.
3. a kind of large span multitower cable-cabin structure bridge as described in claim 1, which is characterized in that the length of the interlude It is the 1/3 of main beam length, the length of the changeover portion is the 1/8 of main beam length.
4. a kind of large span multitower cable-cabin structure bridge as described in claim 1, which is characterized in that the girder is arranged with It is used to support the auxiliary pier of the girder.
5. a kind of large span multitower cable-cabin structure bridge as claimed in claim 4, which is characterized in that the auxiliary pier is set to A kind of both ends of the large span multitower cable-cabin structure bridge.
6. a kind of large span multitower cable-cabin structure bridge as claimed in claim 5, which is characterized in that it is more to be located at a kind of large span The number of the auxiliary pier of any end of tower cable-cabin structure bridge is at least two.
7. a kind of large span multitower cable-cabin structure bridge as described in claim 1, which is characterized in that on the changeover portion, Anchor point of the suspension cable on girder is mutually staggered with anchor point of the suspension cable on girder.
8. a kind of large span multitower cable-cabin structure bridge as described in claim 1, which is characterized in that positioned at the two of the bridge End is respectively arranged with the anchorage positioned at bank.
9. a kind of large span multitower cable-cabin structure method for bridge construction, which is characterized in that for building such as claim 1~8 times A kind of large span multitower cable-cabin structure bridge described in meaning one, comprising the following steps:
Step 1: carrying out the construction of pile foundation and three bridge towers being arranged successively;
Step 2: symmetrical construction head section sets up suspension cable, and one skew cables of every erection are both needed to carry out cable force adjustment;
Step 3: setting up main push-towing rope;
Step 4: setting up changeover portion, set up suspension cable and suspension cable, while carrying out the adjustment of Suo Li;It is symmetrical to set up interlude, it sets up Suspension cable;
Step 5: completing appurtenant work and deck paving, reach bridge completion state.
10. large span multitower cable-cabin structure method for bridge construction as claimed in claim 9, which is characterized in that described to set up Cross section constructing method are as follows: after head section just connects paragraph by paragraph, changeover portion and head section are hinged paragraph by paragraph, realize that beam section is rigid by ballast after closure It connects, then tensioning changeover portion suspension cable.
CN201811352763.7A 2018-11-14 2018-11-14 A long-span multi-tower suspension cable system bridge and its construction method Pending CN109371805A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811352763.7A CN109371805A (en) 2018-11-14 2018-11-14 A long-span multi-tower suspension cable system bridge and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811352763.7A CN109371805A (en) 2018-11-14 2018-11-14 A long-span multi-tower suspension cable system bridge and its construction method

Publications (1)

Publication Number Publication Date
CN109371805A true CN109371805A (en) 2019-02-22

Family

ID=65388682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811352763.7A Pending CN109371805A (en) 2018-11-14 2018-11-14 A long-span multi-tower suspension cable system bridge and its construction method

Country Status (1)

Country Link
CN (1) CN109371805A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939067A (en) * 2019-12-09 2020-03-31 中铁大桥勘测设计院集团有限公司 Method for determining position of bridge closure section of collaboration system
CN112832144A (en) * 2021-01-08 2021-05-25 重庆交通大学工程设计研究院有限公司 Pedestrian suspension bridge reinforcing structure and construction process thereof
CN115094753A (en) * 2022-06-23 2022-09-23 中铁第四勘察设计院集团有限公司 A bridge laminated cable structure and suspension bridge
CN116641311A (en) * 2023-06-09 2023-08-25 中铁建大桥工程局集团第一工程有限公司 Cable saddle pushing-free construction method of cable-stayed suspension cooperative system bridge
CN118886080A (en) * 2024-06-19 2024-11-01 广西容梧高速公路有限公司 A multi-tower suspension bridge combined middle tower, design method and system

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4866803A (en) * 1988-10-24 1989-09-19 Nedelcu Lucian I Bridge structure with inclined towers
WO2005035876A1 (en) * 2003-10-14 2005-04-21 Aas-Jakobsen As Bridge structure comprising tower, bridge beam, main/suspension cable, suspending bars, and diagonal cable-stays
JP2007051426A (en) * 2005-08-15 2007-03-01 Public Works Research Institute Bridge and bridge construction method
CN101736685A (en) * 2009-11-27 2010-06-16 大连理工大学 Ground-anchored-self-anchored suspension combined system bridge
CN101736686A (en) * 2009-11-27 2010-06-16 大连理工大学 Self-anchored hybrid beam cable-stayed suspension cooperative system bridge
CN102713071A (en) * 2009-11-06 2012-10-03 东亚大学校产学协力团 Method for constructing a suspension bridge using temporary cables under tensionless stay cable conditions, and temporary cable for same
CN103850172A (en) * 2014-02-17 2014-06-11 中交公路规划设计院有限公司 Composite beam stayed cable-suspension cable cooperation bridge
CN105274941A (en) * 2015-10-29 2016-01-27 中交第二航务工程局有限公司 General construction method for partially ground-anchored cable-stayed suspension bridge
CN105404721A (en) * 2015-10-29 2016-03-16 中交第二航务工程局有限公司 Method for determining reasonable bridge forming state of cooperative bridge by considering rigidity distribution
CN105421236A (en) * 2015-10-29 2016-03-23 中交第二航务工程局有限公司 Closing method for cable-stayed and suspension composite bridge
CN107059637A (en) * 2017-05-16 2017-08-18 武汉工程大学 Long span self-anchoring type suspension bridge system conversion method
CN108103921A (en) * 2017-12-22 2018-06-01 招商局重庆交通科研设计院有限公司 Part earth anchor oblique pull-suspension cable co-operative system bridge
CN108252216A (en) * 2018-03-16 2018-07-06 西南交通大学 The mounting structure of strand in multi-span suspension bridges cable saddle
CN108660924A (en) * 2018-05-31 2018-10-16 西南交通大学 King-tower saddle structure in double cable multi-span suspension bridges
CN209508790U (en) * 2018-11-14 2019-10-18 西南交通大学 A kind of large span multitower cable-cabin structure bridge

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4866803A (en) * 1988-10-24 1989-09-19 Nedelcu Lucian I Bridge structure with inclined towers
WO2005035876A1 (en) * 2003-10-14 2005-04-21 Aas-Jakobsen As Bridge structure comprising tower, bridge beam, main/suspension cable, suspending bars, and diagonal cable-stays
JP2007051426A (en) * 2005-08-15 2007-03-01 Public Works Research Institute Bridge and bridge construction method
CN102713071A (en) * 2009-11-06 2012-10-03 东亚大学校产学协力团 Method for constructing a suspension bridge using temporary cables under tensionless stay cable conditions, and temporary cable for same
CN101736685A (en) * 2009-11-27 2010-06-16 大连理工大学 Ground-anchored-self-anchored suspension combined system bridge
CN101736686A (en) * 2009-11-27 2010-06-16 大连理工大学 Self-anchored hybrid beam cable-stayed suspension cooperative system bridge
CN103850172A (en) * 2014-02-17 2014-06-11 中交公路规划设计院有限公司 Composite beam stayed cable-suspension cable cooperation bridge
CN105274941A (en) * 2015-10-29 2016-01-27 中交第二航务工程局有限公司 General construction method for partially ground-anchored cable-stayed suspension bridge
CN105404721A (en) * 2015-10-29 2016-03-16 中交第二航务工程局有限公司 Method for determining reasonable bridge forming state of cooperative bridge by considering rigidity distribution
CN105421236A (en) * 2015-10-29 2016-03-23 中交第二航务工程局有限公司 Closing method for cable-stayed and suspension composite bridge
CN107059637A (en) * 2017-05-16 2017-08-18 武汉工程大学 Long span self-anchoring type suspension bridge system conversion method
CN108103921A (en) * 2017-12-22 2018-06-01 招商局重庆交通科研设计院有限公司 Part earth anchor oblique pull-suspension cable co-operative system bridge
CN108252216A (en) * 2018-03-16 2018-07-06 西南交通大学 The mounting structure of strand in multi-span suspension bridges cable saddle
CN108660924A (en) * 2018-05-31 2018-10-16 西南交通大学 King-tower saddle structure in double cable multi-span suspension bridges
CN209508790U (en) * 2018-11-14 2019-10-18 西南交通大学 A kind of large span multitower cable-cabin structure bridge

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
周云岗;肖汝诚;: "大跨径三塔缆索承重桥力学与经济性能", 同济大学学报(自然科学版) *
周云岗;黄晋琛;: "多塔斜拉-悬吊协作体系合理成桥状态确定方法", 石家庄铁道大学学报(自然科学版) *
张哲;朱巍志;王会利;: "自锚式斜拉-悬索协作体系桥的方案设计", 桥梁建设 *
程晓春;钟元;: "某斜拉-自锚悬索组合体系桥梁力学特性分析", 公路交通科技(应用技术版) *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939067A (en) * 2019-12-09 2020-03-31 中铁大桥勘测设计院集团有限公司 Method for determining position of bridge closure section of collaboration system
CN112832144A (en) * 2021-01-08 2021-05-25 重庆交通大学工程设计研究院有限公司 Pedestrian suspension bridge reinforcing structure and construction process thereof
CN112832144B (en) * 2021-01-08 2021-12-07 重庆交通大学工程设计研究院有限公司 Pedestrian suspension bridge reinforcing structure and construction process thereof
CN115094753A (en) * 2022-06-23 2022-09-23 中铁第四勘察设计院集团有限公司 A bridge laminated cable structure and suspension bridge
CN116641311A (en) * 2023-06-09 2023-08-25 中铁建大桥工程局集团第一工程有限公司 Cable saddle pushing-free construction method of cable-stayed suspension cooperative system bridge
CN116641311B (en) * 2023-06-09 2025-07-04 中铁建大桥工程局集团第一工程有限公司 A cable saddle non-pushing construction method for a cable-stayed suspension system bridge
CN118886080A (en) * 2024-06-19 2024-11-01 广西容梧高速公路有限公司 A multi-tower suspension bridge combined middle tower, design method and system
CN118886080B (en) * 2024-06-19 2025-04-04 广西容梧高速公路有限公司 A multi-tower suspension bridge combined middle tower, design method and system

Similar Documents

Publication Publication Date Title
CN109371805A (en) A long-span multi-tower suspension cable system bridge and its construction method
CN101353882B (en) A method for the structure of a continuous rigid frame bridge with oblique legs and its cantilever pouring construction method
CN103088750B (en) Especial-big span suspension bridge of uniparted hyperboloid space rope net main cable and construction method thereof
CN103821079B (en) A kind of combined box beam bridge spanning the sea and construction method thereof
CN104695341B (en) Non-self-balanced beam string structure for reinforcing large-span continuous beam bridge
CN106638259B (en) The superstructure and its assembling and construction method of prefabricated uncovered beam type combined steel plate beam bridge
CN101660291A (en) Pouring construction method for hollow continuous rigid frame bridge structure and inclined hanging basket
CN110965474A (en) Construction method of cable tower cross beam
CN109778667A (en) Arch structure for extra-large span steel-UHPC composite truss arch bridge and its construction method
CN107119583A (en) A kind of T-shaped rigid frame bridge back of the body tower oblique pull ruggedized construction of double width and its construction method
CN106012872A (en) Non-back cable cable-stayed reinforcement system and construction method of continuous rigid frame bridge
CN114837059A (en) A kind of rock anchor cable-stayed flexible arch cooperative system bridge in mountainous area and its construction method
CN106835955A (en) Steel K supports hollow concrete columnar pier
CN1120921C (en) First simply supporting and then continuously tensioning construction technology for post-crossing long-bundle prestressed rib
CN110184916A (en) Cable stayed Bridge Main Tower
CN203080398U (en) Pre-stressed concrete variable cross-section box girder bridge with internally-arranged slant legged rigid frame
CN205329550U (en) Suspension bridge catwalk system
CN209508790U (en) A kind of large span multitower cable-cabin structure bridge
CN206800227U (en) A kind of T-shaped rigid frame bridge back of the body tower oblique pull ruggedized construction
CN105648898A (en) Prefabricated ultra-high-performance concrete half-through beam units, bridge beam structure and construction method
CN205804149U (en) Bridge rigid pulling force is put
CN114197328A (en) Construction method of triangular area structure of beam-arch composite bridge
CN211689854U (en) Large-span steel truss combined continuous beam structure
CN103485271B (en) A prestressed cable truss bridge for pedestrians in mountainous rural areas
CN206800224U (en) A kind of T-shaped rigid frame bridge back of the body tower oblique pull ruggedized construction of double width

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190222