[go: up one dir, main page]

CN109235474A - Structure and its construction technology based on the super large cofferdam under marine environment - Google Patents

Structure and its construction technology based on the super large cofferdam under marine environment Download PDF

Info

Publication number
CN109235474A
CN109235474A CN201811290080.3A CN201811290080A CN109235474A CN 109235474 A CN109235474 A CN 109235474A CN 201811290080 A CN201811290080 A CN 201811290080A CN 109235474 A CN109235474 A CN 109235474A
Authority
CN
China
Prior art keywords
cofferdam
film bag
construction
laid
steel sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811290080.3A
Other languages
Chinese (zh)
Other versions
CN109235474B (en
Inventor
代敬辉
王朝辉
郭建文
张志安
李建芳
肖刚刚
梁素琴
尚颋
陈凯
李盼
张景华
叶忠厚
安然
王世君
郑伟强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201811290080.3A priority Critical patent/CN109235474B/en
Publication of CN109235474A publication Critical patent/CN109235474A/en
Application granted granted Critical
Publication of CN109235474B publication Critical patent/CN109235474B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses one kind based on super large cofferdam construction technology under marine environment, which is characterized in that cofferdam uses sand washing film bag, trapezoidal cross-section structure.Weir crest width about 15m, according to highly carrying out classification slope, upstream face gradient 1:3-1:4, back side gradient 1:4, and one of steel plate pile water stopping curtain of setting is pushed up in cofferdam, one of steel plate pile water stopping curtain is arranged in back side slope foot.The technique combined using sand washing film bag+steel sheet pile, it is fast that advantage includes speed of application, can shorten the construction period;Stability, durability are good, can prevent from washing away, and resist flood;Increase steel plate pile water stopping curtain, more rigid, barrier properties are more preferable, can play good water proof effect;Cofferdam demolition is convenient simultaneously, speed is fast;Steel sheet pile can be used in turn, and reduce construction cost.Reference frame can be provided for similar engineerings such as tunnel near water, harbour cofferdam, crossing bridges the present invention is based on super large cofferdam construction technology under marine environment and experience instructs.

Description

Structure and its construction technology based on the super large cofferdam under marine environment
Technical field
The present invention relates to a kind of cofferdam construction technologies, more particularly to one kind is based on super large cofferdam construction work under marine environment Skill.
Background technique
Currently, the tunnel under marine environment generally uses shield method, shallow burial hidden digging, immersed tunnelling method, cut and cover tunneling.Wherein Cut and cover method cofferdam can be enclosed again using earth rock cofferdam, earth-bag cofferdam, steel sheet-pile cofferdam, reinforced concrete sheeting cofferdam, steel jacket box Weir etc..
The construction periods such as shield method, shallow burial hidden digging, immersed tunnelling method are long, and working face is small;It cannot be segmented, construct simultaneously.Open cut Tunnel earth rock cofferdam, earth-bag cofferdam, waterproof, infiltration effect are poor.Open trench tunnel steel sheet-pile cofferdam, self-stability is poor, need to add steel branch Support, water-stagnating effect are good;Open trench tunnel reinforced concrete sheeting cofferdam, later period removal cost are higher.Wherein, film sack cofferdam method is The filling sand in film bag makes sand in film bag become a fixed entirety, then filled film bag overlap joint adds up and shape At weir body.Construction can gather materials on the spot in this way, construction is simple;Several construction paragraphs can be divided into while being constructed.
Geology locating for tunnel under marine environment is very soft sill clay, medium coarse sand in 1-17 meters generally under sea bed Layer, silty clay are distributed completely decomposed, strong weathered granite layer down, and geological structure is more complex;Locating construction environment typhoon is frequent, Because flood damage easily occurs for typhoon, and cofferdam is also a place vulnerable to typhoon;The depth of water is very deep in construction area, and water Lower environment is extremely complex, is difficult to control.The weir body volume needed to form according to problem above is big, good seepage-proof property.
Summary of the invention
For above-mentioned existing construction technology, geology, hydrologic condition according to locating for tunnel under marine environment, construction environment and work Phase requires, and the present invention provides a kind of based on super large cofferdam construction technology under marine environment.Cofferdam uses sand washing film bag+steel sheet pile phase In conjunction with construction technology, the advantages of both drawing, disadvantage, the advantages of the two, is combined, secured, reliable weir body is formed.This Sample construction is simple, is available locally;Speed of application is fast, can shorten the construction period, ease off the pressure for follow-up work;It is stability, durable Property it is good, can preferably prevent from washing away, flood-protection, resist typhoon;Add steel plate pile water stopping curtain, more rigid, barrier properties More preferably, extraordinary water proof effect can be reached;Cofferdam demolition is convenient, speed is fast;Steel sheet pile can be used in turn, and reduce fund Pressure.
In order to solve the above-mentioned technical problem, the present invention is based on the structures in the super large cofferdam under marine environment, including stacking Sand washing film bag and steel sheet pile, the section in cofferdam be it is trapezoidal, the weir crest width in the cofferdam is 15m, the height in the cofferdam is 9~ 10m, the cofferdam are classified slope in height, and the upstream face gradient is 1:3~1:4, and the back side gradient is 1:4;The cofferdam Weir bottom is equipped with TGXG, equal at the symmetrical position of width and at the slope foot of the cofferdam back side in the cofferdam One of steel plate pile water stopping curtain is set, and the steel plate pile water stopping curtain is made of Lashen IV type steel sheet pile, is stopped in the steel sheet pile Circumferentially every the pre-buried Grouting Pipe of 1m on water curtain, the outer diameter of the Grouting Pipe is 30mm, internal diameter 26mm, the Grouting Pipe Bottom end be conical pipe;In the sand washing film bag of stacking, seam between layers is constructed using the fissure of displacement, fissure of displacement spacing >=2m;It encloses The overlap joint faulting of slab ends and seam crossing of weir back side sand washing film bag are successively equipped with screed-coat, geotextile layer and bed course, the screed-coat Be metalling with bed course, the geotextiles be 400g/m geotextiles, the bed course with a thickness of 200~400mm;It meets in cofferdam Be successively arranged anti-seepage geomembrane, blotter and concrete facing on the water surface, the blotter with a thickness of 200mm, it is described Concrete facing with a thickness of 130mm.
For the cofferdam construction technology of above structure, comprising the following steps:
Step 1: obtaining cofferdam film bag installation site, and surveying and locating using RTK-GPS;According to the position of surveying and locating It is dredged using rake suction and weir location Dredging Construction is carried out to the pre-installed position of cofferdam film bag;Then the paving of weir bottom TGXG is carried out If;
Step 2: film bag fills sand, including the positioning of film bag and laying:
The positioning of film bag fixes the positioning of film bag with positioning row or steel pipe pitching pile surrounding and combines construction, seam between layers It is constructed using the fissure of displacement, fissure of displacement spacing >=2m;
Water surface area above carries out the laying of film bag using manual method according to the position of initial survey setting-out;
Profundal zone carries out the laying of film bag using Working Ships;
Phytal zone hand packing film bag: when low tide or cofferdam construction are 0.0m~1.0m to elevation, the cofferdam depth of water can Satisfaction is lauched when requiring, and sediment transport pipe is inserted directly into the film bag laid for sand using row's pump and directly charges paving bag;
Step 3: antiseepage geotechnique is laid with:
After film bag weir body is fills up to designed elevation, on the outside of cofferdam and upstream face is laid with anti-seepage geotextile, anti-seepage geotextile Heavy weight diving lash ship, which is laid with, by completes, and since entire paving process operates under water, uses fair current or inverse as far as possible when paving It flows direction to carry out, the distance of 2~3 meters of every movement, which is thrown, in paving process throws a rubble or bagged sand packet for the antiseepage to pave geotechnique Cloth is pushed down, to prevent from floating;
Step 4: the construction of steel plate pile water stopping curtain:
Steel sheet pile therein uses Lashen IV type steel sheet pile, after film bag weir body is fills up to designed elevation, carries out steel sheet pile and applies Work, device therefor include Z550 type hydraulic vibration pile-sinking machine and piling machine, and the exciting force of the piling machine is 220kN;
Method is individually squeezed into the construction use of steel plate pile water stopping curtain, i.e., first starting point steel of injection since the centre in cofferdam Then sheet pile respectively circumferentially starts to beat by root cutting up to forming steel plate pile water stopping curtain to the two sides of starting point steel sheet pile toward cofferdam, Every steel sheet pile gets to end midway from and does not stop;Circumferentially every the pre-buried note of 1m on the steel plate pile water stopping curtain Slurry pipe, the outer diameter of the Grouting Pipe are 30mm, and internal diameter 26mm, the bottom end of the Grouting Pipe is conical pipe;
Step 5: the mask and Hu Ding in cofferdam:
On the back side in cofferdam, first with rubble between film bag and film bag overlap joint faulting of slab ends and seam carry out levelling place Then reason is laid with one layer of 400g/m geotextiles, the blotter with a thickness of 200~400mm is finally laid in the geotextiles;
On the upstream face in cofferdam, the blotter with a thickness of 200mm is laid on anti-seepage geomembrane, then in the rubble It is poured on bed course with a thickness of 130mm geomembrane enveloped concrete mask;
It is laid with packed clay at the top in cofferdam, then re-lays the rubble mask of 200mm thickness.
Further, in cofferdam construction technology of the present invention, in step 1, the laying of weir bottom TGXG using artificial and Machinery, which is laid with, combines form construction, wherein offshore section is manually laid with, and profundal zone is laid with using mechanical.
In step 2, profundal zone carries out the laying of film bag using Working Ships, and rake is inhaled shipping sand and directly filled;Work progress It is that first film bag is mounted on Working Ships, Working Ships paving frame slowly stretches out film bag, when stretching by rake suction ship for sand tube and film The cuff of bag connects, and cuff is handled using slip-knot, when sandpipe is extracted into cuff is tied in fact naturally through slip-knot, is avoided husky in filling Sand is gone to outside film bag in the process;Fill husky sequence since cofferdam section on one side fill, when being charged to design thickness, gradually to Another side filling, complete film bag of finally filling.
In step 2, the process of phytal zone hand packing film bag is: when low tide or cofferdam construction to elevation are 0.0m ~1.0m, the cofferdam depth of water meet personnel and are lauched when requiring, and using row's pump for husky artificial paving bag filling, row's pump includes what floating mat loaded Diesel engine unit and mortar pump are manually worn after life jacket is lauched, sediment transport pipe are inserted directly into the film bag laid, is then directly charged Sand.
In step 3, geotextiles carry out sewing splicing in land, by it on geotextile laying drum, drum A length of 30 meters;Then, the drum for being wound with geotextiles has been fixed on the cantilever crane of heavy weight diving lash ship.
In step 3, using RTK-GPS positioning system carry out move ship it is in place, anti-seepage geotextile rise initial line using pressure fills out The method of rubble packet is fixed, or is fixed using the method for insertion steel-pipe pile.
In step 4, to guarantee pile sinking axial location and vertical degree, the leading truck guidance of certain rigidity must be set, that is, beaten Before entering steel sheet pile, weir crest is manually flattened, then, a leading truck is installed on weir crest, is squeezed into during steel sheet pile, using guiding Frame guidance.
To ensure that weir body is stablized, when geomembrane enveloped concrete slope protection construction, is considered as the influence of inside and outside head difference, therefore, steel sheet pile After construction, before the mask and shield top for carrying out step 5 cofferdam, cofferdam internal drainage is carried out, back side slope protection is then carried out Processing, then carries out upstream face slope protection processing again, finally carries out weir crest mask.
Compared with prior art, the beneficial effects of the present invention are:
Previous tunnel is long using construction periods such as shield method, shallow burial hidden digging, immersed tunnelling methods, and working face is small;It cannot be segmented, together When construct.Open trench tunnel earth rock cofferdam, earth-bag cofferdam, waterproof, infiltration effect are poor.Open trench tunnel steel sheet-pile cofferdam, self-stability is poor, Bracing members need to be added;Open trench tunnel reinforced concrete sheeting cofferdam, later period removal cost are higher.
Structure the present invention is based on the super large cofferdam under marine environment is using sand washing film bag, trapezoidal cross-section structure.Weir crest Width about 15m, according to cofferdam stepped height slope, upstream face gradient 1:3-1:4, back side gradient 1:4.One of setting in cofferdam One of steel plate pile water stopping curtain is arranged in steel plate pile water stopping curtain, cofferdam back side slope foot.Cofferdam uses sand washing film bag+steel sheet pile phase In conjunction with construction technology, one of steel plate pile water stopping curtain is respectively arranged in weir crest and cofferdam back side slope foot, by sand washing film bag+steel sheet pile The advantages of combine, form secured, reliable weir body.Such construction is simple, is available locally;Speed of application is fast, can shorten Duration eases off the pressure for follow-up work;Cofferdam overall stability, durability are good, can preferably prevent from washing away, flood-protection, Resist typhoon;Steel plate pile water stopping curtain is added, more rigid, barrier properties are more preferable, can reach extraordinary water proof effect, reach Related job specfication requirement;Later period cofferdam demolition is convenient simultaneously, speed is fast;Steel sheet pile can be used in turn, and reduce financial pressure. The present invention is worth recommending to use to similar engineerings such as seabed tunnel engineering, large-scale dam engineering, natural flow station engineerings.
Detailed description of the invention
Fig. 1 is that the present invention is based on super large cofferdam construction technology flow charts under marine environment;
Fig. 2 is that the present invention is based on super large cofferdam structure cross-section diagrams under marine environment;
Fig. 3 is that the present invention is based on back side super large cofferdam structure structural maps under marine environment;
Fig. 4 is that the present invention is based on upstream face super large cofferdam structure structural maps under marine environment;
Fig. 5 is that the present invention is based on super large cofferdam structure geologic maps under marine environment.
In figure: IV steel sheet pile of 1-YASP-, 2- TGXG, 3- geotextiles, two layers of antiseepage composite geo-membrane of 4-, 5-200mm Thick blotter, 6-130mm thick film bag concrete mask, 7-400g/m2Geotextiles, 8- rubble is levelling, 9- filling bagged sand, and 10- bags Dress clay, the cofferdam 11- axis, 12- upstream face, 13- back side, 14- gravelly sand, 15- Muddy Bottoms silty clay, 16- silty clay, 17- chiltern cohesive soil, 18- strong weathered granite, weathered granite in 19-, 20- geological exploration hole.
Specific embodiment:
Detailed content of the invention is told about by the following examples, and providing embodiment is the convenience for understanding, definitely not The limitation present invention.
Research material:
This research material is related to Tunnel Engineering under a marine environment, and (segment length 0.8 over strait is public for 1.2 kilometers of tunnel overall length In).Using two-lane class II highway standard, 40 kilometers/hour of desin speed, two-way two lane, lane width 2*3.75m.Vehicle Road limit height 5.0m.Horizontal Clearance is each side 0.5m, remaining width 0.25m.Northern bank open section (K0+180-K0+330) knot Configuration formula is U-type groove structure, and northern bank open section total length is 150m.Secretly burying section (K0+330-K1+190) is rectangular configuration, is secretly buried Section total length is 860m, and southern bank open section (K1+190-K1+360) structure type is U-type groove structure, total length 170m.Channel Clear span: open section 10.75m secretly buries a section 15.55m;Asphalt concrete pavement channel uses cofferdam cut and cover tunneling.According to prospecting ground Matter Fig. 5 exploration 20 data of hole shows that about 1.5-5 meters of tunnel place's depth of water over strait is gravelly sand 14, Muddy Bottoms powder in 1-17 meters under riverbed Matter clay 15, chiltern cohesive soil 17, is distributed strong weathered granite 18 at silty clay 16 down;Middle weathered granite 19, ground texture It makes more complex.
Using the sand washing film bag of stacking, cofferdam is trapezoidal cross-section structure in cofferdam.Cofferdam weir body construction be divided into again eastern weir body and Western weir body two parts.Cofferdam is swum apart from channel central axes about 200m, is connected with two sides bunding, upstream cofferdam is about 550m, downstream Cofferdam is about 500m.Most deep 5m of the depth of water or so, north side 0~2m of the depth of water, cofferdam height are 4~9.5m, weir bottom maximum width 161.11m, weir crest width about 15m, weir body section size are big;If execution conditions need, with the increasing of the ocean depth of water, cofferdam height Greatly, it can continue to increase weir bottom width degree, weir body section area be increased, to increase overall stability, the reliability in cofferdam.According to enclosing Weir stepped height slope, upstream face gradient 1:3-1:4, back side gradient 1:4.The weir bottom in the cofferdam is equipped with TGXG, It is located at the symmetrical position of width in the cofferdam and is respectively provided with one of steel sheet pile sealing at the slope foot of the cofferdam back side Curtain, one of steel plate pile water stopping curtain is arranged in cofferdam, and cofferdam back side slope foot is arranged one of steel plate pile water stopping curtain, increases Weir body rigidity keeps cofferdam more stable, reliable;In conjunction with twice steel plate pile water stopping curtain, weir body impermeability is greatly increased, is better able to The immersion and infiltration for resisting ocean water, prevent from washing away, flood-protection.The steel plate pile water stopping curtain is by Lashen IV type steel sheet pile structure At circumferentially every the pre-buried Grouting Pipe of 1m on the steel plate pile water stopping curtain, the outer diameter of the Grouting Pipe is 30mm, interior Diameter 26mm, the bottom end of the Grouting Pipe are conical pipe.In the sand washing film bag of stacking, seam between layers is applied using the fissure of displacement Work, fissure of displacement spacing >=2m;The overlap joint faulting of slab ends and seam crossing of cofferdam back side sand washing film bag are successively equipped with screed-coat, geotextile layer And bed course, the screed-coat and bed course are metalling, the geotextiles be 400g/m geotextiles, the bed course with a thickness of 200~400mm;Anti-seepage geomembrane, blotter and concrete facing are successively arranged on the upstream face of cofferdam, the blotter With a thickness of 200mm, the concrete facing with a thickness of 130mm.The overlap joint faulting of slab ends and seam crossing of cofferdam back side sand washing film bag It is successively equipped with screed-coat, geotextile layer and bed course, the screed-coat and bed course are metalling, and the geotextiles are 400g/m Geotextiles, the bed course with a thickness of 200~400mm;Be successively arranged on the upstream face of cofferdam anti-seepage geomembrane, blotter and Concrete facing, the blotter with a thickness of 200mm, the concrete facing with a thickness of 130mm.
The quantity of cofferdam construction includes coffering construction, depth is widened in auxiliary river and upstream is blocked water closure dam and built If.About 60 ten thousand stere of cofferdam construction project amount, about 250 ten thousand stere of waterway dredging project amount above swim across water closure dam hydraulic reclamation work About 30 ten thousand stere of journey amount.
Open trench tunnel excavation of foundation pit requires excavation slope stability height, deformation of sedimentation small;And the duration is tight, it is desirable that construction speed Degree is fast, so being directed to the above critical factor analysis.
In order to solve open trench tunnel excavation of foundation pit, slope stability is high, deformation of sedimentation is small;And the fast problem of speed of application, For the above-mentioned construction technology based on super large cofferdam under marine environment, steps are as follows:
Step 1: cofferdam surveying and locating and the dredging of weir location:
Cofferdam film bag installation site is obtained using RTK-GPS, cofferdam film bag installation site is measured, and measures and puts Sample;Ensure that underwater film bag position is accurate, the pre-installation dredged using rake suction to cofferdam film bag according to the position of surveying and locating Position carries out weir location Dredging Construction;Then, by drag suction dredger, the cofferdam film bag position of surveying and locating is reached, carries out weir location Dredging Construction.Under normal circumstances, dredging on one side navigate by water while;Then the laying of weir bottom TGXG, weir bottom shown in Fig. 2 are carried out It carries out TGXG 2 or geotextiles 3 is laid with, form is combined using artificial and mechanical laying and is constructed.Offshore section is manually It is laid with, profundal zone is laid with using mechanical.
Step 2: film bag fills sand, including the positioning of film bag and laying:
The positioning of film bag fixes the positioning of film bag with positioning row or steel pipe pitching pile surrounding and combines construction, seam between layers It is constructed using the fissure of displacement, fissure of displacement spacing >=2m;Water surface area above according to the position of initial survey setting-out, using manual method into The laying of row film bag.
Profundal zone shown in Fig. 2 arranges ship film bag and fills sand loading 9, and profundal zone carries out the laying of film bag using Working Ships, and rake inhales ship Fortune is husky directly to be filled.Film bag is first mounted on Working Ships by work progress, and Working Ships paving frame slowly stretches out film bag, Bian Shenbian Rake is inhaled into connecting for sand tube and cuff for ship.Cuff is handled using slip-knot, and bundle is carried out after sandpipe extraction in fact, avoids filling Sand is gone to outside film bag during sand.Fill husky sequence since cofferdam section on one side fill, when being charged to design thickness, gradually It is filled to another side, complete film bag of finally filling, and reaches code requirement.
The phytal zone Fig. 2 artificial membrane bag fills sand loading 9: when low tide or cofferdam construction to certain elevation (0.0m~1.0m), The cofferdam depth of water, which can satisfy, to be lauched when requiring, using row's pump for husky artificial paving bag filling.Row pump by floating mat load diesel engine unit and Mortar pump, manually wear life jacket and be lauched, sediment transport pipe is inserted directly into the sand pocket laid directly charge paving bag charge.Floating mat can show Field is rolled, and can also rent local canoe as buoying device.
Step 3: anti-seepage geomembrane, that is, geotextile laying:
After film bag weir body is fills up to designed elevation, as shown in figure 4, on the outside of cofferdam and upstream face be laid with anti-seepage geotextile be Geotextile laying, anti-seepage geotextile heavy weight diving lash ship by, which is laid with, to be completed, and is carried out, is paved using fair current or countercurrent direction when paving The distance of 2~3 meters of every movement throws rubble of throwing in the process or bagged sand packet pushes down the anti-seepage geotextile to pave, on preventing It is floating.Anti-seepage geotextile 4 divides land laying and underwater laying.Underwater portion be easy to cause soil due to being influenced by water flow and the depth of water Phenomena such as work cloth is by floating, folding, even washed away displacement.In order to meet the requirement of construction, it is ensured that process of deployment it is effective Safety is drawn previous experiences, is laid with using reliable method.
Anti-seepage geotextile 4 is subjected to sewing splicing in land first, then by it on geotextile laying drum, A length of 30 meters of drum.Side seam side is wound under normal circumstances, while both sides are manually straightened to prevent work cloth in winding process Bending fold.
(1) load onto ship: the drum that shipment is mainly wound with geotextiles, which is hung on the cantilever crane of earthwork cloth laying ship, fixes it.
(2) be laid with positioning: being laid with positioning is the critical process in entire process of deployment, it is directly related to laying quality Quality.It is in place that this engineering uses RTK-GPS positioning system to carry out shifting ship, and location data is inputted computer, according to computer screen The hull position of real-time display on curtain, move that ship is in place, carries out the laying positioning operation of native antiseepage work cloth 4.
(3) anti-seepage geotextile 4 plays the fixation of initial line: in the side played initial line and pressure is used to fill out rubble packet that anti-seepage geotextile is laid with Method carries out compacting fixation, and the method construction of insertion steel-pipe pile stationary positioned can be used when necessary.
(4) Fig. 4 anti-seepage geotextile 4 is laid with: after hull is accurately positioned, being played initial line in geotextile laying and is fixed, open Dynamic windlass slowly moves ship and is laid with according to the position location of Survey Software display screen.It rectifies a deviation in time when displacement wanders off.By It is operated under water in entire paving process, fair current or countercurrent direction is used to carry out as far as possible when paving.Simultaneously in paving process In 2~3 meters or so of every movement of distance must throw and throw rubble or bagged sand packet pushes down the geotextiles to pave, prevent it from It is floating.
Step 4: the construction of steel plate pile water stopping curtain:
Before squeezing into steel sheet pile, to guarantee pile sinking axial location and vertical degree, the leading truck that certain rigidity must be arranged draws It leads, leading truck can be used channel steel and be made.Before leading truck is installed, weir crest is manually flattened, is placed into so that leading truck is smooth Weir crest.It squeezes into during steel sheet pile, is guided using leading truck.
Steel sheet pile as shown in Figure 2 uses import Lashen IV type steel sheet pile 1.Film bag weir body back-up sand 9 is to designed elevation Afterwards, steel sheet pile construction is carried out.Steel sheet pile construction uses Z550 type hydraulic vibration pile-sinking machine, makees the major impetus of steel sheet pile pile sinking. Piling machine is that excavator liquid feeding presses high-frequency vibratory hammer to convert, and exciting force reaches 220kN.
Steel sheet pile construction is using individually method is squeezed into, to make the sheet pile after setting have enough rigidity and good sealing to make With.The method is to start first starting point steel sheet pile of injection since the intermediate of cofferdam, then respectively past cofferdam front-rear direction start by Root cutting is beaten, and every steel sheet pile gets to end midway from and do not stop.
Since monolithic is squeezed into, easily banking, cumulative errors are not easy to correct, and metope straightness is difficult to control, steel sheet pile It should be noted the following during squeezing into.
(1) it requires steel sheet pile to be close to leading truck when driving piles, and checks the axis of leading truck at any time.
(2) piling machine slings steel sheet pile, and artificial righting is in place.
(3) single pile notices that height of pile top should not differ too big by the continuous injection of root.
(4) measurement monitors the gradient of every pile at any time during inserting piling, when gradient be more than 2% cannot be with pulling together method tune Timing is pulled up and is beaten again.
There is infiltration phenomenon for prevention, steel sheet pile is every the pre-buried slip casting iron pipe of 1m, outer tube diameter 30mm, internal diameter 26mm, Bottom sharpening aperture, i.e., the bottom end of the described Grouting Pipe are conical pipe;It, can be from Grouting Pipe toward steel sheet pile bottom if there is cofferdam infiltration Carry out grouting for water plugging.
Step 5: the mask and Hu Ding in cofferdam:
To ensure that weir body is stablized, when geomembrane enveloped concrete slope protection construction, is considered as the influence of inside and outside head difference, therefore steel sheet pile After construction, cofferdam internal drainage is carried out first, is then carried out the processing of back side slope protection, is then carried out at upstream face slope protection again Reason finally carries out weir crest mask.
With cofferdam axis 11, it is divided into Fig. 3 back side and Fig. 4 upstream face, two sides cofferdam mask way is different.
(1) on the back side in cofferdam, back side as shown in Figure 3 is wrong to the overlap joint between film bag and film bag with rubble first Platform and seam carry out levelling 8 processing of rubble, are then laid with one layer of 400g/m geotextiles 7, be finally laid in geotextiles with a thickness of 200 blotter 5.
(2) on the upstream face in cofferdam, upstream face as shown in Figure 4 is laid on anti-seepage geomembrane 4 with a thickness of 200mm's Then blotter 5 is poured on blotter with a thickness of 130mm geomembrane enveloped concrete mask 6.
(3) as shown in figure 4, cofferdam shield top carries out packed clay 10, it is then laid with the rubble mask of 200mm thickness above.
Using construction method of the present invention formed cofferdam stabilization each judge index such as: rate of settling vs≤10.0mm/ D, deep layer lateral displacement rate vm≤5.0mm/d, surface horizontal displacement rate vf≤5.0mm/d are all satisfied related code requirement, And weir body does not occur percolating water phenomenon during tunnel excavation and main structure construction, has withstood multiple typhoon test, it can That has hated prevents from washing away.It can be seabed tunnel engineering, large-scale dam the present invention is based on super large cofferdam construction technology under marine environment The similar engineerings such as engineering, natural flow station engineering are improved can refer to and be instructed according to experience.
In terms of in view of tunnel main body Pit Excavation Methods, local environment, construction period and quality safety, using punching The construction technology that sand film bag+steel sheet pile combines.Previous tunnel is using construction periods such as shield method, shallow burial hidden digging, immersed tunnelling methods Long, working face is small;It cannot be segmented, construct simultaneously.Open trench tunnel earth rock cofferdam, earth-bag cofferdam, waterproof, infiltration effect are poor.Open cut Tunnel steel sheet pile cofferdam, self-stability is poor, need to add bracing members;Open trench tunnel reinforced concrete sheeting cofferdam, later period removal cost It is higher.And using the present invention is based on the construction technologies in super large cofferdam under marine environment.Combined using sand washing film bag+steel sheet pile Construction technology, using filling sand film bag, trapezoidal cross-section structure, one of steel sheet pile is respectively arranged in weir crest and cofferdam back side slope foot in cofferdam Water-stop curtain.The advantage and disadvantage for drawing both film sack cofferdam and steel sheet pile, the advantages of the two, is combined, and is formed securely, reliably Weir body.Such construction is simple, is available locally;Speed of application is fast, can shorten the construction period, ease off the pressure for follow-up work;Stablize Property, durability it is good, can preferably prevent from washing away, flood-protection, resist typhoon;Steel plate pile water stopping curtain is added, it is more rigid, Barrier properties are more preferable, can reach extraordinary water proof effect;Cofferdam demolition is convenient, speed is fast;Steel sheet pile can be used in turn, and be subtracted Few financial pressure.
Although invention has been described above, but the invention is not limited in above-mentioned embodiment, on The specific embodiment stated is only schematical, rather than restrictive, and those skilled in the art are of the invention Under enlightenment, without deviating from the spirit of the invention, many variations can also be made, these belong to protection of the invention it It is interior.

Claims (9)

1. a kind of structure based on the super large cofferdam under marine environment, sand washing film bag and steel sheet pile including stacking, cofferdam are broken Face is trapezoidal, it is characterised in that:
The weir crest width in the cofferdam is 15m, and the height in the cofferdam is 4~9.5m, and the cofferdam is classified slope in height, The upstream face gradient is 1:3~1:4, and the back side gradient is 1:4;
The weir bottom in the cofferdam is equipped with TGXG, is located at the symmetrical position of width in the cofferdam and the cofferdam is carried on the back One of steel plate pile water stopping curtain is respectively provided at the slope foot of the water surface, the steel plate pile water stopping curtain is made of Lashen IV type steel sheet pile, Circumferentially every the pre-buried Grouting Pipe of 1m on the steel plate pile water stopping curtain, the outer diameter of the Grouting Pipe is 30mm, internal diameter 26mm, the bottom end of the Grouting Pipe are conical pipe;
In the sand washing film bag of stacking, seam between layers is constructed using the fissure of displacement, fissure of displacement spacing >=2m;
The overlap joint faulting of slab ends and seam crossing of cofferdam back side sand washing film bag are successively equipped with screed-coat, geotextile layer and bed course, described Screed-coat and bed course are metalling, the geotextiles be 400g/m geotextiles, the bed course with a thickness of 200~400mm;
Be successively arranged anti-seepage geomembrane, blotter and concrete facing on the upstream face of cofferdam, the blotter with a thickness of 200mm, the concrete facing with a thickness of 130mm.
2. a kind of construction technology based on the super large cofferdam under marine environment, which is characterized in that the structure in cofferdam such as claim 1 The structure based on the super large cofferdam under marine environment, the construction technology in the cofferdam the following steps are included:
Step 1: obtaining cofferdam film bag installation site, and surveying and locating using RTK-GPS;It is utilized according to the position of surveying and locating Rake suction, which is dredged, carries out weir location Dredging Construction to the pre-installed position of cofferdam film bag;Then the laying of weir bottom TGXG is carried out;
Step 2: film bag fills sand, including the positioning of film bag and laying:
The positioning of film bag fixes the positioning of film bag with positioning row or steel pipe pitching pile surrounding and combines construction, and seam between layers uses Fissure of displacement construction, fissure of displacement spacing >=2m;
Water surface area above carries out the laying of film bag using manual method according to the position of initial survey setting-out;
Profundal zone carries out the laying of film bag using Working Ships;
Phytal zone hand packing film bag: when low tide or cofferdam construction are 0.0m~1.0m to elevation, the cofferdam depth of water be can satisfy It is lauched when requiring, sediment transport pipe is inserted directly into for sand using row's pump by the film bag laid and directly charges paving bag;
Step 3: antiseepage geotechnique is laid with:
After film bag weir body is fills up to designed elevation, on the outside of cofferdam and upstream face is laid with anti-seepage geotextile, and anti-seepage geotextile is by Heavy weight diving lash ship, which is laid with, to be completed, and is carried out when paving using fair current or countercurrent direction, the distance of 2~3 meters of every movement in paving process It throws rubble of throwing or bagged sand packet pushes down the anti-seepage geotextile to pave, to prevent from floating;
Step 4: the construction of steel plate pile water stopping curtain:
Steel sheet pile therein uses Lashen IV type steel sheet pile, after film bag weir body is fills up to designed elevation, carries out steel sheet pile construction, institute It include Z550 type hydraulic vibration pile-sinking machine and piling machine with equipment, the exciting force of the piling machine is 220kN;
Method is individually squeezed into the construction use of steel plate pile water stopping curtain, i.e., first starting point steel plate of injection since the centre in cofferdam Then stake respectively circumferentially starts to be beaten by root cutting until forming steel plate pile water stopping curtain, often toward cofferdam to the two sides of starting point steel sheet pile Root steel sheet pile gets to end midway from and does not stop;Circumferentially every the pre-buried slip casting of 1m on the steel plate pile water stopping curtain Pipe, the outer diameter of the Grouting Pipe are 30mm, and internal diameter 26mm, the bottom end of the Grouting Pipe is conical pipe;
Step 5: the mask and Hu Ding in cofferdam:
On the back side in cofferdam, first with rubble between film bag and film bag overlap joint faulting of slab ends and seam carry out leveling, so It is laid with one layer of 400g/m geotextiles afterwards, the blotter with a thickness of 200~400mm is finally laid in the geotextiles;
On the upstream face in cofferdam, the blotter with a thickness of 200mm is laid on anti-seepage geomembrane, then in the blotter On pour with a thickness of 130mm geomembrane enveloped concrete mask;
It is laid with packed clay at the top in cofferdam, then re-lays the rubble mask of 200mm thickness.
3. the construction technology according to claim 2 based on the super large cofferdam under marine environment, which is characterized in that in step 1 In, the laying of weir bottom TGXG combines form construction using artificial and mechanical be laid with, wherein and offshore section is manually laid with, Profundal zone is laid with using mechanical.
4. the construction technique according to claim 2 based on the super large cofferdam under marine environment, which is characterized in that in step In rapid two, profundal zone carries out the laying of film bag using Working Ships, and rake is inhaled shipping sand and directly filled;Work progress is, first by film bag It is mounted on Working Ships, Working Ships paving frame slowly stretches out film bag, and rake is inhaled connecting for the cuff of sand tube and film bag for ship when stretching It connects, cuff is handled using slip-knot, when sandpipe is extracted into cuff is tied in fact naturally through slip-knot, avoids sand during filling husky It goes to outside film bag;Fill husky sequence since cofferdam section on one side fill, when being charged to design thickness, gradually filled to another side It fills out, complete film bag of finally filling.
5. the construction technology according to claim 2 based on the super large cofferdam under marine environment, which is characterized in that in step 2 In, the process of phytal zone hand packing film bag is: when low tide or cofferdam construction are 0.0m~1.0m to elevation, the cofferdam depth of water is full Sufficient personnel are lauched when requiring, and using row's pump for husky artificial paving bag filling, row's pump includes the diesel engine unit that floating mat loads and mortar pump, It manually wears after life jacket is lauched, sediment transport pipe is inserted directly into the film bag laid, then directly charges sand.
6. the construction technology according to claim 2 based on the super large cofferdam under marine environment, which is characterized in that in step 3 In, geotextiles carry out sewing splicing in land, by it on geotextile laying drum, a length of 30 meters of drum;Then, will The drum for being wound with geotextiles has been fixed on the cantilever crane of heavy weight diving lash ship.
7. the construction technology in the super large cofferdam under Yu Haiyang environment according to claim 2, which is characterized in that in step 3 In, using RTK-GPS positioning system carry out move ship it is in place, anti-seepage geotextile rise initial line using pressure fill out rubble packet method carry out It is fixed, or be fixed using the method for insertion steel-pipe pile.
8. the construction technology according to claim 2 based on the super large cofferdam under marine environment, which is characterized in that in step 4 In, it squeezes into before steel sheet pile, manually flattens weir crest, then, a leading truck is installed on weir crest, is squeezed into during steel sheet pile, is adopted It is guided with leading truck.
9. the construction technology according to claim 2 based on the super large cofferdam under marine environment, which is characterized in that carry out step Before five, cofferdam internal drainage is carried out.
CN201811290080.3A 2018-10-31 2018-10-31 Structure of super-large cofferdam based on marine environment and construction process thereof Active CN109235474B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811290080.3A CN109235474B (en) 2018-10-31 2018-10-31 Structure of super-large cofferdam based on marine environment and construction process thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811290080.3A CN109235474B (en) 2018-10-31 2018-10-31 Structure of super-large cofferdam based on marine environment and construction process thereof

Publications (2)

Publication Number Publication Date
CN109235474A true CN109235474A (en) 2019-01-18
CN109235474B CN109235474B (en) 2020-10-09

Family

ID=65080059

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811290080.3A Active CN109235474B (en) 2018-10-31 2018-10-31 Structure of super-large cofferdam based on marine environment and construction process thereof

Country Status (1)

Country Link
CN (1) CN109235474B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139847A (en) * 2020-01-17 2020-05-12 上海公路桥梁(集团)有限公司 Water stopping structure of shoal reclamation area and water stopping method using water stopping structure
CN113957913A (en) * 2020-07-20 2022-01-21 广西建工集团海河水利建设有限责任公司 Construction method of film bag sand filling combined steel sheet pile cofferdam
CN115467351A (en) * 2022-08-27 2022-12-13 乐昌市恒源水电建筑工程有限公司 Construction method of film bag sand filling combined steel sheet pile cofferdam

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014015809A (en) * 2012-07-11 2014-01-30 Okumura Corp Cut-off of water for joint part of steel sheet pile, and outflow prevention hardware
CN104727332A (en) * 2015-03-19 2015-06-24 中交二航局第三工程有限公司 Steel sheet pile cofferdam bottom rock-socketed anchoring method
CN106759104A (en) * 2016-12-29 2017-05-31 浙江大学城市学院 Ecological slope protection structure and construction method
CN107012878A (en) * 2017-05-19 2017-08-04 中国水利水电第四工程局有限公司 A kind of cofferdam construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014015809A (en) * 2012-07-11 2014-01-30 Okumura Corp Cut-off of water for joint part of steel sheet pile, and outflow prevention hardware
CN104727332A (en) * 2015-03-19 2015-06-24 中交二航局第三工程有限公司 Steel sheet pile cofferdam bottom rock-socketed anchoring method
CN106759104A (en) * 2016-12-29 2017-05-31 浙江大学城市学院 Ecological slope protection structure and construction method
CN107012878A (en) * 2017-05-19 2017-08-04 中国水利水电第四工程局有限公司 A kind of cofferdam construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111139847A (en) * 2020-01-17 2020-05-12 上海公路桥梁(集团)有限公司 Water stopping structure of shoal reclamation area and water stopping method using water stopping structure
CN113957913A (en) * 2020-07-20 2022-01-21 广西建工集团海河水利建设有限责任公司 Construction method of film bag sand filling combined steel sheet pile cofferdam
CN115467351A (en) * 2022-08-27 2022-12-13 乐昌市恒源水电建筑工程有限公司 Construction method of film bag sand filling combined steel sheet pile cofferdam
CN115467351B (en) * 2022-08-27 2024-09-06 乐昌市恒源水电建筑工程有限公司 Construction method of film bag sand filling combined steel sheet pile cofferdam

Also Published As

Publication number Publication date
CN109235474B (en) 2020-10-09

Similar Documents

Publication Publication Date Title
CN106640091B (en) A kind of shallow tunnel section construction method
CN109780325A (en) A kind of water factory's water intaking tunnel submarine pipeline installation method
CN106801424A (en) A kind of cofferdam construction method
CN102605697A (en) Sand dredger filling construction method of soft soil foundation embankment
CN203684242U (en) Mud flat area geotechnical bag mud composite cofferdam type underwater construction platform
CN109235474A (en) Structure and its construction technology based on the super large cofferdam under marine environment
CN112681350A (en) River cofferdam diversion construction method
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN112663558B (en) Construction process for excavating weathered rock in inland river harbor pool
CN110273429A (en) A kind of piling bar plate and film bag sand cofferdam construction method
CN104612128B (en) Vacuum preloading reinforcement construction method applicable to underwater silt environment
CN1773022A (en) Fast soft foundation dyke building method and technology
CN100516367C (en) Geotechnical soil-ballasted sack cofferdam for water piers of river-crossing bridge and its production method
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section
CN111335263B (en) Method for building artificial island
CN85202494U (en) Interlocked reinforced concrete sheet pile
CN201080616Y (en) River spanning bridge underwater pier earthwork mud-filling bag cofferdam
CN112253848B (en) Sand geology water network swamp area pipeline construction method
CN108978645A (en) Rich water sandy gravel shallow embedding riverbed uplift pile anti-floating plate reinforced construction method is worn under shield
Degen et al. Offshore Stone Columns-Equipment, Quality Control and Outlook for Future Applications
CN1069371C (en) Construction method for confferdam and dyke-dam
CN108487273A (en) A kind of foundation in water construction method
YEE Geotextile tube applications for construction of the longest sea-crossing bridge in Vietnam
CN119041460A (en) Land Gao Jiangyan foundation construction method under complex geological environment
Tian et al. Design and Construction of the Interlocking Steel Pipe Pile Cofferdam for the Main Pier of the Shuidu Second Bridge located in Danjiangkou City

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant