CN109162719A - A kind of brick projecting construction of working shaft method - Google Patents
A kind of brick projecting construction of working shaft method Download PDFInfo
- Publication number
- CN109162719A CN109162719A CN201810843141.8A CN201810843141A CN109162719A CN 109162719 A CN109162719 A CN 109162719A CN 201810843141 A CN201810843141 A CN 201810843141A CN 109162719 A CN109162719 A CN 109162719A
- Authority
- CN
- China
- Prior art keywords
- active well
- sheath
- pipeline
- working shaft
- shaft method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 47
- 239000011449 brick Substances 0.000 title claims abstract description 37
- 238000000034 method Methods 0.000 title claims abstract description 35
- 230000008878 coupling Effects 0.000 claims description 9
- 238000010168 coupling process Methods 0.000 claims description 9
- 238000005859 coupling reaction Methods 0.000 claims description 9
- 238000009412 basement excavation Methods 0.000 claims description 6
- 239000002184 metal Substances 0.000 claims description 3
- 238000010586 diagram Methods 0.000 description 5
- 239000004567 concrete Substances 0.000 description 4
- 230000008859 change Effects 0.000 description 3
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 230000007547 defect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 239000011241 protective layer Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D1/00—Sinking shafts
- E21D1/08—Sinking shafts while moving the lining downwards
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D5/00—Lining shafts; Linings therefor
- E21D5/04—Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D7/00—Shaft equipment, e.g. timbering within the shaft
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The present invention provides a kind of brick projecting construction of working shaft method, comprising: a, verifies underground utilities position;B, masonry of symmetrically cutting the earth along active well marginal position active well excavates the earthwork in middle position after the active well of a section digging depth puzzles, then excavates next section active well marginal position;C, when driving arrives underground utilities position, whole pipelines is dug out, whole pipelines is banded together;D, sheath is arranged outside the pipeline banded together, the sheath includes that section is semicircular first pipe valve and the second pipe valve;E, sheath is connected and fixed with the active well puzzled;F, continue step b until completing whole active wells.Pipeline and active well are connected and fixed by sheath, to protect pipeline, prevent pipeline from damaging because of construction to pipeline; or because backfill when to pipeline caused by squeeze, in the case where not destroying existing pipeline, the moving costs of pipeline can be saved; the influence to ambient enviroment is reduced, is shortened the construction period.
Description
Technical field
The present invention relates to building engineering field, especially a kind of brick projecting construction of working shaft method.
Background technique
Subway construction speed was accelerated in recent years, construction puts more effort, with fully under way, each subway bid section of subway construction
Generally existing the phenomenon that changing shifting influence construction progress due to pipeline.In boring construction, especially in tunneling Construction of Silo process
In such as encounter pipeline and influence Shaft Location, can select to avoid pipeline construction by changing Shaft Location under normal circumstances, once
When scene does not have the condition of Shaft Location adjustment, need to wait for constructing after pipeline changes shifting.It thus causes to wait early period and march into the arena,
The problems such as duration in later period pressure is excessive, to directly influence site operation safe mass.
Notification number is a kind of special-shaped vertical shaft of subway work under the conditions of pipeline of CN203499692U, it is characterised in that:
For vertical shaft from lower point of three kinds of excavated sections on, three kinds of excavated sections are respectively as follows: upper half shrink sector: section width 8
~9m, 0.5~1m below depth to pipeline bottom;Middle part gradual change section: section width is to be equal to upper half shrink sector above,
It is equal to standard section below, and is by upper half shrink sector gradual change to standard section, depth is 2~3m;Standard section: section
Width is 10.6~12.1m, deep 7.5~11.6m.
If prior art presence is encountered when can not avoid pipeline and being constructed, the defect of pipeline safety not can guarantee,
What is connect causes claim for eot, increased costs.
Summary of the invention
In order to overcome the above problem, the present invention provides a kind of moving costs that can save pipeline, reduces to ambient enviroment
The brick projecting construction of working shaft method influence, shortened the construction period.
In order to achieve the above-mentioned advantages, the present invention provides brick projecting construction of working shaft method, comprising:
A, underground utilities position is verified;
B, it symmetrically cuts the earth along active well marginal position and builds active well, after the active well of a section digging depth puzzles, dig
Except the earthwork in middle position, then excavate next section active well marginal position;
C, when driving arrives underground utilities position, whole pipelines is dug out, whole pipelines is banded together;
D, it is arranged sheath outside the pipeline banded together, the sheath includes that section is semicircular first pipe valve and the
Two pipe valves;
E, sheath is connected and fixed with the active well puzzled;
F, continue symmetrically to cut the earth along active well marginal position to build active well, when the active well of a section digging depth puzzles
Afterwards, excavate the earthwork in middle position, then excavate next section active well marginal position, until completing whole active wells.
In one embodiment of brick projecting construction of working shaft method of the invention, the first pipe valve and second pipe
Valve, which has, is used for bolted screw hole.
In one embodiment of brick projecting construction of working shaft method of the invention, the sheath further includes and the work
The fixed link that the well borehole wall is fixedly connected, the fixed link is for fixing the sheath.
In one embodiment of brick projecting construction of working shaft method of the invention, the sheath is by multiple sheath tube coupling groups
At sheath tube coupling is fixed with another sheath tube coupling by flanged joint.
In one embodiment of brick projecting construction of working shaft method of the invention, the step b further includes masonry, described
Active well marginal position is built by masonry.
In one embodiment of brick projecting construction of working shaft method of the invention, the masonry is 370 brick walls.
In one embodiment of brick projecting construction of working shaft method of the invention, the pipeline is tied up by band.
In one embodiment of brick projecting construction of working shaft method of the invention, the sheath is made of metal.
In one embodiment of brick projecting construction of working shaft method of the invention, after the active well intensity reaches 70%
Lower section excavation is carried out again.
In one embodiment of brick projecting construction of working shaft method of the invention, each excavation width≤1200mm, depth
Degree≤1000mm.
In the present invention, pipeline and active well are connected and fixed by sheath, to protect pipeline, prevent pipeline because applying
Work damages pipeline, or because backfill when to pipeline caused by squeeze, in the case where not destroying existing pipeline, pipe can be saved
The moving costs of line reduces the influence to ambient enviroment, shortens the construction period.
Detailed description of the invention
Fig. 1 show the structural schematic diagram of the special-shaped vertical shaft of subway work under the conditions of pipeline of the prior art.
Fig. 2 show the structural schematic diagram of the brick projecting construction of working shaft method of first embodiment of the invention.
Fig. 3 show the flow diagram of the brick projecting construction of working shaft method of Fig. 2.
Fig. 4 show the top view of the brick projecting construction of working shaft method of Fig. 2.
Fig. 5 show the structural schematic diagram of the sheath of the brick projecting construction of working shaft method of Fig. 2.
Fig. 6 show the top view of the brick projecting construction of working shaft method of Fig. 2.
Fig. 7 show the structural schematic diagram of the brick projecting construction of working shaft method of second embodiment of the invention.
Specific embodiment
It is of the invention to reach the technical means and efficacy that predetermined goal of the invention is taken further to illustrate, below in conjunction with
Attached drawing and preferred embodiment, to specific embodiment, structure, feature and its effect is proposed according to the present invention, detailed description is as follows.
Refer to Fig. 2, the brick projecting construction of working shaft method of one kind of first embodiment of the invention, comprising:
A, underground utilities position is verified;
Fig. 3 is referred to, b, symmetrically cutting the earth along 1 marginal position of active well builds active well 1, when the work of a section digging depth
After well 1 puzzles, the earthwork in middle position being excavated, then excavating next 1 marginal position of section active well, 1 intensity of active well reaches
Lower section excavation, each excavation width≤1200mm, depth≤1000mm, until in planned well below the absolute altitude of bottom are carried out after 70% again
Until 300mm.
C, when driving arrives underground utilities position, whole pipelines is dug out, whole pipelines is banded together, pipeline passes through
Band is tied up.
Fig. 4, Fig. 5 are referred to, d, is arranged sheath 2 outside the pipeline banded together, the sheath 2 includes that section is semicircle
The the first pipe valve 21 and the second pipe valve 22 of shape, the first pipe valve 21 and the second pipe valve 22, which have, is used for bolted spiral shell
Hole 23.Sheath 2 further includes the fixed link 24 being fixedly connected with 1 borehole wall of active well, and fixed link 24 is for fixing the sheath 2.
E, sheath 2 is connected and fixed with the active well 1 puzzled;
Fig. 6 is referred to, f, continuing symmetrically to cut the earth along 1 marginal position of active well builds active well 1, when a section digging depth
After active well 1 puzzles, the earthwork in middle position is excavated, then excavate next 1 marginal position of section active well, until completing whole works
Make well 1.4 thickness of bottom plate is 200mm, concrete C25, and after active well 1 to set absolute altitude, concrete is arranged further according to pipeline rout
Under the premise of meeting the push pipe working space brick film 11 is arranged in position of back size as needed, in stock mould in rear backrest
C25 concrete is poured between 11 and well bore, as push pipe backrest.
Sheath 2 is made of multiple sheath tube coupling 2a, and sheath tube coupling 2a is connect with another sheath tube coupling 2a by flange 25 solid
It is fixed.The sheath 2 is made of metal.
The step b further includes masonry, and 1 marginal position of active well is built by masonry.The masonry is 370 bricks
Wall.
When constructing to active well 1, being exposed to outer pipeline, there are security risks, and weight falls meeting to pipeline
It damages, therefore the sheath 2 being sheathed on outside pipeline ensure that construction safety.It, can be to pipeline when being backfilled to active well 1
Inward pressure is generated, if backfill unevenly can also be such that pipeline deforms, therefore the sheath 2 being sheathed on outside pipeline avoids pipeline
Using safe.
Refer to Fig. 7, in the second embodiment of brick projecting construction of working shaft method of the invention, according to soil property situation and
Cutting depth, 2 meters to divide into reinforced concrete circle beam 3 one, collar tie beam 3 using 400mm X400mm reinforced concrete structure,
Main reinforcement uses 14mm, and stirrup uses 8@200mm of φ, protective layer 30mm, concrete strength C20.Bottom plate thickness is 200mm, is mixed
Solidifying soil is C25.
Pipeline and active well 1 are connected and fixed by the present invention by sheath 2, to protect pipeline, prevent pipeline because of construction
Pipeline is damaged, or because backfill when to pipeline caused by squeeze, in the case where not destroying existing pipeline, pipeline can be saved
Moving costs, reduce influence to ambient enviroment, shorten the construction period.
More than, it is only presently preferred embodiments of the present invention, is not intended to limit the present invention in any form, although this
Invention has been disclosed in a preferred embodiment above, and however, it is not intended to limit the invention, any person skilled in the art,
It does not depart within the scope of technical solution of the present invention, when the technology contents using the disclosure above make a little change or are modified to equivalent
The equivalent embodiment of variation, but without departing from the technical solutions of the present invention, according to the technical essence of the invention to the above reality
Any simple modification, equivalent variations and modification made by example are applied, all of which are still within the scope of the technical scheme of the invention.
Claims (10)
1. a kind of brick projecting construction of working shaft method characterized by comprising
A, underground utilities position is verified;
B, it symmetrically cuts the earth along active well marginal position and builds active well, when the active well of a section digging depth puzzles after, excavate
Between position the earthwork, then excavate next section active well marginal position;
C, when driving arrives underground utilities position, whole pipelines is dug out, whole pipelines is banded together;
D, sheath is arranged outside the pipeline banded together, the sheath includes that section is semicircular first pipe valve and the second pipe
Valve;
E, sheath is connected and fixed with the active well puzzled;
F, continue symmetrically to cut the earth along active well marginal position to build active well, after the active well of a section digging depth puzzles, dig
Except the earthwork in middle position, then next section active well marginal position is excavated, until completing whole active wells.
2. brick projecting construction of working shaft method according to claim 1, which is characterized in that the first pipe valve and described
Second pipe valve, which has, is used for bolted screw hole.
3. brick projecting construction of working shaft method according to claim 1, which is characterized in that the sheath further includes and institute
The fixed link that the active well borehole wall is fixedly connected is stated, the fixed link is for fixing the sheath.
4. brick projecting construction of working shaft method according to claim 1, which is characterized in that the sheath is by multiple sheaths
Tube coupling composition, sheath tube coupling are fixed with another sheath tube coupling by flanged joint.
5. brick projecting construction of working shaft method according to claim 1, which is characterized in that the step b further includes building
Body, the active well marginal position are built by masonry.
6. brick projecting construction of working shaft method according to claim 5, which is characterized in that the masonry is 370 brick walls.
7. brick projecting construction of working shaft method according to claim 1, which is characterized in that the pipeline is tied by band
It pricks.
8. brick projecting construction of working shaft method according to claim 1, which is characterized in that the sheath is by made of metal
At.
9. brick projecting construction of working shaft method according to claim 1, which is characterized in that the active well intensity reaches
Lower section excavation is carried out after 70% again.
10. brick projecting construction of working shaft method according to claim 9, which is characterized in that each excavation width≤
1200mm, depth≤1000mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810843141.8A CN109162719A (en) | 2018-07-27 | 2018-07-27 | A kind of brick projecting construction of working shaft method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810843141.8A CN109162719A (en) | 2018-07-27 | 2018-07-27 | A kind of brick projecting construction of working shaft method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109162719A true CN109162719A (en) | 2019-01-08 |
Family
ID=64898452
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810843141.8A Pending CN109162719A (en) | 2018-07-27 | 2018-07-27 | A kind of brick projecting construction of working shaft method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109162719A (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0007413A1 (en) * | 1978-07-28 | 1980-02-06 | Hüls Troisdorf Aktiengesellschaft | Process for sealing of walls from water pressure or infiltration |
CN102587391A (en) * | 2011-01-10 | 2012-07-18 | 孙冬梁 | Construction process for large-aperture brick and concrete reverse hanging well |
CN106150506A (en) * | 2016-07-08 | 2016-11-23 | 中铁十六局集团地铁工程有限公司 | A kind of gateway open excavation section inverted side-wall construction method |
CN107090851A (en) * | 2017-04-24 | 2017-08-25 | 北京城建道桥建设集团有限公司 | The inverted side-wall construction method of downtown area open cut groove |
-
2018
- 2018-07-27 CN CN201810843141.8A patent/CN109162719A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0007413A1 (en) * | 1978-07-28 | 1980-02-06 | Hüls Troisdorf Aktiengesellschaft | Process for sealing of walls from water pressure or infiltration |
CN102587391A (en) * | 2011-01-10 | 2012-07-18 | 孙冬梁 | Construction process for large-aperture brick and concrete reverse hanging well |
CN106150506A (en) * | 2016-07-08 | 2016-11-23 | 中铁十六局集团地铁工程有限公司 | A kind of gateway open excavation section inverted side-wall construction method |
CN107090851A (en) * | 2017-04-24 | 2017-08-25 | 北京城建道桥建设集团有限公司 | The inverted side-wall construction method of downtown area open cut groove |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107542108B (en) | A kind of reverse construction method of building basement structure | |
Hu et al. | Artificial ground freezing in tunnelling through aquifer soil layers: A case study in Nanjing Metro Line 2 | |
Henn | Practical guide to grouting of underground structures | |
CN105041333A (en) | Method for treating tunnel collapse through dugand covered method | |
Sun et al. | Technologies for large cross-section subsea tunnel construction using drilling and blasting method | |
CN108005660A (en) | A kind of Optimization of Expressway Tunnel Construction method | |
CN108412503A (en) | Bias shallow-buried tunnel portal construction protection structure and construction method thereof | |
KR101536209B1 (en) | Steel Pipe Multi Step Grouting device Open and cut and NATM complex excavation tunnel construction method | |
CN110284885A (en) | Shield inspection-pit construction method | |
CN105041327B (en) | Bored tunnel is counter to dig shield method of reseptance | |
CN110905536A (en) | Construction method for receiving complex stratum earth pressure shield in underground excavation tunnel | |
CN110259490A (en) | A kind of Underground Subway Station construction method | |
Tan et al. | Catastrophic failure of Shanghai metro line 4 in July 2003: Postaccident rehabilitation | |
CN110439011B (en) | Side slope anti-slip supporting structure and construction method thereof | |
CN105909262A (en) | Subsurface tunnel driving method | |
CN108166532A (en) | A kind of groutable underground continuous wall connector and its construction method | |
CN110344394A (en) | A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method | |
CN205618170U (en) | Protective structure of no template punishment rock mass cavity in tunnel engineering | |
Parashar et al. | Performance monitoring of deep shafts at Changi WRP project, Singapore | |
CN103527205A (en) | Shield underwater oblique crossing hole entering construction method | |
CN109162719A (en) | A kind of brick projecting construction of working shaft method | |
CN105840203A (en) | Large section loess tunnel pre-cutting method construction method | |
CN217518646U (en) | A Wrecker Tunnel Structure Underpassing an Existing Station | |
Yesilnacar | Grouting applications in the Sanliurfa tunnels of GAP, Turkey | |
JP2942874B2 (en) | How to join tunnels |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190108 |