CN109162719A - A kind of brick projecting construction of working shaft method - Google Patents

A kind of brick projecting construction of working shaft method Download PDF

Info

Publication number
CN109162719A
CN109162719A CN201810843141.8A CN201810843141A CN109162719A CN 109162719 A CN109162719 A CN 109162719A CN 201810843141 A CN201810843141 A CN 201810843141A CN 109162719 A CN109162719 A CN 109162719A
Authority
CN
China
Prior art keywords
active well
sheath
pipeline
working shaft
shaft method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810843141.8A
Other languages
Chinese (zh)
Inventor
杨君琦
毛凤森
房阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201810843141.8A priority Critical patent/CN109162719A/en
Publication of CN109162719A publication Critical patent/CN109162719A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/08Sinking shafts while moving the lining downwards
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention provides a kind of brick projecting construction of working shaft method, comprising: a, verifies underground utilities position;B, masonry of symmetrically cutting the earth along active well marginal position active well excavates the earthwork in middle position after the active well of a section digging depth puzzles, then excavates next section active well marginal position;C, when driving arrives underground utilities position, whole pipelines is dug out, whole pipelines is banded together;D, sheath is arranged outside the pipeline banded together, the sheath includes that section is semicircular first pipe valve and the second pipe valve;E, sheath is connected and fixed with the active well puzzled;F, continue step b until completing whole active wells.Pipeline and active well are connected and fixed by sheath, to protect pipeline, prevent pipeline from damaging because of construction to pipeline; or because backfill when to pipeline caused by squeeze, in the case where not destroying existing pipeline, the moving costs of pipeline can be saved; the influence to ambient enviroment is reduced, is shortened the construction period.

Description

A kind of brick projecting construction of working shaft method
Technical field
The present invention relates to building engineering field, especially a kind of brick projecting construction of working shaft method.
Background technique
Subway construction speed was accelerated in recent years, construction puts more effort, with fully under way, each subway bid section of subway construction Generally existing the phenomenon that changing shifting influence construction progress due to pipeline.In boring construction, especially in tunneling Construction of Silo process In such as encounter pipeline and influence Shaft Location, can select to avoid pipeline construction by changing Shaft Location under normal circumstances, once When scene does not have the condition of Shaft Location adjustment, need to wait for constructing after pipeline changes shifting.It thus causes to wait early period and march into the arena, The problems such as duration in later period pressure is excessive, to directly influence site operation safe mass.
Notification number is a kind of special-shaped vertical shaft of subway work under the conditions of pipeline of CN203499692U, it is characterised in that: For vertical shaft from lower point of three kinds of excavated sections on, three kinds of excavated sections are respectively as follows: upper half shrink sector: section width 8 ~9m, 0.5~1m below depth to pipeline bottom;Middle part gradual change section: section width is to be equal to upper half shrink sector above, It is equal to standard section below, and is by upper half shrink sector gradual change to standard section, depth is 2~3m;Standard section: section Width is 10.6~12.1m, deep 7.5~11.6m.
If prior art presence is encountered when can not avoid pipeline and being constructed, the defect of pipeline safety not can guarantee, What is connect causes claim for eot, increased costs.
Summary of the invention
In order to overcome the above problem, the present invention provides a kind of moving costs that can save pipeline, reduces to ambient enviroment The brick projecting construction of working shaft method influence, shortened the construction period.
In order to achieve the above-mentioned advantages, the present invention provides brick projecting construction of working shaft method, comprising:
A, underground utilities position is verified;
B, it symmetrically cuts the earth along active well marginal position and builds active well, after the active well of a section digging depth puzzles, dig Except the earthwork in middle position, then excavate next section active well marginal position;
C, when driving arrives underground utilities position, whole pipelines is dug out, whole pipelines is banded together;
D, it is arranged sheath outside the pipeline banded together, the sheath includes that section is semicircular first pipe valve and the Two pipe valves;
E, sheath is connected and fixed with the active well puzzled;
F, continue symmetrically to cut the earth along active well marginal position to build active well, when the active well of a section digging depth puzzles Afterwards, excavate the earthwork in middle position, then excavate next section active well marginal position, until completing whole active wells.
In one embodiment of brick projecting construction of working shaft method of the invention, the first pipe valve and second pipe Valve, which has, is used for bolted screw hole.
In one embodiment of brick projecting construction of working shaft method of the invention, the sheath further includes and the work The fixed link that the well borehole wall is fixedly connected, the fixed link is for fixing the sheath.
In one embodiment of brick projecting construction of working shaft method of the invention, the sheath is by multiple sheath tube coupling groups At sheath tube coupling is fixed with another sheath tube coupling by flanged joint.
In one embodiment of brick projecting construction of working shaft method of the invention, the step b further includes masonry, described Active well marginal position is built by masonry.
In one embodiment of brick projecting construction of working shaft method of the invention, the masonry is 370 brick walls.
In one embodiment of brick projecting construction of working shaft method of the invention, the pipeline is tied up by band.
In one embodiment of brick projecting construction of working shaft method of the invention, the sheath is made of metal.
In one embodiment of brick projecting construction of working shaft method of the invention, after the active well intensity reaches 70% Lower section excavation is carried out again.
In one embodiment of brick projecting construction of working shaft method of the invention, each excavation width≤1200mm, depth Degree≤1000mm.
In the present invention, pipeline and active well are connected and fixed by sheath, to protect pipeline, prevent pipeline because applying Work damages pipeline, or because backfill when to pipeline caused by squeeze, in the case where not destroying existing pipeline, pipe can be saved The moving costs of line reduces the influence to ambient enviroment, shortens the construction period.
Detailed description of the invention
Fig. 1 show the structural schematic diagram of the special-shaped vertical shaft of subway work under the conditions of pipeline of the prior art.
Fig. 2 show the structural schematic diagram of the brick projecting construction of working shaft method of first embodiment of the invention.
Fig. 3 show the flow diagram of the brick projecting construction of working shaft method of Fig. 2.
Fig. 4 show the top view of the brick projecting construction of working shaft method of Fig. 2.
Fig. 5 show the structural schematic diagram of the sheath of the brick projecting construction of working shaft method of Fig. 2.
Fig. 6 show the top view of the brick projecting construction of working shaft method of Fig. 2.
Fig. 7 show the structural schematic diagram of the brick projecting construction of working shaft method of second embodiment of the invention.
Specific embodiment
It is of the invention to reach the technical means and efficacy that predetermined goal of the invention is taken further to illustrate, below in conjunction with Attached drawing and preferred embodiment, to specific embodiment, structure, feature and its effect is proposed according to the present invention, detailed description is as follows.
Refer to Fig. 2, the brick projecting construction of working shaft method of one kind of first embodiment of the invention, comprising:
A, underground utilities position is verified;
Fig. 3 is referred to, b, symmetrically cutting the earth along 1 marginal position of active well builds active well 1, when the work of a section digging depth After well 1 puzzles, the earthwork in middle position being excavated, then excavating next 1 marginal position of section active well, 1 intensity of active well reaches Lower section excavation, each excavation width≤1200mm, depth≤1000mm, until in planned well below the absolute altitude of bottom are carried out after 70% again Until 300mm.
C, when driving arrives underground utilities position, whole pipelines is dug out, whole pipelines is banded together, pipeline passes through Band is tied up.
Fig. 4, Fig. 5 are referred to, d, is arranged sheath 2 outside the pipeline banded together, the sheath 2 includes that section is semicircle The the first pipe valve 21 and the second pipe valve 22 of shape, the first pipe valve 21 and the second pipe valve 22, which have, is used for bolted spiral shell Hole 23.Sheath 2 further includes the fixed link 24 being fixedly connected with 1 borehole wall of active well, and fixed link 24 is for fixing the sheath 2.
E, sheath 2 is connected and fixed with the active well 1 puzzled;
Fig. 6 is referred to, f, continuing symmetrically to cut the earth along 1 marginal position of active well builds active well 1, when a section digging depth After active well 1 puzzles, the earthwork in middle position is excavated, then excavate next 1 marginal position of section active well, until completing whole works Make well 1.4 thickness of bottom plate is 200mm, concrete C25, and after active well 1 to set absolute altitude, concrete is arranged further according to pipeline rout Under the premise of meeting the push pipe working space brick film 11 is arranged in position of back size as needed, in stock mould in rear backrest C25 concrete is poured between 11 and well bore, as push pipe backrest.
Sheath 2 is made of multiple sheath tube coupling 2a, and sheath tube coupling 2a is connect with another sheath tube coupling 2a by flange 25 solid It is fixed.The sheath 2 is made of metal.
The step b further includes masonry, and 1 marginal position of active well is built by masonry.The masonry is 370 bricks Wall.
When constructing to active well 1, being exposed to outer pipeline, there are security risks, and weight falls meeting to pipeline It damages, therefore the sheath 2 being sheathed on outside pipeline ensure that construction safety.It, can be to pipeline when being backfilled to active well 1 Inward pressure is generated, if backfill unevenly can also be such that pipeline deforms, therefore the sheath 2 being sheathed on outside pipeline avoids pipeline Using safe.
Refer to Fig. 7, in the second embodiment of brick projecting construction of working shaft method of the invention, according to soil property situation and Cutting depth, 2 meters to divide into reinforced concrete circle beam 3 one, collar tie beam 3 using 400mm X400mm reinforced concrete structure, Main reinforcement uses 14mm, and stirrup uses 8@200mm of φ, protective layer 30mm, concrete strength C20.Bottom plate thickness is 200mm, is mixed Solidifying soil is C25.
Pipeline and active well 1 are connected and fixed by the present invention by sheath 2, to protect pipeline, prevent pipeline because of construction Pipeline is damaged, or because backfill when to pipeline caused by squeeze, in the case where not destroying existing pipeline, pipeline can be saved Moving costs, reduce influence to ambient enviroment, shorten the construction period.
More than, it is only presently preferred embodiments of the present invention, is not intended to limit the present invention in any form, although this Invention has been disclosed in a preferred embodiment above, and however, it is not intended to limit the invention, any person skilled in the art, It does not depart within the scope of technical solution of the present invention, when the technology contents using the disclosure above make a little change or are modified to equivalent The equivalent embodiment of variation, but without departing from the technical solutions of the present invention, according to the technical essence of the invention to the above reality Any simple modification, equivalent variations and modification made by example are applied, all of which are still within the scope of the technical scheme of the invention.

Claims (10)

1. a kind of brick projecting construction of working shaft method characterized by comprising
A, underground utilities position is verified;
B, it symmetrically cuts the earth along active well marginal position and builds active well, when the active well of a section digging depth puzzles after, excavate Between position the earthwork, then excavate next section active well marginal position;
C, when driving arrives underground utilities position, whole pipelines is dug out, whole pipelines is banded together;
D, sheath is arranged outside the pipeline banded together, the sheath includes that section is semicircular first pipe valve and the second pipe Valve;
E, sheath is connected and fixed with the active well puzzled;
F, continue symmetrically to cut the earth along active well marginal position to build active well, after the active well of a section digging depth puzzles, dig Except the earthwork in middle position, then next section active well marginal position is excavated, until completing whole active wells.
2. brick projecting construction of working shaft method according to claim 1, which is characterized in that the first pipe valve and described Second pipe valve, which has, is used for bolted screw hole.
3. brick projecting construction of working shaft method according to claim 1, which is characterized in that the sheath further includes and institute The fixed link that the active well borehole wall is fixedly connected is stated, the fixed link is for fixing the sheath.
4. brick projecting construction of working shaft method according to claim 1, which is characterized in that the sheath is by multiple sheaths Tube coupling composition, sheath tube coupling are fixed with another sheath tube coupling by flanged joint.
5. brick projecting construction of working shaft method according to claim 1, which is characterized in that the step b further includes building Body, the active well marginal position are built by masonry.
6. brick projecting construction of working shaft method according to claim 5, which is characterized in that the masonry is 370 brick walls.
7. brick projecting construction of working shaft method according to claim 1, which is characterized in that the pipeline is tied by band It pricks.
8. brick projecting construction of working shaft method according to claim 1, which is characterized in that the sheath is by made of metal At.
9. brick projecting construction of working shaft method according to claim 1, which is characterized in that the active well intensity reaches Lower section excavation is carried out after 70% again.
10. brick projecting construction of working shaft method according to claim 9, which is characterized in that each excavation width≤ 1200mm, depth≤1000mm.
CN201810843141.8A 2018-07-27 2018-07-27 A kind of brick projecting construction of working shaft method Pending CN109162719A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810843141.8A CN109162719A (en) 2018-07-27 2018-07-27 A kind of brick projecting construction of working shaft method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810843141.8A CN109162719A (en) 2018-07-27 2018-07-27 A kind of brick projecting construction of working shaft method

Publications (1)

Publication Number Publication Date
CN109162719A true CN109162719A (en) 2019-01-08

Family

ID=64898452

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810843141.8A Pending CN109162719A (en) 2018-07-27 2018-07-27 A kind of brick projecting construction of working shaft method

Country Status (1)

Country Link
CN (1) CN109162719A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0007413A1 (en) * 1978-07-28 1980-02-06 Hüls Troisdorf Aktiengesellschaft Process for sealing of walls from water pressure or infiltration
CN102587391A (en) * 2011-01-10 2012-07-18 孙冬梁 Construction process for large-aperture brick and concrete reverse hanging well
CN106150506A (en) * 2016-07-08 2016-11-23 中铁十六局集团地铁工程有限公司 A kind of gateway open excavation section inverted side-wall construction method
CN107090851A (en) * 2017-04-24 2017-08-25 北京城建道桥建设集团有限公司 The inverted side-wall construction method of downtown area open cut groove

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0007413A1 (en) * 1978-07-28 1980-02-06 Hüls Troisdorf Aktiengesellschaft Process for sealing of walls from water pressure or infiltration
CN102587391A (en) * 2011-01-10 2012-07-18 孙冬梁 Construction process for large-aperture brick and concrete reverse hanging well
CN106150506A (en) * 2016-07-08 2016-11-23 中铁十六局集团地铁工程有限公司 A kind of gateway open excavation section inverted side-wall construction method
CN107090851A (en) * 2017-04-24 2017-08-25 北京城建道桥建设集团有限公司 The inverted side-wall construction method of downtown area open cut groove

Similar Documents

Publication Publication Date Title
CN107542108B (en) A kind of reverse construction method of building basement structure
Hu et al. Artificial ground freezing in tunnelling through aquifer soil layers: A case study in Nanjing Metro Line 2
Henn Practical guide to grouting of underground structures
CN105041333A (en) Method for treating tunnel collapse through dugand covered method
Sun et al. Technologies for large cross-section subsea tunnel construction using drilling and blasting method
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN108412503A (en) Bias shallow-buried tunnel portal construction protection structure and construction method thereof
KR101536209B1 (en) Steel Pipe Multi Step Grouting device Open and cut and NATM complex excavation tunnel construction method
CN110284885A (en) Shield inspection-pit construction method
CN105041327B (en) Bored tunnel is counter to dig shield method of reseptance
CN110905536A (en) Construction method for receiving complex stratum earth pressure shield in underground excavation tunnel
CN110259490A (en) A kind of Underground Subway Station construction method
Tan et al. Catastrophic failure of Shanghai metro line 4 in July 2003: Postaccident rehabilitation
CN110439011B (en) Side slope anti-slip supporting structure and construction method thereof
CN105909262A (en) Subsurface tunnel driving method
CN108166532A (en) A kind of groutable underground continuous wall connector and its construction method
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN205618170U (en) Protective structure of no template punishment rock mass cavity in tunnel engineering
Parashar et al. Performance monitoring of deep shafts at Changi WRP project, Singapore
CN103527205A (en) Shield underwater oblique crossing hole entering construction method
CN109162719A (en) A kind of brick projecting construction of working shaft method
CN105840203A (en) Large section loess tunnel pre-cutting method construction method
CN217518646U (en) A Wrecker Tunnel Structure Underpassing an Existing Station
Yesilnacar Grouting applications in the Sanliurfa tunnels of GAP, Turkey
JP2942874B2 (en) How to join tunnels

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190108