CN109113255A - A kind of assembled air-entrained concrete building block and its construction method - Google Patents

A kind of assembled air-entrained concrete building block and its construction method Download PDF

Info

Publication number
CN109113255A
CN109113255A CN201811076387.3A CN201811076387A CN109113255A CN 109113255 A CN109113255 A CN 109113255A CN 201811076387 A CN201811076387 A CN 201811076387A CN 109113255 A CN109113255 A CN 109113255A
Authority
CN
China
Prior art keywords
building block
block
building
concrete
protrusion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811076387.3A
Other languages
Chinese (zh)
Inventor
杨泓斌
张亮亮
黄万禧
刘博�
翟皓月
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Bozhilin Robot Co Ltd
Original Assignee
Junheng Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Junheng Consulting Co Ltd filed Critical Junheng Consulting Co Ltd
Priority to CN201811076387.3A priority Critical patent/CN109113255A/en
Publication of CN109113255A publication Critical patent/CN109113255A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Foundations (AREA)

Abstract

The present invention proposes a kind of assembled air-entrained concrete building block and its construction method, including block body and the first protrusion that block body left side top is arranged in, bottom on the right side of the block body is provided with the second protrusion, link block is provided at the top of the block body, the bottom of the block body is provided with link slot, the link slot is mutually adapted with link block, the bottom of first protrusion is provided with strip groove, bar blocks are provided at the top of second protrusion, the bar blocks are mutually adapted with strip groove, deflector hole is set in the block body, ring diversion plate is provided on the deflector hole inner sidewall;The present invention passes through the setting of link block and link slot, the upper and lower surface of block body is correspondingly connected with, guarantee that longitudinal assembly is stablized, it builds close, the a large amount of mortars of energy conservation, it is equipped with strip groove, bar blocks, circular groove and round raised line simultaneously, realizes that the left and right sides of block body is correspondingly connected with, guarantees that laterally assembly is stablized.

Description

A kind of assembled air-entrained concrete building block and its construction method
Technical field
The present invention relates to technical field more particularly to a kind of assembled air-entrained concrete building block and its construction methods.
Background technique
Steam-pressing aero-concrete is a kind of novel wall material with the performances such as lightweight, heat preservation, heat-insulated, fire prevention, is applicable in The masonry of inside and outside wall in architectural engineering, the autoclave aerated concrete building block in China mainly with cement, lime, flyash or Sand, aluminium powder etc. are raw material, are formed through levigate, batching, stirring casting, expansion of getting angry, the quiet means such as cutting, steam press maintenance of stopping A kind of concrete material characterized by porous, however the connection relationship between existing assembled air-entrained concrete building block A kind of assembly method is taken mostly, therefore is installed more built on the sand, while existing assembled air-entrained concrete building block be unable to that This is mutually assembled, to affect the service performance of building block, and when assembling each other, can not achieve horizontal and vertical peace Dress, consequently, it is possible to bringing security risk.Therefore, the present invention proposes a kind of assembled air-entrained concrete building block and its construction method To solve problems of the prior art.
Summary of the invention
In view of the above-mentioned problems, the present invention proposes a kind of assembled air-entrained concrete building block and its construction method, the assembled Air-entrained concrete building block and its construction method pass through the setting of the first protrusion, the second protrusion, link block and link slot, building block The upper and lower surface of ontology is correspondingly connected with, and can be guaranteed that longitudinal assemble is stablized in this way, be built closely, and a large amount of mortars of energy conservation are set simultaneously It is equipped with strip groove, bar blocks, circular groove and round raised line, realizes that the left and right sides of block body is correspondingly connected with, can protect in this way Card laterally stablize by assembly, builds more closely, and the assembled air-entrained concrete building block is provided with deflector hole, the building puzzled It can be avoided long-term ponding gas in use and be damaged, block interiors can be discharged by ring diversion plate, practicability It is relatively strong, while in the construction process to the building block for piling up first layer, it then carries out next layer and piles up, avoid the injustice piled up Surely.
Including block body and the first convex of block body left side top is arranged in a kind of assembled air-entrained concrete building block Portion out, the bottom on the right side of the block body are provided with the second protrusion, link block, institute are provided at the top of the block body The bottom for stating block body is provided with link slot, and the link slot is mutually adapted with link block, the bottom of first protrusion It is provided with strip groove, bar blocks are provided at the top of second protrusion, the bar blocks are mutually adapted with strip groove, described Deflector hole is set in block body, is provided with ring diversion plate on the deflector hole inner sidewall.
Further improvement lies in that: the block body is made by steam-pressing aero-concrete or foam concrete, described Block body is cuboid.
Further improvement lies in that: circular groove, second protrusion are provided on the bottom on the left of the block body Right side be provided with round raised line, the circle raised line is mutually adapted with circular groove.
A kind of construction method of assembled air-entrained concrete building block, comprising the following steps:
Step 1: drawing
It creates monolithic architecture drawing, building structure drawing and builds electromechanical drawing, according to the monolithic architecture drawing, building Structural drawings and the electromechanical drawing creation monolithic architecture of building, building structure and building electromechanical model, integrate the monolithic architecture mould Type, the building structure model and the building electromechanical model, and carry out matching degree inspection;
Step 2: ground
Ground is dug, is filled, is then paved on the ground accomplished fluently with concrete and stone, base with stone and concrete Seat concrete thickness is 1-2 centimetres, and most upper skin brick and top concrete spacing are 1-1.5 centimetres;
Step 3: choosing and bracing wire
It chooses the almost the same building block of enough no bendings, flawless, specification and carries out operation, then by bottom building block concrete It is fixed on footing, masonry panel position is needed to make line setting at the scene, guarantee that base's building block position is accurate, then according to masonry Typesetting design drawing is built;
Step 4: first layer is piled up
New building block is first piled up on the right side of bottom building block, laid bricks with cement mortar allow round raised line on the right side of bottom building block with Circular groove on the left of new building block is mutually clamped, so that two pieces of building blocks or so connection is more secured, is then sequentially completed first layer Pile up;
Step 5: the second layer is piled up
New building block is chosen, being laid bricks with cement mortar allows the link slot of new building block bottom and the link block of bottom block tops It is mutually clamped, so that being vertically connected with more secured, then the repeatedly method of step 4, is sequentially completed piling up for the second layer;
Step 6: wall and the cementation of fissures
It continues up and piles up according to the method in step 4 and step 5, the height until reaching wall, while building block Between vertical mortar joint use the cementation of fissures, crack pouring width finally completes piling up for building at 8-10 millimeters.
Further improvement lies in that: in the step 1 when carrying out matching degree inspection, if matching degree is qualified, not to institute Monolithic architecture model, the building structure model and the building electromechanical model is stated to be adjusted, if matching degree is unqualified, The monolithic architecture model, the building structure model and the building electromechanical model are adjusted, until matching degree is qualified.
Further improvement lies in that: it squeezes into several concrete stakes in the step 2 downwards from ground, keeps it concordant, concrete stake Top be provided with the rib come out from internal stretch, more reinforcing bars are welded to each other, form steel reinforcement cage, steel reinforcement cage all around Upper plank is poured concrete into the chamber that plank is enclosed, when concrete floods 3/7ths height of steel reinforcement cage Stop casting, by vibratory concrete it is uniform after, wait 2-3 as a child to carry out the casting of compound concrete, last type to be composite After concrete is dry, the plank of surrounding is removed.
Further improvement lies in that: two-sided hanging wire in the step 3 is intermediate hard if a few personal use same root lines of long wall If several branch line points, small line will tense, every layer of building block will thread level watching, make horizontal joint uniformity, straight smoothness.
Further improvement lies in that: allow the first protrusion while piling up new building block in the step 4 on the right side of bottom building block Bar blocks at the top of the strip groove of portion bottom and the second protrusion are mutually clamped.
Further improvement lies in that: the first building block of the second layer is first completed in the step 5 and building block that first layer heap puzzles Between connection, then complete right side building block again and pile up.
Further improvement lies in that: it is first piled up to the right according to the method continuation in step 4 in the step 6, Zhi Daoda To the length of wall, then piled up according to the method side of continuing up in step 5, the height until reaching wall.
The invention has the benefit that assembled air-entrained concrete building block of the present invention and its construction method pass through the first protrusion The upper and lower surface of the setting in portion, the second protrusion, link block and link slot, block body is correspondingly connected with, and can guarantee to indulge in this way Stablize to assembly, build close, a large amount of mortars of energy conservation, while being provided with strip groove, bar blocks, circular groove and round raised line, It realizes that the left and right sides of block body is correspondingly connected with, can guarantee laterally to assemble in this way and stablize, build more closely, and the assembly Formula air-entrained concrete building block is provided with deflector hole, and the building puzzled can be avoided long-term ponding gas in use and be damaged It is bad, block interiors can be discharged by ring diversion plate, practicability is stronger, while in the construction process to the block for piling up first layer Then block carries out next layer and piles up, avoids piling up unstable.
Detailed description of the invention
Fig. 1 is main view of the present invention.
Fig. 2 is deflector hole schematic diagram of internal structure of the present invention.
Fig. 3 is block tops structural schematic diagram of the present invention
Fig. 4 is building block bottom substance schematic diagram of the present invention.
Fig. 5 is building block attachment structure schematic diagram of the present invention.
Wherein: 1- block body, the first protrusion of 2-, the second protrusion of 3-, 4- link block, 5- link slot, 6- strip groove, 7- bar blocks, 8- deflector hole, 9- ring diversion plate, 10- circular groove, 11- circle raised line.
Specific embodiment
In order to realize invention technological means, reach purpose and effect is easy to understand, below with reference to specific implementation Mode, the present invention is further explained.
A kind of assembled air-entrained concrete building block including block body 1 and is arranged in the first of 1 left side top of block body The bottom of protrusion 2,1 right side of block body is provided with the second protrusion 3, and the top of the block body 1 is provided with company Block 4 is connect, the bottom of the block body 1 is provided with link slot 5, and the link slot 5 is mutually adapted with link block 4, and described first The bottom of protrusion 2 is provided with strip groove 6, and the top of second protrusion 3 is provided with bar blocks 7, the bar blocks 7 and item Shape slot 6 is mutually adapted, and deflector hole 8 is arranged in the block body 1, is provided with ring diversion plate on 8 inner sidewall of deflector hole 9。
The block body 1 is made by steam-pressing aero-concrete or foam concrete, and the block body 1 is rectangular Body.
It is provided with circular groove 10 on the bottom in 1 left side of block body, the right side of second protrusion 3 is provided with Round raised line 11, the circle raised line 11 are mutually adapted with circular groove 10.
A kind of construction method of assembled air-entrained concrete building block
Step 1: drawing
It creates monolithic architecture drawing, building structure drawing and builds electromechanical drawing, according to the monolithic architecture drawing, building Structural drawings and the electromechanical drawing creation monolithic architecture of building, building structure and building electromechanical model, integrate the monolithic architecture mould Type, the building structure model and the building electromechanical model, and matching degree inspection is carried out, while carrying out matching degree inspection When, if matching degree is qualified, not to the monolithic architecture model, the building structure model and the building electromechanical model into Row adjustment, if matching degree is unqualified, to the electromechanical mould of the monolithic architecture model, the building structure model and the building Type is adjusted, until matching degree is qualified;
Step 2: ground
Ground is dug, squeezes into several concrete stakes downwards from ground, keeps it concordant, is provided at the top of concrete stake from inside and prolongs The rib stretched, more reinforcing bars are welded to each other, and form steel reinforcement cage, in the plank upper all around of steel reinforcement cage, enclose shape to plank At chamber in be poured concrete, when concrete floods 3/7ths height of steel reinforcement cage stop casting, concrete is shaken After moving uniformly, 2-3 is waited as a child to carry out the casting of compound concrete, after last type concrete to be composite is dry, dismounting four The plank in week, pedestal concrete thickness are 2-5 centimetres, and most upper skin brick and top concrete spacing are 1-1.5 centimetres;
Step 3: choosing and bracing wire
It chooses the almost the same building block of enough no bendings, flawless, specification and carries out operation, then by bottom building block concrete It is fixed on footing, masonry panel position is needed to make line setting, two-sided hanging wire, if a few personal use same roots of long wall at the scene Line, centre set several branch line points firmly, and small line will tense, and every layer of building block will thread level watching, make horizontal joint uniformity, straight logical It is suitable, guarantee that base's building block position is accurate, is then built according to masonry typesetting design drawing;
Step 4: first layer is piled up
New building block is first piled up on the right side of bottom building block, the round raised line 11 allowed on the right side of bottom building block of being laid bricks with cement mortar It is mutually clamped with the circular groove 10 on the left of new building block, while allowing the strip groove 6 and the second protrusion 3 of 2 bottom of the first protrusion The bar blocks 7 at top are mutually clamped, so that two pieces of building blocks or so connection is more secured, are then sequentially completed piling up for first layer;
Step 5: the second layer is piled up
New building block is chosen, is first laid bricks with cement mortar and completes the building block that the first building block of the second layer is puzzled with first layer heap Between connection, allow the link slot 5 of new building block bottom and the link block 4 of bottom block tops to be mutually clamped, so that being vertically connected with More secured, then the repeatedly method of step 4, is sequentially completed piling up for the second layer;
Step 6: wall and the cementation of fissures
It is first piled up to the right according to the method continuation in step 4, the length until reaching wall, then according to step 5 In the method side of continuing up pile up, the height until reaching wall, at the same the vertical mortar joint between building block use the cementation of fissures, the cementation of fissures Width finally completes piling up for building at 8-10 millimeters.
Assembled air-entrained concrete building block of the present invention and its construction method pass through the first protrusion 2, the second protrusion 3, connect The setting of block 4 and link slot 5 is connect, the upper and lower surface of block body 1 is correspondingly connected with, and can be guaranteed that longitudinal assemble is stablized in this way, be built Close, a large amount of mortars of energy conservation are built, while being provided with strip groove 6, bar blocks 7, circular groove 10 and round raised line 11, realize building block The left and right sides of ontology 1 is correspondingly connected with, and can be guaranteed laterally to assemble in this way and be stablized, build more closely, and the assembled aerating Concrete segment is provided with deflector hole 8, and the building puzzled can be avoided long-term ponding gas in use and be damaged, and passes through Block interiors can be discharged in ring diversion plate 9, and practicability is stronger, while in the construction process to the building block for piling up first layer, so Next layer is carried out afterwards to pile up, and avoids piling up unstable.
The basic principles, main features and advantages of the invention have been shown and described above.The technical staff of the industry should Understand, the present invention is not limited to the above embodiments, and the above embodiments and description only describe originals of the invention Reason, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these changes and improvements It all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by appended claims and its equivalent circle It is fixed.

Claims (10)

1. a kind of assembled air-entrained concrete building block, it is characterised in that: including block body (1) and be arranged in block body (1) The first protrusion (2) of left side top, the bottom on the right side of the block body (1) are provided with the second protrusion (3), the building block It is provided at the top of ontology (1) link block (4), the bottom of the block body (1) is provided with link slot (5), the link slot (5) it is mutually adapted with link block (4), the bottom of first protrusion (2) is provided with strip groove (6), second protrusion (3) it is provided at the top of bar blocks (7), the bar blocks (7) are mutually adapted with strip groove (6), set in the block body (1) It sets deflector hole (8), is provided with ring diversion plate (9) on deflector hole (8) inner sidewall.
2. a kind of assembled air-entrained concrete building block according to claim 1, it is characterised in that: the block body (1) It is made by steam-pressing aero-concrete or foam concrete, the block body (1) is cuboid.
3. a kind of assembled air-entrained concrete building block according to claim 1, it is characterised in that: the block body (1) It is provided on the bottom in left side circular groove (10), is provided with round raised line (11) on the right side of second protrusion (3), it is described Round raised line (11) is mutually adapted with circular groove (10).
4. a kind of construction method of assembled air-entrained concrete building block, it is characterised in that: the following steps are included:
Step 1: drawing
It creates monolithic architecture drawing, building structure drawing and builds electromechanical drawing, according to the monolithic architecture drawing, building structure Drawing and the electromechanical drawing creation monolithic architecture of building, building structure and building electromechanical model, integrate the monolithic architecture model, institute Building structure model and the building electromechanical model are stated, and carries out matching degree inspection;
Step 2: ground
Ground is dug, is filled with stone and concrete, is then paved on the ground accomplished fluently with concrete and stone, pedestal is mixed Solidifying soil thickness is 2-5 centimetres, and most upper skin brick and top concrete spacing are 1-1.5 centimetres;
Step 3: choosing and bracing wire
It chooses the almost the same building block of enough no bendings, flawless, specification and carries out operation, then bottom building block is fixed with concrete On footing, masonry panel position is needed to make line setting at the scene, guarantee that base's building block position is accurate, then according to masonry typesetting Design drawing is built;
Step 4: first layer is piled up
New building block is first piled up on the right side of bottom building block, being laid bricks with cement mortar allows round raised line 11 on the right side of bottom building block and new Circular groove 10 on the left of building block is mutually clamped, so that two pieces of building blocks or so connection is more secured, is then sequentially completed first layer Pile up;
Step 5: the second layer is piled up
New building block is chosen, being laid bricks with cement mortar allows the link slot 5 of new building block bottom and 4 phase of link block of bottom block tops Mutually engaging, so that being vertically connected with more secured, then the repeatedly method of step 4, is sequentially completed piling up for the second layer;
Step 6: wall and the cementation of fissures
It continues up and piles up according to the method in step 4 and step 5, the height until reaching wall, while between building block Vertical mortar joint use the cementation of fissures, crack pouring width finally completes piling up for building at 8-10 millimeters.
5. a kind of construction method of assembled air-entrained concrete building block according to claim 4, it is characterised in that: the step In rapid one when carrying out matching degree inspection, if matching degree is qualified, not to the monolithic architecture model, the building structure mould Type and the building electromechanical model are adjusted, if matching degree is unqualified, are tied to the monolithic architecture model, the building Structure model and the building electromechanical model are adjusted, until matching degree is qualified.
6. a kind of construction method of assembled air-entrained concrete building block according to claim 4, it is characterised in that: the step It squeezes into several concrete stakes in rapid two downwards from ground, keeps it concordant, be provided at the top of concrete stake and come out from internal stretch Rib, more reinforcing bars are welded to each other, and form steel reinforcement cage, in the plank upper all around of steel reinforcement cage, the chamber being enclosed to plank Interior casting concrete, when concrete floods 3/7ths height of steel reinforcement cage stop casting, by vibratory concrete it is uniform after, It waits 2-3 as a child to carry out the casting of compound concrete and removes the plank of surrounding after last type concrete to be composite is dry.
7. a kind of construction method of assembled air-entrained concrete building block according to claim 4, it is characterised in that: the step Two-sided hanging wire in rapid three, if a few personal use same root lines of long wall, centre sets several branch line points firmly, and small line will tense, and every layer Building block will thread level watching, make horizontal joint uniformity, straight smoothness.
8. a kind of construction method of assembled air-entrained concrete building block according to claim 4, it is characterised in that: the step It is piled up on the right side of bottom building block in rapid four and allows the strip groove 6 and the second protrusion 3 of 2 bottom of the first protrusion while new building block The bar blocks 7 at top are mutually clamped.
9. a kind of construction method of assembled air-entrained concrete building block according to claim 4, it is characterised in that: the step Then right side building block is completed in the connection between building block that the first building block and first layer heap that the second layer is first completed in rapid five puzzle again Pile up.
10. a kind of construction method of assembled air-entrained concrete building block according to claim 4, it is characterised in that: described It is first piled up to the right according to the method continuation in step 4 in step 6, the length until reaching wall, then according to step 5 In the method side of continuing up pile up, the height until reaching wall.
CN201811076387.3A 2018-09-14 2018-09-14 A kind of assembled air-entrained concrete building block and its construction method Pending CN109113255A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811076387.3A CN109113255A (en) 2018-09-14 2018-09-14 A kind of assembled air-entrained concrete building block and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811076387.3A CN109113255A (en) 2018-09-14 2018-09-14 A kind of assembled air-entrained concrete building block and its construction method

Publications (1)

Publication Number Publication Date
CN109113255A true CN109113255A (en) 2019-01-01

Family

ID=64858531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811076387.3A Pending CN109113255A (en) 2018-09-14 2018-09-14 A kind of assembled air-entrained concrete building block and its construction method

Country Status (1)

Country Link
CN (1) CN109113255A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914647A (en) * 2019-04-25 2019-06-21 湖南银河钢结构工程有限责任公司 A kind of dry method is linked and packed formula wall and construction process

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103233543A (en) * 2013-03-06 2013-08-07 宁波北仑大港科技创新服务中心 Self-locking building-free concrete building block
CN204531138U (en) * 2015-04-21 2015-08-05 福建安固新型环保建材有限公司 A kind of exterior wall building block
CN105201125A (en) * 2015-09-22 2015-12-30 成都市凤庭环能科技有限公司 Hollow brick with waterproof structure
CN107956268A (en) * 2017-12-24 2018-04-24 李万 A die-cast building construction brick
CN108049640A (en) * 2017-11-15 2018-05-18 中建四局第六建筑工程有限公司 A kind of building block system building block construction technology
CN108360501A (en) * 2018-01-19 2018-08-03 台州市名泰建设工程有限公司 A kind of construction method of ground
CN108487635A (en) * 2018-03-06 2018-09-04 中建五局华东建设有限公司 Assembled architecture construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103233543A (en) * 2013-03-06 2013-08-07 宁波北仑大港科技创新服务中心 Self-locking building-free concrete building block
CN204531138U (en) * 2015-04-21 2015-08-05 福建安固新型环保建材有限公司 A kind of exterior wall building block
CN105201125A (en) * 2015-09-22 2015-12-30 成都市凤庭环能科技有限公司 Hollow brick with waterproof structure
CN108049640A (en) * 2017-11-15 2018-05-18 中建四局第六建筑工程有限公司 A kind of building block system building block construction technology
CN107956268A (en) * 2017-12-24 2018-04-24 李万 A die-cast building construction brick
CN108360501A (en) * 2018-01-19 2018-08-03 台州市名泰建设工程有限公司 A kind of construction method of ground
CN108487635A (en) * 2018-03-06 2018-09-04 中建五局华东建设有限公司 Assembled architecture construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914647A (en) * 2019-04-25 2019-06-21 湖南银河钢结构工程有限责任公司 A kind of dry method is linked and packed formula wall and construction process

Similar Documents

Publication Publication Date Title
CN106245821B (en) A kind of lightweight steel construction lightweight concrete prefabrication and assembly construction wall and its construction method
CN110145121A (en) The construction method of constructional column concreting
CN112726878A (en) Formwork-erecting-free construction method for masonry filler wall constructional column, prefabricated module and mould
CN104499498B (en) A kind of construction method of mass concrete building
CN103046465A (en) Reinforcing construction method for foam core die precast hollow plate beam
CN109113255A (en) A kind of assembled air-entrained concrete building block and its construction method
CN110126064A (en) A kind of double skin wall production methods
CN108130915A (en) Prefabricated assembling type reinforced frame raft foundation alter-pouring strips mould plate and its construction method
CN102322022B (en) Construction method for concrete of decorative housing of cable stayed bridge
CN112267691B (en) Argil brick hollow wall construction method
CN205712151U (en) Concrete foundation prefabricated slab
CN108149845A (en) The extrusion forming of concrete column and beam exempts from form removal shell and its preparation method and application
CN112962865A (en) Assembly type UHPC disassembly-free template
CN109291208B (en) Large-span prestressed concrete double-T-plate construction method
CN105926657A (en) Concrete foundation prefabricated slab and construction method thereof
CN108824810A (en) A kind of laying construction technique of steel skeleton composite building top plate
CN104110131A (en) Hollow concrete shuttering of constructional wall column
CN104453234A (en) Variable-cross-section oversized annular structure construction method and self-compacting concrete adopted for same
CN106049751A (en) Manufacturing method of ring beam or plate strip of aerated block and special prefabricated brick of ring beam or plate strip
CN108457427A (en) A kind of sealing sizing cushion block and production method for building concrete formwork erection
CN208668745U (en) A kind of hollow floor large scale core mold structure
CN206016054U (en) A kind of collar tie beam of aerated blocks or strip and preformed bricks
CN205399451U (en) Separate house cross concrete foundation who pours with concrete block
CN108716252A (en) A kind of rapid constructing method of no cavity composite thermal-insulating wall
GB2573293A (en) Method of casting a textured concrete walling slab

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20191128

Address after: 528311 East Office Building 201-11, No. 11 Junye East Road, Beijiao Town, Shunde District, Foshan City, Guangdong Province

Applicant after: Guangdong Bozhilin Robot Co., Ltd.

Address before: Room 105-46349, No. 6 Baohua Road, Hengqin New District, Zhuhai City, Guangdong Province

Applicant before: Junheng Consulting Co., Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20190101