CN109056521A - A kind of maintenance platform and maintenance activity method for high-speed rail bridge steel member - Google Patents

A kind of maintenance platform and maintenance activity method for high-speed rail bridge steel member Download PDF

Info

Publication number
CN109056521A
CN109056521A CN201811057695.1A CN201811057695A CN109056521A CN 109056521 A CN109056521 A CN 109056521A CN 201811057695 A CN201811057695 A CN 201811057695A CN 109056521 A CN109056521 A CN 109056521A
Authority
CN
China
Prior art keywords
sole plate
support bar
steel
steel sole
speed rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811057695.1A
Other languages
Chinese (zh)
Other versions
CN109056521B (en
Inventor
王威
冯青松
万旭民
廖松
雷晓燕
龙彭振
尹述遥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Jiaotong University
Original Assignee
East China Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Jiaotong University filed Critical East China Jiaotong University
Priority to CN201811057695.1A priority Critical patent/CN109056521B/en
Publication of CN109056521A publication Critical patent/CN109056521A/en
Application granted granted Critical
Publication of CN109056521B publication Critical patent/CN109056521B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/106Movable inspection or maintenance platforms, e.g. travelling scaffolding or vehicles specially designed to provide access to the undersides of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开一种用于高铁桥梁钢构件的维修平台,涉及高铁建设领域,在第一钢底板上滑动连接有第二钢底板,第一钢底板和第二钢底板的上表面分别设置有两组以上支撑杆组,每组所述支撑杆组均包括第一支撑杆和第二支撑杆,第一支撑杆顶端用于与高铁桥梁人行道板侧边连接,第二支撑杆的顶端用于与角钢支架连接;该用于高铁桥梁钢构件的维修平台结构简单,设计合理,仅需预先搭挂支撑杆组和钢底板即可,搭建时间大大缩短,也节省了建造成本。本发明还提供一种维修作业方法,其中维修平台搭建方法简便,成本低,可以从桥台处开始搭建,并移动至全桥台,流通性好,方便连续施工作业,适用于无法从中间桥墩上墩顶的桥梁维修工作,实用性极强。

The invention discloses a maintenance platform for high-speed rail bridge steel components, and relates to the field of high-speed rail construction. A second steel bottom plate is slidably connected to a first steel bottom plate, and two steel bottom plates are respectively arranged on the upper surfaces of the first steel bottom plate and the second steel bottom plate. More than one set of support rod groups, each group of support rod groups includes a first support rod and a second support rod, the top of the first support rod is used to connect with the side of the sidewalk of the high-speed rail bridge, and the top of the second support rod is used to connect with Angle steel support connection; the maintenance platform for steel components of high-speed rail bridges has a simple structure and reasonable design. It only needs to hang the support rod group and the steel bottom plate in advance, which greatly shortens the construction time and saves the construction cost. The invention also provides a maintenance operation method, wherein the construction method of the maintenance platform is simple and low in cost. It can be built from the abutment and moved to the whole abutment. It has good circulation and is convenient for continuous construction operations. The bridge maintenance work on the top of the pier is extremely practical.

Description

A kind of maintenance platform and maintenance activity method for high-speed rail bridge steel member
Technical field
The present invention relates to high-speed rail construction fields, more particularly to a kind of maintenance platform and dimension for high-speed rail bridge steel member Repair operational method.
Background technique
It is completely to spread foot hand hook, scaffold board below pedestrian way of bridge in existing high-speed rail bridge steel member method for maintaining Mode build maintenance platform, key step is as follows: (1) setting up pier and check ladder, make away from 10 meters of ground level piers below Industry personnel use fixed stair or more, after the pier operating personnel away from 10 meters of ground level or more sets up job platform using steel pipe Reuse fixed stair or more;(2) it is hung using pulley and scaffold board, hook and reinforcing bar crosspiece is hung to pier under bridge, and by By one end pier, from pedestrian way of bridge steel bracket, lodge customizes foot hand hook to another pier to foot hand short slab one by one, synchronizes full paving simultaneously Fixed scaffold board, adds strut rail reinforcing bar later on foot hand hook and pocket sets safety net.
It is above-mentioned it is found that existing maintenance platform needs to set up one by one in advance on the angle bar frame between pier when building Large number of foot hand hook, and scaffold board is completely spread between foot hand hook, full-bridge maintenance channel must also be set up from abutment, not only needed standby Scaffold board quantity is larger, and complex steps, can repair work after needing all to complete foot hand hook and scaffold board Industry, the consuming time is longer, and cost is larger.In addition, in maintenance activity, the lodge of foot hand hook be highly prone to bridge construction error and The influence of bridge self-deformation, there are some potential safety problemss;And the bridge pier for pier height at 15 meters or more, then by setting up steel Bridge pier is also to be unable to satisfy the efficiency requirements and demand for security of construction there are certain difficulty in the mode of pin hand cradle.
Summary of the invention
The object of the present invention is to provide it is a kind of it is structurally reasonable, installation steps are easy, it is at low cost, can guarantee that maintenance activity connects The maintenance platform and maintenance activity method for high-speed rail bridge steel member of continuous property and safety.
To achieve the above object, the present invention provides following schemes:
The present invention provides a kind of maintenance platform for high-speed rail bridge steel member, including the first steel sole plate, first steel One piece or more the second steel sole plate is also slidably connected in the upper surface of bottom plate, second steel sole plate is used for along first steel bottom The length direction of plate slides;The upper surface of first steel sole plate and second steel sole plate is respectively arranged with support more than two Bar group, the support bar group more than two are distributed along the length direction of first steel sole plate and second steel sole plate, often The group support bar group includes first support bar and second support bar, two or more the institutes on first steel sole plate The second support bar for stating first support bar and two or more is located at the two sides of second steel sole plate, is located at described the Two or more the first support bars on two steel sole plates and the first support bar on first steel sole plate are same Side, two or more second support bars on second steel sole plate be located on first steel sole plate described in Second support bar is ipsilateral;The first support bar top with high-speed rail bridge side walk slab side for connecting, second support The top of bar with angle bar frame for connecting.
Optionally, one piece of second steel sole plate is slidably connected in the upper surface of first steel sole plate;Described first The upper surface of steel sole plate is arranged side by side along the width direction of first steel sole plate more raised slideways, second steel sole plate Bottom offer multiple tracks and the raised matched sliding slot of slideway.
Optionally, be provided with two groups on first steel sole plate described in support bar group, support bar group described in two groups distinguish position In the both ends of the first steel sole plate length direction;Support bar group described in being provided with two groups on second steel sole plate, two groups of institutes State the both ends that support bar group is located at the second steel sole plate length direction.
Optionally, the length of the first support bar in support bar group described in every group is all larger than the second support bar, And the top of each first support bar and each second support bar is provided with crotch retaining ring, the crotch button The side of ring is provided with opening, and the both ends of the opening are connected by bolt pair.
Optionally, the first support bar on first steel sole plate and the second support bar are with described One steel sole plate is hinged, and the first support bar and the second support bar on second steel sole plate are with described second Steel sole plate is hinged.
Optionally, between the adjacent first support bar on first steel sole plate and described second adjacent It is detachably connected by reinforcing bar guardrail between strut;The adjacent first support bar on second steel sole plate and It is detachably connected by reinforcing bar guardrail between the adjacent second support bar;The first support bar in every group of support bar group It is detachably connected by reinforcing bar crosspiece between the second support bar.
Optionally, through-hole is offered on the lever arm of the every first support bar and the second support bar, it is described logical Hole is for installing reinforcing bar guardrail and/or reinforcing bar crosspiece.
Optionally, the raised slideway is T shape protrusion slideway, and the top end face of the T shape protrusion slideway is arc surface;Institute Stating sliding slot is the T shape sliding slot to match with the T shape protrusion slideway appearance profile, and the top end face of the T shape sliding slot is circular arc Face.
The present invention also provides a kind of maintenance activity method based on the above-mentioned maintenance platform for high-speed rail bridge steel member, packets Include following steps:
Step 1: inspection ladder is set up in high-speed rail bridge pier, by unassembled first steel sole plate, second steel bottom Plate, the support bar group and other construction material tools are transported at the top of pier;
Step 2: second steel sole plate is slidably connected to the upper surface of first steel sole plate, and described first The support bar group is installed in the upper surface of steel sole plate, and will be located at the every first support bar top on first steel sole plate End connect and locks with high-speed rail bridge side walk slab side, by every be located on first steel sole plate second support The top of bar connect and is locked with angle bar frame;
Step 3: by second steel sole plate along the length direction slidable adjustment of first steel sole plate, it is suitable to be moved to Behind position, the support bar group is installed in the upper surface of second steel sole plate, the every institute on second steel sole plate First support bar top is stated to connect and lock with high-speed rail bridge side walk slab side, it is every on second steel sole plate by being located at The top of second support bar described in root connect and is locked with angle bar frame;
Step 4: operator starts on the maintenance platform that step 3 is put up to the high-speed rail bridge steel at a maintenace point Component repairs and derusts operation;
Step 5: after the completion of maintenance and derusting operation, by the every first support bar in high-speed rail bridge side walk slab side Side unlocks and dismantles, and the every second support bar is unlocked and dismantled on angle bar frame, and by first steel sole plate and After second steel sole plate moves forward to the lower section of next maintenace point, it is repeated in step 2 to step 4 and continues to repair and remove Rust operation;
After work whole that step 6: repeating step 5 until the maintenance of entire high-speed rail bridge derusts, described in every First support bar is unlocked and is dismantled in high-speed rail bridge side walk slab side, and the every second support bar is solved on angle bar frame It locks and dismantles, finally dismantle first steel sole plate, second steel sole plate and the support bar group to reset condition, Ground is transported to by pier inspection ladder together with other material tools of constructing again.
The present invention achieves following technical effect compared with the existing technology:
Simple provided by the present invention for the maintenance platform structure of high-speed rail bridge steel member, design is reasonable, it is only necessary to take in advance Support bar group and steel sole plate are hung, building the time greatly shortens, and also saves construction cost;Maintenance activity provided by the invention In method, maintenance platform building method is easy, at low cost, can build since Abutment, and be moved to full-bridge platform, circulation It is good, facilitate continuous construction operation, suitable for that can not work from the bridge maintaining of pier top on intermediate bridge pier, practicability is extremely strong.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without any creative labor, can also be according to these attached drawings Obtain other attached drawings.
Fig. 1 is structural schematic diagram of the present invention for the maintenance platform of high-speed rail bridge steel member;
Fig. 2 is the structural schematic diagram of the first steel sole plate in Fig. 1;
Fig. 3 is the structural schematic diagram of the second steel sole plate in Fig. 1;
Fig. 4 is the partial structural diagram of the first steel sole plate of Fig. 2;
Fig. 5 is the partial structural diagram of the second steel sole plate of Fig. 3;
Fig. 6 is the connection schematic diagram of the first steel sole plate and the second steel sole plate;
Fig. 7 is the side view that the first steel sole plate of Fig. 6 and the second steel sole plate connect;
Fig. 8 is the structural schematic diagram of crotch retaining ring in Fig. 1;
Wherein, appended drawing reference are as follows: the 1, first steel sole plate;2, the second steel sole plate;3, first support bar;4, second support bar; 5, crotch retaining ring;5-1, opening;5-2, bolt pair;6, reinforcing bar crosspiece;7, reinforcing bar guardrail;8, raised slideway;9, sliding slot.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The object of the present invention is to provide it is a kind of it is structurally reasonable, installation steps are easy, it is at low cost, can guarantee that maintenance activity connects The maintenance platform and maintenance activity method for high-speed rail bridge steel member of continuous property and safety.
Based on this, the present invention provides a kind of maintenance platform for high-speed rail bridge steel member, including the first steel sole plate, and first One piece or more the second steel sole plate is also slidably connected in the upper surface of steel sole plate, the second steel sole plate is used for the length along the first steel sole plate Spend direction sliding;The upper surface of first steel sole plate and the second steel sole plate is respectively arranged with support bar group more than two, more than two Support bar group along the length direction of the first steel sole plate and the second steel sole plate be distributed, every group support bar group includes first support bar And second support bar, the second support bar difference of two or more first support bars on the first steel sole plate and two or more Positioned at the two sides of the second steel sole plate, two or more first support bars on the second steel sole plate be located on the first steel sole plate First support bar it is ipsilateral, two or more second support bars on the second steel sole plate be located on the first steel sole plate the Two support rods are ipsilateral;For connecting with high-speed rail bridge side walk slab side, the top of second support bar is used on first support bar top It is connect in angle bar frame.
The present invention also provides a kind of maintenance activity method based on the above-mentioned maintenance platform for high-speed rail bridge steel member, packets Include following steps:
Step 1: inspection ladder is set up in high-speed rail bridge pier, by the first unassembled steel sole plate, the second steel sole plate, support Bar group and other construction material tools are transported at the top of pier;
Step 2: second steel sole plate is slidably connected to the upper surface of first steel sole plate, and described first The support bar group is installed in the upper surface of steel sole plate, and will be located at the every first support bar top on first steel sole plate End connect and locks with high-speed rail bridge side walk slab side, by every be located on first steel sole plate second support The top of bar connect and is locked with angle bar frame;
Step 3: by second steel sole plate along the length direction slidable adjustment of first steel sole plate, it is suitable to be moved to Behind position, the support bar group is installed in the upper surface of second steel sole plate, the every institute on second steel sole plate First support bar top is stated to connect and lock with high-speed rail bridge side walk slab side, it is every on second steel sole plate by being located at The top of second support bar described in root connect and is locked with angle bar frame;
Step 4: operator starts on the maintenance platform that step 3 is put up to the high-speed rail bridge steel at a maintenace point Component repairs and derusts operation;
Step 5: after the completion of maintenance and derusting operation, by the every first support bar in high-speed rail bridge side walk slab side Side unlocks and dismantles, and the every second support bar is unlocked and dismantled on angle bar frame, and by first steel sole plate and After second steel sole plate moves forward to the lower section of next maintenace point, it is repeated in step 2 to step 4 and continues to repair and remove Rust operation;
After work whole that step 6: repeating step 5 until the maintenance of entire high-speed rail bridge derusts, described in every First support bar is unlocked and is dismantled in high-speed rail bridge side walk slab side, and the every second support bar is solved on angle bar frame It locks and dismantles, finally dismantle first steel sole plate, second steel sole plate and the support bar group to reset condition, Ground is transported to by pier inspection ladder together with other material tools of constructing again.
Simple provided by the present invention for the maintenance platform structure of high-speed rail bridge steel member, design is reasonable, it is only necessary to take in advance Support bar group and steel sole plate are hung, building the time greatly shortens, and also saves construction cost;Maintenance activity provided by the invention In method, maintenance platform building method is easy, at low cost, can build since Abutment, and be moved to full-bridge platform, circulation It is good, facilitate continuous construction operation, suitable for that can not work from the bridge maintaining of pier top on intermediate bridge pier, practicability is extremely strong.
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
Embodiment one:
As shown in Fig. 1~5, the present embodiment provides a kind of maintenance platforms for high-speed rail bridge steel member, including the first steel Bottom plate 1, one piece or more the second steel sole plate 2 is also slidably connected in the upper surface of the first steel sole plate 1, and the second steel sole plate 2 is used for edge The length direction of first steel sole plate 1 slides;The upper surface of first steel sole plate 1 and the second steel sole plate 2 is respectively arranged with more than two Support bar group, support bar group more than two are distributed along the length direction of the first steel sole plate 1 and the second steel sole plate 2, every group of support Bar group includes first support bar 3 and second support bar 4, two or more 3 Hes of first support bar on the first steel sole plate 1 Two or more second support bars 4 are respectively distributed to the two sides of the second steel sole plate 2, two or more on the second steel sole plate 2 First support bar 3 and the first support bar 3 that is located on the first steel sole plate 1 it is ipsilateral, two or more on the second steel sole plate 2 Second support bar 4 and be located at the first steel sole plate 1 on second support bar 4 it is ipsilateral;Wherein, 3 top of first support bar be used for The connection of high-speed rail bridge side walk slab side, the top of second support bar 4 with angle bar frame for connecting.
In this specific embodiment, as shown in Fig. 1~7, at most it is slidably connected in the upper surface of the first steel sole plate 1 two piece Two steel sole plates 2, be slidably connected on the present embodiment preferably the first steel sole plate 1 one piece of second steel sole plate 2;The upper table of first steel sole plate 1 Face is arranged side by side along the width direction of the first steel sole plate 1 more raised slideways 8, and the present embodiment is preferably provided with three raised slideways It 8 and is arranged in parallel, the bottom of the second steel sole plate 2 offers multiple tracks and the matched sliding slot 9 of raised slideway 8, and it is sliding to be preferably provided with three It slot 9 and is arranged in parallel.In the present embodiment, the first steel sole plate 1 is consistent with the length of the second steel sole plate 2, but the width of the second steel sole plate 2 Degree realizes opposite sliding by raised slideway 8 and sliding slot 9 between two pieces of steel sole plates, cooperates the branch on top less than the first steel sole plate 1 Strut group can reach the high effect moved between steel bracket in the air.
Further, as shown in Fig. 1~5, two groups of support bar groups, two groups of support rod components are provided on the first steel sole plate 1 Not Wei Yu 1 length direction of the first steel sole plate both ends, i.e. two first support bars 3 and two second support bars 3 are separately positioned on The quadrangle of first steel sole plate 1;Correspondingly, being provided with two groups of support bar groups on the second steel sole plate 2, two groups of support bar groups are located at The both ends of second steel sole plate, 2 length direction, i.e. two first support bars 3 and two second support bars 3 are separately positioned on the second steel The quadrangle of bottom plate 2.
Further, as shown in Fig. 1~5, the length of the first support bar 3 in every group of support bar group is all larger than the second support Bar 4, and the top of each first support bar 3 and each second support bar 4 is provided with crotch retaining ring 5, as shown in figure 8, Crotch retaining ring 5 is circular rings, and the side of crotch retaining ring 5 is provided with opening 5-1, and the upper and lower ends for the 5-1 that is open are respectively arranged with Connecting plate is connected by bolt pair 5-2 between two pieces of connecting plates, and bolt pair 5-2 includes screw bolt and nut, removes bolt pair 5-2, Convenient for the hook of crotch retaining ring 5 is connected on high-speed rail bridge side walk slab side or angle bar frame by opening 5-1, installs and twist After the screw bolt and nut of tight bolt pair 5-2, that is, it may make that crotch retaining ring 5 is fixed and is locked at high-speed rail bridge side walk slab side Or on angle bar frame, have the effect of for steel sole plate securely connecting with high-speed rail bridge side walk slab side or angle bar frame.
Further, the first support bar 3 on the first steel sole plate 1 and second support bar 4 are cut with scissors with the first steel sole plate 1 It connects, it is preferred to use activity is hinged, so that each support rod can be folded by lower removable hinge, adjustment is unfolded, convenient for suitable Answer angle bar frame position;Correspondingly, be located at the second steel sole plate 2 on first support bar 3 and second support bar 4 with the second steel bottom Plate 2 is hinged, it is preferred to use activity is hinged, so that each support rod can be folded by lower removable hinge, adjustment is unfolded, just It is adaptable for spacing can be adjusted flexibly when error lodge existing for some bridges itself in adaptation angle bar frame position, it is non- Often facilitate maintenance activity.
Further, between the adjacent first support bar 3 on the first steel sole plate 1 and adjacent second support bar 4 it Between be detachably connected by reinforcing bar guardrail 7;Adjacent first support bar 3 on the second steel sole plate 2 and second adjacent It is detachably connected by reinforcing bar guardrail 7 between strut 4;In every group of support bar group on first steel sole plate 1 and the second steel sole plate 2 First support bar 3 and second support bar 4 between be detachably connected by reinforcing bar crosspiece 6.In the present embodiment, every first Through-hole is offered on strut 3 and the lever arm of every second support bar 4, through-hole is used to install reinforcing bar guardrail 7 and reinforcing bar crosspiece 6, Reinforcing bar guardrail 7 and reinforcing bar crosspiece 6 are preferably mounted at the middle position of each support rod, can both reinforce connecting, and improve each pair of Whole device stability and security protection also can be improved in the lateral stability of strut group, and by opening up installation reinforcing bar guardrail 7 With reinforcing bar crosspiece 6, adjustment easy to disassemble.
Further, as shown in figs. 6-7, raised slideway 8 is T shape protrusion slideway, and the top end face of T shape protrusion slideway is Arc surface;Sliding slot 9 is the T shape sliding slot to match with T shape protrusion slideway appearance profile, and the top end face of T shape sliding slot is arc surface.
The building method to the present embodiment for the maintenance platform of high-speed rail bridge steel member is briefly described below, wherein respectively A support rod has passed through moveable hinge and has been mounted on the first steel sole plate 1 and the second steel sole plate 2, mainly includes the following steps:
Step 1: inspection ladder is set up in high-speed rail bridge pier, by the first unassembled steel sole plate 1, the second steel sole plate 2, branch Strut group, reinforcing bar crosspiece 6, reinforcing bar guardrail 7 and other construction material tools are transported at the top of pier;
Second steel sole plate 2: being slidably connected to the upper surface of the first steel sole plate 1 by step 2, and by table on the first steel sole plate 1 Two groups of support bar groups expansion that face folds, and 3 top of every first support bar being located on the first steel sole plate 1 is passed through into crotch Retaining ring 5 connect and locks with high-speed rail bridge side walk slab side, will be located at the every second support bar 4 on the first steel sole plate 1 Top passes through crotch retaining ring 5 and connect and lock with angle bar frame;
Step 3: by the second steel sole plate 2 along the length direction slidable adjustment of the first steel sole plate 1, after being moved to suitable position, The support bar group expansion that the upper surface of second steel sole plate 2 is folded, and every first support bar on the second steel sole plate 2 will be located at 3 tops pass through crotch retaining ring 5 and connect and lock with high-speed rail bridge side walk slab side, every on the second steel sole plate 2 by being located at The top of root second support bar 4 passes through crotch retaining ring 5 and connect and lock with angle bar frame;
Step 4: between the adjacent first support bar 3 being located on the first steel sole plate 1 and the second steel sole plate 2 and adjacent Reinforcing bar guardrail 7 is installed, and between the first support bar 3 and second support bar 4 in every group of support bar group between second support bar 4 Reinforcing bar crosspiece 6 is installed, building for maintenance platform is completed.
It is above-mentioned it is found that the maintenance platform structure provided by the present invention for high-speed rail bridge steel member is simple, design rationally, only Preparatory lodge support bar group and steel sole plate are needed, building the time greatly shortens, and also saves construction cost.
Embodiment two:
The present embodiment provides a kind of maintenances of one maintenance platform for high-speed rail bridge steel member based on the above embodiment Operational method mainly includes the following steps:
Step 1: inspection ladder is set up in high-speed rail bridge pier, by the first unassembled steel sole plate 1, the second steel sole plate 2, branch Strut group, reinforcing bar crosspiece 6, reinforcing bar guardrail 7 and other construction material tools are transported at the top of pier;
Second steel sole plate 2: being slidably connected to the upper surface of the first steel sole plate 1 by step 2, and by table on the first steel sole plate 1 Two groups of support bar groups expansion that face folds, and 3 top of every first support bar being located on the first steel sole plate 1 is passed through into crotch Retaining ring 5 connect and locks with high-speed rail bridge side walk slab side, will be located at the every second support bar 4 on the first steel sole plate 1 Top passes through crotch retaining ring 5 and connect and lock with angle bar frame;
Step 3: by the second steel sole plate 2 along the length direction slidable adjustment of the first steel sole plate 1, after being moved to suitable position, The support bar group expansion that the upper surface of second steel sole plate 2 is folded, and every first support bar on the second steel sole plate 2 will be located at 3 tops pass through crotch retaining ring 5 and connect and lock with high-speed rail bridge side walk slab side, every on the second steel sole plate 2 by being located at The top of root second support bar 4 passes through crotch retaining ring 5 and connect and lock with angle bar frame;
Step 4: between the adjacent first support bar 3 being located on the first steel sole plate 1 and the second steel sole plate 2 and adjacent Reinforcing bar guardrail 7 is installed, and between the first support bar 3 and second support bar 4 in every group of support bar group between second support bar 4 Reinforcing bar crosspiece 6 is installed, building for maintenance platform is completed;
Step 5: operator starts on the maintenance platform that step 4 is put up to the high-speed rail bridge steel at a maintenace point Component repairs and derusts operation;
Step 6: after the completion of maintenance and derusting operation, each first support bar 3 is solved in high-speed rail bridge side walk slab side It locks and dismantles, every second support bar 4 is unlocked and dismantled on angle bar frame, and by the first steel sole plate 1 and the second steel sole plate 2 After moving forward to the lower section of next maintenace point, continue to repair and derust operation after being repeated in step 2 to step 4;
Step 7: repeating step 5 to step 6 until the maintenance of entire high-speed rail bridge derusts after work whole, will After every reinforcing bar crosspiece 6 and reinforcing bar guardrail 7 are dismantled, then by every first support bar 3 in the unlock of high-speed rail bridge side walk slab side And dismantle, every second support bar 4 is unlocked and dismantled on angle bar frame, finally by the first steel sole plate 1 and the second steel sole plate 2 On each support rod be folded to reset condition, then ground is transported to by pier inspection ladder together with other material tools of constructing.
It is above-mentioned it is found that the maintenance platform structure provided by the present invention for high-speed rail bridge steel member is simple, design rationally, only Preparatory lodge support bar group and steel sole plate are needed, building the time greatly shortens, and also saves construction cost;It is provided by the invention In maintenance activity method, maintenance platform building method is easy, at low cost, can build since Abutment, and be moved to full-bridge Platform, circulation is good, facilitates continuous construction operation, suitable for that can not work from the bridge maintaining of pier top on intermediate bridge pier, practicability It is extremely strong.
It should be noted that being not limited to that one piece is only arranged on the first steel sole plate in above-described embodiment one in the present invention Second steel sole plate, also slidable connection has a third steel sole plate on the second steel sole plate, and also slidable connection has the on third steel sole plate Four steel sole plates, and so on, the relationship of being slidably connected between the first steel sole plate and the second steel sole plate is also not limited to above-mentioned implementation Example one, the adaptive change carried out according to actual needs are within the scope of the invention;Every piece of steel sole plate upper support bar Group is not limited to two groups of setting, and the top of every support rod, which is also not limited to, to be connect by crotch retaining ring with bridge dependency structure, The adaptive change carried out according to actual needs is within the scope of the invention;Reinforcing bar crosspiece and reinforcing bar guardrail with it is each Connection type between support rod is also not limited to above-described embodiment one, and the adaptive change carried out according to actual needs exists In protection scope of the present invention.
Specific examples are applied in the present invention, and principle and implementation of the present invention are described, above embodiments Illustrate to be merely used to help understand method and its core concept of the invention;At the same time, for those skilled in the art, according to According to thought of the invention, there will be changes in the specific implementation manner and application range.In conclusion the content of the present specification It should not be construed as limiting the invention.

Claims (9)

1. a kind of maintenance platform for high-speed rail bridge steel member, it is characterised in that: including the first steel sole plate, first steel bottom One piece or more the second steel sole plate is also slidably connected in the upper surface of plate, second steel sole plate is used for along first steel sole plate Length direction sliding;The upper surface of first steel sole plate and second steel sole plate is respectively arranged with support rod more than two Group, the support bar group more than two are distributed along the length direction of first steel sole plate and second steel sole plate, and every group The support bar group includes first support bar and second support bar, described in two or more on first steel sole plate The second support bar of first support bar and two or more are located at the two sides of second steel sole plate, are located at described second Two or more the first support bars on steel sole plate and the first support bar on first steel sole plate are ipsilateral, Two or more second support bars on second steel sole plate be located on first steel sole plate described the Two support rods are ipsilateral;The first support bar top with high-speed rail bridge side walk slab side for connecting, the second support bar Top for being connect with angle bar frame.
2. the maintenance platform according to claim 1 for high-speed rail bridge steel member, it is characterised in that: first steel bottom One piece of second steel sole plate is slidably connected in the upper surface of plate;The upper surface of first steel sole plate is along first steel bottom The width direction of plate, which is arranged side by side, more raised slideways, and the bottom of second steel sole plate offers multiple tracks and the protrusion is sliding The matched sliding slot in road.
3. the maintenance platform according to claim 1 for high-speed rail bridge steel member, it is characterised in that: first steel bottom Support bar group described in being provided with two groups on plate, support bar group described in two groups are located at the two of the first steel sole plate length direction End;Support bar group described in being provided with two groups on second steel sole plate, support bar group described in two groups are located at second steel The both ends in floor length direction.
4. the maintenance platform according to claim 3 for high-speed rail bridge steel member, it is characterised in that: supported described in every group The length of the first support bar in bar group is all larger than the second support bar, and each first support bar and each The top of second support bar described in root is provided with crotch retaining ring, and the side of the crotch retaining ring is provided with opening, the opening Both ends pass through bolt pair connect.
5. the maintenance platform according to claim 1 for high-speed rail bridge steel member, it is characterised in that: be located at described first The first support bar and the second support bar on steel sole plate is hinged with first steel sole plate, is located at second steel The first support bar and the second support bar on bottom plate is hinged with second steel sole plate.
6. the maintenance platform according to claim 5 for high-speed rail bridge steel member, it is characterised in that: be located at described first It is removable to pass through reinforcing bar guardrail between the adjacent first support bar on steel sole plate and between the adjacent second support bar Unload connection;It is logical between the adjacent first support bar and the adjacent second support bar on second steel sole plate Reinforcing bar guardrail is crossed to be detachably connected;Pass through between the first support bar and the second support bar in every group of support bar group Reinforcing bar crosspiece is detachably connected.
7. the maintenance platform according to claim 6 for high-speed rail bridge steel member, it is characterised in that: every described first Through-hole is offered on support rod and the lever arm of the second support bar, the through-hole is for installing reinforcing bar guardrail and/or reinforcing bar Crosspiece.
8. the maintenance platform according to claim 2 for high-speed rail bridge steel member, it is characterised in that: the protrusion slideway For T shape protrusion slideway, and the top end face of the T shape protrusion slideway is arc surface;The sliding slot be with outside the T shape protrusion slideway The T shape sliding slot that shape profile matches, and the top end face of the T shape sliding slot is arc surface.
9. a kind of maintenance based on the maintenance platform for being used for high-speed rail bridge steel member described in claim 1~8 any one is made Industry method, which comprises the steps of:
Step 1: high-speed rail bridge pier set up inspection ladder, by unassembled first steel sole plate, second steel sole plate, The support bar group and other construction material tools are transported at the top of pier;
Step 2: second steel sole plate is slidably connected to the upper surface of first steel sole plate, and at first steel bottom The support bar group is installed in the upper surface of plate, and equal by the every first support bar top on first steel sole plate is located at It connect and locks with high-speed rail bridge side walk slab side, the every second support bar on first steel sole plate will be located at Top connect and is locked with angle bar frame;
Step 3: by second steel sole plate along the length direction slidable adjustment of first steel sole plate, it is moved to suitable position Afterwards, the support bar group is installed in the upper surface of second steel sole plate, every on second steel sole plate described the One supporting bar top connect and locks with high-speed rail bridge side walk slab side, will be located at every institute on second steel sole plate The top for stating second support bar connect and is locked with angle bar frame;
Step 4: operator starts on the maintenance platform that step 3 is put up to the high-speed rail bridge steel member at a maintenace point Repair and derust operation;
Step 5: after the completion of maintenance and derusting operation, the every first support bar is solved in high-speed rail bridge side walk slab side It locks and dismantles, the every second support bar is unlocked and dismantled on angle bar frame, and by first steel sole plate and described After second steel sole plate moves forward to the lower section of next maintenace point, it is repeated in step 2 to step 4 and continues to repair and derust to make Industry;
After work whole that step 6: repeating step 5 until the maintenance of entire high-speed rail bridge derusts, by every described first Support rod is unlocked and is dismantled in high-speed rail bridge side walk slab side, and the every second support bar is unlocked simultaneously on angle bar frame Disassembly, finally dismantles first steel sole plate, second steel sole plate and the support bar group to reset condition, then connect Ground is transported to by pier inspection ladder with other material tools of constructing.
CN201811057695.1A 2018-09-11 2018-09-11 A maintenance platform and maintenance operation method for steel components of high-speed rail bridges Expired - Fee Related CN109056521B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811057695.1A CN109056521B (en) 2018-09-11 2018-09-11 A maintenance platform and maintenance operation method for steel components of high-speed rail bridges

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811057695.1A CN109056521B (en) 2018-09-11 2018-09-11 A maintenance platform and maintenance operation method for steel components of high-speed rail bridges

Publications (2)

Publication Number Publication Date
CN109056521A true CN109056521A (en) 2018-12-21
CN109056521B CN109056521B (en) 2020-06-16

Family

ID=64760105

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811057695.1A Expired - Fee Related CN109056521B (en) 2018-09-11 2018-09-11 A maintenance platform and maintenance operation method for steel components of high-speed rail bridges

Country Status (1)

Country Link
CN (1) CN109056521B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114215323A (en) * 2021-12-27 2022-03-22 广州地铁设计研究院股份有限公司 Civil engineering and mechanical-electrical integration assembly type maintenance platform and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6360490B1 (en) * 2001-06-15 2002-03-26 Richard J Cotriss Containment system
KR20120124276A (en) * 2011-05-03 2012-11-13 (주)디에스지 Device for bridge inspection moving type
CN203430005U (en) * 2013-08-02 2014-02-12 郑州新光色耐火材料有限公司 Overhauling platform for electric melting furnace
CN204754226U (en) * 2015-06-08 2015-11-11 广厦建设集团有限责任公司贵州分公司 Detachable construction platform of unloading
CN207003637U (en) * 2017-12-01 2018-02-13 卢宗鸿 A kind of telescopic movable platform
CN207295493U (en) * 2017-10-10 2018-05-01 江西省公路桥梁工程有限公司 A kind of collapsible interior Hanging Basket of wet seam construction of highway bridge
CN207619849U (en) * 2017-12-01 2018-07-17 中交路桥北方工程有限公司 A kind of single Hanging Basket of simple folding

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6360490B1 (en) * 2001-06-15 2002-03-26 Richard J Cotriss Containment system
KR20120124276A (en) * 2011-05-03 2012-11-13 (주)디에스지 Device for bridge inspection moving type
CN203430005U (en) * 2013-08-02 2014-02-12 郑州新光色耐火材料有限公司 Overhauling platform for electric melting furnace
CN204754226U (en) * 2015-06-08 2015-11-11 广厦建设集团有限责任公司贵州分公司 Detachable construction platform of unloading
CN207295493U (en) * 2017-10-10 2018-05-01 江西省公路桥梁工程有限公司 A kind of collapsible interior Hanging Basket of wet seam construction of highway bridge
CN207003637U (en) * 2017-12-01 2018-02-13 卢宗鸿 A kind of telescopic movable platform
CN207619849U (en) * 2017-12-01 2018-07-17 中交路桥北方工程有限公司 A kind of single Hanging Basket of simple folding

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114215323A (en) * 2021-12-27 2022-03-22 广州地铁设计研究院股份有限公司 Civil engineering and mechanical-electrical integration assembly type maintenance platform and construction method thereof
CN114215323B (en) * 2021-12-27 2023-04-07 广州地铁设计研究院股份有限公司 Civil engineering and mechanical integration assembly type maintenance platform and construction method thereof

Also Published As

Publication number Publication date
CN109056521B (en) 2020-06-16

Similar Documents

Publication Publication Date Title
CA2613171C (en) Rail-guided climbing system
AU2010266835B2 (en) A slab formwork system
CN103821361B (en) Stair studding formwork construction method is built in the gradation improved
CN208502206U (en) Assembling the shaped steel suspension scaffolding
CN104790644B (en) Extending and contracting sliding support frame for roof decorative bottom boards
CN109056521A (en) A kind of maintenance platform and maintenance activity method for high-speed rail bridge steel member
CN218969802U (en) Quick adjusting device of hanging basket template flange plate
CN107604829A (en) A kind of pier cap beam tensioning assembled tensioning job platform and preparation method thereof
CN102979297A (en) Mechanism and Construction Method of Suspension Ladder Well Operation Platform
CN115162156A (en) A folding safety guardrail for trestle platform
AU2017100073A4 (en) Hoarding assembly
CN212535063U (en) Self-supporting detachable steel bar truss floor bearing plate
CN209276917U (en) A kind of suspension type monorail traffic system and its pillarwork
CN217518253U (en) Foldable edge protection instrument that faces
CN110453611A (en) Multifunctional folding assembly operating platform
KR102298233B1 (en) Movable Safety Footboard for High Place Work and Inspection Road Constructing Method Using the Same
CN102400551A (en) Formwork support tool for steel structure floor system and construction method for framework support tool
CN211037864U (en) Reinforcing steel bar binding rack
CN102444293A (en) Cutting and slipping method for extension of existing large-span truss structure
CN210482970U (en) Extension formula elevartor shaft construction operation protection platform
CN208055873U (en) The self-traveling module inner platform system of suspended pouring of box beam Hanging Basket
CN222478095U (en) Movable double-operation platform with foldable protective railing
CN107190974B (en) Cable tower combined type inner sliding die construction method and inner platform frame used by same
JP6247893B2 (en) Suspended scaffolding panel
CN216042811U (en) Interim stair protective structure is used in construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant