CN109025087A - It is a kind of heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method - Google Patents
It is a kind of heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method Download PDFInfo
- Publication number
- CN109025087A CN109025087A CN201810871558.5A CN201810871558A CN109025087A CN 109025087 A CN109025087 A CN 109025087A CN 201810871558 A CN201810871558 A CN 201810871558A CN 109025087 A CN109025087 A CN 109025087A
- Authority
- CN
- China
- Prior art keywords
- outer tube
- roof
- heat preservation
- inner tube
- rain water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
- E04D13/04—Roof drainage; Drainage fittings in flat roofs, balconies or the like
- E04D13/0404—Drainage on the roof surface
- E04D13/0445—Drainage channels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
- E04D13/16—Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
- E04D13/1687—Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure the insulating material having provisions for roof drainage
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Roof Covering Using Slabs Or Stiff Sheets (AREA)
Abstract
The present invention provide it is a kind of heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method, including roof construction layer, it further include waterproof built-in fitting, the waterproof built-in fitting is fixedly connected on the side wall of roof construction layer, the upper end of the waterproof built-in fitting is nested with outer tube, and the tube wall surface of the outer tube circumferentially offers the equidistant drainage hole of 2~4 rows, and the outer tube is embedded to be cased with inner tube, the top of said inner tube is fixedly connected with snap ring, and the lateral wall of the snap ring is fixedly connected on the top of outer tube.Structure of the invention is simple, easy to operate, and screed and insulating layer ponding are discharged from rain pipe using duct wall aperture, to reduce roofing infiltration probability, solves the problems, such as that current rain pipe cannot exclude screed and insulating layer internal water accumulation.
Description
Technical field
The present invention relates to technical field of building construction, specially a kind of heat preservation is mated formation and rain water on roof pipe drainage arrangement and is applied
Work method.
Background technique
Building roof is generally provided with insulating layer using flat roof deck form at present, and part accessible roof, which is additionally provided with, mats formation
Layer.
With the increase for using the time, rainwater, and concrete cover and waterproof can be put aside in the mortar of mating formation of roofing
Layer can also seep water, so as to cause insulating layer ponding.
But since current rain pipe laying is all that pvc pipe mouth leads to roofing, the ponding in screed and insulating layer without
Method excludes, and accumulating over a long period will lead to waterproof damage layer and then lead to roof leakage.
Summary of the invention
It cannot exclude asking for screed and insulating layer internal water accumulation to solve current rain pipe mentioned above in the background art
Topic, the present invention provide it is a kind of heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method:
A kind of heat preservation, rain water on roof pipe drainage arrangement of mating formation, including roof construction layer further includes waterproof built-in fitting, described
Waterproof built-in fitting is fixedly connected on the side wall of roof construction layer, and the upper end of the waterproof built-in fitting is nested with outer tube, the outer tube
Tube wall surface circumferentially offer the equidistant drainage hole of 2~4 rows, the outer tube is embedded to be cased with inner tube, and the top of said inner tube is solid
Surely it is connected with snap ring, the lateral wall of the snap ring is fixedly connected on the top of outer tube.
Preferably, it is coated with marine glue between the outer tube and snap ring, marine glue is coated between said inner tube and snap ring.
Preferably, the outer tube wall most descends the drainage hole of row and the upper surface of roof construction layer to be in the same plane.
Preferably, the length of said inner tube is 10cm longer than outer length of tube, and the caliber of the outer tube is bigger than the caliber of inner tube
1cm。
Preferably, the aperture of the drainage hole is 2~3mm.
Preferably, it is a kind of heat preservation, rain water on roof pipe drainage arrangement of mating formation construction method, comprising the following steps:
Step 1 buries waterproof built-in fitting in the side wall of roof construction layer;
Step 2, the different PVC mouthpiece of two root canal diameters of interception, as outer tube and inner tube;
Step 3 opens up the equidistant drainage hole of 2~4 rows in the side wall of outer tube;
Inner tube is nested in the inside of outer tube by step 4, installs snap ring on the top of inner and outer tubes, and with waterproof gluing
It connects;
Outer tube, is nested in the top of waterproof built-in fitting by step 5, and with waterproof glue sticking.
Preferably, in step 2, PVC mouthpiece caliber needed for intercepting outer tube is than PVC interface needed for interception inner tube
The big 1cm of pipe caliber, and the length of the inner tube intercepted is than outer pipe range 10cm.
Preferably, in step 3, it most descends the row of row after the drainage hole of the outer tube wall opens up position satisfaction installation
Water hole is flushed with the upper surface of roof construction layer.
It is compared with prior art, the present invention having the following advantages and benefits:
1) heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method, the draining aperture opened up by outer tube wall
Screed and insulating layer internal water accumulation is discharged.
2) roofing water is discharged to rain pipe by inner tube by the heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method
It is interior, it can prevent roofing water from penetrating into insulating layer when being discharged.
Structure of the invention is simple, easy to operate, using duct wall aperture by screed and insulating layer ponding from rain pipe
Discharge solves the problems, such as that current rain pipe cannot exclude screed and insulating layer internal water accumulation to reduce roofing infiltration probability.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention;
Fig. 2 is the structural schematic diagram of outer tube of the invention;
Fig. 3 is the structural schematic diagram of inner tube of the invention;
In figure: 1 outer tube, 2 inner tubes, 3 drainage holes, 4 snap rings, 5 waterproof built-in fittings, 6 roof construction layers.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiments, to the present invention
It is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to
Limit the present invention.
With reference to the accompanying drawing and specific embodiment is further described application principle of the invention.
Embodiment one
A kind of heat preservation as shown in Figure 1 to Figure 3, rain water on roof pipe drainage arrangement of mating formation, including roof construction layer 6, are also wrapped
Waterproof built-in fitting 5 is included, waterproof built-in fitting 5 is fixedly connected on the side wall of roof construction layer 6, and the upper end of waterproof built-in fitting 5 is nested with
Outer tube 1, the tube wall surface of outer tube 1 circumferentially offer the equidistant drainage hole 3 of 2~4 rows, and outer tube 1 is embedded to be cased with inner tube 2, inner tube 2
Top is fixedly connected with snap ring 4, and the lateral wall of snap ring 4 is fixedly connected on the top of outer tube 1.
Wherein, it is coated with marine glue between outer tube 1 and snap ring 4, marine glue, outer tube 1 are coated between inner tube 2 and snap ring 4
Side wall most descends the drainage hole 3 of row and the upper surface of roof construction layer 6 to be in the same plane, and the length of inner tube 2 is than 1 length of outer tube
The caliber of long 10cm, outer tube 1 are 1cm bigger than the caliber of inner tube 2, and the aperture of drainage hole 3 is 2~3mm.
It is a kind of heat preservation, rain water on roof pipe drainage arrangement of mating formation construction method, comprising the following steps:
Step 1 buries waterproof built-in fitting 5 in the side wall of roof construction layer 6;
Step 2, the different PVC mouthpiece of two root canal diameters of interception intercept needed for outer tube 1 as outer tube 1 and inner tube 2
PVC mouthpiece caliber is 1cm bigger than PVC mouthpiece caliber needed for interception inner tube 2, and the length of the inner tube 2 intercepted is longer than outer tube 1
10cm;
Step 3 opens up the equidistant drainage hole 3 of 2~4 rows in the side wall of outer tube 1, and the drainage hole 3 of 1 side wall of outer tube opens up position
It most descends the drainage hole 3 of row to flush with the upper surface of roof construction layer 6 after setting satisfaction installation;
Inner tube 2 is nested in the inside of outer tube 1 by step 4, the top of inner tube 2 and outer tube 1 install snap ring 4, and with prevent
Glue bonding;
Outer tube 1, is nested in the top of waterproof built-in fitting 5 by step 5, and with waterproof glue sticking.
It should be noted that, in this document, the terms "include", "comprise" or its any other variant are intended to non-row
His property includes, so that the process, method, article or equipment for including a series of elements not only includes those elements, and
And further include other elements that are not explicitly listed, or further include for this process, method, article or equipment institute it is intrinsic
Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including institute
State in the process, method, article or equipment of element that there is also other identical elements.
The above is made skilled artisans appreciate that or realizing this hair in specific embodiment party of the invention
It is bright.Various modifications to these embodiments will be apparent to one skilled in the art, as defined herein
General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention
It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one
The widest scope of cause.
Claims (8)
1. a kind of heat preservation, rain water on roof pipe drainage arrangement of mating formation, including roof construction layer (6), which is characterized in that further include waterproof
Built-in fitting (5), the waterproof built-in fitting (5) are fixedly connected on the side wall of roof construction layer (6), the waterproof built-in fitting (5)
Upper end is nested with outer tube (1), and the tube wall surface of the outer tube (1) circumferentially offers the equidistant drainage hole of 2~4 rows (3), described outer
Pipe (1) is embedded to be cased with inner tube (2), and the top of said inner tube (2) is fixedly connected with snap ring (4), and the lateral wall of the snap ring (4) is solid
Surely it is connected to the top of outer tube (1).
2. a kind of heat preservation according to claim 1, rain water on roof pipe drainage arrangement of mating formation, which is characterized in that the outer tube
(1) it is coated with marine glue between snap ring (4), is coated with marine glue between said inner tube (2) and snap ring (4).
3. a kind of heat preservation according to claim 1, rain water on roof pipe drainage arrangement of mating formation, which is characterized in that the outer tube
(1) side wall most descends the drainage hole (3) of row and the upper surface of roof construction layer (6) to be in the same plane.
4. a kind of heat preservation according to claim 1, rain water on roof pipe drainage arrangement of mating formation, which is characterized in that said inner tube
(2) length is 10cm longer than outer tube (1) length, and the caliber of the outer tube (1) is 1cm bigger than the caliber of inner tube (2).
5. a kind of heat preservation according to claim 1, rain water on roof pipe drainage arrangement of mating formation, which is characterized in that the draining
The aperture in hole (3) is 2~3mm.
6. the construction party of a kind of heat preservation, rain water on roof pipe drainage arrangement of mating formation described in any one according to claim 1~5
Method, which comprises the following steps:
Step 1 buries waterproof built-in fitting (5) in the side wall of roof construction layer (6);
Step 2, the different PVC mouthpiece of two root canal diameters of interception, as outer tube (1) and inner tube (2);
Step 3 opens up the equidistant drainage hole of 2~4 rows (3) in the side wall of outer tube (1);
Inner tube (2) is nested in the inside of outer tube (1) by step 4, installs snap ring (4) on the top of inner tube (2) and outer tube (1),
And with waterproof glue sticking;
Outer tube (1), is nested in the top of waterproof built-in fitting (5) by step 5, and with waterproof glue sticking.
7. the construction method of a kind of heat preservation according to claim 6, rain water on roof pipe drainage arrangement of mating formation, feature exist
In in step 2, PVC mouthpiece caliber needed for interception outer tube (1) is than PVC mouthpiece caliber needed for interception inner tube (2)
Big 1cm, and the length of the inner tube (2) intercepted is 10cm longer than outer tube (1).
8. the construction method of a kind of heat preservation according to claim 6, rain water on roof pipe drainage arrangement of mating formation, feature exist
In in step 3, it most descends the drainage hole (3) of row after the drainage hole (3) of outer tube (1) side wall opens up position satisfaction installation
It is flushed with the upper surface of roof construction layer (6).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810871558.5A CN109025087A (en) | 2018-08-02 | 2018-08-02 | It is a kind of heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810871558.5A CN109025087A (en) | 2018-08-02 | 2018-08-02 | It is a kind of heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109025087A true CN109025087A (en) | 2018-12-18 |
Family
ID=64648753
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810871558.5A Pending CN109025087A (en) | 2018-08-02 | 2018-08-02 | It is a kind of heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109025087A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111910946A (en) * | 2020-08-18 | 2020-11-10 | 厦门顶巢建筑修缮研究院有限公司 | Construction method of concrete roof water leakage repairing system |
CN114164914A (en) * | 2021-12-10 | 2022-03-11 | 中国十七冶集团有限公司 | Multifunctional connecting pipe for floor drain structural layer |
CN115142535A (en) * | 2022-07-04 | 2022-10-04 | 中国十七冶集团有限公司 | A multifunctional ground drainage facility for wet rooms |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3234719A1 (en) * | 1982-09-18 | 1984-03-22 | Jens Ing.(grad.) 6458 Rodenbach Drefahl | METHOD AND DEVICE FOR PRODUCING A ROOF CONSTRUCTION |
CN201695582U (en) * | 2010-04-30 | 2011-01-05 | 唐山德生防水材料有限公司 | Double-layer waterproof and double-layer water draining structure for heat-insulating roof |
CN201972324U (en) * | 2010-12-30 | 2011-09-14 | 唐山德生防水材料有限公司 | Double-layer drainage floor drain |
CN203583797U (en) * | 2013-11-04 | 2014-05-07 | 深圳市建工集团股份有限公司 | Invisible drainage connecting device in decorative heat-preserving layer of roof |
CN203716414U (en) * | 2014-02-25 | 2014-07-16 | 中铁建工集团有限公司 | Straight double-layer drainage device |
-
2018
- 2018-08-02 CN CN201810871558.5A patent/CN109025087A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3234719A1 (en) * | 1982-09-18 | 1984-03-22 | Jens Ing.(grad.) 6458 Rodenbach Drefahl | METHOD AND DEVICE FOR PRODUCING A ROOF CONSTRUCTION |
CN201695582U (en) * | 2010-04-30 | 2011-01-05 | 唐山德生防水材料有限公司 | Double-layer waterproof and double-layer water draining structure for heat-insulating roof |
CN201972324U (en) * | 2010-12-30 | 2011-09-14 | 唐山德生防水材料有限公司 | Double-layer drainage floor drain |
CN203583797U (en) * | 2013-11-04 | 2014-05-07 | 深圳市建工集团股份有限公司 | Invisible drainage connecting device in decorative heat-preserving layer of roof |
CN203716414U (en) * | 2014-02-25 | 2014-07-16 | 中铁建工集团有限公司 | Straight double-layer drainage device |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111910946A (en) * | 2020-08-18 | 2020-11-10 | 厦门顶巢建筑修缮研究院有限公司 | Construction method of concrete roof water leakage repairing system |
CN111910946B (en) * | 2020-08-18 | 2022-04-05 | 厦门顶巢建筑修缮研究院有限公司 | Construction method of concrete roof water leakage repairing system |
CN114164914A (en) * | 2021-12-10 | 2022-03-11 | 中国十七冶集团有限公司 | Multifunctional connecting pipe for floor drain structural layer |
CN115142535A (en) * | 2022-07-04 | 2022-10-04 | 中国十七冶集团有限公司 | A multifunctional ground drainage facility for wet rooms |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109025087A (en) | It is a kind of heat preservation, mat formation rain water on roof pipe drainage arrangement and construction method | |
KR20100025172A (en) | Draining trap for building floor | |
CN103790181A (en) | Daylight illumination device pier base and manufacturing method thereof | |
KR20210071549A (en) | Outside Insulation And Waterproof Member for Underground Structure And Method for Constructing the Same | |
CN209924297U (en) | Breather pipe leak protection subassembly and breather pipe joint | |
CN113863582A (en) | Inverted roof structure and construction method thereof | |
CN209855082U (en) | Water retaining joint of ventilation pipeline | |
CN110905053A (en) | Construction method for indoor drainage pipeline penetrating through floor slab | |
CN212156084U (en) | Pre-buried antiseep PVC drainage sleeve | |
CN208456124U (en) | A kind of drainage pipeline passes through the pre-embedded device of floor | |
CN211472901U (en) | Composite heat insulation system with embedded part | |
CN112628477A (en) | Drain pipe pre-embedding device with stretching and water drainage preventing functions and installation method | |
CN211058162U (en) | Mounting structure of pre-buried electric wire tube in building roof | |
CN218091374U (en) | Anti-leakage device for heat-preservation nail | |
CN207064863U (en) | A kind of new waterproof sleeve pipe | |
CN113389258A (en) | Concealed water collecting and draining structure on floor of shower room | |
CN210508099U (en) | Waterproof node structure of roofing pipe in water | |
CN102352675B (en) | Roofing eave waterproof structure | |
CN111779157A (en) | Underground outdoor wall structure and construction method thereof | |
CN213233841U (en) | Receiving piece for preventing leakage of sewer position | |
CN204826160U (en) | Balcony surface drainage mouth structure | |
CN109811972B (en) | Breather pipe joint and leak-proof assembly | |
CN210049496U (en) | Waterproof improvement node structure of roofing pipe in water | |
CN105239732A (en) | Extension roof pipe for preventing rainwater leakage and construction method thereof | |
CN219691169U (en) | Waterproof light wear-resisting protective layer structure of roofing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181218 |
|
RJ01 | Rejection of invention patent application after publication |