CN108979172A - A kind of conveyer belt replaces the constructing structure of construction elevator - Google Patents
A kind of conveyer belt replaces the constructing structure of construction elevator Download PDFInfo
- Publication number
- CN108979172A CN108979172A CN201811057663.1A CN201811057663A CN108979172A CN 108979172 A CN108979172 A CN 108979172A CN 201811057663 A CN201811057663 A CN 201811057663A CN 108979172 A CN108979172 A CN 108979172A
- Authority
- CN
- China
- Prior art keywords
- conveyer belt
- delivery section
- replaces
- construction elevator
- constructing structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/162—Handles to carry construction blocks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Structure Of Belt Conveyors (AREA)
Abstract
The invention discloses the constructing structures that a kind of conveyer belt replaces construction elevator, it is related to the realm of building construction, its drip irrigation device includes the transmission device being arranged between a flooring and second floor floor, and the transmission device includes horizontally disposed the first transmission segment, the second delivery section being obliquely installed and the second delivery section being horizontally set on second floor floor on the ground.Loading and unloading are carried out by the conveyer belt of setting, not only reduce construction cost, reduce artificial, and it is more preferably flexible to construct, can be mobile and lay with the need, substantially increase construction efficiency.
Description
Technical field
The present invention relates to a kind of the realm of building construction, more particularly to a kind of conveyer belt replaces the construction of construction elevator
Structure.
Background technique
Architectural engineering generally removes tower crane after the completion of main structure, secondary structure and the material slightly fitted up, small-sized
Equipment conveying usually uses outdoor elevators to solve.
Harbin Taiping international airport former arrangement and method for construction fall into a trap delineating set six construction elevators transport two layers of masonry and
Mortar.The floor of airport building engineering is not high, and periphery is longer, multi-section elevator higher cost is arranged, and outdoor elevators easily occur
Safety accident.
In addition, this engineering plane is reported to the leadship after accomplishing a task simultaneously, operation is more, secondary structure engineering, overhead bridge construction, curtain wall, steel construction, room
Each profession such as outside ductwork is constructed simultaneously, and the arrangement of construction elevator is due to giving construction material conveyer belt many not with stationarity
Just, the last closing of tube net outside and building curtain wall is especially influenced.At the same time, it constructs when in different job locations
When, it is also necessary to additionally mounted construction elevator, not so material traveling time is too long, therefore construction elevator is repeatedly arranged, and increases construction
Cost now provides the constructing structure that a kind of conveyer belt replaces construction elevator.
Summary of the invention
In view of the deficiencies of the prior art, the present invention intends to provide a kind of conveyer belt applying instead of construction elevator
Work structure carries out loading and unloading by the conveyer belt of setting, not only reduces construction cost, reduce manually, and it is more preferably clever to construct
Work can move and lay with the need, substantially increase construction efficiency.
To achieve the above object, the present invention provides the following technical scheme that
A kind of conveyer belt replaces the constructing structure of construction elevator, including the transmission dress being arranged between a flooring and second floor floor
It sets, the second delivery section and level that the transmission device includes horizontally disposed the first transmission segment on the ground, is obliquely installed
The second delivery section on second floor floor is set.
By using above-mentioned technical proposal, by the transmission device of setting, feeding is carried out in the first delivery section, passes through second
Delivery section carries out feeding, then carries out blanking in third delivery section, with the above arrangement, material can be carried out continuing feeding,
Difference feeding can be carried out to different materials of applying, at the same time, compare and construction elevator, not only reduce construction cost, subtract
Lack manually, and it is more preferably flexible to construct, can move and lay with the need, substantially increase construction efficiency.
Preferably, the transmission device includes rack, the rotating roller being rotatably arranged in rack and is socketed in rotating roller
On conveyer belt, wherein rotating roller is each provided with one at the both ends of the first delivery section, the second delivery section and third delivery section respectively
Group is provided with the first pressure holding component in second delivery section and third conveyer belt junction, and the first pressure holding component is located at
Below the conveyer belt;The driving motor for driving that wherein a rotating roller is rotated is provided in the rack.
Material can be passed by using above-mentioned technical proposal by the way that conveyer belt, rotating roller, driving motor is arranged
It send, there is Stall to be moved to second floor material, when construction, different material can be placed in different conveyer belt sections, be divided
Transmission is opened, construction is more preferably convenient, at the same time, can continue to carry out feeding, construct more preferably quick.
Preferably, the conveyer belt is arranged at intervals with partition along its length, strip length is transmitted described in the divider upright
Direction, and striker plate is fixedly installed along the two sides of the conveyer belt length direction;The striker plate and partition surround bearing material chamber
Room, the striker plate are elastic construction.
By using above-mentioned technical proposal, by the partition and baffle of setting, it is in different bearing material chambers that conveyer belt, which is enclosed,
Room can charge to material in bearing material chamber, so that material, when moving up and down, position is relatively stable, without departing from
Conveyer belt is avoided and is caused danger.
Preferably, the bearing material chamber length is 60cm-80cm, width 40cm-50cm, it is highly 25cm-40cm.
By using above-mentioned technical proposal, with the above arrangement, both can be to various secondary structure materials in the work progress
Material is transported, while small volume, facilitates carry out loading and unloading.
Preferably, the two sides of the conveyer belt length direction and being located at the two sides that are located remotely from each other of two pieces of striker plates and being installed with pressure
Side is provided with the second pressure holding group pressed to flanging in the rack between the first delivery section and the second delivery section
Part.
By using above-mentioned technical proposal, the two sides of conveyer belt can be pressed, be made by the pressure holding component of setting
It is more preferably stable in moving process to obtain conveyer belt.
Preferably, the first pressure holding component and the second pressure holding modular construction are identical, it all include being rotatably connected on rack two sidewalls
On compressor arm, be vertically fixed on compressor arm free end rotation axis, socket pressing roller on the rotating shaft, the pressing roller can
It is crimped in the flanging;It is connected with extension spring between the compressor arm and rack, so that the pressing roller is kept and pressure
The impaction state on side.
By using above-mentioned technical proposal, elastic pressure holding is carried out to conveyer belt by the pressing roller of setting, so that conveyer belt
Fitting can either be kept in transmit process on the rack, while will not be mobile because of the excessive influence conveyer belt of press force.
Preferably, being provided with several bearing material buckets on the conveyer belt.
Blowing can be carried out in bearing material bucket by the bearing material bucket of setting by using above-mentioned technical proposal, thus, on
When blanking, only bearing material bucket is operated, so that loading and unloading are more preferably quick, improves construction efficiency.
Preferably, the bearing material bucket includes hopper and is fixed on the upside of hopper and carries out hanging the discharge arm connect to it, it is described
Discharge arm is " U "-shaped, is fixed on above the hopper.
It can more preferably facilitate and bearing material bucket is operated by the way that discharge arm is arranged by using above-mentioned technical proposal.
It is unloaded preferably, being provided on the conveyer belt and positioned at third delivery section end and carrying out undertaking discharging to bearing material bucket
Expect device.
Automatic discharging can be carried out to bearing material bucket by the device for discharging of setting by using above-mentioned technical proposal, so that
Bearing material bucket is detached from conveyer belt, thus, allow conveyer belt to continue to transport material.
Preferably, the device for discharging includes chassis, horizontally rotates along vertical axes support rod, Yi Jishui above chassis
The flat several blanking bars for being fixed on supporting bar top, are provided with splicing bar in the free end of the blanking bar, the splicing bar is in
Skewed upwards and lower close to one end of blanking bar, the higher one end of splicing bar is located at third delivery section end, and is located at low
In the height of the discharge arm.
By using above-mentioned technical proposal, with the above arrangement, splicing bar is turned under third delivery section in discharging
Material mouth position can be socketed in splicing bar, when so that bearing material bucket is mobile by being obliquely installed for splicing bar, so that bearing material bucket
It can be slid downwardly on blanking bar, it, can be with rotary supporting rod, so that another blanking bar is connect when there is multiple bearing material frames
Material, meanwhile, blanking is carried out to the bearing material bucket on blanking bar.It realizes the lasting blanking to bearing material bucket, avoids artificial blanking, so that
The blanking time is more preferably sufficient, and conveyer belt feeding is more preferably coherent, substantially increases construction efficiency.
In conclusion the invention has the following advantages:
1, by the transmission device of setting, feeding is carried out in the first delivery section, feeding is carried out by the second delivery section, then the
Three delivery sections carry out blanking, with the above arrangement, can carry out continuing feeding to material, can carry out area to different materials of applying
Other feeding is compared and construction elevator at the same time, not only reduces construction cost, reduces artificial, and it is more preferably flexible to construct,
It can move and lay with the need, substantially increase construction efficiency;
2, by the partition of setting and baffle, it is in different bearing material chambers that conveyer belt, which is enclosed, can be to object in bearing material chamber
Material charges, so that material, when moving up and down, position is relatively stable, without departing from conveyer belt, avoids and causes danger;
3, elastic pressure holding is carried out to conveyer belt by the pressing roller of setting, so that conveyer belt can either keep pasting in transmit process
It closes on the rack, while will not be mobile because of the excessive influence conveyer belt of press force;
4, the lasting blanking to bearing material bucket is realized by device for discharging, avoids artificial blanking, so that the blanking time is more preferably sufficient,
Conveyer belt feeding is more preferably coherent, substantially increases construction efficiency.
Detailed description of the invention
Fig. 1 is replaced the overall structure diagram of the constructing structure of construction elevator by a kind of conveyer belt;
Fig. 2 is replaced the schematic diagram of prominent conveyer structure in the constructing structure of construction elevator by a kind of conveyer belt;
Fig. 3 is replaced the schematic diagram of prominent pressure holding component in the constructing structure of construction elevator by a kind of conveyer belt;
Fig. 4 is replaced the schematic diagram of prominent device for discharging in the constructing structure of construction elevator by a kind of conveyer belt.
Appended drawing reference: a 1, flooring;2, second floor floor;3, transmission device;31, the first delivery section;32, the second transmission
Section;33, third delivery section;34, rack;35, rotating roller;36, conveyer belt;361, flanging;362, partition;363, striker plate;
364, bearing material chamber;37, driving motor;38, the first pressure holding component;39, the second pressure holding component;391, compressor arm;392, it rotates
Axis;393, pressing roller;394, extension spring;4, bearing material bucket;41, hopper;42, discharge arm;5, device for discharging;51, chassis;52,
Support rod;53, blanking bar;54, splicing bar.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail, wherein the identical appended drawing reference of identical components
It indicates.It should be noted that word "front", "rear" used in the following description, "left", "right", "up" and "down", " bottom surface " and
" top surface " refers to that the direction in attached drawing, word "inner" and "outside" are referred respectively to towards or away from geometric center of specific component
Direction.
A kind of conveyer belt replaces the constructing structure of construction elevator, as shown in Figure 1, including being arranged in a flooring 1 and second floor
Transmission device 3 between floor 2, transmission device 3 include horizontally disposed the first delivery section 31 on the ground, are obliquely installed
The second delivery section 32 between one flooring 1 and second floor floor 2 and the third delivery section being horizontally set on second floor floor 2
33.When being constructed, feeding is carried out at 31 position of the first delivery section and is passed material by the transmission of the second delivery section 32
It send to progress discharging at the second delivery section 32.
Referring to figs. 1 and 2, transmission device 3 include rack 34, be rotatably arranged in rack 34 rotating roller 35, with
And it is socketed in the conveyer belt 36 in rotating roller 35, wherein rotating roller 35 is passed in the first delivery section 31, the second delivery section 32 and third
It send the both ends of section 33 to be each provided with one group respectively, drives conveyer belt 36 to be transmitted by the rotating roller 35 of setting, at the same time,
The driving motor 37 for driving that wherein a rotating roller 35 is rotated is fixedly installed in rack 34.
In conjunction with shown in Fig. 1 and Fig. 3, in the lower section of 33 cohesive position of the second delivery section 32 and third delivery section, there are one
Turning is easy to produce hanging when conveyer belt 36 is moved to the position, therefore in rack 34 and is located at the second delivery section 32 and the
It is disposed below between three delivery sections 33 and is provided with the first pressure holding component 38, wherein the first pressure holding component 38 is located at conveyer belt 36
Lower section, conveyer belt 36 is supported by lower section so that conveyer belt 36 transmission when keep tensioned state.
In the construction process, in order to enable conveyer belt 36 is more preferably stable in transmit process, in 36 length direction of conveyer belt
Two sides be provided with flanging 361, the second pressure holding component 39 pressed to flanging 361 is provided in rack 34, wherein the
Two pressure holding components 39 are arranged between the first delivery section 31 and the second delivery section 32, thus, it prevents in 36 position of conveyer belt
Conveyer belt 36 floats.
First pressure holding component 38 is identical with the second pressure holding 39 structure of component, all includes being rotatably connected on 34 two sidewalls of rack
Compressor arm 391, the rotation axis 392 for being vertically fixed on 391 free end of compressor arm, the pressing roller being socketed in rotation axis 392
393, pressing roller 393 can be crimped in the flanging 361;Extension spring 394 is connected between compressor arm 391 and rack 34,
So that pressing roller 393 keeps the impaction state with flanging 361.
In the construction process, in order to transport to construction material material, interval fixation along its length is set on conveyer belt 36
It is equipped with partition 362, wherein 362 vertical conveyors of partition, 36 surface, and the length direction of 362 plane vertical conveyors 36 of partition.
At the same time, it is fixedly installed striker plate 363 in the two sides of 36 length direction of conveyer belt, it will by striker plate 363 and partition 362
The segmentation of conveyer belt 36 can place some construction materials when in use in several bearing material chambers 364 in bearing material chamber 364.Its
In, striker plate 363 is elastic construction, can be rotated together with conveyer belt 36.
It should be noted that striker plate 363 is located at two pieces of flanging, 361 inside.Further, in order to meet site operation
The length of demand, bearing material chamber 364 is 60cm-80cm, width 40cm-50cm, is highly 25cm-40cm.By setting above
It sets, various secondary structure materials can both be transported in the work progress, while small volume, facilitate carry out loading and unloading.
Further, discharging is carried out for convenience, accelerates construction progress, several bearing material buckets are placed on conveyer belt 36
414, in feeding, preferentially then bearing material bucket 414 is placed on conveyer belt 36 and is passed in bearing material bucket 414 by material
It send, when blanking, directly removes bearing material bucket 414.
As shown in figure 4, bearing material bucket 414 includes hopper 41 and is fixed on the upside of hopper 41 and carries out hanging the discharging connect to it
Bar 42, wherein discharge arm 42 is " U "-shaped, is fixed on 41 top of hopper.
Discharging is carried out to bearing material bucket 414 in third delivery section 33 for convenience, is provided with and unloads in 33 end of third delivery section
Expect device 5, it can be by the mobile lower conveyor belt 36 of bearing material bucket 414 by device for discharging 5.By the device, construction is substantially reduced
Labor intensity.
Device for discharging 5 includes chassis 51, horizontally rotates along vertical axes support rod 52 chassis 51 above and horizontal consolidate
Be scheduled on several blanking bars 53 on 52 top of support rod, the free end of blanking bar 53 be provided with splicing bar 54, splicing bar 54 be in
Upper skewed and lower close to one end of blanking bar 53, the higher one end of splicing bar 54 is located at 33 end of third delivery section, and position
In lower than the height for expecting bar.When in use, splicing bar 54 is turned into 33 feed opening position of third delivery section, so that holding
When hopper 414 is mobile, can be socketed in splicing bar 54, by being obliquely installed for splicing bar 54, allow bearing material bucket 414 to
It, can be with rotary supporting rod 52, so that another blanking bar 53 is connect when there is multiple bearing material frames on lower slide-in blanking bar 53
Material, meanwhile, blanking is carried out to the bearing material bucket 414 on blanking bar 53.
By the transmission device 3 and device for discharging 5 of setting, cost is not only reduced, is reduced manually, and flexibly, it can be with need
It wants and mobile and laying, substantially increases construction efficiency.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, those skilled in the art
Member can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as at this
All by the protection of Patent Law in the scope of the claims of invention.
Claims (10)
1. the constructing structure that a kind of conveyer belt replaces construction elevator, it is characterised in that: including being arranged in a flooring (1) and second floor
Transmission device (3) between floor (2), the transmission device (3) include horizontally disposed the first delivery section (31) on the ground,
The second delivery section (32) being obliquely installed and the second delivery section (32) being horizontally set on second floor floor (2).
2. conveyer belt according to claim 1 replaces the constructing structure of construction elevator, it is characterized in that: the transmission device
It (3) include rack (34), the rotating roller (35) being rotatably arranged on rack (34) and the transmission being socketed on rotating roller (35)
Band (36), wherein rotating roller (35) is at the both ends of the first delivery section (31), the second delivery section (32) and third delivery section (33) point
It is not each provided with one group, second delivery section (32) and third conveyer belt (36) junction are provided with the first pressure holding component
(38), first pressure holding component (38) is located at below the conveyer belt (36);It is provided on the rack (34) and drives it
In the driving motor (37) that is rotated of a rotating roller (35).
3. conveyer belt according to claim 2 replaces the constructing structure of construction elevator, it is characterized in that: the conveyer belt (36)
It is arranged at intervals with along its length partition (362), vertical conveyer belt (36) length direction of the partition (362), and along institute
The two sides for stating conveyer belt (36) length direction are fixedly installed striker plate (363);The striker plate (363) and partition (362) enclose
At bearing material chamber (364), the striker plate (363) is elastic construction.
4. conveyer belt according to claim 3 replaces the constructing structure of construction elevator, it is characterized in that: the bearing material chamber
(364) length is 60cm-80cm, width 40cm-50cm, is highly 25cm-40cm.
5. conveyer belt according to claim 2 replaces the constructing structure of construction elevator, it is characterized in that: the conveyer belt (36)
The two sides of length direction and it is located at the two sides that are located remotely from each other of two pieces of striker plates (363) and is installed with flanging (361), in the rack
(34) the second pressure pressed to flanging (361) is provided between the first delivery section (31) and the second delivery section (32)
Hold component (39).
6. conveyer belt according to claim 5 replaces the constructing structure of construction elevator, it is characterized in that: the first pressure holding component
(38) with second pressure holding component (39) structure it is identical, all include be rotatably connected on rack (34) two sidewalls compressor arm (391),
The rotation axis (392) for being vertically fixed on compressor arm (391) free end, the pressing roller (393) being socketed on rotation axis (392), institute
Stating pressing roller (393) can be crimped on the flanging (361);Drawing is connected between the compressor arm (391) and rack (34)
Spring (394) are stretched, so that the pressing roller (393) keeps the impaction state with flanging (361).
7. conveyer belt according to claim 2 replaces the constructing structure of construction elevator, it is characterized in that: the conveyer belt (36)
On be provided with several bearing material buckets (41).
8. conveyer belt according to claim 7 replaces the constructing structure of construction elevator, it is characterized in that: the bearing material bucket (41)
It including hopper (41) and is fixed on the upside of hopper (41) it is carried out to hang the discharge arm connect (42), the discharge arm (42) is in
" u "-shaped is fixed on above the hopper (41).
9. conveyer belt according to claim 7 replaces the constructing structure of construction elevator, it is characterized in that: the conveyer belt (36)
It is provided with above and positioned at third delivery section (33) end the device for discharging (5) for accept to bearing material bucket (41) discharging.
10. conveyer belt according to claim 9 replaces the constructing structure of construction elevator, it is characterized in that: the device for discharging
(5) include chassis (51), horizontally rotate the support rod (52) above chassis (51) along vertical axes and be horizontally fixed on support
Several blanking bars (53) on bar (52) top are provided with splicing bar (54), the splicing in the free end of the blanking bar (53)
Bar (54) is in skewed upwards, and the one end of close blanking bar (53) is lower, and splicing bar (54) higher one end is located at third biography
Section (33) end is sent, and is located at the height lower than the discharge arm (42).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811057663.1A CN108979172B (en) | 2018-09-11 | 2018-09-11 | Construction structure with conveyor belt replacing construction elevator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811057663.1A CN108979172B (en) | 2018-09-11 | 2018-09-11 | Construction structure with conveyor belt replacing construction elevator |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108979172A true CN108979172A (en) | 2018-12-11 |
CN108979172B CN108979172B (en) | 2020-11-17 |
Family
ID=64545401
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811057663.1A Active CN108979172B (en) | 2018-09-11 | 2018-09-11 | Construction structure with conveyor belt replacing construction elevator |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108979172B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109797973A (en) * | 2019-02-25 | 2019-05-24 | 余杏花 | A kind of building iron structure transporting equipment |
CN110403207A (en) * | 2019-07-19 | 2019-11-05 | 福建省全味食品有限公司 | A nut shelling machine |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3298117A (en) * | 1964-09-26 | 1967-01-17 | Beteiligungs & Patentverw Gmbh | Transloading device, especially bucket wheel transloading device |
JPH08225124A (en) * | 1995-02-22 | 1996-09-03 | Taisei Corp | Belt conveyor equipment |
JP2738254B2 (en) * | 1993-01-27 | 1998-04-08 | 株式会社イナックス | How to bring in the unit room |
EP1279780A2 (en) * | 2001-07-24 | 2003-01-29 | Campbell Thomas Wallace | Handling device |
CN201353565Y (en) * | 2009-01-08 | 2009-12-02 | 浙江天煌科技实业有限公司 | Device for sorting finished products and waste products |
CN203381046U (en) * | 2013-07-31 | 2014-01-08 | 冯承龙 | Bucket-wheel-type feeder |
CN203936365U (en) * | 2014-07-16 | 2014-11-12 | 台州市全顺车辆配件有限公司 | A kind of conveyer |
CN204676909U (en) * | 2015-06-08 | 2015-09-30 | 尤祖材 | A kind of liftable pouring formula brick and tile conveyer |
CN205444943U (en) * | 2016-03-25 | 2016-08-10 | 重庆电子工程职业学院 | Construction is with platform of unloading |
CN105971293A (en) * | 2016-05-24 | 2016-09-28 | 江苏建筑职业技术学院 | High-rise building hydraulic discharging platform device and operating method thereof |
CN106241296A (en) * | 2016-09-27 | 2016-12-21 | 东莞市联洲知识产权运营管理有限公司 | A kind of shoemaking charging basket conveyer device |
CN107008657A (en) * | 2017-05-11 | 2017-08-04 | 东莞市世通国际快件监管中心有限公司 | A kind of logistics sorts platform |
CN206581619U (en) * | 2017-03-07 | 2017-10-24 | 马锦灿 | A kind of construction discharging platform |
CN207030187U (en) * | 2017-05-24 | 2018-02-23 | 朱涛涛 | A kind of anti-deviation constant pressure pinch roller |
CN207142072U (en) * | 2017-09-08 | 2018-03-27 | 广州市威士环保科技有限公司 | A kind of high inclination-angle elevator |
-
2018
- 2018-09-11 CN CN201811057663.1A patent/CN108979172B/en active Active
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3298117A (en) * | 1964-09-26 | 1967-01-17 | Beteiligungs & Patentverw Gmbh | Transloading device, especially bucket wheel transloading device |
JP2738254B2 (en) * | 1993-01-27 | 1998-04-08 | 株式会社イナックス | How to bring in the unit room |
JPH08225124A (en) * | 1995-02-22 | 1996-09-03 | Taisei Corp | Belt conveyor equipment |
EP1279780A2 (en) * | 2001-07-24 | 2003-01-29 | Campbell Thomas Wallace | Handling device |
CN201353565Y (en) * | 2009-01-08 | 2009-12-02 | 浙江天煌科技实业有限公司 | Device for sorting finished products and waste products |
CN203381046U (en) * | 2013-07-31 | 2014-01-08 | 冯承龙 | Bucket-wheel-type feeder |
CN203936365U (en) * | 2014-07-16 | 2014-11-12 | 台州市全顺车辆配件有限公司 | A kind of conveyer |
CN204676909U (en) * | 2015-06-08 | 2015-09-30 | 尤祖材 | A kind of liftable pouring formula brick and tile conveyer |
CN205444943U (en) * | 2016-03-25 | 2016-08-10 | 重庆电子工程职业学院 | Construction is with platform of unloading |
CN105971293A (en) * | 2016-05-24 | 2016-09-28 | 江苏建筑职业技术学院 | High-rise building hydraulic discharging platform device and operating method thereof |
CN106241296A (en) * | 2016-09-27 | 2016-12-21 | 东莞市联洲知识产权运营管理有限公司 | A kind of shoemaking charging basket conveyer device |
CN206581619U (en) * | 2017-03-07 | 2017-10-24 | 马锦灿 | A kind of construction discharging platform |
CN107008657A (en) * | 2017-05-11 | 2017-08-04 | 东莞市世通国际快件监管中心有限公司 | A kind of logistics sorts platform |
CN207030187U (en) * | 2017-05-24 | 2018-02-23 | 朱涛涛 | A kind of anti-deviation constant pressure pinch roller |
CN207142072U (en) * | 2017-09-08 | 2018-03-27 | 广州市威士环保科技有限公司 | A kind of high inclination-angle elevator |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109797973A (en) * | 2019-02-25 | 2019-05-24 | 余杏花 | A kind of building iron structure transporting equipment |
CN110403207A (en) * | 2019-07-19 | 2019-11-05 | 福建省全味食品有限公司 | A nut shelling machine |
Also Published As
Publication number | Publication date |
---|---|
CN108979172B (en) | 2020-11-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205990775U (en) | A kind of automatic wall building machine | |
CN107013043B (en) | Sizing machine and sizing method for uniformly coating mortar on vertical surface and upper surface of brick | |
CN205637638U (en) | Automatic brick -laying machine of flowing water construction | |
CN105453943B (en) | The supporting matrix automatic paver of high-level cultivating | |
CN105883413A (en) | Intelligent glass storage system | |
CN108979172A (en) | A kind of conveyer belt replaces the constructing structure of construction elevator | |
CN203939223U (en) | Machine and control system thereof are built in a kind of spray | |
CN109928237A (en) | A kind of intelligent environment protection grain face cleaning screen | |
CN109577665B (en) | Bricklaying machine | |
CN103758332B (en) | A kind of spray building machine and control system thereof | |
CN208294016U (en) | A kind of building plastering device | |
CN110510331A (en) | A kind of high level curtain wall plate automation promotion vertical feeding equipment | |
CN111924486A (en) | Wall brick transportation equipment for building indoor wall surface construction and use method | |
CN218708966U (en) | Quick loading device for pipes | |
CN113460661A (en) | Brick transfer system for building | |
CN210619365U (en) | Paper tube conveying device | |
CN204822899U (en) | Slide is carried to portable high -rise storehouse material | |
CN214615505U (en) | Platform discharge apparatus for construction | |
CN114352020B (en) | BIM-based distribution device for high-rise building | |
CN211028291U (en) | Device for cutting and arranging aluminum tubes | |
CN113428683B (en) | Plate and belt composite bulk material ship loader | |
CN107901972A (en) | A kind of engineering cart that can be shoveled sand automatically and unload sand | |
CN210794746U (en) | Loading attachment for building | |
CN116025183A (en) | Integrated automatic wall building robot | |
CN211140882U (en) | Drum type discharging device for pneumatically conveying materials |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |