[go: up one dir, main page]

CN108952728A - A kind of headframe main body construction and self well digging freeze parallel construction system and method - Google Patents

A kind of headframe main body construction and self well digging freeze parallel construction system and method Download PDF

Info

Publication number
CN108952728A
CN108952728A CN201810799130.4A CN201810799130A CN108952728A CN 108952728 A CN108952728 A CN 108952728A CN 201810799130 A CN201810799130 A CN 201810799130A CN 108952728 A CN108952728 A CN 108952728A
Authority
CN
China
Prior art keywords
construction
freezing
shaft
well
well tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810799130.4A
Other languages
Chinese (zh)
Other versions
CN108952728B (en
Inventor
雷成祥
刘结高
李晓斌
朱先龙
蒋华云
钱立云
丁晶
黎明镜
刘小虎
何红卫
荣晓光
朱翔斌
蔡士云
王家宝
陈建
纪磊
王�锋
刘安朝
郑东
李启龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inner Mongolia Yin Hong Energy Development Co Ltd
Ordos Huaxing Energy Co Ltd
Ordos Zhongbei Coal Chemical Industry Co Ltd
Huai Mine West Coal Mine Cci Capital Ltd
Anhui University of Science and Technology
Original Assignee
Inner Mongolia Yin Hong Energy Development Co Ltd
Ordos Huaxing Energy Co Ltd
Ordos Zhongbei Coal Chemical Industry Co Ltd
Huai Mine West Coal Mine Cci Capital Ltd
Anhui University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inner Mongolia Yin Hong Energy Development Co Ltd, Ordos Huaxing Energy Co Ltd, Ordos Zhongbei Coal Chemical Industry Co Ltd, Huai Mine West Coal Mine Cci Capital Ltd, Anhui University of Science and Technology filed Critical Inner Mongolia Yin Hong Energy Development Co Ltd
Priority to CN201810799130.4A priority Critical patent/CN108952728B/en
Publication of CN108952728A publication Critical patent/CN108952728A/en
Application granted granted Critical
Publication of CN108952728B publication Critical patent/CN108952728B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/10Preparation of the ground
    • E21D1/12Preparation of the ground by freezing
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/11Lining shafts; Linings therefor with combinations of different materials, e.g. wood, metal, concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

本发明提一种井塔主体施工与井筒掘砌、冻结平行施工系统及方法,平行施工系统包括冻结系统、井塔施工系统和井筒掘砌系统;冻结系统设置在井筒外围四周;冻结系统包括冻结管,冻结管邻近井筒周向设置,多个冻结管组成圆形冻结管幕;井塔施工系统位于井筒掘砌系统上方;井塔施工系统包括井塔框架,井塔框架设有第一层平台和第二层平台;井筒掘砌系统位于冻结系统上方;井筒掘砌系统包括井筒浇筑系统;井筒浇筑系统设置在井塔框架上;本发明采用井塔施工系统、井筒掘砌施工系统和冻结施工系统平行布置的方式,在井塔主体施工的同时可以对井筒掘砌施工和对冻结施工;缩短了施工工期,填补了高寒地区井塔、井筒冻结、掘砌交叉平行快速施工的空白。

The invention provides a parallel construction system and method for well tower main body construction, shaft digging, and freezing. The parallel construction system includes a freezing system, a well tower construction system, and a shaft digging system; the freezing system is arranged around the periphery of the shaft; the freezing system includes freezing The freezing pipes are arranged in the circumferential direction of the wellbore, and multiple freezing pipes form a circular freezing pipe curtain; the well tower construction system is located above the wellbore excavation system; the well tower construction system includes the well tower frame, and the well tower frame is equipped with a first-floor platform and the second floor platform; the shaft excavation system is located above the freezing system; the shaft excavation system includes the shaft pouring system; the shaft pouring system is arranged on the shaft tower frame; the invention adopts the shaft tower construction system, shaft excavation construction system and freezing construction The parallel arrangement of the system enables excavation and masonry construction of the shaft and freezing construction while the main body of the shaft tower is being constructed; the construction period is shortened, and the blank of parallel and rapid construction of the shaft tower, shaft freezing, and excavation and masonry crossing in the alpine region is filled.

Description

一种井塔主体施工与井筒掘砌、冻结平行施工系统及方法A parallel construction system and method for the construction of the main body of the shaft tower and the excavation and laying of the shaft, and freezing

技术领域technical field

本发明属于矿山建设领域,具体涉及一种井塔主体施工与井筒掘砌、冻结平行施工系统及方法。The invention belongs to the field of mine construction, and in particular relates to a parallel construction system and method for shaft tower main body construction, shaft excavation, and freezing.

背景技术Background technique

煤矿立井建设在表土段一般采用冻结法施工,基岩段采用普通凿井法。冻结段外壁掘砌和基岩段掘砌均采用短段掘砌混合作业法,内壁采用滑模法施工。在建井初期,井架或井塔施工、地层冻结造孔、立井掘砌提升设备布置等多个工序集中在井口附近,常规方案顺序及占用工期为:井塔桩基施工(不少于1.5个月)→井口打地层冻结孔(约2.5个月)→井塔桩基承台施工 (约0.5个月)→冻结沟槽施工(约0.3个月)→井塔施工(约6个月)→布置临时凿井设施(约1.2个月)→立井掘砌;累计工期占用时间长,尤其是高寒地区建井,如北方地区最低温度可达-36℃,不适合用钢结构井架,需要施工钢筋混凝土剪力墙结构井塔,基础多设计为大体积钢筋砼+钻孔灌注桩形式,由此引起工期通常在12月以上。The coal mine vertical shaft construction generally adopts the freezing method in the topsoil section, and the ordinary sinking method is used in the bedrock section. Both the excavation and masonry of the outer wall of the frozen section and the excavation of the bedrock section adopt the short section excavation and masonry mixed operation method, and the inner wall is constructed by the sliding form method. In the early stage of well construction, many processes such as derrick or well tower construction, ground freezing hole making, vertical shaft excavation and masonry lifting equipment arrangement are concentrated near the wellhead. months)→Drilling holes for formation freezing at the wellhead (about 2.5 months)→Construction of pile foundation caps for well towers (about 0.5 months)→Construction of frozen trenches (about 0.3 months)→Construction of well towers (about 6 months)→ Arrange temporary sinking facilities (about 1.2 months) → vertical shaft digging; the cumulative construction period takes a long time, especially for well construction in alpine regions. For example, the lowest temperature in northern regions can reach -36°C. It is not suitable for steel structure derricks, and construction reinforcement is required For well towers with concrete shear wall structure, the foundation is usually designed in the form of large-volume reinforced concrete + bored piles, and the resulting construction period is usually more than 12 months.

井塔结构安全的前提是井塔地基,基础必须具有足够的承载能力抵御自身静荷载和外部动荷载。在冻结法建井过程中,尤其要考虑到冻胀、融沉引起的井塔基础不均匀抬升、沉降所造成井塔各种形式的破坏,影响矿井提升和安全生产。永久井塔环境适应性较强,但其最明显的缺点就是占用筹备期时间长,凿井设施安装工序较复杂,特别是冻结工程准备工作多、冻结沟槽施工占用井口附近时间长,如果要缩短工期,则井塔、井筒冻结、立井掘砌必须实现交叉平行施工。The prerequisite for the safety of the well tower structure is the well tower foundation, which must have sufficient bearing capacity to resist its own static load and external dynamic load. In the process of building a well by the freezing method, it is especially necessary to consider various forms of damage to the well tower caused by uneven lifting of the well tower foundation caused by frost heaving and thawing, and settlement, which will affect mine hoisting and safe production. The permanent well tower has strong adaptability to the environment, but its most obvious disadvantage is that it takes a long time for the preparation period, and the installation process of the sinking facilities is relatively complicated, especially the preparation work for the freezing project is too much, and the construction of the freezing trench takes a long time near the wellhead. If the construction period is shortened, then the well tower, well shaft freezing, and vertical shaft excavation must realize cross-parallel construction.

因此,需要提供一种针对上述现有技术不足的改进技术方案。Therefore, it is necessary to provide an improved technical solution for the above-mentioned deficiencies in the prior art.

发明内容Contents of the invention

本发明的目的在于提供一种立井井塔、井筒冻结、掘砌交叉平行施工方法,以至少解决目前现有立井井塔、井筒冻结、掘砌多个工序施工占用整体工期时间长、产生冻结费用增大的问题,确保了井塔、井筒冻结、掘砌交叉平行施工的安全,能够保证安全高效建井,有较为显著的经济效益。The purpose of the present invention is to provide a parallel construction method for shaft tower, shaft freezing, excavation and masonry, to at least solve the problem that the current existing shaft tower, shaft freezing, and excavation multiple processes occupy a long overall construction period and generate freezing costs The increased problem ensures the safety of well towers, well shafts freezing, excavation and masonry cross-parallel construction, and can ensure safe and efficient well construction, which has more significant economic benefits.

为了实现上述目的,本发明提供如下技术方案:In order to achieve the above object, the present invention provides the following technical solutions:

一种井塔主体施工与井筒掘砌、冻结平行施工系统,平行施工系统包括,冻结系统、井塔施工系统和井筒掘砌系统;A parallel construction system for well tower main body construction, shaft excavation, and freezing, the parallel construction system includes a freezing system, a well tower construction system, and a shaft excavation system;

所述冻结系统设置在井筒外围四周;所述冻结系统包括冻结管,所述冻结管邻近所述井筒周向设置,多个所述冻结管组成圆形冻结管幕;The freezing system is arranged around the periphery of the wellbore; the freezing system includes freezing pipes, the freezing pipes are arranged adjacent to the circumference of the wellbore, and a plurality of the freezing pipes form a circular freezing pipe curtain;

所述井塔施工系统位于所述井筒掘砌系统上方;所述井塔施工系统包括井塔框架,所述井塔框架设有第一层平台和第二层平台,所述井塔框架用于提供承载与支撑;The well tower construction system is located above the shaft excavation and laying system; the well tower construction system includes a well tower frame, and the well tower frame is provided with a first floor platform and a second floor platform, and the well tower frame is used for Provide bearing and support;

所述井筒掘砌系统位于所述冻结系统上方;所述井筒掘砌系统包括凿井系统和井筒浇筑系统;所述井筒浇筑系统设置在所述井塔框架上。The shaft excavation system is located above the freezing system; the shaft excavation system includes a sinking system and a shaft pouring system; the shaft pouring system is arranged on the well tower frame.

如上所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,优选,所述井塔施工系统还包括结构柱,四个所述结构柱跨设在在所述井筒上方,所述第一层平台和第二层平台连接在所述结构柱上,所述第二层平台位于所述第一层平台上方,所述第二层平台上铺设有厚木板,所述厚木板用于对第二层平台以下空间断面封闭;所述井塔框架四周还设有井塔防护栏,所述井塔防护栏设置在与第二层平台同一高度处的井塔外侧壁面上;As described above, a parallel construction system for well tower main body construction, shaft excavation, and freezing, preferably, the well tower construction system further includes structural columns, and four structural columns are arranged above the shaft. The first layer platform and the second layer platform are connected on the structural column, the second layer platform is located above the first layer platform, and the second layer platform is laid with thick wooden boards, and the thick wooden boards are used for The space section below the platform on the second floor is closed; the well tower frame is also provided with a well tower guardrail around the well tower frame, and the well tower guardrail is arranged on the outer wall surface of the well tower at the same height as the second floor platform;

优选地,所述井塔防护栏上还配套设有井塔防坠网。Preferably, the well tower guardrail is also equipped with a well tower anti-falling net.

如上所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,优选,所述井塔施工系统还包括绞车提升系统和临时排矸系统,所述绞车提升系统和所述临时排矸系统设在第一层平台上,所述临时排矸系统位于所述绞车提升系统远离所述井塔框架的一侧;所述绞车提升系统包括绞车天轮平台,绞车天轮梁,绞车提升天轮;所述绞车天轮梁设置在所述绞车天轮平台上,所述提绞车升天轮设置在所述绞车天轮梁上;所述临时排矸系统包括排矸天轮平台,排矸天轮梁,排矸天轮和稳车装置,所述排矸天轮梁设置在所述排矸天轮平台上,所述排矸天轮设置在所述排矸天轮梁上;所述稳车装置设置在地面基础上;As described above, a parallel construction system for well tower main body construction, shaft excavation, and freezing, preferably, the well tower construction system further includes a winch lifting system and a temporary gangue discharge system, and the winch lifting system and the temporary gangue discharge system The system is set on the first floor platform, and the temporary gangue removal system is located on the side of the winch hoisting system away from the well tower frame; The winch sky wheel beam is arranged on the winch sky wheel platform, and the winch lifting wheel is arranged on the winch sky wheel beam; the temporary waste discharge system includes the gangue discharge sky wheel platform, and the gangue discharge sky wheel platform wheel beam, gangue discharge sky wheel and vehicle stabilizing device, the gangue discharge sky wheel beam is arranged on the gangue discharge sky wheel platform, and the gangue discharge sky wheel is arranged on the gangue discharge sky wheel beam; The car device is set on the ground foundation;

优选地,所述稳车装置为25t稳车装置。Preferably, the vehicle stabilizing device is a 25t vehicle stabilizing device.

如上所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,优选,所述凿井统包括临时凿井系统,单侧溜矸系统和副溜钩矸系统;所述临时凿井系统包括定滑轮,所述定滑轮通过钢丝绳人字形悬挂在第一层平台下表面,所述单侧溜矸系统设置在第一层平台上,所述副溜钩矸系统设置在所述井塔框架外侧壁,所述副溜钩矸系统位于所述第一层平台与地面中间高度处;As described above, a parallel construction system for the construction of the main body of the well tower and the excavation and freezing of the shaft, preferably, the drilling system includes a temporary drilling system, a single-side sliding gangue system and an auxiliary sliding hook gangue system; the temporary drilling system The system includes a fixed pulley, the fixed pulley is suspended on the lower surface of the first floor platform by a wire rope in a herringbone shape, the single-side slide system is set on the first floor platform, and the auxiliary slide hook system is set on the well tower On the outer wall of the frame, the auxiliary chute and hook gangue system is located at the middle height between the first floor platform and the ground;

优选地,所述定滑轮为20t定滑轮。Preferably, the fixed pulley is a 20t fixed pulley.

如上所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,优选,所述井筒浇筑系统包括压风管悬吊天轮,所述压风管悬吊天轮设置在所述第二层平台的中心的右侧,所述压风管悬吊天轮通过钢丝绳连接有压风管导向天轮,所述压风管导向天轮位于所述的二层平台的最右端;所述压风管悬吊天轮相对于所述第二层平台的中心线所在平面对称处设有排水管悬吊天轮,所述排水管悬吊天轮通过所述钢丝绳连接有排水管导向天轮,所述排水管导向天轮设置在所述第二层平台的最左端。In the above-mentioned parallel construction system for the construction of the main body of the well tower and the excavation and freezing of the shaft, preferably, the shaft pouring system includes a suspension sky wheel of the compressed air pipe, and the suspended sky wheel of the compressed air pipe is arranged on the first On the right side of the center of the second-floor platform, the air pressure pipe suspension sky wheel is connected with a pressure air pipe guide sky wheel through a steel wire rope, and the air pressure pipe guide sky wheel is located at the rightmost end of the second floor platform; The sky wheel suspended by the pressure air pipe is arranged symmetrically with respect to the plane where the center line of the second floor platform is located, and the sky wheel suspended by the drain pipe is connected to the guiding sky wheel of the drain pipe through the steel wire rope. , the drainpipe guiding sky pulley is arranged at the leftmost end of the second-floor platform.

如上所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,优选,所述井筒浇筑系统还包括双层吊盘,所述双层吊盘通过钢丝绳悬挂在井筒内,所述井筒内壁上设有吊盘通过溜槽,便于所述双层吊盘上下移动;所述井筒上端还设有封口盘,所述封口盘为带有通孔的薄饼圆盘。In the above-mentioned parallel construction system for the construction of the main body of the shaft tower and the excavation and freezing of the shaft, preferably, the shaft pouring system further includes a double-layer hanging pan, and the double-layer hanging pan is suspended in the shaft through a wire rope. A hanging plate is provided on the inner wall to pass through the chute, which is convenient for the double-layer hanging plate to move up and down; a sealing plate is also provided at the upper end of the shaft, and the sealing plate is a pancake disc with a through hole.

如上所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,优选,冻结系统还包括冻结沟槽,所述冻结沟槽呈圆环状;所述冻结沟槽外围沿所述冻结沟槽圆周方向设有支撑柱,多个所述支撑柱形成支撑体系用于对所述冻结沟槽外壁支护。In the parallel construction system for the construction of the main body of the well tower and the excavation and freezing of the shaft as described above, preferably, the freezing system further includes a freezing groove, and the freezing groove is in the shape of a ring; A support column is provided in the circumferential direction of the groove, and a plurality of the support columns form a support system for supporting the outer wall of the freezing groove.

如上所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,优选,所述井塔框架外侧壁上还设有安全防护棚,所述安全防护棚为空心圆环状,所述安全防护棚位于所述副溜钩矸系统与所述第一层平台之间,用于对下层工作空间提供安全屏障。In the parallel construction system for the construction of the main body of the well tower and the excavation and freezing of the shaft as described above, preferably, a safety protection shed is also provided on the outer wall of the well tower frame, and the safety protection shed is in the shape of a hollow ring. The safety protection shed is located between the auxiliary chute hook gangue system and the first floor platform, and is used to provide a safety barrier for the lower working space.

一种井塔主体施工与井筒掘砌、冻结平行施工系统的施工方法,优选,所述方法包括以下步骤:A construction method for the parallel construction system of well tower main body construction and shaft excavation and freezing, preferably, the method includes the following steps:

步骤1,施工准备与工期预算:Step 1, construction preparation and construction period budget:

冻结造孔以及冻结沟槽及设备安装之后进行冻结施工,冻结施工预算工期为60天,在冻结沟槽安装的同时,对井筒掘砌做准备,安装掘砌设备;掘砌设备安装预算工期为31天,掘砌设备安装完成之后开始掘砌施工;Freezing construction will be carried out after the frozen hole making, frozen trench and equipment installation. The budgeted construction period for the frozen construction is 60 days. While the frozen trench is installed, prepare for the excavation of the shaft and install the excavation equipment; the budgeted period for the installation of the excavation equipment is 31 days, the excavation and masonry construction will start after the installation of the excavation and masonry equipment is completed;

步骤2,井塔与冻结工程平行施工:Step 2, parallel construction of the well tower and the freezing project:

冻结造孔结束后,井塔基础开挖时,采用分层、分块开挖方法,减小不均匀侧向土应力,对冻结管周围留核心土防止机械破坏;冻结采用一次冻全深的冻结施工方案,井塔采用滑膜施工工艺;在井塔滑膜施工的同时,冻结站同时建设,并开始进行冻结;将冻结站设置在远离井口的地方,冻结施工所需的冻结盐水可用主冻结管敷设至井口,将更大的空间留给井塔和井筒的施工单位;井塔基础剪力墙在施工时,冻结工程需要不间断施工;主冻结管要穿越剪力墙,提前要预留好冻结管道的孔洞位置,并且需要对主冻结管支撑,加固;After the freezing hole is completed, when excavating the foundation of the well tower, the method of layering and block excavation shall be adopted to reduce the uneven lateral soil stress, and the core soil around the frozen pipe shall be left to prevent mechanical damage; In the freezing construction plan, the well tower adopts the synovial film construction technology; at the same time as the synovial film construction of the well tower, the freezing station is constructed at the same time, and the freezing begins; the freezing station is set far from the wellhead, and the frozen brine required for freezing construction can be used in the The freezing pipe is laid to the wellhead, leaving more space for the construction unit of the well tower and well shaft; when the foundation shear wall of the well tower is being constructed, the freezing project needs to be uninterrupted; The hole position of the frozen pipe should be reserved, and the main frozen pipe needs to be supported and reinforced;

步骤3,井塔与凿井、冻结平行施工Step 3, parallel construction of the well tower, sinking and freezing

先期建设2层井塔框架结构,通过铺设钢梁及50mm厚木板全断面封闭,四周增设防护栏及防坠网,形成安全防护棚,确保下部施工安全;第2层以上井塔扎筋、支模、浇筑混凝土等工序正常施工;第一层平台同步施工提升绞车用天轮平台,天轮梁及提升天轮正常安装;两部绞车提升系统未形成前,利用第一层平台安装天轮、钢梁及地面两台25t稳车设置临时提升排矸系统,形成井筒掘砌体系;井筒掘砌工程必须有三个方向的施工空间,设计稳绞系统占据东西两个方向,南侧用于排掘砌矸石,北侧用于人员上下、材料打运;在掘砌爆破时,井塔上面施工人员停止作业。The 2-story well tower frame structure is constructed in advance, and the entire section is closed by laying steel beams and 50mm thick wooden boards, and guardrails and anti-falling nets are added around to form a safety protection shed to ensure the safety of the lower construction; Formwork, concrete pouring and other processes are under normal construction; the first floor platform is constructed synchronously to lift the skywheel platform for the winch, the skywheel beam and the hoisting skywheel are installed normally; before the lifting system of the two winches is formed, use the first floor platform to install the skywheel, The steel beam and the two 25t stabilizing vehicles on the ground are equipped with a temporary lifting and drainage system to form a shaft excavation system; the shaft excavation project must have construction space in three directions, and the design stabilization system occupies two directions in the east and west, and the south side is used for excavation. The gangue is built, and the north side is used for personnel to go up and down and transport materials; during the excavation and blasting, the construction personnel on the well tower stop working.

如上所述的井塔主体施工与井筒掘砌、冻结平行施工系统的施工方法,优选,所述步骤2中,在井塔滑膜施工过程中,除了井塔自身的高空作业安全防护外,采用大于5mm厚的钢板将冻结沟槽全部封闭,防止高空坠物砸漏冻结沟槽内的冻结管道,造成冻结盐水的流失。The construction method of the above-mentioned well tower main body construction and shaft excavation and freezing parallel construction system, preferably, in the step 2, during the well tower synovial film construction process, in addition to the safety protection of the well tower itself for high-altitude operations, adopt The steel plate with a thickness greater than 5mm seals all the freezing grooves to prevent falling objects from leaking the frozen pipes in the freezing grooves and causing the loss of frozen brine.

与最接近的现有技术相比,本发明提供的技术方案具有如下优异效果:Compared with the closest prior art, the technical solution provided by the present invention has the following excellent effects:

本发明采用井塔施工系统、井筒掘砌施工系统和冻结施工系统平行布置的方式,在井塔主体施工的同时可以对井筒掘砌施工和对冻结施工;此外,本发明的井井塔、井筒冻结、掘砌交叉平行施工方法,解决了现有多个工序在技术要求上存在的占用工期时间长、费用增大的问题,提出了多个工序交叉平行施工的新方法,与常规施工方法相比,可实现6个月内开始井筒掘砌,填补高寒地区井塔、井筒冻结、掘砌交叉平行快速施工的空白,是煤矿安全高效建井的重要组成部分,社会、经济效益显著。The present invention adopts the mode that the well tower construction system, the well shaft excavation and masonry construction system and the freezing construction system are arranged in parallel, and the well shaft excavation construction and the freezing construction can be carried out while the main body of the well tower is being constructed; Freezing, excavation and masonry cross-parallel construction method solves the problems of long construction period and increased cost in the technical requirements of existing multiple processes, and proposes a new method of multiple process cross-parallel construction, which is different from conventional construction methods. Compared with that, it can realize the excavation of the shaft within 6 months, filling the gaps in the high-cold area of the well tower, the freezing of the shaft, and the parallel and rapid construction of the excavation and masonry. It is an important part of the safe and efficient construction of coal mines, and the social and economic benefits are significant.

附图说明Description of drawings

构成本申请的一部分的说明书附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。其中:The accompanying drawings constituting a part of the present application are used to provide a further understanding of the present invention, and the schematic embodiments and descriptions of the present invention are used to explain the present invention, and do not constitute an improper limitation of the present invention. in:

图1为本发明实施例的冻结孔、桩基和钻塔的布置示意图;Fig. 1 is the layout schematic diagram of freezing hole, pile foundation and drill tower of the embodiment of the present invention;

图2为本发明实施例的桩基和冻结管重叠时的施工方法结构示意图;Fig. 2 is the structural representation of the construction method when the pile foundation and the frozen pipe overlap according to the embodiment of the present invention;

图3为本发明实施例的井塔、井筒冻结和井筒掘砌平行施工的布置示意图;Fig. 3 is the layout schematic diagram of parallel construction of shaft tower, shaft freezing and shaft excavation according to the embodiment of the present invention;

图4为本发明实施例的平行施工网格计划图。Fig. 4 is a plan diagram of parallel construction grids according to the embodiment of the present invention.

图中:1、桩基孔;2、冻结孔;3、泥浆沟槽;4、吊盘;5、井筒;6、冻结管;7、钻塔;8、桩基孔阵;9、冻结孔阵;10、井塔桩基;11、结构柱; 12、地面基础;13、第一层平台;14、第二层平台;15、压风管悬吊天轮; 16、压风管导向天轮;17、排水管悬吊天轮;18、排水管导向天轮;19、安全防护棚;20、稳车装置;21、绞车。In the figure: 1. Pile foundation hole; 2. Frozen hole; 3. Mud groove; 4. Suspension plate; 5. Well shaft; 6. Frozen pipe; 7. Drilling tower; 10. Well tower pile foundation; 11. Structural column; 12. Ground foundation; 13. First floor platform; 14. Second floor platform; 17. Drainpipe suspension skywheel; 18. Drainage pipe guide skywheel; 19. Safety shed; 20. Vehicle stabilizing device; 21. Winch.

具体实施方式Detailed ways

下面将参考附图并结合实施例来详细说明本发明。需要说明的是,在不冲突的情况下,本发明中的实施例及实施例中的特征可以相互组合。The present invention will be described in detail below with reference to the accompanying drawings and examples. It should be noted that, in the case of no conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other.

在本发明的描述中,术语“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明而不是要求本发明必须以特定的方位构造和操作,因此不能理解为对本发明的限制。本发明中使用的术语“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接;可以是直接相连,也可以通过中间部件间接相连,对于本领域的普通技术人员而言,可以根据具体情况理解上述术语的具体含义。In the description of the present invention, the terms "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", " The orientations or positional relationships indicated by "top", "bottom", etc. are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation, so they cannot be understood as Limitations on the Invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense, for example, it can be fixedly connected or detachably connected; it can be directly connected or indirectly connected through intermediate parts, for ordinary A skilled person can understand the specific meanings of the above terms according to specific situations.

根据本发明的具体实施例,如图1至3所示,一种立井井塔、井筒冻结、掘砌交叉平行施工系统及方法,平行施工系统包括,冻结造孔系统,冻结造孔系统包括冻结系统和冻结孔造孔系统。冻结系统设置在井筒5外围四周。冻结系统包括冻结管6,多个冻结管6邻近井筒5周向设置。冻结孔造孔系统包括吊盘4和钻塔7,钻塔7的下表面连接在吊盘4的上表面,五台钻塔7 靠近吊盘4的周向边缘均匀设置。According to a specific embodiment of the present invention, as shown in Figures 1 to 3, a parallel construction system and method for shaft shaft freezing, excavation and masonry intersection, the parallel construction system includes a freezing pore-making system, and the freezing pore-making system includes freezing system and freeze hole pore making system. The freezing system is arranged around the periphery of the shaft 5 . The freezing system comprises freezing pipes 6 , a plurality of freezing pipes 6 being arranged circumferentially adjacent to the wellbore 5 . The freezing hole drilling system includes a hanging pan 4 and a drilling tower 7 , the lower surface of the drilling tower 7 is connected to the upper surface of the hanging pan 4 , and five drilling towers 7 are evenly arranged near the peripheral edge of the hanging pan 4 .

井塔施工系统,井塔施工系统包括井塔桩基10系统和井塔框架系统,井塔桩基10系统位于冻结孔造孔系统外侧。井塔桩基10系统包括回转钻机,回转钻机穿插设置在钻塔7之间,回转钻机用于形成桩基孔1,多个桩基孔1 形成桩基孔阵8。井塔框架系统包括井塔框架,井塔框架设有第一层平台13 和第二层平台14,井塔框架用于提供承载与支撑。A well tower construction system, the well tower construction system includes a well tower pile foundation 10 system and a well tower frame system, and the well tower pile foundation 10 system is located outside the frozen hole pore making system. The well tower pile foundation 10 system includes a rotary drilling rig interspersed between the drilling towers 7 , the rotary drilling rig is used to form pile foundation holes 1 , and a plurality of pile foundation holes 1 forms a pile foundation hole array 8 . The well tower frame system includes the well tower frame. The well tower frame is provided with a first layer platform 13 and a second layer platform 14. The well tower frame is used to provide bearing and support.

井筒5掘砌系统,井筒5掘砌系统位于冻结系统上方。井筒5掘砌系统包括凿井系统和井筒5浇筑系统。井筒5浇筑系统设置在井塔框架上。Shaft 5 excavation system, the shaft 5 excavation system is located above the freezing system. The shaft 5 excavation system includes a sinking system and a shaft 5 pouring system. The wellbore 5 pouring system is set on the well tower frame.

根据本发明的具体实施例,井塔井塔框架系统还包括结构柱11、绞车21 提升系统和临时排矸系统。四个结构柱11跨设在在井筒5上方,第一层平台 13和第二层平台14连接在结构柱11上,第二层平台14位于第一层平台13 上方,第二层平台14上铺设有厚木板,厚木板用于对第二层平台14以下空间断面封闭。井塔框架四周还设有井塔防护栏,井塔防护栏设置在与第二层平台14同一高度处的井塔外侧壁面上。According to a specific embodiment of the present invention, the well tower and well tower frame system also includes a structural column 11, a winch 21, a lifting system and a temporary gangue discharge system. Four structural columns 11 are arranged above the shaft 5, the first platform 13 and the second platform 14 are connected to the structural columns 11, the second platform 14 is located above the first platform 13, and the second platform 14 Thick planks are laid, and the planks are used to close the space section below the platform 14 on the second floor. The well tower frame is also provided with a well tower guardrail around the well tower frame, and the well tower guardrail is arranged on the well tower outer wall at the same height as the second floor platform 14 .

绞车21提升系统和临时排矸系统设在第一层平台13上,临时排矸系统位于绞车21提升系统远离井塔框架的一侧。绞车21提升系统包括绞车21 天轮平台,绞车21天轮梁,绞车21提升天轮。绞车21天轮梁设置在绞车 21天轮平台上,提绞车21升天轮设置在绞车21天轮梁上。临时排矸系统包括排矸天轮平台,排矸天轮梁,排矸天轮和稳车装置20,排矸天轮梁设置在排矸天轮平台上,排矸天轮设置在排矸天轮梁上。稳车装置20设置在地面基础12上。优选地,稳车装置20为25t稳车装置20。再优选地,井塔防护栏上还配套设有井塔防坠网。The hoisting system of the winch 21 and the temporary gangue removal system are arranged on the first floor platform 13, and the temporary gangue removal system is located on the side of the hoisting system of the winch 21 away from the well tower frame. The winch 21 hoisting system includes a winch 21 skywheel platform, a winch 21 skywheel beam, and a winch 21 hoisting skywheel. The 21 sky wheel beams of the winch are arranged on the 21 sky wheel platforms of the winch, and the 21 sky wheels of the winch are arranged on the 21 sky wheel beams of the winch. The temporary gangue discharge system includes the gangue discharge skywheel platform, the gangue discharge skywheel beam, the gangue discharge skywheel and the vehicle stabilization device 20, the gangue discharge skywheel beam is set on the gangue discharge skywheel platform, and the gangue discharge skywheel is set on the gangue discharge skywheel on the wheel beam. The vehicle stabilizing device 20 is arranged on the ground foundation 12 . Preferably, the vehicle stabilizing device 20 is a 25t vehicle stabilizing device 20 . More preferably, the well tower guardrail is also equipped with a well tower anti-falling net.

根据本发明的具体实施例,冻结系统还包括制冷设备、进液管、分流管、冻结沟槽、合流管和回液管。冻结管6为空心状圆管,冻结管6位于冻结孔 2内,冻结管6自冻结孔2的顶部沿冻结孔2的深度方向延伸铺设至冻结孔2 底部。According to a specific embodiment of the present invention, the freezing system further includes a refrigeration device, a liquid inlet pipe, a distribution pipe, a freezing groove, a confluence pipe and a liquid return pipe. Freezing pipe 6 is a hollow circular pipe, and freezing pipe 6 is positioned in freezing hole 2, and freezing pipe 6 extends and lays to freezing hole 2 bottoms along the depth direction of freezing hole 2 from the top of freezing hole 2.

多个冻结孔2形成冻结孔阵9,多个冻结管6形成冻结管6幕,冻结管6 幕的内壁靠近吊盘4的圆周外侧面。冻结管6幕上端设有冻结沟槽,冻结沟槽呈圆环状,冻结沟槽外围沿冻结沟槽圆周方向设有支撑柱,多个支撑柱形成支撑体系用于对冻结沟槽外壁支护。A plurality of freezing holes 2 form a freezing hole array 9, and a plurality of freezing pipes 6 form a curtain of freezing pipes 6, and the inner wall of the curtain of freezing pipes 6 is close to the outer peripheral surface of the suspension plate 4. The upper end of the freezing pipe 6 curtain is provided with a freezing groove, the freezing groove is in the shape of a ring, and the periphery of the freezing groove is provided with supporting columns along the circumferential direction of the freezing groove, and a plurality of supporting columns form a support system for supporting the outer wall of the freezing groove .

冻结沟槽内设有分流管与合流管,分流管与合流管均呈空心圆环状,合流管位于分流管下方。分流管下表面沿周向均匀开设有分流通孔,每个冻结管6的上端均通过多个分流通孔与分流管导通,冻结孔2上端靠近上端面处设有合流管通孔,冻结孔2通过合流管通孔与合流管连通。A diversion pipe and a confluence pipe are arranged in the freezing groove, both of which are in the shape of a hollow ring, and the confluence pipe is located below the diversion pipe. The lower surface of the shunt pipe is evenly opened with shunt flow holes along the circumferential direction. The upper end of each freezing pipe 6 is connected with the shunt pipe through a plurality of shunt flow holes. Hole 2 communicates with the confluence pipe through the confluence pipe through hole.

进液管的前端连接在制冷设备上,进液管的后端连接在分流管上。回液管的前端连接在合流管上,回液管的后端与制冷设备导通,用于将低温盐水回流至制冷设备。The front end of the liquid inlet pipe is connected to the refrigeration equipment, and the rear end of the liquid inlet pipe is connected to the shunt pipe. The front end of the liquid return pipe is connected to the confluence pipe, and the rear end of the liquid return pipe is connected to the refrigeration equipment for returning the low-temperature brine to the refrigeration equipment.

制冷设备、进液管、分流管、冻结管6、冻结孔2、合流管和回液管形成可供低温盐水循环的连续回路。优选地,制冷设备位于桩基孔阵8外。再优选地,冻结沟槽所在圆的直径与冻结管6幕的直径相同。Refrigeration equipment, liquid inlet pipe, distribution pipe, freezing pipe 6, freezing hole 2, confluence pipe and liquid return pipe form a continuous loop for circulation of low-temperature brine. Preferably, the refrigeration equipment is located outside the hole array 8 of the pile foundation. Preferably again, the diameter of the circle where the freezing groove is located is the same as the diameter of the freezing tube 6 curtain.

根据本发明的具体实施例,井筒5浇筑系统包括压风管悬吊天轮15和双层吊盘4。压风管悬吊天轮15设置在第二层平台14的中心的右侧,压风管悬吊天轮15通过钢丝绳连接有压风管导向天轮16,压风管导向天轮16位于的二层平台的最右端。压风管悬吊天轮15相对于第二层平台14的中心线所在平面对称处设有排水管悬吊天轮17,排水管悬吊天轮17通过钢丝绳连接有排水管导向天轮18,排水管导向天轮18设置在第二层平台14的最左端。According to a specific embodiment of the present invention, the pouring system of the well shaft 5 includes the air pressure pipe suspension sky pulley 15 and the double-layer suspension pan 4 . The air pressure pipe suspension sky wheel 15 is arranged on the right side of the center of the second floor platform 14, the air pressure pipe suspension sky wheel 15 is connected with the pressure air pipe guide sky wheel 16 through the steel wire rope, and the pressure air pipe guide sky wheel 16 is located on the The far right end of the second floor platform. The air pressure pipe suspension skywheel 15 is provided with a drainpipe suspension skywheel 17 at the plane symmetry with respect to the center line of the second floor platform 14, and the drainage pipe suspension skywheel 17 is connected with a drainage pipe guide skywheel 18 through a steel wire rope. The drainage pipe guiding wheel 18 is arranged on the leftmost end of the platform 14 on the second floor.

双层吊盘4通过钢丝绳悬挂在井筒5内,井筒5内壁上设有吊盘4通过溜槽,便于双层吊盘4上下移动。井筒5上端还设有封口盘,封口盘为带有通孔的薄饼圆盘。The double-layer hanging pan 4 is suspended in the shaft 5 by a wire rope, and the inner wall of the shaft 5 is provided with a hanging pan 4 passing through a chute, so that the double-layer hanging pan 4 moves up and down. The upper end of the shaft 5 is also provided with a sealing disc, which is a pancake disc with through holes.

根据本发明的具体实施例,凿井统包括临时凿井系统,单侧溜矸系统,副溜钩矸系统临时凿井系统包括定滑轮,定滑轮通过钢丝绳人字形悬挂在第一层平台13下表面,单侧溜矸系统设置在第一层平台13上,副溜钩矸系统设置在井塔框架外侧壁,副溜钩矸系统位于第一层平台13与地面中间高度处。优选地,定滑轮为20t定滑轮。According to a specific embodiment of the present invention, the sinking system includes a temporary sinking system, a unilateral sliding gangue system, and an auxiliary sliding hook gangue system. The temporary sinking system includes a fixed pulley, which is suspended under the platform 13 on the first floor through a herringbone wire rope. On the surface, the single-side sliding and gangue system is arranged on the first floor platform 13, the auxiliary sliding hook and gangue system is arranged on the outer wall of the well tower frame, and the auxiliary sliding hook and gangue system is located at the middle height between the first floor platform 13 and the ground. Preferably, the fixed pulley is a 20t fixed pulley.

根据本发明的具体实施例,冻结孔2造孔系统包括泥浆沟槽3和泥浆导管,泥浆沟槽3的截面呈凹字形,泥浆沟槽3的一端连接在吊盘4的圆周外侧面,并紧贴吊盘4的圆周外侧面周向延伸至首尾相连,形成环形结构。泥浆沟槽3底部还设有泥浆通孔。多个泥浆导管的一端密闭连接在多个泥浆通孔内,多个泥浆导管的另一端延伸至多个冻结孔2的上端。According to a specific embodiment of the present invention, the freezing hole 2 drilling system includes a mud groove 3 and a mud conduit, the cross section of the mud groove 3 is concave, and one end of the mud groove 3 is connected to the outer surface of the circumference of the suspension plate 4, and The outer surface of the circumference close to the suspension plate 4 extends circumferentially until connected end to end, forming a ring structure. A mud through hole is also provided at the bottom of the mud trench 3 . One end of the plurality of mud conduits is airtightly connected in the plurality of mud through holes, and the other end of the plurality of mud conduits extends to the upper ends of the plurality of freezing holes 2 .

根据本发明的具体实施例,灌注系统包括泥浆池、灌注导管和钢筋笼。泥浆池为无顶空心长方体状,泥浆池下表面设有万向轮,用于为泥浆池的移动提供方便。泥浆池的下表面还设有灌注孔。多个灌注导管的一端密封连接在多个灌注孔内,多个灌注导管的另一端延伸至不同的桩基孔1底部。钢筋笼设在桩基孔1内,用于形成桩基。井塔框架外侧壁上还设有安全防护棚19,安全防护棚19为空心圆环状,安全防护棚19位于副溜钩矸系统与第一层平台13之间,用于对下层工作空间提供安全屏障。桩基孔阵8外围呈正方形状,桩基孔阵8位于冻结管6幕外侧。桩基孔阵8中设有预留浇注桩基砼的道路。优选地,桩基孔1有55~65个。再优选地,在水平方向和竖直方向每两个相邻的桩基孔1的间距小于3m。According to a specific embodiment of the present invention, the perfusion system includes a mud tank, a perfusion conduit and a reinforcement cage. The mud pool is in the shape of a hollow cuboid without a roof, and universal wheels are provided on the lower surface of the mud pool to provide convenience for the movement of the mud pool. The lower surface of the mud pool is also provided with pouring holes. One end of multiple perfusion conduits is sealed and connected in multiple perfusion holes, and the other end of multiple perfusion conduits extends to the bottom of different pile foundation holes 1 . The reinforcement cage is arranged in the pile foundation hole 1 for forming the pile foundation. A safety protection shed 19 is also provided on the outer wall of the well tower frame, and the safety protection shed 19 is a hollow ring shape. The safety protection shed 19 is located between the auxiliary chute hook gangue system and the first floor platform 13, and is used to provide protection for the lower working space. security barrier. The periphery of the pile foundation hole array 8 is in a square shape, and the pile foundation hole array 8 is located outside the freezing pipe 6 curtain. The pile foundation hole array 8 is provided with a reserved road for pouring pile foundation concrete. Preferably, there are 55-65 pile foundation holes 1 . More preferably, the distance between every two adjacent pile foundation holes 1 in the horizontal direction and the vertical direction is less than 3m.

根据本发明的具体实施例,如图4所示,提供了本发明平行施工网格计划图,自开工开始,冻结造孔和井塔桩基10施工同时进行,冻结造孔结束后,冻结沟槽及设备安装和井筒5掘砌准备工作同时进行,冻结沟槽及设备安装完成之后,开始冻结施工,井筒5掘砌准备完成之后开始掘砌设备安装,掘砌设备安装完成之后,掘砌开始施工。与上述施工步骤同时进行的步骤有,破桩头,破桩头施工完成之后,开始基础施工,基础施工所需的工期大致为30天,之后进行金塔主体施工交付安装,之后完成掘砌设备安装和掘砌开始施工。According to a specific embodiment of the present invention, as shown in Figure 4, the parallel construction grid planning diagram of the present invention is provided. From the beginning of construction, the freezing hole making and the well tower pile foundation 10 construction are carried out simultaneously, and after the freezing hole making is finished, the freezing ditch The trench and equipment installation and shaft 5 excavation preparations are carried out at the same time. After the freezing trench and equipment installation are completed, the freezing construction starts. After the shaft 5 excavation preparations are completed, the excavation equipment installation starts. construction. The steps to be carried out simultaneously with the above construction steps include breaking the pile head. After the pile head is broken, the foundation construction will start. The construction period required for the foundation construction is about 30 days. Installation and excavation started construction.

本发明还提供了立井井塔、井筒5冻结、掘砌交叉平行施工系统的平行施工方法,平行施工方法包括如下步骤,The present invention also provides a parallel construction method of the vertical shaft tower, shaft 5 freezing, excavation and masonry cross parallel construction system, and the parallel construction method includes the following steps,

步骤1,井塔桩基10与冻结造孔平行施工:Step 1, parallel construction of well tower pile foundation 10 and frozen hole making:

在吊盘4上靠近吊盘4边缘处周向等角度的设置五台钻塔7,钻塔7底部与吊盘4活动链接,以便钻塔7移动至不同工位施工。钻塔7设置好后,同时开启五台钻塔7,在设计的位置钻进形成冻结孔2。在冻结孔阵9形成的同时,用于施工桩基孔1的汽车回转钻机穿插设置在钻塔7缝隙中,在冻结孔阵9周围钻出桩基孔1,并逐渐形成桩基孔阵8。On the hanging pan 4, five drilling towers 7 are arranged at a circumferential equiangular position near the edge of the hanging pan 4, and the bottoms of the drilling towers 7 are movably linked with the hanging pan 4, so that the drilling towers 7 can be moved to different stations for construction. After drilling tower 7 is set up, open five drilling towers 7 simultaneously, drill into and form freezing hole 2 at the position of design. While the frozen hole array 9 is being formed, the automobile rotary drilling rig used for constructing the pile foundation hole 1 is interspersed in the gap of the drilling tower 7, and the pile foundation hole 1 is drilled around the frozen hole array 9, and the pile foundation hole array 8 is gradually formed. .

在吊盘4外侧圆周面上焊接一圈泥浆沟槽3,在泥浆沟槽3内放入泥浆,冻结孔2泥浆护壁采用冻采用的泥浆为PHP-HPAN泥浆和C-PAN-KHm泥浆。泥浆在泥浆沟槽3内循环流动,泥浆沟槽3内的泥浆通过泥浆导管导入冻结孔阵9中,进行冻结孔2泥浆护壁。冻结孔2泥浆护壁的同时,将钢筋笼吊放进桩基孔阵8中,为后面工序做准备。Weld a circle of mud groove 3 on the peripheral surface of suspension plate 4, put into mud in mud groove 3, freeze hole 2 mud retaining walls and adopt freezing mud to be PHP-HPAN mud and C-PAN-KHm mud. The mud circulates in the mud trench 3, and the mud in the mud trench 3 is introduced into the freezing hole array 9 through the mud conduit to protect the wall of the freezing hole 2 with mud. While freezing the hole 2 mud retaining walls, the reinforcement cage is hoisted into the pile foundation hole array 8 to prepare for the following process.

在冻结孔阵9上端挖设一圈冻结沟槽,往每个冻结孔2内下放入冻结管 6,下放冻结管6的同时,往泥浆池内倒入施工现场自拌砼,灌注导管连接在泥浆池底部,将砼引入桩基孔1内钢筋笼的底部,泥浆池沿着预留的灌桩路径边移动边灌注,形成桩基。部分桩基孔1与冻结管6相邻,造成施工难度大,桩基孔1与冻结管6相邻距离小于100mm时,必须先施工桩基,后施工冻结孔2,避免冻结管6挤压变形或者移位,造成冻结管6的报废。桩基与冻结管6道重叠时,将冻结管6偏离原位置,与桩基至少保持0.3m距离,当冻结管6施工至桩基底部后,采用陀螺导向法将冻结管6导向原设计位置。Dig a circle of freezing grooves at the upper end of the freezing hole array 9, put the freezing pipe 6 into each freezing hole 2, and pour the self-mixing concrete at the construction site into the mud pool at the same time as lowering the freezing pipe 6. At the bottom of the mud pool, concrete is introduced into the bottom of the reinforcement cage in the pile foundation hole 1, and the mud pool is poured while moving along the reserved pile filling path to form the pile foundation. Part of the pile foundation hole 1 is adjacent to the frozen pipe 6, which makes the construction difficult. When the adjacent distance between the pile foundation hole 1 and the frozen pipe 6 is less than 100mm, the pile foundation must be constructed first, and then the frozen hole 2 should be constructed to avoid extrusion of the frozen pipe 6. Deformation or displacement causes the freezing tube 6 to be scrapped. When the pile foundation overlaps with the 6 frozen pipes, deviate the frozen pipe 6 from the original position and keep a distance of at least 0.3m from the pile foundation. When the frozen pipe 6 reaches the bottom of the pile foundation, guide the frozen pipe 6 to the original design position .

步骤2,井塔与冻结工程平行施工:Step 2, parallel construction of the well tower and the freezing project:

冻结造孔结束后,井塔基础开挖时,采用分层、分块开挖方法,减小不均匀侧向土应力,对冻结管6周围留核心土防止机械破坏。冻结采用一次冻全深的冻结施工方案,井塔采用滑膜施工工艺。在井塔滑膜施工的同时,冻结站同时建设,并开始进行冻结。将冻结站设置在远离井口的地方,冻结施工所需的冻结盐水可用主冻结管6敷设至井口,将更大的空间留给井塔和井筒5的施工单位。井塔基础剪力墙在施工时,冻结工程需要不间断施工。主冻结管6要穿越剪力墙,提前要预留好冻结管6道的孔洞位置,并且需要对主冻结管6支撑,加固。在井塔滑膜施工过程中,除了井塔自身的高空作业安全防护外,采用大于5mm厚的钢板将冻结沟槽全部封闭,防止高空坠物砸漏冻结沟槽内的冻结管6道,造成冻结盐水的流失。After the freezing hole is finished, when the well tower foundation is excavated, adopt layered and block excavation methods to reduce the uneven lateral soil stress, and leave the core soil around the frozen pipe 6 to prevent mechanical damage. Freezing adopts a one-time freezing and full-depth freezing construction scheme, and the well tower adopts a synovial membrane construction process. Simultaneously with the construction of the well tower synovium, the freezing station was constructed at the same time and started to freeze. The freezing station is arranged at a place away from the wellhead, and the frozen brine required for freezing construction can be laid to the wellhead with the main freezing pipe 6, leaving more space for the construction unit of the well tower and the well shaft 5. During the construction of the foundation shear wall of the well tower, the freezing project requires uninterrupted construction. The main freezing pipe 6 will pass through the shear wall, and the hole positions of the freezing pipe 6 will be reserved in advance, and the main freezing pipe 6 needs to be supported and reinforced. During the construction of the well tower synovial film, in addition to the safety protection of the well tower itself for high-altitude operations, the freezing trenches are completely sealed with steel plates thicker than 5mm, to prevent falling objects from falling from the heights from leaking the 6 frozen pipes in the freezing trenches, causing Freeze the loss of brine.

步骤3,井塔与凿井、冻结平行施工Step 3, parallel construction of the well tower, sinking and freezing

先期建设2层井塔框架结构,通过铺设钢梁及50mm厚木板全断面封闭,四周增设防护栏及防坠网,形成安全防护棚19,确保下部施工安全。第2层以上井塔扎筋、支模、浇筑混凝土等工序正常施工。第一层平台13同步施工提升绞车21用天轮平台,天轮梁及提升天轮正常安装。两部绞车21提升系统未形成前,利用第一层平台13安装天轮、钢梁及地面两台25t稳车设置临时提升排矸系统,形成井筒5掘砌体系。井筒5掘砌工程必须有三个方向的施工空间,设计稳绞系统占据东西两个方向,南侧用于排掘砌矸石,北侧用于人员上下、材料打运。在掘砌爆破时,井塔上面施工人员停止作业。A 2-story well tower frame structure was built in advance, and the entire section was closed by laying steel beams and 50mm thick wooden boards, and guardrails and anti-falling nets were added around to form a safety shed 19 to ensure the safety of the lower construction. On the second floor and above, the well tower reinforcement, formwork support, concrete pouring and other processes are under normal construction. First floor platform 13 synchronous construction hoists 21 sky wheel platforms, sky wheel beams and lifting sky wheels are normally installed. Before the lifting system of the two winches 21 is formed, the first floor platform 13 is used to install the sky wheel, steel beams and two 25t stabilizers on the ground to set up a temporary lifting and discharging system to form the shaft 5 excavation and masonry system. The excavation project of shaft 5 must have construction space in three directions. The design stabilizer system occupies two directions, east and west. The south side is used for excavation and masonry, and the north side is used for personnel to go up and down and transport materials. During the excavation and blasting, the construction personnel above the well tower stopped working.

实施例1:Example 1:

本实施例针对内蒙古自治区鄂尔多斯市塔然高勒矿区南部泊江海子煤矿副井进行施工,立井深611m,矿井于2010年元月正式开工,2012年底正式投产,工期36个月。井筒5采用冻结法施工,基岩段采用普通凿井法施工,副井设计采用钢筋混凝土剪力墙结构井塔,井塔高66m,基础设计为大体积钢筋砼结构,埋深-6m,基础以下为钻孔灌注桩,泥浆护壁。桩基直径为 井塔桩基10身长22m,共60根。This example is aimed at the construction of the auxiliary shaft of Bojiang Haizi Coal Mine in the south of Tarangaole Mining Area, Ordos City, Inner Mongolia Autonomous Region. The depth of the vertical shaft is 611m. Shaft 5 is constructed by the freezing method, and the bedrock section is constructed by the ordinary sinking method. The auxiliary shaft design adopts a reinforced concrete shear wall structure well tower with a height of 66m. The foundation is designed as a large-volume reinforced concrete structure with a buried depth of -6m. The following are bored piles and mud retaining walls. The pile foundation diameter is There are 60 well tower pile foundations 10 with a length of 22m.

根据矿井建设的总工期计划,关键线路:冻结-井筒5掘砌—巷道掘进的施工工期已确定,且压缩空间已经很小,为了不影响矿井总工期,采用本专利提出的井塔与冻结、凿井的平行施工方法,具体可分为三个阶段:According to the total construction period plan of the mine construction, the key line: freezing-shaft 5 excavation-the construction period of roadway excavation has been determined, and the compression space is already very small. In order not to affect the total construction period of the mine, the shaft tower proposed by this patent is adopted. The parallel construction method of sinking wells can be divided into three stages:

(1)井塔桩基10与冻结造孔平行施工(1) Well tower pile foundation 10 is constructed in parallel with frozen hole making

副井冻结凿孔计划工期65天,冻结孔2共44个,测温孔3个,水文孔 2个,累计造孔22690m。采用5台22.5KW的钻塔7按图1所示布置进行同时施工,井塔桩基10共60个,分部在冻结孔2的四周,桩基采用反循环化学造浆护壁,三翼刮刀式钻头回转钻进成孔,钢筋笼整节加箍定位成型,孔口整节直接下笼,导管水下灌筑自拌砼成桩的施工工艺。The planned construction period of the auxiliary well freezing and drilling is 65 days. There are 44 freezing holes 2, 3 temperature measuring holes, and 2 hydrological holes, with a total of 22690m of drilling. Five 22.5KW drilling towers 7 are used for simultaneous construction according to the layout shown in Figure 1. There are 60 well tower pile foundations 10 in total, and the divisions are around the freezing hole 2. The drill bit is rotated to drill into the hole, the entire section of the steel cage is hooped for positioning and forming, the entire section of the hole is directly lowered into the cage, and the conduit is poured underwater to form a construction process of self-mixing concrete to form a pile.

冻结造孔采用的PHP—HPAN泥浆和C-PAN-KHm泥浆,泥浆沟槽3布满吊盘4四周,桩基施工采用膨润土自制的泥浆,采用钢板焊移动泥浆池,用管道连接的方法,避免了桩基泥浆与冻结泥浆交叉混合。PHP-HPAN mud and C-PAN-KHm mud are used for frozen hole making. Mud grooves 3 are covered around hanging pan 4. Pile foundation construction uses bentonite homemade mud. Steel plate welding is used to move the mud pool and pipes are used to connect. Cross-mixing of pile foundation mud and frozen mud is avoided.

部分桩基与冻结管6道相邻小于100mm时,必须先施工桩基,后施工冻结孔2,避免冻结管6挤压变形或者移位,造成冻结管6的报废。When part of the pile foundation is less than 100mm adjacent to the frozen pipe 6, the pile foundation must be constructed first, and then the frozen hole 2 must be constructed to avoid extrusion deformation or displacement of the frozen pipe 6, which will cause the frozen pipe 6 to be scrapped.

桩基与冻结管6道重叠时,按图2所示将冻结管6偏离原位置,与桩基至少保持0.3m距离,当施工至桩基底部后,采用陀螺导向法将冻结管6导向原设计位置。When the pile foundation overlaps with the 6 frozen pipes, deviate the frozen pipe 6 from the original position as shown in Figure 2, and keep a distance of at least 0.3m from the pile foundation. When the construction reaches the bottom of the pile foundation, guide the frozen pipe 6 to the original design position.

(2)井塔桩基10与冻结造孔平行施工(2) Well tower pile foundation 10 is constructed in parallel with frozen hole making

冻结凿孔结束后,井塔和冻结开始施工,冻结采用一次冻全深的冻结施工方案,低温大流量的冻结方式,积极期盐水温度为-32℃,维护期盐水温度为-24~-26℃;井塔采用滑膜施工工艺,在井塔滑膜施工的同时,冻结站同时建设,并开始进行冻结。After the freeze drilling is completed, the well tower and the freeze start construction. The freeze adopts a one-time freeze full-depth freeze construction plan, a low-temperature and high-flow freeze method, and the brine temperature in the active period is -32°C, and the brine temperature in the maintenance period is -24~-26 ℃; The well tower adopts the synovial film construction technology, and at the same time as the synovial film construction of the well tower, the freezing station is constructed at the same time, and the freezing begins.

井塔基础开挖时,由于基础深度为-6m,必须要保护冻结管6,第一防止机械破坏,第二防止土方坍塌挤压导致冻结管6变形。When the well tower foundation is excavated, since the foundation depth is -6m, the frozen pipe 6 must be protected, firstly to prevent mechanical damage, and secondly to prevent the deformation of the frozen pipe 6 caused by the collapse and extrusion of the earthwork.

(3)井塔与凿井、冻结平行施工(3) Parallel construction of well tower, sinking and freezing

井塔施工至33m,冻结至1.8个月后,井筒5具备开工条件,开始掘砌施工。井筒5施工前一个月为设备安装时间如图4所示,此时井塔暂停施工,停工时间安排在冬歇期,缩短了井塔的总工期。冻结工程在此期间继续施工,同时安装天轮、稳绞系统,冬歇期结束后,井塔继续向上施工,井筒5向下掘砌,冻结也继续工作。After the well tower was constructed to 33m and frozen for 1.8 months, the wellbore 5 was ready for start-up, and the excavation and laying began. One month before the construction of well shaft 5 is the equipment installation time as shown in Figure 4. At this time, the construction of the well tower is suspended, and the shutdown time is arranged during the winter break, which shortens the total construction period of the well tower. During this period, the freezing project continued to be constructed, and the sky wheel and the anchoring system were installed at the same time. After the winter break, the well tower continued to be constructed upwards, and the well shaft 5 was dug downward, and the freezing also continued to work.

实施例2:Example 2:

本实施例针对泊江海子矿副井采用永久井塔凿井施工,井塔高度82米,最大容量52709.8m3m3,最大梁跨度26m,最大支撑高度为17m,共分+15.5m、+24m、+32.5m和+44.9m四个楼层。凿井施工平台利用+15.5m和+24m两楼层,并在+26.2m利用井塔中央4根矩形布置的大型钢混立柱自制提升绞车 21用天轮平台。In this example, the auxiliary shaft of Bojiang Haizi Mine is drilled with a permanent shaft tower. The height of the shaft tower is 82 meters, the maximum capacity is 52709.8m3m 3 , the maximum beam span is 26m, and the maximum support height is 17m. It is divided into +15.5m, +24m, Four floors of +32.5m and +44.9m. The sinking construction platform uses two floors of +15.5m and +24m, and at +26.2m uses four large steel-concrete columns arranged in the center of the well tower to make a self-made hoisting winch 21 sky wheel platform.

泊江海子矿主、副井井塔均采用钢筋混凝土箱型结构,采用滑模施工,连续浇筑混凝土,施工速度快,模板重复利用率高,可大大降低工程造价。为了全面准确的掌握主井承台内部温度场发展变化规律,在承台中部沿四周均匀布置1号和2号两串测温线,每串12个测点,共计24个测点。其中1 号测温线布置在中排桩位置,2号测温线布置在承台的内排桩位置。井塔基础承台受力特征监测的主要内容包括承台底部压力监测、承台内部钢筋应力监测、以及混凝土温度应力监测等方面的内容,在此基础上采用有限元方法,模拟分析了外荷载作用下的承台受力变化特征及大体积混凝土内部温度应力的分布规律。沿基础周边的四个角点及近南北向平行基础边的侧线上,布置井塔基础沉降测点。Both the main shaft and auxiliary shaft towers of Bojiang Haizi Mine adopt reinforced concrete box structure, adopt sliding form construction, and pour concrete continuously. The construction speed is fast and the formwork reuse rate is high, which can greatly reduce the project cost. In order to fully and accurately grasp the development and change of the internal temperature field of the main shaft cap, two series of temperature measuring lines No. 1 and No. 2 are evenly arranged around the middle of the cap, with 12 measuring points in each string, a total of 24 measuring points. Among them, the No. 1 temperature measuring line is arranged at the position of the middle row of piles, and the No. 2 temperature measuring line is arranged at the inner row of piles of the cap. The main content of the monitoring of the mechanical characteristics of the foundation cap of the well tower includes the monitoring of the bottom pressure of the cap, the monitoring of the internal reinforcement stress of the cap, and the monitoring of the temperature and stress of the concrete. On this basis, the finite element method is used to simulate and analyze the external load. The variation characteristics of the bearing capacity of the bearing platform and the distribution law of the internal temperature stress of the mass concrete. Along the four corner points around the foundation and the lateral line near the north-south direction parallel to the foundation edge, the settlement measuring points of the well tower foundation are arranged.

通过综合技术分析,在井塔基础浇筑过程中,分2层、四个区块进行浇筑,混凝土利用热水搅拌、输送车采用裹棉毯保温,入模装置全封闭,井塔内每间隔数米放置一个火炉,井塔四周用厚塑料布封闭,确保混凝土凝固条件。Through comprehensive technical analysis, during the pouring process of the well tower foundation, it is divided into two floors and four blocks for pouring. A stove is placed in the middle of the well, and the well tower is closed with thick plastic sheets to ensure the conditions for the concrete to solidify.

将永久井塔的+32.6m、+24.0m两楼层通过铺设钢梁及50mm厚木板全断面封闭,四周增设防护栏及防坠网,确保两楼层以下施工安全。+32.6m以上井塔扎筋、支模、浇筑混凝土等工序正常施工。+24.0m同步施工提升绞车 21用天轮平台(即自制+26.2m平台),天轮梁及提升天轮正常安装。两部绞车 21提升系统未形成前,利用+24.0m平台安装天轮、钢梁及地面两台25t稳车设置临时提升排矸系统,井筒5掘砌同步进行。The two floors of +32.6m and +24.0m of the permanent shaft tower are closed by laying steel beams and 50mm thick wooden boards in full section, and guardrails and anti-falling nets are added around to ensure the safety of construction below the two floors. +32.6m above the well tower reinforcement, formwork, pouring concrete and other processes are under normal construction. +24.0m synchronous construction hoisting winch 21 uses sky wheel platform (namely self-made +26.2m platform), sky wheel beam and lifting sky wheel are installed normally. Before the two winches 21 hoisting system is formed, use the +24.0m platform to install the skywheel, steel beams and two 25t stabilizer trucks on the ground to set up a temporary lifting gangue removal system, and the excavation and laying of shaft 5 is carried out synchronously.

(1)、临时凿井系统(1) Temporary sinking system

a、提升排矸a. Improve waste discharge

利用+24.0m平台N2、N3号工字钢梁通过40mm钢丝绳“人”字形悬挂 20t定滑轮,相对标高位置+20.5m,东西稳车群中选定两台靠近井筒5提升中心线的25t稳车,通过38mm钢丝绳提升5m3吊桶,迎头留座底罐,井下摘挂钩,装罐不能过满。利用东侧溜矸系统排矸至地面,采用人工、铲车清理矸土。同时用一天时间将+11.5m翻矸台完善,将副钩溜矸系统形成,施工期间,井下撤人。Utilize the I-shaped steel beams N2 and N3 on the +24.0m platform to suspend the 20t fixed pulley in a "herringbone" shape with a 40mm steel wire rope. The car lifts the 5m3 bucket through a 38mm steel wire rope, leaves a bottom tank head-on, picks up the hook in the well, and the tank cannot be overfilled. Use the gangue sliding system on the east side to discharge the gangue to the ground, and use manual and forklift trucks to clean up the gangue soil. At the same time, it took one day to complete the +11.5m gangue turning platform, and the auxiliary hook sliding system was formed. During the construction period, people were removed from the mine.

b、井筒5掘进b. Excavation of shaft 5

采用2台PC60小松挖掘机挖土、铁锹修边,小挖机直接将土运到井口,利用铲车人工及时清理。采用先挖超前小井,短段台阶式挖掘,最后人工刷帮至设计圈径,对冻结沟槽墙体进行打点柱支撑。施工至3m深左右,小挖机无法从工作面将土直接抛出时,采用临时提升排矸方案施工。Two PC60 Komatsu excavators were used to excavate the soil and the edge was trimmed with shovels. The small excavators directly transported the soil to the wellhead, and the forklift was used to manually clean it in time. First dig the small well in advance, short step excavation, and finally manually brush the side to the design circle diameter, and support the wall of the frozen trench with dotted columns. When the construction reaches a depth of about 3m and the small excavator cannot directly throw the soil out from the working face, a temporary lifting and gangue removal scheme will be used for construction.

c、浇筑用模板悬吊及下灰系统c. Formwork suspension and ash lowering system for pouring

液压金属整体模板高4m、半径6.05m,利用+15.5m已经安装完成的天轮平台设置悬吊,选用该平台2个模板悬吊天轮、一套压风管悬吊及导向天轮、1套排水管悬吊及导向天轮共4个悬吊点,相应4台稳车同步升降模板以满足砌壁使用。井筒5掘砌20m前浇筑混凝土使用远距离输送泵车直接入模,20m以后下下灰系统另制,具体方案:先安装双层吊盘4,悬吊绳及吊盘4高约9m,其下方模板高4m,迎头4m掘进段高,通过计算可以安装封口盘。浇筑混凝土时,在下层吊盘4利用溜槽直接入模。The overall formwork of the hydraulic metal is 4m high and the radius is 6.05m. The skywheel platform that has been installed at +15.5m is used to set up the suspension. The platform uses 2 templates to suspend the skywheel, a set of air pressure pipe suspension and guide skywheel, 1 There are 4 suspension points for the set of drainage pipe suspension and guide sky wheel, and the corresponding 4 stable cars synchronously lift the formwork to meet the use of wall building. Shaft 5 is excavated 20m before the concrete is poured into the mould, and the ash lowering system is made separately after 20m. The lower formwork is 4m high, and the head-on excavation section is 4m high, and the sealing plate can be installed through calculation. When pouring concrete, utilize the chute to directly enter the mold at the lower floor suspension plate 4.

(2)、井塔施工(2), well tower construction

井塔剪力墙及承重边柱采用组装液压滑模施工,楼板及中间“井”字形支撑立柱采用现支木模板浇筑,每小班钢管架设工30人,钢筋工20人,木工10人,浇筑采用泵送入模,局部泵车大臂无法施工,则利用吊塔悬吊灰槽入模,确保入模温度不低于15℃,并严格控制混凝土初凝时间。井塔+32.6m 以上扎筋、支模、浇筑混凝土等工序正常施工时,下层天轮平台同步安装,要切实做好坠物防护。The shear wall and load-bearing side columns of the well tower are constructed by assembling hydraulic sliding form, and the floor and the middle "well"-shaped support column are poured with existing wooden formwork. There are 30 steel pipe erectors, 20 steel workers, and 10 carpenters in each small class. Pumping is used to enter the mold, and the boom of some pump trucks cannot be constructed, so the ash tank is suspended by the crane tower to enter the mold to ensure that the temperature of the mold entering is not lower than 15°C, and the initial setting time of the concrete is strictly controlled. During the normal construction of the well tower +32.6m above the reinforcement, formwork, concrete pouring and other processes, the sky wheel platform on the lower floor is installed synchronously, and the falling objects must be effectively protected.

(3)、绞车21提升天轮平台安装(3), Winch 21 lifts the sky wheel platform installation

+26.2m天轮平台为自制凿井平台,利用5根H700×30钢梁焊接于永久井塔中间四根立柱预埋钢板上,形成平台框架,其上架设5根Ⅰ63a及2根 950×300组合焊钢梁作为天轮梁。主副提升均选用2JKZ-4.0m/15双滚筒大绞车21,提升天轮直径3.0m。井塔施工的同时,在+24m平台以上东西两侧剪力墙各留有8m×9m(高×宽)天轮梁及天轮吊装用窗口,利用一台50t吊车与塔吊配合使用,将各梁及天轮安装就位。The +26.2m skywheel platform is a self-made sinking platform, using 5 H700×30 steel beams welded to the four pre-embedded steel plates in the middle of the permanent well tower to form a platform frame, on which 5 Ⅰ63a and 2 950×300 steel beams are erected Combined welded steel beams are used as sky wheel beams. 2JKZ-4.0m/15 double-drum large winch 21 is used for the main and auxiliary lifting, and the diameter of the lifting sky wheel is 3.0m. At the same time as the construction of the shaft tower, 8m×9m (height×width) sky wheel beams and windows for hoisting of the sky wheel are left on the east and west sides of the shear walls above the +24m platform. Install in place.

(4)、实施效果(4) Implementation effect

至2009年12月30日,井塔施工至40.8m,副井已完成永久锁口施工、 +24.0m及+26.2m天轮平台安装完毕、两部4m大绞车21及20部稳车均已试验正常运转、井筒5掘砌32m,同时完成液压金属模板、双层凿井吊盘4井下组装、封口盘安装、井口双轨道铺设等重点工序,仅用时24d。As of December 30, 2009, the construction of the well tower reached 40.8m, the permanent locking construction of the auxiliary well was completed, the +24.0m and +26.2m skywheel platforms were installed, and the two 4m large winches 21 and 20 stabilizers were completed. The test was running normally, the wellbore 5 was dug and laid for 32m, and key processes such as hydraulic metal formwork, double-layer sinking suspension plate 4 underground assembly, sealing plate installation, and wellhead double track laying were completed in only 24 days.

综上所述,本发明的井井塔、井筒冻结、掘砌交叉平行施工方法,解决了现有多个工序在技术要求上存在的占用工期时间长、费用增大的问题,提出了多个工序交叉平行施工的新方法,与常规施工方法相比,可实现6个月内开始井筒掘砌,填补高寒地区井塔、井筒冻结、掘砌交叉平行快速施工的空白,是煤矿安全高效建井的重要组成部分,社会、经济效益显著。In summary, the well tower, well shaft freezing, excavation and masonry cross-parallel construction method of the present invention solves the problems of long construction period and increased cost in the technical requirements of the existing multiple processes, and proposes several Compared with the conventional construction method, the new method of intersecting and parallel construction of the process can realize the excavation of the shaft within 6 months, filling the gaps in the high-cold area of the well tower, the freezing of the shaft, and the rapid construction of the intersecting and parallel construction of the excavation. It is a safe and efficient construction of coal mines. An important part of it, the social and economic benefits are remarkable.

以上所述仅为本发明的优选实施例,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included within the protection scope of the present invention.

Claims (10)

1.一种井塔主体施工与井筒掘砌、冻结平行施工系统,其特征在于,平行施工系统包括:冻结系统、井塔施工系统和井筒掘砌系统;1. A well tower main body construction and shaft excavation and laying, freezing parallel construction system, is characterized in that, parallel construction system comprises: freezing system, well tower construction system and shaft excavation and laying system; 所述冻结系统设置在井筒外围四周;所述冻结系统包括冻结管,所述冻结管邻近所述井筒周向设置,多个所述冻结管组成圆形冻结管幕;The freezing system is arranged around the periphery of the wellbore; the freezing system includes freezing pipes, the freezing pipes are arranged adjacent to the circumference of the wellbore, and a plurality of the freezing pipes form a circular freezing pipe curtain; 所述井塔施工系统位于所述井筒掘砌系统上方;所述井塔施工系统包括井塔框架,所述井塔框架设有第一层平台和第二层平台,所述井塔框架用于提供承载与支撑;The well tower construction system is located above the shaft excavation and laying system; the well tower construction system includes a well tower frame, and the well tower frame is provided with a first floor platform and a second floor platform, and the well tower frame is used for Provide bearing and support; 所述井筒掘砌系统位于所述冻结系统上方;所述井筒掘砌系统包括凿井系统和井筒浇筑系统;所述井筒浇筑系统设置在所述井塔框架上。The shaft excavation system is located above the freezing system; the shaft excavation system includes a sinking system and a shaft pouring system; the shaft pouring system is arranged on the well tower frame. 2.如权利要求1所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,其特征在于,所述井塔施工系统还包括结构柱,四个所述结构柱跨设在在所述井筒上方,所述第一层平台和第二层平台连接在所述结构柱上,所述第二层平台位于所述第一层平台上方,所述第二层平台上铺设有厚木板,所述厚木板用于对第二层平台以下空间断面封闭;所述井塔框架四周还设有井塔防护栏,所述井塔防护栏设置在与第二层平台同一高度处的井塔外侧壁面上;2. A kind of well tower body construction as claimed in claim 1 and shaft digging, freezing parallel construction system, it is characterized in that, described well tower construction system also comprises structural column, and four described structural columns are arranged on Above the well shaft, the first-layer platform and the second-layer platform are connected to the structural column, the second-layer platform is located above the first-layer platform, and planks are laid on the second-layer platform , the thick wooden board is used to close the space section below the second floor platform; the well tower frame is also provided with a well tower guardrail, and the well tower guardrail is arranged on the well tower at the same height as the second floor platform on the outer wall; 优选地,所述井塔防护栏上还配套设有井塔防坠网。Preferably, the well tower guardrail is also equipped with a well tower anti-falling net. 3.如权利要求1所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,其特征在于,所述井塔施工系统还包括绞车提升系统和临时排矸系统,所述绞车提升系统和所述临时排矸系统设在第一层平台上,所述临时排矸系统位于所述绞车提升系统远离所述井塔框架的一侧;所述绞车提升系统包括绞车天轮平台,绞车天轮梁,绞车提升天轮;所述绞车天轮梁设置在所述绞车天轮平台上,所述提绞车升天轮设置在所述绞车天轮梁上;3. A parallel construction system for well tower main body construction, shaft excavation, and freezing as claimed in claim 1, characterized in that, the well tower construction system also includes a winch lifting system and a temporary gangue discharge system, and the winch lifts The system and the temporary gangue removal system are arranged on the first floor platform, and the temporary gangue removal system is located on the side of the winch hoisting system away from the well tower frame; the winch hoisting system includes a winch sky wheel platform, a winch The sky wheel beam, the winch lifts the sky wheel; the winch sky wheel beam is set on the winch sky wheel platform, and the winch lifting wheel is set on the winch sky wheel beam; 所述临时排矸系统包括排矸天轮平台,排矸天轮梁,排矸天轮和稳车装置,所述排矸天轮梁设置在所述排矸天轮平台上,所述排矸天轮设置在所述排矸天轮梁上;所述稳车装置设置在地面基础上;The temporary gangue discharge system includes a gangue discharge sky wheel platform, a gangue discharge sky wheel beam, a gangue discharge sky wheel and a vehicle stabilizing device, the gangue discharge sky wheel beam is arranged on the gangue discharge sky wheel platform, and the gangue discharge sky wheel The sky wheel is set on the gangue discharge sky wheel beam; the vehicle stabilizing device is set on the ground foundation; 优选地,所述稳车装置为25t稳车装置。Preferably, the vehicle stabilizing device is a 25t vehicle stabilizing device. 4.如权利要求1所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,其特征在于,所述凿井统包括临时凿井系统,单侧溜矸系统和副溜钩矸系统;所述临时凿井系统包括定滑轮,所述定滑轮通过钢丝绳人字形悬挂在第一层平台下表面,所述单侧溜矸系统设置在第一层平台上,所述副溜钩矸系统设置在所述井塔框架外侧壁,所述副溜钩矸系统位于所述第一层平台与地面中间高度处;4. A parallel construction system for well tower main body construction, shaft excavation, and freezing as claimed in claim 1, characterized in that, the drilling system includes a temporary drilling system, a single-side sliding system and an auxiliary sliding hook gangue system; the temporary sinking system includes a fixed pulley, and the fixed pulley is suspended on the lower surface of the first floor platform through a wire rope in a herringbone shape; the single-side sliding gangue system is arranged on the first floor platform; The system is set on the outer wall of the well tower frame, and the auxiliary chute hook gangue system is located at the middle height between the first floor platform and the ground; 优选地,所述定滑轮为20t定滑轮。Preferably, the fixed pulley is a 20t fixed pulley. 5.如权利要求1所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,其特征在于,所述井筒浇筑系统包括压风管悬吊天轮,所述压风管悬吊天轮设置在所述第二层平台的中心的右侧,所述压风管悬吊天轮通过钢丝绳连接有压风管导向天轮,所述压风管导向天轮位于所述的二层平台的最右端;所述压风管悬吊天轮相对于所述第二层平台的中心线所在平面对称处设有排水管悬吊天轮,所述排水管悬吊天轮通过所述钢丝绳连接有排水管导向天轮,所述排水管导向天轮设置在所述第二层平台的最左端。5. A parallel construction system for well tower main body construction, shaft excavation, and freezing as claimed in claim 1, characterized in that, the shaft pouring system includes a sky pulley suspended by a compressed air pipe, and the suspended air wheel by the compressed air pipe The sky wheel is set on the right side of the center of the second-floor platform, and the air pressure pipe suspension sky wheel is connected with the air pressure pipe guide sky wheel through a steel wire rope, and the air pressure pipe guide sky wheel is located on the second floor. The rightmost end of the platform; the suspension sky wheel of the pressure air pipe is provided with a drainage pipe suspension sky wheel at a plane symmetrical to the center line of the second floor platform, and the suspension sky wheel of the drainage pipe passes through the steel wire rope It is connected with a drainage pipe guiding sky wheel, and the drainage pipe guiding sky wheel is arranged at the leftmost end of the second-floor platform. 6.如权利要求1所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,其特征在于,所述井筒浇筑系统还包括双层吊盘,所述双层吊盘通过钢丝绳悬挂在井筒内,所述井筒内壁上设有吊盘通过溜槽,便于所述双层吊盘上下移动;所述井筒上端还设有封口盘,所述封口盘为带有通孔的薄饼圆盘。6. A parallel construction system for well tower main body construction, shaft excavation, and freezing as claimed in claim 1, characterized in that, the shaft pouring system further includes a double-layer hanging pan, and the double-layer hanging pan is suspended by a wire rope In the well shaft, a hanging plate is provided on the inner wall of the well shaft to pass through the chute, so that the double-layer hanging pan can move up and down; the upper end of the well shaft is also provided with a sealing plate, and the sealing plate is a pancake disc with through holes. 7.如权利要求1所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,其特征在于,冻结系统还包括冻结沟槽,所述冻结沟槽呈圆环状;所述冻结沟槽外围沿所述冻结沟槽圆周方向设有支撑柱,多个所述支撑柱形成支撑体系用于对所述冻结沟槽外壁支护。7. A kind of well tower main body construction as claimed in claim 1 and shaft digging, freezing parallel construction system, is characterized in that, freezing system also comprises freezing groove, and described freezing groove is annular; Said freezing The periphery of the groove is provided with supporting columns along the circumferential direction of the freezing groove, and a plurality of the supporting columns form a supporting system for supporting the outer wall of the freezing groove. 8.如权利要求1所述的一种井塔主体施工与井筒掘砌、冻结平行施工系统,其特征在于,所述井塔框架外侧壁上还设有安全防护棚,所述安全防护棚为空心圆环状,所述安全防护棚位于所述副溜钩矸系统与所述第一层平台之间,用于对下层工作空间提供安全屏障。8. A kind of well tower main body construction as claimed in claim 1 and shaft digging, freezing parallel construction system, it is characterized in that, the outer wall of the well tower frame is also provided with a safety protection shed, the safety protection shed is The safety shed is in the shape of a hollow ring, and is located between the auxiliary chute hook gangue system and the first floor platform, and is used to provide a safety barrier for the lower working space. 9.一种如权利要求1至8任一项所述的井塔主体施工与井筒掘砌、冻结平行施工系统的施工方法,其特征在于,所述方法包括以下步骤:9. A construction method of the well tower main body construction and shaft excavation and freezing parallel construction system according to any one of claims 1 to 8, characterized in that the method comprises the following steps: 步骤1,施工准备与工期预算:Step 1, construction preparation and construction period budget: 冻结造孔以及冻结沟槽及设备安装之后进行冻结施工,冻结施工预算工期为60天,在冻结沟槽安装的同时,对井筒掘砌做准备,安装掘砌设备;掘砌设备安装预算工期为31天,掘砌设备安装完成之后开始掘砌施工;Freezing construction will be carried out after the frozen hole making, frozen trench and equipment installation. The budgeted construction period for the frozen construction is 60 days. While the frozen trench is installed, prepare for the excavation of the shaft and install the excavation equipment; the budgeted period for the installation of the excavation equipment is 31 days, the excavation and masonry construction will start after the installation of the excavation and masonry equipment is completed; 步骤2,井塔与冻结工程平行施工:Step 2, parallel construction of the well tower and the freezing project: 冻结造孔结束后,井塔基础开挖时,采用分层、分块开挖方法,减小不均匀侧向土应力,对冻结管周围留核心土防止机械破坏;冻结采用一次冻全深的冻结施工方案,井塔采用滑膜施工工艺;在井塔滑膜施工的同时,冻结站同时建设,并开始进行冻结;将冻结站设置在远离井口的地方,冻结施工所需的冻结盐水可用主冻结管敷设至井口,将更大的空间留给井塔和井筒的施工单位;井塔基础剪力墙在施工时,冻结工程需要不间断施工;主冻结管要穿越剪力墙,提前要预留好冻结管道的孔洞位置,并且需要对主冻结管支撑,加固;After the freezing hole is completed, when excavating the foundation of the well tower, the method of layering and block excavation shall be adopted to reduce the uneven lateral soil stress, and the core soil around the frozen pipe shall be left to prevent mechanical damage; In the freezing construction plan, the well tower adopts the synovial film construction technology; at the same time as the synovial film construction of the well tower, the freezing station is constructed at the same time, and the freezing starts; the freezing station is set far from the wellhead, and the frozen brine required for freezing construction can be used in the main The freezing pipe is laid to the wellhead, leaving more space for the construction unit of the well tower and well shaft; when the foundation shear wall of the well tower is being constructed, the freezing project needs to be uninterrupted; The hole position of the frozen pipe should be reserved, and the main frozen pipe needs to be supported and reinforced; 步骤3,井塔与凿井、冻结平行施工:Step 3, parallel construction of the well tower, sinking and freezing: 先期建设2层井塔框架结构,通过铺设钢梁及50mm厚木板全断面封闭,四周增设防护栏及防坠网,形成安全防护棚,确保下部施工安全;第2层以上井塔扎筋、支模、浇筑混凝土等工序正常施工;第一层平台同步施工提升绞车用天轮平台,天轮梁及提升天轮正常安装;两部绞车提升系统未形成前,利用第一层平台安装天轮、钢梁及地面两台25t稳车设置临时提升排矸系统,形成井筒掘砌体系;井筒掘砌工程必须有三个方向的施工空间,设计稳绞系统占据东西两个方向,南侧用于排掘砌矸石,北侧用于人员上下、材料打运;在掘砌爆破时,井塔上面施工人员停止作业。The 2-story well tower frame structure is constructed in advance, and the entire section is closed by laying steel beams and 50mm thick wooden boards, and guardrails and anti-falling nets are added around to form a safety protection shed to ensure the safety of the lower construction; Formwork, concrete pouring and other processes are under normal construction; the first floor platform is constructed synchronously to lift the skywheel platform for the winch, the skywheel beam and the hoisting skywheel are installed normally; before the lifting system of the two winches is formed, use the first floor platform to install the skywheel, The steel beam and the two 25t stabilizing vehicles on the ground are equipped with a temporary lifting and drainage system to form a shaft excavation system; the shaft excavation project must have construction space in three directions, and the design stabilization system occupies two directions in the east and west, and the south side is used for excavation. The gangue is built, and the north side is used for personnel to go up and down and transport materials; during the excavation and blasting, the construction personnel on the well tower stop working. 10.如权利要求9所述的井塔主体施工与井筒掘砌、冻结平行施工系统的施工方法,其特征在于,所述步骤2中,在井塔滑膜施工过程中,除了井塔自身的高空作业安全防护外,采用大于5mm厚的钢板将冻结沟槽全部封闭,防止高空坠物砸漏冻结沟槽内的冻结管道,造成冻结盐水的流失。10. The construction method of the construction of the main body of the well tower as claimed in claim 9 and the parallel construction system of shaft excavation and laying, freezing, is characterized in that, in the step 2, during the construction of the well tower synovial film, except for the construction of the well tower itself In addition to the safety protection of high-altitude operations, the freezing trenches are completely sealed with steel plates thicker than 5mm, so as to prevent falling objects from dropping and leaking the frozen pipes in the freezing trenches, resulting in the loss of frozen brine.
CN201810799130.4A 2018-07-19 2018-07-19 A kind of headframe main body construction and self well digging freeze parallel construction system and method Active CN108952728B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810799130.4A CN108952728B (en) 2018-07-19 2018-07-19 A kind of headframe main body construction and self well digging freeze parallel construction system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810799130.4A CN108952728B (en) 2018-07-19 2018-07-19 A kind of headframe main body construction and self well digging freeze parallel construction system and method

Publications (2)

Publication Number Publication Date
CN108952728A true CN108952728A (en) 2018-12-07
CN108952728B CN108952728B (en) 2019-06-25

Family

ID=64482042

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810799130.4A Active CN108952728B (en) 2018-07-19 2018-07-19 A kind of headframe main body construction and self well digging freeze parallel construction system and method

Country Status (1)

Country Link
CN (1) CN108952728B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110155867A (en) * 2019-06-25 2019-08-23 陕西陕煤韩城矿业有限公司 Milling coal hole winch overtravel protection system
CN110566173A (en) * 2019-09-12 2019-12-13 杰瑞能源服务有限公司 Fracturing system with antifreezing performance
CN113356859A (en) * 2021-06-10 2021-09-07 山东黄金矿业(莱州)有限公司三山岛金矿 Pouring and mounting construction method between permanent engineering layers of blind shaft well cap

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536249A (en) * 2012-02-23 2012-07-04 中煤第五建设有限公司 Fast construction method of headframe lifting system
CN106761765A (en) * 2016-12-24 2017-05-31 中铁十八局集团有限公司 One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method
CN108035335A (en) * 2017-09-30 2018-05-15 中煤第五建设有限公司 A kind of construction freezing method well shaft type underground parking garage method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536249A (en) * 2012-02-23 2012-07-04 中煤第五建设有限公司 Fast construction method of headframe lifting system
CN106761765A (en) * 2016-12-24 2017-05-31 中铁十八局集团有限公司 One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method
CN108035335A (en) * 2017-09-30 2018-05-15 中煤第五建设有限公司 A kind of construction freezing method well shaft type underground parking garage method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110155867A (en) * 2019-06-25 2019-08-23 陕西陕煤韩城矿业有限公司 Milling coal hole winch overtravel protection system
CN110566173A (en) * 2019-09-12 2019-12-13 杰瑞能源服务有限公司 Fracturing system with antifreezing performance
CN110566173B (en) * 2019-09-12 2021-11-12 杰瑞能源服务有限公司 Fracturing system with antifreezing performance
CN113356859A (en) * 2021-06-10 2021-09-07 山东黄金矿业(莱州)有限公司三山岛金矿 Pouring and mounting construction method between permanent engineering layers of blind shaft well cap
CN113356859B (en) * 2021-06-10 2024-02-20 山东黄金矿业(莱州)有限公司三山岛金矿 Interlayer pouring and installing construction method for permanent engineering of blind vertical shaft cap

Also Published As

Publication number Publication date
CN108952728B (en) 2019-06-25

Similar Documents

Publication Publication Date Title
CN101139838B (en) Construction method for high artesian area ultra-deep foundation pit
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN106013052B (en) The construction method of steel sheet pile and open caisson Combined type underground garage parking
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN101215834A (en) Construction Method of Outrigger Type Diaphragm Wall
CN112554177A (en) Construction method of ultra-long small-diameter cast-in-situ bored pile
CN111576431A (en) Excavation method for foundation pit of four-layer subway station
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN114016513B (en) A time-sequential excavation method for complex foundation pit group support system
CN111236241B (en) Reinforcement and excavation method of subway foundation pit in soft and water-rich stratum based on half-cover excavation method
CN207892615U (en) A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN107227961A (en) Heavy caliber dewatering well construction method in metro built by mining method hole
CN106013053A (en) Steel sheet pile support construction method for building underground garage open caisson
JP7352048B1 (en) Construction method of large-span station with open wings and semi-top-down excavation and semi-reverse drilling
CN111101540B (en) Construction method for passing existing electric power tunnel on open cut tunnel
CN108952728B (en) A kind of headframe main body construction and self well digging freeze parallel construction system and method
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
CN104264663A (en) Hard cutting construction technology for secant piles
CN111455977A (en) Underground continuous wall construction method
CN105714769A (en) Construction method for anti-sliding cast-in-place pile
CN108843325A (en) Cross parallel construction system and method are built in vertical headframe, pit shaft freezing, pick
CN111218938A (en) Excavation construction method for foundation pit above existing tunnel
CN108678750B (en) A kind of headframe pile foundation and freezing drill bore parallel construction system and parallel construction method
CN114991165A (en) Construction method for subway deep foundation pit adjacent to railway business line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant