CN108818115A - Automatic feeding - Google Patents

Automatic feeding Download PDF

Info

Publication number
CN108818115A
CN108818115A CN201810737886.6A CN201810737886A CN108818115A CN 108818115 A CN108818115 A CN 108818115A CN 201810737886 A CN201810737886 A CN 201810737886A CN 108818115 A CN108818115 A CN 108818115A
Authority
CN
China
Prior art keywords
plunger
wedge
fixed
stamping mechanism
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810737886.6A
Other languages
Chinese (zh)
Other versions
CN108818115B (en
Inventor
谢小文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou University
Original Assignee
Wenzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou University filed Critical Wenzhou University
Priority to CN201810737886.6A priority Critical patent/CN108818115B/en
Publication of CN108818115A publication Critical patent/CN108818115A/en
Application granted granted Critical
Publication of CN108818115B publication Critical patent/CN108818115B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23QDETAILS, COMPONENTS, OR ACCESSORIES FOR MACHINE TOOLS, e.g. ARRANGEMENTS FOR COPYING OR CONTROLLING; MACHINE TOOLS IN GENERAL CHARACTERISED BY THE CONSTRUCTION OF PARTICULAR DETAILS OR COMPONENTS; COMBINATIONS OR ASSOCIATIONS OF METAL-WORKING MACHINES, NOT DIRECTED TO A PARTICULAR RESULT
    • B23Q7/00Arrangements for handling work specially combined with or arranged in, or specially adapted for use in connection with, machine tools, e.g. for conveying, loading, positioning, discharging, sorting
    • B23Q7/14Arrangements for handling work specially combined with or arranged in, or specially adapted for use in connection with, machine tools, e.g. for conveying, loading, positioning, discharging, sorting co-ordinated in production lines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Forging (AREA)
  • Press Drives And Press Lines (AREA)

Abstract

本发明属于机械加工技术领域,具体公开了自动送料装置,包括机架、传动单元、存料单元和加工单元,加工单元包括工作台和冲压机构;存料单元包括切割机构和存放筒;传动单元包括连通管和转动柱,转动柱与机架之间连接有扭簧;连通管内装有液压油,连通管的一侧内滑动连接有第一柱塞,另一侧内滑动连接有第二柱塞,第一柱塞、第二柱塞分别位于冲压机构相邻的两侧,存料单元位于第一柱塞和冲压机构之间;连通管内滑动连接有活塞,活塞上固定有一端穿过连通管的推杆,转动柱上开有螺旋形的凹槽,推杆上设有连接杆;转动柱与冲压机构之间连接有拉线。采用本发明的装置,能够实现自动送料,有效降低工人的劳动强度。

The invention belongs to the technical field of mechanical processing, and specifically discloses an automatic feeding device, including a frame, a transmission unit, a storage unit and a processing unit. The processing unit includes a workbench and a stamping mechanism; the storage unit includes a cutting mechanism and a storage cylinder; the transmission unit It includes a connecting pipe and a rotating column. A torsion spring is connected between the rotating column and the frame; the connecting pipe is filled with hydraulic oil, and one side of the connecting pipe is slidably connected to the first plunger, and the other side is slidably connected to the second column. Plug, the first plunger and the second plunger are respectively located on both sides adjacent to the stamping mechanism, and the storage unit is located between the first plunger and the stamping mechanism; a piston is slidably connected in the communication pipe, and one end of the piston is fixed through the communication pipe. The push rod of the pipe has a spiral groove on the rotating column, and a connecting rod is arranged on the pushing rod; a pull wire is connected between the rotating column and the stamping mechanism. By adopting the device of the invention, automatic material feeding can be realized, and the labor intensity of workers can be effectively reduced.

Description

自动送料装置Automatic feeding device

技术领域technical field

本发明属于机械加工技术领域,尤其涉及一种自动送料装置。The invention belongs to the technical field of mechanical processing, and in particular relates to an automatic feeding device.

背景技术Background technique

镦粗是使坯料高度减小而横截面增大的锻造工序,镦粗加工通常包括以下步骤:将长条形的坯料切割成固定长度的段状,然后对段状坯料加热,最后利用冲头对段状的坯料进行冲压,使坯料的高度减小。在压镦机床上进行大批量镦粗加工时,每分钟可加工23-27个,冲头的工作行程可根据镦粗的高度一次性调整好。Upsetting is a forging process that reduces the height of the billet and increases the cross-section. The upsetting process usually includes the following steps: cutting the long billet into a fixed-length segment, then heating the segmental billet, and finally using the punch Stamping is performed on a segmented blank to reduce the height of the blank. When carrying out large-scale upsetting processing on the upsetting machine tool, 23-27 pieces can be processed per minute, and the working stroke of the punch can be adjusted at one time according to the height of the upsetting.

目前镦粗加工的送料通常采用人工送料的方式,工人操作时要用手将坯料推入冲头范围,操作频率须和机床压头上下来回的频率相同。由于镦粗件批量大、操作时间长,对操作工而言劳动强度大,且存在很大的安全隐患。At present, the feeding of upsetting process usually adopts the manual feeding method. When the worker operates, the blank should be pushed into the range of the punch by hand, and the operating frequency must be the same as the frequency of the machine tool's indenter going up and down. Due to the large batch of upsetting parts and long operation time, the labor intensity is high for the operator, and there is a great potential safety hazard.

发明内容Contents of the invention

本发明的目的在于提供一种自动送料装置,以解决人工送料劳动强度大、安全隐患大的问题。The object of the present invention is to provide an automatic feeding device to solve the problems of high labor intensity and potential safety hazards in manual feeding.

为了达到上述目的,本发明的基础方案为:自动送料装置,包括机架、传动单元、存料单元和加工单元,加工单元包括工作台和对坯料进行镦粗加工的冲压机构;存料单元位于工作台的上方,存料单元包括用于将坯料切割成固定高度的切割机构和固定在机架上的存放筒,存放筒与工作台之间的距离为1-1.5倍待镦粗坯料的长度;传动单元包括连通管和转动连接在机架上的转动柱,转动柱与机架之间连接有扭簧;连通管内装有液压油,连通管的一侧内滑动连接有第一柱塞,连通管内设有限位槽,第一柱塞上设有滑动连接在限位槽内的凸起;连通管的另一侧内滑动连接有第二柱塞,第一柱塞、第二柱塞分别位于冲压机构相邻的两侧,存料单元位于第一柱塞和冲压机构之间,第一柱塞用于将存料单元上的坯料推送到冲压机构的下方;连通管内滑动连接有活塞,活塞上固定有一端穿过连通管的推杆,转动柱上开有螺旋形的凹槽,推杆上设有一端卡合在凹槽内的连接杆;转动柱上缠绕有线圈,线圈的自由端固定在冲压机构上。In order to achieve the above object, the basic solution of the present invention is: an automatic feeding device, including a frame, a transmission unit, a storage unit and a processing unit, and the processing unit includes a workbench and a stamping mechanism for upsetting the blank; the storage unit is located at Above the workbench, the storage unit includes a cutting mechanism for cutting the blank into a fixed height and a storage cylinder fixed on the frame. The distance between the storage cylinder and the workbench is 1-1.5 times the length of the blank to be upset The transmission unit includes a connecting pipe and a rotating column that is rotatably connected to the frame, and a torsion spring is connected between the rotating column and the frame; hydraulic oil is installed in the connecting pipe, and a first plunger is slidably connected to one side of the connecting pipe. A limiting groove is provided in the connecting pipe, and a protrusion that is slidably connected in the limiting groove is provided on the first plunger; a second plunger is slidably connected in the other side of the connecting pipe, and the first plunger and the second plunger are respectively Located on both sides adjacent to the stamping mechanism, the storage unit is located between the first plunger and the stamping mechanism, the first plunger is used to push the blank on the storage unit to the bottom of the stamping mechanism; a piston is slidably connected in the communication pipe, A push rod with one end passing through the connecting pipe is fixed on the piston, a spiral groove is opened on the rotating column, and a connecting rod with one end engaged in the groove is provided on the rotating column; The end is fixed on the stamping mechanism.

本基础方案的工作原理在于:将切割完成后长度符合要求的坯料放置在存放筒中,使冲压机构下行,冲压机构下行过程中线圈上的线逐渐变松,在扭簧的作用下转动柱发生转动,转动柱通过推杆驱动活塞往第一柱塞一侧滑动,连通管内的液压油驱动第一柱塞向外部伸出,第一柱塞将存放筒下方切割完成后的坯料推向冲压机构,当第一柱塞运动到极限位置时,坯料被推至冲压机构的下方,冲压机构继续下行即能对该坯料进行镦粗。镦粗加工完成后,使冲压机构上行,冲压机构通过线圈带动转动柱往反方向转动,转动柱通过推杆驱动活塞往第二柱塞一侧滑动,活塞驱使液压油向第二柱塞一侧流动,液压推动第二柱塞向外伸出,第二柱塞能将镦粗完成的工件推离冲压机构。The working principle of this basic scheme is: place the blank with the required length after cutting in the storage cylinder, make the stamping mechanism go down, the wire on the coil gradually becomes loose during the down process of the stamping mechanism, and the rotating column rotates under the action of the torsion spring , the rotating column drives the piston to slide towards the first plunger side through the push rod, and the hydraulic oil in the communication pipe drives the first plunger to extend outward, and the first plunger pushes the cut blank under the storage cylinder to the stamping mechanism, When the first plunger moves to the limit position, the blank is pushed to the bottom of the punching mechanism, and the punching mechanism continues to go down to upset the blank. After the upsetting process is completed, the stamping mechanism is moved upward, the stamping mechanism drives the rotating column to rotate in the opposite direction through the coil, the rotating column drives the piston to slide to the second plunger side through the push rod, and the piston drives the hydraulic oil to the second plunger side flow, the hydraulic pressure pushes the second plunger to extend outward, and the second plunger can push the upsetting workpiece away from the stamping mechanism.

本基础方案的有益效果在于:The beneficial effects of this basic plan are:

1、使用本发明申请的装置,能够实现镦粗加工的自动送料,镦粗加工完成后能够自动将工件推走,送料以及卸料均不需工人参与,降低工人的劳动强度以及能够减少用工成本。1. Using the device applied for in the present invention can realize the automatic feeding of upsetting processing. After the upsetting processing is completed, the workpiece can be automatically pushed away. The feeding and unloading do not require workers to participate, reducing the labor intensity of workers and reducing labor costs. .

2、第一柱塞、第二柱塞工作的动力均来源于冲压机构,在本发明申请中不需额外增设动力装置驱动第一柱塞、第二柱塞运动,有效节省装置的生产成本。2. The working power of the first plunger and the second plunger comes from the stamping mechanism. In the application of the present invention, no additional power device is required to drive the movement of the first plunger and the second plunger, which effectively saves the production cost of the device.

3、通过合理的设置,第一柱塞、第二柱塞和冲压机构三者之间的运动相互配合、互不干涉,整个加工过程高效、流畅。3. Through reasonable setting, the movements among the first plunger, the second plunger and the stamping mechanism cooperate with each other without interfering with each other, and the whole processing process is efficient and smooth.

进一步,切割机构包括滑动套、顶出结构、滑动连接在滑动套内的第一楔块和固定在第一楔块上且位于存放筒一侧的切割刀;第一楔块上开有滑槽,滑槽内滑动连接有卡条,卡条与滑槽之间连接有第一弹簧;滑动套上开有能供卡条卡合的通孔,通孔位于靠近存放筒的一侧;第一楔块上连接有用于使第一楔块复位的第二弹簧;顶出结构包括顶出杆、电磁铁、用于控制电磁铁断电第一开关、用于控制电磁铁通电的第二开关和连接在机架与顶出杆之间的第三弹簧,顶出杆内设有能与电磁铁相吸的磁铁,顶出杆与通孔相对且能伸入通孔中;电磁铁固定在滑动套上且位于通孔的一侧,第一开关固定在滑动套的内壁上且与顶出杆相对;冲压机构包括按压块和第二楔块,第二开关固定在机架上,第二开关与按压块正对,按压块运动到下极限位置时,按压块能够按压第二开关;第二楔块的斜面与第一楔块的斜面相对,第二楔块上行能够驱动第一楔块向存放筒一侧运动。Further, the cutting mechanism includes a sliding sleeve, an ejection structure, a first wedge slidably connected in the sliding sleeve, and a cutting knife fixed on the first wedge and located on one side of the storage cylinder; the first wedge is provided with a slide groove , a card bar is slidably connected in the chute, and a first spring is connected between the card bar and the chute; a through hole for the card bar to be engaged is opened on the sliding sleeve, and the through hole is located on the side close to the storage tube; the first The wedge is connected with a second spring for resetting the first wedge; the ejector structure includes an ejector rod, an electromagnet, a first switch for controlling the power-off of the electromagnet, a second switch for controlling the power-on of the electromagnet and The third spring is connected between the frame and the ejector rod. The ejector rod is provided with a magnet capable of attracting the electromagnet. The ejector rod is opposite to the through hole and can extend into the through hole; the electromagnet is fixed on the slide The first switch is fixed on the inner wall of the sliding sleeve and is opposite to the ejector rod; the stamping mechanism includes a pressing block and a second wedge, the second switch is fixed on the frame, and the second switch It is opposite to the pressing block, and when the pressing block moves to the lower limit position, the pressing block can press the second switch; the slope of the second wedge is opposite to the slope of the first wedge, and the upward movement of the second wedge can drive the first wedge to Storage barrel side movement.

通过设置切割机构,无需事先对长条形的坯料进行切割,直接将长条形的坯料放置在存放筒内,在冲压机构工作的过程中,切割刀能够自动将坯料切割成长度符合要求的坯料,有效减少事先切割的步骤,提高加工的效率。By setting up the cutting mechanism, there is no need to cut the long blanks in advance, and the long blanks are directly placed in the storage cylinder. During the working process of the stamping mechanism, the cutting knife can automatically cut the blanks into lengths that meet the requirements. , effectively reduce the steps of cutting in advance and improve the efficiency of processing.

进一步,冲压机构包括固定在机架上的液压缸和固定在液压缸活塞杆上的安装板,安装板上设有冲头;第二楔块和按压块均固定在安装板上。通过液压缸驱动冲头上下运动,操作简单、方便。Further, the stamping mechanism includes a hydraulic cylinder fixed on the frame and a mounting plate fixed on the piston rod of the hydraulic cylinder, and a punch is arranged on the mounting plate; the second wedge and the pressing block are both fixed on the mounting plate. The hydraulic cylinder drives the punch to move up and down, which is easy and convenient to operate.

进一步,连通管上设有储液箱,储液箱位于活塞靠近第一柱塞的一侧,连通管上均设有能够连通储液箱和连通管的单向进液阀和单向排液阀。连通管上设有储液箱,根据连通管内压强的情况,储液箱自动吸入或排出液压油,确保连通管内的压强维持在相对稳定的状态。Further, a liquid storage tank is provided on the communication pipe, and the liquid storage tank is located on the side of the piston close to the first plunger, and a one-way liquid inlet valve and a one-way liquid discharge that can communicate with the liquid storage tank and the communication pipe are provided on the communication pipe valve. The connecting pipe is provided with a liquid storage tank, and according to the pressure in the connecting pipe, the liquid storage tank automatically sucks in or discharges hydraulic oil to ensure that the pressure in the connecting pipe is maintained at a relatively stable state.

进一步,工作台上开有位于冲压机构一侧的落料槽,落料槽与第二柱塞相对。设置落料槽,落料槽能够有效对加工后的工件进行收集。Further, a blanking groove located on one side of the stamping mechanism is opened on the workbench, and the blanking groove is opposite to the second plunger. A blanking chute is provided, which can effectively collect processed workpieces.

附图说明Description of drawings

图1是本发明自动送料装置实施例的俯视图;Fig. 1 is the top view of automatic feeding device embodiment of the present invention;

图2是图1中传动单元的剖视图;Fig. 2 is a sectional view of the transmission unit in Fig. 1;

图3是存料单元的正剖视图;Figure 3 is a front sectional view of the storage unit;

图4是冲压机构的结构示意图。Fig. 4 is a structural schematic diagram of the stamping mechanism.

具体实施方式Detailed ways

下面通过具体实施方式进一步详细说明:The following is further described in detail through specific implementation methods:

说明书附图1至4中的附图标记包括:工作台10、落料槽11、冲压机构20、液压缸21、安装板22、按压块23、冲头24、第二楔块25、连通管30、第二柱塞31、第一柱塞32、活塞33、推杆34、连接杆341、转动柱40、凹槽41、线圈42、储液箱50、单向进液阀51、单向排液阀52、存放筒60、坯料61、切割机构70、滑动套71、通孔711、第一楔块72、滑槽721、第一弹簧722、卡条723、电磁铁73、第二弹簧74、顶出杆75、第三弹簧751、切割刀76、第一开关77。The reference signs in the accompanying drawings 1 to 4 of the specification include: workbench 10, blanking chute 11, stamping mechanism 20, hydraulic cylinder 21, mounting plate 22, pressing block 23, punch 24, second wedge 25, connecting pipe 30. Second plunger 31, first plunger 32, piston 33, push rod 34, connecting rod 341, rotating column 40, groove 41, coil 42, liquid storage tank 50, one-way liquid inlet valve 51, one-way Drain valve 52, storage cylinder 60, blank 61, cutting mechanism 70, sliding sleeve 71, through hole 711, first wedge 72, chute 721, first spring 722, clip 723, electromagnet 73, second spring 74, ejector rod 75, third spring 751, cutting knife 76, first switch 77.

如图1所示,自动送料装置,包括机架、传动单元、存料单元和加工单元,加工单元包括工作台10和对坯料61进行镦粗加工的冲压机构20,工作台10上开有位于冲压机构20前侧的落料槽11,落料槽11用于存放加工完成后的工件。冲压机构20位于工作台10的上方,结合图4所示,冲压机构20包括固定在机架上的液压缸21和固定在液压缸21活塞杆上的安装板22,安装板22的下表面焊接有冲头24和按压块23,安装板22的右侧壁上焊接有第二楔块25。As shown in Figure 1, the automatic feeding device includes a frame, a transmission unit, a storage unit and a processing unit. The processing unit includes a workbench 10 and a stamping mechanism 20 for upsetting the blank 61. The workbench 10 is provided with a The blanking chute 11 on the front side of the stamping mechanism 20 is used to store the finished workpieces. The stamping mechanism 20 is positioned at the top of the workbench 10. As shown in FIG. A punch 24 and a pressing block 23 are arranged, and a second wedge 25 is welded on the right side wall of the mounting plate 22 .

结合图2所示,传动单元包括连通管30和转动连接在机架上的转动柱40,转动柱40与机架之间连接有扭簧,转动柱40的圆周表面开有螺旋形的凹槽41。转动柱40上缠绕有线圈42,线圈42的自由端固定在安装板22上,液压缸21驱动安装板22向上活动时,安装板22通过线圈42带动转动柱40发生转动;液压缸21驱动安装板22向下活动时,线圈42上的线放松,在扭簧的作用下,转动柱40反转复位。连通管30内装有液压油,连通管30的一侧内滑动且密封连接有第一柱塞32,连通管30的另一侧内滑动且密封连接有第二柱塞31,第一柱塞32位于冲压机构20的右侧,第二柱塞31位于冲压机构20的后侧,存料单元位于第一柱塞32与冲压机构20之间,第一柱塞32用于将存料单元上的切割完成后的坯料61推送到冲压机构20的正下方。连通管30的内壁上开有限位槽,第一柱塞32上固定有滑动连接在限位槽内的凸起,限位槽和凸起的设置限制了第一柱塞32的活动范围,避免第一柱塞32的运动超范围。连通管30内滑动且密封连接有活塞33,活塞33上固定有左侧穿过连通管30左侧壁的推杆34,推杆34滑动且密封连接在连通管30的左侧壁上。推杆34上固定有位于连通管30外的连接杆341,连接杆341的一端卡合在凹槽41内,转动柱40发生转动时,能够通过凹槽41、连接杆341驱动推杆34滑动。连通管30上设有储液箱50,储液箱50位于活塞33靠近第一柱塞32的一侧,连通管30上均设有能够连通储液箱50和连通管30的单向进液阀51和单向排液阀52。以活塞33为界线划分连通管30的左右两侧,连通管30右侧内的压强增大时,单向排液阀52自动打开,连通管30右侧内的液压油能够通过单向排液阀52进入储液箱50内;连通管30右侧内的压强减小时,单向进液阀51自动打开,储液箱50内的液压油能够通过单向进液阀51进入连通管30右侧内。As shown in FIG. 2, the transmission unit includes a connecting pipe 30 and a rotating column 40 that is rotatably connected to the frame. A torsion spring is connected between the rotating column 40 and the frame. The circumferential surface of the rotating column 40 is provided with a spiral groove. 41. A coil 42 is wound on the rotating column 40, and the free end of the coil 42 is fixed on the mounting plate 22. When the hydraulic cylinder 21 drives the mounting plate 22 to move upward, the mounting plate 22 drives the rotating column 40 to rotate through the coil 42; the hydraulic cylinder 21 drives the installation When the plate 22 moves downward, the wire on the coil 42 is relaxed, and under the action of the torsion spring, the rotating post 40 reverses and resets. Hydraulic oil is housed in the communication pipe 30, a first plunger 32 is slid and sealed in one side of the communication pipe 30, and a second plunger 31 is slid and sealed in the other side of the communication pipe 30, and the first plunger 32 Located on the right side of the stamping mechanism 20, the second plunger 31 is positioned at the rear side of the stamping mechanism 20, and the storage unit is located between the first plunger 32 and the stamping mechanism 20, and the first plunger 32 is used to store the material on the storage unit. The blank 61 after cutting is pushed directly below the stamping mechanism 20 . A limiting groove is opened on the inner wall of the connecting pipe 30, and a protrusion that is slidably connected in the limiting groove is fixed on the first plunger 32. The setting of the limiting groove and the protrusion limits the range of motion of the first plunger 32, avoiding The movement of the first plunger 32 is out of range. A piston 33 is slidably and sealingly connected in the communication pipe 30 , and a push rod 34 passing through the left side wall of the communication pipe 30 is fixed on the piston 33 . The push rod 34 is fixed with a connecting rod 341 outside the connecting pipe 30, and one end of the connecting rod 341 is engaged in the groove 41. When the rotating column 40 rotates, the push rod 34 can be driven to slide through the groove 41 and the connecting rod 341. . A liquid storage tank 50 is provided on the communication pipe 30, and the liquid storage tank 50 is located on the side of the piston 33 close to the first plunger 32. The communication pipe 30 is provided with a one-way liquid inlet that can communicate with the liquid storage tank 50 and the communication pipe 30. valve 51 and one-way drain valve 52. The left and right sides of the communication pipe 30 are divided by the piston 33. When the pressure in the right side of the communication pipe 30 increases, the one-way drain valve 52 is automatically opened, and the hydraulic oil in the right side of the communication pipe 30 can be drained through the one-way drain. The valve 52 enters the liquid storage tank 50; when the pressure in the right side of the communication pipe 30 decreases, the one-way liquid inlet valve 51 is automatically opened, and the hydraulic oil in the liquid storage tank 50 can enter the right side of the communication pipe 30 through the one-way liquid inlet valve 51. side inside.

存料单元位于工作台10的上方,结合图3所示,存料单元包括切割机构70和固定在机架上的存放筒60,存放筒60与工作台10之间的距离为1-1.5倍待镦粗坯料61的长度,在本实施例中,存放筒60与工作台10之间的距离为1.1倍待镦粗坯料61的长度。切割机构70位于存放筒60的左侧,切割机构70用于将存放筒60内的坯料61切割成固定高度的段状。切割机构70包括滑动套71、顶出结构、滑动连接在滑动套71内的第一楔块72和固定在第一楔块72右侧壁上的切割刀76,切割刀76到工作台10之间的距离等于待镦粗坯料61的长度。第一楔块72的斜面与第二楔块25的斜面相对,第二楔块25上行时,第二楔块25对第一楔块72施加作用力,能够驱动第一楔块72向存放筒60一侧运动。第一楔块72的上部开有滑槽721,滑槽721内滑动连接有卡条723,卡条723的下表面与滑槽721的底部之间连接有第一弹簧722。滑动套71的上部开有通孔711,卡条723与通孔711正对时,在第一弹簧722的作用力下卡条723能够卡合在通孔711中。第一楔块72上的卡条723向通孔711一侧运动的过程中,第一楔块72驱使切割刀76向坯料61一侧伸出,切割刀76能够完成对坯料61的切割。第一楔块72与存放筒60的外壁之间连接第二弹簧74。顶出结构包括顶出杆75、电磁铁73、用于控制电磁铁73断电第一开关77、用于控制电磁铁73通电的第二开关和连接在机架与顶出杆75之间的第三弹簧751,按压第一开关77后,第一开关77控制电磁铁73断电,按压第二开关后,第二开关控制电磁铁73通电。电磁铁73固定在滑动套71上且位于通孔711的左下侧,第一开关77固定在滑动套71的内壁上且位于通孔711的右下方。第二开关固定在机架上,第二开关与按压块23正对,当按压块23向下运动到冲头24运动行程的终点时,按压块23能够按压第二开关。顶出杆75与通孔711正对且能伸入通孔711中,顶出杆75内固定有磁铁,第三弹簧751对顶出杆的拉力作用大于磁铁与不通电的电磁铁73之间产生的吸引力,而电磁铁73通电后与磁铁产生的吸引力大于第三弹簧751对顶出杆的拉力,即电磁铁73不通电时,磁铁与电磁铁73之间的吸引力不足以驱使顶出杆75伸入通孔711中,而电磁铁73通电时,磁铁与电磁铁73产生较大的吸引力,电磁铁73驱使顶出杆75向下运动伸入通孔711中,顶出杆75伸入通孔711后会对第一开关77进行按压。The storage unit is located above the workbench 10. As shown in FIG. 3, the storage unit includes a cutting mechanism 70 and a storage cylinder 60 fixed on the frame. The distance between the storage cylinder 60 and the workbench 10 is 1-1.5 times The length of the blank 61 to be upset, in this embodiment, the distance between the storage cylinder 60 and the worktable 10 is 1.1 times the length of the blank 61 to be upset. The cutting mechanism 70 is located on the left side of the storage tube 60 , and the cutting mechanism 70 is used for cutting the blank 61 in the storage tube 60 into segments with a fixed height. The cutting mechanism 70 comprises a sliding sleeve 71, an ejection structure, a first wedge 72 slidably connected in the sliding sleeve 71, and a cutting knife 76 fixed on the right side wall of the first wedge 72, and the cutting knife 76 is connected to the workbench 10. The distance between them is equal to the length of the blank 61 to be upset. The slope of the first wedge 72 is opposite to the slope of the second wedge 25. When the second wedge 25 goes up, the second wedge 25 exerts a force on the first wedge 72, which can drive the first wedge 72 to the storage cylinder. 60 side movement. The upper part of the first wedge 72 is provided with a chute 721 , and a clip 723 is slidably connected to the chute 721 , and a first spring 722 is connected between the lower surface of the clip 723 and the bottom of the chute 721 . The upper part of the sliding sleeve 71 is provided with a through hole 711 . When the clamping strip 723 is facing the through hole 711 , the clamping strip 723 can be engaged in the through hole 711 under the force of the first spring 722 . When the clip 723 on the first wedge 72 moves toward the through hole 711 , the first wedge 72 drives the cutting knife 76 to protrude toward the blank 61 , and the cutting knife 76 can complete the cutting of the blank 61 . A second spring 74 is connected between the first wedge 72 and the outer wall of the storage tube 60 . The ejector structure includes an ejector rod 75, an electromagnet 73, a first switch 77 for controlling the power-off of the electromagnet 73, a second switch for controlling the power-on of the electromagnet 73, and a switch connected between the frame and the ejector rod 75. For the third spring 751, after the first switch 77 is pressed, the first switch 77 controls the electromagnet 73 to be powered off, and after the second switch is pressed, the second switch controls the electromagnet 73 to be powered on. The electromagnet 73 is fixed on the sliding sleeve 71 and located at the lower left side of the through hole 711 , and the first switch 77 is fixed on the inner wall of the sliding sleeve 71 and located at the lower right side of the through hole 711 . The second switch is fixed on the frame, and the second switch is facing the pressing block 23. When the pressing block 23 moves down to the end point of the punch 24 movement stroke, the pressing block 23 can press the second switch. The ejector rod 75 is opposite to the through hole 711 and can be inserted into the through hole 711. A magnet is fixed in the ejector rod 75, and the pulling force of the third spring 751 on the ejector rod is greater than that between the magnet and the non-energized electromagnet 73. The attractive force generated by the electromagnet 73 is greater than the pulling force of the third spring 751 on the ejector rod after the electromagnet 73 is energized. The ejector rod 75 stretches into the through hole 711, and when the electromagnet 73 is energized, the magnet and the electromagnet 73 generate a relatively large attraction force, and the electromagnet 73 drives the ejector rod 75 to move downwards and extend into the through hole 711 to eject the ejector rod 75. After the rod 75 extends into the through hole 711 , it will press the first switch 77 .

具体实施过程如下:人为对第一楔块72施加指向右侧的作用力,使第一楔块72上的卡条723卡合在通孔711上,往存放筒60中加入长条形的坯料61,此时坯料61是放置在切割刀76上的。操作液压缸21,使安装板22带动冲头24和按压块23向下运动到冲头24行程的终点,当冲头24下行到终点位置时,按压块23按压第二开关,电磁铁73通电,磁铁与电磁铁73相吸,电磁铁73驱使顶出杆75向下运动伸入通孔711中,顶出杆75将卡条723完全压回滑槽721内,此时由于没有了卡条723的限位作用,在第二弹簧74的作用下,第一楔块72和切割刀76向左侧滑动,恢复原位,存放筒60内的坯料61落在了工作台10上。顶出杆75伸入通孔711后会对第一开关77进行按压,第一开关77控制电磁铁73断电,在第三弹簧751的作用下,顶出杆75向上运动脱离通孔711,最后恢复原位。The specific implementation process is as follows: artificially apply a force pointing to the right on the first wedge 72, so that the clip 723 on the first wedge 72 is engaged with the through hole 711, and a long blank is added to the storage cylinder 60. 61, the blank 61 is placed on the cutting knife 76 at this time. Operate the hydraulic cylinder 21 to make the mounting plate 22 drive the punch 24 and the pressing block 23 to move down to the end of the stroke of the punch 24. When the punch 24 goes down to the end position, the pressing block 23 presses the second switch, and the electromagnet 73 is energized , the magnet and the electromagnet 73 attract each other, the electromagnet 73 drives the ejector rod 75 to move downwards and extend into the through hole 711, and the ejector rod 75 completely presses the clip 723 back into the chute 721. 723, under the action of the second spring 74, the first wedge 72 and the cutting knife 76 slide to the left and return to their original positions, and the blank 61 in the storage tube 60 falls on the workbench 10. After the ejector rod 75 extends into the through hole 711, it will press the first switch 77, and the first switch 77 controls the electromagnet 73 to power off. Return to original position at last.

再次操作液压缸21,使安装板22带动冲头24和第二楔块25向上运动,安装板22上行过程中,安装板22通过线圈42带动转动柱40往固定方向发生转动,此时转动柱40通过凹槽41、连接杆341驱动推杆34向左侧运动。第二楔块25随安装板22上行到一定位置时,第二楔块25与第一楔块72的斜面相互接触,第二楔块25对第一楔块72施加作用力,使第一楔块72和切割刀76沿滑动套71向右侧滑动,在这个过程中,切割刀76向坯料61一侧伸出,对坯料61进行切割,使坯料61切割成段状,当第一楔块72运动到右极限位置时,卡条723再次卡合在通孔711上。在安装板22上行过程中,活塞33沿着连通管30的内壁向左侧滑动,连通管30左侧内的压强增大,液压油向第二柱塞31一侧的运动,推动第二柱塞31向外伸出(若此时工作台10上存在镦粗完成的工件,第二柱塞31会将该工件推入落料槽11中)。Operate the hydraulic cylinder 21 again to make the mounting plate 22 drive the punch 24 and the second wedge 25 to move upwards. During the upward movement of the mounting plate 22, the mounting plate 22 drives the rotating column 40 to rotate in a fixed direction through the coil 42. At this time, the rotating column 40 drives the push rod 34 to move to the left through the groove 41 and the connecting rod 341. When the second wedge 25 moves up to a certain position along with the mounting plate 22, the slopes of the second wedge 25 and the first wedge 72 contact each other, and the second wedge 25 exerts a force on the first wedge 72, so that the first wedge The block 72 and the cutting knife 76 slide to the right along the sliding sleeve 71. In this process, the cutting knife 76 protrudes to one side of the blank 61 to cut the blank 61, so that the blank 61 is cut into segments. When the first wedge When 72 moves to the right limit position, the clip bar 723 is engaged on the through hole 711 again. During the upward movement of the mounting plate 22, the piston 33 slides to the left along the inner wall of the communication pipe 30, the pressure in the left side of the communication pipe 30 increases, and the hydraulic oil moves to the side of the second plunger 31, pushing the second column The plug 31 protrudes outwards (if there is an upsetting workpiece on the workbench 10 at this moment, the second plunger 31 will push the workpiece into the blanking groove 11).

冲头24上行到其运动行程的终点时,再次操作液压缸21,使安装板22带动冲头24、按压块23和第二楔块25下行,此时线圈42上的线逐渐变松,在扭簧的作用下转动柱40的转动方向发生改变,转动柱40通过连接杆341、推杆34驱动活塞33沿连通管30的内壁向右侧滑动。活塞33推动连通管30右侧内的液压油向第一柱塞32一侧流动,液压油驱动第一柱塞32向连通管30的外部伸出,第一柱塞32将存放筒60下方切割完成后的段状坯料61推向冲压机构20。当第一柱塞32运动到极限位置时,坯料61被推至冲头24的正下方,冲头24继续下行即能对该坯料61进行镦粗。当第一柱塞32运动到极限位置不能继续伸出时,连通管30右侧内的压强增大,单向排液阀52自动打开,连通管30右侧内的液压油通过单向排液阀52进入储液箱50内,避免连通管30的压强过大而发生爆炸。与此同时,连通管30左侧内的压强减小,第二柱塞31逐渐缩回连通管30内。When the punch 24 goes up to the end of its motion stroke, operate the hydraulic cylinder 21 again, so that the mounting plate 22 drives the punch 24, the pressing block 23 and the second wedge 25 to go down. At this time, the wire on the coil 42 becomes loose gradually. Under the action of the torsion spring, the rotation direction of the rotating column 40 changes, and the rotating column 40 drives the piston 33 to slide rightward along the inner wall of the connecting pipe 30 through the connecting rod 341 and the push rod 34 . The piston 33 pushes the hydraulic oil in the right side of the communication pipe 30 to flow to the first plunger 32 side, and the hydraulic oil drives the first plunger 32 to protrude to the outside of the communication pipe 30, and the first plunger 32 cuts the bottom of the storage cylinder 60 The completed segment blank 61 is pushed toward the punching mechanism 20 . When the first plunger 32 moves to the limit position, the blank 61 is pushed directly under the punch 24 , and the punch 24 continues to go down to upset the blank 61 . When the first plunger 32 moves to the limit position and cannot continue to extend, the pressure in the right side of the communication pipe 30 increases, and the one-way drain valve 52 automatically opens, and the hydraulic oil in the right side of the communication pipe 30 passes through the one-way drain. The valve 52 enters the liquid storage tank 50 to prevent the communication pipe 30 from being exploded due to excessive pressure. At the same time, the pressure in the left side of the communication tube 30 decreases, and the second plunger 31 gradually retracts into the communication tube 30 .

以上所述的仅是本发明的实施例,方案中公知的具体结构及特性等常识在此未作过多描述。应当指出,对于本领域的技术人员来说,在不脱离本发明结构的前提下,还可以作出若干变形和改进,这些也应该视为本发明的保护范围,这些都不会影响本发明实施的效果和专利的实用性。本申请要求的保护范围应当以其权利要求的内容为准,说明书中的具体实施方式等记载可以用于解释权利要求的内容。What is described above is only an embodiment of the present invention, and common knowledge such as specific structures and characteristics known in the scheme are not described here too much. It should be pointed out that for those skilled in the art, under the premise of not departing from the structure of the present invention, several modifications and improvements can also be made, and these should also be regarded as the protection scope of the present invention, and these will not affect the implementation of the present invention. Effects and utility of patents. The scope of protection required by this application shall be based on the content of the claims, and the specific implementation methods and other records in the specification may be used to interpret the content of the claims.

Claims (5)

1.自动送料装置,其特征在于:包括机架、传动单元、存料单元和加工单元,加工单元包括工作台和对坯料进行镦粗加工的冲压机构;存料单元位于工作台的上方,存料单元包括用于将坯料切割成固定高度的切割机构和固定在机架上的存放筒,存放筒与工作台之间的距离为1-1.5倍待镦粗坯料的长度;传动单元包括连通管和转动连接在机架上的转动柱,转动柱与机架之间连接有扭簧;连通管内装有液压油,连通管的一侧内滑动连接有第一柱塞,连通管的另一侧内滑动连接有第二柱塞,连通管内设有限位槽,第一柱塞上设有滑动连接在限位槽内的凸起;第一柱塞、第二柱塞分别位于冲压机构相邻的两侧,存料单元位于第一柱塞和冲压机构之间,第一柱塞用于将存料单元上的坯料推送到冲压机构的下方;连通管内滑动连接有活塞,活塞上固定有一端穿过连通管的推杆,转动柱上开有螺旋形的凹槽,推杆上设有一端卡合在凹槽内的连接杆;转动柱上缠绕有线圈,线圈的自由端固定在冲压机构上。1. The automatic feeding device is characterized in that: it includes a frame, a transmission unit, a storage unit and a processing unit, and the processing unit includes a workbench and a stamping mechanism for upsetting the blank; the storage unit is located above the workbench, and the storage unit The material unit includes a cutting mechanism for cutting the blank into a fixed height and a storage cylinder fixed on the frame. The distance between the storage cylinder and the worktable is 1-1.5 times the length of the blank to be upset; the transmission unit includes a connecting pipe It is connected with the rotating column on the frame, and a torsion spring is connected between the rotating column and the frame; hydraulic oil is installed in the connecting pipe, and the first plunger is slidably connected to one side of the connecting pipe, and the other side of the connecting pipe The inner sliding connection has a second plunger, the communication pipe is provided with a limit groove, and the first plunger is provided with a protrusion that is slidably connected in the limit groove; the first plunger and the second plunger are respectively located On both sides, the storage unit is located between the first plunger and the stamping mechanism, and the first plunger is used to push the blank on the storage unit to the bottom of the stamping mechanism; a piston is slidably connected to the communication pipe, and a piston is fixed on one end through the Through the push rod of the connecting pipe, there is a spiral groove on the rotating column, and a connecting rod with one end engaged in the groove is arranged on the pushing rod; a coil is wound on the rotating column, and the free end of the coil is fixed on the stamping mechanism . 2.根据权利要求1所述的自动送料装置,其特征在于:切割机构包括滑动套、顶出结构、滑动连接在滑动套内的第一楔块和固定在第一楔块上且位于存放筒一侧的切割刀;第一楔块上开有滑槽,滑槽内滑动连接有卡条,卡条与滑槽之间连接有第一弹簧;滑动套上开有能供卡条卡合的通孔,通孔位于靠近存放筒的一侧;第一楔块上连接有用于使第一楔块复位的第二弹簧;顶出结构包括顶出杆、电磁铁、用于控制电磁铁断电第一开关、用于控制电磁铁通电的第二开关和连接在机架与顶出杆之间的第三弹簧,顶出杆内设有能与电磁铁相吸的磁铁,顶出杆与通孔相对且能伸入通孔中;电磁铁固定在滑动套上且位于通孔的一侧,第一开关固定在滑动套的内壁上且与顶出杆相对;冲压机构包括按压块和第二楔块,第二开关固定在机架上,第二开关与按压块正对,按压块运动到下极限位置时,按压块能够按压第二开关;第二楔块的斜面与第一楔块的斜面相对,第二楔块上行能够驱动第一楔块向存放筒一侧运动。2. The automatic feeding device according to claim 1, characterized in that: the cutting mechanism comprises a sliding sleeve, an ejection structure, a first wedge slidably connected in the sliding sleeve, and a first wedge fixed on the first wedge and located in the storage cylinder. A cutting knife on one side; a chute is opened on the first wedge, and a clamping strip is slidably connected in the chute, and a first spring is connected between the clamping strip and the chute; A through hole, the through hole is located on the side close to the storage cylinder; the first wedge is connected with a second spring for resetting the first wedge; the ejector structure includes an ejector rod, an electromagnet, and a The first switch, the second switch used to control the electrification of the electromagnet, and the third spring connected between the frame and the ejector rod, the ejector rod is provided with a magnet capable of attracting the electromagnet, and the ejector rod and the The holes are opposite and can extend into the through hole; the electromagnet is fixed on the sliding sleeve and is located on one side of the through hole, the first switch is fixed on the inner wall of the sliding sleeve and is opposite to the ejector rod; the stamping mechanism includes a pressing block and a second Wedge, the second switch is fixed on the frame, the second switch is facing the pressing block, when the pressing block moves to the lower limit position, the pressing block can press the second switch; the inclined plane of the second wedge and the first wedge The inclined surfaces are opposite to each other, and the upward movement of the second wedge can drive the first wedge to move toward one side of the storage cylinder. 3.根据权利要求2所述的自动送料装置,其特征在于:冲压机构包括固定在机架上的液压缸和固定在液压缸活塞杆上的安装板,安装板上设有冲头;第二楔块和按压块均固定在安装板上。3. The automatic feeding device according to claim 2, characterized in that: the stamping mechanism includes a hydraulic cylinder fixed on the frame and a mounting plate fixed on the piston rod of the hydraulic cylinder, the mounting plate is provided with a punch; the second Both the wedge and the pressing block are fixed on the mounting plate. 4.根据权利要求1-3任一项所述的自动送料装置,其特征在于:连通管上设有储液箱,储液箱位于活塞靠近第一柱塞的一侧,连通管上均设有能够连通储液箱和连通管的单向进液阀和单向排液阀。4. The automatic feeding device according to any one of claims 1-3, characterized in that: the connecting pipe is provided with a liquid storage tank, the liquid storage tank is located on the side of the piston close to the first plunger, and the connecting pipes are equipped with There is a one-way liquid inlet valve and a one-way liquid discharge valve that can communicate with the liquid storage tank and the communication pipe. 5.根据权利要求1-3任一项所述的自动送料装置,其特征在于:工作台上开有位于冲压机构一侧的落料槽,落料槽与第二柱塞相对。5. The automatic feeding device according to any one of claims 1-3, characterized in that: a blanking groove located on one side of the stamping mechanism is opened on the workbench, and the blanking groove is opposite to the second plunger.
CN201810737886.6A 2018-07-06 2018-07-06 Automatic feeding Expired - Fee Related CN108818115B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810737886.6A CN108818115B (en) 2018-07-06 2018-07-06 Automatic feeding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810737886.6A CN108818115B (en) 2018-07-06 2018-07-06 Automatic feeding

Publications (2)

Publication Number Publication Date
CN108818115A true CN108818115A (en) 2018-11-16
CN108818115B CN108818115B (en) 2019-11-05

Family

ID=64135561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810737886.6A Expired - Fee Related CN108818115B (en) 2018-07-06 2018-07-06 Automatic feeding

Country Status (1)

Country Link
CN (1) CN108818115B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112207357A (en) * 2020-09-22 2021-01-12 湖州至诚精密金属科技股份有限公司 A kind of alloy steel pipe production equipment and production process
CN117297173A (en) * 2023-11-29 2023-12-29 新乡市中汇过滤技术有限公司 Composite filter element winding device and composite filter element preparation method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07328992A (en) * 1994-06-02 1995-12-19 Yokohama Rubber Co Ltd:The Automatic punching method and automatic punching device for rubber test piece
CN201023125Y (en) * 2007-03-20 2008-02-20 吐哈石油勘探开发指挥部机械厂 Thin and long tube end upsetting automatic feeding and discharging device
CN102825429A (en) * 2012-09-06 2012-12-19 浙江科朗汽车配件有限公司 Automatic punching machine for steel strip
CN106112540A (en) * 2016-07-07 2016-11-16 蔡靖 Before one is used in manufacture electric cooker shell, raw material plate face roughness reduces and manufactures device
CN106312566A (en) * 2016-08-24 2017-01-11 新昌县宏宇制冷有限公司 Cutting-punching integrated machine for ceiling tile production
CN206153905U (en) * 2016-11-01 2017-05-10 广州英固特音响拉杆有限公司 Integrative device that punches a hole is managed to full -automatic cutting of numerical control
CN207464680U (en) * 2017-12-01 2018-06-08 东莞市国锐自动化设备科技有限公司 A four-in-one automatic production line

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07328992A (en) * 1994-06-02 1995-12-19 Yokohama Rubber Co Ltd:The Automatic punching method and automatic punching device for rubber test piece
CN201023125Y (en) * 2007-03-20 2008-02-20 吐哈石油勘探开发指挥部机械厂 Thin and long tube end upsetting automatic feeding and discharging device
CN102825429A (en) * 2012-09-06 2012-12-19 浙江科朗汽车配件有限公司 Automatic punching machine for steel strip
CN106112540A (en) * 2016-07-07 2016-11-16 蔡靖 Before one is used in manufacture electric cooker shell, raw material plate face roughness reduces and manufactures device
CN106312566A (en) * 2016-08-24 2017-01-11 新昌县宏宇制冷有限公司 Cutting-punching integrated machine for ceiling tile production
CN206153905U (en) * 2016-11-01 2017-05-10 广州英固特音响拉杆有限公司 Integrative device that punches a hole is managed to full -automatic cutting of numerical control
CN207464680U (en) * 2017-12-01 2018-06-08 东莞市国锐自动化设备科技有限公司 A four-in-one automatic production line

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112207357A (en) * 2020-09-22 2021-01-12 湖州至诚精密金属科技股份有限公司 A kind of alloy steel pipe production equipment and production process
CN117297173A (en) * 2023-11-29 2023-12-29 新乡市中汇过滤技术有限公司 Composite filter element winding device and composite filter element preparation method
CN117297173B (en) * 2023-11-29 2024-03-08 新乡市中汇过滤技术有限公司 Composite filter element winding device and composite filter element preparation method

Also Published As

Publication number Publication date
CN108818115B (en) 2019-11-05

Similar Documents

Publication Publication Date Title
CN211191676U (en) A kind of automatic demoulding stamping die
CN102861855B (en) Automatic riveting device
CN101376149B (en) Feeding device on pipe-winding machine
CN108818115B (en) Automatic feeding
CN110935813B (en) Automatic punching machine and punching method
CN206263050U (en) Automatic feed/discharge decompressor
CN107052150A (en) Weld tabs is with reverse drawing diel
CN104354190A (en) Automatic perforating machine
CN204545106U (en) With the Wedge mechanism of movable drift
CN107520385B (en) Hollow rivet radial punching cold heading forming mechanism
CN209814910U (en) Stamping workpiece garbage collection transports transfer chain
CN207403227U (en) A kind of pop can flattening device
CN204172414U (en) Automatic punching machine
CN106734488B (en) Hydraulic cylinder for punching press
CN204685804U (en) Plate punching device
CN214919741U (en) Rectifier bridge welds pin punching press facility
CN104209442A (en) Automatic riveting machine
CN211803354U (en) Electric hydraulic punching machine
CN214768317U (en) Stamping forming die
CN210160730U (en) Screw manufacturing equipment
CN112275930A (en) Centre gripping feeding mechanism and cold punching upgrade mould
CN206455385U (en) A kind of automatic nailing machine
CN221773352U (en) Automatic feeding device for punching machine
CN111673481A (en) Be used for automatic continuous blank pay-off structure of brazing sheet
CN110449508A (en) A kind of steel bar Die structure device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Xie Xiaowen

Inventor before: Xie Xiaowen

GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20181116

Assignee: Zhejiang guangzhiyuan Technology Co.,Ltd.

Assignor: Wenzhou University

Contract record no.: X2023330000101

Denomination of invention: Automatic feeding device

Granted publication date: 20191105

License type: Common License

Record date: 20230311

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191105