[go: up one dir, main page]

CN108725703A - Profundal zone monitoring facilities bury platform and application method - Google Patents

Profundal zone monitoring facilities bury platform and application method Download PDF

Info

Publication number
CN108725703A
CN108725703A CN201810566296.1A CN201810566296A CN108725703A CN 108725703 A CN108725703 A CN 108725703A CN 201810566296 A CN201810566296 A CN 201810566296A CN 108725703 A CN108725703 A CN 108725703A
Authority
CN
China
Prior art keywords
bracing members
platform
strake
monitoring facilities
flat boat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810566296.1A
Other languages
Chinese (zh)
Inventor
葛国昌
姜建芳
俞炯奇
王卫
吴雄伟
李红文
谢龙
占川
姜永兴
姚永新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Institute of Hydraulics and Estuary
Zhejiang Guangchuan Engineering Consulting Co Ltd
Original Assignee
Zhejiang Institute of Hydraulics and Estuary
Zhejiang Guangchuan Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Institute of Hydraulics and Estuary, Zhejiang Guangchuan Engineering Consulting Co Ltd filed Critical Zhejiang Institute of Hydraulics and Estuary
Priority to CN201810566296.1A priority Critical patent/CN108725703A/en
Publication of CN108725703A publication Critical patent/CN108725703A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B17/00Vessels parts, details, or accessories, not otherwise provided for
    • B63B17/04Stanchions; Guard-rails ; Bulwarks or the like

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

本发明提供了一种深水区监测设施埋设平台及使用方法。本发明深水区监测设施埋设平台包括平板船、外挑支架、防护装置和钻机;所述平板船通过船锚和缆绳固定于海面上,所述钻机通过所述外挑支架架设于所述平板船的侧面,所述防护装置设置于所述外挑支架的最外端。本发明通过外挑支架将钻机架设于船体侧面,结合海上潮汐和风浪作用锚固移动船位,有效避免船体与已埋设设施之间的相互干扰,实现深水监测设施任意方位及间距的埋设。本发明具有结构简单、安装方便、安全可靠等优点,且避免已埋设设施对船体锚固位置的限制以及船体对已埋设设施的碰撞损坏,大大提高工作效率,具有广泛的应用价值。

The invention provides a monitoring facility embedding platform in a deep water area and a use method thereof. The embedding platform of the monitoring facility in the deep water area of the present invention includes a flat boat, an overhanging bracket, a protective device and a drilling rig; the flat boat is fixed on the sea surface through anchors and cables, and the drilling rig is erected on the flat boat through the overhanging bracket The side of the protective device is arranged at the outermost end of the overhanging bracket. The invention erects the drilling rig on the side of the hull through the overhanging bracket, combines the sea tide and wind and waves to anchor and move the ship position, effectively avoids the mutual interference between the hull and the buried facilities, and realizes the embedding of deep-water monitoring facilities at any position and distance. The invention has the advantages of simple structure, convenient installation, safety and reliability, etc., and avoids the limitation of the anchorage position of the hull by the buried facilities and the collision damage of the hull to the buried facilities, greatly improves the work efficiency, and has wide application value.

Description

深水区监测设施埋设平台及使用方法Embedded platform and usage method of monitoring facilities in deep water area

技术领域technical field

本发明属于监测设施埋设技术领域,特别涉及一种深水区监测设施埋设平台及使用方法。The invention belongs to the technical field of monitoring facility embedding, and in particular relates to a monitoring facility embedding platform in a deep water area and a use method thereof.

背景技术Background technique

在岩土工程中,由于地质条件、荷载历时和外界因素的复杂影响,通常出现滑坡、失稳、沉陷变形等灾害现象,为及时对灾害进行预警处置,保证工程建设安全顺利实施,需要埋设必要的监测设施。监测设施的埋设通常包括钻机成孔、仪器埋设安装、设施保护等工序内容。陆地条件监测设施埋设各工序均处于陆地可视环境,其埋设技术已经比较成熟。而深水区监测设施埋设所面临的作业环境与陆地条件完全不同,陆地埋设技术方法对于深水区监测设施埋设存在使用局限性和诸多缺点:(1)深水埋设各工序均需借助水上作业平台才可完成,且作业平台需满足深水作业所需的承载力、空间、安全要求;(2)仪器电缆敷设、保护设施安装均需在水上实施,平台至水面间仍需一定可视作业空间;(3)监测设施需高出水面一定距离,作业平台的移位应不受前期已埋设监测设施的限制。In geotechnical engineering, due to the complex influence of geological conditions, load duration and external factors, disasters such as landslides, instability, subsidence and deformation usually occur. monitoring facilities. The embedding of monitoring facilities usually includes drilling rigs, instrument embedding and installation, and facility protection. The embedding process of land condition monitoring facilities is in the land visible environment, and its embedding technology is relatively mature. However, the operating environment faced by the embedding of monitoring facilities in deep water areas is completely different from that on land. Land embedding techniques and methods have limitations and many disadvantages for the embedding of monitoring facilities in deep water areas: (1) Each process of deep water embedding requires the help of a water operation platform. completed, and the operating platform must meet the bearing capacity, space, and safety requirements required for deep-water operations; (2) The laying of instrument cables and the installation of protective facilities must be carried out on the water, and a certain visible operating space is still required between the platform and the water surface; (3) ) The monitoring facilities need to be a certain distance above the water surface, and the displacement of the operating platform should not be restricted by the previously buried monitoring facilities.

发明内容Contents of the invention

为解决现有技术在深水区钻机成孔、仪器埋设安装、设施保护等存在的诸多问题,本发明提供一种深水区监测设施埋设平台及使用方法,其技术方案如下:In order to solve many problems existing in the prior art in deep-water areas such as drilling with drilling rigs, instrument embedding and installation, and facility protection, the present invention provides a deep-water area monitoring facility embedding platform and its use method. The technical scheme is as follows:

深水区监测设施埋设平台,包括平板船、外挑支架、防护装置和钻机,其特征在于:所述平板船通过船锚和缆绳固定于海面上,所述钻机通过所述外挑支架架设于所述平板船的侧面,所述防护装置设置于所述外挑支架的最外端。The buried platform of monitoring facilities in deep water area includes a flat boat, an overhanging bracket, a protective device and a drilling rig. The side of the flat boat, the protective device is arranged at the outermost end of the overhanging bracket.

所述平板船包括甲板、船侧板;所述外挑支架包括钢支撑、固定件;所述防护装置包括防护栏杆、木跳板;所述钻机包括底座、立轴;钢支撑的一端通过固定件固定于所述甲板上,钢支撑的另一端伸出船侧板,钢支撑伸出船侧板的长度根据所述钻机和埋设作业所需空间大小确定;防护栏杆固接于钢支撑的最外端,底座架设于钢支撑上,立轴保持竖直,底座周围伸出船侧板的钢支撑上铺设有木跳板。The flat boat includes a deck and a side plate; the overhanging bracket includes a steel support and a fixing piece; the protective device includes a protective railing and a wooden springboard; the drilling machine includes a base and a vertical shaft; one end of the steel support is fixed by a fixing piece On the deck, the other end of the steel support protrudes from the ship's side plate, and the length of the steel support protruding from the ship's side plate is determined according to the size of the space required for the drilling rig and the embedding operation; the protective railing is fixed on the outermost end of the steel support, and the base It is erected on a steel support, the vertical shaft is kept vertical, and a wooden springboard is laid on the steel support protruding from the ship's side plate around the base.

利用如上所述的深水区监测设施埋设平台的使用方法,包括以下步骤:The method for using the buried platform of the monitoring facility in the deep water area as described above comprises the following steps:

(a)根据埋设作业位置将所述平板船锚固于海面上,将埋设平台预架设范围内平板船的栏杆切除;(a) anchoring the flat boat on the sea surface according to the embedding operation position, and removing the railings of the flat boat within the pre-set range of the buried platform;

(b)将所述钢支撑的一端通过所述固定件固定于所述甲板上,钢支撑的另一端伸出所述船侧板外侧,根据所需空间大小可设置多根钢支撑;(b) one end of the steel support is fixed on the deck through the fixing member, and the other end of the steel support is stretched out from the outside of the ship side plate, and multiple steel supports can be arranged according to the required space size;

(c)将所述防护栏杆固接于钢支撑的最外端,将所述底座平稳架设于木跳板上,调整所述立轴距船侧板外边缘的距离,保持立轴竖直,将底座周围伸出船侧板的钢支撑上铺满所述木跳板;(c) Fix the protective railing to the outermost end of the steel support, erect the base on the wooden springboard stably, adjust the distance between the vertical shaft and the outer edge of the ship's side plate, keep the vertical shaft vertical, and place the base around the The steel support protruding from the side plate of the ship is covered with the wooden springboard;

(d)根据测点预设钻孔深度钻进成孔,进行监测仪器及保护设施的埋设安装,通过缆绳移位船体至另一测点,重复上述操作,直至埋设完成全部测点监测设施。(d) Drill the hole according to the preset drilling depth of the measuring point, carry out the buried installation of the monitoring instrument and protection facilities, move the hull to another measuring point through the cable, repeat the above operation until all the monitoring facilities of the measuring point are buried.

本发明深水区监测设施埋设平台及使用方法的所述钢支撑可以采用工字钢、钢管或替换为木桩等形式,所述固定件可以采用U型锚筋、螺栓或替换为焊接等形式。The steel support of the deep-water area monitoring facility embedding platform and the method of use of the present invention can be in the form of I-beams, steel pipes or wooden piles, and the fixing parts can be in the form of U-shaped anchor bars, bolts or welding.

本发明的有益效果是:The beneficial effects of the present invention are:

本发明提供了深水区监测设施埋设平台及使用方法,利用平板船提供海上深水作业平台,通过外挑支架将钻机架设于船体侧面,保证了钻机成孔、仪器埋设、设施保护所需的作业空间要求,结合海上潮汐和风浪条件锚固移动船位,有效避免船体与已埋设监测设施之间的相互干扰,实现深水区监测设施任意方位及间距的埋设;本发明具有结构简单、安装方便、安全可靠、适应能力强等优点,且避免已埋设设施对船体锚固位置的限制以及船体对已埋设设施的碰撞损坏,有效克服了现有技术中存在的诸多缺点,大大提高深水区监测设施的埋设质量和工作效率,具有广泛的应用价值。The invention provides a platform for embedding monitoring facilities in a deep water area and a method for using it. A flat boat is used to provide an offshore deep water operation platform, and a drilling rig is erected on the side of the hull through an overhanging bracket, thereby ensuring the required working space for the drilling rig to form holes, to embed instruments, and to protect facilities. Requirements, combined with sea tide and wind and wave conditions to anchor the mobile ship position, effectively avoid the mutual interference between the hull and the buried monitoring facilities, and realize the embedding of monitoring facilities in deep water areas at any position and distance; the invention has simple structure, convenient installation, safety and reliability, It has the advantages of strong adaptability, and avoids the restriction of the anchorage position of the hull by the buried facilities and the collision damage of the hull to the buried facilities, effectively overcomes many shortcomings in the existing technology, and greatly improves the buried quality and work of monitoring facilities in deep water areas. efficiency and has wide application value.

附图说明Description of drawings

图1是本发明的埋设平台结构示意图。Fig. 1 is a structural schematic diagram of the buried platform of the present invention.

图中:1-平板船;11-甲板;12-船侧板;2-外挑支架;21-钢支撑;22-固定件;3-防护装置;31-防护栏杆;32-木跳板;4-钻机;41-底座;42-立轴。In the figure: 1-flat boat; 11-deck; 12-side board; 2-overhanging bracket; 21-steel support; 22-fixture; 3-protection device; - drilling machine; 41 - base; 42 - vertical shaft.

具体实施方式Detailed ways

下面结合附图对本发明进行详细说明。The present invention will be described in detail below in conjunction with the accompanying drawings.

如图1所示,本发明深水区监测设施埋设平台,包括平板船1、外挑支架2、防护装置3和钻机4,所述平板船1通过船锚和缆绳固定于海面上,所述钻机4通过所述外挑支架2架设于所述平板船1的侧面,所述防护装置3设置于所述外挑支架2的最外端。As shown in Figure 1, the buried platform of monitoring facilities in deep water area of the present invention comprises a flat boat 1, an overhang bracket 2, a protective device 3 and a drilling rig 4, and the flat boat 1 is fixed on the sea surface by anchors and cables, and the drilling rig 4. The overhanging bracket 2 is erected on the side of the flat boat 1, and the protection device 3 is arranged at the outermost end of the overhanging bracket 2.

所述平板船1包括甲板11、船侧板12;所述外挑支架2包括钢支撑21、固定件22;所述防护装置3包括防护栏杆31、木跳板32;所述钻机4包括底座41、立轴42;钢支撑21的一端通过固定件22固定于所述甲板11上,钢支撑21的另一端伸出船侧板12,钢支撑21伸出船侧板12的长度根据所述钻机4和埋设作业所需空间大小确定;防护栏杆31焊接于钢支撑21的最外端,底座41架设于钢支撑21上,立轴42保持竖直,底座41周围伸出船侧板12的钢支撑上21铺设有木跳板32。防护栏杆31的高度不小于1.2m,木跳板32的厚度应不小于5cm;立轴42距所述船侧板12外边缘的距离以0.5m左右为宜。The flat boat 1 includes a deck 11 and a side plate 12; the overhang bracket 2 includes a steel support 21 and a fixing piece 22; the protection device 3 includes a protective railing 31 and a wooden springboard 32; the drilling rig 4 includes a base 41 , vertical shaft 42; one end of the steel support 21 is fixed on the deck 11 by the fixture 22, the other end of the steel support 21 stretches out the side plate 12, and the length of the steel support 21 stretches out the side plate 12 according to the rig 4 and the embedding The size of the space required for the operation is determined; the protective railing 31 is welded to the outermost end of the steel support 21, the base 41 is erected on the steel support 21, the vertical shaft 42 remains vertical, and the steel support 21 stretching out from the side plate 12 around the base 41 is laid with Wooden diving board32. The height of protective railing 31 is not less than 1.2m, and the thickness of wooden springboard 32 should be not less than 5cm; Vertical shaft 42 is advisable with the distance of about 0.5m apart from described ship side plate 12 outer edges.

本实施例提供的深水区监测设施埋设平台使用方法,包括以下步骤:The method for using the buried platform of the monitoring facility in the deep water area provided by this embodiment includes the following steps:

(a)根据埋设作业位置将所述平板船1锚固于海面上,将埋设平台预架设范围内平板船1的栏杆切除;(a) anchor the flat boat 1 on the sea surface according to the embedding operation position, and cut off the railing of the flat boat 1 within the pre-erected range of the buried platform;

(b)将所述钢支撑21一端通过所述固定件22固定于所述甲板11,另一端悬挑于所述船侧板12外侧,根据所需空间大小可设置多根钢支撑21,钢支撑21间距应小于1.0m;(b) One end of the steel support 21 is fixed to the deck 11 through the fixing member 22, and the other end is suspended from the outside of the ship side plate 12, and multiple steel supports 21 can be set according to the required space size. The distance between supports 21 should be less than 1.0m;

(c)将所述防护栏杆31固接于钢支撑21的最外端,防护栏杆31间距应小于1.5m,将所述底座41平稳架设于木跳板32上,调整所述立轴42距船侧板12外边缘的距离以0.5m左右为宜,保持立轴42竖直,将底座41周围伸出船侧板12的钢支撑21上铺满所述木跳板32。(c) Fix the protective railing 31 to the outermost end of the steel support 21, the distance between the protective railings 31 should be less than 1.5m, erect the base 41 stably on the wooden springboard 32, adjust the distance between the vertical shaft 42 and the side of the ship The distance of plate 12 outer edge is advisable with about 0.5m, keeps vertical shaft 42 vertical, and spreads out described wooden springboard 32 on the steel support 21 that stretches out ship side plate 12 around base 41.

(d)根据测点预设钻孔深度钻进成孔,进行监测仪器及保护设施的埋设安装,通过缆绳移位船体至另一测点,重复上述操作,直至埋设完成全部测点监测设施。(d) Drill the hole according to the preset drilling depth of the measuring point, carry out the buried installation of the monitoring instrument and protection facilities, move the hull to another measuring point through the cable, repeat the above operation until all the monitoring facilities of the measuring point are buried.

本发明深水区监测设施埋设平台及使用方法的实施例中所述钢支撑可以采用工字钢、钢管或替换为木桩等形式,所述固定件可以采用U型锚筋、螺栓或替换为焊接等形式。In the embodiment of the buried platform of the monitoring facility in the deep water area and the method of use of the present invention, the steel supports can be in the form of I-beams, steel pipes, or wooden piles, and the fixing parts can be U-shaped anchor bars, bolts, or welded. and other forms.

上述实施例结合附图对本发明进行了描述,但并不能因此而理解为对本发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些均属于本发明的保护范围。The above embodiments describe the present invention in conjunction with the accompanying drawings, but it should not be construed as limiting the patent scope of the present invention. It should be noted that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention, and these all belong to the protection scope of the present invention.

Claims (3)

1. profundal zone monitoring facilities bury platform, including Flat boat (1), holder (2), protective device (3) and drilling machine (4) are chosen outside, It is characterized in that:The Flat boat (1) is fixed on by ship anchor and hawser on sea, and the drilling machine (4) chooses branch outside by described Frame (2) is set up in the side of the Flat boat (1), and the protective device (3) is set to the outer outermost end for choosing holder (2).
2. profundal zone monitoring facilities according to claim 1 bury platform, it is characterised in that:The Flat boat (1) includes Deck (11), strake (12);It includes bracing members (21), fixing piece (22) to choose holder (2) outside described;The protective device (3) Including guard rail (31), the wooden springboard (32);The drilling machine (4) includes pedestal (41), vertical shaft (42);One end of bracing members (21) It is fixed on the deck (11) by fixing piece (22), the other end of bracing members (21) stretches out strake (12), bracing members (21) length for stretching out strake (12) is determined according to space size needed for the drilling machine (4) and embedded operation;Guard rail (31) it is fixed in the outermost end of bracing members (21), pedestal (41) is set up on bracing members (21), and vertical shaft (42) keeps vertical, pedestal (41) it is stretched out around on the bracing members (21) of strake (12) and is equipped with the wooden springboard (32).
3. burying the application method of platform using profundal zone monitoring facilities according to claim 1 or 2, it is characterised in that: This approach includes the following steps:
(a) Flat boat (1) is anchored on sea according to embedded job position, embedded platform is set up into tablet in range in advance The railing of ship (1) is cut off;
(b) one end of the bracing members (21) is fixed on by the fixing piece (22) on the deck (11), bracing members (21) the other end stretches out the outside of the strake (12), and more bracing members (21) are arranged according to required space size;
(c) guard rail (31) is fixed in the outermost end of bracing members (21), the pedestal (41) is steadily set up in wood On springboard (32), the vertical shaft (42) is adjusted away from strake (12) outer peripheral distance, vertical shaft (42) is kept vertically, by pedestal (41) it is stretched out around on the bracing members (21) of strake (12) and is paved with the wooden springboard (32);
(d) drilling depth drilling and forming hole is preset according to measuring point, is monitored instrument and the Embedment and installation of protection facility, passes through hawser Hull is shifted to another measuring point, repeats aforesaid operations, until embedded complete whole measuring point monitoring facilities.
CN201810566296.1A 2018-06-05 2018-06-05 Profundal zone monitoring facilities bury platform and application method Pending CN108725703A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810566296.1A CN108725703A (en) 2018-06-05 2018-06-05 Profundal zone monitoring facilities bury platform and application method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810566296.1A CN108725703A (en) 2018-06-05 2018-06-05 Profundal zone monitoring facilities bury platform and application method

Publications (1)

Publication Number Publication Date
CN108725703A true CN108725703A (en) 2018-11-02

Family

ID=63932154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810566296.1A Pending CN108725703A (en) 2018-06-05 2018-06-05 Profundal zone monitoring facilities bury platform and application method

Country Status (1)

Country Link
CN (1) CN108725703A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4907657A (en) * 1986-12-01 1990-03-13 Shell Offshore, Inc. Method for protecting a shallow water well
US6729804B1 (en) * 2002-08-22 2004-05-04 Itrec B.V. Cantilevered tower for jack-up platform
CN101643110A (en) * 2009-08-27 2010-02-10 中交第三航务工程勘察设计院有限公司 Unilateral cantilever type water survey platform system
CN201972600U (en) * 2011-04-01 2011-09-14 中铁港航工程局有限公司 Drilling device for handling bare rocks
WO2012053982A1 (en) * 2010-10-21 2012-04-26 Conocophillips Company Dual-derrick ice-worthy jack-up drilling unit
WO2013133694A1 (en) * 2012-03-06 2013-09-12 Itrec B.V. An offshore system comprising a rig and a cantilever
KR101487650B1 (en) * 2014-07-04 2015-01-29 주식회사 삼안 Barge and boring excavation device separated marine boring system
WO2015024310A1 (en) * 2013-08-22 2015-02-26 中交第三航务工程勘察设计院有限公司 Shipborne truss combined in-situ testing platform
CN208306934U (en) * 2018-06-05 2019-01-01 浙江省水利河口研究院 Profundal zone monitoring facilities bury platform

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4907657A (en) * 1986-12-01 1990-03-13 Shell Offshore, Inc. Method for protecting a shallow water well
US6729804B1 (en) * 2002-08-22 2004-05-04 Itrec B.V. Cantilevered tower for jack-up platform
CN101643110A (en) * 2009-08-27 2010-02-10 中交第三航务工程勘察设计院有限公司 Unilateral cantilever type water survey platform system
WO2012053982A1 (en) * 2010-10-21 2012-04-26 Conocophillips Company Dual-derrick ice-worthy jack-up drilling unit
CN201972600U (en) * 2011-04-01 2011-09-14 中铁港航工程局有限公司 Drilling device for handling bare rocks
WO2013133694A1 (en) * 2012-03-06 2013-09-12 Itrec B.V. An offshore system comprising a rig and a cantilever
WO2015024310A1 (en) * 2013-08-22 2015-02-26 中交第三航务工程勘察设计院有限公司 Shipborne truss combined in-situ testing platform
KR101487650B1 (en) * 2014-07-04 2015-01-29 주식회사 삼안 Barge and boring excavation device separated marine boring system
CN208306934U (en) * 2018-06-05 2019-01-01 浙江省水利河口研究院 Profundal zone monitoring facilities bury platform

Similar Documents

Publication Publication Date Title
KR101797263B1 (en) Undersea anchoring system and method
US20180223497A1 (en) Construction device and method for offshore wind turbine foundation with piling performed later
EP2574698B1 (en) Method and device for driving a multiplicity of piles into a seabed
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN101289864A (en) Positioning sinking process for steel open caisson under water
JP4043380B2 (en) Method for sinking a floating body of a floating foundation and apparatus for carrying out this method
JP2005194792A (en) Offshore wind turbine generator foundation and offshore wind turbine generator installation method
CN108832551A (en) The laying of batholith sea bed high-pressure undersea cable and guard method
JP2515888B2 (en) Construction method of steel pipe pile for building offshore structure and its equipment
JP3518856B2 (en) Wind power generator
KR20180019914A (en) Seabed settle apparatus drilling barge vessel
US5788417A (en) Offshore well stabilization apparatus and method
WO2024186220A1 (en) Stabilizing device, a subsea system and use of the stabilizing device
CN108725703A (en) Profundal zone monitoring facilities bury platform and application method
CN117627534A (en) Complicated sea area reef area investigation device and method based on lifting platform
CN203511998U (en) Offshore construction platform for vibrating punching operation
CN212738453U (en) Special ship for laying submarine cable at landing section under small tidal range
CN208306934U (en) Profundal zone monitoring facilities bury platform
CN212321328U (en) Offshore in-situ cross plate shearing test system
JP2000355960A (en) Intake method for deep ocean water
KR100677898B1 (en) Anchor for installing a stain prevention film and installation method of a stain prevention film using the same
KR102622212B1 (en) Pre-drilling method for offshore wind power using guide frame and pre-drilling equipment
CN211977874U (en) Device for measuring water depth at position of pile leg on platform
CN102966102A (en) Fixing structure for steel casing on steep bare rock without covering layer in deep water and rapids
JPS6133930B2 (en)

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181102

WD01 Invention patent application deemed withdrawn after publication