CN108532604A - A kind of steady stake platform construction technique - Google Patents

A kind of steady stake platform construction technique Download PDF

Info

Publication number
CN108532604A
CN108532604A CN201810184263.0A CN201810184263A CN108532604A CN 108532604 A CN108532604 A CN 108532604A CN 201810184263 A CN201810184263 A CN 201810184263A CN 108532604 A CN108532604 A CN 108532604A
Authority
CN
China
Prior art keywords
steady stake
platform
stake platform
steady
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810184263.0A
Other languages
Chinese (zh)
Inventor
张海生
陈强
曹春潼
刘旦
王徽华
廖卫勇
冯小星
王海波
梅卫东
袁司
高建忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU LONGYUAN ZHENHUA MARINE ENGINEERING CO LTD
Original Assignee
JIANGSU LONGYUAN ZHENHUA MARINE ENGINEERING CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU LONGYUAN ZHENHUA MARINE ENGINEERING CO LTD filed Critical JIANGSU LONGYUAN ZHENHUA MARINE ENGINEERING CO LTD
Priority to CN201810184263.0A priority Critical patent/CN108532604A/en
Publication of CN108532604A publication Critical patent/CN108532604A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a kind of steady stake platform construction techniques, include the following steps:A, steady stake platform and the fixed pile pile of support are transported to designated position, 6 card keys of steady stake platform support pile pipe is installed to platform machine frame inside later;B, the support pile pile of steady stake platform is adjusted;C, steady stake platform Current Collector Sleave is got out, and is installed in place after detecting quality;D, cable wind rope is hung up properly on steady stake platform, after tooling dismounting is tied up in the sea of steady stake platform, rises crane gib head, steady stake platform is hung into deck;E, steady stake platform is integrally sling into submerged, and steady stake platform Current Collector Sleave is removed, the construction technology that the present invention uses can improve the stability after steady stake stage+module, improve bearing capacity.

Description

A kind of steady stake platform construction technique
Technical field
The present invention relates to steady stake stage+module technical field, specially a kind of steady stake platform construction technique.
Background technology
The steady stake platform of monoblock type of so-called card key connection be it is a kind of it is novel can be quickly by interior casing, Integral-type platform and steel Pile pile couples integral steady stake plateform system.The steady stake system is applicable not only in thick soft formation, and in thin soft formation In can also rapid construction steady stake platform.
The steady stake system has the characteristics that big bearing capacity(Based on platform bearer, supplemented by steel pile casting carrying).It is required that platform Need to have carrying drilling equipment and platform dead weight(Containing always about 1000 tons of steel pile casting)Ability, while being also subjected to seaway load Marine environment power inside.
In river or when sea bed builds basic wind turbine, need, first by more engineering pile pile sinking to river bottom or seabed, at this moment, Lifting is first passed through, engineering pile is hung to pile sinking point, then carries out pile sinking again.In order to enable engineering pile smoothly to enter mud pitching pile and pile sinking Pile body verticality is ensured in the process within 3 ‰, often steady stake is carried out to engineering pile using steady stake platform.
Current steady stake stage+module complex process, the platform stabilization after installation are poor.
Invention content
The purpose of the present invention is to provide a kind of steady stake platform construction techniques, to solve mentioned above in the background art ask Topic.
To achieve the above object, the present invention provides the following technical solutions:A kind of steady stake platform construction technique, including following step Suddenly:
A, steady stake platform and the fixed pile pile of support are transported to designated position, 6 card keys of steady stake platform is supported into pile pipe later It is installed to platform machine frame inside, card key is used in combination to firmly install;
B, data, hydrological data etc. are surveyed according to the ground of seat in the plane to calculate in advance, the support pile pile of steady stake platform is adjusted in place in advance;
C, after ensuring that the support pile pile of steady stake platform is adjusted in place, steady stake platform Current Collector Sleave is got out, and detect quality zero defect Current Collector Sleave is installed in place afterwards;
D, Current Collector Sleave hangs up properly cable wind rope after installation is complete on steady stake platform, the sea of steady stake platform is tied up after tooling removes, slowly Steady stake platform is hung deck by raising crane gib head, isolated pillar crane arm support to seat in the plane center, while twist anchor will twist from Ship certain position is to vacate the position of steady stake platform;
E, crane hook is transferred, steady stake platform is integrally sling into submerged, sea bed is submerged by the dead weight of steady stake platform Certain depth, after steady stake platform sink to mud face it is basicly stable after, by steady stake platform Current Collector Sleave remove;
F, survey crew utilizes the Realize of the steady stake platform of transit survey, then again that the steady lower side of stake platform is removable Card key is opened, coordinates loop wheel machine by the pedestal slight elevations of downside with suspender belt;With card key card jail after steady stake plateau levels;
G, the card key of a steel-pipe pile is dismantled, gradually card key adjusting screw is unclamped simultaneously to discharge the pressure that steel-pipe pile is born, incites somebody to action The steel-pipe pile is squeezed into vibration hammer to scar, in place after, again by the card key of the steel-pipe pile connection install;Repeat above procedure Each steel-pipe pile is squeezed into one by one;Since there are six steel-pipe pile symmetric supports for platform, one of steel-pipe pile is once only being removed In the case of, platform still maintains stable and horizontal;
H, after the completion of steady stake plateau levels adjustment, the Realize of steady stake platform is observed, it is ensured that after steady stake platform stable, prepare to hang Fill casing in steady stake platform;
I, it is ready to lift the Current Collector Sleave of casing in steady stake platform, is installed in place Current Collector Sleave after detecting Current Collector Sleave zero defect;
J, raising crane gib head lifts casing in steady stake platform to steady stake platform, after waiting for that interior casing is drowned oneself, incited somebody to action It crosses section to be installed at the top of interior casing, and fastens and connect bolt, then will wear interior casing with S2000 hydraulic impact hammers squeezes into rock Rock layers;After interior casing is installed in place, the changeover portion at top is removed;Platform lock-screw suitable for reading is pre-tightened, steel pile casting is made It is suitable for reading to be linked together with platform.
Preferably, it is not required to adjust if levelness is not exceeded in the step F, if levelness is exceeded, first be hung with crane Dress vibration hammer applies certain vibration to the fixation stake top end of upper side, and platform progress coarse adjustment is put down.
Preferably, steady stake platform Current Collector Sleave includes the first hanging beam, the first endless steel cable circle, second in the step C Endless steel cable circle, the first shackle, the one or two shackle and third shackle.
Preferably, the Current Collector Sleave of interior casing includes the second hanging beam, third endless steel cable circle, the 4th in the step I Endless steel cable circle, the 4th shackle and the 5th shackle.
Compared with prior art, the beneficial effects of the invention are as follows:It is flat that the construction technology that the present invention uses can improve steady stake Stability after platform installation, improves bearing capacity;The steady stake platform of the present invention uses six steel-pipe pile symmetric supports, improves steady The stabilization and level of stake platform entirety do not influence the stabilization and level of steady stake platform still if removing one of steel-pipe pile;In code Head installs 6 pile leg pipes, reduces marine boisterous working procedure;The steady stake platform integral lifting of the present invention sinks to water In, it is not necessarily to installation spud leg waterborne, reduces operation near water, process is more reasonable, more efficient;Furthermore it is possible to ensure steady stake platform Verticality, be conducive to the construction of embedding rock single pile, drill hole of drilling machine.
Description of the drawings
Fig. 1 is the steady stake platform lifting schematic diagram of the present invention;
Fig. 2 is casing erection drawing in the steady stake platform of the present invention.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
- 2 are please referred to Fig.1, the present invention provides a kind of technical solution:A kind of steady stake platform construction technique, includes the following steps:
A, steady stake platform and the fixed pile pile of support are transported to designated position, 6 card keys of steady stake platform is supported into pile pipe later It is installed to platform machine frame inside, card key is used in combination to firmly install;
B, data, hydrological data etc. are surveyed according to the ground of seat in the plane to calculate in advance, the support pile pile of steady stake platform is adjusted in place in advance; By taking the single pile of the bases A19 as an example:The seats in the plane A19 absolute altitude:-12.76m;Climax tidal level:+4m;Ground is surveyed:Mud about 4m, granular media shape are strong Weathered granite layer about 2-3m;Consider that steady stake table top is higher 1.5m than climax tidewater when operation;It integrates according to the above It calculates, considers that 6 spud piles enter mud 7m(Enter granular media shape strong weathered granite layer 3m), in advance will support pile pile bottom adjust to away from From the pedestal bottom positions about 10.27m, then by card key clamping, when spud pile is installed in pedestal, by platform stake lifting gear Adjusting block be adjusted to about intermediate position, with the horizontal adjustment of steady stake platform during aspect subsequent construction;
C, after ensuring that the support pile pile of steady stake platform is adjusted in place, steady stake platform Current Collector Sleave is got out, and detect quality zero defect Current Collector Sleave is installed in place afterwards;
D, Current Collector Sleave hangs up properly cable wind rope after installation is complete on steady stake platform, the sea of steady stake platform is tied up after tooling removes, slowly Steady stake platform is hung deck by raising crane gib head, isolated pillar crane arm support to seat in the plane center, while twist anchor will twist from Ship certain position is to vacate the position of steady stake platform;
E, crane hook is transferred, steady stake platform is integrally sling into submerged, sea bed is submerged by the dead weight of steady stake platform Certain depth, after steady stake platform sink to mud face it is basicly stable after, by steady stake platform Current Collector Sleave remove;
F, survey crew utilizes the Realize of the steady stake platform of transit survey, is not required to adjust if levelness is not exceeded, if water Pingdu is exceeded, first applies certain vibration to the fixation stake top end of upper side with crane hanging component vibration hammer, platform is carried out Coarse adjustment is flat;Then the removable card key in the steady lower side of stake platform is lifted the pedestal of downside with suspender belt cooperation loop wheel machine slightly again It is high;With card key card jail after steady stake plateau levels;
G, the card key of a steel-pipe pile is dismantled, gradually card key adjusting screw is unclamped simultaneously to discharge the pressure that steel-pipe pile is born, incites somebody to action The steel-pipe pile is squeezed into vibration hammer to scar, in place after, again by the card key of the steel-pipe pile connection install;Repeat above procedure Each steel-pipe pile is squeezed into one by one;Since there are six steel-pipe pile symmetric supports for platform, one of steel-pipe pile is once only being removed In the case of, platform still maintains stable and horizontal;
H, after the completion of steady stake plateau levels adjustment, the Realize of steady stake platform is observed, it is ensured that after steady stake platform stable, prepare to hang Fill casing in steady stake platform;
I, it is ready to lift the Current Collector Sleave of casing in steady stake platform, is installed in place Current Collector Sleave after detecting Current Collector Sleave zero defect;
J, raising crane gib head lifts casing in steady stake platform to steady stake platform, after waiting for that interior casing is drowned oneself, incited somebody to action It crosses section to be installed at the top of interior casing, and fastens and connect bolt, then will wear interior casing with S2000 hydraulic impact hammers squeezes into rock Rock layers;After interior casing is installed in place, the changeover portion at top is removed;Platform lock-screw suitable for reading is pre-tightened, steel pile casting is made It is suitable for reading to be linked together with platform.
In the present invention, steady stake platform Current Collector Sleave includes the first hanging beam 1, the first endless steel cable circle 2, second in step C Endless steel cable circle 3, the first shackle 4, the second shackle 5 and third shackle 6;The Current Collector Sleave of interior casing includes second in step I Hanging beam 7, third endless steel cable circle 8, the 4th endless steel cable circle 9, the 4th shackle 10 and the 5th shackle 11.
The construction technology that the present invention uses can improve the stability after steady stake stage+module, improve bearing capacity;This hair Bright steady stake platform uses six steel-pipe pile symmetric supports, improves the stabilization and level of steady stake platform entirety, if removing wherein One steel-pipe pile does not influence the stabilization and level of steady stake platform still;6 pile leg pipes are installed in harbour, are reduced marine severe The working procedure of weather;The steady stake platform integral lifting submerged of the present invention is not necessarily to installation spud leg waterborne, reduces and make near water Industry, process is more reasonable, more efficient;Furthermore it is possible to ensure the verticality of steady stake platform, be conducive to embedding rock single pile construction, drilling machine Drilling.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of variations, modification, replace And modification, the scope of the present invention is defined by the appended.

Claims (4)

1. a kind of steady stake platform construction technique, it is characterised in that:Include the following steps:
A, steady stake platform and the fixed pile pile of support are transported to designated position, 6 card keys of steady stake platform is supported into pile pipe later It is installed to platform machine frame inside, card key is used in combination to firmly install;
B, data, hydrological data etc. are surveyed according to the ground of seat in the plane to calculate in advance, the support pile pile of steady stake platform is adjusted in place in advance;
C, after ensuring that the support pile pile of steady stake platform is adjusted in place, steady stake platform Current Collector Sleave is got out, and detect quality zero defect Current Collector Sleave is installed in place afterwards;
D, Current Collector Sleave hangs up properly cable wind rope after installation is complete on steady stake platform, the sea of steady stake platform is tied up after tooling removes, slowly Steady stake platform is hung deck by raising crane gib head, isolated pillar crane arm support to seat in the plane center, while twist anchor will twist from Ship certain position is to vacate the position of steady stake platform;
E, crane hook is transferred, steady stake platform is integrally sling into submerged, sea bed is submerged by the dead weight of steady stake platform Certain depth, after steady stake platform sink to mud face it is basicly stable after, by steady stake platform Current Collector Sleave remove;
F, survey crew utilizes the Realize of the steady stake platform of transit survey, then again that the steady lower side of stake platform is removable Card key is opened, coordinates loop wheel machine by the pedestal slight elevations of downside with suspender belt;With card key card jail after steady stake plateau levels;
G, the card key of a steel-pipe pile is dismantled, gradually card key adjusting screw is unclamped simultaneously to discharge the pressure that steel-pipe pile is born, incites somebody to action The steel-pipe pile is squeezed into vibration hammer to scar, in place after, again by the card key of the steel-pipe pile connection install;Repeat above procedure Each steel-pipe pile is squeezed into one by one;Since there are six steel-pipe pile symmetric supports for platform, one of steel-pipe pile is once only being removed In the case of, platform still maintains stable and horizontal;
H, after the completion of steady stake plateau levels adjustment, the Realize of steady stake platform is observed, it is ensured that after steady stake platform stable, prepare to hang Fill casing in steady stake platform;
I, it is ready to lift the Current Collector Sleave of casing in steady stake platform, is installed in place Current Collector Sleave after detecting Current Collector Sleave zero defect;
J, raising crane gib head lifts casing in steady stake platform to steady stake platform, after waiting for that interior casing is drowned oneself, incited somebody to action It crosses section to be installed at the top of interior casing, and fastens and connect bolt, then will wear interior casing with S2000 hydraulic impact hammers squeezes into rock Rock layers;After interior casing is installed in place, the changeover portion at top is removed;Platform lock-screw suitable for reading is pre-tightened, steel pile casting is made It is suitable for reading to be linked together with platform.
2. a kind of steady stake platform construction technique according to claim 1, it is characterised in that:If levelness in the step F It is not exceeded, it is not required to adjust, if levelness is exceeded, crane hanging component vibration hammer is first used to apply the fixation stake top end of upper side Platform progress coarse adjustment is put down in certain vibration.
3. a kind of steady stake platform construction technique according to claim 1, it is characterised in that:Steady stake platform in the step C Current Collector Sleave includes the first hanging beam, the first endless steel cable circle, the second endless steel cable circle, the first shackle, the one or two shackle With third shackle.
4. a kind of steady stake platform construction technique according to claim 1, it is characterised in that:Interior casing in the step I Current Collector Sleave includes the second hanging beam, third endless steel cable circle, the 4th endless steel cable circle, the 4th shackle and the 5th shackle.
CN201810184263.0A 2018-03-07 2018-03-07 A kind of steady stake platform construction technique Pending CN108532604A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810184263.0A CN108532604A (en) 2018-03-07 2018-03-07 A kind of steady stake platform construction technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810184263.0A CN108532604A (en) 2018-03-07 2018-03-07 A kind of steady stake platform construction technique

Publications (1)

Publication Number Publication Date
CN108532604A true CN108532604A (en) 2018-09-14

Family

ID=63486798

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810184263.0A Pending CN108532604A (en) 2018-03-07 2018-03-07 A kind of steady stake platform construction technique

Country Status (1)

Country Link
CN (1) CN108532604A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109208538A (en) * 2018-11-06 2019-01-15 江苏龙源振华海洋工程有限公司 A kind of marine guidance piling berths construction technology by stake
CN109371970A (en) * 2018-11-13 2019-02-22 南通市海洋水建工程有限公司 One kind being used for offshore wind farm single pile pile sinking stable platform and its localization method
CN111364470A (en) * 2020-03-28 2020-07-03 江苏龙源振华海洋工程有限公司 Construction method for inner protective cylinder redrawing pile sinking
CN112627177A (en) * 2020-12-09 2021-04-09 保利长大工程有限公司 Leveling method of pile stabilizing platform
CN114703890A (en) * 2022-04-02 2022-07-05 中国港湾工程有限责任公司 Pipe pile construction process for wharf pile foundation structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105523477A (en) * 2016-01-08 2016-04-27 招商局重工(江苏)有限公司 Method for carrying out pile leg connection by utilizing 3000t floating crane
CN106400764A (en) * 2016-11-25 2017-02-15 平煤建工集团特殊凿井工程有限公司 Assembled offshore single-pile foundation construction platform and construction process thereof
CN206428687U (en) * 2016-11-25 2017-08-22 平煤建工集团特殊凿井工程有限公司 A kind of marine single-pile foundation construction platform of pin-connected panel
CN107326887A (en) * 2017-06-22 2017-11-07 广东华尔辰海上风电工程有限责任公司 Installation method of pile-first jacket for offshore wind power
CN108396762A (en) * 2018-01-12 2018-08-14 江苏龙源振华海洋工程有限公司 A kind of steady stake platform of monoblock type

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105523477A (en) * 2016-01-08 2016-04-27 招商局重工(江苏)有限公司 Method for carrying out pile leg connection by utilizing 3000t floating crane
CN106400764A (en) * 2016-11-25 2017-02-15 平煤建工集团特殊凿井工程有限公司 Assembled offshore single-pile foundation construction platform and construction process thereof
CN206428687U (en) * 2016-11-25 2017-08-22 平煤建工集团特殊凿井工程有限公司 A kind of marine single-pile foundation construction platform of pin-connected panel
CN107326887A (en) * 2017-06-22 2017-11-07 广东华尔辰海上风电工程有限责任公司 Installation method of pile-first jacket for offshore wind power
CN108396762A (en) * 2018-01-12 2018-08-14 江苏龙源振华海洋工程有限公司 A kind of steady stake platform of monoblock type

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109208538A (en) * 2018-11-06 2019-01-15 江苏龙源振华海洋工程有限公司 A kind of marine guidance piling berths construction technology by stake
CN109371970A (en) * 2018-11-13 2019-02-22 南通市海洋水建工程有限公司 One kind being used for offshore wind farm single pile pile sinking stable platform and its localization method
CN109371970B (en) * 2018-11-13 2023-11-07 南通市海洋水建工程有限公司 Single pile sinking stable platform for offshore wind power and positioning method thereof
CN111364470A (en) * 2020-03-28 2020-07-03 江苏龙源振华海洋工程有限公司 Construction method for inner protective cylinder redrawing pile sinking
CN112627177A (en) * 2020-12-09 2021-04-09 保利长大工程有限公司 Leveling method of pile stabilizing platform
CN114703890A (en) * 2022-04-02 2022-07-05 中国港湾工程有限责任公司 Pipe pile construction process for wharf pile foundation structure
CN114703890B (en) * 2022-04-02 2023-09-12 中国港湾工程有限责任公司 Tubular pile construction process for wharf pile foundation structure

Similar Documents

Publication Publication Date Title
CN108532604A (en) A kind of steady stake platform construction technique
CN206826891U (en) A kind of offshore wind turbine single pile pile sinking operation based on barge with deck transformation is refuted
KR101491740B1 (en) A method of installing a submerged tidal hydroelectric turbine
CN101775809B (en) Construction method of marine self-floating type steel soleplate single-wall suspension box cofferdam and single-wall suspension box cofferdam
CN102116017B (en) Foam platform for drilling on waterways
CN102328732A (en) Offshore pile driving, pile pressing and installing united engineering ship
CN108396762A (en) A kind of steady stake platform of monoblock type
JPS62215711A (en) Ocean structure and method for anchoring the same
CN202023182U (en) Waterborne drilling foam platform
CN102409650A (en) Installation method of shallow water ocean jacket platform
CN102923261A (en) A bottom-mounted offshore wind turbine installation barge
CN208167773U (en) A kind of steady stake platform of monoblock type
CN115637724A (en) Low-cost method for installing guide pipe frame of suction bucket
CN115704209A (en) Shallow water area offshore platform installation method
US10988905B2 (en) Harbour plant and method for mooring a floating body in a harbour plant
CN202966598U (en) A new type of bottom-mounted offshore wind turbine installation barge
CN201546211U (en) Static pressure fixed drilling platform assembled at sea
CN111764418A (en) Steel cofferdam positioning system in deep water
JP2017166169A (en) Construction method of structure, and work barge
CN211900555U (en) Underwater manifold device with fiber reinforced composite cover plate
CN217201683U (en) It refutes with sitting bottom hoist and mount to be applicable to marine hoist and mount construction
TW202106602A (en) Work ship having tower crane and crane operating method therefor
CN203174612U (en) Underwater construction device for large objects
CN114855796B (en) Multi-ship coordinated marine steel cylinder vibration sinking construction method
CN202787206U (en) Reusable shoal water pitshaft structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination