CN108457147A - A kind of construction method of the interim sidewalk in construction site - Google Patents

A kind of construction method of the interim sidewalk in construction site Download PDF

Info

Publication number
CN108457147A
CN108457147A CN201810234734.4A CN201810234734A CN108457147A CN 108457147 A CN108457147 A CN 108457147A CN 201810234734 A CN201810234734 A CN 201810234734A CN 108457147 A CN108457147 A CN 108457147A
Authority
CN
China
Prior art keywords
roach
cement
water
building waste
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810234734.4A
Other languages
Chinese (zh)
Inventor
柴艳飞
刘智勇
徐利
任富芝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201810234734.4A priority Critical patent/CN108457147A/en
Publication of CN108457147A publication Critical patent/CN108457147A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • E01C9/08Temporary pavings
    • E01C9/086Temporary pavings made of concrete, wood, bitumen, rubber or synthetic material or a combination thereof
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/16Reinforcements
    • E01C11/18Reinforcements for cement concrete pavings

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of construction methods of the interim sidewalk in construction site, using following steps:1) according to the requirement of the minimum intensity of interim sidewalk and requirement, roach, building waste, cement and water is mixed, the trial test of mixing inverse proportion is carried out, while keeping cement that roach and building waste is cemented together securely;2) the mix ratio determined according to step 1), by roach, building waste, cement and water uniform mixing;3) mixture of the roach of step 2) uniform mixing, building waste, cement and water is subjected to layering decking and rolling, forms roadbed;4) reinforced mesh is laid on the roadbed that the step 3) is formed;5) mixture of the roach of step 2) uniform mixing, building waste, cement and water is paved on reinforced mesh, and is rolled repeatedly, form road surface.The present invention can realize the recycling of waste and meet construction site to the requirement of interim sidewalk, greatly reduce construction cost.

Description

A kind of construction method of the interim sidewalk in construction site
Technical field
The present invention relates to a kind of construction method of temporary road, the construction party of especially a kind of interim sidewalk in construction site Method.
Background technology
Railway traffic engineering or the interim sidewalk at Municipal Engineering Construction scene are typically all to be carried out firmly using armored concrete Change, cost is higher.Actually requirement of the construction site to interim sidewalk be not high, if not occurrence of large-area collapse or Person's large deformation.And construction site has many building wastes and spoir not to efficiently use, directly when waste is transported to field It is handled outside ground.Construction site seldom uses hardening structure of the existing waste as temporary construction sidewalk at present.
Invention content
The present invention provides a kind of construction of the interim sidewalk in construction site to solve technical problem present in known technology Method, this method can realize the recycling of waste and meet construction site to the requirement of interim sidewalk, pole The earth reduces construction cost.
The present invention is adopted the technical scheme that solve technical problem present in known technology:A kind of construction site is faced When sidewalk construction method, using following steps:1) according to the intensity requirement and requirement of interim sidewalk, by roach, building Rubbish, cement and water mix, and carry out the trial test of mixing inverse proportion, while keeping cement that roach and building waste is secured Ground is cemented together;2) the mix ratio determined according to step 1), by roach, building waste, cement and water uniform mixing;3) will The roach of step 2) uniform mixing, building waste, cement and water mixture carry out layering decking and rolling, form roadbed;4) will Reinforced mesh is laid on the roadbed that the step 3) is formed;5) by the roach of step 2) uniform mixing, building waste, cement and The mixture of water paves on reinforced mesh, and is rolled repeatedly, and road surface is formed.
The volume of cement is 8~12%.
The grain size of building waste is not greater than 500mm, and the water content of roach is not greater than 50%.
Building waste is at least one of brick, broken concrete and rubble.
Roach is the soil or place surface layer miscellaneous fill that building enclosure bored pile construction drills out.
The thickness of layered rolling is not more than 500mm.
The steel wire diameter of reinforced mesh is 8-12mm, spacing 150-300mm;The lap of splice between reinforced mesh must not be small In 200mm, a height of 10-15cm of top mark of the reinforced mesh apart from road surface.
The invention has the advantages and positive effects that:It is mixed according to a certain percentage using roach, building waste, cement and water The mixture formed is closed as temporary road of the main material construction with some strength, layered rolling, at the top of temporary road Embedded reinforced mesh, increases the deformation stability on road surface, has not only realized the recycling of waste, but also meet construction site Road occupation deformation requirements, significantly reduce the construction cost of the interim sidewalk in construction site.
Description of the drawings
Fig. 1 is the structural schematic diagram that the present invention applies.
In figure:1, roadbed;2, reinforced mesh;3, road surface.
Specific implementation mode
In order to further understand the content, features and effects of the present invention, the following examples are hereby given, and coordinate attached drawing Detailed description are as follows:
Referring to Fig. 1, a kind of construction method of the interim sidewalk in construction site, using following steps:
1) according to the intensity requirement and requirement of interim sidewalk, roach, building waste, cement and water are blended in one It rises, carries out the trial test of mixing inverse proportion, while keeping cement that roach and building waste is cemented together securely,
2) the mix ratio determined according to step 1), by roach, building waste, cement and water uniform mixing;
3) mixture of the roach of step 2) uniform mixing, building waste, cement and water is subjected to layering decking and rolling, shape At roadbed 1;
4) reinforced mesh 2 is laid on the roadbed 1 that the step 3) is formed;
5) mixture of the roach of step 2) uniform mixing, building waste, cement and water is paved on reinforced mesh 2, And rolled repeatedly, form road surface 3.
In the present embodiment, the volume of the step 2), cement is 8~12%;The grain size of building waste is not greater than The water content of 500mm, roach are not greater than 50%, otherwise need the drying for carrying out roach;Building waste can be brick, coagulation At least one of native fragment and rubble;Roach is that the soil that building enclosure bored pile construction drills out or place surface layer are miscellaneous It bankets.The thickness of the step 3), layered rolling is not more than 500mm.The steel wire diameter of the step 4), reinforced mesh 2 is 8- 12mm, spacing 150-300mm;The lap of splice between reinforced mesh 2 cannot be less than 200mm, top of the reinforced mesh 2 apart from road surface Absolute altitude is 10-15cm.
Although the preferred embodiment of the present invention is described above in conjunction with attached drawing, the invention is not limited in upper The specific implementation mode stated, the above mentioned embodiment is only schematical, be not it is restrictive, this field it is common Technical staff under the inspiration of the present invention, in the case where not departing from present inventive concept and scope of the claimed protection, goes back Many forms can be made, within these are all belonged to the scope of protection of the present invention.

Claims (7)

1. a kind of construction method of the interim sidewalk in construction site, which is characterized in that use following steps:
1) according to the intensity requirement and requirement of interim sidewalk, roach, building waste, cement and water are mixed, into The trial test of row mixing inverse proportion, while keeping cement that roach and building waste is cemented together securely;
2) the mix ratio determined according to step 1), by roach, building waste, cement and water uniform mixing;
3) mixture of the roach of step 2) uniform mixing, building waste, cement and water is subjected to layering decking and rolling, forms road Base;
4) reinforced mesh is laid on the roadbed that the step 3) is formed;
5) mixture of the roach of step 2) uniform mixing, building waste, cement and water is paved on reinforced mesh, and carried out It rolls repeatedly, forms road surface.
2. the construction method of the interim sidewalk in construction site according to claim 1, which is characterized in that the step 2), water The volume of mud is 8~12%.
3. the construction method of the interim sidewalk in construction site according to claim 1, which is characterized in that the step 2) is built The grain size of building refuse is not greater than 500mm, and the water content of roach is not greater than 50%.
4. the construction method of the interim sidewalk in construction site according to claim 1, which is characterized in that the step 2) is built Building refuse is at least one of brick, broken concrete and rubble.
5. the construction method of the interim sidewalk in construction site according to claim 1, which is characterized in that the step 2) is given up Soil is the soil or place surface layer miscellaneous fill that building enclosure bored pile construction drills out.
6. the construction method of the interim sidewalk in construction site according to claim 1, which is characterized in that the step 3), point The thickness that layer rolls is not more than 500mm.
7. the construction method of the interim sidewalk in construction site according to claim 1, which is characterized in that the step 4), steel The steel wire diameter of muscle mesh sheet is 8-12mm, spacing 150-300mm;The lap of splice between reinforced mesh cannot be less than 200mm, steel The a height of 10-15cm of top mark of the muscle mesh sheet apart from road surface.
CN201810234734.4A 2018-03-21 2018-03-21 A kind of construction method of the interim sidewalk in construction site Pending CN108457147A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810234734.4A CN108457147A (en) 2018-03-21 2018-03-21 A kind of construction method of the interim sidewalk in construction site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810234734.4A CN108457147A (en) 2018-03-21 2018-03-21 A kind of construction method of the interim sidewalk in construction site

Publications (1)

Publication Number Publication Date
CN108457147A true CN108457147A (en) 2018-08-28

Family

ID=63237095

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810234734.4A Pending CN108457147A (en) 2018-03-21 2018-03-21 A kind of construction method of the interim sidewalk in construction site

Country Status (1)

Country Link
CN (1) CN108457147A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110093833A (en) * 2019-05-20 2019-08-06 山西工程技术学院 A method of temporary pavement is laid with using building materials waste material
CN113897837A (en) * 2021-11-19 2022-01-07 北京顺杰伟业消防工程有限公司 Movable floor and manufacturing method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2937231Y (en) * 2006-05-08 2007-08-22 杨庆国 Cement concrete road structure of regenerated cement concrete surface
CN2937230Y (en) * 2006-05-08 2007-08-22 杨庆国 Road structure of regenerated aggregate substrate
KR100852393B1 (en) * 2007-06-01 2008-08-14 이갑석 Solidification method of soil and industrial waste and solidified body of soil and industrial waste by this method
CN101265685A (en) * 2007-06-24 2008-09-17 沧州市市政工程公司 Method for regenerating waste solid for use in road foundation
CN101624277A (en) * 2009-08-20 2010-01-13 三门峡豫鑫路桥工程有限责任公司 Roadbed material adopting regenerative raw materials including construction wastes and discarded glass to replace sand and stone
CN205205600U (en) * 2015-11-06 2016-05-04 首钢环境产业有限公司 Regeneration road surface structure
CN205474668U (en) * 2016-01-21 2016-08-17 嘉兴市万盛建设股份有限公司 Temporary road
CN107151960A (en) * 2017-06-24 2017-09-12 中铁十局集团第二工程有限公司 The soft interim sidewalk laying structure in base and laying method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2937231Y (en) * 2006-05-08 2007-08-22 杨庆国 Cement concrete road structure of regenerated cement concrete surface
CN2937230Y (en) * 2006-05-08 2007-08-22 杨庆国 Road structure of regenerated aggregate substrate
KR100852393B1 (en) * 2007-06-01 2008-08-14 이갑석 Solidification method of soil and industrial waste and solidified body of soil and industrial waste by this method
CN101265685A (en) * 2007-06-24 2008-09-17 沧州市市政工程公司 Method for regenerating waste solid for use in road foundation
CN101624277A (en) * 2009-08-20 2010-01-13 三门峡豫鑫路桥工程有限责任公司 Roadbed material adopting regenerative raw materials including construction wastes and discarded glass to replace sand and stone
CN205205600U (en) * 2015-11-06 2016-05-04 首钢环境产业有限公司 Regeneration road surface structure
CN205474668U (en) * 2016-01-21 2016-08-17 嘉兴市万盛建设股份有限公司 Temporary road
CN107151960A (en) * 2017-06-24 2017-09-12 中铁十局集团第二工程有限公司 The soft interim sidewalk laying structure in base and laying method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110093833A (en) * 2019-05-20 2019-08-06 山西工程技术学院 A method of temporary pavement is laid with using building materials waste material
CN113897837A (en) * 2021-11-19 2022-01-07 北京顺杰伟业消防工程有限公司 Movable floor and manufacturing method thereof

Similar Documents

Publication Publication Date Title
CN107419630B (en) Soft soil foundation high-filling embankment capable of effectively controlling post-construction settlement and construction method
CN108560542B (en) A kind of bidirectional reinforcement of waste tire covering building slag and construction method thereof
CN113774917B (en) Safe construction method for earth and rockfill excavation and side slope supporting engineering
CN104264680B (en) The method for processing foundation of Tian Wa joint portion, a kind of collapsible loess slope
CN102587243A (en) Urban road water permeability cement concrete pavement structure and construction process thereof
CN113186766A (en) Shallow soft soil foundation foam light soil embankment structure and construction method
CN108914912A (en) A kind of Foundation Treatment engineering method of column-hammer forced tamping displacement
CN106676993B (en) Reinforced broken stone frame structure roadbed reinforcing system and reinforcing method thereof
CN104711974A (en) Steel tube recycled concrete composite bearing base pile and manufacturing method thereof
CN114319455B (en) Full-coverage sealing field, environment treatment and re-greening process for large refuse landfill
Feng et al. Elimination of loess collapsibility with application to construction and demolition waste during dynamic compaction
CN111794030A (en) The method of widening the embankment foundation at the building through the embankment
CN101200888A (en) Construction method of composite foundation
CN104763017B (en) Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system
CN108457147A (en) A kind of construction method of the interim sidewalk in construction site
CN102767170A (en) Earth pressure calculation method of upper buried structure
CN102409660A (en) Multi-section expanded head granular material pile composite foundation prestress construction method
CN100424272C (en) Construction Method of Static Pressure Pile Composite Foundation with Scattered Material
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN103669329B (en) Ultra-deep building waste cheats direct dynamic compaction Processing tecchnics
CN1548661A (en) Method of supporting foundation pit in soft layer with brad
CN209114276U (en) track pavement structure
CN106958176A (en) Quick prefabricated pin-connected panel soft base processing method
CN207160074U (en) A kind of non-settling structure of stable public way well body
CN110593242A (en) Heavy-load ground foundation structure of seepage-proofing area of soft foundation and processing method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180828