CN108445185A - One kind can opening door multifunctional tunnel Excavation simulation threedimensional model testing stand - Google Patents
One kind can opening door multifunctional tunnel Excavation simulation threedimensional model testing stand Download PDFInfo
- Publication number
- CN108445185A CN108445185A CN201810197383.4A CN201810197383A CN108445185A CN 108445185 A CN108445185 A CN 108445185A CN 201810197383 A CN201810197383 A CN 201810197383A CN 108445185 A CN108445185 A CN 108445185A
- Authority
- CN
- China
- Prior art keywords
- model
- tank wall
- tunnel excavation
- partition board
- box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N33/00—Investigating or analysing materials by specific methods not covered by groups G01N1/00 - G01N31/00
- G01N33/24—Earth materials
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Health & Medical Sciences (AREA)
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Food Science & Technology (AREA)
- Analytical Chemistry (AREA)
- Geology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Medicinal Chemistry (AREA)
- Physics & Mathematics (AREA)
- Remote Sensing (AREA)
- Biochemistry (AREA)
- General Health & Medical Sciences (AREA)
- General Physics & Mathematics (AREA)
- Immunology (AREA)
- Pathology (AREA)
- Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
Abstract
本发明公布了一种可开门式三维隧道开挖模拟模型试验箱,模型试验箱设置侧门、中央隔板和进水管网。侧门可方便开关,同时关闭后采用螺栓与模型箱连接,既便于隧道开挖试验结束后易于围岩的清理,又能保证模型箱整体的刚度。隔板将模型箱分为大小相同的两个小模型箱,可进行大、小两种尺寸的三维隧道开挖模型试验,尤其是可以同时进行两个小尺寸的三维隧道开挖模型试验。围岩填筑完成后可通过进水管网向模型箱内注水,可以将围岩内自由液面控制在试验设计位置。采用该模型箱可完成饱和地层、非饱和地层围岩条件,不同埋深、以及不同开挖面形式等复杂条件下的三维隧道开挖模型试验。
The invention discloses an openable three-dimensional tunnel excavation simulation model test box. The model test box is provided with a side door, a central partition and a water inlet pipe network. The side door can be opened and closed conveniently, and at the same time, bolts are used to connect with the model box after closing, which not only facilitates the cleaning of the surrounding rock after the tunnel excavation test, but also ensures the overall rigidity of the model box. The partition plate divides the model box into two small model boxes of the same size, which can be used for three-dimensional tunnel excavation model tests of large and small sizes, especially two small-sized three-dimensional tunnel excavation model tests can be carried out at the same time. After the filling of the surrounding rock is completed, water can be injected into the model box through the water inlet pipe network, and the free liquid level in the surrounding rock can be controlled at the test design position. The model box can be used to complete the three-dimensional tunnel excavation model test under complex conditions such as saturated strata, unsaturated stratum surrounding rock conditions, different buried depths, and different excavation face forms.
Description
技术领域technical field
一种可开门式三维隧道开挖模拟模型试验箱,属于盾构模拟技术领域。An openable three-dimensional tunnel excavation simulation model test box belongs to the technical field of shield tunneling simulation.
背景技术Background technique
地质力学模型试验方法是研究隧道开挖问题的一种行之有效的方法,它能够真实地反映地质条件和工程结构的关系,准确地模拟施工过程和影响,试验结果更加直观,使人们更容易从全局上把握隧道工程整体力学特征、变形趋势和稳定性的特点,从而做出判断。因此,隧道开挖模拟模型试验平台的研究非常必要。Yong-Joo Lee(2006)研制了尺寸为1.058m×0.93m×0.075m(宽×高×厚)的隧道开挖模型试验平台,该平台采用铝棒模拟围岩,以一种特制的变直径装置模拟隧道开挖过程,可用于隧道开挖过程中地层损失对围岩变形和临近建筑物影响的研究;山东大学(2008)研制了可模拟高地应力额隧道开挖模型试验平台,尺寸为4.5m×3.55m×2m(宽×高×厚),可实现四面加载,最大可模拟埋深2000m,试验台可实现均匀梯级加载,模拟真实的初始地应力场,进行高地应力以及超载破坏模拟试验;北京交通大学(2010)研制了隧道开挖平面应变模型试验平台,尺寸为3m×1.62m×0.3m,可用于进行逐级加载过程中隧道围岩破坏过程的研究;同济大学(2013)研制了平面应变隧道开挖模型试验平台,尺寸为1.6m×1.3m×0.4m(宽×高×厚),开挖系统由四块钢板和内部支撑螺栓组成,通过钢板的拆卸模式隧道的开挖,可用于进行逐级加载过程中隧道围岩破坏过程的研究;北京工业大学(2014)研制了尺寸为1.5m×1.5m×0.4m(宽×高×厚)的隧道开挖模型试验平台,采用气囊模拟隧道开挖的过程,可用于隧道开挖过程中地层损失对围岩变形和临近建筑物影响的研究。上述试验平台都只能模拟二维隧道开挖试验,无法进行隧道开挖过程围岩、结构等的三维时空受力、变形规律的研究。山东大学(2007)研制了新型组合式三维地质力学模型试验台架装置,尺寸为4×3.2m×1.7m(宽×高×厚),该装置规模较大,尺寸可任意调整,既能进行三维模型试验,又能进行平面模型试验,同时,可模拟岩土工程的实际地形地貌特征;Jong-Ho Shin(2008),研制了大型三维隧道开挖模拟试验平台,尺寸为3.6m×4m×3.3m,隧道开挖直径可达到1.1m,可实现顶部加载,可进行隧道开工程对围岩和开挖面稳定性的研究;山东大学(2013)研制了海底隧道流固耦合模型试验系统,尺寸为3.4m×3m×0.8m,试验系统组装方便、密封性好、可视化,模型试验架尺寸及结构可以纵向拓展,可以进行大比尺三维流–固耦合模型试验,可模拟海水深度最大为57m。根据研究的问题不同,近年来,各高校和科研单位已经研制了大量的三维隧道开挖模型试验平台,但隧道开挖试验完成后台架内部的围岩材料很难清理出来,这是这些试验平台的存在一个共同的问题。因此,研制一种既能实现不同条件下隧道开挖模拟,又能方便试验完成后围岩材料清理的多功能模型试验台十分必要。The geomechanics model test method is an effective method for studying tunnel excavation problems. It can truly reflect the relationship between geological conditions and engineering structures, and accurately simulate the construction process and impact. The test results are more intuitive and make it easier for people to Grasp the overall mechanical characteristics, deformation trend and stability characteristics of tunnel engineering from an overall perspective, so as to make judgments. Therefore, the research on the tunnel excavation simulation model test platform is very necessary. Yong-Joo Lee (2006) developed a tunnel excavation model test platform with a size of 1.058m×0.93m×0.075m (width×height×thickness). The device simulates the tunnel excavation process, which can be used to study the influence of stratum loss on surrounding rock deformation and adjacent buildings during tunnel excavation; Shandong University (2008) developed a model test platform that can simulate high ground stress tunnel excavation, with a size of 4.5 m×3.55m×2m (width×height×thickness), can realize four-sided loading, and can simulate a maximum buried depth of 2000m. The test bench can realize uniform step loading, simulate the real initial stress field, and conduct high stress and overload damage simulation tests ; Beijing Jiaotong University (2010) developed a plane strain model test platform for tunnel excavation, with a size of 3m × 1.62m × 0.3m, which can be used to study the failure process of tunnel surrounding rock during step-by-step loading; Tongji University (2013) developed A plane strain tunnel excavation model test platform is established, with a size of 1.6m×1.3m×0.4m (width×height×thickness). The excavation system consists of four steel plates and internal support bolts. , which can be used to study the failure process of tunnel surrounding rock during step-by-step loading; Beijing University of Technology (2014) developed a tunnel excavation model test platform with a size of 1.5m×1.5m×0.4m (width×height×thickness), The airbag is used to simulate the process of tunnel excavation, which can be used to study the influence of formation loss on surrounding rock deformation and adjacent buildings during tunnel excavation. The above-mentioned test platforms can only simulate two-dimensional tunnel excavation tests, and cannot conduct research on the three-dimensional spatiotemporal force and deformation laws of surrounding rock and structures during tunnel excavation. Shandong University (2007) developed a new combined three-dimensional geomechanics model test bench device with a size of 4×3.2m×1.7m (width×height×thickness). The three-dimensional model test can also carry out the plane model test, and at the same time, it can simulate the actual terrain and landform characteristics of geotechnical engineering; Jong-Ho Shin (2008), developed a large-scale three-dimensional tunnel excavation simulation test platform with a size of 3.6m×4m× 3.3m, the tunnel excavation diameter can reach 1.1m, can realize top loading, and can conduct research on the stability of surrounding rock and excavation surface in tunnel engineering; Shandong University (2013) developed a fluid-solid coupling model test system for subsea tunnels, The size is 3.4m×3m×0.8m. The test system is easy to assemble, has good sealing performance, and is visualized. The size and structure of the model test frame can be expanded vertically, and large-scale three-dimensional fluid-solid coupling model tests can be carried out. The maximum depth of seawater that can be simulated is 57m. According to different research problems, in recent years, various universities and research institutes have developed a large number of three-dimensional tunnel excavation model test platforms, but it is difficult to clean the surrounding rock materials inside the frame after the tunnel excavation test is completed. There is a common problem. Therefore, it is necessary to develop a multifunctional model test bench that can realize tunnel excavation simulation under different conditions and facilitate the cleaning of surrounding rock materials after the test is completed.
发明内容Contents of the invention
本发明的目的在于提供可一种可开门式三维隧道开挖模拟模型试验箱,既可以进行复杂条件下三维隧道开挖模型试验,又能在试验完成后方便的清理台架内部的围岩材料。The purpose of the present invention is to provide an openable three-dimensional tunnel excavation simulation model test box, which can not only carry out three-dimensional tunnel excavation model test under complex conditions, but also can conveniently clean the surrounding rock materials inside the bench after the test is completed. .
为了达到上述目的,本发明采用了以下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:
一种可开门式三维隧道开挖模拟模型试验箱,该模型试验箱由底座(1)、底板(2)、箱壁a(3)、箱壁b(4)、箱壁c(5)、箱壁d(6)五部分组成。箱壁a(3)、箱壁b(4)、箱壁c(5)、箱壁d(6)顺次连接组成长方体结构;箱壁(4)b和箱壁d(6)上分别设置前预留开挖孔(7)和后预留开挖孔(8)。箱壁c(5)由两扇能开关的侧门(9)组成,侧门(9)能绕安装于两侧的合页(10)旋转,从而实现侧门(9)的开关。箱壁c(5)内侧设置一圈钢梁(11),为保证试验中箱壁c(5)的强度,用高强螺栓(12)将两扇侧门(9)固定在钢梁(11)上。箱壁a(3)和箱壁c(5)的中央位置处安装有隔板(13),隔板(13)安装后将长方体结构的模型试验箱分成两个大小相同的小模型箱。隔板(13)通过卡槽(14)固定在箱壁a(3)和箱壁c(5),隔板(13)能够自由拆卸。为保证试验过程中隔板(13)的强度,用螺栓将隔板(13)固定在卡槽(14)上。隔板(13)上设置有开挖孔(16),开挖孔(16)的直径与前预留开挖孔(7)和后预留开挖孔(8)的直径相等。A door-openable three-dimensional tunnel excavation simulation model test box, the model test box consists of a base (1), a bottom plate (2), a box wall a (3), a box wall b (4), a box wall c (5), Box wall d (6) is made up of five parts. Box wall a(3), box wall b(4), box wall c(5), box wall d(6) are sequentially connected to form a cuboid structure; box wall (4)b and box wall d(6) are respectively set Reserve the excavation hole (7) and the back reservation excavation hole (8) before. Box wall c (5) is made up of two side doors (9) that can switch, and side door (9) can rotate around the hinge (10) that is installed on both sides, thereby realizes the switch of side door (9). A circle of steel beams (11) is set on the inner side of the box wall c(5). In order to ensure the strength of the box wall c(5) in the test, the two side doors (9) are fixed on the steel beams (11) with high-strength bolts (12). . A partition (13) is installed at the central position of the box wall a (3) and the box wall c (5). After the partition (13) is installed, the model test box of the cuboid structure is divided into two small model boxes of the same size. The partition (13) is fixed on the box wall a (3) and the box wall c (5) through the card slot (14), and the partition (13) can be disassembled freely. In order to ensure the strength of the dividing plate (13) during the test, the dividing plate (13) is fixed on the draw-in groove (14) with bolts. The dividing plate (13) is provided with an excavation hole (16), and the diameter of the excavation hole (16) is equal to the diameter of the front reserved excavation hole (7) and the rear reserved excavation hole (8).
模型箱底板(2)上安装有两套独立的进水管网(17、18),两套独立的进水管网分别对被隔板(13)两个小模型箱内的围岩进行饱和。每套进水管网(17、18)由进水口(19)、总管(20)和支管(21)组成。进水口(19)由箱壁(3)底部引出。支管(21)上每隔100mm设置一对出水孔(22),两出水孔(22)与支管(21)圆心的连线正交,且对称布置。Two sets of independent water inlet pipe networks (17, 18) are installed on the model box bottom plate (2), and the two sets of independent water inlet pipe networks respectively saturate the surrounding rocks in the two small model boxes by the clapboard (13) . Each set of water inlet pipe network (17, 18) is made up of water inlet (19), main pipe (20) and branch pipe (21). Water inlet (19) is drawn by the bottom of case wall (3). A pair of water outlet holes (22) are arranged every 100mm on the branch pipe (21), and the connection line between the two water outlet holes (22) and the center of the branch pipe (21) is orthogonal and arranged symmetrically.
进行大模型试验时将隔板(13)拆卸,通过隔板(13)上部的吊装孔(23)用吊车将隔板(13)移出至模型试验箱的外部。进行小模型试验时再将隔板(13)安装在模型试验箱的内部。When carrying out the large model test, the dividing plate (13) is disassembled, and the dividing plate (13) is moved out to the outside of the model test box with a crane through the hoisting hole (23) on the upper part of the dividing plate (13). When carrying out small model test, dividing plate (13) is installed in the inside of model test box again.
侧门(9)与钢梁(11)连接的部位设置密封圈,隔板(13)与卡槽(14)连接的位置也设置密封圈,侧门(9)与钢梁(11)之间的缝隙的位置用密封胶进行密封,使模型试验箱有良好的密封性。侧门(9)上安装透明的有机玻璃,能够观测到模型试验箱内水位的变化。A sealing ring is provided at the connection between the side door (9) and the steel beam (11), and a sealing ring is also provided at the connection between the partition plate (13) and the slot (14). The gap between the side door (9) and the steel beam (11) The position is sealed with sealant, so that the model test box has good airtightness. Transparent plexiglass is installed on the side door (9), and the variation of the water level in the model test chamber can be observed.
支管(21)通过钢制卡子(24)固定在模型箱底板(2)上。Branch pipe (21) is fixed on the model box bottom plate (2) by steel clamp (24).
本发明的工作过程和工作原理是:Work process and working principle of the present invention are:
试验开始之前先将两扇门关闭,用螺栓将其固定在钢梁上,同时将前、后开挖孔封闭。若开展大模型试验,将隔板从模型箱内部吊出。先在模型箱底部平铺一层砾石,保证能将底部的进水管道全部覆盖,防止填土过程中管道出水孔堵塞。然后按填土方案向模型箱内部填土,土体内埋有土压力盒、渗压计和位移计,这些传感器均与数据采集及处理装置相连。围岩填筑完成后向模型箱底部的进水管网内注水,控制自由液面达到试验设计的位置。将前开挖孔挡板取下进行隧道开挖,并采集记录各项数据。试验完成后,将侧门的固定螺栓全部取下,打开侧门,将模型箱内部的围岩材料取出。若开展小模型试验,则将隔板安装在模型箱中部,重复上述过程。Before the test started, the two doors were closed and bolted to the steel beam, and the front and rear excavation holes were closed at the same time. If a large model test is carried out, the partition is lifted out from the inside of the model box. Spread a layer of gravel on the bottom of the model box first to ensure that the water inlet pipes at the bottom can be completely covered to prevent the pipe outlet holes from being blocked during the filling process. Then fill the model box with soil according to the soil filling scheme. The soil body is embedded with earth pressure cells, piezometers and displacement meters, and these sensors are connected with data acquisition and processing devices. After the filling of the surrounding rock is completed, water is injected into the water inlet pipe network at the bottom of the model box, and the free liquid surface is controlled to reach the position designed for the test. Remove the front excavation hole baffle for tunnel excavation, and collect and record various data. After the test is completed, all the fixing bolts of the side door are removed, the side door is opened, and the surrounding rock material inside the model box is taken out. If a small model test is carried out, install the partition in the middle of the model box and repeat the above process.
本发明的有益效果在于:The beneficial effects of the present invention are:
(1)本隧道开挖模拟模型试验台可完成饱和地层、非饱和地层围岩条件,不同开挖面形式等复杂条件下的三维隧道开挖模型试验;(1) The tunnel excavation simulation model test bench can complete the three-dimensional tunnel excavation model test under complex conditions such as saturated stratum, unsaturated stratum surrounding rock conditions, and different excavation face forms;
(2)本隧道开挖模拟模型试验台可进行大、小两种尺寸的三维隧道开挖模型试验,尤其是可以同时进行两个小尺寸的三维隧道开挖模型试验;(2) The tunnel excavation simulation model test bench can carry out three-dimensional tunnel excavation model tests of large and small sizes, especially two small-sized three-dimensional tunnel excavation model tests can be carried out at the same time;
(3)本隧道开挖模拟模型试验台在试验完成后打开侧门,可以方便模型箱内围岩材料的清理。(3) The tunnel excavation simulation model test bench opens the side door after the test is completed, which can facilitate the cleaning of surrounding rock materials in the model box.
附图说明Description of drawings
图1是本发明所述隧道开挖模拟模型箱三围视图;Fig. 1 is three-dimensional view of tunnel excavation simulation model box of the present invention;
图2是本发明所述隧道开挖模拟模型箱进水管网布置图;Fig. 2 is the tunnel excavation simulation model box water inlet pipe network layout diagram of the present invention;
图3是本发明所述进水管网支管出水孔设计图。Fig. 3 is a design drawing of outlet holes of branch pipes of the water inlet pipe network according to the present invention.
具体实施方式Detailed ways
下面结合附图对本发明作进一步具体描述:Below in conjunction with accompanying drawing, the present invention is described in further detail:
如图1~图3所示,本发明所述一种可开门式多功能隧道开挖模拟三维模型箱As shown in Figures 1 to 3, a door-openable multifunctional tunnel excavation simulation three-dimensional model box according to the present invention
试验开始之前先将两扇侧门(9)关闭,用螺栓(12)将其固定在钢梁(11)上,同时将前、后开挖孔(7、8)封闭。若开展大模型试验,将隔板(13)从模型箱(1)内部吊出。先在模型箱(1)底部平铺一层砾石,保证能将底部的管网(17、18)全部覆盖,防止填土过程中管道出水孔堵塞。然后按填土方案向模型箱内部填土,土体内埋有土压力盒、渗压计和位移计,这些传感器均与数据采集及处理装置相连。围岩填筑完成后向模型箱内部注水,使围岩内自由液面位置达到试验要求。将前开挖孔(7)挡板取下进行隧道开挖,并采集记录各项数据。试验完成后,将侧门的固定螺栓(12)全部取下,打开侧门(9),将模型箱内部的围岩材料取出。若开展小模型试验,则将隔板(13)安装在模型箱中部卡槽(14)内,并用螺栓固定,重复上述试验过程。若同时开展两个小模型试验,则同时向由隔板(13)分隔成的两小模型箱内填筑围岩,从前、后预留开挖孔(7、8)分别开挖隧道。Two fan side doors (9) are closed earlier before the test begins, and it is fixed on the steel beam (11) with bolt (12), and front and rear excavation holes (7,8) are closed simultaneously. If carrying out the large-scale model test, the dividing plate (13) is hung out from the inside of the model box (1). Pave a layer of gravel at the bottom of the model box (1) earlier to ensure that the pipe network (17, 18) at the bottom can be fully covered to prevent the pipe outlet hole from being blocked in the soil filling process. Then fill the model box with soil according to the soil filling scheme. The soil body is embedded with earth pressure cells, piezometers and displacement meters, and these sensors are connected with data acquisition and processing devices. After the filling of the surrounding rock is completed, water is injected into the model box to make the position of the free liquid surface in the surrounding rock meet the test requirements. The baffle plate of the front excavation hole (7) is removed for tunnel excavation, and various data are collected and recorded. After the test was completed, the fixing bolts (12) of the side door were all taken off, the side door (9) was opened, and the surrounding rock material inside the model box was taken out. If the small model test is carried out, the partition plate (13) is installed in the slot (14) in the middle of the model box, and fixed with bolts, and the above test process is repeated. If two small model tests are carried out simultaneously, surrounding rocks are filled in two small model boxes separated by dividing plates (13) simultaneously, and excavation holes (7,8) are reserved for excavating tunnels from the front and back.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810197383.4A CN108445185A (en) | 2018-03-11 | 2018-03-11 | One kind can opening door multifunctional tunnel Excavation simulation threedimensional model testing stand |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810197383.4A CN108445185A (en) | 2018-03-11 | 2018-03-11 | One kind can opening door multifunctional tunnel Excavation simulation threedimensional model testing stand |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN108445185A true CN108445185A (en) | 2018-08-24 |
Family
ID=63194546
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810197383.4A Pending CN108445185A (en) | 2018-03-11 | 2018-03-11 | One kind can opening door multifunctional tunnel Excavation simulation threedimensional model testing stand |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108445185A (en) |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109374868A (en) * | 2018-12-29 | 2019-02-22 | 中交第三航务工程局有限公司 | A quasi-prototype test model and hoisting method for tunnel pipe joints that are easy to hoist |
| CN109406759A (en) * | 2018-12-14 | 2019-03-01 | 北京工业大学 | A kind of multi-functional geotechnical engineering test model case of assembled |
| CN109655596A (en) * | 2018-12-14 | 2019-04-19 | 广州海洋地质调查局 | A kind of multivariable condition submarine shallow gas leakage analogy method |
| CN109931981A (en) * | 2019-03-15 | 2019-06-25 | 山东黄河河务局工程建设中心 | A kind of fiber-optic grating sensor distribution method for Yellow River lock |
| CN110057676A (en) * | 2019-05-29 | 2019-07-26 | 国网河北省电力有限公司石家庄供电分公司 | A kind of pipe jacking tunnel work progress model test hole |
| CN110187080A (en) * | 2019-06-26 | 2019-08-30 | 北京中煤矿山工程有限公司 | A kind of modularization soil case of subway analog simulation test |
| CN110284530A (en) * | 2019-05-17 | 2019-09-27 | 同济大学 | In conjunction with the Multifunctional assembled model test case apparatus and application in foundation pit and tunnel |
| CN111677020A (en) * | 2020-05-30 | 2020-09-18 | 湖南科技大学 | A prefabricated geotechnical test model box with a separable box body |
| CN112304665A (en) * | 2020-11-30 | 2021-02-02 | 福州大学 | Model box for tunnel excavation supporting and static force pushing test and using method |
| CN117388081A (en) * | 2023-12-12 | 2024-01-12 | 西南交通大学 | A test device and test method for determining the bearing capacity of tunnel anchors by push-back loading |
| CN119124861A (en) * | 2024-11-12 | 2024-12-13 | 华侨大学 | A deep rock excavation water inrush disaster testing device |
Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101738331A (en) * | 2009-12-28 | 2010-06-16 | 北京交通大学 | Tunnel construction simulation plane strain model test device |
| CN103091222A (en) * | 2013-01-04 | 2013-05-08 | 西南交通大学 | Device for simulating and testing water burst of tunnel fissure |
| CN203287239U (en) * | 2013-05-29 | 2013-11-13 | 浙江大学 | Earth pressure balance shield excavation face stability control model test device |
| CN103431502A (en) * | 2013-09-03 | 2013-12-11 | 曹县海纳食品有限公司 | High-pressure cleaning device |
| CN104330533A (en) * | 2014-10-30 | 2015-02-04 | 中国矿业大学 | Testing device and method for simulating collapse of tunnel surrounding rock under conditions of rainfall and underground water seepage |
| CN104713987A (en) * | 2015-01-25 | 2015-06-17 | 北京工业大学 | Model test apparatus for stimulating tunnel excavation process |
| CN107132338A (en) * | 2017-06-21 | 2017-09-05 | 山东大学 | A kind of tunnel surrounding grouting and reinforcing Excavation simulation device and method |
| CN206467702U (en) * | 2017-02-17 | 2017-09-05 | 南京新吉泰岩土工程有限公司 | A kind of multi-functional pile foundation simulation chamber |
| CN206573572U (en) * | 2017-03-21 | 2017-10-20 | 河南工业大学 | A kind of analogue means of natural arch |
-
2018
- 2018-03-11 CN CN201810197383.4A patent/CN108445185A/en active Pending
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101738331A (en) * | 2009-12-28 | 2010-06-16 | 北京交通大学 | Tunnel construction simulation plane strain model test device |
| CN103091222A (en) * | 2013-01-04 | 2013-05-08 | 西南交通大学 | Device for simulating and testing water burst of tunnel fissure |
| CN203287239U (en) * | 2013-05-29 | 2013-11-13 | 浙江大学 | Earth pressure balance shield excavation face stability control model test device |
| CN103431502A (en) * | 2013-09-03 | 2013-12-11 | 曹县海纳食品有限公司 | High-pressure cleaning device |
| CN104330533A (en) * | 2014-10-30 | 2015-02-04 | 中国矿业大学 | Testing device and method for simulating collapse of tunnel surrounding rock under conditions of rainfall and underground water seepage |
| CN104713987A (en) * | 2015-01-25 | 2015-06-17 | 北京工业大学 | Model test apparatus for stimulating tunnel excavation process |
| CN206467702U (en) * | 2017-02-17 | 2017-09-05 | 南京新吉泰岩土工程有限公司 | A kind of multi-functional pile foundation simulation chamber |
| CN206573572U (en) * | 2017-03-21 | 2017-10-20 | 河南工业大学 | A kind of analogue means of natural arch |
| CN107132338A (en) * | 2017-06-21 | 2017-09-05 | 山东大学 | A kind of tunnel surrounding grouting and reinforcing Excavation simulation device and method |
Cited By (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109655596B (en) * | 2018-12-14 | 2021-06-29 | 广州海洋地质调查局 | A Multivariable Conditional Subsea Shallow Gas Seepage Simulation Method |
| CN109406759A (en) * | 2018-12-14 | 2019-03-01 | 北京工业大学 | A kind of multi-functional geotechnical engineering test model case of assembled |
| CN109655596A (en) * | 2018-12-14 | 2019-04-19 | 广州海洋地质调查局 | A kind of multivariable condition submarine shallow gas leakage analogy method |
| CN109374868A (en) * | 2018-12-29 | 2019-02-22 | 中交第三航务工程局有限公司 | A quasi-prototype test model and hoisting method for tunnel pipe joints that are easy to hoist |
| CN109931981A (en) * | 2019-03-15 | 2019-06-25 | 山东黄河河务局工程建设中心 | A kind of fiber-optic grating sensor distribution method for Yellow River lock |
| CN110284530A (en) * | 2019-05-17 | 2019-09-27 | 同济大学 | In conjunction with the Multifunctional assembled model test case apparatus and application in foundation pit and tunnel |
| CN110057676A (en) * | 2019-05-29 | 2019-07-26 | 国网河北省电力有限公司石家庄供电分公司 | A kind of pipe jacking tunnel work progress model test hole |
| CN110187080A (en) * | 2019-06-26 | 2019-08-30 | 北京中煤矿山工程有限公司 | A kind of modularization soil case of subway analog simulation test |
| CN111677020A (en) * | 2020-05-30 | 2020-09-18 | 湖南科技大学 | A prefabricated geotechnical test model box with a separable box body |
| CN112304665A (en) * | 2020-11-30 | 2021-02-02 | 福州大学 | Model box for tunnel excavation supporting and static force pushing test and using method |
| CN117388081A (en) * | 2023-12-12 | 2024-01-12 | 西南交通大学 | A test device and test method for determining the bearing capacity of tunnel anchors by push-back loading |
| CN117388081B (en) * | 2023-12-12 | 2024-04-02 | 西南交通大学 | Test device and test method for determining bearing capacity of tunnel anchor by backward-pushing loading |
| CN119124861A (en) * | 2024-11-12 | 2024-12-13 | 华侨大学 | A deep rock excavation water inrush disaster testing device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108445185A (en) | One kind can opening door multifunctional tunnel Excavation simulation threedimensional model testing stand | |
| CN110284530B (en) | Multifunctional combined assembled model test box device combining foundation pit and tunnel and application | |
| CN203949915U (en) | A kind of soil body penetration of studying destroys the multifunction test device developing | |
| CN207730761U (en) | A kind of experimental rig of simulation shield tunnel construction | |
| CN108625865A (en) | A kind of test method of simulation shield tunnel construction | |
| CN109377849A (en) | A true 3D physical model test system for simulating water inrush disasters in deep caverns | |
| CN105839679B (en) | Model test apparatus of double ground-connecting-wall excavation of foundation pit to tunnel convergence deformation effect | |
| CN105510534A (en) | Testing device and method capable of simulating filling and grouting of water-containing coal seams with different inclination angles | |
| CN109632509A (en) | Hypergravity true triaxial rock loading experimental apparatus and method | |
| CN107119731A (en) | Foundation ditch group excavates the model test apparatus to close to buildings deformation effect | |
| US11906481B1 (en) | Grouting and water-plugging device for fractured rock in mine coupling state, and test method | |
| CN117589493B (en) | Experimental device for simulating underground water to influence compression energy storage stability of coal mine tunnel | |
| CN116242757B (en) | Shield tunnel service environment simulation method and system considering water effects | |
| CN113432997A (en) | Device and method for testing three-dimensional damage mode of tunnel face soil body of river-crossing sea shield tunnel | |
| CN113049780A (en) | Testing device and testing method for gangue fluidized filling material | |
| CN115825339A (en) | Karst tunnel water gushing test device and method | |
| CN109958420B (en) | Visualized test device and test method for simulating the evolution of cracks in coal mining roadway | |
| CN105486835A (en) | Expansive-soft-rock roadway-surrounding-rock damage analog simulation test apparatus and test method | |
| CN105954499A (en) | Method and device for evaluating collapsible site after carrying out fracturing grouting reinforcement on collapsible loess site | |
| CN108922368A (en) | A kind of continuous wall trench underground overall process test method and its simulator | |
| CN206115855U (en) | Tunnel is supporting construction experimental model case in advance | |
| CN100343485C (en) | Analogue soil box for analogue shiold tunnelling machine testing | |
| CN109637334A (en) | It is a kind of solid similarity simulation experiment model and its simulation implementation method | |
| CN108374666B (en) | The method that native case bankets in earth pressure balanced shield, EPBS identification of formation research experiment | |
| CN210141128U (en) | Test device for simulating pipe curtain undercut |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180824 |