CN108425673A - A kind of production practice of copper mine - Google Patents

A kind of production practice of copper mine Download PDF

Info

Publication number
CN108425673A
CN108425673A CN201810138215.8A CN201810138215A CN108425673A CN 108425673 A CN108425673 A CN 108425673A CN 201810138215 A CN201810138215 A CN 201810138215A CN 108425673 A CN108425673 A CN 108425673A
Authority
CN
China
Prior art keywords
ore
mine
production
copper mine
annular solid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810138215.8A
Other languages
Chinese (zh)
Inventor
李文康
张宸宇
欧西江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Huayang Mineral Source Material Co Ltd
Original Assignee
Guangxi Huayang Mineral Source Material Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Huayang Mineral Source Material Co Ltd filed Critical Guangxi Huayang Mineral Source Material Co Ltd
Priority to CN201810138215.8A priority Critical patent/CN108425673A/en
Publication of CN108425673A publication Critical patent/CN108425673A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/22Methods of underground mining; Layouts therefor for ores, e.g. mining placers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B03SEPARATION OF SOLID MATERIALS USING LIQUIDS OR USING PNEUMATIC TABLES OR JIGS; MAGNETIC OR ELECTROSTATIC SEPARATION OF SOLID MATERIALS FROM SOLID MATERIALS OR FLUIDS; SEPARATION BY HIGH-VOLTAGE ELECTRIC FIELDS
    • B03BSEPARATING SOLID MATERIALS USING LIQUIDS OR USING PNEUMATIC TABLES OR JIGS
    • B03B9/00General arrangement of separating plant, e.g. flow sheets
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Remote Sensing (AREA)
  • Manufacture And Refinement Of Metals (AREA)

Abstract

The present invention provides a kind of production practice of copper mine, is related to exploitation of mineral resources technical field, includes the following steps:(1) minery setting, (2) mine locating, (3) mining, (4) back production, (5) desliming;The production practice of the present invention is high to the controlling extent of ore body, copper mine rate of recovery when mining can be effectively improved, copper mine loss late and the copper mine rate of dilution is reduced, improves the utilization rate of mineral resources, resource guarantee is provided for Sustainable Development of Mine, there is good use value and application prospect.

Description

A kind of production practice of copper mine
【Technical field】
The present invention relates to exploitation of mineral resources technical fields, and in particular to a kind of production practice of copper mine.
【Background technology】
Copper is one of the earliest copper alloy that the mankind have found, its matter is soft, rich in ductility, has good heat conduction and conduction Performance, tool and daily necessities can be processed by slightly beaing.The development of human society depends on substance, and mineral resources are then One of these important substance bases.Currently, 95% or more the energy, 80% or more the raw material of industry and 70% or more agricultural it is raw Production data both is from mineral resources.Mineral resources come from mine mostly, and have an opencast mining of building stone type mine as China The part in all kinds of mines can account for total mine 60% or so for the number of mine, therefore its comprehensive utilization of resources is realized Degree, to China's mine resources comprehensive utilization overall development play very important effect, in building mine field how Mine resources are comprehensively utilized, mine environment is protected, build Green Mine, promotes green mining to do more and benefits our pursuits, promote mine The lasting health coordinated development for producing development of resources comprehensive utilization and ecological environment has important directive significance.
Since early 1980s, China's mining activities order is more chaotic, and a large amount of people adopt so that in natural ore body There is a goaf there are many, and the mining methods of advanced winning equipment and science could not be used since the people adopt so that natural mine Internal goaf shape, structure not science, and its distribution is irregular, causes goaf stability poor, and personnel can not be direct Into goaf operation, prodigious difficulty is caused to the safe and efficient back production of ore body, and cause the damage of ore in exploitation process Mistake rate and the excessively high problem of the rate of dilution.
【Invention content】
In view of this, the purpose of the present invention is to provide a kind of production practice of copper mine, production practice of the invention is to mine The controlling extent of body is high, can effectively improve copper mine rate of recovery when mining, reduces copper mine loss late and the copper mine rate of dilution, improves The utilization rate of mineral resources provides resource guarantee for Sustainable Development of Mine, has good use value and application prospect.
In order to solve the above-mentioned technical problem, present invention employs the following technical solutions:
A kind of production practice of copper mine, includes the following steps:
(1) it prospects:Perpendicular to the exploration row of the direction arrangement interval certain distance of ore body principal length on predetermined absolute altitude Line tunnels prospecting drift, until puncturing entire ore body along exploration line;
(2) it digs up mine:It is dug up mine by the way of big cross section driving, while mining, vacant mining area will have been exploited Four walls are built into the annular solid in four faces up and down with reinforced concrete structure, and one section of annular is just constructed per exploiting one section forward Body, adjacent two annular solid are built into integral structure, and the vertical beam of build support is spaced between the inner wall up and down of annular solid, right The internal face of annular solid carries out Anti-steam-leakage, leakproof water process, and the mine hole of production or life is formed after the completion of coal mining;
(3) back production:On predetermined absolute altitude described in step (1), ore body is divided into two ore beds and carries out back production respectively, along mine Phosphor bodies trend caunches to ore body main body using shallow hole shrinkage method;
(4) desliming:One section of graded desliming, the sand setting of one section of classification are carried out to the ore pulp collected using hydrocyclone The agitator being sent into before flotation, the overflow of one section of classification are sent into dense bucket and carry out two sections of graded deslimings, and the sand setting of two sections of classifications is sent Enter the agitator, tail is lost in the overflow of two sections of classifications.
In the present invention, further, the back production in the step (3) is to carry out back production respectively to two ore bed of ore body, is first adopted Upper layer Hou Cai lower layers, back production lower layer ore bed after after upper layer mine balkstone avalanche and stablizing.
In the present invention, further, the interlayer between two kinds of mining methods stope of the upper and lower layer should ensure that 4-6m's Thickness.
In the present invention, further, Anti-steam-leakage, leakproof water process are carried out to the internal face of annular solid in the step (2) Concrete mode be:The internal face of annular solid is handled by way of injection or slip casting or surface plastic spraying.
In the present invention, further, back production step releases ore using rock drill rock drilling, explosion in the step (3) One third is left workbench of the ore as next back production rock drilling.
In the present invention, further, the outside in minery is provided with the logical of fresh air conveying to minery Wind facility.
It is further, described that gas boring and surveying and warning device are provided in minery in the present invention.
In conclusion by adopting the above-described technical solution, the beneficial effects of the invention are as follows:
1. the production practice of the copper mine of the present invention is on predetermined absolute altitude perpendicular to the direction prospecting drift of ore body principal length Up to puncturing entire ore body, under the situation that mine locating wears that arteries and veins discloses ore body and country rock distribution, cutting work is adopted by being carried out to ore body, Back production of caunching is carried out to ore body main body using shallow hole shrinkage method, it is high to the controlling extent of ore body, mine when mining can be effectively improved The stone rate of recovery reduces ore loss ratio and ore dilution rate, improves the utilization rate of mineral resources, provided for Sustainable Development of Mine Resource guarantee.The present invention makees the cutting of adopting that ore body carries out, and stability is good, safe and reliable, can effectively improve mining efficiency.
2. the present invention greatly reduces the danger coefficient of cutter's operation, and the overall cost dug up mine is low, is suitble to various The exploitation of mineral.
3. the present invention carries out back production of caunching using shallow hole shrinkage method to ore body main body, simple in structure, management facilitates, adopts quasi- work Journey amount is small, has good use value and application prospect.
4. the present invention is directed to the characteristics of copper mine, that is, is digging up mine in each flow of ore dressing or operation, easy ting produce particulate With the crushing sludge excessively of micro-size fraction, directly affect preparation equipment sorts efficiency, reduces the copper ore dressing rate of recovery and money Source utilization rate, therefore the step of carrying out desliming after mining carry out one section of graded desliming using hydrocyclone, and dense bucket carries out Two sections of graded deslimings are adjusted ore particle degree using the difference of hydrocyclone and dense bucket grading power, especially pair The removal of fine particles mineral reduces fine particles mineral to the greatest extent in the case where ensureing that coarse particles mineral loss is reduced Content makes ore pulp reach the desired particle size needed for flotation.
【Specific implementation mode】
The following examples can help those skilled in the art that the present invention is more fully understood, but cannot be with any Mode limits the present invention.
Embodiment 1
A kind of production practice for copper mine that the present embodiment is provided includes the following steps:
(1) minery is arranged:The outside in minery is provided with the ventilation equipment of fresh air conveying to minery;It is adopting Gas boring and surveying and warning device are provided in mining area;
(2) it prospects:Perpendicular to the exploration row of the direction arrangement interval certain distance of ore body principal length on predetermined absolute altitude Line tunnels prospecting drift, until puncturing entire ore body along exploration line;
(3) it digs up mine:It is dug up mine by the way of big cross section driving, while mining, vacant mining area will have been exploited Four walls are built into the annular solid in four faces up and down with reinforced concrete structure, and one section of annular is just constructed per exploiting one section forward Body, adjacent two annular solid are built into integral structure, and the vertical beam of build support is spaced between the inner wall up and down of annular solid, right The internal face of annular solid carries out Anti-steam-leakage, leakproof water process, and the mine hole of production or life is formed after the completion of coal mining;Its In, Anti-steam-leakage is carried out to the internal face of annular solid, the concrete mode of leakproof water process is:Pass through injection or slip casting or surface plastic spraying Mode the internal face of annular solid is handled.
(4) back production:On predetermined absolute altitude described in step (2), ore body is divided into two ore beds and carries out back production respectively, is first adopted Ceng Houcai lower layers, the interlayer between two kinds of mining methods stope of upper and lower layer should ensure that the thickness of 4m, using rock drill rock drilling, The one third of ore is released in explosion, is left workbench of the ore as next back production rock drilling, is waited in exploitation process Upper layer mine balkstone avalanche and back production lower layer ore bed after stablizing, along ore body main body trend using shallow hole shrinkage method to ore body master Body caunches;
(5) desliming:One section of graded desliming, the sand setting of one section of classification are carried out to the ore pulp collected using hydrocyclone The agitator being sent into before flotation, the overflow of one section of classification are sent into dense bucket and carry out two sections of graded deslimings, and the sand setting of two sections of classifications is sent Enter the agitator, tail is lost in the overflow of two sections of classifications.
Embodiment 2
A kind of production practice for copper mine that the present embodiment is provided includes the following steps:
(1) minery is arranged:The outside in minery is provided with the ventilation equipment of fresh air conveying to minery;It is adopting Gas boring and surveying and warning device are provided in mining area;
(2) it prospects:Perpendicular to the exploration row of the direction arrangement interval certain distance of ore body principal length on predetermined absolute altitude Line tunnels prospecting drift, until puncturing entire ore body along exploration line;
(3) it digs up mine:It is dug up mine by the way of big cross section driving, while mining, vacant mining area will have been exploited Four walls are built into the annular solid in four faces up and down with reinforced concrete structure, and one section of annular is just constructed per exploiting one section forward Body, adjacent two annular solid are built into integral structure, and the vertical beam of build support is spaced between the inner wall up and down of annular solid, right The internal face of annular solid carries out Anti-steam-leakage, leakproof water process, and the mine hole of production or life is formed after the completion of coal mining;Its In, Anti-steam-leakage is carried out to the internal face of annular solid, the concrete mode of leakproof water process is:Pass through injection or slip casting or surface plastic spraying Mode the internal face of annular solid is handled.
(4) back production:On predetermined absolute altitude described in step (2), ore body is divided into two ore beds and carries out back production respectively, is first adopted Ceng Houcai lower layers, the interlayer between two kinds of mining methods stope of upper and lower layer should ensure that the thickness of 5m, using rock drill rock drilling, The one third of ore is released in explosion, is left workbench of the ore as next back production rock drilling, is waited in exploitation process Upper layer mine balkstone avalanche and back production lower layer ore bed after stablizing, along ore body main body trend using shallow hole shrinkage method to ore body master Body caunches;
(5) desliming:One section of graded desliming, the sand setting of one section of classification are carried out to the ore pulp collected using hydrocyclone The agitator being sent into before flotation, the overflow of one section of classification are sent into dense bucket and carry out two sections of graded deslimings, and the sand setting of two sections of classifications is sent Enter the agitator, tail is lost in the overflow of two sections of classifications.
Embodiment 3
A kind of production practice for copper mine that the present embodiment is provided includes the following steps:
(1) minery is arranged:The outside in minery is provided with the ventilation equipment of fresh air conveying to minery;It is adopting Gas boring and surveying and warning device are provided in mining area;
(2) it prospects:Perpendicular to the exploration row of the direction arrangement interval certain distance of ore body principal length on predetermined absolute altitude Line tunnels prospecting drift, until puncturing entire ore body along exploration line;
(3) it digs up mine:It is dug up mine by the way of big cross section driving, while mining, vacant mining area will have been exploited Four walls are built into the annular solid in four faces up and down with reinforced concrete structure, and one section of annular is just constructed per exploiting one section forward Body, adjacent two annular solid are built into integral structure, and the vertical beam of build support is spaced between the inner wall up and down of annular solid, right The internal face of annular solid carries out Anti-steam-leakage, leakproof water process, and the mine hole of production or life is formed after the completion of coal mining;Its In, Anti-steam-leakage is carried out to the internal face of annular solid, the concrete mode of leakproof water process is:Pass through injection or slip casting or surface plastic spraying Mode the internal face of annular solid is handled.
(4) back production:On predetermined absolute altitude described in step (2), ore body is divided into two ore beds and carries out back production respectively, is first adopted Ceng Houcai lower layers, the interlayer between two kinds of mining methods stope of upper and lower layer should ensure that the thickness of 6m, using rock drill rock drilling, The one third of ore is released in explosion, is left workbench of the ore as next back production rock drilling, is waited in exploitation process Upper layer mine balkstone avalanche and back production lower layer ore bed after stablizing, along ore body main body trend using shallow hole shrinkage method to ore body master Body caunches;
(5) desliming:One section of graded desliming, the sand setting of one section of classification are carried out to the ore pulp collected using hydrocyclone The agitator being sent into before flotation, the overflow of one section of classification are sent into dense bucket and carry out two sections of graded deslimings, and the sand setting of two sections of classifications is sent Enter the agitator, tail is lost in the overflow of two sections of classifications.
Although above the present invention is described in detail with a general description of the specific embodiments, On the basis of the present invention, it can be made some modifications or improvements, this will be apparent to those skilled in the art.Cause This, these modifications or improvements, belong to the scope of protection of present invention without departing from theon the basis of the spirit of the present invention.

Claims (7)

1. a kind of production practice of copper mine, which is characterized in that include the following steps:
(1) it prospects:Perpendicular to the exploration line of the direction arrangement interval certain distance of ore body principal length, edge on predetermined absolute altitude It explores line and tunnels prospecting drift, until puncturing entire ore body;
(2) it digs up mine:Difference is upward at the both ends difference exploration line of ore body main body on predetermined absolute altitude first described in step (1) Western combined shaft and eastern combined shaft are tunneled, as the channel above and below ventilation and pedestrian and material;Then the side of big cross section driving is used Formula is dug up mine, and while mining, four walls for having exploited vacant mining area are built into up and down with reinforced concrete structure The annular solid in four faces just constructs one section of annular solid per exploiting one section forward, and adjacent two annular solid is built into integral structure, It is spaced the vertical beam of build support between the inner wall up and down of annular solid, Anti-steam-leakage is carried out, at preventing water leakage to the internal face of annular solid Reason, coal mining form the mine hole of production or life after the completion;
(3) back production:On predetermined absolute altitude described in step (1), ore body is divided into two ore beds and carries out back production respectively, along ore body master Body trend caunches to ore body main body using shallow hole shrinkage method;
(4) desliming:One section of graded desliming is carried out to the ore pulp collected using hydrocyclone, the sand setting of one section of classification is sent into Agitator before flotation, the overflow of one section of classification are sent into dense bucket and carry out two sections of graded deslimings, and the sand setting of two sections of classifications is sent into institute Agitator is stated, tail is lost in the overflow of two sections of classifications.
2. a kind of production practice of copper mine according to claim 1, which is characterized in that the back production in the step (3) is Back production is carried out respectively to two ore bed of ore body, first adopts upper layer Hou Cai lower layers, after after upper layer mine balkstone avalanche and stablizing under back production Layer ore bed.
3. a kind of production practice of copper mine according to claim 2, which is characterized in that two kinds of mining side of the upper and lower layer Interlayer between method stope should ensure that the thickness of 4-6m.
4. a kind of production practice of copper mine according to claim 1, which is characterized in that annular solid in the step (2) Internal face carry out Anti-steam-leakage, leakproof water process concrete mode be:To ring by way of injection or slip casting or surface plastic spraying The internal face of body is handled.
5. a kind of production practice of copper mine according to claim 1, which is characterized in that back production step in the step (3) Using rock drill rock drilling, explosion, the one third of ore is released, the work for being left the ore as next back production rock drilling is flat Platform.
6. a kind of production practice of copper mine according to claim 1, which is characterized in that the external setting in minery Have the ventilation equipment of fresh air conveying to minery.
7. a kind of production practice of copper mine according to claim 1, which is characterized in that described to be provided in minery watt This detection and warning device.
CN201810138215.8A 2018-02-10 2018-02-10 A kind of production practice of copper mine Pending CN108425673A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810138215.8A CN108425673A (en) 2018-02-10 2018-02-10 A kind of production practice of copper mine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810138215.8A CN108425673A (en) 2018-02-10 2018-02-10 A kind of production practice of copper mine

Publications (1)

Publication Number Publication Date
CN108425673A true CN108425673A (en) 2018-08-21

Family

ID=63156821

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810138215.8A Pending CN108425673A (en) 2018-02-10 2018-02-10 A kind of production practice of copper mine

Country Status (1)

Country Link
CN (1) CN108425673A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109630120A (en) * 2019-01-25 2019-04-16 中南大学 A kind of mining methods for the rich or poor co-layer ore body of low-angle dip
CN114251095A (en) * 2020-09-22 2022-03-29 麻阳华森矿业有限责任公司 Method for collecting natural copper ore of nonferrous metal

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100295359A1 (en) * 2009-05-20 2010-11-25 Mti Products Pty Ltd Collapsible Cushion
CN102434159A (en) * 2011-11-28 2012-05-02 浙江永昌仪表有限公司 Mining method for ore bed
CN102619514A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Top-filled pillarless cornice end-wall sublevel caving method extraction technique
CN104314567A (en) * 2014-09-25 2015-01-28 白银有色集团股份有限公司 Medium-thick ore body mining method
CN105041317A (en) * 2015-07-03 2015-11-11 中国瑞林工程技术有限公司 Medium-length hole shrinkage stoping method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100295359A1 (en) * 2009-05-20 2010-11-25 Mti Products Pty Ltd Collapsible Cushion
CN102434159A (en) * 2011-11-28 2012-05-02 浙江永昌仪表有限公司 Mining method for ore bed
CN102619514A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Top-filled pillarless cornice end-wall sublevel caving method extraction technique
CN104314567A (en) * 2014-09-25 2015-01-28 白银有色集团股份有限公司 Medium-thick ore body mining method
CN105041317A (en) * 2015-07-03 2015-11-11 中国瑞林工程技术有限公司 Medium-length hole shrinkage stoping method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
胡建国等: "补偿工艺在分级脱泥工艺流程中的应用", 《江西有色金属》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109630120A (en) * 2019-01-25 2019-04-16 中南大学 A kind of mining methods for the rich or poor co-layer ore body of low-angle dip
CN114251095A (en) * 2020-09-22 2022-03-29 麻阳华森矿业有限责任公司 Method for collecting natural copper ore of nonferrous metal

Similar Documents

Publication Publication Date Title
CN109083644B (en) A kind of safe and efficient mining methods of gently inclined medium thick orebody
CN100356037C (en) Remote pressure relief and gas drainage method for low permeability and high gas soft thick coal seam
CN106499396B (en) Medium-thickness slowly-inclined waste rock-containing interlayer ore body room-column mining method
CN106761754A (en) A kind of girdle comprehensive mining and gas control network one cooperative control system and method
CA2986062C (en) Fully mechanized mining-filling mixed mining working face filling section length determination method
CN107882565B (en) A kind of adopt without driving without coal column stays integrated production practice
CN101775974B (en) Coalbed methane mining method for hydraulic migration of butt joint wells for pressure relief
CN104033153A (en) Coal mine underground mining, dress and filling integral method
CN110714760B (en) A mining method for coal-aluminum symbiosis layered induced cooperative mining
CN101915100B (en) Loess-filling coal-mining method in a coal mine
CN106089205A (en) A kind of room-and-pillar method filling mining method being applicable to very thin ore body under water body
CN102086765A (en) High-sublevel multi-layer mining method of ultrathin copper ore body
CN108301866A (en) Mining of closed distance coal seam group adjacent layer gas pressure relief directional drilling stops pumping method
CN109403974A (en) A kind of mine, which picks up, unloads pumping and fills lasting exploit design method
CN106591606B (en) A kind of churning modular rare earth mining methods
CN114622953A (en) Coal mine gangue and CO2Mining overburden rock isolation grouting filling emission reduction method
CN108222940A (en) A kind of recovery method of manganese ore
CN103147759B (en) Prospecting and short-hole shrinkage mining method of small inclined ore body
CN108425673A (en) A kind of production practice of copper mine
CN104481538B (en) A treatment method for interlayers in steeply inclined multi-layer ore bodies in non-coal mines
Wang et al. Non-explosive mechanized and intelligent mining/heading in underground mine
CN104612692B (en) Mining method of segmental collapse and bottom structure followed by continuous filling
CN108331580B (en) Clean and efficient coal mining method
CN106246182A (en) Medium-length hole room column method for synchronously forming spaced ore columns
CN109026003A (en) A kind of auger Mars Miner continuous mining of Synergism inhibition soft rock ore body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180821

RJ01 Rejection of invention patent application after publication