[go: up one dir, main page]

CN108086784A - The construction method of steel construction indirect cool tower upper cylinder - Google Patents

The construction method of steel construction indirect cool tower upper cylinder Download PDF

Info

Publication number
CN108086784A
CN108086784A CN201711421646.7A CN201711421646A CN108086784A CN 108086784 A CN108086784 A CN 108086784A CN 201711421646 A CN201711421646 A CN 201711421646A CN 108086784 A CN108086784 A CN 108086784A
Authority
CN
China
Prior art keywords
tripod
construction
installation
crossbeam
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711421646.7A
Other languages
Chinese (zh)
Inventor
张云金
娄祥顺
李文蔚
罗胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Chemical Engineering Third Construction Co Ltd
Original Assignee
China National Chemical Engineering Third Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Chemical Engineering Third Construction Co Ltd filed Critical China National Chemical Engineering Third Construction Co Ltd
Priority to CN201711421646.7A priority Critical patent/CN108086784A/en
Publication of CN108086784A publication Critical patent/CN108086784A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A kind of construction method of steel construction indirect cool tower upper cylinder, including step:1) tripod surrounded by crossbeam and cant beam is made;2) installed respectively at crossbeam both ends and two cant beam intersections, lower locking plate, through hole is opened up on upper and lower jam plate;3) tripod of passed examination is transported in cone segments institute enclosure cavity body;4) tripod handstand lifting will be pre-installed to installation site using tower crane, it is ensured that its bottom lower locking plate aligns with having installed the upper lock plate on tripod crossbeam, and back of the body thick stick is interted in up and down jam plate through hole, and fills in chock;5) chock is hammered, flushes tripod outer surface;6) verticality for the line adjustment tripod that rises is utilized;7) tripod is fixed and welded using spot welding;8) step 4)~7 are repeated), circumference installs this layer remaining tripod;9) step 4)~8 are repeated), remaining number of plies tripod is installed.Construction efficiency of the present invention is high, and installation positioning is reliable, solves the technical issues of larger diameter cylinder is difficult to construct.

Description

The construction method of steel construction indirect cool tower upper cylinder
Technical field
The present invention relates to steel construction indirect cool tower construction fields, are especially a kind of applying for steel construction indirect cool tower upper cylinder Work method.
Background technology
Certain power plant creates the indirect cool tower of two steel construction types, it includes lower part cone segments, upper cylinder, reinforcing ring, Broadening platform, upper tower cat ladder, peripheral protective aluminium sheet etc..The high 169.01m of head tower, the base diameter of lower part cone segments is 129.44m, height Spend 55m, a diameter of 82m, the height 114.01m of upper cylinder.The indirect cool tower is by triangular mesh, reinforcing ring, broadening and outer It goes along with sb. to guard him aluminium sheet to assemble, entire tower body is steel construction, and separate unit tower body steel structure weighs about 4102.2 tons, separate unit peripheral protective aluminium sheet Weigh about 238 tons.Totally 5 layers of lower part centrum section, totally 13 layers of upper cylinder, every layer includes 36 groups of tripods, and single tripod is about 5.42 tons, wherein, have three layers reinforcing ring in Upper cylindrical body, about 166.45 tons of every layer of reinforcing ring, height respectively 90.08m, 125.16m and 160.24m.Entire tower body is sealed to form (about 42868 ㎡) by aluminium alloy contour plate.
Due to being relatively large in diameter for steel construction indirect cool tower upper cylinder, and height is high, and it is very big to install difficulty in place, without applying Work method may be referred to, therefore, it is necessary to a set of practicable construction method be designed, to meet indirect cool tower upper cylinder section Construction.
The content of the invention
The technical problem to be solved by the present invention is to, a kind of construction method of steel construction indirect cool tower upper cylinder is provided, Solve the technical issues of larger diameter cylinder is difficult to install.
The technical solution of the present invention is to provide a kind of construction method of steel construction indirect cool tower upper cylinder, including Following steps:
1) tripod is made, which is enclosed and made by a steel structure beam and two steel construction cant beams;
2) upper lock plate is installed at the both ends of crossbeam, lower locking plate, upper lock plate and lower locking plate is installed in the intersection of two cant beams On offer through hole;
3) quality examination is carried out to several tripods to complete, is carried it after qualified to lower part cone segments institute enclosure cavity In body;
4) tripod handstand lifting will be pre-installed to installation site using tower crane, it is ensured that the lower locking plate of its bottom is with having installed Upper lock plate on tripod crossbeam aligns, and a back of the body thick stick is interted in the through hole of up and down jam plate, and between back of the body thick stick and hole wall Fill in flat chock;
5) flat chock is hammered, adjusts the wrong variable between upper and lower tripod, flushes the two outer surface;
6) adjustment lifting angle, and using the verticality for the line adjustment pre-installation tripod that rises, pass through the vertical standard set up in advance Instrument detects its verticality, it is made to meet design specification requirement;
7) by tripod fixation and welded using spot welding mode;
8) step 4)~7 are repeated), by the circumference installation by drawing of remaining tripod of this layer;
9) step 4)~8 are repeated), the tripod in the remaining number of plies is installed, is finally completed applying for entire cylinder Work.
After more than structure, compared with prior art, the construction method of steel construction indirect cool tower upper cylinder of the present invention It has the following advantages:The present invention first constructs to single tripod, is then lifted to pre-installed position, then to right Intert back of the body thick stick in neat upper and lower jam plate through hole, carry out centering, welding to tripod by way of hammering flat chock, next Remaining tripod is installed one by one again, is finally completed the construction operation of entire upper cylinder;The present invention is this to Upper cylindrical The modularization installation of body, construction efficiency is higher, and it is reliable to install positioning.
Description of the drawings
Fig. 1 is side structure schematic view when intermediate cam frame of the present invention, jam plate, back of the body thick stick and flat chock are installed together.
Specific embodiment
The construction method of steel construction indirect cool tower upper cylinder of the present invention is made with reference to the accompanying drawings and detailed description It is further described:
As shown in Figure 1, in this embodiment, the construction method of steel construction indirect cool tower upper cylinder of the present invention, Include the following steps:
1) tripod is made, which is enclosed and made by a steel structure beam and two steel construction cant beams;
2) upper lock plate 12 is installed at the both ends of crossbeam, lower locking plate 15,12 He of upper lock plate is installed in the intersection of two cant beams Through hole is offered on lower locking plate 15;
3) quality examination is carried out to several tripods to complete, is carried it after qualified to lower part cone segments institute enclosure cavity In body;
4) tripod 10 will be pre-installed using tower crane and stand upside down lifting to installation site, it is ensured that the lower locking plate 15 of its bottom with Upper lock plate 12 on installation 11 crossbeam of tripod aligns, and a back of the body thick stick 14 is interted in the through hole of up and down jam plate, and in back of the body thick stick Flat chock 13 is filled between 14 and hole wall;
5) flat chock 13 is hammered, adjusts the wrong variable between upper and lower tripod, flushes the two outer surface;
6) adjustment lifting angle, and utilize the line that rises (line that rises is arranged on the both sides of pre-installation tripod 10) adjustment pre-installation The verticality of tripod 10 detects its verticality by the plumb aligner set up in advance, it is made to meet design specification requirement;
7) by tripod fixation and welded using spot welding mode;
8) step 4)~7 are repeated), by the circumference installation by drawing of remaining tripod of this layer;
9) step 4)~8 are repeated), the tripod in the remaining number of plies is installed, is finally completed applying for entire cylinder Work.
The present invention first constructs to single tripod, is then lifted to pre-installed position, then to alignment Intert back of the body thick stick in upper and lower jam plate through hole, carry out centering, welding to tripod by way of hammering flat chock, it is next right again Remaining tripod is installed one by one, is finally completed the construction operation of entire upper cylinder;The present invention is this to upper cylinder Modularization is installed, and construction efficiency is higher, and it is reliable to install positioning.
Embodiment described above is only that the preferred embodiment of the present invention is described, not to the model of the present invention It encloses and is defined, on the premise of design spirit of the present invention is not departed from, those of ordinary skill in the art are to the technical side of the present invention The various modifications and improvement that case is made, should all fall within the scope of protection of the present invention.

Claims (1)

1. a kind of construction method of steel construction indirect cool tower upper cylinder, which is characterized in that include the following steps:
1) tripod is made, which is enclosed and made by a steel structure beam and two steel construction cant beams;
2) in the both ends of crossbeam installation upper lock plate (12), lower locking plate (15), upper lock plate (12) are installed in the intersection of two cant beams Through hole is offered on lower locking plate (15);
3) quality examination is carried out to several tripods to complete, is carried it after qualified to lower part cone segments institute enclosure cavity body In;
4) tripod (10) will be pre-installed using tower crane and stand upside down lifting to installation site, it is ensured that the lower locking plate (15) of its bottom with Upper lock plate (12) on installation tripod (11) crossbeam aligns, and a back of the body thick stick (14) is interted in the through hole of up and down jam plate, and Flat chock (13) is filled between hole wall in back of the body thick stick (14);
5) flat chock (13) is hammered, adjusts the wrong variable between upper and lower tripod, flushes the two outer surface;
6) adjustment lifting angle, and using the verticality for the line adjustment pre-installation tripod (10) that rises, pass through the vertical standard set up in advance Instrument detects its verticality, it is made to meet design specification requirement;
7) by tripod fixation and welded using spot welding mode;
8) step 4)~7 are repeated), by the circumference installation by drawing of remaining tripod of this layer;
9) step 4)~8 are repeated), the tripod in the remaining number of plies is installed, is finally completed the construction of entire cylinder.
CN201711421646.7A 2017-12-25 2017-12-25 The construction method of steel construction indirect cool tower upper cylinder Pending CN108086784A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711421646.7A CN108086784A (en) 2017-12-25 2017-12-25 The construction method of steel construction indirect cool tower upper cylinder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711421646.7A CN108086784A (en) 2017-12-25 2017-12-25 The construction method of steel construction indirect cool tower upper cylinder

Publications (1)

Publication Number Publication Date
CN108086784A true CN108086784A (en) 2018-05-29

Family

ID=62177886

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711421646.7A Pending CN108086784A (en) 2017-12-25 2017-12-25 The construction method of steel construction indirect cool tower upper cylinder

Country Status (1)

Country Link
CN (1) CN108086784A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109488103A (en) * 2018-11-08 2019-03-19 中国化学工程第三建设有限公司 Large-scale full steel structure indirect cool tower hydraulic pressure lift construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001098794A (en) * 1999-09-30 2001-04-10 Kajima Corp Expansion method of operating radio tower
CN201794356U (en) * 2010-08-12 2011-04-13 中冶成工上海五冶建设有限公司 Overhead assembly positioner used for tower equipment

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001098794A (en) * 1999-09-30 2001-04-10 Kajima Corp Expansion method of operating radio tower
CN201794356U (en) * 2010-08-12 2011-04-13 中冶成工上海五冶建设有限公司 Overhead assembly positioner used for tower equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109488103A (en) * 2018-11-08 2019-03-19 中国化学工程第三建设有限公司 Large-scale full steel structure indirect cool tower hydraulic pressure lift construction method

Similar Documents

Publication Publication Date Title
CN105586833B (en) Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method
CN101691815B (en) Fast hoisting-aligning method for Large-sized steel frames, and steel frame base structure
CN102689736B (en) Special supporting device of cover head of nuclear island containment vessel made of steel and transportation method
EP2458094A1 (en) Installing method for anchor cage and installing method for industrial equipment
CN107327023A (en) A kind of steel structure module installs installation method
CN105926958B (en) A kind of installation method for the sill anchor combined support frame for being used for high-rise building steel construction shear wall and outline border suspension column
CN205295950U (en) High mound steel reinforcement cage of cast -in -place thin wall installation strength nature location skeleton body system
CN106948367B (en) Wind power foundation assembled by quadrangular jacket column jacket and construction method thereof
CN103510541B (en) In a kind of mast-up hole, the device of steel pipe column is installed in lifting
CN112343256B (en) Construction method for prefabricating concrete-filled steel tube superposed frame column under reverse construction condition
CN102496771B (en) Method and device for installing large-sized steel structural antenna
CN108086784A (en) The construction method of steel construction indirect cool tower upper cylinder
CN106593779A (en) Operating platform for tower, operating method thereof and wind generating set
CN202577338U (en) Tower crane pedestal and steel cushion cap connecting device
CN111441254A (en) On-site pre-assembled jig frame for steel box girder bridge and installation method thereof
CN206637189U (en) A kind of large-scale tower crane foundation pre-embedded bolt fixing device
CN101949215A (en) Mounting construction method of steel structure support seat
CN108049634A (en) The construction method of steel construction indirect cool tower cone segments
CN107267165B (en) A kind of dry coke quenching furnace body is circular layout pre-embedded bolt fixed structure and installation method
CN212771968U (en) Full-prefabricated assembled bridge bearing platform positioning system
CN107938841A (en) A kind of positioning adjusting of steel column pairing and method of temporarily fixing
CN107881914B (en) Wire-dividing tube type cable saddle back field assembly type positioning device and assembly method
CN110886332A (en) Wall foundation underpinning device and construction method thereof
CN206667213U (en) A kind of embedded parts structure of ship lift main equipment room steel lattice column
CN102128015B (en) Ash sledge assembling process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 230000 East Fozhang Road and North Tingyun Road Office Building, Hefei Economic and Technological Development Zone, Anhui Province

Applicant after: China National Chemical Engineering Third Construction Co., Ltd.

Address before: 232038 No. 98 Dongshan Road, Tianjiaan District, Huainan City, Anhui Province

Applicant before: China National Chemical Engineering Third Construction Co., Ltd.

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication

Application publication date: 20180529

RJ01 Rejection of invention patent application after publication