CN108086784A - The construction method of steel construction indirect cool tower upper cylinder - Google Patents
The construction method of steel construction indirect cool tower upper cylinder Download PDFInfo
- Publication number
- CN108086784A CN108086784A CN201711421646.7A CN201711421646A CN108086784A CN 108086784 A CN108086784 A CN 108086784A CN 201711421646 A CN201711421646 A CN 201711421646A CN 108086784 A CN108086784 A CN 108086784A
- Authority
- CN
- China
- Prior art keywords
- tripod
- construction
- installation
- crossbeam
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 35
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 21
- 239000010959 steel Substances 0.000 title claims abstract description 21
- 238000009434 installation Methods 0.000 claims abstract description 16
- 238000003466 welding Methods 0.000 claims abstract description 6
- 230000003014 reinforcing effect Effects 0.000 description 4
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 3
- 229910052782 aluminium Inorganic materials 0.000 description 3
- 239000004411 aluminium Substances 0.000 description 3
- 238000000034 method Methods 0.000 description 2
- 230000002093 peripheral effect Effects 0.000 description 2
- 230000001681 protective effect Effects 0.000 description 2
- 229910000838 Al alloy Inorganic materials 0.000 description 1
- 241000282326 Felis catus Species 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A kind of construction method of steel construction indirect cool tower upper cylinder, including step:1) tripod surrounded by crossbeam and cant beam is made;2) installed respectively at crossbeam both ends and two cant beam intersections, lower locking plate, through hole is opened up on upper and lower jam plate;3) tripod of passed examination is transported in cone segments institute enclosure cavity body;4) tripod handstand lifting will be pre-installed to installation site using tower crane, it is ensured that its bottom lower locking plate aligns with having installed the upper lock plate on tripod crossbeam, and back of the body thick stick is interted in up and down jam plate through hole, and fills in chock;5) chock is hammered, flushes tripod outer surface;6) verticality for the line adjustment tripod that rises is utilized;7) tripod is fixed and welded using spot welding;8) step 4)~7 are repeated), circumference installs this layer remaining tripod;9) step 4)~8 are repeated), remaining number of plies tripod is installed.Construction efficiency of the present invention is high, and installation positioning is reliable, solves the technical issues of larger diameter cylinder is difficult to construct.
Description
Technical field
The present invention relates to steel construction indirect cool tower construction fields, are especially a kind of applying for steel construction indirect cool tower upper cylinder
Work method.
Background technology
Certain power plant creates the indirect cool tower of two steel construction types, it includes lower part cone segments, upper cylinder, reinforcing ring,
Broadening platform, upper tower cat ladder, peripheral protective aluminium sheet etc..The high 169.01m of head tower, the base diameter of lower part cone segments is 129.44m, height
Spend 55m, a diameter of 82m, the height 114.01m of upper cylinder.The indirect cool tower is by triangular mesh, reinforcing ring, broadening and outer
It goes along with sb. to guard him aluminium sheet to assemble, entire tower body is steel construction, and separate unit tower body steel structure weighs about 4102.2 tons, separate unit peripheral protective aluminium sheet
Weigh about 238 tons.Totally 5 layers of lower part centrum section, totally 13 layers of upper cylinder, every layer includes 36 groups of tripods, and single tripod is about
5.42 tons, wherein, have three layers reinforcing ring in Upper cylindrical body, about 166.45 tons of every layer of reinforcing ring, height respectively 90.08m,
125.16m and 160.24m.Entire tower body is sealed to form (about 42868 ㎡) by aluminium alloy contour plate.
Due to being relatively large in diameter for steel construction indirect cool tower upper cylinder, and height is high, and it is very big to install difficulty in place, without applying
Work method may be referred to, therefore, it is necessary to a set of practicable construction method be designed, to meet indirect cool tower upper cylinder section
Construction.
The content of the invention
The technical problem to be solved by the present invention is to, a kind of construction method of steel construction indirect cool tower upper cylinder is provided,
Solve the technical issues of larger diameter cylinder is difficult to install.
The technical solution of the present invention is to provide a kind of construction method of steel construction indirect cool tower upper cylinder, including
Following steps:
1) tripod is made, which is enclosed and made by a steel structure beam and two steel construction cant beams;
2) upper lock plate is installed at the both ends of crossbeam, lower locking plate, upper lock plate and lower locking plate is installed in the intersection of two cant beams
On offer through hole;
3) quality examination is carried out to several tripods to complete, is carried it after qualified to lower part cone segments institute enclosure cavity
In body;
4) tripod handstand lifting will be pre-installed to installation site using tower crane, it is ensured that the lower locking plate of its bottom is with having installed
Upper lock plate on tripod crossbeam aligns, and a back of the body thick stick is interted in the through hole of up and down jam plate, and between back of the body thick stick and hole wall
Fill in flat chock;
5) flat chock is hammered, adjusts the wrong variable between upper and lower tripod, flushes the two outer surface;
6) adjustment lifting angle, and using the verticality for the line adjustment pre-installation tripod that rises, pass through the vertical standard set up in advance
Instrument detects its verticality, it is made to meet design specification requirement;
7) by tripod fixation and welded using spot welding mode;
8) step 4)~7 are repeated), by the circumference installation by drawing of remaining tripod of this layer;
9) step 4)~8 are repeated), the tripod in the remaining number of plies is installed, is finally completed applying for entire cylinder
Work.
After more than structure, compared with prior art, the construction method of steel construction indirect cool tower upper cylinder of the present invention
It has the following advantages:The present invention first constructs to single tripod, is then lifted to pre-installed position, then to right
Intert back of the body thick stick in neat upper and lower jam plate through hole, carry out centering, welding to tripod by way of hammering flat chock, next
Remaining tripod is installed one by one again, is finally completed the construction operation of entire upper cylinder;The present invention is this to Upper cylindrical
The modularization installation of body, construction efficiency is higher, and it is reliable to install positioning.
Description of the drawings
Fig. 1 is side structure schematic view when intermediate cam frame of the present invention, jam plate, back of the body thick stick and flat chock are installed together.
Specific embodiment
The construction method of steel construction indirect cool tower upper cylinder of the present invention is made with reference to the accompanying drawings and detailed description
It is further described:
As shown in Figure 1, in this embodiment, the construction method of steel construction indirect cool tower upper cylinder of the present invention,
Include the following steps:
1) tripod is made, which is enclosed and made by a steel structure beam and two steel construction cant beams;
2) upper lock plate 12 is installed at the both ends of crossbeam, lower locking plate 15,12 He of upper lock plate is installed in the intersection of two cant beams
Through hole is offered on lower locking plate 15;
3) quality examination is carried out to several tripods to complete, is carried it after qualified to lower part cone segments institute enclosure cavity
In body;
4) tripod 10 will be pre-installed using tower crane and stand upside down lifting to installation site, it is ensured that the lower locking plate 15 of its bottom with
Upper lock plate 12 on installation 11 crossbeam of tripod aligns, and a back of the body thick stick 14 is interted in the through hole of up and down jam plate, and in back of the body thick stick
Flat chock 13 is filled between 14 and hole wall;
5) flat chock 13 is hammered, adjusts the wrong variable between upper and lower tripod, flushes the two outer surface;
6) adjustment lifting angle, and utilize the line that rises (line that rises is arranged on the both sides of pre-installation tripod 10) adjustment pre-installation
The verticality of tripod 10 detects its verticality by the plumb aligner set up in advance, it is made to meet design specification requirement;
7) by tripod fixation and welded using spot welding mode;
8) step 4)~7 are repeated), by the circumference installation by drawing of remaining tripod of this layer;
9) step 4)~8 are repeated), the tripod in the remaining number of plies is installed, is finally completed applying for entire cylinder
Work.
The present invention first constructs to single tripod, is then lifted to pre-installed position, then to alignment
Intert back of the body thick stick in upper and lower jam plate through hole, carry out centering, welding to tripod by way of hammering flat chock, it is next right again
Remaining tripod is installed one by one, is finally completed the construction operation of entire upper cylinder;The present invention is this to upper cylinder
Modularization is installed, and construction efficiency is higher, and it is reliable to install positioning.
Embodiment described above is only that the preferred embodiment of the present invention is described, not to the model of the present invention
It encloses and is defined, on the premise of design spirit of the present invention is not departed from, those of ordinary skill in the art are to the technical side of the present invention
The various modifications and improvement that case is made, should all fall within the scope of protection of the present invention.
Claims (1)
1. a kind of construction method of steel construction indirect cool tower upper cylinder, which is characterized in that include the following steps:
1) tripod is made, which is enclosed and made by a steel structure beam and two steel construction cant beams;
2) in the both ends of crossbeam installation upper lock plate (12), lower locking plate (15), upper lock plate (12) are installed in the intersection of two cant beams
Through hole is offered on lower locking plate (15);
3) quality examination is carried out to several tripods to complete, is carried it after qualified to lower part cone segments institute enclosure cavity body
In;
4) tripod (10) will be pre-installed using tower crane and stand upside down lifting to installation site, it is ensured that the lower locking plate (15) of its bottom with
Upper lock plate (12) on installation tripod (11) crossbeam aligns, and a back of the body thick stick (14) is interted in the through hole of up and down jam plate, and
Flat chock (13) is filled between hole wall in back of the body thick stick (14);
5) flat chock (13) is hammered, adjusts the wrong variable between upper and lower tripod, flushes the two outer surface;
6) adjustment lifting angle, and using the verticality for the line adjustment pre-installation tripod (10) that rises, pass through the vertical standard set up in advance
Instrument detects its verticality, it is made to meet design specification requirement;
7) by tripod fixation and welded using spot welding mode;
8) step 4)~7 are repeated), by the circumference installation by drawing of remaining tripod of this layer;
9) step 4)~8 are repeated), the tripod in the remaining number of plies is installed, is finally completed the construction of entire cylinder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711421646.7A CN108086784A (en) | 2017-12-25 | 2017-12-25 | The construction method of steel construction indirect cool tower upper cylinder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711421646.7A CN108086784A (en) | 2017-12-25 | 2017-12-25 | The construction method of steel construction indirect cool tower upper cylinder |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108086784A true CN108086784A (en) | 2018-05-29 |
Family
ID=62177886
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711421646.7A Pending CN108086784A (en) | 2017-12-25 | 2017-12-25 | The construction method of steel construction indirect cool tower upper cylinder |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108086784A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109488103A (en) * | 2018-11-08 | 2019-03-19 | 中国化学工程第三建设有限公司 | Large-scale full steel structure indirect cool tower hydraulic pressure lift construction method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001098794A (en) * | 1999-09-30 | 2001-04-10 | Kajima Corp | Expansion method of operating radio tower |
CN201794356U (en) * | 2010-08-12 | 2011-04-13 | 中冶成工上海五冶建设有限公司 | Overhead assembly positioner used for tower equipment |
-
2017
- 2017-12-25 CN CN201711421646.7A patent/CN108086784A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001098794A (en) * | 1999-09-30 | 2001-04-10 | Kajima Corp | Expansion method of operating radio tower |
CN201794356U (en) * | 2010-08-12 | 2011-04-13 | 中冶成工上海五冶建设有限公司 | Overhead assembly positioner used for tower equipment |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109488103A (en) * | 2018-11-08 | 2019-03-19 | 中国化学工程第三建设有限公司 | Large-scale full steel structure indirect cool tower hydraulic pressure lift construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105586833B (en) | Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method | |
CN101691815B (en) | Fast hoisting-aligning method for Large-sized steel frames, and steel frame base structure | |
CN102689736B (en) | Special supporting device of cover head of nuclear island containment vessel made of steel and transportation method | |
EP2458094A1 (en) | Installing method for anchor cage and installing method for industrial equipment | |
CN107327023A (en) | A kind of steel structure module installs installation method | |
CN105926958B (en) | A kind of installation method for the sill anchor combined support frame for being used for high-rise building steel construction shear wall and outline border suspension column | |
CN205295950U (en) | High mound steel reinforcement cage of cast -in -place thin wall installation strength nature location skeleton body system | |
CN106948367B (en) | Wind power foundation assembled by quadrangular jacket column jacket and construction method thereof | |
CN103510541B (en) | In a kind of mast-up hole, the device of steel pipe column is installed in lifting | |
CN112343256B (en) | Construction method for prefabricating concrete-filled steel tube superposed frame column under reverse construction condition | |
CN102496771B (en) | Method and device for installing large-sized steel structural antenna | |
CN108086784A (en) | The construction method of steel construction indirect cool tower upper cylinder | |
CN106593779A (en) | Operating platform for tower, operating method thereof and wind generating set | |
CN202577338U (en) | Tower crane pedestal and steel cushion cap connecting device | |
CN111441254A (en) | On-site pre-assembled jig frame for steel box girder bridge and installation method thereof | |
CN206637189U (en) | A kind of large-scale tower crane foundation pre-embedded bolt fixing device | |
CN101949215A (en) | Mounting construction method of steel structure support seat | |
CN108049634A (en) | The construction method of steel construction indirect cool tower cone segments | |
CN107267165B (en) | A kind of dry coke quenching furnace body is circular layout pre-embedded bolt fixed structure and installation method | |
CN212771968U (en) | Full-prefabricated assembled bridge bearing platform positioning system | |
CN107938841A (en) | A kind of positioning adjusting of steel column pairing and method of temporarily fixing | |
CN107881914B (en) | Wire-dividing tube type cable saddle back field assembly type positioning device and assembly method | |
CN110886332A (en) | Wall foundation underpinning device and construction method thereof | |
CN206667213U (en) | A kind of embedded parts structure of ship lift main equipment room steel lattice column | |
CN102128015B (en) | Ash sledge assembling process |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 230000 East Fozhang Road and North Tingyun Road Office Building, Hefei Economic and Technological Development Zone, Anhui Province Applicant after: China National Chemical Engineering Third Construction Co., Ltd. Address before: 232038 No. 98 Dongshan Road, Tianjiaan District, Huainan City, Anhui Province Applicant before: China National Chemical Engineering Third Construction Co., Ltd. |
|
CB02 | Change of applicant information | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180529 |
|
RJ01 | Rejection of invention patent application after publication |