CN108060932B - A kind of tunnel waterstop fixed setting method - Google Patents
A kind of tunnel waterstop fixed setting method Download PDFInfo
- Publication number
- CN108060932B CN108060932B CN201711315956.0A CN201711315956A CN108060932B CN 108060932 B CN108060932 B CN 108060932B CN 201711315956 A CN201711315956 A CN 201711315956A CN 108060932 B CN108060932 B CN 108060932B
- Authority
- CN
- China
- Prior art keywords
- threaded hole
- water stop
- buried water
- screw
- fixed setting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 44
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 54
- 239000010959 steel Substances 0.000 claims abstract description 54
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 48
- 238000004873 anchoring Methods 0.000 claims abstract description 14
- 238000012545 processing Methods 0.000 claims abstract description 10
- 238000004080 punching Methods 0.000 claims abstract description 4
- 238000003780 insertion Methods 0.000 claims abstract description 3
- 230000037431 insertion Effects 0.000 claims abstract description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 30
- 238000003825 pressing Methods 0.000 claims description 14
- 210000003205 muscle Anatomy 0.000 claims description 11
- 238000003466 welding Methods 0.000 claims description 6
- 238000007789 sealing Methods 0.000 claims description 4
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical group [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 3
- 238000000926 separation method Methods 0.000 claims description 3
- 239000000463 material Substances 0.000 abstract description 5
- 230000008569 process Effects 0.000 description 11
- 238000010276 construction Methods 0.000 description 10
- 238000005553 drilling Methods 0.000 description 5
- 238000009434 installation Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 238000013461 design Methods 0.000 description 2
- 208000015181 infectious disease Diseases 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000012512 characterization method Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
- E21D11/381—Setting apparatus or devices
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The present invention provides a kind of tunnel waterstop fixed setting methods, belong to Tunnel Engineering field, this tunnel waterstop fixed setting method, comprising the following steps: drill on the preliminary bracing abutment wall of inverted arch end, the insertion anchoring steel pipe in hole, punching inclination angle keep horizontal;In the upper circulation being arranged in middle buried water stop and inverted arch end after the processing of buried water stop overlap joint, fixed in lap-joint using the first fixture;Separate type template is set far from the adjacent one end of inverted arch end in middle buried water stop;Support frame is fixedly mounted close to one end of preliminary bracing abutment wall, support frame is close to separate type template, it is ensured that support frame is far from buried water stop in one end abutting of preliminary bracing abutment wall;The end point that middle buried water stop stretches out separate type template is installed by the second fixture;By pulling chain block to make the second fixture close to anchoring steel pipe.The tunnel waterstop fixed setting method provided through the invention can save consumptive material, reduce the accidents such as waterstop breakage.
Description
Technical field
The present invention relates to Tunnel Engineering fields, in particular to a kind of tunnel waterstop fixed setting method.
Background technique
Middle buried water stop is the important component of tunnel waterproofing construction, is mainly used for tunnel inverted arch and two lining construction joints
Waterproof measure, when construction must assure that buried water strip position is in the center position of lining thickness, and Transducers Embedded in Concrete portion
Divide the half just for sealing bandwidth, waterstop cannot damage, and line style wants straight.Buried water stop is constructed in tunnel side wall
Method is many in the process, but its main method predominantly uses the fixed waterstop of reinforcing bar card.
Routine is in such a way that self-control reinforcing bar card is fixed, since reinforcing bar is stuck in processing, fixture is welded in fixation procedure and deforms
Larger, the position fixed is the reinforcing bar that binding is completed, and in concreting process, reinforcing bar can be displaced and deviation,
And it is big to continue adjustment difficulty after fixed, often results in that waterstop is damaged during the installation process, it is not straight etc. to apply post-construction deformation
Problem.
Common process is fixed using the every 50cm~100cm setting reinforcing bar card of spacing, every circulation inverted arch (pressing 9m drilling depth)
Two sides abutment wall at least needs to process and weld 20 Reinforcing bar clamps of installation, and not recoverable, material loss are big.
The Reinforcing bar clamp that common process needs processing quantity very big, while needing to be arranged again after welding each fixture
Waterstop, time-consuming, and every circulation inverted arch (by 9m drilling depth) waterstop installation at least needs 4 people while carrying out cooperation to construct,
Reinforcing bar clamp processing, installation and waterstop fixation take a long time.
Summary of the invention
The present invention provides a kind of tunnel waterstop fixed setting methods, it is intended to it is solid to solve tunnel waterstop in the prior art
Determine the above problem existing for installation method.
The present invention is implemented as follows:
A kind of tunnel waterstop fixed setting method, comprising the following steps:
On the preliminary bracing abutment wall of inverted arch end, drills at the inverted arch end 1.5-2m, anchor is inserted into hole
Gu steel pipe, punching inclination angle keeps horizontal;
Be provided with buried water stop in circulation in the inverted arch end, middle buried water stop with it is buried in the upper circulation
After the processing of waterstop overlap joint, fixed in lap-joint using the first fixture;
Separate type template is set far from the adjacent one end of the inverted arch end in the middle buried water stop;
Support frame is fixedly mounted close to one end of the preliminary bracing abutment wall, support frame as described above is close to the separate type mould
Plate, it is ensured that support frame as described above abuts the middle buried water stop far from one end of the preliminary bracing abutment wall;
The end point that the middle buried water stop stretches out the separate type template is installed by the second fixture;
Using iron chains by one end of second fixture and chain block connect, the other end of the chain block with it is described
Anchor steel pipe connection;
Chain block described in tensioning is tightened the middle buried water stop, is tightly attached on support frame as described above.
In an embodiment of the present invention, the step of tightening the middle buried water stop by the chain block it
Afterwards, also there is step: being reinforced at the middle part of the middle buried water stop length using structure reinforcing bars electric welding temporary support reinforcing bar card
It is fixed.
In an embodiment of the present invention, according to one-time-concreting inverted arch length, respectively it is whole it is described in buried sealing
Reinforce fixing using structure reinforcing bars electric welding temporary support reinforcing bar card at the 1/3 of strip length and 2/3.
In an embodiment of the present invention, the anchoring steel pipe uses diameter for the seamless steel pipe of 42mm.
In an embodiment of the present invention, it is exposed described first after the anchoring steel pipe is inserted into the preliminary bracing abutment wall
The part tendency face angular separation of phase supporting abutment wall is kept for 80 ° or less.
In an embodiment of the present invention, the hole depth to drill at the inverted arch end 1.5-2m is more than or equal to
30cm。
In an embodiment of the present invention, the middle buried water stop stretch out the separate type template end portion it is small
In equal to 1m.
In an embodiment of the present invention, first fixture include two the first bolts and be parallel to each other
One screw-thread steel and the second screw-thread steel, the both ends of first screw-thread steel are respectively arranged with the first threaded hole and the second threaded hole, institute
The both ends for stating the second screw-thread steel are respectively arranged with third threaded hole and the 4th threaded hole, first threaded hole and the third spiral shell
Pit is coaxial, and second threaded hole and the 4th threaded hole are coaxial, first described in first screw bolt passes
Threaded hole and the third threaded hole, the second threaded hole and the 4th screw thread described in another first screw bolt passes
Hole.
In an embodiment of the present invention, second fixture include two the second bolts and be parallel to each other
The both ends of three screw-thread steels and the 4th screw-thread steel, the third screw-thread steel are respectively arranged with the 5th threaded hole and the 6th threaded hole, institute
The both ends for stating the 4th screw-thread steel are respectively arranged with the 7th threaded hole and the 8th threaded hole, the 5th threaded hole and the 7th spiral shell
Pit is coaxial, and the 6th threaded hole and the 8th threaded hole are coaxial, the 5th described in second screw bolt passes
Threaded hole and the 7th threaded hole, the 6th threaded hole and the 8th screw thread described in another second screw bolt passes
Hole.
In an embodiment of the present invention, support frame as described above is triangular prism, including pressing lever and two foundation muscle, pressing lever and two
Foundation muscle is fixedly connected, and the pressing lever is for abutting the middle buried water stop.
The beneficial effects of the present invention are: the tunnel waterstop fixed setting method provided through the invention, has following excellent
Gesture:
1. it is reusable after simple to install, time processing, avoid material loss.
2. project amount is few, process is simple, construction efficiency is high.
3. construction personnel needed for is reduced, the convenient disassemblies such as equipment, fixture.
4. integral tension can be provided in such a way that the second fixture connects chain block, it is ensured that waterstop design position, mistake
It is small by construction infection error in journey.
5. the offset for effectively controlling the impact generated in concreting process and causing waterstop.
Detailed description of the invention
It, below will be to use required in embodiment in order to illustrate more clearly of the technical solution of embodiment of the present invention
Attached drawing be briefly described, it should be understood that the following drawings illustrates only certain embodiments of the present invention, therefore is not to be seen as
It is the restriction to range, it for those of ordinary skill in the art, without creative efforts, can be with root
Other relevant attached drawings are obtained according to these attached drawings.
Fig. 1 is integrally-built first view after waterstop fixed setting method in tunnel provided in an embodiment of the present invention is implemented
The structural schematic diagram at angle;
Fig. 2 is integrally-built second view after waterstop fixed setting method in tunnel provided in an embodiment of the present invention is implemented
The structural schematic diagram at angle;
Fig. 3 is the structural schematic diagram of the first fixture provided in an embodiment of the present invention;
Fig. 4 is the structural schematic diagram of support frame provided in an embodiment of the present invention.
Icon: 100- inverted arch end;200- preliminary bracing abutment wall;The hole 201-;300- anchors steel pipe;It is buried in circulation on 110-
Formula waterstop;Buried water stop in 400-;The first fixture of 510-;600- separate type template;700- support frame;530- second is pressed from both sides
Tool;800- chain block;900- temporary support reinforcing bar card;010- inverted arch circumferential direction structure reinforcing bars;The first bolt of 511-;513- first
Screw-thread steel;The second screw-thread steel of 515-;517- nut;710- pressing lever;The bottom 730- muscle.
Specific embodiment
To keep the purposes, technical schemes and advantages of embodiment of the present invention clearer, implement below in conjunction with the present invention
The technical solution in embodiment of the present invention is clearly and completely described in attached drawing in mode, it is clear that described reality
The mode of applying is some embodiments of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ability
Domain those of ordinary skill every other embodiment obtained without creative efforts, belongs to the present invention
The range of protection.Therefore, the detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit below and is wanted
The scope of the present invention of protection is sought, but is merely representative of selected embodiment of the invention.Based on the embodiment in the present invention,
Every other embodiment obtained by those of ordinary skill in the art without making creative efforts belongs to this
Invent the range of protection.
In the description of the present invention, it is to be understood that, indicating position or the term of positional relationship are based on shown in attached drawing
Orientation or positional relationship, be merely for convenience of description of the present invention and simplification of the description, rather than the equipment of indication or suggestion meaning
Or element must have a particular orientation, be constructed and operated in a specific orientation, therefore be not considered as limiting the invention.
In the present invention unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " fixation " etc.
Term shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be mechanical connect
It connects, is also possible to be electrically connected;It can be directly connected, can also can be in two elements indirectly connected through an intermediary
The interaction relationship of the connection in portion or two elements.It for the ordinary skill in the art, can be according to specific feelings
Condition understands the concrete meaning of above-mentioned term in the present invention.
In the present invention unless specifically defined or limited otherwise, fisrt feature can be on or below second feature
Directly contacted including the first and second features, also may include the first and second features be not direct contact but by them it
Between other characterisation contact.Moreover, fisrt feature is on second feature, top and above include fisrt feature second spy
Right above sign and oblique upper, or first feature horizontal height is merely representative of higher than second feature.Fisrt feature second feature it
Under, lower section and fisrt feature included below be directly below and diagonally below the second feature, or be merely representative of first feature horizontal height
Less than second feature.
Embodiment one
Fig. 1 and Fig. 2 are please referred to, the present invention provides a kind of tunnel waterstop fixed setting method, this tunnel waterstop
Fixed setting method, comprising the following steps:
On the preliminary bracing abutment wall 200 of inverted arch end 100, the drilling 201 at the 1001.5m of inverted arch end, in hole 201
Interior insertion anchors steel pipe 300, and 201 inclination angles of punching keep horizontal;
It is provided with buried water stop 110 in circulation in inverted arch end 100, is buried in middle buried water stop 400 and upper circulation
It is fixed using the first fixture 510 in lap-joint after the processing of 110 overlap joint of formula waterstop;After the first fixture 510 is fixed, also need
Carry out desk checking, it is ensured that buried water stop 400 in the firm clamping of the first fixture 510.
Separate type template 600 is set far from the adjacent one end of inverted arch end 100 in middle buried water stop 400;
Support frame 700 is fixedly mounted close to one end of preliminary bracing abutment wall 200, support frame 700 is close to separate type template
600, it is ensured that support frame 700 is far from buried water stop 400 in one end abutting of preliminary bracing abutment wall 200;
The end point that middle buried water stop 400 stretches out separate type template 600 is installed by the second fixture 530;
The second fixture 530 is connect with one end of chain block 800 using iron chains, the other end and anchor of chain block 800
Gu steel pipe 300 connects;
Tensioning chain block 800 is tightened middle buried water stop 400, is tightly attached on support frame 700.With and bury in ensuring
Formula waterstop 400 is straight not to relax.
In the present embodiment, after tensioning chain block 800, structure is utilized at the middle part of middle 400 length of buried water stop
Reinforcing bar is welded temporary support reinforcing bar card 900 and reinforces fixing, and prevents buried water strip interlude from falling heavy.Temporary support reinforcing bar card
900 are fixedly connected with the inverted arch circumferential direction structure reinforcing bars 010 in inverted arch nascent structure, i.e., right by inverted arch circumferential direction structure reinforcing bars 010
Temporary support reinforcing bar card 900 positions, and 900 centering buried water stop 400 of temporary support reinforcing bar card positions.
Specifically, according to one-time-concreting inverted arch length, respectively at the 1/3 and 2/3 of whole middle 400 length of buried water stop
Reinforce fixing using structure reinforcing bars electric welding temporary support reinforcing bar card 900.On the basis of buried water stop 400 is firm in guarantee,
It reduces process to the greatest extent, saves material.
In the present embodiment, anchoring steel pipe 300 uses the seamless steel pipe that diameter is 42mm to guarantee to anchor the strong of steel pipe 300
Degree, meanwhile, the diameter of steel pipe can properly reduce the difficulty of processing of drilling 201.
Specifically, the part of exposed preliminary bracing abutment wall 200 is inclined to after anchoring steel pipe 300 is inserted into preliminary bracing abutment wall 200
80 ° of face angular separation holding is hereinafter, can be by anchor by the angle for reducing anchoring steel pipe 300 and preliminary bracing abutment wall 200
Gu the stress of steel pipe 300 is largely converted into the radial force of anchoring steel pipe 300, and anchoring steel pipe 300 is avoided to rotate displacement.
Specifically, the hole 201 of drilling 201 is deep at the 1001.5-2m of inverted arch end is more than or equal to 30cm, it is further ensured that anchoring
The stability of steel pipe 300.
In the present embodiment, the end portion that middle buried water stop 400 stretches out separate type template 600 is less than or equal to 1m.In
There is buried water stop 400 enough length to be just easy to the clamping of the second fixture 530 and the stretching of chain block 800.
Specifically, referring to Fig. 3, the first fixture 510 includes two the first bolts 511 and the first spiral shell being parallel to each other
Line steel 513 and the second screw-thread steel 515, the both ends of the first screw-thread steel 513 are respectively arranged with the first threaded hole and the second threaded hole, the
The both ends of two screw-thread steels 515 are respectively arranged with third threaded hole and the 4th threaded hole, and the first threaded hole and third threaded hole are coaxial,
Second threaded hole and the 4th threaded hole are coaxial, and first bolt 511 sequentially passes through the first threaded hole and third threaded hole, another
The first bolt 511 sequentially passes through the second threaded hole and the 4th threaded hole.
Wherein the first threaded hole, the second threaded hole, third threaded hole and the 4th threaded hole, by welding spiral shell on screw-thread steel
Mother 517 realizes that before welded nut 517, place corresponding with the threaded hole of nut 517 should drill on screw-thread steel
201。
In the present embodiment, the second fixture 530 is identical as the structure of the first fixture 510, i.e. the second fixture 530 includes two
Second bolt and the third screw-thread steel and the 4th screw-thread steel being parallel to each other, the both ends of third screw-thread steel are respectively arranged with the 5th
Threaded hole and the 6th threaded hole, the both ends of the 4th screw-thread steel are respectively arranged with the 7th threaded hole and the 8th threaded hole, the 5th screw thread
Seven threaded hole of Kong Yu is coaxial, and the 6th threaded hole and the 8th threaded hole are coaxial, the 5th threaded hole of the second screw bolt passes
With the 7th threaded hole, another the 6th threaded hole of the second screw bolt passes and the 8th threaded hole.In other examples,
The fixture of different structure can be used.
First fixture 510 is to be detachably connected with the second fixture 530, can save next utilization after removal.
In the present embodiment, support frame 700 is triangular prism, including pressing lever 710 and two foundation muscle 730, pressing lever 710 and two
Bottom muscle 730 is fixedly connected, and pressing lever 710 is for buried water stop 400 in abutting.The wherein steel that pressing lever 710 is 42mm using diameter
Pipe, the reinforcing bar that bottom muscle 730 is 25mm using diameter.It is fixedly connected between pressing lever 710 and bottom muscle 730 using reinforcing bar.Please refer to figure
4, pressing lever 710 is with a wherein foundation muscle 730 altogether in the first face, and for two foundation muscle 730 altogether in the second face, the first face and the second face are in x
Angle, x angle are 90 °.In actual implementation tunnel when waterstop fixed setting method, separate type template 600 is close in the first face.
Support frame 700 is supported using the stability centering buried water stop 400 of triangle, and support frame 700 is using
When be also detachably connected with separate type template 600 without being completely fixed, therefore it is also detachable after to use next time.
The tunnel waterstop fixed setting method provided through the invention:
1. it is reusable after simple to install, time processing, avoid material loss.
2. project amount is few, process is simple, construction efficiency is high.
3. construction personnel needed for is reduced, the convenient disassemblies such as equipment, fixture.
4. integral tension can be provided in such a way that the second fixture 530 connects chain block 800, it is ensured that waterstop designs position
It sets, it is small by construction infection error in the process.
5. the offset for effectively controlling the impact generated in concreting process and causing waterstop.
Embodiment two
A kind of tunnel waterstop fixed setting method is present embodiments provided, Fig. 1 and Fig. 2, this tunnel sealing are please referred to
Difference with fixed setting method and the tunnel waterstop fixed setting method in embodiment one is only that, in inverted arch end 100
Preliminary bracing abutment wall 200 on, at the 1002m of inverted arch end drill 201.
Waterstop fixed setting method in tunnel provided in this embodiment is suitble to the entire length of middle buried water stop 400 to be greater than
The case where middle buried water stop 400 in embodiment one.
The foregoing is merely the preferred embodiment of the present invention, are not intended to restrict the invention, for this field
For technical staff, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any
Modification, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.
Claims (9)
1. a kind of tunnel waterstop fixed setting method, which comprises the following steps:
On the preliminary bracing abutment wall of inverted arch end, drill at the inverted arch end 1.5-2m, the insertion anchoring steel in hole
Pipe, punching inclination angle keep horizontal;
Buried water stop in circulation, buried sealing in middle buried water stop and the upper circulation are provided in the inverted arch end
After band overlap joint processing, fixed in lap-joint using the first fixture;
Separate type template is set far from the adjacent one end of the inverted arch end in the middle buried water stop;
Support frame is fixedly mounted close to one end of the preliminary bracing abutment wall, support frame as described above is close to the separate type template, really
It protects support frame as described above and abuts the middle buried water stop far from one end of the preliminary bracing abutment wall;
The end point that the middle buried water stop stretches out the separate type template is installed by the second fixture;
One end of second fixture and chain block is connected using iron chains, the other end of the chain block and the anchoring
Steel pipe connection;
Chain block described in tensioning is tightened the middle buried water stop, is tightly attached on support frame as described above;
First fixture includes two the first bolts and the first screw-thread steel and the second screw-thread steel that are parallel to each other, and described
The both ends of one screw-thread steel are respectively arranged with the first threaded hole and the second threaded hole, and the both ends of second screw-thread steel are respectively arranged with
Third threaded hole and the 4th threaded hole, first threaded hole and the third threaded hole are coaxial, second threaded hole and institute
It is coaxial to state the 4th threaded hole, the first threaded hole described in first screw bolt passes and the third threaded hole are another
Second threaded hole and the 4th threaded hole described in first screw bolt passes.
2. waterstop fixed setting method in tunnel according to claim 1, which is characterized in that passing through the chain block
After the step of tightening the middle buried water stop, also with step: utilizing knot at the middle part of the middle buried water stop length
Structure reinforcing bar is welded temporary support reinforcing bar card and reinforces fixing.
3. waterstop fixed setting method in tunnel according to claim 2, which is characterized in that long according to one-time-concreting inverted arch
Degree is added at the 1/3 and 2/3 of whole middle buried water stop length using structure reinforcing bars electric welding temporary support reinforcing bar card respectively
It is strong fixed.
4. waterstop fixed setting method in tunnel according to claim 1, which is characterized in that the anchoring steel pipe is using straight
Diameter is the seamless steel pipe of 42mm.
5. waterstop fixed setting method in tunnel according to claim 1, which is characterized in that the anchoring steel pipe is inserted into institute
After stating preliminary bracing abutment wall, the part tendency face angular separation of the exposed preliminary bracing abutment wall is kept for 80 ° or less.
6. waterstop fixed setting method in tunnel according to claim 1, which is characterized in that apart from the inverted arch end
The hole depth to drill at 1.5-2m is more than or equal to 30cm.
7. waterstop fixed setting method in tunnel according to claim 1, which is characterized in that the middle buried water stop is stretched
The end portion of the separate type template is less than or equal to 1m out.
8. waterstop fixed setting method in tunnel according to claim 1, which is characterized in that second fixture includes two
The second bolt and the third screw-thread steel and the 4th screw-thread steel being parallel to each other, the both ends of the third screw-thread steel are respectively set
There are the 5th threaded hole and the 6th threaded hole, the both ends of the 4th screw-thread steel are respectively arranged with the 7th threaded hole and the 8th screw thread
Hole, the 5th threaded hole and the 7th threaded hole are coaxial, and the 6th threaded hole and the 8th threaded hole are coaxial, and one
5th threaded hole described in second screw bolt passes and the 7th threaded hole, another second screw bolt passes
6th threaded hole and the 8th threaded hole.
9. waterstop fixed setting method in tunnel according to claim 1, which is characterized in that support frame as described above is triangular prism,
Including pressing lever and two foundation muscle, pressing lever is fixedly connected with two foundation muscle, and the pressing lever is for abutting the middle buried water stop.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711315956.0A CN108060932B (en) | 2017-12-11 | 2017-12-11 | A kind of tunnel waterstop fixed setting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711315956.0A CN108060932B (en) | 2017-12-11 | 2017-12-11 | A kind of tunnel waterstop fixed setting method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108060932A CN108060932A (en) | 2018-05-22 |
CN108060932B true CN108060932B (en) | 2019-09-06 |
Family
ID=62138161
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711315956.0A Active CN108060932B (en) | 2017-12-11 | 2017-12-11 | A kind of tunnel waterstop fixed setting method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108060932B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111271096A (en) * | 2020-03-26 | 2020-06-12 | 中国电建集团华东勘测设计研究院有限公司 | Installation structure and method of steel edge rubber waterstop at tunnel induced joint |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000145394A (en) * | 1998-11-13 | 2000-05-26 | Ohbayashi Corp | Plastic sheet-adhered segment and its joint processing method |
JP4513146B2 (en) * | 1999-10-25 | 2010-07-28 | シーアイ化成株式会社 | Manufacturing method of wearing band seat |
CN101929344B (en) * | 2010-07-14 | 2012-07-04 | 中铁隧道集团二处有限公司 | Method for mounting medium-deep buried water stop of tunnel archwall lining concrete toroidal construction joint |
CN103437791B (en) * | 2013-09-13 | 2016-02-17 | 中铁隧道集团二处有限公司 | The mounting method of buried water stop in a kind of tunnel lining trolley termination |
-
2017
- 2017-12-11 CN CN201711315956.0A patent/CN108060932B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN108060932A (en) | 2018-05-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20150000227A1 (en) | Splice sleeve with elliptical or compound curve cross section | |
CN103132656B (en) | Connecting structure for vertical reinforcement bars of prefabricated wall parts | |
CN210316151U (en) | Steel construction floor composite beam component | |
US12060718B2 (en) | Concrete pouring guiding device and construction method for sewage treatment tank | |
CN204781607U (en) | Prestressing force carbon fiber plate stretch -draw anchored integrated device | |
CN209855831U (en) | Lock foot anchor pipe positioner | |
CN108060932B (en) | A kind of tunnel waterstop fixed setting method | |
CN107503766A (en) | A kind of shield tunnel staggered joint erection method | |
CN210049123U (en) | Road and bridge crack reinforced structure | |
CN110259105A (en) | Cantilever Beams and construction method | |
CN207420036U (en) | Steel bar template positions constructing structure in reinforced concrete member | |
CN211202011U (en) | Movable clamp for mounting water stop belt of tunnel construction joint | |
CN207525789U (en) | Buried rubber fastening band fixing device for installing in one kind | |
WO2024053171A1 (en) | Road bridge deck slab connection construction method | |
CN207435906U (en) | For the bracket of bridge construction | |
KR101210827B1 (en) | Steel reinforcement connector | |
CN204608847U (en) | A kind of anti-floats request anchor rod drawing test instrument | |
CN103669335B (en) | Pile Connection Structure and Pile | |
CN111331711A (en) | A kind of tunnel pre-embedded groove mould locking device | |
AU2021102932A4 (en) | Novel unbonded annular anchor prestressed concrete lining and construction method thereof | |
CN211396871U (en) | Installation device for heavy steel column | |
CN103334424B (en) | Rail fabrication and installation technology and rail antislide pile | |
CN106939616A (en) | Steel plate structure and assembled soil nail wall | |
CN211992588U (en) | T-shaped clamp for channel steel | |
CN118881096B (en) | Tensioning anchoring structure for integral seamless terrace |
Legal Events
Date | Code | Title | Description |
---|---|---|---|