CN108005264B - Steel frame constraint precast reinforced concrete shear wall structure and preparation and installation methods - Google Patents
Steel frame constraint precast reinforced concrete shear wall structure and preparation and installation methods Download PDFInfo
- Publication number
- CN108005264B CN108005264B CN201711379390.8A CN201711379390A CN108005264B CN 108005264 B CN108005264 B CN 108005264B CN 201711379390 A CN201711379390 A CN 201711379390A CN 108005264 B CN108005264 B CN 108005264B
- Authority
- CN
- China
- Prior art keywords
- steel
- shear wall
- reinforced concrete
- steel frame
- wall structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
- E04B2/58—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
The invention discloses a steel frame constraint precast reinforced concrete shear wall structure, wherein mounting holes are formed in the outer side flanges of end beams at the upper end or the lower end of the steel frame constraint precast reinforced concrete shear wall structure; the end without the beam is provided with a connecting steel plate seat, and the connecting steel plate seat is also provided with a mounting hole which corresponds to the mounting hole on the outer flange of the end beam; and a process groove for installing bolts or nuts is formed in the precast concrete at the position corresponding to the installation hole on the outer flange of the end beam. The steel frame constraint prefabricated reinforced concrete shear wall structure has the advantages of high factory prefabrication degree and less field wet operation. The assembled steel reinforced concrete shear walls and the peripheral steel beams are connected by adopting full bolts, so that the site construction speed is high. The earthquake-proof performance is good, the earthquake-proof structure is applicable to areas with high earthquake intensity, and the structure is high in applicable height.
Description
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a steel frame constraint precast reinforced concrete shear wall structure and a preparation and construction method thereof.
Background
In the residential building of China, the cast-in-situ reinforced concrete shear wall residential structure is widely applied. The cast-in-situ reinforced concrete shear wall structure house has: (1) The structure is integrated with the enclosure, and the shear wall is used as a structural member and an enclosure member; (2) The structure and the heat preservation are integrated, the concrete is a heat inert material, and the heat preservation performance is good; (3) The structure and the protection are integrated, the steel bars are coated in the concrete, corrosion prevention and fire prevention are not needed, and maintenance is avoided. (4) The structure and the decoration are integrated, and the concrete can be directly used as a decoration surface layer. (5) good economical efficiency and high structural rigidity. (6) good use effect, and no beam or column is exposed in the room. (7) good sound insulation effect. And the like. But the house with the cast-in-situ reinforced concrete shear wall structure still exists: the method has the advantages of multiple on-site wet operations, low assembly degree, resource waste, environmental pollution, incapability of realizing four-section environment protection and the like, and does not meet the modern development requirements of the building industry.
The prefabricated reinforced concrete shear wall structure system has the advantages of factory prefabrication, field assembly construction, less resource waste, less environmental pollution and the like, but the prefabricated reinforced concrete shear wall structure system still has the defects of large number of connection areas, inconvenient node connection, more field wet operation, low construction efficiency, high cost and the like. The steel bars in the precast reinforced concrete shear wall structure are connected by adopting grouting sleeves, the connecting mode has higher requirements on the machining precision of the precast reinforced concrete shear wall, the positions of the steel bars are slightly deviated, and the on-site steel bars are difficult to penetrate into the sleeves; meanwhile, as the number of the steel bars of the shear wall is large and the shear wall is operated at high altitude, the centering and steel bar connection site construction difficulties of the precast reinforced concrete shear walls at the upper layer and the lower layer are large; after the steel bars of the lower-layer precast reinforced concrete shear wall extend outwards to penetrate into the upper-layer precast reinforced concrete shear wall reserved sleeve, high-strength grouting material is required to be poured into the sleeve, and as the process is a hidden engineering and on-site operation worker, most of common farmers, the grouting construction quality of the reinforced concrete sleeve is difficult to guarantee, and even if a problem is found, the problem is difficult to remedy, and a certain potential safety hazard exists.
Therefore, developing a novel fabricated shear wall structure system with comprehensive advantages of industrial production, field full-fabricated connection, small number of connection joints, high construction efficiency, good economy and the like becomes a technical problem to be solved by those skilled in the art.
Disclosure of Invention
The invention aims to provide a steel frame constraint precast reinforced concrete shear wall structure which has novel and unique structure, is convenient to use, can effectively avoid the problems of multiple field wet operations, low construction efficiency, high cost, larger field construction difficulty of reinforcing steel bar grouting sleeve connection, difficult quality assurance, high cost and the like, and is a building structural member; the specific technical scheme is as follows:
a steel frame constraint precast reinforced concrete shear wall structure comprises a reinforced structure and precast concrete; the steel bar structure comprises vertical steel bars which are horizontally distributed and horizontal steel bars which are longitudinally distributed; the steel frame constrains the height of the precast reinforced concrete shear wall structure to be higher than one layer of height; the steel bar structure also comprises a plurality of cross beams and a plurality of upright posts; the cross beam and the upright post are made of profile steel; the top surface of the beam is consistent with the bottom surface of the floor slab in height; the left end part and the right end part of the horizontal steel bar are respectively welded on the inner flange between the two upright posts; the precast concrete is arranged in a segmented mode, and a pouring reserved section is arranged at a position corresponding to each floor slab; the precast concrete is arranged between the inner flanges between the two upright posts; the steel bar structure continuously passes through casting reserved sections among all layers of precast concrete; the outer side flanges of the end beams at the upper end or the lower end of the steel frame constraint precast reinforced concrete shear wall structure are provided with mounting holes; the end without the beam is provided with a connecting steel plate seat, and the connecting steel plate seat is also provided with a mounting hole which corresponds to the mounting hole on the outer flange of the end beam; a process groove for installing bolts or nuts is formed in the precast concrete at the position corresponding to the installation hole on the outer flange of the end beam; the two ends of the cross beam are provided with T-shaped beam supports and connecting steel plates, and bolt holes are formed in the cross beam fixing seat and the connecting steel plates; the steel frame constraint precast reinforced concrete shear wall structure further comprises an L-shaped connecting piece, and bolt holes are formed in the L-shaped connecting piece.
Further, the height of the pouring reserved section is not larger than the thickness of the floor slab of the layer.
Further, the height of the connecting steel plate seat is 50 mm-150 mm.
Further, the precast concrete has the same thickness as the flanges of the cross member and the column.
The invention also provides a preparation method of the steel frame constraint precast reinforced concrete shear wall structure, which comprises the following steps:
1) Welding a beam and a stand column made of profile steel into a steel frame in a factory, wherein one end of the steel frame is provided with an end beam, the outer side flange plate of the end beam is provided with a bolt mounting hole, and the other end of the stand column is provided with a connecting steel plate seat;
2) Placing the steel frame on a die table; fixing horizontal steel bars and vertical steel bars on the steel frame; respectively welding two ends of a horizontal steel bar on an inner side flange plate between two upright posts, welding one end of a vertical steel bar on an end beam rib plate at the end part of the steel frame, and welding the other end of the vertical steel bar on the connecting steel plate seat rib plate;
3) A pouring reserved section is arranged at the position corresponding to each floor slab; pouring concrete between the two upright posts, and vibrating while pouring;
4) And (5) curing the concrete after pouring is completed.
Further, the method also comprises the following steps:
and the step 1) further comprises welding stiffening ribs between the column flanges of the beam column node area.
Further, in the step 1), the two ends of the beam are welded with a beam fixing seat and a connecting steel plate, and an L-shaped connecting piece is processed.
The invention also discloses an installation method of the steel frame constraint precast reinforced concrete shear wall structure, which comprises the following steps:
1) Installing a next layer of steel frame to restrain the precast reinforced concrete shear wall structure; the method comprises the steps of using temporary support to fix, respectively connecting T-shaped beam supports and connecting plates at two ends of a beam of a steel frame constraint precast reinforced concrete shear wall structure with a lower flange and a web of a peripheral beam, and respectively connecting an L-shaped connecting piece with an upper flange of the peripheral beam and the connecting steel plate seat;
2) Installing each layer of horizontal floor slab in the next layer of steel frame constraint precast reinforced concrete shear wall structure, and sequentially arranging each layer of horizontal floor slab steel bars;
3) Pouring the laminated layer concrete of each layer of floor and pouring the reserved section;
4) Connecting the end cross beam between the upper steel frame and the lower steel frame restraining precast reinforced concrete shear wall structures with the connecting steel plate seat, and connecting the connecting steel plate seat with the peripheral cross beam;
5) Setting horizontal distribution steel bars in the casting reserved section at the joint, and casting the casting reserved section at the joint;
6) Installing a layer of steel frame to restrict each layer of horizontal precast floor slab in the precast reinforced concrete shear wall structure, and arranging horizontal floor slab steel bars;
7) Pouring concrete to fill the floor slab;
and (3) repeating the steps 1) to 7) until all the layer steel frame constraint precast reinforced concrete shear wall structures are installed.
Further, the cross beam and the L-shaped connecting piece are connected with the peripheral cross beam through high-strength bolts.
The invention uses the built-in steel frame as a bearing framework during construction, realizes that a plurality of structural layers are used as a prefabricating unit, greatly reduces the number of connecting joints and can greatly improve the construction efficiency. The steel bars in the upper layer and the lower layer type steel concrete shear walls are connected through the built-in cross beam and the end connection steel plate seat by high-strength bolts, so that the defects of high field construction difficulty, difficult quality assurance and high cost in grouting connection of the steel bar sleeves are avoided. The steel reinforced concrete shear wall structure has good earthquake resistance, can be suitable for high-intensity areas, and has high structure application height.
Drawings
FIG. 1 is a schematic structural view of a steel frame-constrained precast reinforced concrete shear wall structure of the present invention;
FIG. 2 is a schematic view of the internal structure of the steel frame-constrained precast reinforced concrete shear wall structure of the present invention;
FIG. 3 is a schematic view of the internal structure of the upper connection part;
FIG. 4 is a schematic view of the internal structure of the lower connecting portion;
fig. 5 is an assembled schematic view of a steel frame-constrained precast reinforced concrete shear wall structure.
In the figure: 1. a cross beam; 2. a column; 3. horizontal steel bars; 4. vertical steel bars; 5. connecting a steel plate seat; 6. T-shaped beam support; 7. concrete; 8. a connecting plate; 9. an L-shaped connecting plate; 10. t-shaped connecting bottom corners; 11. a peripheral beam; A. an upper shear wall structure; B. and a lower shear wall structure.
Description of the embodiments
The present invention will be described more fully with reference to the following examples. This invention may be embodied in many different forms and should not be construed as limited to the exemplary embodiments set forth herein.
Spatially relative terms, such as "upper," "lower," "left," "right," and the like, may be used herein for ease of description to describe one element or feature's relationship to another element or feature's illustrated in the figures. It will be understood that the spatial terms are intended to encompass different orientations of the device in use or operation in addition to the orientation depicted in the figures. For example, if the device in the figures is turned over, elements described as "under" other elements or features would then be oriented "over" the other elements or features. Thus, the exemplary term "lower" may encompass both an upper and lower orientation. The device may be otherwise positioned (rotated 90 degrees or at other orientations) and the spatially relative descriptors used herein interpreted accordingly.
As shown in fig. 1, the steel frame in the present embodiment constrains a precast reinforced concrete shear wall structure, including a concrete 7 and a reinforced structure. When pouring, the concrete 7 of the whole shear wall is not poured into a whole; but rather casting in segments. The position of the concrete 7 corresponding to the floor slab is provided with a casting reserved section, the steel bars of the floor slab or only the upper layer steel bars extend into and are anchored between the precast concrete layers, and the casting reserved section is cast with the floor slab and the precast steel reinforced concrete shear wall on site, so that the structural strength and the integrity of the building are improved. The concrete 7 does not cover the two upright posts 2, and flange plates on the inner sides of the two upright posts 2 are used as frames.
As shown in fig. 2 to 4, the reinforcing structure includes vertical reinforcing bars 4 horizontally distributed and horizontal reinforcing bars 3 longitudinally distributed. In order to improve the strength, the rigidity, the ductility and the convenience in connection of the shear wall structure, the steel bar structure also comprises a steel frame consisting of a plurality of layer cross beams 1 and a plurality of upright posts 2; the steel frame may be arranged on a floor basis. The reinforced structure continuously passes through the pouring reserved sections among the precast concrete layers, so that the number of connecting joints is reduced, and the construction process is simplified. The vertical steel bars 4 penetrating up and down can improve the strength and the integrity of the steel frame constraint precast reinforced concrete shear wall structure. Connecting structures are arranged in casting reserved sections at the upper end and the lower end of the steel frame constraint precast reinforced concrete shear wall structure; the shear wall structure can be conveniently connected in series up and down through the connecting structure, and is suitable for multi-layer or high-rise buildings.
The steel frame constraint precast reinforced concrete shear wall structure can be in a straight shape, a T shape, an L shape or a cross shape; an inclined support can be arranged between the layer beam 1 and the upright post 2; the strength of the steel frame is improved.
The bottom of the connecting steel plate seat 5 is a steel plate seat, and the thickness is not less than 10mm; the steel plate seat is provided with a plurality of bolt mounting holes. A central stiffening rib is vertically welded along the length direction, and a plurality of auxiliary stiffening ribs perpendicular to the central stiffening rib are arranged along the length direction of the central stiffening rib. The position of the auxiliary stiffening rib corresponds to the setting position of the vertical steel bar 4; the vertical steel bars 4 can be welded on the side surfaces of the steel plates of the auxiliary stiffening ribs, and the force of the vertical steel bars 4 is transmitted to the connecting steel plate seat.
T-shaped beam supports 6 are welded on the upright posts 2 and are used for supporting the peripheral cross beams during hoisting. Bolt holes are formed in the top plate of the T-shaped beam support 6, and the T-shaped beam support 6 is fixedly connected with the lower flange of the peripheral beam through bolts.
An L-shaped connecting plate 9 can also be arranged, the bottom plate and the side plates of the L-shaped connecting plate 9 are both provided with bolt holes, and the L-shaped connecting plate 9 is fixedly connected with the upright posts 2 and the upper flanges of the peripheral cross beams through bolts. Stiffening ribs can be arranged between the bottom plate and the side plate of the L-shaped connecting plate 9, so that the connecting strength is improved.
The connecting plate 8 can be welded at the position between the upper flange and the lower flange of the peripheral beam on the upright post 2, and the connecting plate 8 is fixedly connected with the web plate of the peripheral beam by bolts.
The two ends of the steel plate seat 5 are connected, and the bottom end part of the upright post 2 can be welded with a T-shaped connecting bottom corner 10. The T-shaped connecting bottom corner 10 is fixedly connected with the upper flange of the peripheral beam through bolts.
The web height of the cross beam 1 is as consistent as possible with the web height of the peripheral cross beam. Stiffening ribs are welded between the left flange and the right flange of the upright post, and the positions corresponding to the upper flange plate and the lower flange plate of the cross beam 1; the supporting strength of the upright post 2 is improved.
In order to facilitate connection with each floor slab, the integrity of the structure is improved, and the height of the casting reserved section is not greater than the thickness of the floor slab of the layer.
In order to improve the connection strength of the upper shear wall structure A and the lower shear wall structure B; the height of the connecting steel plate seat is 50 mm-150 mm.
The steel frame constraint precast reinforced concrete shear wall structure is prepared by the following method:
1) In a factory, welding a beam 1 and a column 2 which are made of profile steel into a steel frame, and welding an end beam at the upper end of the column 2; the lower end part is welded and connected with a steel plate seat 5 and a T-shaped connecting bottom corner 10; welding a T-shaped beam support 6 and a connecting plate 8 on the side surface of the upright post 2; if necessary, a stiffening rib can be welded between the flanges of the beam column joint area;
2) Pouring a concrete outer blade (not shown in the figure), arranging a heat-insulating connecting piece (not shown in the figure) on the concrete outer blade, and curing;
3) After the curing of the concrete outer blade is completed, placing the concrete outer blade on a mold table, and placing an insulation layer (not shown in the figure) on the outer blade, wherein the insulation connecting piece penetrates through the insulation layer; if no insulation layer is required or no insulation layer and no outer leaf are required, step 2) and step 3) may be omitted;
4) Placing the steel frame on a die table; fixing a horizontal steel bar 3 and a vertical steel bar 4 on a steel frame; respectively welding two ends of a horizontal steel bar 3 on an inner side flange plate between two upright posts 2, welding the upper end of a vertical steel bar 4 on an end cross beam rib plate, and welding the lower end of the vertical steel bar 4 on a connecting steel plate seat 5 rib plate;
5) A pouring reserved section is arranged at the position corresponding to each floor slab; pouring concrete between the two upright posts 2 by taking the two inner side flange plates as side molds, and vibrating while pouring; the process grooves for installing bolts or nuts are arranged at the positions corresponding to the bolt installation holes of the end cross beam, so that the bolts or nuts can be conveniently installed;
6) And (5) curing the concrete after pouring is completed. A casting reserved section is reserved in the middle of the concrete 7 formed by casting and is used for casting in situ. Precast concrete segments 7 surround the steel frame segments.
The end cross member may be disposed below, and the connection steel plate holder 5 may be disposed above.
As shown in fig. 5, after the steel frame-constrained precast reinforced concrete shear wall structure is transported to the site, the installation is performed by the following method:
1) Installing a lower shear wall structure B; the method comprises the steps of using temporary support to fix, respectively connecting T-shaped beam supports 6 and connecting plates 8 at two ends of a beam 1 of a steel frame constraint precast reinforced concrete shear wall structure with a lower flange and a web plate of a peripheral beam 11, and respectively connecting an L-shaped connecting piece 9 with an upper flange of the peripheral beam 11 and the connecting steel plate seat 5;
2) Installing each layer of horizontal floor slab in the steel frame constraint precast reinforced concrete shear wall structure, and sequentially arranging each layer of horizontal floor slab steel bars;
3) Pouring laminated layer concrete of each layer of floor slab of the lower shear wall structure B and pouring a reserved section;
4) Connecting a steel plate fixing seat 5 at the lower end of an upper shear wall structure A with an end beam at the upper end of a lower shear wall structure B by using a high-strength bolt, and connecting the connecting steel plate seat with a peripheral beam 11;
5) Setting horizontal distribution steel bars in the casting reserved section at the joint, and casting the casting reserved section at the joint;
6) The horizontal precast floor slabs of the upper shear wall structure A are installed, and horizontal floor slab reinforcing steel bars are sequentially arranged;
7) Pouring concrete to fill the floor slab;
the upper layer shear wall structure A and the lower layer shear wall structure B are installed; and repeating the steps 1) to 7) until all the shear wall structures are installed.
Compared with the prior art, the prefabricated reinforced concrete shear wall structure only takes one structure layer height as one prefabricated unit, so that the number of connecting joints is large, and the construction efficiency is low; the invention uses the built-in steel frame as a bearing framework during construction, realizes that a plurality of structural layers are used as a prefabricating unit, greatly reduces the number of connecting joints and can greatly improve the construction efficiency. The peripheral steel frame columns adopt hot rolled H-shaped steel, so that the hot rolled H-shaped steel is conveniently connected with the steel beam through full bolts; the thickness of the peripheral steel frame columns is the same as that of the shear wall, the out-of-plane bending resistance bearing capacity of the shear wall is stronger, and the connection with the steel beam is more convenient. The vertical connection of the precast reinforced concrete shear wall structure usually adopts a steel bar lap joint or grouting sleeve connection mode, and the connection mode has higher requirements on the processing precision of precast components and is difficult to construct on site; sleeve grouting is a concealed project, grouting quality is difficult to guarantee, and the cost of the steel bar connecting sleeve is high. The invention comprises the following steps: 1) The lower base of the upper precast shear wall is connected with the peripheral steel frame of the lower precast shear wall through high-strength bolts, so that the difficulty of vertical steel bar connection is avoided; 2) The prefabricated shear wall and the steel beam are connected through the high-strength bolts, and the steel plate seat connected with the lower part of the upper section of the prefabricated shear wall plays a role in connecting the upper and lower prefabricated shear walls and the steel beam, so that the prefabricated shear wall is multipurpose and has good economical efficiency. The steel structure has high machining precision, and the connection mode can ensure the field construction quality; meanwhile, the connection mode has no hidden engineering, and the quality is easy to ensure. The peripheral steel frame can play a role in bearing a framework during installation, connecting pieces connected with the upper layer of installation units and the peripheral cross beams 11, can restrain concrete, bear load together with reinforced concrete parts, has higher structural bearing capacity and better anti-seismic performance, and can be suitable for areas with high earthquake intensity.
The invention relates to a steel frame constraint precast reinforced concrete shear wall structure and a preparation and installation method thereof, which comprises the following steps:
(1) The factory prefabrication degree is high, and the field wet operation is few. The steel frame constraint precast reinforced concrete shear wall structure is integrally precast in a factory by taking the heights of a plurality of structural layers as an installation unit.
(2) And (5) assembling construction. The steel frame constraint precast reinforced concrete shear wall structure, the steel beam and the upper layer of steel frame constraint precast reinforced concrete shear wall structure adopt a full-bolt connection mode, and the site construction speed is high.
(3) Good anti-corrosion and fireproof performance and low cost. Most of steel structures in the steel frame constraint precast reinforced concrete shear wall structure are coated in concrete, so that the steel frame constraint precast reinforced concrete shear wall structure has good corrosion and fire resistance and greatly reduces corrosion and fire prevention cost.
(4) Structure, enclosure, heat preservation and decoration. The steel frame constraint precast reinforced concrete shear wall structure not only plays a function of structural load bearing, but also plays a function of building enclosure, meanwhile, the heat preservation layer can be compounded with the steel frame constraint precast reinforced concrete shear wall structure in a factory, the outer surface of the outer blade plate of the structure can realize the effects of bare concrete and decorative concrete, and the integration of structure, enclosure, heat preservation and decoration is realized.
(5) The steel reinforced concrete shear wall structure has good earthquake resistance, can be suitable for high-intensity areas, and has high structure application height.
And the like, can be applied to multi-story high-rise steel structure buildings, and has better popularization and application prospects especially in steel structure houses.
The above examples are for illustration of the invention only and, in addition, there are many different embodiments which will be apparent to those skilled in the art after having the insight into the present invention and are not explicitly recited herein.
Claims (9)
1. A steel frame constraint precast reinforced concrete shear wall structure comprises a reinforced structure and precast concrete; the steel bar structure comprises vertical steel bars which are horizontally distributed and horizontal steel bars which are longitudinally distributed; the steel frame restraining prefabricated reinforced concrete shear wall structure is characterized in that the height of the steel frame restraining prefabricated reinforced concrete shear wall structure is higher than one layer of height; the steel bar structure also comprises a plurality of cross beams and a plurality of upright posts; the cross beam and the upright post are made of profile steel; the top surface of the beam is consistent with the bottom surface of the floor slab in height; the left end part and the right end part of the horizontal steel bar are respectively welded on the inner flange between the two upright posts; the precast concrete is arranged in a segmented mode, and a casting reserved section is arranged at a position corresponding to each floor slab; the precast concrete is arranged between the inner flanges between the two upright posts; the steel bar structure continuously passes through a casting reserved section among all layers of precast concrete; the outer side flanges of the end beams at the upper end or the lower end of the steel frame constraint precast reinforced concrete shear wall structure are provided with mounting holes; the end without the beam is provided with a connecting steel plate seat, and the connecting steel plate seat is also provided with a mounting hole which corresponds to the mounting hole on the outer flange of the end beam; a process groove for installing bolts or nuts is formed in the precast concrete at the position corresponding to the installation hole on the outer flange of the end beam; the two ends of the cross beam are provided with T-shaped beam supports and connecting steel plates, and bolt holes are formed in the T-shaped beam supports and the connecting steel plates; the steel frame constraint precast reinforced concrete shear wall structure further comprises an L-shaped connecting piece, and bolt holes are formed in the L-shaped connecting piece.
2. The steel frame restrained precast reinforced concrete shear wall structure of claim 1, wherein the height of the casting reserve is not greater than the thickness of the floor slab.
3. The steel frame restrained precast reinforced concrete shear wall structure of claim 2, wherein the height of the connecting steel plate seat is 50 mm-150 mm.
4. The steel frame restrained precast reinforced concrete shear wall structure of claim 2, wherein the precast concrete has the same thickness as the flange widths of the cross beams and the columns.
5. A method of manufacturing a steel frame restrained precast reinforced concrete shear wall structure according to any one of claims 1 to 4, comprising the steps of:
1) Welding a beam and a stand column made of profile steel into a steel frame in a factory, wherein one end of the steel frame is provided with an end beam, the outer side flange plate of the end beam is provided with a bolt mounting hole, and the other end of the stand column is provided with a connecting steel plate seat;
2) Placing the steel frame on a die table; fixing horizontal steel bars and vertical steel bars on the steel frame; respectively welding two ends of a horizontal steel bar on an inner side flange plate between two upright posts, welding one end of a vertical steel bar on an end beam rib plate at the end part of the steel frame, and welding the other end of the vertical steel bar on the connecting steel plate seat rib plate;
3) A casting reserved section is arranged at the position corresponding to each floor slab; pouring concrete between the two upright posts, and vibrating while pouring;
4) And (5) curing the concrete after pouring is completed.
6. The method for manufacturing a steel frame restrained precast reinforced concrete shear wall structure according to claim 5, wherein in the step 1), stiffening ribs are welded between column flanges in a beam column node area.
7. The method for manufacturing the steel frame constraint precast reinforced concrete shear wall structure according to claim 5, wherein the step 1) further comprises welding beam fixing seats and connecting steel plates at two ends of the beams, and machining L-shaped connecting pieces.
8. A method of installing a steel frame restrained precast reinforced concrete shear wall structure according to any one of claims 1 to 4, comprising the steps of:
1) Installing a next layer of steel frame to restrain the precast reinforced concrete shear wall structure; the method comprises the steps of using temporary support to fix, respectively connecting T-shaped beam supports and connecting plates at two ends of a beam of a steel frame constraint precast reinforced concrete shear wall structure with a lower flange of a peripheral steel beam and a web plate, and respectively connecting an L-shaped connecting piece with an upper flange of the peripheral steel beam and the upright post;
2) Installing each layer of horizontal floor slab in the next layer of steel frame constraint precast reinforced concrete shear wall structure, and sequentially arranging each layer of horizontal floor slab steel bars;
3) Pouring the laminated layer concrete of each layer of floor and pouring the reserved section;
4) Connecting the end cross beam between the upper steel frame and the lower steel frame restraining precast reinforced concrete shear wall structures with the connecting steel plate seat, and connecting the connecting steel plate seat with the peripheral steel beam;
5) Setting horizontal distribution steel bars in the casting reserved section at the joint, and casting the casting reserved section at the joint;
6) Installing a layer of steel frame to restrict each layer of horizontal precast floor slab in the precast reinforced concrete shear wall structure, and arranging horizontal floor slab steel bars;
7) Pouring concrete to fill the floor slab;
and (3) repeating the steps 1) to 7) until all the layer steel frame constraint precast reinforced concrete shear wall structures are installed.
9. The method for installing the steel frame constraint precast reinforced concrete shear wall structure according to claim 8, wherein the T-shaped beam brackets, the connecting plates and the L-shaped connecting pieces at the two ends of the cross beam are connected with the peripheral steel beams through high-strength bolts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711379390.8A CN108005264B (en) | 2017-12-20 | 2017-12-20 | Steel frame constraint precast reinforced concrete shear wall structure and preparation and installation methods |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711379390.8A CN108005264B (en) | 2017-12-20 | 2017-12-20 | Steel frame constraint precast reinforced concrete shear wall structure and preparation and installation methods |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108005264A CN108005264A (en) | 2018-05-08 |
CN108005264B true CN108005264B (en) | 2023-06-20 |
Family
ID=62059943
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711379390.8A Active CN108005264B (en) | 2017-12-20 | 2017-12-20 | Steel frame constraint precast reinforced concrete shear wall structure and preparation and installation methods |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108005264B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108678223A (en) * | 2018-06-29 | 2018-10-19 | 北京工业大学 | A kind of recoverable steel pipe concrete frame compound shear wall and the practice |
CN110644646A (en) * | 2019-09-16 | 2020-01-03 | 佛山建装建筑科技有限公司 | Split-level grouting sleeve connected assembled shear wall system |
CN111155680A (en) * | 2019-12-30 | 2020-05-15 | 中冶建筑研究总院有限公司 | All-bolt connection multilayer prefabricated section steel concrete shear wall structure and preparation and construction method thereof |
CN112196142B (en) * | 2020-10-23 | 2024-08-16 | 沈阳建筑大学 | Connection node of box-type steel column and steel frame light wall panel |
CN114232782B (en) * | 2021-12-16 | 2023-11-21 | 中建五局第三建设有限公司 | Non-shear wall system of fully assembled building and wallboard module prefabrication method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001012102A (en) * | 1999-06-29 | 2001-01-16 | Maeda Corp | Parallel multi-layer aseismatic wall structure |
AU2015100669A4 (en) * | 2014-09-24 | 2015-07-02 | Conrock Australia Pty Ltd | Hollow Wall |
CN105544801A (en) * | 2016-01-28 | 2016-05-04 | 湖南大学 | Bolted connection technique for prefabricated large plate shear wall provided with concealed bracing and construction method |
CN107090925A (en) * | 2017-05-12 | 2017-08-25 | 姚攀峰 | Reinforced precast reinforced concrete shear wall, structural system and its construction method |
CN207739439U (en) * | 2017-12-20 | 2018-08-17 | 中冶建筑研究总院有限公司 | A kind of steel framework constraint precast reinforced concrete shear wall structure |
-
2017
- 2017-12-20 CN CN201711379390.8A patent/CN108005264B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001012102A (en) * | 1999-06-29 | 2001-01-16 | Maeda Corp | Parallel multi-layer aseismatic wall structure |
AU2015100669A4 (en) * | 2014-09-24 | 2015-07-02 | Conrock Australia Pty Ltd | Hollow Wall |
CN105544801A (en) * | 2016-01-28 | 2016-05-04 | 湖南大学 | Bolted connection technique for prefabricated large plate shear wall provided with concealed bracing and construction method |
CN107090925A (en) * | 2017-05-12 | 2017-08-25 | 姚攀峰 | Reinforced precast reinforced concrete shear wall, structural system and its construction method |
CN207739439U (en) * | 2017-12-20 | 2018-08-17 | 中冶建筑研究总院有限公司 | A kind of steel framework constraint precast reinforced concrete shear wall structure |
Also Published As
Publication number | Publication date |
---|---|
CN108005264A (en) | 2018-05-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107989227B (en) | Assembled steel reinforced concrete shear wall structure and preparation and installation methods thereof | |
CN108005265B (en) | Multilayer prefabricated steel reinforced concrete shear wall structure and preparation and construction methods thereof | |
CN108005410B (en) | Assembled steel-concrete combined structure residential system and construction method thereof | |
CN107989228B (en) | Prefabricated steel reinforced concrete shear wall structure and preparation and installation methods thereof | |
CN108005264B (en) | Steel frame constraint precast reinforced concrete shear wall structure and preparation and installation methods | |
CN111155681B (en) | Steel concrete composite connection multilayer prefabricated section steel concrete shear wall structure and preparation and construction method thereof | |
JP5523179B2 (en) | Building construction method and room module | |
US11466445B2 (en) | Integrated steel concrete building and construction method thereof | |
EP1971727B1 (en) | Construction of buildings | |
CN207739436U (en) | A kind of assembled steel reinforced concrete shear walls structure | |
EA029731B1 (en) | Method of casting in-situ steel wire mesh cement slab with spliced rack and suspended formwork | |
CN207739437U (en) | A kind of prefabricated steel reinforced concrete shear wall structure | |
CN106193292A (en) | A kind of steel frame assembled integral reinforced concrete shear wall structure system | |
CN111155680A (en) | All-bolt connection multilayer prefabricated section steel concrete shear wall structure and preparation and construction method thereof | |
KR20210038684A (en) | Precast building construction system | |
CN207739674U (en) | A kind of assembled Residential System of Steel-concrete Composite Structure | |
CN210767437U (en) | Assembled light floor | |
CN207739438U (en) | A kind of strip frame precast reinforced concrete shear wall structure | |
CN111411694A (en) | Integrated assembly type frame structure building system | |
CN108005266B (en) | Strip steel frame precast reinforced concrete shear wall structure and preparation and installation methods | |
KR101665622B1 (en) | the construction method of steel-concrete hybrid precast concrete structure | |
CN110965635B (en) | Supporting structure and layering industrialization building of building | |
CN208202224U (en) | A kind of prefabricated steel reinforced concrete shear wall structure of multilayer | |
CN207739439U (en) | A kind of steel framework constraint precast reinforced concrete shear wall structure | |
CN212001725U (en) | Full bolted connection multilayer prefabricated section steel concrete shear wall structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |