CN107994517B - Manufacturing method of fusion-connection type straight-through joint for 10 kV-35 kV cable process - Google Patents
Manufacturing method of fusion-connection type straight-through joint for 10 kV-35 kV cable process Download PDFInfo
- Publication number
- CN107994517B CN107994517B CN201711172751.1A CN201711172751A CN107994517B CN 107994517 B CN107994517 B CN 107994517B CN 201711172751 A CN201711172751 A CN 201711172751A CN 107994517 B CN107994517 B CN 107994517B
- Authority
- CN
- China
- Prior art keywords
- layer
- original
- tape
- semi
- wrap
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/14—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for joining or terminating cables
Landscapes
- Processing Of Terminals (AREA)
Abstract
Description
技术领域technical field
本发明涉及电缆连接技术领域,具体指一种10kV至35kV电缆工艺熔接式直通接头的制作方法。The invention relates to the technical field of cable connection, in particular to a method for manufacturing a 10kV to 35kV cable technology fusion-bonded straight-through joint.
背景技术Background technique
随着我国城镇化进程不断推进,电缆线路有逐渐取代高压架空线的趋势。配网电缆每盘的长度一般在600米左右,即电缆线路上每隔相应的距离就要设置一个直通接头,可见其数量是相当庞大的,而直通接头处往往是电缆线路中最薄弱的地方,因此直通接头的质量是决定电缆线路能否安全运行的一个重要因素。With the continuous advancement of my country's urbanization process, cable lines have a tendency to gradually replace high-voltage overhead lines. The length of each reel of the distribution network cable is generally about 600 meters, that is, a straight-through joint must be installed every corresponding distance on the cable line, which shows that the number is quite large, and the straight-through joint is often the weakest place in the cable line , so the quality of the straight-through joint is an important factor in determining whether the cable line can run safely.
现有的直通接头主要分为以下三种类型:绝缘带材绕包式,热缩式和冷缩预制式,但上述三种类型的直通接头故障率都比较高。目前国内配网所使用的电缆绝大数都是三芯的,一旦发生电缆直通接头发生击穿事故,单纯修补无法恢复接头的绝缘性能,必须换上新的电缆充当接头。此外由于电缆沟/井内的电缆布置较为密集,一根电缆上的接头发生故障起火后还会引燃其他电缆,容易酿成重大事故。Existing straight-through joints are mainly divided into the following three types: insulating tape wrapping type, heat-shrinkable type and cold-shrinkable prefabricated type, but the failure rate of the above-mentioned three types of straight-through joints is relatively high. At present, the vast majority of cables used in the domestic distribution network are three-core. Once a breakdown accident occurs at the cable straight-through joint, simple repairs cannot restore the insulation performance of the joint, and a new cable must be replaced as a joint. In addition, due to the dense arrangement of cables in the cable trench/well, if a joint on one cable breaks down and catches fire, other cables will be ignited, which will easily lead to major accidents.
引发现有直通接头故障的主要有以下两点因素:(1)因电缆主绝缘与接头应力锥为两种介质且存在搭接界面,其绝缘性能靠乙丙橡胶或硅橡胶材质的应力锥自身抱紧电缆主绝缘来维持。电缆运行过程中因流过电流的变化存在一定程度的热胀冷缩,而电缆主绝缘与接头应力锥的膨胀系数不同,随着应力锥的老化,其抱紧力也会相应下降进而与电缆主绝缘产生间隙,诱发局部放电直至发生击穿事故;(2)电缆沟/井内环境较为潮湿,现有直通接头主要靠应力锥分散电场,而10kV至35kV电缆不能使用金属防水接头,只能靠包缠防水胶带防水,防水胶带在使用过程中防水性能会逐渐下降,时间一长水汽就会进入电缆主绝缘与应力锥的间隙,引发电缆接头故障。There are two main factors that lead to the failure of the existing straight-through joints: (1) Since the main insulation of the cable and the stress cone of the joint are two media and there is an overlapping interface, its insulation performance depends on the stress cone itself made of ethylene-propylene rubber or silicone rubber. Hold the cable mains insulation tight to maintain it. During the operation of the cable, there is a certain degree of thermal expansion and contraction due to the change of the flowing current, and the expansion coefficient of the main insulation of the cable is different from that of the stress cone of the joint. Insulation creates gaps, which induce partial discharge until a breakdown accident occurs; (2) The environment in the cable trench/well is relatively humid, and the existing straight-through joints mainly rely on stress cones to disperse the electric field, while metal waterproof joints cannot be used for 10kV to 35kV cables. Wrap waterproof tape for waterproofing. The waterproof performance of the waterproof tape will gradually decrease during use. Over time, water vapor will enter the gap between the main insulation of the cable and the stress cone, causing cable joint failure.
发明内容Contents of the invention
本发明为解决现有技术中存在的问题提出了一种10kV至35kV电缆工艺熔接式直通接头的制作方法,通过该方法能够在施工现场快速制作出具有优良绝缘强度和防水性的电缆直通接头。In order to solve the problems existing in the prior art, the present invention proposes a method for manufacturing a 10kV to 35kV cable technology fusion-type straight-through joint, through which the cable straight-through joint with excellent insulation strength and waterproofness can be quickly produced at the construction site.
本发明所述10kV至35kV电缆工艺熔接式直通接头的制作方法包括下列步骤:The manufacturing method of the 10kV to 35kV cable process fusion type straight-through joint of the present invention comprises the following steps:
1)电缆外层的切剥:在两条电缆的对接端分别沿径向锯出两个断口,自两条电缆的断口处逐层剥除长度依次减小的外护层、钢铠层、内护层并切除外露的填充层。1) Cutting and stripping of the outer layer of the cable: saw two fractures in the radial direction at the butt ends of the two cables, and peel off the outer sheath, steel armor layer, Inner sheath and cut off the exposed padding.
2)芯缆的切剥及精修:将电缆内的芯缆自断口处逐层剥除长度依次减小的铜屏蔽层、外半导电层、绝缘层和内半导电层,将外半导电层及内半导电层的端部削成平滑过渡的斜坡状并用600目砂带打磨平滑,将绝缘层的端部削成铅笔头状,用800#砂纸打磨平滑并洗净吹干,用600目砂带去除外露的内半导电层表面的绝缘残留并抛光表面,再将外露的外半导电层、绝缘层和内半导电层以聚四氟乙烯胶带反方向缠包多层进行隔热保护;用240目砂带打磨去除外露的线芯表面及断口处的氧化层并用胶带包缠封闭。2) Cutting, stripping and finishing of the core cable: peel off the copper shielding layer, outer semi-conductive layer, insulating layer and inner semi-conductive layer layer by layer from the core cable in the cable, and remove the outer semi-conductive layer. The end of the insulating layer and the inner semi-conductive layer is cut into a smooth transitional slope and polished smooth with a 600-mesh abrasive belt. Remove the insulation residue on the surface of the exposed inner semi-conductive layer with a mesh belt and polish the surface, then wrap the exposed outer semi-conductive layer, insulating layer and inner semi-conductive layer with polytetrafluoroethylene tape in the opposite direction for heat insulation protection ; Use a 240-mesh abrasive belt to remove the exposed core surface and the oxide layer at the fracture, and wrap and seal it with tape.
3)管材的预设:在电缆上套上两根热缩管,并在电缆内部的三根芯缆上各套上一个硅橡胶防尘套。3) Presetting of pipe materials: put two heat shrinkable tubes on the cable, and put a silicone rubber dustproof cover on each of the three core cables inside the cable.
4)线芯的焊接:去除线芯外的胶带,对线芯进行校直及加热除湿处理后插入焊接模具固定,向焊接模具内填充与线芯材质相同的金属粉末进行放热焊接,随后将焊接处打磨至与原电缆线芯等径。4) Welding of the wire core: Remove the tape outside the wire core, straighten the wire core and heat and dehumidify it, insert it into the welding mold to fix it, fill the welding mold with metal powder of the same material as the wire core for exothermic welding, and then put Grind the welding place to the same diameter as the original cable core.
5)带材的包缠:去除包缠于外半导电层、绝缘层和内半导电层外的耐高温胶带,采用与内半导电层材质相同的带材紧密包缠线芯表面及原内半导电层形成表面高出原芯缆内半导电层1mm以内且两端盖过原内半导电层斜坡状的端部的内半导电修复层;采用与绝缘层相同的带材紧密包缠内半导电修复层、原内半导电层及原绝缘层形成表面高出原绝缘层5~8mm且两端与原绝缘层平滑过渡的绝缘修复层,所述绝缘修复层的两端盖过原绝缘层铅笔头状的端部;采用与外半导电层材质相同的带材紧密包缠绝缘修复层、原绝缘层及原外半导电层表面形成厚度与原外半导电层相同的外半导电修复层,所述外半导电修复层的两端盖过原外半导电层斜坡状的端部。5) Tape wrapping: Remove the high-temperature-resistant tape wrapped around the outer semiconductive layer, insulating layer and inner semiconductive layer, and use the same tape as the inner semiconductive layer to tightly wrap the core surface and the original inner The surface of the semi-conductive layer is higher than the inner semi-conductive layer of the original core cable within 1mm, and the two ends cover the slope-shaped end of the original inner semi-conductive layer; the inner semi-conductive repair layer is tightly wrapped with the same tape as the insulating layer. The semi-conductive repair layer, the original inner semi-conductive layer and the original insulating layer form an insulating repair layer whose surface is 5-8mm higher than the original insulating layer and whose two ends transition smoothly with the original insulating layer. The two ends of the insulating repair layer cover the original insulating layer The end of the pencil head of the layer; use the same material as the outer semi-conductive layer to tightly wrap the insulating repair layer, the original insulating layer and the surface of the original outer semi-conductive layer to form an outer semi-conductive repair with the same thickness as the original outer semi-conductive layer layer, the two ends of the outer semiconductive repair layer cover the slope-shaped end of the original outer semiconductive layer.
6)内半导电层、绝缘层及外半导电层的熔接恢复:将硅橡胶防尘套移至外半导修复层处,完整包覆并紧裹外半导电修复层,在硅橡胶防尘套外包裹一层铝箔并以酰亚胺胶带包缠固定,再以塑形模具锁紧固定后置于加热筒中加热以熔合构成外半导电修复层、绝缘修复层及内半导电层的带材,采用高频感应加热装置加热靠近加热筒两端的芯缆段使外半导电修复层与原外半导电层、绝缘修复层与原修复层、内半导电修复层与原内半导电层融为一体,结束加热时塑形模具内的压力不得低于1.8MPa。6) Fusion recovery of the inner semiconductive layer, insulating layer and outer semiconductive layer: move the silicone rubber dust cover to the outer semiconductive repair layer, completely cover and tightly wrap the outer semiconductive repair layer, Wrap a layer of aluminum foil on the outside of the sleeve and wrap it with imide tape to fix it, then lock and fix it with a plastic mold, and then heat it in a heating cylinder to fuse the strips that form the outer semi-conductive repair layer, insulating repair layer and inner semi-conductive layer , using high-frequency induction heating device to heat the core cable section near the two ends of the heating cylinder to make the outer semi-conductive repair layer and the original outer semi-conductive layer, the insulation repair layer and the original repair layer, the inner semi-conductive repair layer and the original inner semi-conductive layer to fuse Integral, the pressure in the shaping mold should not be lower than 1.8MPa when the heating is finished.
7)铜屏蔽层的恢复:拆除加热筒、塑形模具、酰亚胺胶带、铝箔及硅橡胶防尘套,用铜网分别包缠连接每根芯缆上的原铜屏蔽层并以恒力弹簧固定铜网两端,再以绝缘胶带将三根芯缆包缠捆绑为一体。7) Restoration of the copper shielding layer: Remove the heating cylinder, plastic mold, imide tape, aluminum foil and silicone rubber dust cover, wrap and connect the original copper shielding layer on each core cable with copper mesh and apply a constant force The two ends of the copper mesh are fixed by springs, and then the three core cables are wrapped and bundled together with insulating tape.
8)内护层的恢复:以防水胶带包缠在绝缘胶带外侧并连接两条电缆的原内护层,包缠时需将防水胶带百分百拉伸并半搭接缠绕多层,随后将防水胶水均匀涂抹在防水胶带表面并套以一根热缩管,均匀加热热缩管使其充分收缩并以防水胶带包封热缩管的两端。8) Restoration of the inner sheath: Wrap the outer side of the insulating tape with waterproof tape and connect the original inner sheath of the two cables. When wrapping, the waterproof tape needs to be 100% stretched and half-lapped and wound for multiple layers, and then the The waterproof glue is evenly applied on the surface of the waterproof tape and covered with a heat-shrinkable tube, and the heat-shrinkable tube is evenly heated to make it fully shrink, and the two ends of the heat-shrinkable tube are wrapped with waterproof tape.
9)钢铠层的接通:以240目砂带磨去两根电缆连接端原钢铠层表面的防锈漆,再以两端与原电缆钢铠层搭接的铜编织带包裹热缩管并以恒力弹簧固定铜编织带两端,最后以绝缘胶带包缠固定两恒力弹簧。9) Connection of the steel armor layer: Use a 240-mesh abrasive belt to grind off the anti-rust paint on the surface of the original steel armor layer at the connection end of the two cables, and then wrap the heat-shrinkable copper braid with the two ends overlapping the original cable steel armor layer. The two ends of the braided copper braid are fixed with constant force springs, and finally the two constant force springs are wrapped and fixed with insulating tape.
10)外护层的恢复:用600目砂带打磨两条电缆连接端的原外护层表面并包缠填充胶带,再以防水胶带包缠接通后的钢铠层及两条电缆上缠有填充胶带的原外护层,包缠时需将防水胶带百分百拉伸并半搭接缠多层,随后用防水胶水均匀涂抹在防水胶带表面,并套以另一根热缩管,均匀加热热缩管使其充分收缩并以防水胶带包封热缩管的两端,最后以铠装带在热缩管表面半搭接缠绕多层。10) Restoration of the outer sheath: use a 600-mesh abrasive belt to polish the surface of the original outer sheath at the connection end of the two cables and wrap the filling tape, then wrap the connected steel armor layer and the two cables with waterproof tape. Fill the original outer sheath of the tape. When wrapping, the waterproof tape needs to be stretched 100% and half-lapped to wrap multiple layers, and then the waterproof glue is evenly applied to the surface of the waterproof tape, and another heat-shrinkable tube is covered, evenly Heat the heat-shrinkable tube to make it fully shrink and wrap the two ends of the heat-shrinkable tube with waterproof tape, and finally wrap multiple layers of armored tape on the surface of the heat-shrinkable tube.
所述步骤6)中加热筒的加热过程为:均匀升温20~30min至100℃并恒温5~10min,随后缓慢升温15~25min至185℃并恒温40~50min,加热筒升温至100℃以上后开启高频感应加热装置在380V电压下输出350A感应加热电流对靠近加热筒两端的芯缆段同步进行加热。The heating process of the heating cylinder in the step 6) is: uniformly increase the temperature for 20-30 minutes to 100°C and keep the temperature for 5-10 minutes, then slowly increase the temperature for 15-25 minutes to 185°C and keep the temperature for 40-50 minutes, after the heating cylinder is heated to above 100°C Turn on the high-frequency induction heating device to output 350A induction heating current at 380V voltage to simultaneously heat the core cable sections near both ends of the heating cylinder.
以聚四氟乙烯胶带包缠能够有效阻隔焊接处辐射出的热量保护芯缆,并且受热后不易与内半导电层、绝缘层和外半导电层发生粘连,便于剥除。硅橡胶防尘套可有效隔绝水汽和杂质,使包缠好的带材保持国标要求的洁净度并对带材施加一定的压力进行固定,铝箔通过耐高温的酰亚胺胶带固定在硅橡胶防尘套上,可起到均匀导热的作用。Wrapping with PTFE tape can effectively block the heat radiated from the welding point to protect the core cable, and it is not easy to adhere to the inner semiconductive layer, insulating layer and outer semiconductive layer after being heated, so it is easy to peel off. The silicone rubber dust cover can effectively isolate water vapor and impurities, so that the wrapped strip can maintain the cleanliness required by the national standard and fix the strip by applying a certain pressure. On the dust jacket, it can play the role of uniform heat conduction.
加热筒在上述加热过程中采用阶段升温的方式将热量由外向内传递给三种带材芯,可兼顾三种带材的熔合并在外界压力的作用下形成致密的外半导电修复层、绝缘修复层和内半导电修复层。高频感应加热装置则直接作用于线芯,热量由内向外从线芯依次传递给原内半导电层、原绝缘层和原外半导电层,这样外半导电修复层与原外半导电层、绝缘修复层与原绝缘层、内半导电修复层与原内半导电层的交界处都能达到所需的温度并充分熔接结合,从而一次性完成芯缆的三层修复。In the above heating process, the heating cylinder adopts a staged heating method to transfer heat from the outside to the inside to the three kinds of strip cores, which can take into account the fusion of the three kinds of strips and form a dense outer semi-conductive repair layer and insulation under the action of external pressure. repair layer and inner semiconductive repair layer. The high-frequency induction heating device directly acts on the wire core, and the heat is transferred from the wire core to the original inner semiconducting layer, the original insulating layer and the original outer semiconducting layer from the inside to the outside, so that the outer semiconducting repair layer and the original outer semiconducting layer 1. The junction between the insulation repair layer and the original insulation layer, the inner semi-conductive repair layer and the original inner semi-conductive layer can reach the required temperature and be fully welded and combined, thereby completing the three-layer repair of the core cable at one time.
由于上述工艺熔接式直通接头的外半导电修复层、绝缘修复层和内半导电修复层采用的材料与原电缆完全一致且熔接充分,不存在常规接头中应力锥老化抱紧力下降、界面进水导致的放电击穿问题。整套制作方法依次进行线芯焊接、接头处内半导电层、绝缘层及外半导电层的三层熔合、缠绕铜网、绕包防水胶带、恢复钢带铠装及外护层等步骤,用到的设备较少,较易于操作且得到的直通接头能够较好地与原先的两根电缆衔接,且具有较好的绝缘强度和防水性能。另外由于制作过程中电缆芯缆的外半导电层、绝缘层和内半导电层是同时修复的,可大幅提高接头的制作效率。Since the material used for the outer semiconductive repair layer, insulating repair layer and inner semiconductive repair layer of the fusion-bonded straight-through joint in the above process is completely consistent with the original cable and fully welded, there is no aging of the stress cone in the conventional joint. Discharge breakdown problem caused by water. The whole set of production method is followed by steps such as wire core welding, three-layer fusion of inner semiconductive layer, insulating layer and outer semiconductive layer at the joint, winding copper mesh, wrapping waterproof tape, restoring steel tape armor and outer sheath, etc. The obtained equipment is less, easier to operate, and the obtained straight-through joint can be better connected with the original two cables, and has better insulation strength and waterproof performance. In addition, since the outer semiconductive layer, insulating layer and inner semiconductive layer of the cable core cable are repaired at the same time during the production process, the production efficiency of the joint can be greatly improved.
本发明所述10kV至35kV电缆工艺熔接式直通接头的制作方法较易于操作且制作效率高,得到的直通接头具有较好的绝缘强度和防水性。The manufacturing method of the 10kV to 35kV electric cable process welding type straight-through joint of the present invention is relatively easy to operate and has high production efficiency, and the obtained straight-through joint has better insulation strength and waterproofness.
附图说明Description of drawings
图1:10kV至35kV电缆的结构示意图;Figure 1: Schematic diagram of the structure of a 10kV to 35kV cable;
图2:加热熔接内半导电层、绝缘层及外半导电层前的直通接头结构示意图;Figure 2: Schematic diagram of the straight-through joint structure before heating and welding the inner semiconducting layer, insulating layer and outer semiconducting layer;
图3:图2中A处的放大结构示意图;Figure 3: Schematic diagram of the enlarged structure at A in Figure 2;
图4:完成内护层修复后的直通接头结构示意图;Figure 4: Schematic diagram of the straight-through joint structure after the repair of the inner sheath is completed;
图5:接通钢铠层后的直通接头结构示意图;Figure 5: Schematic diagram of the straight-through joint structure after connecting the steel armor layer;
图6:完成外护层修复后的直通接头结构示意图;Figure 6: Schematic diagram of the through-joint structure after the repair of the outer sheath is completed;
图7:图6中B处的放大结构示意图。Figure 7: Schematic diagram of the enlarged structure at B in Figure 6.
其中:1-外护层、2-钢铠层、3-内护层、4-填充层、5-铜屏蔽层、6-外半导电层、7-绝缘层、8-内半导电层、9-线芯、10-热缩管、11-硅橡胶防尘套、12-内半导电修复层、13-绝缘修复层、14-外半导电修复层、15-铝箔、16-酰亚胺胶带、17-塑形模具、18-铜网、19-恒力弹簧、20-PVC绝缘胶带、21-防水胶带、22-环氧树脂防水胶水、23-铜编织带、24-填充胶带、25-铠装带。Among them: 1-outer sheath, 2-steel armor, 3-inner sheath, 4-filling layer, 5-copper shielding layer, 6-outer semiconducting layer, 7-insulating layer, 8-inner semiconducting layer, 9-wire core, 10-heat shrink tube, 11-silicone rubber dust cover, 12-inner semi-conductive repair layer, 13-insulation repair layer, 14-outer semi-conductive repair layer, 15-aluminum foil, 16-imide Adhesive tape, 17-shaping mold, 18-copper mesh, 19-constant force spring, 20-PVC insulating tape, 21-waterproof tape, 22-epoxy resin waterproof glue, 23-copper braided tape, 24-filling tape, 25 - Armored tape.
具体实施方式Detailed ways
下面结合附图和具体实施例对本发明所述10kV至35kV电缆工艺熔接式直通接头的制作方法作进一步说明,图1为10kV至35kV电缆的结构示意图。下文中某些地方为与修复材料相区分在原本就存在于电缆中的结构名称前加上了一个“原”字,比如“原外半导电层6”和“外半导电层6”指的是同一结构。The manufacturing method of the 10kV to 35kV cable process fusion type straight-through joint of the present invention will be further described below in conjunction with the accompanying drawings and specific examples. Figure 1 is a schematic structural diagram of a 10kV to 35kV cable. In some places below, the word "original" is added before the name of the structure that originally existed in the cable to distinguish it from the repair material, for example, "original outer semiconductive layer 6" and "outer semiconductive layer 6" refer to is the same structure.
实施例中使用的高频感应加热装置为上海聚豹机电科技有限公司生产的DD-25I型高频感应加热器;使用的加热筒由相关厂家按所需尺寸定制,并配备有智能温控箱和压力传感器;使用的防水胶带为3M公司的Scotch 2228型全天候专业级防水绝缘胶带;使用的填充胶带24为深圳市普瑞曼材料科技有限公司生产的电缆附件填充胶带。The high-frequency induction heating device used in the embodiment is the DD-25I high-frequency induction heater produced by Shanghai Jubao Electromechanical Technology Co., Ltd.; the heating cylinder used is customized by the relevant manufacturer according to the required size, and is equipped with an intelligent temperature control box and pressure sensor; the waterproof tape used is Scotch 2228 type all-weather professional grade waterproof insulating tape of 3M Company; the filling tape 24 used is the cable accessory filling tape produced by Shenzhen Priman Material Technology Co., Ltd.
实施例1Example 1
一种10kV至35kV电缆工艺熔接式直通接头的制作方法,包括下列步骤:A method for manufacturing a 10kV to 35kV cable process fusion type straight-through joint, comprising the following steps:
1)电缆外层的切剥:在两条电缆的对接端分别沿径向锯出两个断口,两根电缆分别自电缆断口处向内剥除1000mm及800mm的外护层1。自外护层1断口处向外量取50mm钢铠层2予以保留,其余剥除。最后自外护层1断口处向外量取100mm内护层3予以保留,其余剥除。切除外露的填充层4并用PVC胶带包缠钢铠层2的端部防止氧化。1) Cutting and stripping of the outer layer of the cable: saw two fractures in the radial direction at the butt ends of the two cables, and peel off the outer sheath 1 of 1000mm and 800mm inwards from the cable fractures of the two cables respectively. Measure 50mm outward from the fracture of the outer sheath 1 to keep the steel armor 2, and strip off the rest. Finally, measure 100mm of the inner sheath 3 outward from the fracture of the outer sheath 1 and keep it, and peel off the rest. Cut off the exposed filling layer 4 and wrap the end of the steel armor layer 2 with PVC tape to prevent oxidation.
2)芯缆的切剥及精修:自电缆断口处向内剥除300mm的铜屏蔽层5、200mm的外半导电层6、75mm的绝缘层7及60mm的内半导电层8使线芯9暴露,并以PVC胶带包缠铜屏蔽层5端部以防松散。将外半导电层6及内半导电层8的端部削成平滑过渡的斜坡状并用600目砂带打磨平滑,将绝缘层7的端部削成铅笔头状,再用800#砂纸打磨平滑并洗净吹干。用600目砂带去除外露的内半导电层8表面的绝缘残留并抛光表面,再将外露的外半导电层6、绝缘层7和内半导电层8以聚四氟乙烯胶带反方向缠包两层进行隔热保护。用240目砂带打磨去除外露的线芯9表面及断口处的氧化层并用PVC胶带包缠封闭。2) Cutting, stripping and finishing of the core cable: Strip 300mm of copper shielding layer 5, 200mm of outer semiconducting layer 6, 75mm of insulating layer 7 and 60mm of inner semiconducting layer 8 from the cable fracture inward to make the wire core 9 is exposed, and the end of the copper shielding layer 5 is wrapped with PVC tape to prevent loosening. Shave the ends of the outer semiconductive layer 6 and the inner semiconductive layer 8 into a smooth transitional slope and smooth them with a 600-mesh abrasive belt, and cut the ends of the insulating layer 7 into pencil heads, and then smooth them with 800# sandpaper And rinse and blow dry. Use a 600-mesh abrasive belt to remove the insulation residue on the surface of the exposed inner semiconductive layer 8 and polish the surface, then wrap the exposed outer semiconductive layer 6, insulating layer 7 and inner semiconductive layer 8 with polytetrafluoroethylene tape in the opposite direction Two layers for thermal protection. Use a 240-mesh abrasive belt to remove the exposed oxide layer on the surface of the core 9 and the fracture, and wrap and seal it with PVC tape.
3)管材的预设:在电缆上套上两根热缩管10,并在电缆内部的三根芯缆上各套上一个硅橡胶防尘套11。3) Presetting of pipe materials: Put two heat-shrinkable tubes 10 on the cable, and put a silicon rubber dustproof cover 11 on each of the three core cables inside the cable.
4)线芯的焊接:去除线芯9外的PVC胶带,对线芯9进行校直及加热除湿处理后插入焊接模具固定,箱焊接模具内填充与线芯9材质相同的金属粉末进行放热焊接,随后将焊接处打磨至与原电缆线芯9等径。4) Welding of the wire core: remove the PVC tape outside the wire core 9, straighten the wire core 9, heat and dehumidify it, insert it into a welding mold to fix it, and fill the metal powder of the same material as the wire core 9 in the box welding mold to release heat Welding, and then the welding place is ground to the same diameter as the original cable core 9.
5)带材的包缠:去除包缠于外半导电层6、绝缘层7和内半导电层8外的聚四氟乙烯耐高温胶带,采用与内半导电层8材质相同的带材紧密包缠线芯9及原内半导电层8形成表面高出原内半导电层8不超过1mm且两端盖过原内半导电层8的斜坡状端部的内半导电修复层12;采用与绝缘层7相同的带材(具体为交联聚乙烯材质)紧密包缠内半导电修复层12、原内半导电层8及原绝缘层7形成表面高出原绝缘层7表面5mm且两端与原绝缘层7平滑过渡的绝缘修复层13,绝缘修复层13的两端盖过原绝缘层7铅笔头状的端部;采用与外半导电层6材质相同的带材紧密包缠绝缘修复层13、原绝缘层7及原外半导电层6表面形成厚度与原外半导电层6相同的外半导电修复层14,外半导电修复层14的两端盖过原外半导电层6斜坡状的端部。5) Wrapping of strips: Remove the polytetrafluoroethylene high-temperature-resistant tape wrapped around the outer semiconductive layer 6, the insulating layer 7 and the inner semiconductive layer 8, and use the same strip material as the inner semiconductive layer 8 to tightly Wrap the wire core 9 and the original inner semiconductive layer 8 to form an inner semiconductive repair layer 12 whose surface is no more than 1 mm higher than the original inner semiconductive layer 8 and whose two ends cover the slope-shaped end of the original inner semiconductive layer 8; The same tape as the insulating layer 7 (specifically cross-linked polyethylene material) tightly wraps the inner semiconducting repair layer 12, the original inner semiconducting layer 8 and the original insulating layer 7 to form a surface that is 5mm higher than the surface of the original insulating layer 7 and two The insulating repair layer 13 with a smooth transition between the end and the original insulating layer 7, the two ends of the insulating repairing layer 13 cover the pencil-shaped end of the original insulating layer 7; use the same material as the outer semiconducting layer 6 to tightly wrap the insulation The repair layer 13, the original insulating layer 7 and the original outer semiconductive layer 6 surface form the outer semiconductive repair layer 14 with the same thickness as the original outer semiconductive layer 6, and the two ends of the outer semiconductive repair layer 14 cover the original outer semiconductive layer 6 sloped ends.
6)内半导电层、绝缘层及外半导电层的熔接恢复:将硅橡胶防尘套11移至外半导修复层14处,完整包覆并紧裹外半导修复层14,在硅橡胶防尘套11外包裹一层铝箔15并以酰亚胺胶带16包缠固定,再以塑形模具17锁紧固定(如图2、3所示),之后置于加热筒中加热以熔合构成外半导电修复层14、绝缘修复层13及内半导电层8的带材,采用高频感应加热装置加热靠近加热筒两端的芯缆段使外半导电修复层14与原外半导电层6、绝缘修复层13与原修复层7、内半导电修复层12与原内半导电层8融为一体,结束加热时塑形模具内的压力不低于1.8MPa。6) Fusion recovery of the inner semiconductive layer, insulating layer and outer semiconductive layer: move the silicone rubber dust cover 11 to the outer semiconductive repair layer 14, completely cover and tightly wrap the outer semiconductive repair layer 14, The rubber dust jacket 11 is wrapped with a layer of aluminum foil 15 and wrapped and fixed with imide tape 16, and then locked and fixed with a molding mold 17 (as shown in Figures 2 and 3), and then placed in a heating cylinder to heat to form a fusion The outer semiconductive repair layer 14, the insulation repair layer 13 and the strip of the inner semiconductive layer 8 adopt a high-frequency induction heating device to heat the core cable sections near the two ends of the heating cylinder to make the outer semiconductive repair layer 14 and the original outer semiconductive layer 6 1. The insulating repair layer 13 is integrated with the original repair layer 7, the inner semiconductive repair layer 12 is integrated with the original inner semiconductive layer 8, and the pressure in the shaping mold is not lower than 1.8MPa when the heating is finished.
加热筒的加热过程为:均匀升温20min至100℃并恒温8min,随后缓慢升温20min至185℃并恒温40min;加热筒升温至100℃以上后开启高频感应加热装置在380V电压下输出350A感应加热电流对靠近加热筒两端的芯缆段同步感应加热60min(即在加热筒由100℃缓慢升温至185℃的20min及加热筒在185℃恒温40min的这两个阶段同时对靠近加热筒两端的芯缆段进行加热)。The heating process of the heating cylinder is as follows: evenly increase the temperature for 20 minutes to 100°C and keep the temperature for 8 minutes, then slowly increase the temperature for 20 minutes to 185°C and keep the temperature for 40 minutes; after the heating cylinder is heated to above 100°C, turn on the high-frequency induction heating device and output 350A induction heating at 380V voltage The current inductively heats the core cable sections near both ends of the heating cylinder for 60 minutes (that is, the heating cylinder is heated slowly from 100°C to 185°C for 20 minutes and the heating cylinder is kept at 185°C for 40 minutes at the same time. Cable sections are heated).
7)铜屏蔽层的恢复:拆除加热筒、塑形模具17、酰亚胺胶带16、铝箔15及硅橡胶防尘套11,检查外半导电修复层14表面是否光滑,之后用铜网18分别包缠连接每根芯缆上的原铜屏蔽层5并以恒力弹簧19固定铜网两端,再以PVC绝缘胶带20将三根芯缆包缠捆绑为一体。7) Restoration of the copper shielding layer: remove the heating cylinder, plastic mold 17, imide tape 16, aluminum foil 15 and silicone rubber dust cover 11, check whether the surface of the outer semi-conductive repair layer 14 is smooth, and then use copper mesh 18 to separate The original copper shielding layer 5 on each core cable is wrapped and connected, and the two ends of the copper net are fixed with a constant force spring 19, and then the three core cables are wrapped and bound together with a PVC insulating tape 20.
8)内护层的恢复:如图4所示,以防水胶带21包缠在PVC绝缘胶带20外侧并连接两条电缆的原内护层3,包缠时需将防水胶带21百分百拉伸并半搭接缠绕三层,随后将环氧树脂防水胶水22均匀涂抹在防水胶带21表面并套以一根热缩管10,均匀加热热缩管10使其充分收缩并以防水胶带21包封热缩管10的两端。8) Restoration of the inner sheath: As shown in Figure 4, wrap the original inner sheath 3 on the outside of the PVC insulating tape 20 with waterproof tape 21 and connect the two cables. Stretch and half-lap wound three layers, then apply epoxy resin waterproof glue 22 evenly on the surface of waterproof tape 21 and cover with a heat shrinkable tube 10, evenly heat the heat shrinkable tube 10 to make it fully shrink and wrap it with waterproof tape 21 Seal both ends of the heat shrink tube 10.
9)钢铠层的接通:如图5所示,去除包缠于原钢铠层2端部的PVC胶带并以240目砂带磨去表面的防锈漆,以两端与原钢铠层2搭接的铜编织带23包裹热缩管10并以恒力弹簧19固定铜编织带23两端,再以PVC绝缘胶带20包缠固定两恒力弹簧19以防发生松动。9) Connection of the steel armor layer: as shown in Figure 5, remove the PVC tape wrapped in the original steel armor layer 2 ends and grind off the antirust paint on the surface with a 240-mesh abrasive belt, and connect the two ends with the original steel armor layer Layer 2 overlapped copper braid 23 wraps the heat-shrinkable tube 10 and fixes both ends of the copper braid 23 with a constant force spring 19, then wraps and fixes the two constant force springs 19 with PVC insulating tape 20 to prevent loosening.
10)外护层的恢复:如图6、7所示,用600目砂带打磨两条电缆连接端长150mm的原外护层1表面并包缠填充胶带24,再以防水胶带21包缠接通后的钢铠层及两条电缆上缠有填充胶带24的外护层1,包缠时需将防水胶带21百分百拉伸并半搭接缠绕三层,随后用环氧树脂防水胶水22均匀涂抹在防水胶带21表面并套以另一根热缩管10,均匀加热热缩管10使其充分收缩并以防水胶带21包封热缩管10的两端,最后以铠装带25在热缩管10表面半搭接缠绕4层。10) Restoration of the outer sheath: As shown in Figures 6 and 7, use a 600-mesh abrasive belt to polish the surface of the original outer sheath 1 with a length of 150 mm at the connection ends of the two cables and wrap it with a filling tape 24, and then wrap it with a waterproof tape 21 After connecting the steel armor layer and the outer sheath 1 wrapped with filling tape 24 on the two cables, the waterproof tape 21 needs to be 100% stretched and half-lapped and wound three layers when wrapping, and then waterproofed with epoxy resin Glue 22 is evenly spread on the surface of waterproof tape 21 and covered with another heat-shrinkable tube 10, heat the heat-shrinkable tube 10 evenly to make it fully shrink and wrap both ends of the heat-shrinkable tube 10 with waterproof tape 21, and finally wrap the heat-shrinkable tube 10 with armor tape 25. Wrap 4 layers on the surface of the heat-shrinkable tubing 10 by half-lapping.
实施例2Example 2
一种10kV至35kV电缆工艺熔接式直通接头的制作方法,本实施例与实施例1所述方法除步骤5)和6)不同外其余步骤完全一致,具体表现在:A method for manufacturing a 10kV to 35kV electric cable process fusion splicing type straight-through joint, this embodiment is completely consistent with the method described in Embodiment 1 except for steps 5) and 6), and the other steps are exactly the same, specifically as follows:
步骤5)中绝缘修复层13表面高出原绝缘层7表面6mm,步骤6)中加热筒的加热过程为:均匀升温24min至100℃并恒温5min,随后缓慢升温25min至185℃并恒温46min;加热筒升温至100℃以上后开启高频感应加热装置在380V电压下输出350A感应加热电流对靠近加热筒两端的芯缆段感应加热71min。The surface of the insulating repair layer 13 in step 5) is 6 mm higher than the surface of the original insulating layer 7. The heating process of the heating cylinder in step 6) is: uniformly increase the temperature for 24 minutes to 100°C and keep the temperature for 5 minutes, then slowly increase the temperature for 25 minutes to 185°C and keep the temperature for 46 minutes; After the heating cylinder is heated to above 100°C, the high-frequency induction heating device is turned on, and an induction heating current of 350A is output at a voltage of 380V to inductively heat the core cable section near both ends of the heating cylinder for 71 minutes.
实施例3Example 3
一种10kV至35kV电缆工艺熔接式直通接头的制作方法,本实施例与实施例1所述方法除步骤5)和6)不同外其余步骤完全一致,具体表现在:A method for manufacturing a 10kV to 35kV electric cable process fusion splicing type straight-through joint, this embodiment is completely consistent with the method described in Embodiment 1 except for steps 5) and 6), and the other steps are exactly the same, specifically as follows:
步骤5)中绝缘修复层13表面高出原绝缘层7表面8mm,步骤6)中加热筒的加热过程为:均匀升温30min至100℃并恒温10min,随后缓慢升温15min至185℃并恒温50min;加热筒升温至100℃以上后开启高频感应加热装置在380V电压下输出350A感应加热电流对靠近加热筒两端的芯缆段感应加热65min。The surface of the insulating repair layer 13 in step 5) is 8 mm higher than the surface of the original insulating layer 7. The heating process of the heating cylinder in step 6) is: uniformly increase the temperature for 30 minutes to 100°C and keep the temperature for 10 minutes, then slowly increase the temperature for 15 minutes to 185°C and keep the temperature for 50 minutes; After the heating cylinder is heated to above 100°C, the high-frequency induction heating device is turned on, and an induction heating current of 350A is output at a voltage of 380V to inductively heat the core cable section near both ends of the heating cylinder for 65 minutes.
国家智能电网输配电设备质量监督检验中心(广东)对按照3个实施例所述方法制作出的10kV至35kV电缆工艺熔接式直通接头依据GB/T 12706.4-2008《额定电压1kV(Um=1.2kV)到35kV(Um=40.5kV)挤包绝缘电力电缆及附件第4部分:额定电压6kV(Um=7.2kV)到35kV(Um=40.5kV)电力电缆附件试验要求》规定的方法进行检测,检验项目及结果见表1。由表1可以看出,所检试验项目均符合要求,表明按本发明所述方法制备的10kV至35kV电缆工艺熔接式直通接头的各项性能均达到国家标准。National Smart Grid Power Transmission and Distribution Equipment Quality Supervision and Inspection Center (Guangdong) is based on GB/T 12706.4-2008 "Rated Voltage 1kV (U m = 1.2kV) to 35kV (U m = 40.5kV) extruded insulated power cables and accessories Part 4: Rated voltage 6kV (U m = 7.2kV) to 35kV (U m = 40.5kV) power cable accessories test requirements "stipulations Methods for detection, test items and results are shown in Table 1. It can be seen from Table 1 that the tested test items all meet the requirements, indicating that the performances of the 10kV to 35kV cable technology fusion-type straight-through joints prepared by the method of the present invention all reach the national standard.
表1:检验项目及结果Table 1: Inspection items and results
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711172751.1A CN107994517B (en) | 2017-11-22 | 2017-11-22 | Manufacturing method of fusion-connection type straight-through joint for 10 kV-35 kV cable process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711172751.1A CN107994517B (en) | 2017-11-22 | 2017-11-22 | Manufacturing method of fusion-connection type straight-through joint for 10 kV-35 kV cable process |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107994517A CN107994517A (en) | 2018-05-04 |
CN107994517B true CN107994517B (en) | 2019-08-09 |
Family
ID=62031863
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711172751.1A Active CN107994517B (en) | 2017-11-22 | 2017-11-22 | Manufacturing method of fusion-connection type straight-through joint for 10 kV-35 kV cable process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107994517B (en) |
Families Citing this family (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10723064B2 (en) | 2018-10-11 | 2020-07-28 | Nvent Services Gmbh | Device and methods for armoring heat shrink kits for impact and flammability protection |
CN109256743A (en) * | 2018-10-22 | 2019-01-22 | 深圳市沃尔核材股份有限公司 | A kind of cable intermediate joint and attaching method thereof |
CN109064828A (en) * | 2018-11-05 | 2018-12-21 | 广东电网有限责任公司教育培训评价中心 | A kind of T production training apparatus of 10KV cable based on augmented reality |
CN109616847A (en) * | 2018-12-14 | 2019-04-12 | 中复碳芯电缆科技有限公司 | A kind of manufacturing method of lightning-protective cable connector |
CN109616962A (en) * | 2018-12-21 | 2019-04-12 | 吴江市华鼎热缩制品有限公司 | A kind of hot melten type cable centre connection mounting process |
CN109818161A (en) * | 2019-01-14 | 2019-05-28 | 和瑞达(广州)电力服务有限公司 | A kind of recovery 10kV and 27.5kV cable body melt connection method |
CN109818227A (en) * | 2019-03-15 | 2019-05-28 | 炜达科技股份有限公司 | A kind of quick connecting method applied to cable |
CN110034424B (en) * | 2019-03-26 | 2021-06-15 | 武汉船用机械有限责任公司 | Cable connection assembly and cable connection assembly using method |
CN111987495A (en) * | 2019-05-23 | 2020-11-24 | 广东昊阳电力建设有限公司 | Cable mold injection welding type straight joint |
CN111082278A (en) * | 2019-07-22 | 2020-04-28 | 宁波中缆电力科技有限公司 | Manufacturing process and structure of power cable T-shaped intermediate joint |
CN110932049A (en) * | 2019-11-15 | 2020-03-27 | 东莞市输变电工程公司 | Combustion connection method for cable |
CN112038790B (en) * | 2020-08-05 | 2021-08-06 | 瑞邦电力科技有限公司 | Prefabricated fusion-spliced cable insulation joint and manufacturing method thereof |
CN112271657B (en) * | 2020-11-04 | 2022-10-28 | 南方电网科学研究院有限责任公司 | Polypropylene 10kV molded cable joint and manufacturing method thereof |
CN112826390A (en) * | 2020-12-18 | 2021-05-25 | 杭州巍云科技有限公司 | Special robots, composite cables for special robots and cable processing technology |
CN113744932A (en) * | 2021-09-08 | 2021-12-03 | 黄石市深博电气有限公司 | Process method for recovering welding type cable outer semi-conductive layer |
CN114069495A (en) * | 2021-10-11 | 2022-02-18 | 岭澳核电有限公司 | Cable Field Repair Method |
CN113690808B (en) * | 2021-10-25 | 2022-02-22 | 国网天津市电力公司电力科学研究院 | Outer sheath breaking and repairing method used in repair of high-voltage cable buffer layer |
CN114094423B (en) * | 2021-11-05 | 2022-08-16 | 瑞邦电力科技有限公司 | Manufacturing process of straight-through joint of crosslinked cable |
CN114566312A (en) * | 2022-03-22 | 2022-05-31 | 南方电网科学研究院有限责任公司 | Polypropylene cable and insulating layer repairing method and application thereof |
CN116435925A (en) * | 2023-04-06 | 2023-07-14 | 广东安诺新材料科技有限公司 | Manufacturing method of waterproof cable joint |
CN117240018B (en) * | 2023-11-14 | 2024-03-08 | 天津普友机电设备股份有限公司 | Joint process of stator winding wire and power cable of submersible motor |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100578689C (en) * | 2005-08-12 | 2010-01-06 | 3M创新有限公司 | Self-welding insulation clad band |
CN201655984U (en) * | 2010-04-12 | 2010-11-24 | 上海机场(集团)有限公司 | Primary cable joint of light |
CN105845261B (en) * | 2016-06-13 | 2017-11-10 | 湖北华特红旗电缆有限公司 | Twisted polyethylene cable and its restorative procedure are pressed in one kind |
-
2017
- 2017-11-22 CN CN201711172751.1A patent/CN107994517B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN107994517A (en) | 2018-05-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107994517B (en) | Manufacturing method of fusion-connection type straight-through joint for 10 kV-35 kV cable process | |
CN106451313B (en) | A kind of DC ultra-high-voltage crosslinked cable connecting hose and manufacture craft | |
CN102709866B (en) | The crosslinked polyetylene insulated stress cone cable terminal of middle pressure and restorative procedure | |
CN109616962A (en) | A kind of hot melten type cable centre connection mounting process | |
CN203367959U (en) | A cable intermediate connector | |
CN110350376B (en) | Cross-linked polyethylene power cable intermediate connection joint and manufacturing method thereof | |
CN206272207U (en) | A kind of DC ultra-high-voltage crosslinked cable connecting hose | |
CN105281260A (en) | 35kV heat shrink power cable intermediate connector manufacturing technology method | |
CN112271657B (en) | Polypropylene 10kV molded cable joint and manufacturing method thereof | |
CN102611067B (en) | High-voltage cable flexible joint with non-linear shielding layers | |
CN103117117A (en) | Insulation tube bus and manufacturing method thereof | |
CN2874880Y (en) | Middle joint welding fitting for 66KV-500KV crosslink polyvinyl insulation power cable | |
CN105552791A (en) | Method for making 10KV heat-shrinkable three-core cross-linked polyethylene cable intermediate joint | |
CN109216966A (en) | A kind of recovery cable body structure jointing and its method | |
CN113270224B (en) | High-voltage-resistant superconducting cable potential detection wire insulation leading-out structure | |
CN113937589A (en) | A cable connection construction technology | |
CN209375031U (en) | A kind of hot melten type cable intermediate connection structure | |
CN208093772U (en) | A waterproof cable fusion joint | |
CN112787302A (en) | Wrapping and welding type intermediate joint for cables of 35KV and below and welding process | |
CN1734874B (en) | Equal diameter connector of power cable, and manufacturing process thereof | |
CN106384977B (en) | A kind of restorative procedure of twisted polyethylene cable single-phase fault | |
CN117080988A (en) | Manufacturing method of cold-shrink terminal end of three-core high-voltage crosslinked polyethylene insulated cable | |
CN108683119A (en) | A kind of 10kV power cables single-phase fault restorative procedure | |
CN207116729U (en) | A kind of reducing cable core joint | |
CN114360764A (en) | Manufacturing method of high-pressure submarine cable factory joint |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |