[go: up one dir, main page]

CN107916935A - A kind of soil body composite reinforcing structure and construction method of the existing subway of weak soil shield crossing - Google Patents

A kind of soil body composite reinforcing structure and construction method of the existing subway of weak soil shield crossing Download PDF

Info

Publication number
CN107916935A
CN107916935A CN201711116073.7A CN201711116073A CN107916935A CN 107916935 A CN107916935 A CN 107916935A CN 201711116073 A CN201711116073 A CN 201711116073A CN 107916935 A CN107916935 A CN 107916935A
Authority
CN
China
Prior art keywords
pipe
grouting
angle
pipe shed
shed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711116073.7A
Other languages
Chinese (zh)
Other versions
CN107916935B (en
Inventor
丁智
费豪
张霄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou City University
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201711116073.7A priority Critical patent/CN107916935B/en
Publication of CN107916935A publication Critical patent/CN107916935A/en
Application granted granted Critical
Publication of CN107916935B publication Critical patent/CN107916935B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明涉及一种软土盾构穿越既有地铁的土体复合加固结构,包括:盾构隧道轮廓线、可调角度管棚和水平旋喷桩;所述在待挖盾构隧道轮廓线外侧设有一排可调角度管棚,所述可调角度管棚包括管棚钢管,所述相邻管棚钢管之间设有水平旋喷桩,所述水平旋喷桩将可调角度管棚包裹并和相邻的水平旋喷桩咬合搭接;所述水平旋喷桩包括旋喷钻杆和钻杆外套,所述管棚钢管与旋喷钻杆之间相间连接。本发明的有益效果是:本发明联合使用可调角度管棚与水平旋喷,刚柔并济,软硬兼施,既充分发挥了各自的特点,又能很好的协同工作,取得了良好的整体支护效果,能很好的适应软土地区环境,加固土体,能很好的控制既有地铁的变形。

The invention relates to a soil composite reinforcement structure for a soft soil shield passing through an existing subway, comprising: a shield tunnel outline, an angle-adjustable pipe shed and a horizontal rotary grouting pile; There is a row of adjustable-angle pipe sheds, the adjustable-angle pipe sheds include pipe shed steel pipes, and horizontal jet grouting piles are arranged between the adjacent pipe shed steel pipes, and the horizontal jet grouting piles wrap the adjustable-angle pipe sheds The horizontal jet grouting piles are overlapped with the adjacent horizontal jet grouting piles; the horizontal jet jetting piles include jetting drill pipes and drill pipe casings, and the pipe shed steel pipes are connected alternately with the jet jetting drilling pipes. The beneficial effects of the present invention are: the present invention uses the adjustable angle pipe shed and the horizontal rotary spraying in combination, combining rigidity and softness, both soft and hard, not only giving full play to their respective characteristics, but also working well together, and achieving good overall support It can well adapt to the environment of soft soil areas, strengthen the soil, and can well control the deformation of the existing subway.

Description

一种软土盾构穿越既有地铁的土体复合加固结构及施工方法A Soil Composite Reinforcement Structure and Construction Method for Soft Soil Shield Crossing Existing Subway

技术领域technical field

本发明涉及软土区盾构穿越既有地铁的土体复合加固施工领域,具体涉及软土区盾构穿越既有地铁的土体复合加固结构及施工方法。The invention relates to the field of soil compound reinforcement construction in which a shield machine passes through an existing subway in a soft soil area, in particular to a soil compound reinforcement structure and a construction method for a shield machine to pass through an existing subway in a soft soil area.

背景技术Background technique

随着城市化进程的不断推进,城市地下轨道交通显得愈发重要,要建成完整的地铁网,就一定会存在着地铁线路的交汇。在地铁隧道盾构施工中,新建盾构隧道穿越既有运营地铁隧道的情况与日俱增。新建盾构隧道对已运营的地铁隧道会产生许多不利影响,诸如管片开裂,接头张开,螺栓失效,纵向不均匀沉降及水平位移过大等危害,特别是软土区既有隧道更易发生变形和管片破损,影响机车运行的舒适度,平整度,加剧列车磨损,严重将导致机车脱轨等重大事故。所以在穿越之前,需要对既有运营地铁范围内土体进行加固处理,加强既有地铁抵抗变形的能力,保证既有地铁的正常运营。With the continuous advancement of the urbanization process, urban underground rail transit is becoming more and more important. To build a complete subway network, there must be intersections of subway lines. In shield construction of subway tunnels, the number of new shield tunnels crossing existing subway tunnels is increasing day by day. Newly built shield tunnels will have many adverse effects on existing subway tunnels, such as segment cracking, joint opening, bolt failure, uneven longitudinal settlement, and excessive horizontal displacement, especially in existing tunnels in soft soil areas. Deformation and segment damage will affect the comfort and smoothness of the locomotive running, aggravate the wear and tear of the train, and seriously cause major accidents such as locomotive derailment. Therefore, before crossing, it is necessary to reinforce the soil within the scope of the existing subway to strengthen the ability of the existing subway to resist deformation and ensure the normal operation of the existing subway.

发明内容Contents of the invention

本发明的目的是克服现有技术中的不足,提供一种软土盾构穿越既有地铁的土体复合加固结构及施工方法。The purpose of the present invention is to overcome the deficiencies in the prior art, and provide a soil composite reinforcement structure and construction method for soft soil shield tunneling through the existing subway.

本发明的另一个目的是提供一种软土盾构穿越既有地铁的土体复合加固结构。本发明的目的是通过以下技术方案实现的:Another object of the present invention is to provide a soil composite reinforcement structure for soft soil shield tunneling through existing subways. The purpose of the present invention is achieved through the following technical solutions:

这种软土盾构穿越既有地铁的土体复合加固结构,包括:盾构隧道轮廓线、可调角度管棚和水平旋喷桩;所述在待挖盾构隧道轮廓线外侧设有一排可调角度管棚,所述可调角度管棚包括管棚钢管,所述相邻管棚钢管之间设有水平旋喷桩,所述水平旋喷桩将可调角度管棚包裹并和相邻的水平旋喷桩咬合搭接;所述水平旋喷桩包括旋喷钻杆和钻杆外套,所述管棚钢管与旋喷钻杆之间相间连接,所述管棚钢管外侧设有限位轨道,所述旋喷钻杆外表面设有钻杆外套,所述限位轨道与钻杆外套通过限位焊接形成整体拱壳。This kind of soft soil shield crosses the soil composite reinforcement structure of the existing subway, including: the outline of the shield tunnel, the adjustable angle pipe shed and the horizontal jet grouting pile; Adjustable angle pipe shed, said adjustable angle pipe shed includes pipe shed steel pipes, horizontal jet spray piles are arranged between said adjacent pipe shed steel pipes, said horizontal jet spray piles wrap the adjustable angle pipe sheds and The adjacent horizontal jet grouting piles are occluded and overlapped; the horizontal jet grouting piles include jet grouting drill pipes and drill pipe jackets, the pipe shed steel pipes are connected alternately with the jet grouting drill pipes, and the outer side of the pipe shed steel pipes is provided with a limit track, the outer surface of the jet-jet drill pipe is provided with a drill pipe jacket, and the limit rail and the drill pipe jacket form an integral arch shell through limit welding.

作为优选:所述可调角度管棚沿隧道纵向延伸方向由后向前分多个节段。As a preference: the angle-adjustable pipe shed is divided into multiple sections from back to front along the longitudinal extension direction of the tunnel.

作为优选:所述管棚钢管使用热扎无缝钢管,管棚钢管两端均预加工成外丝扣。As a preference: the pipe shed steel pipe is made of hot-rolled seamless steel pipe, and both ends of the pipe shed steel pipe are pre-processed into external threaded buckles.

作为优选:通过盾构隧道的圆心作既有地铁隧道的两条切线,两条切线所夹角度为α,通过盾构隧道的圆心与可调角度管棚8两边缘所成角度为β,β=2α。As a preference: through the center of the shield tunnel to make two tangents of the existing subway tunnel, the angle between the two tangents is α, and the angle formed by the center of the shield tunnel and the two edges of the adjustable angle pipe shed 8 is β, β = 2α.

一种软土盾构穿越既有地铁的土体复合加固结构的施工方法,包括以下步骤:A construction method for a soft soil shield passing through an existing subway soil composite reinforcement structure, comprising the following steps:

S1、螺旋出土可调角度管棚拱顶支护;S1. Spiral unearthed adjustable angle pipe shed arch support;

S1.1、搭设钻孔平台,水平旋喷施工共用平台;S1.1. Set up a drilling platform and a shared platform for horizontal rotary spraying construction;

S1.2、安装钻机,可调角度管棚施工完毕后,钻机继续进行水平旋喷施工;S1.2. Install the drilling rig. After the construction of the adjustable angle pipe shed is completed, the drilling rig continues to carry out the horizontal rotary spraying construction;

S1.3、破除掌子面和地层入口段的素混凝土障碍物:掌子面结构墙采用高速水钻按设计位置开孔,开孔角度按照可调角度管棚设计施工角度钻进;采用潜孔锤沿掌子面开孔钻进破碎地层入口段的素混凝土障碍物;S1.3. Remove the plain concrete obstacles on the tunnel surface and the entrance section of the formation: the structural wall of the tunnel surface uses high-speed water drilling to drill holes according to the design position, and the opening angle is drilled according to the design and construction angle of the adjustable angle pipe shed; the submerged hole is used The hammer drills into the plain concrete barrier at the entrance section of the broken formation along the face opening;

S1.4、将螺旋出土钻具穿入加工好的管棚钢管内,管棚钢管两端公母丝扣,螺旋钻具端头安装扩孔螺旋钻楔形钻头,钻具内部安装角度探测仪器;S1.4. Insert the auger unearthed drilling tool into the processed pipe shed steel pipe, male and female threaded fasteners at both ends of the pipe shed steel pipe, install a reaming auger wedge drill bit at the end of the auger drilling tool, and install an angle detection instrument inside the drilling tool;

S1.5、管棚钢管顶进前先检查钻机机械状况和仪器工作状态;钻机就位施钻时,钻机与掌子面固定;管棚钢管顶进土层后启动钻机旋转,测量入土管棚钢管角度变化;S1.5. Check the mechanical condition of the drilling rig and the working status of the instrument before jacking the steel pipe in the pipe shed; when the rig is in place for drilling, the rig is fixed to the face of the operation; after the steel pipe in the pipe shed is jacked into the soil layer, start the rig to rotate and measure the pipe shed into the soil Steel pipe angle change;

S1.6、第一根管棚钢管顶进结束后,拆卸钻机与可调角度管棚接头,沿导轨退回原位,人工装入第二根管棚钢管,管棚钢管内安装螺旋钻,与第一根管棚钢管进行扣连接成一体,顶进旋转出土;S1.6. After the jacking of the first pipe shed steel pipe is completed, disassemble the drilling rig and the angle-adjustable pipe shed joint, return to the original position along the guide rail, manually install the second pipe shed steel pipe, install the auger in the pipe shed steel pipe, and The first pipe shed steel pipe is buckled and connected into one, jacking and rotating to unearth;

S1.7、当管棚钢管角度发生倾角偏差时,启动纠偏程序,停止钻具旋转,按设计方法操作顶进管棚钢管:管棚钢管向上偏差,降低管棚钢管倾角,向下调节螺旋钻楔形钻头角度位置;管棚钢管向下偏差,向上调整管棚钢管倾角,向上调节螺旋钻楔形钻头角度位置;管棚钢管向左右偏斜时,参照倾角调整方法将楔形板调整纠偏方位,顶进管棚钢管进行纠偏作业;S1.7. When the inclination deviation occurs in the angle of the steel pipe in the pipe shed, start the deviation correction program, stop the rotation of the drilling tool, and operate the jacking of the steel pipe in the pipe shed according to the design method: the steel pipe in the pipe shed deviates upwards, reduce the inclination of the steel pipe in the shed, and adjust the auger downward The angle position of the wedge drill bit; the downward deviation of the pipe shed steel pipe, adjust the inclination angle of the pipe shed steel pipe upward, and adjust the angle position of the auger wedge drill bit upward; The steel pipe of the pipe shed is corrected;

S1.8、施工中的管棚钢管在安装前必须逐孔逐根进行编号,按编号顺序接管顶进;S1.8. The steel pipes under construction must be numbered hole by hole and root by root before installation, and the pipes are jacked in the order of numbering;

S1.9、可调角度管棚注浆:注浆前先检查管路和机械状况,确认正常后做压浆实验,确定合理的注浆参数;注浆过程中随时检查孔口、邻孔、覆盖层较薄部位有无串浆现象;注浆过程派专人负责,记录注浆时间、浆液消耗量及注浆压力等数据;注浆结束后对泵及管路进行清孔,完成可调角度管棚的施工工艺;S1.9, Adjustable angle pipe shed grouting: check the pipeline and mechanical conditions before grouting, do a grouting test after confirming that it is normal, and determine reasonable grouting parameters; check the orifice, adjacent holes, Whether there is grouting in the thinner part of the covering layer; send a special person to be responsible for the grouting process, record the grouting time, grout consumption and grouting pressure and other data; after the grouting, clean the pump and pipeline to complete the adjustable angle The construction technology of the pipe shed;

S2、水平旋喷注浆土体加固改良;S2, horizontal jet grouting soil reinforcement and improvement;

S2.1、安装旋喷钻具和限位轨道;S2.1. Install the rotary spray drilling tool and the limit rail;

S2.2、钻进:开孔,配制循环浆液,钻孔打设;S2.2. Drilling: opening holes, preparing circulating slurry, and drilling;

S2.3、高压旋喷:检查高压注浆泵,泵压达到设计要求时开始喷浆;喷浆前检查钻机具的密封性,加压达到设计值后喷浆;在高压喷浆安排专人操作和观察泵压变化;钻杆旋喷至设计终孔位置停止注浆,并用清水高压冲洗干净管路;S2.3. High-pressure rotary grouting: Check the high-pressure grouting pump, and start grouting when the pump pressure meets the design requirements; check the sealing of the drilling rig before grouting, and spray grouting after the pressure reaches the design value; arrange special personnel to operate the high-pressure grouting and observe the change of pump pressure; the drill pipe is sprayed to the design end hole position to stop grouting, and the pipeline is washed with clean water under high pressure;

S2.4、封孔:喷浆至设计终孔位置后,停止喷浆,拔出钻杆和钻头,采用编织袋或者棉丝进行孔口封堵;S2.4. Hole sealing: After spraying grout to the designed final hole position, stop spraying, pull out the drill pipe and drill bit, and use woven bags or cotton silk to seal the hole;

S2.5、清洗管道及设备,完成水平旋喷的施工工艺。S2.5. Clean the pipeline and equipment, and complete the construction process of horizontal rotary spraying.

本发明的有益效果是:本发明联合使用可调角度管棚与水平旋喷,刚柔并济,软硬兼施,既充分发挥了各自的特点,又能很好的协同工作,取得了良好的整体支护效果,能很好的适应软土地区环境,加固土体,能很好的控制既有地铁的变形。The beneficial effects of the present invention are: the present invention uses the adjustable angle pipe shed and the horizontal rotary spraying in combination, combining rigidity and softness, both soft and hard, not only giving full play to their respective characteristics, but also working well together, and achieving good overall support It can well adapt to the environment of soft soil areas, strengthen the soil, and can well control the deformation of the existing subway.

附图说明Description of drawings

图1为螺旋出土可调角度管棚施工工艺流程图;Fig. 1 is the construction process flow chart of spiral unearthed adjustable angle pipe shed;

图2为水平旋喷施工工艺流程图;Figure 2 is a flow chart of the horizontal rotary spraying construction process;

图3为杭州地铁2号线下穿1号线平面图;Figure 3 is a plan view of Hangzhou Metro Line 2 passing through Line 1;

图4为可调角度管棚施工布置图;Figure 4 is a construction layout diagram of the adjustable angle pipe shed;

图5为水平旋喷桩与可调角度管棚布置图;Figure 5 is a layout diagram of the horizontal jet grouting pile and the adjustable angle pipe shed;

图6为钢管向上偏差时楔形钻头方向示意图;Fig. 6 is a schematic diagram of the direction of the wedge-shaped drill bit when the steel pipe deviates upward;

图7为钢管向下偏差时楔形钻头方向示意图;Fig. 7 is a schematic diagram of the direction of the wedge-shaped drill bit when the steel pipe is deflected downward;

图8为钢管角度正常时楔形钻头位置示意图;Figure 8 is a schematic diagram of the position of the wedge-shaped drill bit when the angle of the steel pipe is normal;

图9为水平旋喷施工布置图;Fig. 9 is a construction layout diagram of horizontal rotary spraying;

附图标记说明:杭州地铁2号线下行线1、杭州地铁2号线上行线2、杭州地铁1号线上行线3、杭州地铁1号线下行线4、杭州地铁2号线凤起路站5、杭州地铁1号线凤起路站6、盾构隧道轮廓线7、可调角度管棚8、水平旋喷桩9、掌子面10、螺旋钻楔形钻头11、管棚钢管12、限位焊接13、旋喷钻杆14、钻杆外套15、限位轨道16。Explanation of Reference Signs: Downlink Line 1 of Hangzhou Metro Line 2, Uplink Line 2 of Hangzhou Metro Line 2, Uplink Line 3 of Hangzhou Metro Line 1, Downlink Line 4 of Hangzhou Metro Line 1, Fengqi Road Station of Hangzhou Metro Line 2 5. Fengqi Road Station of Hangzhou Metro Line 1 6. Shield tunnel outline 7. Angle-adjustable pipe shed 8. Horizontal rotary grouting pile 9. Face 10. Spiral drill wedge bit 11. Pipe shed steel pipe 12. Position welding 13, rotary spraying drill pipe 14, drill pipe jacket 15, limit rail 16.

具体实施方式Detailed ways

下面结合实施例对本发明做进一步描述。下述实施例的说明只是用于帮助理解本发明。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以对本发明进行若干改进和修饰,这些改进和修饰也落入本发明权利要求的保护范围内。The present invention will be further described below in conjunction with the examples. The description of the following examples is provided only to aid the understanding of the present invention. It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, some improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the protection scope of the claims of the present invention.

如图1至图9所示,所述的软土盾构穿越既有地铁的土体复合加固结构能够有效的控制既有地铁的沉降和管片损坏,从而使盾构顺利推进。所述软土盾构穿越既有地铁的土体复合加固结构包括:杭州地铁2号线下行线1、杭州地铁2号线上行线2、杭州地铁1号线上行线3、杭州地铁1号线下行线4、杭州地铁2号线凤起路站5、杭州地铁1号线凤起路站6、盾构隧道轮廓线7、可调角度管棚8、水平旋喷桩9、掌子面10、螺旋钻楔形钻头11、管棚钢管12、限位焊接13、旋喷钻杆14、钻杆外套15和限位轨道16。As shown in Figures 1 to 9, the soft soil shield passing through the soil composite reinforcement structure of the existing subway can effectively control the settlement and segment damage of the existing subway, thereby enabling the shield to advance smoothly. The soil composite reinforcement structure of the soft soil shield passing through the existing subway includes: Hangzhou Metro Line 2 Down Line 1, Hangzhou Metro Line 2 Up Line 2, Hangzhou Metro Line 1 Up Line 3, Hangzhou Metro Line 1 Downline 4, Hangzhou Metro Line 2 Fengqi Road Station 5, Hangzhou Metro Line 1 Fengqi Road Station 6, shield tunnel contour line 7, angle-adjustable pipe shed 8, horizontal jet spray pile 9, tunnel face 10 , Spiral drill wedge-shaped drill bit 11, pipe shed steel pipe 12, limit welding 13, rotary spraying drill pipe 14, drill pipe jacket 15 and limit track 16.

如图3所示,所述杭州地铁2号线凤起路站5处的杭州地铁2号线下行线1和杭州地铁2号线上行线2穿越杭州地铁1号线凤起路站6处的杭州地铁1号线上行线3和杭州地铁1号线下行线4。如图4所示,在新建盾构隧道2号线下穿既有地铁隧道1号线中,所述在待挖盾构隧道轮廓线7外侧设置一排超前支护可调角度管棚8,沿隧道纵向延伸方向由后向前分多个节段对盾构穿越既有地铁土体进行可调角度管棚8超前支护施工,多个节段的可调角度管棚8超前支护施工方法均相同。如图5、9所示,所述可调角度管棚8包括管棚钢管12,所述相邻管棚钢管12之间设有水平旋喷桩9,所述水平旋喷桩9将可调角度管棚8包裹并和相邻的水平旋喷桩9咬合搭接,形成具有较高承载和帷幕隔断效果的支护结构,共同承载外部负荷。相邻水平旋喷桩9的间距为300mm,相邻水平旋喷桩9相互咬合200mm,水平旋喷桩9直径为500mm,单根施工长度为45m。如图9所示,所述水平旋喷桩9包括旋喷钻杆14和钻杆外套15,所述管棚钢管12与旋喷钻杆14之间相间连接,所述管棚钢管12外侧设有限位轨道16,所述旋喷钻杆14外表面设有钻杆外套15,所述限位轨道16与钻杆外套15通过限位焊接13形成整体拱壳。所述管棚钢管12使用热扎无缝钢管,外径159mm,壁厚8mm,每节钢管长度6m,两端均预加工成外丝扣。所述可调角度管棚8与水平旋喷桩9共同作用加固土体,达到防止既有地铁产生沉降或其他破坏的目的。As shown in Figure 3, the downlink 1 of Hangzhou Metro Line 2 at Fengqi Road Station 5 of Hangzhou Metro Line 2 and the uplink 2 of Hangzhou Metro Line 2 pass through Fengqi Road Station 6 of Hangzhou Metro Line 1. Line 3 of Hangzhou Metro Line 1 and Line 4 of Hangzhou Metro Line 1. As shown in Figure 4, in the new shield tunnel No. 2 line passing under the existing subway tunnel No. 1 line, a row of advanced support adjustable angle pipe sheds 8 is set outside the contour line 7 of the shield tunnel to be excavated. Along the longitudinal extension direction of the tunnel, it is divided into multiple sections from the back to the front to carry out the adjustable angle pipe shed 8 advance support construction for the shield tunneling through the existing subway soil, and the adjustable angle pipe shed 8 advance support construction of multiple sections The methods are the same. As shown in Figures 5 and 9, the adjustable-angle pipe shed 8 includes pipe shed steel pipes 12, and horizontal jet grouting piles 9 are arranged between said adjacent pipe shed steel pipes 12, and said horizontal jet grouting piles 9 will be adjustable The angled pipe shed 8 is wrapped and overlapped with the adjacent horizontal jet grouting pile 9 to form a support structure with high load bearing and curtain partition effect, and jointly bear the external load. The distance between adjacent horizontal jet grouting piles 9 is 300mm, the adjacent horizontal jet grouting piles 9 interlock each other by 200mm, the diameter of horizontal jet grouting piles 9 is 500mm, and the single construction length is 45m. As shown in Figure 9, the horizontal jet grouting pile 9 includes a jet grouting drill pipe 14 and a drill pipe jacket 15. There is a limiting track 16, and the outer surface of the jet-jet drill pipe 14 is provided with a drill pipe jacket 15, and the limiting rail 16 and the drill pipe jacket 15 form an integral arch shell through limiting welding 13. The pipe shed steel pipe 12 is made of hot-rolled seamless steel pipe with an outer diameter of 159mm and a wall thickness of 8mm. The length of each steel pipe is 6m, and both ends are pre-processed into outer threads. The angle-adjustable pipe shed 8 and the horizontal jet grouting pile 9 work together to reinforce the soil, so as to prevent the existing subway from subsidence or other damages.

所述软土区盾构隧道穿越既有地铁隧道中,两隧道外边缘之间的净距小于(等于)12m的工况。所述可调角度管棚8施工的范围由两隧道外边缘之间的净距所决定,净距越大,所施工的范围越小,净距越小,所施工的范围越大。如图4、5所示,通过盾构隧道的圆心作既有地铁隧道的两条切线,形成一个角度α,所述可调角度管棚8所施工的范围角度为β,令β=2α,β就是可调角度管棚8所施工用的范围。The shield tunnel in the soft soil area passes through the existing subway tunnel, and the working condition that the clear distance between the outer edges of the two tunnels is less than (equal to) 12m. The construction range of the adjustable angle pipe shed 8 is determined by the clear distance between the outer edges of the two tunnels. The larger the clear distance, the smaller the construction scope, and the smaller the net distance, the larger the construction scope. As shown in Figures 4 and 5, two tangent lines of the existing subway tunnel are made through the center of the shield tunnel to form an angle α, and the angle of the construction range of the adjustable angle pipe shed 8 is β, so that β=2α, β is exactly the range that the angle-adjustable pipe shed 8 is used for construction.

新建杭州地铁2号线一期中河路站~凤起路站区间盾构下穿地铁1号线段采用“螺旋出土定向管棚为骨架,水平旋喷桩帷幕包裹隔断”的工艺,工程施工主要分为两部分:螺旋出土管棚拱顶支护、水平旋喷注浆土体加固改良。The first phase of the new Hangzhou Metro Line 2, Zhonghe Road Station to Fengqi Road Station, under the section of the No. It is divided into two parts: spiral unearthed pipe shed vault support, and horizontal jet grouting soil reinforcement and improvement.

(一)螺旋出土管棚拱顶支护(1) Spiral unearthed pipe shed vault support

“螺旋出土定向管棚”采用直径159mm管棚钢管12为外套管,管内安装螺旋钻具,安装测量探棒后的管棚钢管12用顶管钻机顶进入土,同时顺时针转动螺旋钻具,将进入管内的土体破碎输送出管外;当管棚钢管12角度发生偏转时,依据探棒测量和地表沉降监测利用钻具端部安装的楔形板进行角度修正。可调角度管棚8施工中,可调角度管棚8的打设要完全在导向仪器的监控下进行,且需要进行光学测量,保证可调角度管棚8不能侵入下方盾构且保持在设计范围内。水平旋喷桩9施工需在导向仪器的监控下进行,要保证一定的一致性从而形成拱形支护结构。管棚螺旋钻具内安装LED测量灯,通过经纬仪从管口测量LED灯点的标高和角度,配合探棒仪器测量数据,共同测算出管棚钢管12的轨迹。管棚钢管12使用热扎无缝钢管,外径159mm,壁厚8mm,每节管棚钢管12长度6m,两端均预加工成外丝扣,可调角度管棚8环向间距350mm,弧向布置25根,单根施工长度为45m,共1260m。外插角1.5%-2%,采用0.1%精度探棒测量,注浆材料为P.O42.5水泥,水灰比为0.8:1,注浆压力为0.5~1.0MPa。单根管棚钢管12的注浆量按下式估算:Q=πRk 2Lηξ,式中Rk为浆液扩散半径,取Rk=1.2r,r为钢管半径;L为钢管长;ξ取0.85,为注浆饱满系数;η为空隙率(%)。"Spiral unearthed directional pipe shed" uses pipe shed steel pipe 12 with a diameter of 159mm as the outer casing, and auger drilling tools are installed in the pipe. After installing the measurement probe, the pipe shed steel pipe 12 is pushed into the soil with a pipe jacking rig, and at the same time, the helical drilling tool is turned clockwise. The soil that enters the pipe is crushed and transported out of the pipe; when the angle of the steel pipe 12 of the pipe shed is deflected, the wedge plate installed at the end of the drilling tool is used to correct the angle according to the probe measurement and surface settlement monitoring. During the construction of the adjustable-angle pipe shed 8, the installation of the adjustable-angle pipe shed 8 must be carried out completely under the monitoring of the guiding instrument, and optical measurement must be carried out to ensure that the adjustable-angle pipe shed 8 cannot invade the shield below and remain in the designed position. within range. The construction of the horizontal jet grouting pile 9 needs to be carried out under the monitoring of guiding instruments, and a certain consistency must be ensured so as to form an arch support structure. The LED measuring light is installed in the auger tool of the pipe shed, and the elevation and angle of the LED light point are measured from the mouth of the pipe by the theodolite, and the trajectory of the steel pipe 12 of the pipe shed is jointly measured and calculated by cooperating with the measurement data of the probe instrument. The pipe shed steel pipe 12 is made of hot-rolled seamless steel pipe, with an outer diameter of 159mm and a wall thickness of 8mm. The length of each pipe shed steel pipe 12 is 6m. There are 25 vertically arranged, and the construction length of each single root is 45m, totaling 1260m. The extrapolation angle is 1.5%-2%, measured with a 0.1% precision probe, the grouting material is P.O42.5 cement, the water-cement ratio is 0.8:1, and the grouting pressure is 0.5-1.0MPa. The grouting amount of a single pipe shed steel pipe 12 is estimated by the following formula: Q=πR k 2 Lηξ, where R k is the slurry diffusion radius, R k =1.2r, r is the steel pipe radius; L is the steel pipe length; ξ is taken as 0.85 is the fullness coefficient of grouting; η is the void ratio (%).

1.可调角度管棚8的施工要点:1. Construction points of adjustable angle pipe shed 8:

(1)管棚钢管12不打设注浆小花眼,而在每米开4cm左右直径的注浆孔作注浆及水平旋喷的泄压孔之用;(1) The steel pipe 12 of the pipe shed does not have grouting florets, but a grouting hole with a diameter of about 4cm per meter is used as a pressure relief hole for grouting and horizontal rotary spraying;

(2)可调角度管棚8间隔跳孔施工,避免连续施工扰动范围过大;(2) The angle-adjustable pipe shed is constructed with 8 spaced jump holes to avoid excessive disturbance range of continuous construction;

(3)可调角度管棚8入口段因地层内含有素混凝土结构,先用潜孔锤破碎成孔,完成后送入管棚钢管12,采用螺旋出土施工工艺;(3) The entrance section of the angle-adjustable pipe shed 8 has a plain concrete structure in the strata, and it is first broken into holes with a down-the-hole hammer, and then sent to the pipe shed steel pipe 12 after completion, using a spiral excavation construction process;

(4)管内螺旋实际出土量应小于理论出土量,避免出土超量引起沉降;(4) The actual unearthed volume of the spiral inside the pipe should be less than the theoretical unearthed volume, so as to avoid settlement caused by excess unearthed;

(5)可调角度管棚8施工应根据监控量测数据进行计划或调整,无数据严禁施工。(5) The construction of the adjustable-angle pipe shed 8 should be planned or adjusted according to the monitoring and measurement data, and construction without data is strictly prohibited.

2.螺旋出土管棚施工工艺流程图如图1所示,具体实施如下:2. The construction process flow chart of the spiral unearthed pipe shed is shown in Figure 1, and the specific implementation is as follows:

(1)搭设钻孔平台,水平旋喷施工共用平台;(1) Set up a drilling platform and a shared platform for horizontal rotary spraying construction;

(2)安装钻机,可调角度管棚8施工完毕后,钻机继续进行水平旋喷施工;(2) The drilling rig is installed, and after the construction of the angle-adjustable pipe shed 8 is completed, the drilling rig continues to carry out the horizontal rotary spraying construction;

(3)破除掌子面10和地层入口段的素混凝土障碍物:(3) Get rid of plain concrete obstacles on the face 10 and the entry section of the formation:

①掌子面10结构墙采用高速水钻按设计位置开孔,孔直径180mm,开孔角度按照可调角度管棚8设计施工角度钻进;①The structural wall of the operation face 10 adopts high-speed water drill to open holes according to the design position, the hole diameter is 180mm, and the opening angle is drilled according to the design and construction angle of the adjustable angle pipe shed 8;

②距离掌子面10为6~10m地层内有素混凝土障碍物,采用Φ170mm潜孔锤沿掌子面10开孔钻进破碎。②There are plain concrete obstacles in the stratum 6-10m away from the face 10, and the Φ170mm down-the-hole hammer is used to drill and break along the opening of the face 10.

(4)将Φ138mm螺旋出土钻具穿入加工好的管棚钢管12内,管棚钢管12两端公母丝扣,螺旋钻具端头安装扩孔楔形钻头11,钻具内部安装角度探测仪器;(4) Put the Φ138mm helical unearthed drilling tool into the processed pipe shed steel pipe 12, the two ends of the pipe shed steel pipe 12 have male and female threads, install the reaming wedge drill bit 11 at the end of the helical drilling tool, and install the angle detection instrument inside the drill tool ;

(5)管棚钢管12顶进前前先检查钻机机械状况和仪器工作状态;(5) Check the mechanical status of the drilling rig and the working status of the instrument before the steel pipe 12 of the pipe shed is jacked;

(6)钻机就位施钻时,钻机与掌子面10固定,提高施工精度;管棚钢管12顶进土层内1m后启动钻机旋转,测量入土管棚钢管12角度变化;(6) When the drilling rig is in place for drilling, the drilling rig and the face 10 are fixed to improve the construction accuracy; after the pipe shed steel pipe 12 is pushed into the soil layer 1m, the rig is started to rotate, and the angle change of the pipe shed steel pipe 12 is measured;

(7)第一根管棚钢管12顶进结束后,拆卸钻机与可调角度管棚8接头,沿导轨退回原位,人工装入第二根管棚钢管12,管棚钢管12内安装螺旋钻,与第一根管棚钢管12进行扣连接成一体,顶进旋转出土;(7) After the jacking of the first pipe shed steel pipe 12 is completed, disassemble the joint between the drilling rig and the angle-adjustable pipe shed 8, return to the original position along the guide rail, and manually install the second pipe shed steel pipe 12, and install a screw in the pipe shed steel pipe 12. Drilling, buckled and connected with the first pipe shed steel pipe 12 to form a whole, jacking and rotating to unearth;

(8)当管棚钢管12角度发生倾角偏差时,当偏差超过设计值±0.5%,启动纠偏程序,停止钻具旋转,按设计方法操作顶进管棚钢管12:(8) When there is an inclination deviation in the angle of the steel pipe 12 in the pipe shed, when the deviation exceeds the design value ±0.5%, start the deviation correction program, stop the rotation of the drilling tool, and operate the jacking steel pipe 12 in the pipe shed according to the design method:

①管棚钢管12向上偏差,需要降低管棚钢管12倾角,向下调节螺旋钻楔形钻头11角度位置,如图6楔形钻头11所示方向。① The upward deviation of the pipe shed steel pipe 12 requires reducing the inclination angle of the pipe shed steel pipe 12 and adjusting the angular position of the auger wedge bit 11 downward, as shown in the direction of the wedge bit 11 in Fig. 6 .

②管棚钢管12向下偏差,需要向上调整管棚钢管12倾角,向上调节螺旋钻楔形钻头11角度位置,如图7楔形钻头11所示方向。② The downward deviation of the pipe shed steel pipe 12 requires upward adjustment of the inclination angle of the pipe shed steel pipe 12 and upward adjustment of the angular position of the auger wedge bit 11, as shown in the direction of the wedge bit 11 in FIG. 7 .

③管棚钢管12角度正常,无需调整,如图8所示。③ The angle of the steel pipe 12 in the pipe shed is normal and no adjustment is required, as shown in Figure 8.

④管棚钢管12向左右偏斜时,参照倾角调整方法,将楔形板调整纠偏方位,顶进管棚钢管12进行纠偏作业。④ When the steel pipe 12 of the pipe shed deviates to the left and right, refer to the inclination adjustment method, adjust the wedge-shaped plate to adjust the deviation correction position, and push the steel pipe 12 into the pipe shed to perform the deviation correction operation.

(9)施工中的管棚钢管12在安装前必须逐孔逐根进行编号,按编号顺序接管顶进;(9) The pipe shed steel pipes 12 under construction must be numbered hole by hole and root by root before installation, and take over and jack them in the order of numbering;

(10)可调角度管棚8注浆:(10) Adjustable angle pipe shed 8 grouting:

①注浆前先检查管路和机械状况,确认正常后做压浆实验,确定合理的注浆参数,方可以施工;① Check the pipeline and mechanical condition before grouting, and do a grouting test after confirming that it is normal, and determine the reasonable grouting parameters before construction can be carried out;

②注浆过程中随时检查孔口、邻孔、覆盖层较薄部位有无串浆现象,必要时采取加注水玻璃等速凝措施;注浆过程中压力如突然升高,可能发生堵管,应停机检查;② During the grouting process, check at any time whether there is any grouting at the orifice, adjacent holes, and the thinner parts of the covering layer, and take quick-setting measures such as adding water glass if necessary; if the pressure suddenly rises during the grouting process, pipe blockage may occur , should be stopped for inspection;

③注浆压力达到设计压力值;③The grouting pressure reaches the design pressure value;

④注浆过程应派专人负责,详细记录注浆时间、浆液消耗量及注浆压力等数据;④ The grouting process should be assigned special personnel to record in detail the grouting time, grout consumption and grouting pressure and other data;

⑤注浆结束后,对泵及管路进行清孔;⑤ After the grouting is finished, clean the holes of the pump and pipeline;

⑥注浆顺序:从下而上,跳孔注浆。⑥ Grouting sequence: from bottom to top, skip hole grouting.

(二)水平旋喷注浆土体加固改良(2) Improvement of horizontal jet grouting soil reinforcement

“水平旋喷桩帷幕包裹隔断”是指在相邻可调角度管棚8之间施工水平旋喷桩9,利用水泥浆液的超高压力切割和搅拌,将可调角度管棚8周围的土体扰动固结,旋喷成桩后将可调角度管棚8包裹并和相邻的水平旋喷桩9咬合搭接,形成具有较高承载和帷幕隔断效果的支护结构。水平旋喷桩9施工利用已有可调角度管棚8的管棚钢管12外侧布置的限位轨道16通过限位焊接13实现施工精度。水平旋喷桩9布置在盾构钢环外侧170mm的盾构隧道轮廓线7上侧,相邻水平旋喷桩9间距为300mm,水平旋喷桩9直径为500mm,相邻水平旋喷桩9相互咬合200mm,水平旋喷桩9单根施工长度为45m,水平旋喷桩9固结材料选用P.O42.5水泥,水灰比为1:1;水平旋喷桩9施工轨迹与相邻可调角度管棚8相同,一般要求施工转速为5~15r/min,回拔速度为15~25cm/min。"Horizontal rotary grouting pile curtain wrapping partition" refers to the construction of horizontal rotary grouting piles 9 between adjacent adjustable angle pipe sheds 8, and the use of ultra-high pressure cutting and stirring of cement slurry to separate the soil around the adjustable angle pipe sheds 8. The body is disturbed and consolidated, and the angle-adjustable pipe shed 8 is wrapped and overlapped with the adjacent horizontal jet grouted pile 9 after jet spraying into piles to form a support structure with high load bearing and curtain partition effect. The construction of the horizontal rotary grouting pile 9 utilizes the limit track 16 arranged outside the pipe shed steel pipe 12 of the existing angle-adjustable pipe shed 8 to achieve construction accuracy through the limit welding 13 . The horizontal jet grouting piles 9 are arranged on the upper side of the shield tunnel outline 7 170 mm outside the shield steel ring, the distance between adjacent horizontal jet grouting piles 9 is 300 mm, and the diameter of horizontal jet grouting piles 9 is 500 mm. Interlocking 200mm, the construction length of a single horizontal jet grouting pile 9 is 45m, the consolidation material of the horizontal jet grouting pile 9 is P.O42.5 cement, and the water-cement ratio is 1:1; the construction track of the horizontal jet grouting pile 9 is adjacent to The angle-adjustable pipe shed 8 is the same. Generally, the construction speed is required to be 5-15 r/min, and the pull-back speed is 15-25 cm/min.

1.水平旋喷桩9技术要求:1. Technical requirements for horizontal jet grouting pile 9:

(1)水平旋喷桩9采取合金钻头配合循环液钻进控制泥沙流失,打设长度结合现场实际情况采取一次性打设完成预定桩长;(1) The horizontal jet grouting pile 9 adopts alloy drill bit and circulating fluid drilling to control the loss of sediment, and the length of the pile is set in one time according to the actual situation on site to complete the predetermined pile length;

(2)水平打设精度通过装在钻头上的限位与可调角度管棚8轨道保持一致,根据隧道角度和施工经验通过试验桩施工来确定适宜的限位装置;(2) The accuracy of horizontal drilling is kept consistent with the 8 rails of the adjustable angle pipe shed through the limit installed on the drill bit, and the appropriate limit device is determined through the construction of test piles according to the tunnel angle and construction experience;

(3)水平旋喷桩9采用水泥单液浆,注浆浆液水灰比控制为1:1;(3) The horizontal rotary grouting pile 9 adopts cement single-fluid slurry, and the water-cement ratio of the grouting slurry is controlled to be 1:1;

(4)进钻压力为3~5MPa,退钻压力控制在35MPa±5MPa,喷浆时需控制返浆量及拱部沉降;注浆流量为80L/min~90L/min;(4) The drilling pressure is 3-5MPa, and the drill-exiting pressure is controlled at 35MPa±5MPa. When spraying grout, it is necessary to control the amount of grout return and the settlement of the arch; the grouting flow rate is 80L/min-90L/min;

(5)水平旋喷桩9位置偏差为±50mm;倾角与设计误差为±1%;(5) The position deviation of the horizontal jet grouting pile 9 is ±50mm; the inclination angle and the design error are ±1%;

(6)水平旋喷桩9长不小于设计桩长;水泥土固结体28天无侧限抗压强度大于3MPa,桩体应确保连续,均匀达到支护效果;(6) The length of the horizontal jet grouting pile 9 shall not be less than the design pile length; the 28-day unconfined compressive strength of the cement-soil consolidation body shall be greater than 3MPa, and the pile body shall ensure continuous and uniform support effect;

(7)对每根水平旋喷桩9从钻孔至成桩做以下记录:施工日期、开钻时间、结束时间、旋喷压力、旋喷提升速度、桩长、注浆量;(7) Make the following records for each horizontal jet grouting pile 9 from drilling to pile formation: construction date, drilling time, end time, jet jet pressure, jet jet lifting speed, pile length, grouting volume;

(8)桩体施工过程要连续,不能间断,防止出现断桩,短桩现象。如因机械故障或其它原因停机在30~120min的,应重复旋喷1m,超过2小时的,按断桩处理,应重新钻孔补桩。(8) The construction process of the pile body should be continuous and cannot be interrupted to prevent the phenomenon of broken piles and short piles. If the machine stops for 30-120 minutes due to mechanical failure or other reasons, the rotary spraying should be repeated for 1m, and if it exceeds 2 hours, it should be treated as a broken pile and the pile should be re-drilled.

2.水平旋喷施工工艺流程图如图2所示,具体实施如下:2. The flow chart of the horizontal rotary spraying construction process is shown in Figure 2, and the specific implementation is as follows:

(1)安装旋喷钻具和限位轨道;(1) Install rotary spray drilling tools and limit rails;

(2)钻进:(2) Drilling:

①开孔;① opening;

②配制循环浆液;② Preparation of circulating slurry;

③钻孔打设。③Drilling and drilling.

(3)高压旋喷:(3) High-pressure rotary spraying:

①检查高压注浆泵,泵压达到设计要求时才能开始喷浆;① Check the high-pressure grouting pump, the grouting can only be started when the pump pressure meets the design requirements;

②喷浆前检查钻机具的密封性,缓慢加压达到设计值后稳定喷浆;② Check the tightness of the drilling rig before spraying, and slowly pressurize to the design value to stabilize the spraying;

③在高压喷浆安排专人操作和观察泵压变化,发现问题及时通知解决;③ Arrange special personnel to operate and observe pump pressure changes in high-pressure spraying, and notify and solve problems in time if any problems are found;

④钻杆旋喷至设计终孔位置停止注浆,并用清水高压冲洗干净管路;④ Spray the drill pipe to the design end hole position to stop grouting, and clean the pipeline with clean water under high pressure;

⑤严格按照设计要求施工压力和浆液配比。⑤ Strictly follow the design requirements for construction pressure and grout ratio.

(4)封孔:(4) Sealing:

喷浆至设计终孔位置后,停止喷浆,快速拔出钻杆和钻头,采用编织袋或者棉丝进行孔口封堵。After spraying to the designed final hole position, stop spraying, quickly pull out the drill pipe and drill bit, and use woven bags or cotton silk to seal the hole.

(5)清洗管道及设备。(5) Clean pipes and equipment.

施工完毕后及时清水高压冲洗管道及设备,完毕后移至下一桩位。After the construction is completed, the pipeline and equipment should be flushed with clean water and high pressure in time, and moved to the next pile position after completion.

Claims (5)

1.一种软土盾构穿越既有地铁的土体复合加固结构,其特征在于,包括:盾构隧道轮廓线(7)、可调角度管棚(8)和水平旋喷桩(9);所述在待挖盾构隧道轮廓线(7)外侧设有一排可调角度管棚(8),所述可调角度管棚(8)包括管棚钢管(12),所述相邻管棚钢管(12)之间设有水平旋喷桩(9),所述水平旋喷桩(9)将可调角度管棚(8)包裹并和相邻的水平旋喷桩(9)咬合搭接;所述水平旋喷桩(9)包括旋喷钻杆(14)和钻杆外套(15),所述管棚钢管(12)与旋喷钻杆(14)之间相间连接,所述管棚钢管(12)外侧设有限位轨道(16),所述旋喷钻杆(14)外表面设有钻杆外套(15),所述限位轨道(16)与钻杆外套(15)通过限位焊接(13)形成整体拱壳。1. A soil composite reinforcement structure for a soft soil shield passing through an existing subway, characterized in that it includes: a shield tunnel outline (7), an adjustable angle pipe shed (8) and a horizontal jet grouting pile (9) ; The outer side of the outline (7) of the shield tunnel to be excavated is provided with a row of adjustable angle pipe sheds (8), the adjustable angle pipe sheds (8) include pipe shed steel pipes (12), and the adjacent pipe sheds Horizontal jet grouting piles (9) are arranged between the steel pipes (12) in the shed, and the horizontal jet grouting piles (9) wrap the angle-adjustable pipe shed (8) and engage with the adjacent horizontal jet grouting piles (9) connected; the horizontal jet grouting pile (9) comprises a jet grouting drill pipe (14) and a drill pipe overcoat (15), and the pipe shed steel pipe (12) is connected alternately with the jet jet drilling pipe (14), and the The outside of the pipe shed steel pipe (12) is provided with a limit track (16), and the outer surface of the rotary jet drill pipe (14) is provided with a drill pipe jacket (15), and the limit track (16) and the drill pipe jacket (15) The integral arch shell is formed by limit welding (13). 2.根据权利要求1所述的软土盾构穿越既有地铁的土体复合加固结构,其特征在于:所述可调角度管棚(8)沿隧道纵向延伸方向由后向前分多个节段。2. The soil composite reinforcement structure for soft soil shield passing through the existing subway according to claim 1, characterized in that: the angle-adjustable pipe shed (8) is divided into multiple sections from back to front along the longitudinal extension direction of the tunnel Segments. 3.根据权利要求1所述的软土盾构穿越既有地铁的土体复合加固结构,其特征在于:所述管棚钢管(12)使用热扎无缝钢管,管棚钢管(12)两端均预加工成外丝扣。3. The soft soil shield according to claim 1 passes through the soil composite reinforcement structure of the existing subway, characterized in that: the pipe shed steel pipe (12) uses hot-rolled seamless steel pipes, and the pipe shed steel pipes (12) are two Both ends are pre-processed into outer threaded buckles. 4.根据权利要求1所述的软土盾构穿越既有地铁的土体复合加固结构,其特征在于:通过盾构隧道的圆心作既有地铁隧道的两条切线,两条切线所夹角度为α,通过盾构隧道的圆心与可调角度管棚(8)两边缘所成角度为β,β=2α。4. according to claim 1, the soft soil shield passing through the soil composite reinforcement structure of the existing subway is characterized in that: two tangents of the existing subway tunnel are made through the center of the shield tunnel, and the angle between the two tangents is is α, and the angle formed by the center of the shield tunnel and the two edges of the adjustable angle pipe shed (8) is β, and β=2α. 5.一种如权利要求1所述的软土盾构穿越既有地铁的土体复合加固结构的施工方法,其特征在于,包括以下步骤:5. A construction method for the soft soil shield passing through the soil composite reinforcement structure of the existing subway as claimed in claim 1, characterized in that, comprising the following steps: S1、螺旋出土可调角度管棚(8)拱顶支护;S1, spiral unearthed adjustable angle pipe shed (8) vault support; S1.1、搭设钻孔平台,水平旋喷施工共用平台;S1.1. Set up a drilling platform and a shared platform for horizontal rotary spraying construction; S1.2、安装钻机,可调角度管棚(8)施工完毕后,钻机继续进行水平旋喷施工;S1.2, install the drilling rig, after the construction of the adjustable angle pipe shed (8) is completed, the drilling rig continues to carry out the horizontal rotary spraying construction; S1.3、破除掌子面(10)和地层入口段的素混凝土障碍物:掌子面(10)结构墙采用高速水钻按设计位置开孔,开孔角度按照可调角度管棚(8)设计施工角度钻进;采用潜孔锤沿掌子面(10)开孔钻进破碎地层入口段的素混凝土障碍物;S1.3. Remove plain concrete obstacles on the tunnel surface (10) and the entrance section of the formation: the structural wall of the tunnel surface (10) uses high-speed water drills to open holes according to the design position, and the opening angle is adjusted according to the angle of the pipe shed (8) Drilling at the design and construction angle; using a down-the-hole hammer to drill into the plain concrete obstacle at the entrance section of the broken stratum along the opening of the face (10); S1.4、将螺旋出土钻具穿入加工好的管棚钢管(12)内,管棚钢管(12)两端公母丝扣,螺旋钻具端头安装扩孔螺旋钻楔形钻头(11),钻具内部安装角度探测仪器;S1.4. Insert the auger unearthed drilling tool into the processed pipe shed steel pipe (12), the male and female threads at both ends of the pipe shed steel pipe (12), and install the reaming auger wedge-shaped drill bit (11) at the end of the auger drilling tool , the angle detection instrument is installed inside the drilling tool; S1.5、管棚钢管(12)顶进前先检查钻机机械状况和仪器工作状态;钻机就位施钻时,钻机与掌子面(10)固定;管棚钢管(12)顶进土层后启动钻机旋转,测量入土管棚钢管(12)角度变化;S1.5. Check the mechanical status of the drilling rig and the working status of the instrument before jacking the pipe shed steel pipe (12); After starting the drilling rig to rotate, measure the angle change of the pipe shed steel pipe (12) into the soil; S1.6、第一根管棚钢管(12)顶进结束后,拆卸钻机与可调角度管棚(8)接头,沿导轨退回原位,人工装入第二根管棚钢管(12),管棚钢管(12)内安装螺旋钻,与第一根管棚钢管(12)进行扣连接成一体,顶进旋转出土;S1.6. After the jacking of the first pipe shed steel pipe (12) is completed, disassemble the joint between the drilling rig and the angle-adjustable pipe shed (8), return to the original position along the guide rail, and manually install the second pipe shed steel pipe (12). An auger is installed in the pipe shed steel pipe (12), and is buckled and connected with the first pipe shed steel pipe (12) to form a whole, and is pushed in and rotated to be unearthed; S1.7、当管棚钢管(12)角度发生倾角偏差时,启动纠偏程序,停止钻具旋转,按设计方法操作顶进管棚钢管(12):管棚钢管(12)向上偏差,降低管棚钢管(12)倾角,向下调节螺旋钻楔形钻头(11)角度位置;管棚钢管(12)向下偏差,向上调整管棚钢管(12)倾角,向上调节螺旋钻楔形钻头(11)角度位置;管棚钢管(12)向左右偏斜时,参照倾角调整方法将楔形板调整纠偏方位,顶进管棚钢管(12)进行纠偏作业;S1.7. When the inclination angle of the pipe shed steel pipe (12) deviates, start the deviation correction program, stop the drilling tool rotation, and operate the jacking pipe shed steel pipe (12) according to the design method: the pipe shed steel pipe (12) deviates upward, lower the pipe shed The inclination angle of the shed steel pipe (12) is to adjust the angular position of the auger wedge bit (11) downward; the downward deviation of the shed steel pipe (12) is to adjust the inclination angle of the shed steel pipe (12) upward, and the angle of the auger wedge bit (11) is adjusted upward position; when the pipe shed steel pipe (12) deviates to the left and right, refer to the inclination angle adjustment method to adjust the wedge-shaped plate to adjust the deviation correction position, and push into the pipe shed steel pipe (12) to perform the deviation correction operation; S1.8、施工中的管棚钢管(12)在安装前必须逐孔逐根进行编号,按编号顺序接管顶进;S1.8. The steel pipes (12) under construction must be numbered hole by hole and root by root before installation, and take over and jack in the order of numbering; S1.9、可调角度管棚(8)注浆:注浆前先检查管路和机械状况,确认正常后做压浆实验,确定合理的注浆参数;注浆过程中随时检查孔口、邻孔及覆盖层较薄部位有无串浆现象;注浆过程派专人负责,记录注浆时间、浆液消耗量及注浆压力等数据;注浆结束后对泵及管路进行清孔,完成可调角度管棚(8)的施工工艺;S1.9, Adjustable angle pipe shed (8) grouting: check the pipeline and mechanical condition before grouting, do a grouting test after confirming normal, and determine reasonable grouting parameters; check the orifice, Whether there is any grouting phenomenon in the adjacent holes and the thinner part of the covering layer; assign a special person to be responsible for the grouting process, record the grouting time, grout consumption and grouting pressure and other data; after the grouting, clean the pump and pipeline to complete The construction technique of the angle-adjustable pipe shed (8); S2、水平旋喷注浆土体加固改良;S2, horizontal jet grouting soil reinforcement improvement; S2.1、安装旋喷钻具和限位轨道;S2.1. Install the rotary spray drilling tool and the limit rail; S2.2、钻进:开孔,配制循环浆液,钻孔打设;S2.2. Drilling: opening holes, preparing circulating slurry, and drilling; S2.3、高压旋喷:检查高压注浆泵,泵压达到设计要求时开始喷浆;喷浆前检查钻机具的密封性,加压达到设计值后喷浆;在高压喷浆安排专人操作和观察泵压变化;钻杆旋喷至设计终孔位置停止注浆,并用清水高压冲洗干净管路;S2.3. High-pressure rotary grouting: Check the high-pressure grouting pump, and start grouting when the pump pressure meets the design requirements; check the sealing of the drilling rig before grouting, and spray grouting after the pressure reaches the design value; arrange special personnel to operate the high-pressure grouting and observe the change of pump pressure; the drill pipe is sprayed to the design end hole position to stop grouting, and the pipeline is washed with clean water under high pressure; S2.4、封孔:喷浆至设计终孔位置后,停止喷浆,拔出钻杆和钻头,采用编织袋或者棉丝进行孔口封堵;S2.4. Hole sealing: After spraying grout to the designed final hole position, stop spraying, pull out the drill pipe and drill bit, and use woven bags or cotton silk to seal the hole; S2.5、清洗管道及设备,完成水平旋喷的施工工艺。S2.5. Clean the pipeline and equipment, and complete the construction process of horizontal rotary spraying.
CN201711116073.7A 2017-11-13 2017-11-13 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method Active CN107916935B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711116073.7A CN107916935B (en) 2017-11-13 2017-11-13 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711116073.7A CN107916935B (en) 2017-11-13 2017-11-13 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method

Publications (2)

Publication Number Publication Date
CN107916935A true CN107916935A (en) 2018-04-17
CN107916935B CN107916935B (en) 2024-01-23

Family

ID=61895438

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711116073.7A Active CN107916935B (en) 2017-11-13 2017-11-13 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method

Country Status (1)

Country Link
CN (1) CN107916935B (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108678666A (en) * 2018-07-28 2018-10-19 徐工集团工程机械有限公司 A kind of multifunctional drill and pipe canopy mounting device
CN108952765A (en) * 2018-07-18 2018-12-07 中铁十二局集团第二工程有限公司 Construction method of the super steel tube shed in water-rich sand layer advance support
CN109538256A (en) * 2018-08-28 2019-03-29 北京瑞威世纪铁道工程有限公司 Tunnel pipe shed construction method and device
CN109723443A (en) * 2018-12-30 2019-05-07 中铁十四局集团有限公司 Method for tunnel construction
CN109723454A (en) * 2019-01-09 2019-05-07 中水电四局武汉轨道交通工程有限公司 A kind of bored tunnel advance support is with pipe canopy with the accurate drilling construction method of pipe
CN109869156A (en) * 2019-04-02 2019-06-11 北京首尔工程技术有限公司 The jacking tube row of the unearthed amount of control for the construction of pipe comb curtain and its jacking method
CN109869154A (en) * 2019-02-26 2019-06-11 朔黄铁路发展有限责任公司 Under wear existing railway technique and lower penetrating device
CN110578536A (en) * 2019-10-15 2019-12-17 中铁十二局集团有限公司 Excavation support reinforcing method for underground excavation section of subway to penetrate existing street crossing channel
CN111379571A (en) * 2018-12-30 2020-07-07 中铁十四局集团有限公司 Pipeline, pipe shed structure and pipe shed construction method with same
CN112857223A (en) * 2021-01-19 2021-05-28 吉力此且 Optical fiber gyroscope positioning device and method for subway pipe shed positioning measurement
CN113279693A (en) * 2021-05-09 2021-08-20 苏州中车建设工程有限公司 Structure for newly-built subway tunnel in soft soil area to traverse existing tunnel and construction method thereof
CN113685205A (en) * 2021-09-22 2021-11-23 中铁隧道股份有限公司 Rotary spraying lifting structure and construction method
CN114687760A (en) * 2022-03-24 2022-07-01 中铁九局集团第四工程有限公司 Anti-displacement subway tunnel structure based on soft foundation
CN114780907A (en) * 2022-06-22 2022-07-22 中国铁路设计集团有限公司 Method for determining surface subsidence limit value of underground tunnel passing through road in subway section

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05112929A (en) * 1991-10-24 1993-05-07 Nippon Steel Corp Steel pipe pile column construction method
KR20070002328A (en) * 2005-06-30 2007-01-05 한미기초개발주식회사 Construction method of steel pipe loop structure
KR100825074B1 (en) * 2007-08-31 2008-04-24 윤인병 Steel pipe loop structure and construction method
CN101215969A (en) * 2008-01-17 2008-07-09 上海交通大学 Deformation control method for large-diameter shield passing through small-diameter subway tunnel at short distance
KR20090060608A (en) * 2007-12-10 2009-06-15 한미기초개발주식회사 Steel pipe loop structure and construction method
CN202441393U (en) * 2012-02-10 2012-09-19 中南大学 Forepoling structure of horizontal rotary jet grouting and big pipe shed combined tunnel
CN202690065U (en) * 2012-05-25 2013-01-23 中铁四局集团有限公司 Reinforced structure formed by advanced treatment of weathering ball of impact drill in tunneling range of shield tunneling machine
CN204753606U (en) * 2015-07-06 2015-11-11 济南轨道交通集团有限公司 Modular curtain
CN205117357U (en) * 2015-11-21 2016-03-30 中铁二十局集团第二工程有限公司 Weak surrounding rock tunnel advance support structure based on self -drilling spiral pipe canopy
CN205172598U (en) * 2015-12-16 2016-04-20 海南大学 Pipe curtain spouts a supporting construction soon
CN205260041U (en) * 2015-12-26 2016-05-25 海南大学 Method of freezing supporting construction is spouted soon to level
WO2016095630A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
CN105781573A (en) * 2016-03-18 2016-07-20 中铁九局集团第六工程有限公司 Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN105781557A (en) * 2016-03-25 2016-07-20 广东水电二局股份有限公司 Method for constructing underground excavated tunnel by adopting chemical grouting for sand layer consolidation
CN105909259A (en) * 2016-06-12 2016-08-31 中铁十九局集团轨道交通工程有限公司 Pipe curtain construction settlement control system and method for close-range underpassing of existing shield tunnel
CN205936640U (en) * 2016-05-09 2017-02-08 铁道第三勘察设计院集团有限公司 Interior tub leading deep pre -reinforcing secant pile supporting construction in tunnel of canopy core that establishes
CN206158753U (en) * 2016-09-30 2017-05-10 中铁第一勘察设计院集团有限公司 Shield constructs well end bassoon canopy system of consolidating based on major structure
KR20170087786A (en) * 2016-01-21 2017-07-31 이평우 Reinforcement method of Tunnel
CN207620794U (en) * 2017-11-13 2018-07-17 浙江大学城市学院 The soil body composite reinforcing structure of the existing subway of weak soil shield crossing

Patent Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05112929A (en) * 1991-10-24 1993-05-07 Nippon Steel Corp Steel pipe pile column construction method
KR20070002328A (en) * 2005-06-30 2007-01-05 한미기초개발주식회사 Construction method of steel pipe loop structure
KR100825074B1 (en) * 2007-08-31 2008-04-24 윤인병 Steel pipe loop structure and construction method
KR20090060608A (en) * 2007-12-10 2009-06-15 한미기초개발주식회사 Steel pipe loop structure and construction method
CN101215969A (en) * 2008-01-17 2008-07-09 上海交通大学 Deformation control method for large-diameter shield passing through small-diameter subway tunnel at short distance
CN202441393U (en) * 2012-02-10 2012-09-19 中南大学 Forepoling structure of horizontal rotary jet grouting and big pipe shed combined tunnel
CN202690065U (en) * 2012-05-25 2013-01-23 中铁四局集团有限公司 Reinforced structure formed by advanced treatment of weathering ball of impact drill in tunneling range of shield tunneling machine
WO2016095630A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
CN204753606U (en) * 2015-07-06 2015-11-11 济南轨道交通集团有限公司 Modular curtain
CN205117357U (en) * 2015-11-21 2016-03-30 中铁二十局集团第二工程有限公司 Weak surrounding rock tunnel advance support structure based on self -drilling spiral pipe canopy
CN205172598U (en) * 2015-12-16 2016-04-20 海南大学 Pipe curtain spouts a supporting construction soon
CN205260041U (en) * 2015-12-26 2016-05-25 海南大学 Method of freezing supporting construction is spouted soon to level
KR20170087786A (en) * 2016-01-21 2017-07-31 이평우 Reinforcement method of Tunnel
CN105781573A (en) * 2016-03-18 2016-07-20 中铁九局集团第六工程有限公司 Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN105781557A (en) * 2016-03-25 2016-07-20 广东水电二局股份有限公司 Method for constructing underground excavated tunnel by adopting chemical grouting for sand layer consolidation
CN205936640U (en) * 2016-05-09 2017-02-08 铁道第三勘察设计院集团有限公司 Interior tub leading deep pre -reinforcing secant pile supporting construction in tunnel of canopy core that establishes
CN105909259A (en) * 2016-06-12 2016-08-31 中铁十九局集团轨道交通工程有限公司 Pipe curtain construction settlement control system and method for close-range underpassing of existing shield tunnel
CN206158753U (en) * 2016-09-30 2017-05-10 中铁第一勘察设计院集团有限公司 Shield constructs well end bassoon canopy system of consolidating based on major structure
CN207620794U (en) * 2017-11-13 2018-07-17 浙江大学城市学院 The soil body composite reinforcing structure of the existing subway of weak soil shield crossing

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
中铁二局股份有限公司: "土木工程施工工艺.隧道及地铁工程", vol. 1, 北京:中国铁道出版社, pages: 177 - 184 *
刘斌: "软弱围岩隧道洞口段预加固技术研究", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》, vol. 1, no. 3, pages 177 - 184 *
李建平等: "长距离管棚加固技术在盾构下穿既有运营地铁线路中的应用", 施工技术, vol. 46, no. 1, pages 782 - 784 *
石钰锋等: "富水软弱地层隧道水平旋喷与大管棚预支护研究及应用", 岩土工程学报, vol. 37, no. 2, pages 101 - 106 *
陈伟庚: "富水软弱围岩铁路隧道预加固技术", 铁道建筑, no. 5, pages 104 - 106 *
马骏: "城市地铁硬岩隧道下穿既有隧道施工控制技术", 国防交通工程与技术, vol. 14, no. 1, pages 49 - 52 *

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952765A (en) * 2018-07-18 2018-12-07 中铁十二局集团第二工程有限公司 Construction method of the super steel tube shed in water-rich sand layer advance support
CN108678666B (en) * 2018-07-28 2024-02-02 江苏徐工工程机械研究院有限公司 Multifunctional drilling machine and pipe shed mounting device
CN108678666A (en) * 2018-07-28 2018-10-19 徐工集团工程机械有限公司 A kind of multifunctional drill and pipe canopy mounting device
CN109538256A (en) * 2018-08-28 2019-03-29 北京瑞威世纪铁道工程有限公司 Tunnel pipe shed construction method and device
CN111379571A (en) * 2018-12-30 2020-07-07 中铁十四局集团有限公司 Pipeline, pipe shed structure and pipe shed construction method with same
CN109723443A (en) * 2018-12-30 2019-05-07 中铁十四局集团有限公司 Method for tunnel construction
CN109723443B (en) * 2018-12-30 2021-07-20 中铁十四局集团有限公司 Tunnel construction method
CN109723454A (en) * 2019-01-09 2019-05-07 中水电四局武汉轨道交通工程有限公司 A kind of bored tunnel advance support is with pipe canopy with the accurate drilling construction method of pipe
CN109869154A (en) * 2019-02-26 2019-06-11 朔黄铁路发展有限责任公司 Under wear existing railway technique and lower penetrating device
CN109869154B (en) * 2019-02-26 2020-08-11 朔黄铁路发展有限责任公司 Underpass device for existing railway
CN109869156A (en) * 2019-04-02 2019-06-11 北京首尔工程技术有限公司 The jacking tube row of the unearthed amount of control for the construction of pipe comb curtain and its jacking method
CN109869156B (en) * 2019-04-02 2024-04-26 北京首尔工程技术有限公司 Jacking pipe row for controlling soil discharge amount for pipe row pipe curtain construction and jacking method thereof
CN110578536A (en) * 2019-10-15 2019-12-17 中铁十二局集团有限公司 Excavation support reinforcing method for underground excavation section of subway to penetrate existing street crossing channel
CN112857223A (en) * 2021-01-19 2021-05-28 吉力此且 Optical fiber gyroscope positioning device and method for subway pipe shed positioning measurement
CN113279693B (en) * 2021-05-09 2022-05-03 苏州中车建设工程有限公司 Structure for enabling newly built subway tunnel in soft soil body area to transversely penetrate existing tunnel and construction method of structure
CN113279693A (en) * 2021-05-09 2021-08-20 苏州中车建设工程有限公司 Structure for newly-built subway tunnel in soft soil area to traverse existing tunnel and construction method thereof
CN113685205A (en) * 2021-09-22 2021-11-23 中铁隧道股份有限公司 Rotary spraying lifting structure and construction method
CN114687760A (en) * 2022-03-24 2022-07-01 中铁九局集团第四工程有限公司 Anti-displacement subway tunnel structure based on soft foundation
CN114687760B (en) * 2022-03-24 2025-07-18 中铁九局集团第四工程有限公司 Anti-displacement subway tunnel structure based on soft foundation
CN114780907A (en) * 2022-06-22 2022-07-22 中国铁路设计集团有限公司 Method for determining surface subsidence limit value of underground tunnel passing through road in subway section
CN114780907B (en) * 2022-06-22 2022-09-02 中国铁路设计集团有限公司 Method for determining surface settlement limit value of underpass road of subway interval tunnel

Also Published As

Publication number Publication date
CN107916935B (en) 2024-01-23

Similar Documents

Publication Publication Date Title
CN107916935A (en) A kind of soil body composite reinforcing structure and construction method of the existing subway of weak soil shield crossing
CN100501124C (en) The construction method of the connecting channel of the tunnel in the shield section of the subway
CN101737060B (en) Beneath-soil through-tunnel superlarge diameter pipe curtain construction method
CN105804758B (en) Across constructing metro tunnel method on the rectangular top pipe of the shallow small spacing of earthing big cross section
CN110056369B (en) Construction method for entrance and exit hole of tunnel
CN108104824A (en) A kind of Soft Soil Area slurry shield passes through existing constructing metro tunnel method
CN113107501B (en) A Construction Method of Excavation Excavation by Extending the Steel Ring of the Portal
WO2020259059A1 (en) Tbm parallel heading tunnel trunk construction method
CN110735653A (en) A deep hole retreat grouting water plugging construction method for igneous rock water-rich faults
CN106988750B (en) Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
JP2023500745A (en) A Comprehensive Construction Method for a Tunnel with Low Overburden Section Using the Regional Railway Mining Method
CN108547644B (en) Tunnel crossing crushing belt shed protection structure and supporting method
CN111677520A (en) Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method
CN110700853A (en) Shallow soil covering shield tunnel reinforcing method based on weak stratum
CN110259466A (en) A kind of subway station water-rich sand layer big cross section shield-tunneling construction technique
CN109139018A (en) The method for tunnel construction and system that deep hole sleeve valve barrel grouting is combined with horizontal jet grouting
CN207620794U (en) The soil body composite reinforcing structure of the existing subway of weak soil shield crossing
CN108049876A (en) A kind of construction method of compound stratum tunneling close range down bored tunnel
WO2022117124A1 (en) Construction method for outward expansion pipe in drill hole in goaf
CN115467673A (en) Construction method based on urban subway tunnel shield receiving
CN115163122A (en) A construction method of a tunnel approaching a structure with an upper span and a lower span
CN112727470B (en) Construction reinforcing method for shield tunnel at overlapped section
CN103147435A (en) Method for treating construction engineering foundation in gob
CN204646251U (en) The shield end reinforcement system of a kind of land pebble stratum super-front large pipe shed
CN209397608U (en) A high-pressure rotary grouting reinforced anchor pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant