[go: up one dir, main page]

CN107798427B - Construction method of extra-high voltage power transmission grid structure scheme of large-scale energy base - Google Patents

Construction method of extra-high voltage power transmission grid structure scheme of large-scale energy base Download PDF

Info

Publication number
CN107798427B
CN107798427B CN201710967229.6A CN201710967229A CN107798427B CN 107798427 B CN107798427 B CN 107798427B CN 201710967229 A CN201710967229 A CN 201710967229A CN 107798427 B CN107798427 B CN 107798427B
Authority
CN
China
Prior art keywords
grid
planning
power
selection scheme
power transmission
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710967229.6A
Other languages
Chinese (zh)
Other versions
CN107798427A (en
Inventor
吉平
严欢
姜宁
张鑫
杨海涛
王喆
宋云亭
郑超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Economic and Technological Research Institute of State Grid Shaanxi Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Economic and Technological Research Institute of State Grid Shaanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI, Economic and Technological Research Institute of State Grid Shaanxi Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710967229.6A priority Critical patent/CN107798427B/en
Publication of CN107798427A publication Critical patent/CN107798427A/en
Application granted granted Critical
Publication of CN107798427B publication Critical patent/CN107798427B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Health & Medical Sciences (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

本发明公开了一种大规模能源基地特高压电力送出电网结构方案的构建方法,包括以下步骤:1)构建大规模能源基地特高压电力送出电网初始模型;2)确定2‑3个直流背靠背的容量值;3)确定2‑3个直流背靠背的交流落点方案;4)得若干规划网架,然后将各规划网架作为初选方案构建初选方案集;5)对各规划网架进行电学性能分析;6)当不满足预设要求时,则从初选方案集中删除该规划网架;7)当经步骤6)处理后初选方案集为空集时,则转至步骤2);否则,则转至步骤8);8)对初选方案集中的各规划网架进行经济性分析;9)根据所述多目标优化规划模型选取最优规划网架,该方法能够综合电学性能及经济性实现电网结构方案的构建。

Figure 201710967229

The invention discloses a construction method of a large-scale energy base ultra-high voltage power transmission grid structure scheme, comprising the following steps: 1) constructing an initial model of a large-scale energy base ultra-high voltage power transmission grid; capacity value; 3) Determine the 2-3 DC back-to-back AC placement plans; 4) Obtain a number of planned grids, and then use each planned grid as a preliminary selection scheme to construct a preliminary selection scheme set; 5) Carry out Electrical performance analysis; 6) When the preset requirements are not met, delete the planning grid from the preliminary selection scheme set; 7) When the preliminary selection scheme set is empty after processing in step 6), go to step 2) otherwise, go to step 8); 8) carry out economic analysis to each planning grid in the primary selection scheme; 9) select the optimal planning grid according to the multi-objective optimization planning model, this method can integrate electrical performance And the economic realization of the construction of the power grid structure scheme.

Figure 201710967229

Description

Construction method of extra-high voltage power transmission grid structure scheme of large-scale energy base
Technical Field
The invention belongs to the field of power grid development and planning, and relates to a construction method of a structural scheme of an extra-high voltage power transmission power grid of a large-scale energy base.
Background
Energy resources in China are extremely unbalanced in distribution, nearly two thirds of hydropower can be developed in China to be distributed in the three provinces (regions) of Sichuan, Yunnan and Tibet in the west, nearly two thirds of reserves of coal are concentrated in the three provinces (regions) of Shanxi, inner Mongolia and Shaanxi in the north and the northwest of China, and large hydropower bases and coal-electricity bases are formed. The distribution of energy resources and economic development in China are in a reverse distribution layout, and the necessity of large-scale flow of energy and power across regions is determined. The transmission capacity of an extra-high voltage line is limited by the stability level of the grid, the load level and the transmission distance. When long-distance and large-capacity power transmission is completed through an extra-high voltage line, the transmission capacity of the transmission lines mainly depends on the stability limit of the line, and the stability limit of the long-distance transmission lines is usually lower due to the lack of enough power support in the middle, so that the limitation is brought to the transmission capacity of the extra-high voltage line. Therefore, for large capacity, long distance transportation of large scale coal electric bases, the transportation requirements may not be met with the use of ultra high voltage lines alone.
The extra-high voltage line has the characteristics of high voltage level, long power transmission distance and large power transmission capacity, a power transmission channel is added after the extra-high voltage line is put into operation, a grid structure is reinforced, the stability level of a power transmission section can be obviously improved, the power supply of a region is guaranteed, and the capability of optimizing configuration resources of a power grid is improved. Meanwhile, when the power grid fails, the extra-high voltage power grid can enhance the power flow transfer capacity of the power grid and obviously enhance the capacity of resisting the impact of multiple serious faults of the power grid, and the extra-high voltage power grid is an important and effective way for utilizing clean energy and preventing air pollution.
After the ultra-high voltage project is built and put into operation, the interconnection mode of the ultra-high voltage transformer substation and the original sending end ultra-high voltage power grid has certain influence on the short circuit current level, the transient stability and the power transmission capacity of an outgoing section of the power grid. In the initial stage of extra-high voltage construction, a grid structure is not formed, and if an extra-high voltage transformer substation and a transmission end extra-high voltage power grid are interconnected by adopting an alternating current circuit, the short-circuit current level of the original transmission end power grid can exceed the switch interruption capacity, and adverse effects can be brought to the transmission capacity of the transmission end power grid; if the ultra-high voltage transformer substation is not interconnected with the transmission end ultra-high voltage power grid, the voltage supporting capability is weak, and the possibility of limited power output of the energy base due to weak transient stability capability also exists.
With the development of an extra-high voltage power grid, an extra-high voltage alternating current and direct current series-parallel large-scale long-distance power transmission network is gradually formed, and a complex power grid structure is gradually formed at the power transmission end and the power receiving end and faces various technical problems. The reasonable planning of the extra-high voltage power transmission power grid structure of the large-scale energy base is to avoid the situation that the short-circuit current exceeds the breaking capacity of a related breaker and improve the transmission capacity, and is a difficult problem to be solved in the planning stage of the power grid at the transmission end, and meanwhile, the economy of the power grid is also considered in the planning stage of the power grid, so that a construction method of the power grid structure scheme comprehensively considering the electrical performance and the economy is required to be designed.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a method for constructing a large-scale energy base extra-high voltage power transmission power grid structure scheme, which can realize the construction of the power grid structure scheme by integrating electrical performance and economy.
In order to achieve the aim, the method for constructing the structural scheme of the extra-high voltage power transmission grid of the large-scale energy base comprises the following steps:
1) constructing an initial model of an extra-high voltage power transmission grid of a large-scale energy base;
2) carrying out power and electric quantity balance analysis according to a power supply and load development plan of a sending end power grid, determining the surplus power sending demand of the sending end power grid, and then determining 2-3 direct current back-to-back capacity values according to the surplus power sending demand of the sending end power grid, a direct current back-to-back engineering system, equipment set design and equipment manufacturing process level;
3) determining 2-3 direct-current back-to-back alternating-current drop point schemes according to power grid construction planning of a sending-end power grid and construction time sequences of an ultrahigh-voltage transformer substation;
4) according to the 2-3 direct current back-to-back capacity values determined in the step 2) and the 2-3 direct current back-to-back alternating current drop point schemes determined in the step 3), connecting different ultrahigh voltage alternating current drop points with direct current back-to-back converter stations with different capacities to obtain a plurality of planning net racks, and then constructing a primary selection scheme set by taking each planning net rack as a primary selection scheme;
5) analyzing the electrical performance of each planning net rack in the primary selection scheme set constructed in the step 4);
6) judging whether the electrical performance of each planning network frame in the primary selection scheme set meets the preset requirement, and deleting the planning network frame from the primary selection scheme set when the electrical performance of any planning network frame does not meet the preset requirement;
7) judging whether the initially selected scheme set processed in the step 6) is an empty set, and turning to the step 2) when the initially selected scheme set processed in the step 6) is the empty set; when the initially selected scheme set is not an empty set after the processing in the step 6), turning to a step 8);
8) carrying out economic analysis on each planned net rack in the primary selection scheme set;
9) and constructing a multi-objective optimization planning model taking the performance and the economy of the power grid as indexes, then selecting an optimal planning grid frame from planning grid frames in the primary selection scheme set according to the multi-objective optimization planning model, and then sending the optimal planning grid frame out of the power grid structure scheme as the extra-high voltage power of the large-scale energy base.
The specific operation of the step 1) is as follows: according to construction and production information of an ultra-high voltage transformer substation, a matched power supply of the ultra-high voltage transformer, a transmission end grid network frame and a generator set in a planned horizontal year, and with transformer substation capacity, short-circuit current level, line transmission capacity and grid transient stability as constraint conditions, an ultra-high voltage power transmission grid initial model of a large-scale energy base is constructed according to data information of a generator, a load, a balance node, a transformer and a line in a grid.
The specific operation of the step 5) is as follows: and (3) carrying out static safety analysis, short circuit current level evaluation, tide distribution characteristic analysis, transient stability characteristic analysis and transmission capacity analysis on each planning network frame in the primary selection scheme set constructed in the step 4).
The specific operation of step 8) is: and calculating the total engineering construction investment, operation and maintenance cost, investment recovery period and power transmission engineering economy of each planned net rack in the primary selection scheme set.
The specific operation of step 6) is: and judging whether the static safety, the short-circuit current level, the tide distribution characteristic, the transient stability characteristic and the transmission capacity of the transmission end power grid of each planning grid in the primary selection scheme set all meet preset requirements, and deleting the planning grid from the primary selection scheme set when the static safety, the short-circuit current level, the tide distribution characteristic, the transient stability characteristic and the transmission capacity of the transmission end power grid of any planning grid do not all meet the preset requirements.
The specific operation of constructing the multi-objective optimization planning model taking the power grid performance and the economy as indexes in the step 9) is as follows: and (3) weighting the performance and the economy of the power grid to construct a multi-objective optimization planning model.
The invention has the following beneficial effects:
the construction method of the structural scheme of the extra-high voltage power transmission grid of the large-scale energy base has the advantages that during specific operation, determining 2-3 direct current back-to-back capacity values according to the surplus power sending demand of a sending end power grid, a direct current back-to-back engineering system, equipment complete set design and equipment manufacturing process level, determining 2-3 direct current back-to-back alternating current point placement schemes according to the power grid construction plan of the sending end power grid and the construction time sequence of an ultrahigh voltage transformer substation, thereby forming a plurality of planning net racks, analyzing the electrical property of each planning net rack, deleting the planning net racks with the electrical property not meeting the requirement, then, each planning net rack is subjected to economic analysis, a multi-objective optimization planning model is constructed by taking the electrical performance and the economic performance of the power grid as indexes, the optimal planning net rack is selected, and the situation that the electrical performance of the selected planning net rack does not meet the requirement is avoided. In addition, the direct current back-to-back converter stations with different capacities are interconnected with different ultrahigh voltage alternating current drop points, so that adverse effects of a planning grid frame on the short circuit current level of the original sending-end power grid are avoided, the control is flexible, and the method and the device can be applied to multiple scenes and multiple operation modes.
Drawings
FIG. 1 is a flow chart of the present invention;
FIG. 2 is a schematic diagram of a power grid structure scheme in which extra-high voltages are interconnected with a sending-end extra-high voltage power grid through direct current back-to-back connections;
fig. 3 is a schematic diagram of a structural scheme of an extra-high voltage power transmission grid of a transmission-end power grid.
Detailed Description
The invention is described in further detail below with reference to the accompanying drawings:
referring to fig. 1, the method for constructing the structural scheme of the extra-high voltage power transmission grid of the large-scale energy base includes the following steps:
1) constructing an initial model of an extra-high voltage power transmission grid of a large-scale energy base;
the specific operation of the step 1) is as follows: according to construction and production information of an ultra-high voltage transformer substation, a matched power supply of the ultra-high voltage transformer, a transmission end grid network frame and a generator set in a planned horizontal year, and with transformer substation capacity, short-circuit current level, line transmission capacity and grid transient stability as constraint conditions, an ultra-high voltage power transmission grid initial model of a large-scale energy base is constructed according to data information of a generator, a load, a balance node, a transformer and a line in a grid.
2) Carrying out power and electric quantity balance analysis according to a power supply and load development plan of a sending end power grid, determining the surplus power sending demand of the sending end power grid, and then determining 2-3 direct current back-to-back capacity values according to the surplus power sending demand of the sending end power grid, a direct current back-to-back engineering system, equipment set design and equipment manufacturing process level;
3) determining 2-3 direct-current back-to-back alternating-current drop point schemes according to power grid construction planning of a sending-end power grid and construction time sequences of an ultrahigh-voltage transformer substation;
4) according to the 2-3 direct current back-to-back capacity values determined in the step 2) and the 2-3 direct current back-to-back alternating current drop point schemes determined in the step 3), connecting different ultrahigh voltage alternating current drop points with direct current back-to-back converter stations with different capacities to obtain a plurality of planning net racks, and then constructing a primary selection scheme set by taking each planning net rack as a primary selection scheme;
5) analyzing the electrical performance of each planning net rack in the primary selection scheme set constructed in the step 4);
the specific operation of the step 5) is as follows: and (3) carrying out static safety analysis, short circuit current level evaluation, tide distribution characteristic analysis, transient stability characteristic analysis and transmission capacity analysis on each planning network frame in the primary selection scheme set constructed in the step 4).
6) Judging whether the electrical performance of each planning network frame in the primary selection scheme set meets the preset requirement, and deleting the planning network frame from the primary selection scheme set when the electrical performance of any planning network frame does not meet the preset requirement;
the specific operation of step 6) is: and judging whether the static safety, the short-circuit current level, the tide distribution characteristic, the transient stability characteristic and the transmission capacity of the transmission end power grid of each planning grid in the primary selection scheme set all meet preset requirements, and deleting the planning grid from the primary selection scheme set when the static safety, the short-circuit current level, the tide distribution characteristic, the transient stability characteristic and the transmission capacity of the transmission end power grid of any planning grid do not all meet the preset requirements.
7) Judging whether the initially selected scheme set processed in the step 6) is an empty set, and turning to the step 2) when the initially selected scheme set processed in the step 6) is the empty set; when the initially selected scheme set is not an empty set after the processing in the step 6), turning to a step 8);
8) carrying out economic analysis on each planned net rack in the primary selection scheme set;
the specific operation of step 8) is: and calculating the total engineering construction investment, operation and maintenance cost, investment recovery period and power transmission engineering economy of each planned net rack in the primary selection scheme set.
9) And constructing a multi-objective optimization planning model taking the performance and the economy of the power grid as indexes, then selecting an optimal planning grid frame from planning grid frames in the primary selection scheme set according to the multi-objective optimization planning model, and then sending the optimal planning grid frame out of the power grid structure scheme as the extra-high voltage power of the large-scale energy base.
The specific operation of constructing the multi-objective optimization planning model taking the power grid performance and the economy as indexes in the step 9) is as follows: and (3) weighting the performance and the economy of the power grid to construct a multi-objective optimization planning model.
In fig. 2, ABCDEFH is a 1000kV substation, a and B represent extra-high voltage stations of a transmitting-end grid, C represents an intermediate station, D represents an extra-high voltage station of a receiving-end grid, a1, B1, and C1 are extra-high voltage substations, G1-G9 are generator sets, T1-T9 are transformers, L1 and L2 are receiving-end loads, and the extra-high voltage substation B1 are interconnected back-to-back by direct current.
Example one
According to a planning report of a certain transmitting end power grid, the construction progress of an ultra-high voltage power grid in the horizontal year and the production condition of a generator of the transmitting end ultra-high voltage power grid are clearly researched, abundant power of the transmitting end power grid is preliminarily determined through power and electric quantity balance, and then the capacity of direct current back-to-back is preliminarily set to be 1000MW and 1500MW respectively. According to the construction planning of the grid structure of the ultra-high voltage transmission end and the consideration of the sustainability of the planning scheme, the determined direct-current back-to-back alternating-current falling points can be initially selected as an ultra-high voltage transformer substation A or E in the graph 3, so that the structural scheme set of the ultra-high voltage power transmission grid of the large-scale energy base can be constructed as follows:
the first scheme is as follows: the direct current back-to-back capacity is 1000MW, and the direct current back-to-back alternating current drop point is a transformer substation A;
scheme II: the direct current back-to-back capacity is 1000MW, and the direct current back-to-back alternating current drop point is a transformer substation E;
the third scheme is as follows: the direct current back-to-back capacity is 1500MW, and a direct current back-to-back alternating current drop point is a transformer substation A;
and the scheme is as follows: the direct current back-to-back capacity is 1500MW, and the direct current back-to-back alternating current drop point is a transformer substation E.
Static safety analysis, short circuit current level analysis, transient stability check and outgoing transmission capacity analysis are carried out on the first scheme to the fourth scheme, the economy of each scheme is evaluated, and the results are listed in table 1.
TABLE 1
Figure GDA0003117447550000081
And (3) sequencing the planning schemes by adopting a multi-attribute decision method to obtain the programming schemes with the sequence of the degrees of merits of the planning schemes of F3 & gt F4 & gt F1 & gt F2, wherein the symbol '>' indicates 'superior', and the optimal programming scheme is scheme III, namely the direct-current back-to-back capacity is 1500MW, and the direct-current back-to-back alternating-current drop point is the programming scheme of the transformer substation A.

Claims (6)

1.一种大规模能源基地特高压电力送出电网结构方案的构建方法,其特征在于,包括以下步骤:1. a construction method of a large-scale energy base UHV power transmission grid structure scheme, is characterized in that, comprises the following steps: 1)构建大规模能源基地特高压电力送出电网初始模型;1) Build the initial model of large-scale energy base UHV power transmission grid; 2)按照送端电网电源及负荷发展规划进行电力电量平衡分析,确定送端电网的富裕电力送出需求,然后根据送端电网的富裕电力送出需求、直流背靠背工程系统、设备成套设计及设备制造工艺水平确定2-3个直流背靠背的容量值;2) Carry out power and electricity balance analysis according to the power supply and load development plan of the sending-end power grid, determine the abundant power transmission demand of the sending-end power grid, and then according to the rich power transmission demand of the sending-end power grid, DC back-to-back engineering system, complete equipment design and equipment manufacturing process Determine the capacity value of 2-3 DC back-to-back horizontally; 3)根据送端电网的电网建设规划及超高压变电站的建设时序确定2-3个直流背靠背的交流落点方案;3) According to the power grid construction plan of the sending end power grid and the construction sequence of the ultra-high voltage substation, determine the 2-3 DC back-to-back AC placement plans; 4)根据步骤2)确定的2-3个直流背靠背的容量值及步骤3)确定的2-3个直流背靠背的交流落点方案,通过不同容量的直流背靠背换流站与不同的超高压交流落点进行互联,得若干规划网架,然后将各规划网架作为初选方案构建初选方案集;4) According to the capacity value of 2-3 DC back-to-back determined in step 2) and the AC placement scheme of 2-3 DC back-to-back determined in step 3), through DC back-to-back converter stations of different capacities and different ultra-high voltage AC Connect the locations to get a number of planning grids, and then use each planning grid as a primary selection scheme to build a primary selection scheme set; 5)对步骤4)构建的初选方案集中的各规划网架进行电学性能分析;5) Perform electrical performance analysis on each planning grid in the primary selection scheme set in step 4); 6)判断初选方案集中各规划网架的电学性能是否满足预设要求,当任一规划网架的电能性能不满足预设要求时,则从初选方案集中删除该规划网架;6) Judging whether the electrical performance of each planned grid in the preliminary selection scheme meets the preset requirements, and when the electrical performance of any planned grid does not meet the preset requirements, delete the planned grid from the preliminary selection scheme; 7)判断经步骤6)处理后初选方案集是否为空集,当经步骤6)处理后初选方案集为空集时,则转至步骤2);当步骤6)处理后初选方案集不为空集,则转至步骤8);7) Judging whether the preliminary selection scheme set is an empty set after processing in step 6), when the preliminary selection scheme set is an empty set after processing in step 6), go to step 2); when the preliminary selection scheme is processed in step 6) If the set is not an empty set, go to step 8); 8)对初选方案集中的各规划网架进行经济性分析;8) Carry out economic analysis on each planning grid in the primary selection scheme; 9)构建以电网性能及经济性为指标的多目标优化规划模型,然后根据所述多目标优化规划模型从初选方案集中的各规划网架中选取最优规划网架,然后将所述最优规划网架作为大规模能源基地特高压电力送出电网结构方案。9) Build a multi-objective optimization planning model with power grid performance and economy as indicators, and then select the optimal planning grid from each planning grid in the set of preliminary selection schemes according to the multi-objective optimization planning model, and then select the optimal planning grid. The optimal planning grid is a large-scale energy base UHV power transmission grid structure scheme. 2.根据权利要求1所述的大规模能源基地特高压电力送出电网结构方案的构建方法,其特征在于,步骤1)的具体操作为:按照规划水平年特高压变电站、特高压变压器的配套电源、送端电网网架及发电机组的建设投产信息,以变电站容量、短路电流水平、线路输送容量及电网暂态稳定性为约束条件,根据电网中发电机、负荷、平衡节点、变压器及线路的数据信息构建大规模能源基地特高压电力送出电网初始模型。2. the construction method of large-scale energy base UHV power transmission grid structure scheme according to claim 1, it is characterized in that, the concrete operation of step 1) is: according to planning level year UHV substation, the supporting power supply of UHV transformer , The construction and commissioning information of the grid and generator sets at the sending end, with the substation capacity, short-circuit current level, line transmission capacity and grid transient stability as constraints, according to the power grid generators, loads, balance nodes, transformers and lines. The data information constructs the initial model of the large-scale energy base UHV power transmission grid. 3.根据权利要求1所述的大规模能源基地特高压电力送出电网结构方案的构建方法,其特征在于,步骤5)的具体操作为:对步骤4)构建的初选方案集中的各规划网架进行静态安全性分析、短路电流水平评估、潮流分布特性分析、暂态稳定特性分析及送端电网输电能力分析。3. the construction method of large-scale energy base UHV power transmission grid structure scheme according to claim 1, is characterized in that, the concrete operation of step 5) is: to each planning network that the primary selection scheme constructed in step 4) is concentrated The static safety analysis, short-circuit current level assessment, power flow distribution characteristic analysis, transient stability characteristic analysis and transmission capacity analysis of the sending end power grid are carried out on the frame. 4.根据权利要求1所述的大规模能源基地特高压电力送出电网结构方案的构建方法,其特征在于,步骤8)的具体操作为:计算初选方案集中各规划网架的工程建设总投资、运维费用、投资回收期及输电工程经济性。4. the construction method of large-scale energy base UHV power transmission grid structure scheme according to claim 1, is characterized in that, the concrete operation of step 8) is: calculate the total investment of engineering construction of each planning grid in the primary selection scheme , operation and maintenance costs, payback period and economics of transmission projects. 5.根据权利要求3所述的大规模能源基地特高压电力送出电网结构方案的构建方法,其特征在于,步骤6)的具体操作为:判断初选方案集中各规划网架的静态安全性、短路电流水平、潮流分布特性、暂态稳定特性及送端电网输电能力是否全部满足预设要求,当任意一个规划网架的静态安全性、短路电流水平、潮流分布特性、暂态稳定特性及送端电网输电能力不是全部满足预设要求,则从初选方案集中删除该规划网架。5. the construction method of large-scale energy base UHV power transmission grid structure scheme according to claim 3, is characterized in that, the concrete operation of step 6) is: judging the static safety of each planning grid in the preliminary selection scheme, Whether the short-circuit current level, power flow distribution characteristics, transient stability characteristics and transmission capacity of the sending end grid all meet the preset requirements, when the static safety, short-circuit current level, power flow distribution characteristics, transient stability characteristics and transmission capacity of any planned grid If the transmission capacity of the end grid does not fully meet the preset requirements, the planned grid will be deleted from the preliminary selection scheme set. 6.根据权利要求3所述的大规模能源基地特高压电力送出电网结构方案的构建方法,其特征在于,步骤9)中构建以电网性能及经济性为指标的多目标优化规划模型的具体操作为:通过对电网性能及经济性赋予权重以构建多目标优化规划模型。6. the construction method of large-scale energy base UHV power transmission grid structure scheme according to claim 3, is characterized in that, in step 9), construct the concrete operation of the multi-objective optimization planning model that takes grid performance and economy as indicators To construct a multi-objective optimization planning model by assigning weights to power grid performance and economy.
CN201710967229.6A 2017-10-17 2017-10-17 Construction method of extra-high voltage power transmission grid structure scheme of large-scale energy base Active CN107798427B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710967229.6A CN107798427B (en) 2017-10-17 2017-10-17 Construction method of extra-high voltage power transmission grid structure scheme of large-scale energy base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710967229.6A CN107798427B (en) 2017-10-17 2017-10-17 Construction method of extra-high voltage power transmission grid structure scheme of large-scale energy base

Publications (2)

Publication Number Publication Date
CN107798427A CN107798427A (en) 2018-03-13
CN107798427B true CN107798427B (en) 2021-08-17

Family

ID=61533243

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710967229.6A Active CN107798427B (en) 2017-10-17 2017-10-17 Construction method of extra-high voltage power transmission grid structure scheme of large-scale energy base

Country Status (1)

Country Link
CN (1) CN107798427B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109190801A (en) * 2018-08-10 2019-01-11 中国电力科学研究院有限公司 A kind of preferred integrated approach and system of extra-high voltage sending end electric network composition scheme
CN111327045A (en) * 2018-12-13 2020-06-23 国网新疆电力有限公司乌鲁木齐供电公司 Intelligent arrangement and risk analysis method based on real-time power flow
CN112417628A (en) * 2020-11-23 2021-02-26 中国能源建设集团浙江省电力设计院有限公司 A construction method of a typical grid of ultra-high voltage power grid
CN113852136B (en) * 2021-09-24 2023-07-25 广东电网有限责任公司 Power supply configuration method and device for new energy base delivery scheme

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7288921B2 (en) * 2004-06-25 2007-10-30 Emerson Process Management Power & Water Solutions, Inc. Method and apparatus for providing economic analysis of power generation and distribution
CN102663515B (en) * 2012-03-23 2016-04-27 湖北省电力公司 A kind of method for optimizing of extra-high voltage transformer substation location
US9058443B2 (en) * 2012-07-17 2015-06-16 International Business Machines Corporation Planning economic energy dispatch in electrical grid under uncertainty
CN103123713B (en) * 2012-11-08 2016-12-28 中国电力科学研究院 Adapt to the grid structure optimization method that many direct-current emergency power is supported
DE102014206191A1 (en) * 2014-04-01 2015-10-01 Friedrich-Alexander-Universität Erlangen-Nürnberg Method for establishing a grid for a power grid and dual power grid
CN105098764B (en) * 2014-05-19 2017-12-05 国家电网公司 A kind of extra-high-voltage alternating current drop point transmission project method for optimizing
CN105096019B (en) * 2014-05-19 2022-02-01 国家电网公司 Provincial power grid layered and partitioned typical power supply mode planning method
CN105356465B (en) * 2015-12-10 2017-07-21 中国电力科学研究院 Transmission Expansion Planning in Electric platform and application that a kind of economy is coordinated with security
CN106786557B (en) * 2017-01-23 2023-08-18 中国电力科学研究院 Extra-high voltage layered direct current capacity and drop point selection method and system

Also Published As

Publication number Publication date
CN107798427A (en) 2018-03-13

Similar Documents

Publication Publication Date Title
Liu Ultra-high voltage AC/DC grids
CN107798427B (en) Construction method of extra-high voltage power transmission grid structure scheme of large-scale energy base
CN105512472B (en) Large-scale wind electricity base power collects system topology hierarchy optimization design method
CN104281737B (en) A kind of wind power collection system of offshore wind power plant topological structure selection method
CN103123713B (en) Adapt to the grid structure optimization method that many direct-current emergency power is supported
Orths et al. The European North seas countries' offshore grid initiative—The way forward
CN103903192A (en) Method for establishing power supply mode bank of power distribution network
CN105139081A (en) Highly reliable planning method for contact points in power distribution system
CN106356872A (en) Configuration method for static synchronous compensator of ultrahigh-voltage weak-direct-current receiving end power grid
CN105071395A (en) High-voltage distribution network load transfer method based on power supply path logic search
CN109768543B (en) Elastic bottom-preserving net rack search modeling method based on mixed integer linear programming
CN111953003B (en) Site selection and capacity calculation method of flexible direct current access point
CN110048446A (en) A kind of method and system of the determining layering best drop point of direct current access system receiving end
CN105552880A (en) Electric power system typical fault set determination method based on state enumeration method
CN110096767B (en) Cascading failure simulation method for alternating current-direct current series-parallel power grid
CN112531762A (en) Method for evaluating stability of receiving end voltage of simultaneous-transmission and simultaneous-receiving ultrahigh voltage direct current transmission system
CN109802418B (en) Local power grid electromagnetic transient model equivalence method suitable for extra-high voltage direct current access
CN113675872B (en) Multi-direct-current simultaneous commutation failure coordination recovery ordering method based on sending end stability constraint
CN109980679A (en) Power distribution network net capability calculation method based on distributed new addressing
CN112417629A (en) 1000/500kV layered partition planning method for multi-direct-current feed-in district receiving-end power grid
CN115102211A (en) Energy transmission node positioning method for converting station area electric energy into power
Shah et al. Role of multi-infeed VSC-HVDC on dynamic behaviour of future north scotland transmission system
Khraijah et al. Optimization planning for large-scale offshore wind farms using multi-terminal HVDC transmission system
CN112417628A (en) A construction method of a typical grid of ultra-high voltage power grid
CN110994588A (en) Power distribution network structure assessment method suitable for investment planning

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant