CN107453383A - A kind of flexible direct current collocation method and device for power supply zone interconnection - Google Patents
A kind of flexible direct current collocation method and device for power supply zone interconnection Download PDFInfo
- Publication number
- CN107453383A CN107453383A CN201710556583.XA CN201710556583A CN107453383A CN 107453383 A CN107453383 A CN 107453383A CN 201710556583 A CN201710556583 A CN 201710556583A CN 107453383 A CN107453383 A CN 107453383A
- Authority
- CN
- China
- Prior art keywords
- flexible
- grid
- power
- power supply
- sending
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/36—Arrangements for transfer of electric power between AC networks via a high-tension DC link
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H7/00—Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
- H02H7/26—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
- H02H7/261—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured involving signal transmission between at least two stations
- H02H7/263—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured involving signal transmission between at least two stations involving transmissions of measured values
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H7/00—Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
- H02H7/26—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
- H02H7/268—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured for DC systems
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H7/00—Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
- H02H7/26—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
- H02H7/28—Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured for meshed systems
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
- Y02E60/60—Arrangements for transfer of electric power between AC networks or generators via a high voltage DC link [HVCD]
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
本发明涉及一种用于供电分区互联的柔性直流配置方法及装置,所述方法包括:根据供电分区的电网供电裕度确定柔性直流送受端电网;确定柔性直流额定功率上下限,并利用所述柔性直流额定功率上下限确定柔性直流额定功率限制条件;分别确定柔性直流送受端电网的柔性直流落点母线;柔性直流并网后对所述柔性直流送受端电网进行安全稳定校核;本发明提供的技术方案,通过柔性直流联接两供电分区,可避免电磁环网产生,抑制短路电流超标,同时在某一分区出现故障时,可通过柔性直流功率控制提供有功、无功功率支撑,实现另一分区对故障分区的支持。
The invention relates to a flexible DC configuration method and device for interconnection of power supply partitions. The method includes: determining the flexible DC sending and receiving end power grid according to the power supply margin of the power supply partition; determining the upper and lower limits of the flexible DC rated power, and using the The upper and lower limits of the flexible DC rated power determine the limit conditions of the flexible DC rated power; respectively determine the flexible DC drop-point busbars of the flexible DC sending and receiving end grid; after the flexible DC is connected to the grid, check the safety and stability of the flexible DC sending and receiving end grid; the invention provides The technical scheme of connecting the two power supply partitions through flexible DC can avoid the generation of electromagnetic ring network and suppress the short-circuit current from exceeding the standard. Partition support for failed partitions.
Description
技术领域technical field
本发明涉及供电分区领域,具体涉及一种用于供电分区互联的柔性直流配置方法及装置。The invention relates to the field of power supply partitions, in particular to a flexible DC configuration method and device for interconnection of power supply partitions.
背景技术Background technique
随着电网的发展,在电力系统在高一级电压网络尚未满足供电可靠性或不够坚强的情况下,为了合理利用现有资源保障输电能力,以及满足用户对用电的要求,会形成高低压电磁环网。With the development of the power grid, when the high-level voltage network of the power system has not yet met the reliability of power supply or is not strong enough, in order to make reasonable use of existing resources to ensure power transmission capacity and meet user requirements for power consumption, high and low voltage will be formed. Electromagnetic ring network.
电磁环网在新的电压等级建成初期有其存在的意义,有利于提高系统供电能力,减少备用容量。而随着较高电压等级电网的发展和传输负荷的不断增大,电磁环网成为电力系统严重的事故隐患。例如高一级电压线路开断后,其所带负荷将大量转移至第一级电压线路,低压线路功率可能超过其热稳限额。The electromagnetic ring network has its significance in the early stage of the new voltage level, which is conducive to improving the power supply capacity of the system and reducing the reserve capacity. With the development of higher-voltage power grids and the increasing transmission load, the electromagnetic ring network has become a serious accident hazard in the power system. For example, after the high-level voltage line is disconnected, a large number of loads carried by it will be transferred to the first-level voltage line, and the power of the low-voltage line may exceed its thermal stability limit.
《电力系统安全稳定导则》规定,随着高一级电压电网的建设,下一级电压电网应逐步实现分区运行相邻分区之间保持联络互为备用。国内多个省网公司,结合各地区情况已开展了电磁环网解环的研究和实施工作。The "Guidelines for the Safety and Stability of Electric Power Systems" stipulates that with the construction of a high-level voltage grid, the next-level voltage grid should gradually realize partition operation and maintain communication between adjacent partitions as backup. A number of provincial network companies in China have carried out the research and implementation of the electromagnetic ring network solution in combination with the conditions of each region.
通常将变压器分列运行或将变压器低压母线分段运行,形成低压供电分区,以将电磁环网解环、控制短路电流水平、提升整体供电能力。但这种方法存在以下缺点:Usually, the transformers are operated separately or the low-voltage buses of the transformers are operated in sections to form low-voltage power supply partitions, so as to de-loop the electromagnetic ring network, control the short-circuit current level, and improve the overall power supply capacity. But this method has the following disadvantages:
(1)各分区供电可靠性将随之降低;(1) The power supply reliability of each district will decrease accordingly;
(2)某一分区下注变压器出现问题时,该分区损失电源点,仅通过其他分区经热备线路供电,无法满足负荷需求,大量损失负荷;(2) When there is a problem with the transformer in a certain partition, the partition loses the power point and only supplies power through other partitions through the hot standby line, which cannot meet the load demand and loses a large amount of load;
(3)各分区间电气联系减弱,电压支撑能力降低。(3) The electrical connection between the districts is weakened, and the voltage support ability is reduced.
柔性直流输电技术作为新一代直流输电技术,可实现有功功率和无功功率的独立控制,并且无需无功补偿装置。结合柔性直流输电技术的技术特点和工程实际,柔性直流输电技术非常适合可再生能源并网、城市电网供电等场景。As a new generation of DC transmission technology, flexible DC transmission technology can realize independent control of active power and reactive power, and does not require reactive power compensation devices. Combining the technical characteristics and engineering practice of flexible DC transmission technology, flexible DC transmission technology is very suitable for scenarios such as renewable energy grid integration and urban grid power supply.
发明内容Contents of the invention
本发明提供一种用于供电分区互联的柔性直流配置方法及装置,其目的是通过柔性直流联接两供电分区,可避免电磁环网产生,抑制短路电流超标,同时在某一分区出现故障时,可通过柔性直流功率控制提供有功、无功功率支撑,实现另一分区对故障分区的支持。The present invention provides a flexible DC configuration method and device for the interconnection of power supply partitions. The purpose is to connect two power supply partitions through flexible DC, which can avoid the generation of electromagnetic ring network, suppress the short-circuit current from exceeding the standard, and at the same time, when a fault occurs in a partition, Active and reactive power support can be provided through flexible DC power control, and another partition can support the fault partition.
本发明的目的是采用下述技术方案实现的:The object of the present invention is to adopt following technical scheme to realize:
一种用于供电分区互联的柔性直流配置方法,其改进之处在于,包括:A flexible DC configuration method for interconnection of power supply partitions, the improvement of which includes:
根据供电分区的电网供电裕度确定柔性直流送受端电网;Determine the flexible DC sending and receiving end grid according to the grid power supply margin of the power supply partition;
确定柔性直流额定功率上下限,并利用所述柔性直流额定功率上下限确定柔性直流额定功率限制条件;Determine the upper and lower limits of the flexible DC rated power, and use the upper and lower limits of the flexible DC rated power to determine the limiting conditions for the flexible DC rated power;
分别确定柔性直流送受端电网的柔性直流落点母线;Respectively determine the flexible DC drop-point bus of the flexible DC sending and receiving end grid;
柔性直流并网后对所述柔性直流送受端电网进行安全稳定校核。After the flexible DC is connected to the grid, the safety and stability of the flexible DC sending and receiving end grid is checked.
优选的,按下式确定供电分区的电网供电裕度η:Preferably, the grid power supply margin η of the power supply partition is determined as follows:
上式中,PTmax为电网最大供电能力时所有下注变压器的有功功率,PT0为电网初始状态下所有下注变压器的有功功率;In the above formula, P Tmax is the active power of all transformers at the maximum power supply capacity of the grid, and P T0 is the active power of all transformers in the initial state of the grid;
其中,按下式确定电网最大供电能力时所有下注变压器的有功功率PTmax:Among them, the active power P Tmax of all betting transformers when the maximum power supply capacity of the grid is determined by the following formula:
PTmax=Pmax-Gmax P Tmax =P max -G max
上式中,Pmax为电网最大供电能力,Gmax为电网最大供电能力时对应的所有发电机功率。In the above formula, P max is the maximum power supply capacity of the grid, and G max is the power of all generators corresponding to the maximum power supply capacity of the grid.
优选的,所述供电分区包括:第一供电分区和第二供电分区。Preferably, the power supply partition includes: a first power supply partition and a second power supply partition.
进一步的,所述根据供电分区的电网供电裕度确定柔性直流送受端电网,包括:Further, the determination of the flexible DC sending and receiving end grid according to the grid power supply margin of the power supply partition includes:
将供电分区中电网供电裕度大的供电分区作为柔性直流送端电网,电网供电裕度小的供电分区作为柔性直流受端电网。Among the power supply partitions, the power supply partition with a large grid power supply margin is used as a flexible DC sending-end grid, and the power supply partition with a small grid power supply margin is used as a flexible DC receiving-end grid.
优选的,所述确定柔性直流额定功率上下限,并利用所述柔性直流额定功率上下限确定柔性直流额定功率限制条件,包括:Preferably, the determining the upper and lower limits of the flexible DC rated power, and using the upper and lower limits of the flexible DC rated power to determine the limiting conditions of the flexible DC rated power include:
按下式确定柔性直流额定功率下限PNmin:Determine the flexible DC rated power lower limit P Nmin according to the following formula:
PNmin=Pr-max-Pr-max-N-1 P Nmin =P r-max -P r-max-N-1
上式中,Pr-max为柔性直流并网前受端电网的最大受电能力,Pr-max-N-1为受端电网中任一下注变压器损失或任一主力电厂损失条件下的最大受电能力;In the above formula, P r-max is the maximum power receiving capacity of the receiving end grid before the flexible DC grid connection, and P r-max-N-1 is the power receiving capacity under the condition of any betting transformer loss or any main power plant loss in the receiving end grid Maximum receiving capacity;
按下式确定柔性直流额定功率上限PNmax:Determine the flexible DC rated power upper limit P Nmax according to the following formula:
PNmax=Psmax-Gs0-PTs0 P Nmax =P smax -G s0 -P Ts0
上式中,Psmax为柔性直流并网前送端电网的最大受电能力,Gs0为初始状态下送端电网所有发电机功率,PTs0为初始状态下送端电网所有下注变压器功率;In the above formula, P smax is the maximum receiving capacity of the sending-end grid before flexible DC grid-connection, G s0 is the power of all generators in the sending-end grid in the initial state, and P Ts0 is the power of all transformers in the sending-end grid in the initial state;
则柔性直流额定功率限制条件为PNmin≤PN≤PNmax,其中,PN为柔性直流额定功率。Then the limiting condition of the flexible DC rated power is P Nmin ≤ P N ≤ P Nmax , where P N is the flexible DC rated power.
优选的,所述分别确定柔性直流送受端电网的柔性直流落点母线,包括:Preferably, the respectively determining the flexible DC drop-point busbars of the flexible DC sending and receiving end grid includes:
柔性直流接入受端电网中母线后,若柔性直流受端电网中最先满载的功率下注变压器的功率减少量最大,且柔性直流受端电网的供电能力最大,则选择该母线作为柔性直流受端电网的柔性直流落点母线;After the flexible DC is connected to the busbar in the receiving-end grid, if the power reduction of the first fully-loaded power betting transformer in the flexible DC receiving-end grid is the largest, and the power supply capacity of the flexible DC receiving-end grid is the largest, then the busbar is selected as the flexible DC The flexible DC drop-point busbar of the receiving power grid;
选择汇集通道能够承载柔性直流额定容量且距离分区内电源最近的母线作为柔性直流送端电网的柔性直流落点母线。The bus that can carry the rated capacity of flexible DC and is closest to the power supply in the zone is selected as the flexible DC drop-point bus of the flexible DC sending-end grid.
优选的,所述柔性直流并网后对所述柔性直流送受端电网进行安全稳定校核,包括:Preferably, after the flexible DC is connected to the grid, the safety and stability of the flexible DC sending and receiving end grid is checked, including:
利用系统N-1故障,柔性直流单级、双极闭锁故障对所述柔性直流送受端电网进行安全稳定校核。Using system N-1 faults, flexible DC single-stage, bipolar blocking faults to check the safety and stability of the flexible DC sending and receiving end power grid.
一种用于供电分区互联的柔性直流配置装置,其改进之处在于,所述装置包括:A flexible DC configuration device for interconnection of power supply partitions, the improvement of which is that the device includes:
第一确定单元,用于根据供电分区的电网供电裕度确定柔性直流送受端电网;The first determining unit is configured to determine the flexible DC sending and receiving end grid according to the grid power supply margin of the power supply zone;
第二确定单元,用于确定柔性直流额定功率上下限,并利用所述柔性直流额定功率上下限确定柔性直流额定功率限制条件;The second determination unit is configured to determine the upper and lower limits of the flexible DC rated power, and use the upper and lower limits of the flexible DC rated power to determine the limiting conditions of the flexible DC rated power;
第三确定单元,用于分别确定柔性直流送受端电网的柔性直流落点母线;The third determination unit is used to respectively determine the flexible DC drop-point buses of the flexible DC sending and receiving end grid;
校核单元,用于柔性直流并网后对所述柔性直流送受端电网进行安全稳定校核。The checking unit is used to check the safety and stability of the flexible DC sending and receiving end grid after the flexible DC grid is connected.
优选的,按下式确定供电分区的电网供电裕度η:Preferably, the grid power supply margin η of the power supply partition is determined as follows:
上式中,PTmax为电网最大供电能力时所有下注变压器的有功功率,PT0为电网初始状态下所有下注变压器的有功功率;In the above formula, P Tmax is the active power of all transformers at the maximum power supply capacity of the grid, and P T0 is the active power of all transformers in the initial state of the grid;
其中,按下式确定电网最大供电能力时所有下注变压器的有功功率PTmax:Among them, the active power P Tmax of all betting transformers when the maximum power supply capacity of the grid is determined by the following formula:
PTmax=Pmax-Gmax P Tmax =P max -G max
上式中,Pmax为电网最大供电能力,Gmax为电网最大供电能力时对应的所有发电机功率。In the above formula, P max is the maximum power supply capacity of the grid, and G max is the power of all generators corresponding to the maximum power supply capacity of the grid.
优选的,所述供电分区包括:第一供电分区和第二供电分区。Preferably, the power supply partition includes: a first power supply partition and a second power supply partition.
进一步的,所述第一确定单元,包括:Further, the first determination unit includes:
第一确定模块,用于将供电分区中电网供电裕度大的供电分区作为柔性直流送端电网,电网供电裕度小的供电分区作为柔性直流受端电网。The first determination module is configured to use a power supply zone with a large grid power supply margin among the power supply zones as a flexible DC sending-end grid, and a power supply zone with a small grid power supply margin as a flexible DC receiving-end grid.
优选的,所述第二确定单元,包括:Preferably, the second determining unit includes:
第二确定模块,用于按下式确定柔性直流额定功率下限PNmin:The second determination module is used to determine the flexible DC rated power lower limit P Nmin according to the following formula:
PNmin=Pr-max-Pr-max-N-1 P Nmin =P r-max -P r-max-N-1
上式中,Pr-max为柔性直流并网前受端电网的最大受电能力,Pr-max-N-1为受端电网中任一下注变压器损失或任一主力电厂损失条件下的最大受电能力;In the above formula, P r-max is the maximum power receiving capacity of the receiving end grid before the flexible DC grid connection, and P r-max-N-1 is the power receiving capacity under the condition of any betting transformer loss or any main power plant loss in the receiving end grid Maximum receiving capacity;
第三确定模块,用于按下式确定柔性直流额定功率上限PNmax:The third determination module is used to determine the flexible DC rated power upper limit P Nmax according to the following formula:
PNmax=Psmax-Gs0-PTs0 P Nmax =P smax -G s0 -P Ts0
上式中,Psmax为柔性直流并网前送端电网的最大受电能力,Gs0为初始状态下送端电网所有发电机功率,PTs0为初始状态下送端电网所有下注变压器功率;In the above formula, P smax is the maximum receiving capacity of the sending-end grid before flexible DC grid-connection, G s0 is the power of all generators in the sending-end grid in the initial state, and P Ts0 is the power of all transformers in the sending-end grid in the initial state;
则柔性直流额定功率限制条件为PNmin≤PN≤PNmax,其中,PN为柔性直流额定功率。Then the limiting condition of the flexible DC rated power is P Nmin ≤ P N ≤ P Nmax , where P N is the flexible DC rated power.
优选的,所述第三确定单元,包括:Preferably, the third determination unit includes:
第一选择模块,用于柔性直流接入受端电网中母线后,若柔性直流受端电网中最先满载的功率下注变压器的功率减少量最大,且柔性直流受端电网的供电能力最大,则选择该母线作为柔性直流受端电网的柔性直流落点母线;The first selection module is used for after the flexible DC is connected to the busbar in the receiving-end grid, if the first fully-loaded power betting transformer in the flexible DC receiving-end grid has the largest power reduction, and the power supply capacity of the flexible DC receiving-end grid is the largest, Then select the busbar as the flexible DC drop-point busbar of the flexible DC receiving end grid;
第二选择模块,用于选择汇集通道能够承载柔性直流额定容量且距离分区内电源最近的母线作为柔性直流送端电网的柔性直流落点母线。The second selection module is used to select the busbar that can carry the rated capacity of flexible DC in the converging channel and is closest to the power supply in the partition as the flexible DC drop-point busbar of the flexible DC sending-end grid.
优选的,所述校核单元,包括:Preferably, the checking unit includes:
校核模块,用于利用系统N-1故障,柔性直流单级、双极闭锁故障对所述柔性直流送受端电网进行安全稳定校核。The checking module is used to check the safety and stability of the flexible DC sending and receiving end power grid by using the system N-1 fault and flexible DC single-stage and double-pole blocking faults.
本发明的有益效果:Beneficial effects of the present invention:
本发明提供的技术方案,利用供电分区的电网供电裕度确定柔性直流送受端电网,并利用柔性直流额定功率上下限确定柔性直流额定功率限制条件,同时,确定了柔性直流送受端电网的柔性直流落点母线,明确柔性直流的输电方向、额定容量及送受端落点,可提升各分区间有功、无功功率支援能力,可避免电磁环网产生,抑制短路电流超标,同时在某一分区出现故障时,可通过柔性直流功率控制提供有功、无功功率支撑,实现另一分区对故障分区的支持,提升供电可靠性。The technical solution provided by the invention uses the power supply margin of the power supply partition to determine the flexible DC sending and receiving end grid, and uses the upper and lower limits of the flexible DC rated power to determine the flexible DC rated power limit conditions, and at the same time, determines the flexible DC sending and receiving end grid. The drop-point busbar defines the transmission direction, rated capacity and drop point of the sending and receiving ends of the flexible DC, which can improve the active and reactive power support capabilities of each zone, avoid the generation of electromagnetic ring network, and suppress the short-circuit current exceeding the standard, and at the same time appear in a certain zone In the event of a fault, flexible DC power control can be used to provide active and reactive power support, enabling another partition to support the fault partition and improving power supply reliability.
附图说明Description of drawings
图1是本发明一种用于供电分区互联的柔性直流配置方法的流程图;Fig. 1 is a flow chart of a flexible DC configuration method for power supply partition interconnection according to the present invention;
图2是本发明实施例中BJ电网HC分区同CC分区的网架结构示意图;Fig. 2 is a schematic diagram of the grid structure of the HC partition and the CC partition of the BJ power grid in the embodiment of the present invention;
图3是本发明实施例中柔性直流并网后HC分区及CC分区网架结构示意图;Fig. 3 is a schematic diagram of the grid structure of the HC partition and the CC partition after the flexible DC grid connection in the embodiment of the present invention;
图4是本发明一种用于供电分区互联的柔性直流配置装置的结构示意图。Fig. 4 is a schematic structural diagram of a flexible DC configuration device for power supply partition interconnection according to the present invention.
具体实施方式detailed description
下面结合附图对本发明的具体实施方式作详细说明。The specific implementation manners of the present invention will be described in detail below in conjunction with the accompanying drawings.
为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments It is a part of embodiments of the present invention, but not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
现有电网供电分区方法存在分区供电可靠性降低,各分区间有功、无功功率支援能力不足问题,本发明提供的一种用于供电分区互联的柔性直流配置方法,通过柔性直流联接两供电分区,可避免电磁环网产生,抑制短路电流超标,同时在某一分区出现故障时,可通过柔性直流功率控制提供有功、无功功率支撑,实现另一分区对故障分区的支持,如图1所示,包括:The existing grid power supply partition method has the problems of reduced reliability of power supply in each partition and insufficient support capacity of active and reactive power between partitions. The present invention provides a flexible DC configuration method for interconnection of power supply partitions, which connects two power supply partitions through flexible DC , can avoid the generation of electromagnetic ring network, suppress the short-circuit current from exceeding the standard, and at the same time, when a fault occurs in a certain partition, it can provide active and reactive power support through flexible DC power control, and realize the support of another partition to the faulty partition, as shown in Figure 1 display, including:
101.根据供电分区的电网供电裕度确定柔性直流送受端电网;101. Determine the flexible DC sending and receiving end grid according to the grid power supply margin of the power supply zone;
102.确定柔性直流额定功率上下限,并利用所述柔性直流额定功率上下限确定柔性直流额定功率限制条件;102. Determine the upper and lower limits of the flexible DC rated power, and use the upper and lower limits of the flexible DC rated power to determine the limiting conditions for the flexible DC rated power;
103.分别确定柔性直流送受端电网的柔性直流落点母线;103. Determine the flexible DC drop-point buses of the flexible DC sending and receiving end grids respectively;
104.柔性直流并网后对所述柔性直流送受端电网进行安全稳定校核。104. After the flexible DC is connected to the grid, check the safety and stability of the flexible DC sending and receiving end grid.
其中,按下式确定供电分区的电网供电裕度η:Among them, the grid power supply margin η of the power supply partition is determined according to the following formula:
上式中,PTmax为电网最大供电能力时所有下注变压器的有功功率,PT0为电网初始状态下所有下注变压器的有功功率;In the above formula, P Tmax is the active power of all transformers at the maximum power supply capacity of the grid, and P T0 is the active power of all transformers in the initial state of the grid;
其中,按下式确定电网最大供电能力时所有下注变压器的有功功率PTmax:Among them, the active power P Tmax of all betting transformers when the maximum power supply capacity of the grid is determined by the following formula:
PTmax=Pmax-Gmax P Tmax =P max -G max
上式中,Pmax为电网最大供电能力,Gmax为电网最大供电能力时对应的所有发电机功率。In the above formula, P max is the maximum power supply capacity of the grid, and G max is the power of all generators corresponding to the maximum power supply capacity of the grid.
所述供电分区包括:第一供电分区和第二供电分区。The power supply partition includes: a first power supply partition and a second power supply partition.
本发明提供的技术方案在两个供电分区之间选择柔性直流送受端电网,因此,所述步骤101,包括:The technical solution provided by the present invention selects a flexible DC sending and receiving end grid between two power supply partitions. Therefore, the step 101 includes:
将供电分区中电网供电裕度大的供电分区作为柔性直流送端电网,电网供电裕度小的供电分区作为柔性直流受端电网。Among the power supply partitions, the power supply partition with a large grid power supply margin is used as a flexible DC sending-end grid, and the power supply partition with a small grid power supply margin is used as a flexible DC receiving-end grid.
所述步骤102,包括:The step 102 includes:
按下式确定柔性直流额定功率下限PNmin:Determine the flexible DC rated power lower limit P Nmin according to the following formula:
PNmin=Pr-max-Pr-max-N-1 P Nmin =P r-max -P r-max-N-1
上式中,Pr-max为柔性直流并网前受端电网的最大受电能力,Pr-max-N-1为受端电网中任一下注变压器损失或任一主力电厂损失条件下的最大受电能力;In the above formula, P r-max is the maximum power receiving capacity of the receiving end grid before the flexible DC grid connection, and P r-max-N-1 is the power receiving capacity under the condition of any betting transformer loss or any main power plant loss in the receiving end grid Maximum receiving capacity;
其中,柔性直流并网前受端电网的最大受电能力Pr-max为受端电网负荷按照恒功率因数增长时,任一变压器负载功率达到热稳极限时对应对的负荷总量,受端电网中任一下注变压器损失或任一主力电厂损失条件下的最大受电能力Pr-max-N-1为受端电网N-1方式下,负荷按照恒功率因数增长时,任一变压器负载功率达到热稳极限时对应对的负荷总量,取其中的最小值。Among them, the maximum power receiving capacity P r-max of the receiving-end grid before flexible DC grid-connection is the total load corresponding to the load power of any transformer when the load power of the receiving-end grid increases according to the constant power factor, and the receiving-end The maximum power receiving capacity P r-max-N-1 under the condition of loss of any betting transformer or loss of any main power plant in the power grid is N-1 mode of the receiving end power grid. When the load increases according to the constant power factor, the load of any transformer When the power reaches the thermal stability limit, take the minimum value corresponding to the total load.
按下式确定柔性直流额定功率上限PNmax:Determine the flexible DC rated power upper limit P Nmax according to the following formula:
PNmax=Psmax-Gs0-PTs0 P Nmax =P smax -G s0 -P Ts0
上式中,Psmax为柔性直流并网前送端电网的最大受电能力,Gs0为初始状态下送端电网所有发电机功率,PTs0为初始状态下送端电网所有下注变压器功率;In the above formula, P smax is the maximum receiving capacity of the sending-end grid before flexible DC grid-connection, G s0 is the power of all generators in the sending-end grid in the initial state, and P Ts0 is the power of all transformers in the sending-end grid in the initial state;
其中,柔性直流并网前送端电网的最大受电能力Psmax为送端电网负荷按照恒功率因数增长时,任一变压器负载功率达到热稳极限时对应对的负荷总量;Among them, the maximum power receiving capacity P smax of the sending-end power grid before flexible DC grid-connection is the total load corresponding to when the load power of any transformer reaches the thermal stability limit when the load of the sending-end power grid increases according to the constant power factor;
则柔性直流额定功率限制条件为PNmin≤PN≤PNmax,其中,PN为柔性直流额定功率。Then the limiting condition of the flexible DC rated power is P Nmin ≤ P N ≤ P Nmax , where P N is the flexible DC rated power.
所述步骤103,包括:The step 103 includes:
柔性直流接入受端电网中母线后,若柔性直流受端电网中最先满载的功率下注变压器的功率减少量最大,且柔性直流受端电网的供电能力最大,则选择该母线作为柔性直流受端电网的柔性直流落点母线;After the flexible DC is connected to the busbar in the receiving-end grid, if the power reduction of the first fully-loaded power betting transformer in the flexible DC receiving-end grid is the largest, and the power supply capacity of the flexible DC receiving-end grid is the largest, then the busbar is selected as the flexible DC The flexible DC drop-point busbar of the receiving power grid;
选择汇集通道能够承载柔性直流额定容量且距离分区内电源最近的母线作为柔性直流送端电网的柔性直流落点母线。The bus that can carry the rated capacity of flexible DC and is closest to the power supply in the zone is selected as the flexible DC drop-point bus of the flexible DC sending-end grid.
所述步骤4,包括:The step 4 includes:
利用系统N-1故障,柔性直流单级、双极闭锁故障对所述柔性直流送受端电网进行安全稳定校核。Using system N-1 faults, flexible DC single-stage, bipolar blocking faults to check the safety and stability of the flexible DC sending and receiving end power grid.
本发明提供一种用于供电分区互联的柔性直流配置方法的实施例,对BJ电网进行分析计算,提出应用柔性直流互联BJ220kV供电分区的配置方案,BJ电网HC分区同CC分区的网架结构如图2所示,CC分区有三台500kV/220kV功率下注变压器,分别为CP1、CP2及CB2,额定功率分别为800MW、800MW及1200MW;HC分区有两台500kV/220kV功率下注变压器,分别为HD2、CP3,额定功率均为1200MW。The present invention provides an embodiment of a flexible DC configuration method for the interconnection of power supply partitions, analyzes and calculates the BJ power grid, and proposes a configuration scheme for applying flexible DC interconnection to BJ220kV power supply partitions. The grid structure of the HC partition and the CC partition of the BJ power grid is as follows As shown in Figure 2, there are three 500kV/220kV power transformers in the CC division, namely CP1, CP2 and CB2, with rated powers of 800MW, 800MW and 1200MW respectively; there are two 500kV/220kV power transformers in the HC division, respectively The rated power of HD2 and CP3 is 1200MW.
步骤1:柔性直流送受端电网选择。Step 1: Selection of the power grid at the flexible DC sending and receiving end.
分别计算CC分区和HC分区的供电裕度。Calculate the power supply margins of the CC partition and the HC partition respectively.
针对CC分区,负荷按照恒功率因数增长,当有功负荷增长至3300MW时,CP2主变功率达到800MW,达到热稳极限,则Pmax-CC为3300MW,此时CC分区所有发电机出力Gmax-CC为795MW,则PTmax-CC为2505MW,通过初试潮流可知CP1、CP2及CB2分别为252.1、255.4及297.6MW,即PT0-CC=805MW则可知:For the CC partition, the load increases according to the constant power factor. When the active load increases to 3300MW, the power of the CP2 main transformer reaches 800MW and reaches the limit of thermal stability, then P max-CC is 3300MW. At this time, the output of all generators in the CC partition is G max- CC is 795MW, then PTmax -CC is 2505MW. According to the preliminary power flow test, CP1, CP2 and CB2 are 252.1, 255.4 and 297.6MW respectively, that is, PT0 -CC = 805MW, it can be known that:
同理可知,针对HC分区,Pmax-HC为3870MW,Gmax-HC为1875MW,PTmax-HC为1995MW,PT0-HC为950MW,则ηHC为1.10,所以选择CC分区作为互联柔性直流的送端,HC分区作为互联柔性直流的受端。Similarly, for HC partition, P max-HC is 3870MW, G max-HC is 1875MW, P Tmax-HC is 1995MW, P T0-HC is 950MW, then η HC is 1.10, so CC partition is selected as the interconnection flexible DC The sending end of the HC partition serves as the receiving end of the interconnected flexible DC.
步骤2:柔性直流额定容量选择。Step 2: Selection of flexible DC rated capacity.
(1)通过受端电网确定柔性直流额定功率下限。(1) Determine the lower limit of the flexible DC rated power through the receiving end grid.
由步骤1可知柔性直流并网前受端电网HC分区的最大受电能力Pr-max为3830MW。计算不同下注变压器、主力电厂损失条件下,受端电网最大受电能力结果如表1所示:From step 1, it can be seen that the maximum power receiving capacity P r-max of the HC partition of the receiving end grid before the flexible DC grid connection is 3830MW. The results of calculating the maximum power receiving capacity of the receiving end power grid under the conditions of different power transformers and main power plants are shown in Table 1:
表1不同下注变压器、主力电厂损失条件下,受端电网最大受电能力Table 1 The maximum power receiving capacity of the receiving end power grid under the conditions of different transformers and main power plant losses
则Pr-max-N-1=2855MW,相应地,柔性直流额定功率下限PNmin为975MW。Then P r-max-N-1 =2855MW, correspondingly, the lower limit P Nmin of the flexible DC rated power is 975MW.
(2)通过送端电网确定柔性直流额定功率上限。(2) Determine the upper limit of the flexible DC rated power through the power grid at the sending end.
由步骤1可知,柔性直流并网前送端电网CC分区的最大受电能力Ps-max为3870MW,PTs0为950MW,由潮流结果可知Gs0为785MW,柔性直流额定功率上限PNmax为:It can be seen from step 1 that the maximum power receiving capacity P s-max of the CC partition of the sending-end power grid before flexible DC grid-connection is 3870 MW, P Ts0 is 950 MW, and G s0 is 785 MW from the power flow results, and the upper limit of the flexible DC rated power P Nmax is:
PNmax=Psmax-Gs0-PTs0 P Nmax =P smax -G s0 -P Ts0
=3870-785-950 =3870-785-950
=2135 =2135
从而在为其他分区提供功率支援时,不影响本分区电网安全供电。Therefore, when providing power support for other partitions, it will not affect the safe power supply of the power grid in this partition.
3)结合送端电网和受端电网的不同要求,柔性直流额定功率PN满足:975≤PN≤2135;结合柔性直流工程实践,确定柔性直流额定功率PN为1000MW。3) Combined with the different requirements of the sending-end power grid and the receiving-end power grid, the flexible DC rated power P N satisfies: 975≤P N≤2135 ; combined with the flexible DC engineering practice, the flexible DC rated power P N is determined to be 1000MW.
步骤3:柔性直流送受端落点选择。Step 3: Select the landing point of the flexible DC sending and receiving terminal.
(1)计算柔性直流受端落点不同母线后,原受端电网供电能力限值条件的改善情况。柔性直流额定功率PN为1000MW,从经济性和安全性两个方面考虑,应选择负荷大且疏散通道多的母线作为受端落点。初步选择XST、SZ及KYH母线,计算柔性直流分别接入这些母线后供电能力限值条件的改善情况,如表2所示:(1) Calculate the improvement of the power supply capacity limit conditions of the original receiving end power grid after calculating the different busbars at the flexible DC receiving end. The flexible DC rated power PN is 1000MW. Considering economy and safety, the busbar with heavy load and many evacuation channels should be selected as the receiving end drop point. Initially select the XST, SZ and KYH buses, and calculate the improvement of the power supply capacity limit conditions after the flexible DC is respectively connected to these buses, as shown in Table 2:
表2柔性直流接入不同母线后,供电能力限值条件改善情况Table 2 Improvement of power supply capacity limit conditions after flexible DC is connected to different buses
(2)计算柔性直流受端落点不同母线后,受端电网供电能力,结果见表3:(2) Calculate the power supply capacity of the receiving end grid after the flexible DC receiving end is placed on different buses, and the results are shown in Table 3:
表3柔性直流接入不同母线后HC供电能力Table 3 HC power supply capacity after flexible DC is connected to different buses
(3)综合柔性直流落点不同母线后对供电能力及限值条件的影响,选出柔性直流受端落点。由表2、表3可知,柔性直流落点XST母线可使CP2主变下注功率减少最大,并对HC分区的供电能力提上提升最大,故选择XST母线作为柔性直流受端落点。(3) Integrating the influence of different busbars on the power supply capacity and limit conditions of the flexible DC landing point, the flexible DC receiving terminal landing point is selected. It can be seen from Table 2 and Table 3 that the XST busbar of the flexible DC drop point can reduce the power of the CP2 main transformer to the greatest extent, and increase the power supply capacity of the HC partition the most, so the XST busbar is selected as the drop point of the flexible DC receiving terminal.
(4)结合柔性直流输送功率及送端网架结构确定柔性直流送端落点。通过步骤2可知,柔性直流额定功率PN为1000MW,从安全性方面考虑,应选择汇集通道多的母线节点,以降低每个通道的输送容量;从经济性考虑,应选择离电源较近的母线节点,从而将富裕电力直接通过柔性直流送往受端负荷区域,减少损耗。从以上两方面考虑,结合送端网架结构,筛选送端母线节点后发现,HJY母线离电源最近,且有3个汇集通道,最适宜作为柔性直流送端母线。(4) Combining the flexible DC transmission power and the grid structure of the sending end to determine the drop point of the flexible DC sending end. It can be seen from step 2 that the rated power of flexible DC is 1000MW . From the perspective of safety, bus nodes with more converging channels should be selected to reduce the transmission capacity of each channel; from the perspective of economy, one should be selected closer to the power supply. The bus node, so that the rich power can be directly sent to the load area of the receiving end through flexible DC to reduce losses. Considering the above two aspects, combined with the sending-end grid structure, after screening the sending-end bus nodes, it is found that the HJY bus is the closest to the power supply and has 3 converging channels, which is most suitable as a flexible DC sending-end bus.
步骤4:柔性直流并网后安全稳定校核。Step 4: Check the safety and stability of the flexible DC grid after grid connection.
柔性直流并网后安全稳定校核,主要包括交流系统N-1故障,柔性直流单级、双极闭锁故障,结果见表4:The safety and stability check after flexible DC grid connection mainly includes AC system N-1 faults, flexible DC single-stage and double-pole blocking faults, and the results are shown in Table 4:
表4不容功率下注变压器N-1故障后安全稳定校核结果Table 4 Safety and Stability Check Results of Transformer N-1 Not Allowed to Power Down After Fault
柔性直流并网后HC分区及CC分区网架结构如图3所示。Figure 3 shows the grid structure of HC partition and CC partition after flexible DC grid connection.
本发明还提供一种用于供电分区互联的柔性直流配置装置,如图4所示,所述装置包括:The present invention also provides a flexible DC configuration device for power supply partition interconnection, as shown in Figure 4, the device includes:
第一确定单元,用于根据供电分区的电网供电裕度确定柔性直流送受端电网;The first determining unit is configured to determine the flexible DC sending and receiving end grid according to the grid power supply margin of the power supply zone;
第二确定单元,用于确定柔性直流额定功率上下限,并利用所述柔性直流额定功率上下限确定柔性直流额定功率限制条件;The second determination unit is configured to determine the upper and lower limits of the flexible DC rated power, and use the upper and lower limits of the flexible DC rated power to determine the limiting conditions of the flexible DC rated power;
第三确定单元,用于分别确定柔性直流送受端电网的柔性直流落点母线;The third determination unit is used to respectively determine the flexible DC drop-point buses of the flexible DC sending and receiving end grid;
校核单元,用于柔性直流并网后对所述柔性直流送受端电网进行安全稳定校核。The checking unit is used to check the safety and stability of the flexible DC sending and receiving end grid after the flexible DC grid is connected.
其中,按下式确定供电分区的电网供电裕度η:Among them, the grid power supply margin η of the power supply partition is determined according to the following formula:
上式中,PTmax为电网最大供电能力时所有下注变压器的有功功率,PT0为电网初始状态下所有下注变压器的有功功率;In the above formula, P Tmax is the active power of all transformers at the maximum power supply capacity of the grid, and P T0 is the active power of all transformers in the initial state of the grid;
其中,按下式确定电网最大供电能力时所有下注变压器的有功功率PTmax:Among them, the active power P Tmax of all betting transformers when the maximum power supply capacity of the grid is determined by the following formula:
PTmax=Pmax-Gmax P Tmax =P max -G max
上式中,Pmax为电网最大供电能力,Gmax为电网最大供电能力时对应的所有发电机功率。In the above formula, P max is the maximum power supply capacity of the grid, and G max is the power of all generators corresponding to the maximum power supply capacity of the grid.
所述供电分区包括:第一供电分区和第二供电分区。The power supply partition includes: a first power supply partition and a second power supply partition.
具体的,所述第一确定单元,包括:Specifically, the first determining unit includes:
第一确定模块,用于将供电分区中电网供电裕度大的供电分区作为柔性直流送端电网,电网供电裕度小的供电分区作为柔性直流受端电网。The first determination module is configured to use a power supply zone with a large grid power supply margin among the power supply zones as a flexible DC sending-end grid, and a power supply zone with a small grid power supply margin as a flexible DC receiving-end grid.
所述第二确定单元,包括:The second determination unit includes:
第二确定模块,用于按下式确定柔性直流额定功率下限PNmin:The second determination module is used to determine the flexible DC rated power lower limit P Nmin according to the following formula:
PNmin=Pr-max-Pr-max-N-1 P Nmin =P r-max -P r-max-N-1
上式中,Pr-max为柔性直流并网前受端电网的最大受电能力,Pr-max-N-1为受端电网中任一下注变压器损失或任一主力电厂损失条件下的最大受电能力;In the above formula, P r-max is the maximum power receiving capacity of the receiving end grid before the flexible DC grid connection, and P r-max-N-1 is the power receiving capacity under the condition of any betting transformer loss or any main power plant loss in the receiving end grid Maximum receiving capacity;
第三确定模块,用于按下式确定柔性直流额定功率上限PNmax:The third determination module is used to determine the flexible DC rated power upper limit P Nmax according to the following formula:
PNmax=Psmax-Gs0-PTs0 P Nmax =P smax -G s0 -P Ts0
上式中,Psmax为柔性直流并网前送端电网的最大受电能力,Gs0为初始状态下送端电网所有发电机功率,PTs0为初始状态下送端电网所有下注变压器功率;In the above formula, P smax is the maximum receiving capacity of the sending-end grid before flexible DC grid-connection, G s0 is the power of all generators in the sending-end grid in the initial state, and P Ts0 is the power of all transformers in the sending-end grid in the initial state;
则柔性直流额定功率限制条件为PNmin≤PN≤PNmax,其中,PN为柔性直流额定功率。Then the limiting condition of the flexible DC rated power is P Nmin ≤ P N ≤ P Nmax , where P N is the flexible DC rated power.
所述第三确定单元,包括:The third determination unit includes:
第一选择模块,用于柔性直流接入受端电网中母线后,若柔性直流受端电网中最先满载的功率下注变压器的功率减少量最大,且柔性直流受端电网的供电能力最大,则选择该母线作为柔性直流受端电网的柔性直流落点母线;The first selection module is used for after the flexible DC is connected to the busbar in the receiving-end grid, if the first fully-loaded power betting transformer in the flexible DC receiving-end grid has the largest power reduction, and the power supply capacity of the flexible DC receiving-end grid is the largest, Then select the busbar as the flexible DC drop-point busbar of the flexible DC receiving end grid;
第二选择模块,用于选择汇集通道能够承载柔性直流额定容量且距离分区内电源最近的母线作为柔性直流送端电网的柔性直流落点母线。The second selection module is used to select the busbar that can carry the rated capacity of flexible DC in the converging channel and is closest to the power supply in the partition as the flexible DC drop-point busbar of the flexible DC sending-end grid.
所述校核单元,包括:The checking unit includes:
校核模块,用于利用系统N-1故障,柔性直流单级、双极闭锁故障对所述柔性直流送受端电网进行安全稳定校核。The checking module is used to check the safety and stability of the flexible DC sending and receiving end power grid by using the system N-1 fault and flexible DC single-stage and double-pole blocking faults.
本领域内的技术人员应明白,本申请的实施例可提供为方法、系统、或计算机程序产品。因此,本申请可采用完全硬件实施例、完全软件实施例、或结合软件和硬件方面的实施例的形式。而且,本申请可采用在一个或多个其中包含有计算机可用程序代码的计算机可用存储介质(包括但不限于磁盘存储器、CD-ROM、光学存储器等)上实施的计算机程序产品的形式。Those skilled in the art should understand that the embodiments of the present application may be provided as methods, systems, or computer program products. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) having computer-usable program code embodied therein.
本申请是参照根据本申请实施例的方法、设备(系统)、和计算机程序产品的流程图和/或方框图来描述的。应理解可由计算机程序指令实现流程图和/或方框图中的每一流程和/或方框、以及流程图和/或方框图中的流程和/或方框的结合。可提供这些计算机程序指令到通用计算机、专用计算机、嵌入式处理机或其他可编程数据处理设备的处理器以产生一个机器,使得通过计算机或其他可编程数据处理设备的处理器执行的指令产生用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的装置。The present application is described with reference to flowcharts and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the present application. It should be understood that each procedure and/or block in the flowchart and/or block diagram, and a combination of procedures and/or blocks in the flowchart and/or block diagram can be realized by computer program instructions. These computer program instructions may be provided to a general purpose computer, special purpose computer, embedded processor, or processor of other programmable data processing equipment to produce a machine such that the instructions executed by the processor of the computer or other programmable data processing equipment produce a An apparatus for realizing the functions specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.
这些计算机程序指令也可存储在能引导计算机或其他可编程数据处理设备以特定方式工作的计算机可读存储器中,使得存储在该计算机可读存储器中的指令产生包括指令装置的制造品,该指令装置实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能。These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing apparatus to operate in a specific manner, such that the instructions stored in the computer-readable memory produce an article of manufacture comprising instruction means, the instructions The device realizes the function specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.
这些计算机程序指令也可装载到计算机或其他可编程数据处理设备上,使得在计算机或其他可编程设备上执行一系列操作步骤以产生计算机实现的处理,从而在计算机或其他可编程设备上执行的指令提供用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的步骤。These computer program instructions can also be loaded onto a computer or other programmable data processing device, causing a series of operational steps to be performed on the computer or other programmable device to produce a computer-implemented process, thereby The instructions provide steps for implementing the functions specified in the flow chart or blocks of the flowchart and/or the block or blocks of the block diagrams.
最后应当说明的是:以上实施例仅用以说明本发明的技术方案而非对其限制,尽管参照上述实施例对本发明进行了详细的说明,所属领域的普通技术人员应当理解:依然可以对本发明的具体实施方式进行修改或者等同替换,而未脱离本发明精神和范围的任何修改或者等同替换,其均应涵盖在本发明的权利要求保护范围之内。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit them. Although the present invention has been described in detail with reference to the above embodiments, those of ordinary skill in the art should understand that: the present invention can still be Any modifications or equivalent replacements that do not depart from the spirit and scope of the present invention shall fall within the protection scope of the claims of the present invention.
Claims (14)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710556583.XA CN107453383B (en) | 2017-07-10 | 2017-07-10 | Flexible direct current configuration method and device for power supply partition interconnection |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710556583.XA CN107453383B (en) | 2017-07-10 | 2017-07-10 | Flexible direct current configuration method and device for power supply partition interconnection |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107453383A true CN107453383A (en) | 2017-12-08 |
CN107453383B CN107453383B (en) | 2021-04-30 |
Family
ID=60488762
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710556583.XA Active CN107453383B (en) | 2017-07-10 | 2017-07-10 | Flexible direct current configuration method and device for power supply partition interconnection |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107453383B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108182493A (en) * | 2017-12-29 | 2018-06-19 | 国网宁夏电力有限公司 | A kind of site selecting method and system of power supply zone interconnection point |
CN108493976A (en) * | 2018-02-28 | 2018-09-04 | 中国电力科学研究院有限公司 | A kind of method and system applied to the back-to-back device drop point selection of flexible direct current and capacity configuration |
CN108988374A (en) * | 2018-06-22 | 2018-12-11 | 国家电网公司华中分部 | The Optimal Configuration Method of flexible direct current interconnect device position in transmission cross-section |
CN111987720A (en) * | 2020-08-26 | 2020-11-24 | 国网江苏省电力有限公司 | Method for evaluating power receiving and power supply margin intervals of receiving-end power grid under constraint of multichannel quota |
CN112952887A (en) * | 2021-02-05 | 2021-06-11 | 国网四川省电力公司经济技术研究院 | Method and system for evaluating direct current bearing capacity of sending-end power grid |
CN113922409A (en) * | 2021-10-19 | 2022-01-11 | 国网江苏省电力有限公司 | Constant volume method for multi-partition flexible interconnected converter station of urban power grid |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104934982A (en) * | 2015-05-21 | 2015-09-23 | 广东电网有限责任公司电网规划研究中心 | Direct current partitioning method for multi-direct current feed-in system |
US20160308359A1 (en) * | 2012-11-08 | 2016-10-20 | Nr Electric Co., Ltd | Coordination control method of multi-terminal VSC-HVDC transmission system |
CN106451446A (en) * | 2016-12-07 | 2017-02-22 | 天津大学 | Constant volume method of urban power grid district-dividing interconnection device based on flexible direct current technology |
CN106786557A (en) * | 2017-01-23 | 2017-05-31 | 中国电力科学研究院 | A kind of extra-high voltage is layered D.C. capacity and drop point system of selection and system |
CN106875287A (en) * | 2015-12-11 | 2017-06-20 | 中国电力科学研究院 | A kind of power system switched-mode power supply capacity judging method |
CN106911131A (en) * | 2015-12-22 | 2017-06-30 | 国网智能电网研究院 | A kind of em ergency power support control method of AC network subregion interconnect device |
-
2017
- 2017-07-10 CN CN201710556583.XA patent/CN107453383B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20160308359A1 (en) * | 2012-11-08 | 2016-10-20 | Nr Electric Co., Ltd | Coordination control method of multi-terminal VSC-HVDC transmission system |
CN104934982A (en) * | 2015-05-21 | 2015-09-23 | 广东电网有限责任公司电网规划研究中心 | Direct current partitioning method for multi-direct current feed-in system |
CN106875287A (en) * | 2015-12-11 | 2017-06-20 | 中国电力科学研究院 | A kind of power system switched-mode power supply capacity judging method |
CN106911131A (en) * | 2015-12-22 | 2017-06-30 | 国网智能电网研究院 | A kind of em ergency power support control method of AC network subregion interconnect device |
CN106451446A (en) * | 2016-12-07 | 2017-02-22 | 天津大学 | Constant volume method of urban power grid district-dividing interconnection device based on flexible direct current technology |
CN106786557A (en) * | 2017-01-23 | 2017-05-31 | 中国电力科学研究院 | A kind of extra-high voltage is layered D.C. capacity and drop point system of selection and system |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108182493A (en) * | 2017-12-29 | 2018-06-19 | 国网宁夏电力有限公司 | A kind of site selecting method and system of power supply zone interconnection point |
CN108182493B (en) * | 2017-12-29 | 2023-11-14 | 国网宁夏电力有限公司 | A location selection method and system for power supply zone interconnection points |
CN108493976A (en) * | 2018-02-28 | 2018-09-04 | 中国电力科学研究院有限公司 | A kind of method and system applied to the back-to-back device drop point selection of flexible direct current and capacity configuration |
CN108988374A (en) * | 2018-06-22 | 2018-12-11 | 国家电网公司华中分部 | The Optimal Configuration Method of flexible direct current interconnect device position in transmission cross-section |
CN108988374B (en) * | 2018-06-22 | 2021-11-02 | 国家电网公司华中分部 | Optimal configuration method of flexible DC interconnection device location in transmission section |
CN111987720A (en) * | 2020-08-26 | 2020-11-24 | 国网江苏省电力有限公司 | Method for evaluating power receiving and power supply margin intervals of receiving-end power grid under constraint of multichannel quota |
CN112952887A (en) * | 2021-02-05 | 2021-06-11 | 国网四川省电力公司经济技术研究院 | Method and system for evaluating direct current bearing capacity of sending-end power grid |
CN113922409A (en) * | 2021-10-19 | 2022-01-11 | 国网江苏省电力有限公司 | Constant volume method for multi-partition flexible interconnected converter station of urban power grid |
CN113922409B (en) * | 2021-10-19 | 2024-03-22 | 国网江苏省电力有限公司 | Constant volume method for urban power grid multi-partition flexible interconnection converter station |
Also Published As
Publication number | Publication date |
---|---|
CN107453383B (en) | 2021-04-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107453383A (en) | A kind of flexible direct current collocation method and device for power supply zone interconnection | |
CN104993513B (en) | Control method and system for battery energy storage power station supporting black start of photovoltaic storage power generation system | |
CN111668846A (en) | A photovoltaic dual-mode self-adaptive cross-platform absorption method and system | |
CN104022527B (en) | Direct current micro-grid system | |
Shu et al. | A back-to-back VSC-HVDC system of Yu-E power transmission lines to improve cross-region capacity | |
CN107221930A (en) | A kind of intelligent Sofe Switch service restoration method of active power distribution network | |
CN109193734B (en) | Adaptive evaluation method and system of AC and DC power grid for DC system restoration | |
CN103701146B (en) | A method to improve DC transmission capacity under DC fault steady-state voltage constraints | |
CN105527545A (en) | DC power distribution network dynamic simulation experimental device and method | |
CN114629174A (en) | Microgrid operation control method, control device and microgrid | |
CN115333246B (en) | Chain energy Internet of Things, chain energy coupling method, equipment and medium | |
CN205212448U (en) | Black start -up system suitable for light stores up little electric wire netting | |
CN109617098B (en) | Internal three-phase unbalance disturbance suppression method suitable for micro-grid group | |
Yang et al. | Dynamic performance of series multiterminal HVDC during AC faults at inverter stations | |
CN111740427A (en) | A reactive power compensation configuration method and system for an offshore wind farm access system | |
CN205450176U (en) | Dynamic simulation experiment device of DC distribution net | |
Bhuyan et al. | Contingency analysis of low voltage DC microgrid | |
Lin et al. | Coordinated power control strategy of voltage source converter‐based multiterminal high‐voltage direct current based on the voltage‐current curve | |
CN111244999B (en) | Control method of hybrid energy consumption device | |
CN207910525U (en) | A kind of pure electric vehicle AC power output system device peculiar to vessel | |
Yousefpoor et al. | Convertible static transmission controller (CSTC) system model validation by controller hardware-in-the-loop-simulation | |
CN111628490A (en) | Direct current transformer substation based on modularized double-active-bridge converter | |
CN106058915A (en) | Active grid-connected-to-off-network switching control method based on single-phase multiple microgrids | |
Zhang et al. | Cooperative AC/DC Voltage Margin Control for Mitigating Voltage Violation of Rural Distribution Networks With Interconnected DC Link | |
CN111711210B (en) | Energy storage system and offshore wind power device suitable for offshore wind power |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |