[go: up one dir, main page]

CN107246003B - Device for improving radial perpendicularity of underground diaphragm wall reinforcement cage and construction method - Google Patents

Device for improving radial perpendicularity of underground diaphragm wall reinforcement cage and construction method Download PDF

Info

Publication number
CN107246003B
CN107246003B CN201710583876.7A CN201710583876A CN107246003B CN 107246003 B CN107246003 B CN 107246003B CN 201710583876 A CN201710583876 A CN 201710583876A CN 107246003 B CN107246003 B CN 107246003B
Authority
CN
China
Prior art keywords
steel
poured
bars
cage
shaped steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710583876.7A
Other languages
Chinese (zh)
Other versions
CN107246003A (en
Inventor
张其玉
张金禄
汤剑辉
徐涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Construction Co Ltd Of Cccc Second Highway Engineering Co ltd
Original Assignee
CCCC SHEC Second Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Second Engineering Co Ltd filed Critical CCCC SHEC Second Engineering Co Ltd
Priority to CN201710583876.7A priority Critical patent/CN107246003B/en
Publication of CN107246003A publication Critical patent/CN107246003A/en
Application granted granted Critical
Publication of CN107246003B publication Critical patent/CN107246003B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Reinforcement Elements For Buildings (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention belongs to the technical field of building construction methods and devices, and particularly relates to a device and a construction method for improving radial perpendicularity of an underground continuous wall reinforcement cage. The invention solves the problem of larger radial deflection generated in the process of lowering the reinforcement cage due to the influence of the rigidity of the reinforcement cage and the backfill material on the back side of the H-shaped steel, adopts the triangular support and the comb-tooth steel plate, takes measures from two directions of horizontal and vertical, controls the integral deflection of the reinforcement cage, and has more obvious effect; the existing reinforcing steel bars on site are utilized, the construction is simple, the cost is low, the material cost and the labor cost can be effectively saved, and the purposes of small investment and good effect are achieved.

Description

一种提高地下连续墙钢筋笼径向垂直度的装置和施工方法A device and construction method for improving the radial verticality of underground continuous wall steel cages

技术领域Technical field

本发明属于建筑施工方法以及装置技术领域,具体涉及一种提高地下连续墙钢筋笼径向垂直度的装置和施工方法。The invention belongs to the technical field of building construction methods and devices, and specifically relates to a device and a construction method for improving the radial verticality of underground continuous wall steel cages.

背景技术Background technique

地下连续墙在大型公路、市政及水利工程中广泛使用,尤其是随着施工设备的改进和对设计技能的提升,地下连续墙向着更深、更大的方向发展,H型钢接头是最为常见的接头处理方式。Underground diaphragm walls are widely used in large highways, municipalities and water conservancy projects. Especially with the improvement of construction equipment and the improvement of design skills, underground diaphragm walls are developing in a deeper and larger direction. H-shaped steel joints are the most common joints. processing method.

为了满足钢筋笼顺直下放的要求,在设计时已浇筑完成槽段的H型钢与待浇筑槽段的钢筋笼之间有约25cm的间隙,但在钢筋笼下放的过程中,尤其是超深地下连续墙钢筋笼,受钢筋笼自身刚度影响,垂直度不好控制,再次受H型钢背侧回材料的影响,向已浇筑侧产生水平推力,导致钢筋笼整体偏向已浇筑侧;另外,槽段成孔深度一般略深于设计值,及H型钢略短于设置孔深,导致H型钢在底部产生悬空,加大了在H型钢背侧回填材料时的钢筋笼偏移量,最终导致整个钢筋笼的径向偏移量达到60cm以上。In order to meet the requirements for the steel cage to be lowered straight down, there is a gap of about 25cm between the H-shaped steel that has been poured in the trough section and the steel cage in the trough section to be poured during the design. However, during the process of lowering the steel cage, especially the ultra-deep The underground continuous wall steel cage is affected by the stiffness of the steel cage itself, and the verticality is difficult to control. It is also affected by the material on the back side of the H-shaped steel, which generates horizontal thrust towards the poured side, causing the overall steel cage to deviate to the poured side; in addition, the groove The hole depth of the section is generally slightly deeper than the designed value, and the H-shaped steel is slightly shorter than the set hole depth, causing the H-shaped steel to be suspended at the bottom, increasing the offset of the steel cage when backfilling material on the back side of the H-shaped steel, and ultimately causing the entire The radial offset of the steel cage reaches more than 60cm.

发明内容Contents of the invention

本发明的目的是克服现有技术中受钢筋笼刚度和H型钢背侧回填材料影响导致钢筋笼在下放的过程中产生的较大的径向偏移问题。The purpose of the present invention is to overcome the problem of large radial deflection in the prior art caused by the stiffness of the steel cage and the backfill material on the back of the H-shaped steel, which causes the steel cage to be lowered during the lowering process.

为此,本发明提供了一种提高地下连续墙钢筋笼径向垂直度的装置,包括已浇筑槽段的H型钢、待浇筑槽段钢筋笼、待浇筑侧H型钢和待浇筑开挖槽孔,已浇筑槽段的H型钢竖直连接在已浇筑槽段和待浇筑开挖槽孔交接处,待浇筑槽段钢筋笼位于待浇筑开挖槽孔内,待浇筑槽段钢筋笼一侧与已浇筑槽段的H型钢之间具有间隙,待浇筑槽段钢筋笼另一侧连接待浇筑侧H型钢,已浇筑槽段的H型钢包括H型钢翼缘板和H型钢腹板,H型钢腹板的两端均连接H型钢翼缘板,待浇筑槽段钢筋笼包括多条横筋和纵筋,横筋垂直连接纵筋,待浇筑侧H型钢包括钢翼缘板和钢腹板,钢腹板两端分别连接钢翼缘板,还包括三角支撑和梳齿钢筋,三角支撑水平连接待浇筑槽段钢筋笼且位于间隙内,梳齿钢筋竖直连接在待浇筑侧H型钢底部和待浇筑开挖槽孔底部之间。To this end, the present invention provides a device for improving the radial verticality of underground diaphragm wall steel cages, including H-shaped steel in the poured channel section, steel cages in the channel section to be poured, side H-shaped steel to be poured, and excavated slots to be poured. , the H-shaped steel of the poured trough section is vertically connected at the intersection of the poured trough section and the excavated slot hole to be poured. The steel cage of the trough section to be poured is located in the excavated slot hole to be poured. One side of the steel cage of the trough section to be poured is connected to There is a gap between the H-shaped steel in the poured trough section. The other side of the steel cage in the trough section to be poured is connected to the H-shaped steel on the side to be poured. The H-shaped steel in the poured trough section includes H-shaped steel flange plates and H-shaped steel webs. The H-shaped steel web Both ends of the plate are connected to H-shaped steel flange plates. The steel cage of the channel section to be poured includes multiple transverse and longitudinal bars. The transverse bars are vertically connected to the longitudinal bars. The H-shaped steel on the side to be poured includes steel flange plates and steel webs. The steel webs Both ends are connected to steel flange plates respectively, and also include triangular supports and comb-toothed steel bars. The triangular supports are horizontally connected to the steel cages of the tank sections to be poured and are located in the gaps. The comb-toothed steel bars are vertically connected to the bottom of the H-shaped steel on the side to be poured and the opening to be poured. Dig between the bottoms of the trench holes.

所述的三角支撑包括水平钢筋、中间水平钢筋和竖向联系钢筋,水平钢筋和中间水平钢筋一端连接横筋且水平钢筋数量为两个分别位于中间水平钢筋两侧,中间水平钢筋垂直连接横筋,水平钢筋和中间水平钢筋的另一端汇集连接竖向联系钢筋。The triangular support includes a horizontal steel bar, a middle horizontal steel bar and a vertical connecting steel bar. One end of the horizontal steel bar and the middle horizontal steel bar is connected to the horizontal bar, and the number of horizontal steel bars is two, respectively located on both sides of the middle horizontal steel bar. The middle horizontal steel bar is vertically connected to the horizontal bar. The other end of the steel bar and the middle horizontal steel bar are brought together to connect the vertical contact steel bars.

所述的待浇筑槽段钢筋笼竖向每隔2m连接一个三角支撑,三角支撑与H型钢腹板之间的间距为10cm,水平钢筋和中间水平钢筋的直径长度为28mm,竖向联系钢筋的直径长度为20mm。The steel cage of the groove section to be poured is vertically connected to a triangular support every 2m. The distance between the triangular support and the H-shaped steel web is 10cm. The diameter length of the horizontal steel bar and the middle horizontal steel bar is 28mm. The vertical contact steel bar is Diameter length is 20mm.

所述的梳齿钢筋双面焊接在待浇筑侧H型钢底部内侧,梳齿钢筋数量为多个且相邻两个的间距为15cm,梳齿钢筋的直径长度为20mm,焊脚高度不小于6mm,梳齿钢筋深入待浇筑开挖槽孔底部深度为10cm。The comb-toothed steel bars are double-sided welded on the inside of the bottom of the H-shaped steel on the side to be poured. The number of comb-toothed steel bars is multiple and the distance between two adjacent ones is 15cm. The diameter of the comb-toothed steel bars is 20mm, and the welding leg height is not less than 6mm. , the depth of the comb-toothed steel bars into the bottom of the trench to be poured is 10cm.

一种提高地下连续墙钢筋笼径向垂直度的施工方法,包括如下步骤:A construction method for improving the radial verticality of underground diaphragm wall steel cages, including the following steps:

1)对待浇筑开挖槽孔进行成孔检测,确定成孔深度和已浇筑槽段的H型钢的垂直度;1) Conduct hole formation inspection on the trench holes to be poured and excavated to determine the depth of the hole formation and the verticality of the H-shaped steel in the poured trench section;

2)确定三角支撑高度和梳齿钢筋长度;2) Determine the height of the triangular support and the length of the comb steel bars;

3)备料:根据三角支撑高度和梳齿钢筋长度准备相应的钢筋;3) Material preparation: Prepare corresponding steel bars according to the height of the triangular support and the length of the comb steel bars;

4)焊接三角支撑:首先确定焊接位置并标识,然后找出备好的钢筋材料逐根逐处焊接,最后利用竖向联系钢筋将三角支撑连成整体;4) Welding the triangular support: first determine the welding position and mark it, then find the prepared steel bar materials and weld them one by one, and finally use vertical connecting steel bars to connect the triangular support into a whole;

5)焊接梳齿钢筋:首先在待浇筑侧H型钢底部定位和标识,将备好的钢筋逐根焊接到待浇筑侧H型钢上,焊接完成后确保各根钢筋顺直、无弯曲变形;5) Welding comb steel bars: First, locate and mark the bottom of the H-shaped steel on the side to be poured, and weld the prepared steel bars one by one to the H-shaped steel on the side to be poured. After the welding is completed, ensure that each steel bar is straight and has no bending deformation;

6)下放待浇筑槽段钢筋笼:待浇筑开挖槽孔检测合格后,下放待浇筑槽段钢筋笼,下方时三角支撑和已浇筑槽段的H型钢不可相互碰撞;6) Lower the steel cage of the trough section to be poured: After the excavated slot hole to be poured has passed the test, lower the steel cage of the trough section to be poured. The triangular support and the H-shaped steel of the poured trough section cannot collide with each other when lowered;

7)水下连续灌注混凝土,灌注时确保待浇筑槽段钢筋笼不移动和不上浮。7) Continuously pour concrete underwater. During pouring, ensure that the steel cage of the tank section to be poured does not move or float.

所述的备料的钢筋顺直、无污染和无质量缺陷。The steel bars prepared as described are straight, pollution-free and have no quality defects.

本发明的有益效果:本发明提供的这种提高地下连续墙钢筋笼径向垂直度的装置和施工方法,三角支撑设置在H型钢和钢筋笼之间,减小了H型钢和钢筋笼之间可以移动的间隙,梳齿钢板掺入槽孔底部,限制了钢筋笼的自由活动,同时可以避免回填材料从H型钢底部滑入待浇筑槽段,有效的解决了钢筋笼的径向偏移,提高了钢筋笼的径向垂直度,保证了接头质量,避免了地下连续墙漏水问题的发生,对后续工程的施工起到了保护作用,达到了安全生产的目的,可广泛应用于采取H型钢接头的超深地下连续墙施工工艺中,采用三角支撑和梳齿钢板,从水平和竖向两个方向采取措施,控制了钢筋笼整体偏移,效果更加明显;本发明所采取的措施均利用现场既有的钢筋,施工简单,费用低,能够有效节约材料成本和人工费用,具有投入小、效果好的显著特点。Beneficial effects of the present invention: In the device and construction method for improving the radial verticality of underground continuous wall steel cages provided by the present invention, the triangular support is arranged between the H-shaped steel and the steel cage, which reduces the gap between the H-shaped steel and the steel cage. There is a movable gap, and the comb-toothed steel plate is incorporated into the bottom of the slot, which limits the free movement of the steel cage. At the same time, it can prevent the backfill material from sliding from the bottom of the H-shaped steel into the slot section to be poured, effectively solving the radial offset of the steel cage. It improves the radial verticality of the steel cage, ensures the quality of the joints, avoids the occurrence of water leakage in the underground diaphragm wall, protects the construction of subsequent projects, and achieves the purpose of safe production. It can be widely used in H-shaped steel joints. In the construction process of the ultra-deep underground diaphragm wall, triangular supports and comb-toothed steel plates are used, and measures are taken from both horizontal and vertical directions to control the overall deflection of the steel cage, and the effect is more obvious; the measures taken in the present invention all use on-site The existing steel bars are simple to construct and low in cost, which can effectively save material costs and labor costs. They have the remarkable characteristics of low investment and good results.

附图说明Description of the drawings

以下将结合附图对本发明做进一步详细说明。The present invention will be further described in detail below with reference to the accompanying drawings.

图1:安装三角支撑的槽段平视图;Figure 1: Plan view of the trough section where the triangular support is installed;

图2:三角支撑的放大结构图;Figure 2: Enlarged structural view of the triangular support;

图3:安装梳齿钢筋的槽段剖视图;Figure 3: Cross-sectional view of the trough section where the comb steel bars are installed;

图4:梳齿钢筋放大结构图。Figure 4: Enlarged structural view of comb steel bars.

附图标记说明:1、已浇筑槽段的H型钢;11、H型钢翼缘板;12、H型钢腹板;2、三角支撑;21、水平钢筋;22、中间水平钢筋;23、竖向联系钢筋;3、待浇筑槽段钢筋笼;31、横筋;32、纵筋;4、待浇筑侧H型钢;41、钢翼缘板;42、钢腹板;5、待浇筑开挖槽孔;6、梳齿钢筋;7、间隙;W、三角支撑与已浇筑槽段的H型钢之间的间距;L、三角支撑的高度;B、梳齿钢筋长度;B1、梳齿钢筋插入待浇筑开挖槽孔底部的深度;B2、焊脚长度;JH、焊脚高度。Explanation of reference signs: 1. H-shaped steel in the poured trough section; 11. H-shaped steel flange plate; 12. H-shaped steel web; 2. Triangular support; 21. Horizontal steel bar; 22. Middle horizontal steel bar; 23. Vertical Contact steel bars; 3. Reinforcement cage of the trough section to be poured; 31. Transverse bars; 32. Longitudinal bars; 4. Side H-shaped steel to be poured; 41. Steel flange plate; 42. Steel web; 5. Excavated slot hole to be poured. ; 6. Comb-toothed steel bars; 7. Gap; W, the distance between the triangular support and the H-shaped steel of the poured tank section; L, the height of the triangular support; B. The length of the comb-toothed steel bar; B1, the comb-toothed steel bar is inserted to be poured The depth of the bottom of the excavation slot; B2, the length of the welding leg; JH, the height of the welding leg.

具体实施方式Detailed ways

实施例1:Example 1:

如图1和图3所示,一种提高地下连续墙钢筋笼径向垂直度的装置,包括已浇筑槽段的H型钢1、待浇筑槽段钢筋笼3、待浇筑侧H型钢4和待浇筑开挖槽孔5,已浇筑槽段的H型钢1竖直连接在已浇筑槽段和待浇筑开挖槽孔5交接处,待浇筑槽段钢筋笼3位于待浇筑开挖槽孔5内,待浇筑槽段钢筋笼3一侧与已浇筑槽段的H型钢1之间具有间隙7,待浇筑槽段钢筋笼3另一侧连接待浇筑侧H型钢4,已浇筑槽段的H型钢1包括H型钢翼缘板11和H型钢腹板12,H型钢腹板12的两端均连接H型钢翼缘板11,待浇筑槽段钢筋笼3包括多条横筋31和纵筋32,横筋31垂直连接纵筋32,待浇筑侧H型钢4包括钢翼缘板41和钢腹板42,钢腹板42两端分别连接钢翼缘板41,还包括三角支撑2和梳齿钢筋6,三角支撑2水平连接待浇筑槽段钢筋笼3且位于间隙7内,梳齿钢筋6竖直连接在待浇筑侧H型钢4底部和待浇筑开挖槽孔5底部之间;三角支撑2设置在间隙7内,减小了已浇筑槽段的H型钢1和待浇筑槽段钢筋笼3之间可以移动的间隙,梳齿钢筋6掺入待浇筑开挖槽孔5底部,限制了待浇筑槽段钢筋笼的自由活动,同时可以避免回填材料从待浇筑侧H型钢4底部滑入待浇筑槽段,有效的解决了待浇筑槽段钢筋笼3的径向偏移,提高了待浇筑槽段钢筋笼3的径向垂直度,保证了接头质量,避免了地下连续墙漏水问题的发生,对后续工程的施工起到了保护作用,达到了安全生产的目的,可广泛应用于采取H型钢接头的超深地下连续墙施工工艺中。As shown in Figures 1 and 3, a device for improving the radial verticality of underground diaphragm wall steel cages includes H-shaped steel 1 in the poured channel section, steel cage 3 in the channel section to be poured, H-shaped steel 4 on the side to be poured, and H-shaped steel cages 4 to be poured. Pour the excavation slot 5. The H-shaped steel 1 of the poured trough section is vertically connected at the intersection of the poured trough section and the excavated slot 5 to be poured. The steel cage 3 of the trough section to be poured is located in the excavated slot 5 to be poured. , there is a gap 7 between one side of the steel cage 3 of the trough section to be poured and the H-shaped steel 1 of the trough section that has been poured, and the other side of the steel cage 3 of the trough section to be poured is connected to the H-shaped steel 4 of the side to be poured, and the H-shaped steel of the trough section that has been poured 1 includes an H-shaped steel flange plate 11 and an H-shaped steel web 12. Both ends of the H-shaped steel web 12 are connected to the H-shaped steel flange plate 11. The steel cage 3 of the tank section to be poured includes a plurality of transverse bars 31 and longitudinal bars 32. The transverse bars 31 is vertically connected to the longitudinal bars 32. The side H-shaped steel 4 to be poured includes steel flange plates 41 and steel webs 42. Both ends of the steel web 42 are connected to steel flange plates 41 respectively, and also includes triangular supports 2 and comb-tooth steel bars 6. The triangular support 2 is horizontally connected to the steel cage 3 of the trough section to be poured and is located in the gap 7, and the comb-toothed steel bars 6 are vertically connected between the bottom of the H-shaped steel 4 on the side to be poured and the bottom of the excavated slot 5 to be poured; the triangular support 2 is set in In the gap 7, the movable gap between the H-shaped steel 1 of the poured trough section and the steel cage 3 of the trough section to be poured is reduced. The comb-toothed steel bars 6 are mixed into the bottom of the excavated slot hole 5 to be poured, limiting the trough to be poured. The free movement of the steel cage of the section can also prevent the backfill material from sliding from the bottom of the H-shaped steel 4 on the side to be poured into the tank section to be poured, which effectively solves the radial offset of the steel cage 3 in the tank section to be poured and improves the efficiency of the tank section to be poured. The radial verticality of the steel cage 3 ensures the quality of the joints, avoids the occurrence of water leakage in the underground diaphragm wall, protects the construction of subsequent projects, achieves the purpose of safe production, and can be widely used in H-shaped steel joints. Ultra-deep underground diaphragm wall construction process.

实施例2:Example 2:

如图1和图2所示,在实施例1的基础上,所述的三角支撑2包括水平钢筋21、中间水平钢筋22和竖向联系钢筋23,水平钢筋21和中间水平钢筋22一端连接横筋31且水平钢筋21数量为两个分别位于中间水平钢筋22两侧,中间水平钢筋22垂直连接横筋31,水平钢筋21和中间水平钢筋22的另一端汇集连接竖向联系钢筋23;所述的待浇筑槽段钢筋笼3竖向每隔2m连接一个三角支撑2,三角支撑2与H型钢腹板12之间的间距为10cm,水平钢筋21和中间水平钢筋22的直径长度为28mm,竖向联系钢筋23的直径长度为20mm。三角支撑2与待浇筑槽段钢筋笼3焊接成一体,三角支撑2竖向2m设置一处,每处的高度L可能不一致,根据实测已浇筑槽段的H型钢1和待浇筑槽段钢筋笼3之间间隙确定,减小了已浇筑槽段的H型钢1和待浇筑槽段钢筋笼3之间可以移动的间隙,提高了待浇筑槽段钢筋笼3的径向垂直度,保证了接头质量,有效的解决了待浇筑槽段钢筋笼3的径向偏移问题。As shown in Figures 1 and 2, based on Embodiment 1, the triangular support 2 includes a horizontal steel bar 21, a middle horizontal steel bar 22 and a vertical connecting steel bar 23. One end of the horizontal steel bar 21 and the middle horizontal steel bar 22 is connected to a transverse bar. 31 and the number of horizontal steel bars 21 is two, which are located on both sides of the middle horizontal steel bar 22. The middle horizontal steel bar 22 is vertically connected to the transverse bar 31, and the other ends of the horizontal steel bars 21 and the middle horizontal steel bar 22 are connected together to connect the vertical contact steel bars 23; The steel cage 3 of the pouring tank section is vertically connected to a triangular support 2 every 2m. The distance between the triangular support 2 and the H-shaped steel web 12 is 10cm. The diameter length of the horizontal steel bar 21 and the middle horizontal steel bar 22 is 28mm. The vertical connection The diameter length of the steel bar 23 is 20mm. The triangular support 2 and the steel cage 3 of the trough section to be poured are welded together. The triangular support 2 is set at a vertical position of 2m. The height L of each place may be inconsistent. According to the actual measurement of the H-shaped steel 1 of the poured trough section and the steel cage of the trough section to be poured. The gap between 3 is determined, which reduces the movable gap between the H-shaped steel 1 of the poured trough section and the steel cage 3 of the trough section to be poured, improves the radial verticality of the steel cage 3 of the trough section to be poured, and ensures the joint quality, effectively solving the problem of radial offset of the steel cage 3 in the tank section to be poured.

如图3和图4所示,所述的梳齿钢筋6双面焊接在待浇筑侧H型钢4底部内侧,梳齿钢筋6数量为多个且相邻两个的间距为15cm,梳齿钢筋6的直径长度为20mm,焊脚高度不小于6mm,梳齿钢筋6深入待浇筑开挖槽孔5底部深度为10cm。梳齿钢筋6采用钢筋设置,焊接在待浇筑槽段H型钢4底部的内侧(待浇筑混凝土侧),双面焊,焊缝长度满足设计要求,钢筋长度B根据槽孔实测深度确定,需满足深入槽孔底部深度在10cm左右,梳齿钢筋6掺入待浇筑开挖槽孔5底部,限制了待浇筑槽段钢筋笼的自由活动,同时可以避免回填材料从待浇筑侧H型钢4底部滑入待浇筑槽段,有效的解决了待浇筑槽段钢筋笼3的径向偏移,提高了待浇筑槽段钢筋笼3的径向垂直度,保证了接头质量,避免了地下连续墙漏水问题的发生,对后续工程的施工起到了保护作用,达到了安全生产的目的。As shown in Figures 3 and 4, the comb-toothed steel bars 6 are welded on both sides on the inside of the bottom of the H-shaped steel 4 on the side to be poured. There are multiple comb-toothed steel bars 6 and the distance between two adjacent ones is 15cm. The comb-toothed steel bars The diameter length of 6 is 20mm, the height of the welding leg is not less than 6mm, and the depth of the bottom of the comb-tooth steel bar 6 into the trench 5 to be poured and excavated is 10cm. The comb-toothed steel bars 6 are set with steel bars and are welded on the inside of the bottom of the H-shaped steel 4 in the tank section to be poured (concrete side to be poured). They are double-sided welded. The length of the weld meets the design requirements. The length of the steel bar B is determined according to the measured depth of the slot hole, which needs to be met. The depth of the bottom of the slot is about 10cm, and the comb-toothed steel bars 6 are incorporated into the bottom of the excavated slot 5 to be poured, which limits the free movement of the steel cage in the slot section to be poured, and at the same time prevents the backfill material from sliding from the bottom of the H-shaped steel 4 on the side to be poured. into the trough section to be poured, which effectively solves the radial offset of the steel cage 3 in the trough section to be poured, improves the radial verticality of the steel cage 3 in the trough section to be poured, ensures the joint quality, and avoids the leakage problem of the underground diaphragm wall occurrence, it plays a protective role in the construction of subsequent projects and achieves the purpose of safe production.

实施例3Example 3

如图1-4所示,在实施例1和2的基础上,一种提高地下连续墙钢筋笼径向垂直度的施工方法,包括如下步骤:As shown in Figures 1-4, based on Embodiments 1 and 2, a construction method for improving the radial verticality of underground continuous wall steel cages includes the following steps:

1)对待浇筑开挖槽孔5进行成孔检测,确定成孔深度和已浇筑槽段的H型钢1的垂直度;利用超声波检孔设备和测绳对槽孔进行成孔检测,确定成孔深度和已浇筑槽段的H型钢1的垂直度;1) Perform hole formation inspection on the slot hole 5 to be excavated to determine the hole formation depth and the verticality of the H-shaped steel 1 of the poured slot section; use ultrasonic hole inspection equipment and measuring ropes to conduct hole formation inspection on the slot hole to determine the hole formation Depth and verticality of H-shaped steel 1 in the poured trough section;

2)确定三角支撑2高度和梳齿钢筋6长度;①根据超声波检孔结果,绘制已浇筑槽段的H型钢1竖向线形,结合实施例2所述三角支撑2特征,计算出每个三角支撑的高度L;②根据测绳检测的成孔深度,结合实施例2所述梳齿钢筋6特征,计算出梳齿钢筋长度B;2) Determine the height of the triangular support 2 and the length of the comb-tooth steel bar 6; ① According to the ultrasonic hole inspection results, draw the vertical line shape of the H-shaped steel 1 of the poured tank section, and calculate each triangle based on the characteristics of the triangular support 2 described in Embodiment 2 The height of the support L; ② According to the hole depth detected by the measuring rope and the characteristics of the comb steel bar 6 described in Example 2, the length B of the comb steel bar is calculated;

3)备料:根据三角支撑2高度和梳齿钢筋6长度准备相应的钢筋;要求钢筋顺直、无污染、无质量缺陷,不得随意减小钢筋直径;3) Material preparation: Prepare corresponding steel bars according to the height of the triangular support 2 and the length of the comb steel bars 6; the steel bars are required to be straight, pollution-free, and have no quality defects, and the diameter of the steel bars must not be reduced arbitrarily;

4)焊接三角支撑2:首先确定焊接位置并标识,然后找出备好的钢筋材料逐根逐处焊接,最后利用竖向联系钢筋23将三角支撑2连成整体;三角支撑2竖向间距2m一处,首先确定焊接位置,在需要焊接的待浇筑槽段钢筋笼3横筋31处做出标识,因每处三角支撑2可能高度不一致,对应找出备好的钢筋材料,逐根逐处焊接,最后利用竖向联系钢筋32连成整体,水平钢筋21与待浇筑槽段钢筋笼3焊接要牢固,同时不得烧伤待浇筑槽段钢筋笼3钢筋。4) Welding the triangular support 2: First determine the welding position and mark it, then find the prepared steel bar materials and weld them one by one, and finally use the vertical connecting steel bars 23 to connect the triangular support 2 into a whole; the vertical distance between the triangular supports 2 is 2m At one point, first determine the welding position, and mark the transverse bars 31 of the steel cage 3 of the channel section to be welded to be poured. Since the height of the triangular support 2 may be inconsistent at each place, find the prepared steel bar materials accordingly and weld them one by one. , and finally use the vertical connecting steel bars 32 to connect them into a whole. The horizontal steel bars 21 and the steel cage 3 of the tank section to be poured must be firmly welded, and at the same time, the steel bars of the steel cage 3 of the tank section to be poured must not be burned.

5)焊接梳齿钢筋6:首先在待浇筑侧H型钢4底部定位和标识,将备好的钢筋逐根焊接到待浇筑侧H型钢4上,焊接完成后确保各根钢筋顺直、无弯曲变形;采用双面焊,长度满足规范要求,焊脚高度不小于6mm;5) Welding comb steel bars 6: First, locate and mark the bottom of the H-shaped steel 4 on the side to be poured, and weld the prepared steel bars one by one to the H-shaped steel 4 on the side to be poured. After the welding is completed, ensure that each steel bar is straight and without bends. Deformation; double-sided welding is used, the length meets the specification requirements, and the welding leg height is not less than 6mm;

6)下放待浇筑槽段钢筋笼3:待浇筑开挖槽孔5检测合格后,下放待浇筑槽段钢筋笼3,下方时三角支撑2和已浇筑槽段的H型钢1不可相互碰撞;待槽孔检测合格后,及时下放待浇筑槽段钢筋笼3,注意三角支撑2与已浇筑槽段的H型钢1之间间隙,避免产生碰撞,以及已浇筑槽段的H型钢1顶面标高,避免已浇筑槽段的H型钢1下放不到位,梳齿钢筋6进入待浇筑开挖槽孔5底部深度不够。6) Lower the steel cage 3 of the trough section to be poured: After the excavated slot hole 5 to be poured is inspected, lower the steel cage 3 of the trough section to be poured. The triangular support 2 and the H-shaped steel 1 of the poured trough section cannot collide with each other when lowering; After passing the slot inspection, lower the steel cage 3 of the trough section to be poured in time. Pay attention to the gap between the triangular support 2 and the H-shaped steel 1 of the poured trough section to avoid collision, as well as the top elevation of the H-shaped steel 1 of the poured trough section. It is avoided that the H-shaped steel 1 of the poured trough section cannot be lowered in place, and the depth of the comb-toothed steel bars 6 into the bottom of the excavated slot 5 to be poured is not enough.

7)水下连续灌注混凝土,灌注时确保待浇筑槽段钢筋笼3不移动和不上浮;混凝土灌注过程要连续,注意观察浇筑槽段钢筋笼3不得移动、上浮。7) Continuously pour concrete underwater. During pouring, ensure that the steel cage 3 in the section to be poured does not move or float. The concrete pouring process must be continuous. Pay attention to the fact that the steel cage 3 in the pouring tank section must not move or float.

以上例举仅仅是对本发明的举例说明,并不构成对本发明的保护范围的限制,凡是与本发明相同或相似的设计均属于本发明的保护范围之内。The above examples are only illustrative of the present invention and do not constitute a limitation on the protection scope of the present invention. All designs that are the same or similar to the present invention fall within the protection scope of the present invention.

Claims (2)

1.一种提高地下连续墙钢筋笼径向垂直度的装置的施工方法,其特征在于,所述的提高地下连续墙钢筋笼径向垂直度的装置,包括已浇筑槽段的H型钢(1)、待浇筑槽段钢筋笼(3)、待浇筑侧H型钢(4)和待浇筑开挖槽孔(5),已浇筑槽段的H型钢(1)竖直连接在已浇筑槽段和待浇筑开挖槽孔(5)交接处,待浇筑槽段钢筋笼(3)位于待浇筑开挖槽孔(5)内,待浇筑槽段钢筋笼(3)一侧与已浇筑槽段的H型钢(1)之间具有间隙(7),待浇筑槽段钢筋笼(3)另一侧连接待浇筑侧H型钢(4),已浇筑槽段的H型钢(1)包括H型钢翼缘板(11)和H型钢腹板(12),H型钢腹板(12)的两端均连接H型钢翼缘板(11),待浇筑槽段钢筋笼(3)包括多条横筋(31)和纵筋(32),横筋(31)垂直连接纵筋(32),待浇筑侧H型钢(4)包括钢翼缘板(41)和钢腹板(42),钢腹板(42)两端分别连接钢翼缘板(41),其特征在于:还包括三角支撑(2)和梳齿钢筋(6),三角支撑(2)水平连接待浇筑槽段钢筋笼(3)且位于间隙(7)内,梳齿钢筋(6)竖直连接在待浇筑侧H型钢(4)底部和待浇筑开挖槽孔(5)底部之间;1. A construction method for a device that improves the radial verticality of underground diaphragm wall steel cages, characterized in that the device for improving the radial verticality of underground diaphragm wall steel cages includes H-shaped steel (1 ), the steel cage (3) of the trough section to be poured, the H-shaped steel (4) on the side to be poured, and the excavated slot (5) to be poured. The H-shaped steel (1) of the poured trough section is vertically connected to the poured trough section and At the intersection of the excavated slot hole (5) to be poured, the steel cage (3) of the trough section to be poured is located in the excavated slot hole (5) to be poured. One side of the steel cage (3) of the trough section to be poured is in contact with the trough section that has been poured There is a gap (7) between the H-shaped steels (1). The other side of the steel cage (3) of the tank section to be poured is connected to the H-shaped steel (4) on the side to be poured. The H-shaped steel (1) of the poured tank section includes the H-shaped steel flange. plate (11) and H-shaped steel web (12). Both ends of the H-shaped steel web (12) are connected to the H-shaped steel flange plate (11). The steel cage (3) of the channel section to be poured includes multiple transverse bars (31) and longitudinal bars (32), and transverse bars (31) are vertically connected to the longitudinal bars (32). The side H-shaped steel (4) to be poured includes a steel flange plate (41) and a steel web (42). The steel web (42) Each end is connected to the steel flange plate (41), which is characterized in that it also includes a triangular support (2) and a comb-toothed steel bar (6). The triangular support (2) is horizontally connected to the steel cage (3) of the tank section to be poured and is located in the gap ( 7), the comb-tooth steel bar (6) is vertically connected between the bottom of the H-shaped steel (4) on the side to be poured and the bottom of the excavated slot (5) to be poured; 所述的三角支撑(2)包括水平钢筋(21)、中间水平钢筋(22)和竖向联系钢筋(23),水平钢筋(21)和中间水平钢筋(22)一端连接横筋(31)且水平钢筋(21)数量为两个分别位于中间水平钢筋(22)两侧,中间水平钢筋(22)垂直连接横筋(31),水平钢筋(21)和中间水平钢筋(22)的另一端汇集连接竖向联系钢筋(23);The triangular support (2) includes a horizontal steel bar (21), a middle horizontal steel bar (22) and a vertical connecting steel bar (23). One end of the horizontal steel bar (21) and the middle horizontal steel bar (22) is connected to the transverse bar (31) and is horizontally connected. The number of steel bars (21) is two, which are respectively located on both sides of the middle horizontal steel bar (22). The middle horizontal steel bar (22) is vertically connected to the horizontal bar (31), and the other ends of the horizontal steel bar (21) and the middle horizontal steel bar (22) are connected to the vertical bars. To contact steel(23); 所述的梳齿钢筋(6)双面焊接在待浇筑侧H型钢(4)底部内侧,梳齿钢筋(6)数量为多个且相邻两个的间距为15cm,梳齿钢筋(6)的直径长度为20mm,焊脚高度不小于6mm,梳齿钢筋(6)深入待浇筑开挖槽孔(5)底部深度为10cm;The comb-toothed steel bars (6) are welded on both sides on the inside of the bottom of the H-shaped steel (4) on the side to be poured. There are multiple comb-toothed steel bars (6) and the distance between two adjacent ones is 15cm. The comb-toothed steel bars (6) The diameter length is 20mm, the height of the welding leg is not less than 6mm, and the depth of the comb tooth steel bar (6) into the bottom of the excavated slot (5) to be poured is 10cm; 所述的待浇筑槽段钢筋笼(3)竖向每隔2m连接一个三角支撑(2),三角支撑(2)与H型钢腹板(12)之间的间距为10cm,水平钢筋(21)和中间水平钢筋(22)的直径长度为28mm,竖向联系钢筋(23)的直径长度为20mm;The steel cage (3) of the tank section to be poured is vertically connected to a triangular support (2) every 2m. The distance between the triangular support (2) and the H-shaped steel web (12) is 10cm. The horizontal steel bars (21) The diameter length of the middle horizontal steel bar (22) is 28mm, and the diameter length of the vertical contact steel bar (23) is 20mm; 所述的方法包括如下步骤:The method includes the following steps: 1)对待浇筑开挖槽孔(5)进行成孔检测,确定成孔深度和已浇筑槽段的H型钢(1)的垂直度;1) Carry out hole inspection on the trench hole (5) to be excavated to be poured, and determine the depth of the hole and the verticality of the H-shaped steel (1) of the poured trench section; 2)确定三角支撑(2)高度和梳齿钢筋(6)长度;2) Determine the height of the triangular support (2) and the length of the comb steel bars (6); 3)备料:根据三角支撑(2)高度和梳齿钢筋(6)长度准备相应的钢筋;3) Material preparation: Prepare the corresponding steel bars according to the height of the triangular support (2) and the length of the comb steel bars (6); 4)焊接三角支撑(2):首先确定焊接位置并标识,然后找出备好的钢筋材料逐根逐处焊接,最后利用竖向联系钢筋(23)将三角支撑(2)连成整体;4) Welding the triangular support (2): first determine the welding position and mark it, then find the prepared steel bar materials and weld them one by one, and finally use the vertical connecting steel bars (23) to connect the triangular support (2) into a whole; 5)焊接梳齿钢筋(6):首先在待浇筑侧H型钢(4)底部定位和标识,将备好的钢筋逐根焊接到待浇筑侧H型钢(4)上,焊接完成后确保各根钢筋顺直、无弯曲变形;5) Welding comb steel bars (6): First, locate and mark the bottom of the H-shaped steel (4) on the side to be poured, and weld the prepared steel bars one by one to the H-shaped steel (4) on the side to be poured. After the welding is completed, ensure that each The steel bars are straight and have no bending deformation; 6)下放待浇筑槽段钢筋笼(3):待浇筑开挖槽孔(5)检测合格后,下放待浇筑槽段钢筋笼(3),下方时三角支撑(2)和已浇筑槽段的H型钢(1)不可相互碰撞;6) Lower the steel cage (3) of the trough section to be poured: After the excavated slot hole (5) to be poured has passed the test, lower the steel cage (3) of the trough section to be poured. The triangular support (2) and the trough section that have been poured are lower. H-shaped steel (1) cannot collide with each other; 7)水下连续灌注混凝土,灌注时确保待浇筑槽段钢筋笼(3)不移动和不上浮;7) Continuously pour concrete underwater. During pouring, ensure that the steel cage (3) of the tank section to be poured does not move or float; 三角支撑(2)设置在H型钢和钢筋笼之间,减小了H型钢和钢筋笼之间可以移动的间隙,梳齿钢板掺入槽孔底部,限制了钢筋笼的自由活动,从水平和竖向两个方向控制了钢筋笼整体偏移;同时可以避免回填材料从H型钢底部滑入待浇筑槽段,有效的解决了钢筋笼的径向偏移,提高了钢筋笼的径向垂直度,保证了接头质量,避免了地下连续墙漏水问题的发生,对后续工程的施工起到了保护作用。The triangular support (2) is set between the H-shaped steel and the steel cage, which reduces the movable gap between the H-shaped steel and the steel cage. The comb-toothed steel plate is incorporated into the bottom of the slot, which limits the free movement of the steel cage. From the horizontal and The overall offset of the steel cage is controlled in two vertical directions; at the same time, it can prevent the backfill material from sliding from the bottom of the H-shaped steel into the groove section to be poured, effectively solving the radial offset of the steel cage and improving the radial verticality of the steel cage. , ensuring the quality of the joints, avoiding the occurrence of water leakage problems in the underground diaphragm wall, and playing a protective role in the construction of subsequent projects. 2.如权利要求1所述的提高地下连续墙钢筋笼径向垂直度的施工方法,其特征在于:所述的备料的钢筋顺直、无污染和无质量缺陷。2. The construction method for improving the radial verticality of underground diaphragm wall steel cages as claimed in claim 1, characterized in that the prepared steel bars are straight, pollution-free and have no quality defects.
CN201710583876.7A 2017-07-18 2017-07-18 Device for improving radial perpendicularity of underground diaphragm wall reinforcement cage and construction method Active CN107246003B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710583876.7A CN107246003B (en) 2017-07-18 2017-07-18 Device for improving radial perpendicularity of underground diaphragm wall reinforcement cage and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710583876.7A CN107246003B (en) 2017-07-18 2017-07-18 Device for improving radial perpendicularity of underground diaphragm wall reinforcement cage and construction method

Publications (2)

Publication Number Publication Date
CN107246003A CN107246003A (en) 2017-10-13
CN107246003B true CN107246003B (en) 2024-03-15

Family

ID=60014166

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710583876.7A Active CN107246003B (en) 2017-07-18 2017-07-18 Device for improving radial perpendicularity of underground diaphragm wall reinforcement cage and construction method

Country Status (1)

Country Link
CN (1) CN107246003B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114622545A (en) * 2022-03-10 2022-06-14 中交第二航务工程局有限公司 Closed-width underground continuous wall reinforcement cage matching manufacturing method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101205717A (en) * 2006-12-18 2008-06-25 上海华瀛建筑科技有限公司 An ultra-deep underground diaphragm wall joint
CN201354456Y (en) * 2009-01-22 2009-12-02 龙元建设集团股份有限公司 Steel reinforcement cage used for construction of diaphragm wall
CN203129188U (en) * 2013-02-27 2013-08-14 中国建筑第八工程局有限公司 Anti-flowing-around device for underground continuous wall connector
CN203334319U (en) * 2013-06-13 2013-12-11 武汉地质勘察基础工程有限公司 Novel joint device of underground diaphragm wall
CN105696546A (en) * 2016-03-25 2016-06-22 广东水电二局股份有限公司 Low-consumption underground diaphragm wall and construction method thereof
CN106168037A (en) * 2016-08-31 2016-11-30 上海市地矿建设有限责任公司 A kind of diaphram wall peg shaped-steel joint device and application thereof
CN207659956U (en) * 2017-07-18 2018-07-27 中交二公局第二工程有限公司 A kind of device improving diaphram wall steel reinforcement cage radial direction verticality

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561404B (en) * 2012-03-16 2014-06-18 中建八局第三建设有限公司 Steel reinforced concrete column type joint and construction method of underground diaphragm wall using same

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101205717A (en) * 2006-12-18 2008-06-25 上海华瀛建筑科技有限公司 An ultra-deep underground diaphragm wall joint
CN201354456Y (en) * 2009-01-22 2009-12-02 龙元建设集团股份有限公司 Steel reinforcement cage used for construction of diaphragm wall
CN203129188U (en) * 2013-02-27 2013-08-14 中国建筑第八工程局有限公司 Anti-flowing-around device for underground continuous wall connector
CN203334319U (en) * 2013-06-13 2013-12-11 武汉地质勘察基础工程有限公司 Novel joint device of underground diaphragm wall
CN105696546A (en) * 2016-03-25 2016-06-22 广东水电二局股份有限公司 Low-consumption underground diaphragm wall and construction method thereof
CN106168037A (en) * 2016-08-31 2016-11-30 上海市地矿建设有限责任公司 A kind of diaphram wall peg shaped-steel joint device and application thereof
CN207659956U (en) * 2017-07-18 2018-07-27 中交二公局第二工程有限公司 A kind of device improving diaphram wall steel reinforcement cage radial direction verticality

Also Published As

Publication number Publication date
CN107246003A (en) 2017-10-13

Similar Documents

Publication Publication Date Title
CN104314070A (en) Shield tunneling construction method for n-shaped underground diaphragm wall
CN108643247B (en) Testing device and testing method for soil body reinforcement model at bottom of rectangular foundation pit in soft soil area
CN110700237A (en) Construction method of diaphragm wall for preventing concrete from flowing around
CN108205055B (en) A stratum deformation test system for shallow buried tunnels under operating highways
CN112502133A (en) Construction process of building underground continuous wall based on steel grating
CN107059881A (en) The foundation pit supporting method that a kind of campshed is combined with steel sheet pile
CN112064676A (en) A mobile formwork structure and its construction method
CN105240018A (en) Vertical shaft construction device and method
CN207659956U (en) A kind of device improving diaphram wall steel reinforcement cage radial direction verticality
CN107246003B (en) Device for improving radial perpendicularity of underground diaphragm wall reinforcement cage and construction method
CN110644499A (en) Construction tool and construction method for asynchronous construction conversion support of foundation pit
CN111155535A (en) Underground continuous wall and foundation slab's pre-buried steel sheet connection structure
CN115506272A (en) Installation and construction method for regular octagonal steel ladle concrete cable tower
CN206409743U (en) The steel pipe pile-supported structure of underground utilities
CN206829158U (en) A kind of reusable steel boxed cofferdam structure
CN109024717A (en) SMW engineering method pile-type steel method for measuring stress
CN211948464U (en) Underground continuous wall and foundation slab's pre-buried steel sheet connection structure
CN205839768U (en) Cantilever Steel Sheet Pile foundation pit supporting construction
CN216108526U (en) Underground continuous wall structure for foundation pit support
CN201660973U (en) Concrete post-pouring belt pre-sealing air exhaust structure
CN115288136A (en) Anti-floating steel cage and construction method of static pressure immersed pipe cast-in-place pile
CN103741724B (en) A kind of prefabricated prestressed underground continuous wall joint
CN207244640U (en) A kind of Double-Wall Steel Boxed Cofferdam
CN205421871U (en) Elevation measuring tool for construction site
CN103758155B (en) An underground diaphragm wall joint and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20250314

Address after: 210000 No. 396 Binjiang Avenue, Jiangbei new area, Nanjing, Jiangsu

Patentee after: East China Construction Co., Ltd. of CCCC Second Highway Engineering Co.,Ltd.

Country or region after: China

Address before: 710119 No.29, No.1 Enterprise Park, West Avenue, high tech Zone, Xi'an City, Shaanxi Province

Patentee before: CCCC-SHEC SECOND ENGINEERING Co.,Ltd.

Country or region before: China