CN107237641A - The intelligent sprayed construction method and device of single shell lining based on monitoring feedback technique - Google Patents
The intelligent sprayed construction method and device of single shell lining based on monitoring feedback technique Download PDFInfo
- Publication number
- CN107237641A CN107237641A CN201710664215.7A CN201710664215A CN107237641A CN 107237641 A CN107237641 A CN 107237641A CN 201710664215 A CN201710664215 A CN 201710664215A CN 107237641 A CN107237641 A CN 107237641A
- Authority
- CN
- China
- Prior art keywords
- lining
- spraying
- monitoring
- injection
- parameter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/18—Special adaptations of signalling or alarm devices
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
一种基于监测反馈技术的单层衬砌智能喷射施工方法与装置:装置包括控制系统、监测反馈系统、喷射系统、供料系统、驱动系统。监测反馈系统可以实时监控测量整个喷射施工装置的位置,实时监控测量喷射点与隧道轴线、预先设定的衬砌表面之间的相对位置。将预先设定的衬砌内径参数、喷射材料参数输入控制系统,该系统即可自动运行,通过分三层喷射施工,形成完整衬砌。本发明可实现智能化喷射施工,施工精度高,效率高。
A single-layer lining intelligent injection construction method and device based on monitoring and feedback technology: the device includes a control system, a monitoring and feedback system, an injection system, a material supply system, and a drive system. The monitoring feedback system can monitor and measure the position of the entire spraying construction device in real time, and monitor and measure the relative position between the spraying point and the tunnel axis and the preset lining surface in real time. Input the pre-set inner diameter parameters of the lining and spray material parameters into the control system, and the system can operate automatically, and form a complete lining by spraying in three layers. The invention can realize intelligent jetting construction, and has high construction precision and high efficiency.
Description
技术领域technical field
本发明涉及一种施工方法与装置,更详细地说是一种基于监测反馈技术的单层衬砌智能喷射施工方法与装置,属于水利水电工程中的水工隧洞衬砌施工方法及设备领域。The invention relates to a construction method and device, more specifically, a single-layer lining intelligent jetting construction method and device based on monitoring and feedback technology, and belongs to the field of hydraulic tunnel lining construction methods and equipment in water conservancy and hydropower projects.
背景技术Background technique
为了保证水工隧洞安全有效运行,通常需要对隧洞进行衬砌。水工隧洞衬砌一般为复合式衬砌,即由初衬和复衬组合形成衬砌结构。初衬主要用于封闭围岩和提供初期支护,一般采用挂网喷锚混凝土;复衬用于形成最终支护和标准化过水通道,满足过水的要求,一般采用模筑混凝土,需要立模、浇筑混凝土、拆模以及回填灌浆等工序。初衬与复衬之间一般要设置一层防水板,层间不传递剪力,其承载机理类似于“叠合梁”。复合式衬砌工序复杂、工期长、施工难度较大。In order to ensure the safe and effective operation of hydraulic tunnels, it is usually necessary to line the tunnels. The lining of hydraulic tunnels is generally a composite lining, that is, the lining structure is formed by combining the primary lining and the secondary lining. The primary lining is mainly used to close the surrounding rock and provide initial support, and generally adopts spray-anchored concrete; the secondary lining is used to form the final support and standardized water passages to meet the requirements of water passage, and generally adopts molded concrete, which needs to be erected. Formwork, concrete pouring, formwork removal and backfill grouting and other processes. A layer of waterproof board is generally installed between the primary lining and the secondary lining, and no shear force is transmitted between the layers, and its bearing mechanism is similar to that of a "laminated beam". Composite lining has complex procedures, long construction period and relatively difficult construction.
单层衬砌是由单层或多层混凝土构成的,各层间能够充分传递剪力的支护体系,与组合式衬砌的最大区别是层间不设防水板,通过层间径向和环向上的抗滑移性,使得各混凝土层形成共同承载体系。其承载机理类似于“组合梁”,比等厚度的复合式衬砌产生的应力小,可适当减薄厚度,减少开挖量,节约投资。The single-layer lining is composed of single-layer or multi-layer concrete, and the support system can fully transmit the shear force between the layers. The biggest difference from the combined lining is that there is no waterproof board between the layers. The excellent slip resistance makes each concrete layer form a common bearing system. Its load-bearing mechanism is similar to "composite beams", and the stress generated by it is smaller than that of the composite lining of equal thickness, which can appropriately reduce the thickness, reduce the amount of excavation, and save investment.
单层衬砌的第一层一般采用喷射混凝土,后续层采用模筑混凝土。与复合式衬砌相比,单层衬砌虽然减去了防水板的施工,但由于模筑混凝土仍然需要立模、浇筑混凝土、拆模等工序,施工周期长、施工难度大。喷射混凝土虽然施工快,机械化程度高,但由于喷射施工精度无法满足水工隧洞衬砌断面标准化和衬砌表面平整度、糙率的要求,一般不用于后续层的施工。The first layer of single-layer lining is generally shotcrete, and subsequent layers are molded concrete. Compared with the composite lining, although the construction of the waterproof board is omitted for the single-layer lining, the construction period is long and the construction is difficult because the formwork concrete still needs to be erected, poured concrete, and demolished. Although shotcrete is constructed quickly and has a high degree of mechanization, it is generally not used for the construction of subsequent layers because the spraying construction accuracy cannot meet the requirements of standardization of hydraulic tunnel lining section and lining surface flatness and roughness.
发明内容Contents of the invention
针对上述技术问题,本发明提出一种隧洞衬砌的智能喷射施工方法,解决了喷射混凝土衬砌断面标准化和衬砌表面平整度、糙率的技术问题,可用于一次性施工隧洞单层衬砌,也可用于施作复合式衬砌的复衬。施工效果满足水工隧洞衬砌断面标准化和衬砌表面平整度、糙率的要求。In view of the above technical problems, the present invention proposes an intelligent spraying construction method for tunnel lining, which solves the technical problems of sprayed concrete lining section standardization and lining surface smoothness and roughness, and can be used for one-time construction of single-layer lining of tunnels. Relining for compound lining. The construction effect meets the requirements of the standardization of the lining section of the hydraulic tunnel and the smoothness and roughness of the lining surface.
为了实现上述技术目的,本发明采用如下具体技术方案:In order to realize above-mentioned technical purpose, the present invention adopts following concrete technical scheme:
一种基于监测反馈技术的单层衬砌智能喷射施工方法,基于喷射施工装置,分三层完成衬砌的喷射施工;An intelligent jetting construction method for single-layer lining based on monitoring and feedback technology. Based on the jetting construction device, the jetting construction of the lining is completed in three layers;
步骤S1、设置好惯性坐标装置,在控制系统中输入衬砌完成后的隧洞内表面参数和喷射材料参数;Step S1, setting up the inertial coordinate device, and inputting the parameters of the inner surface of the tunnel and the parameters of the injection material after the lining is completed into the control system;
步骤S2、监测反馈系统启动,获得以下两个实时参数:Step S2, start the monitoring feedback system to obtain the following two real-time parameters:
第一、整个喷射施工装置的实时位置,经惯性坐标装置偏移修正,得到喷射系统的相对位置参数;First, the real-time position of the entire spraying construction device is corrected by the offset of the inertial coordinate device to obtain the relative position parameters of the spraying system;
第二、围岩或衬砌表面距喷射系统喷头的距离及其在惯性坐标装置中的相对位置参数;Second, the distance between the surrounding rock or the lining surface and the nozzle of the injection system and its relative position parameters in the inertial coordinate device;
步骤S3、监测反馈系统将获得的上述两个参数反馈至控制系统,控制系统通过将预设衬砌表面目标点位置坐标和监测反馈系统反馈获得的两个实时参数进行比较,得出喷射实施参数;Step S3, the monitoring feedback system feeds back the above two parameters obtained to the control system, and the control system compares the preset lining surface target point position coordinates with the two real-time parameters obtained from the feedback of the monitoring feedback system to obtain the injection implementation parameters;
步骤S4、控制系统将得到的喷射实施参数传输至喷射系统,喷射系统按照次序实施喷射混凝土作业;Step S4, the control system transmits the obtained spraying implementation parameters to the spraying system, and the spraying system performs the spraying concrete operation in sequence;
步骤S5、监测反馈系统实时采集到喷射施作表面坐标,并将其与预设衬砌表面坐标进行比较,若二者距离差在100mm~200mm范围内,则控制系统向驱动装置发出前进的驱动指令;Step S5: The monitoring and feedback system collects the surface coordinates of the spraying application in real time, and compares them with the preset lining surface coordinates. If the distance difference between the two is within the range of 100mm~200mm, the control system sends a forward driving command to the driving device ;
步骤S6、整个喷射施工装置进入新位置后,循环执行步骤S1~步骤S5,直至喷射混凝土作业完成10m~100m;Step S6, after the entire spraying construction device enters a new position, execute steps S1 to S5 in a loop until the spraying concrete operation is completed for 10m to 100m;
步骤S7、等待2小时~48小时后,实施砂浆喷射作业,步骤同步骤S1~步骤S5,将喷射材料换为砂浆;Step S7, after waiting for 2 hours to 48 hours, implement the mortar spraying operation, the steps are the same as steps S1 to S5, and replace the spraying material with mortar;
步骤S8、等待2小时~48小时后,实施聚合物喷射作业,步骤同步骤S1~步骤S5,将喷射材料换为聚合物。Step S8, after waiting for 2 hours to 48 hours, implement the polymer injection operation, the steps are the same as steps S1 to S5, and replace the injection material with polymer.
所述隧洞内表面参数为隧道内表面的位置参数,例如圆形隧道可以为隧洞半径。The tunnel inner surface parameter is a position parameter of the tunnel inner surface, for example, a circular tunnel may be a tunnel radius.
所述喷射材料参数包括:喷射材料的最大粒径,一次喷层的厚度,凝结时间和最大允许喷射速度。The spray material parameters include: the maximum particle size of the spray material, the thickness of the primary spray layer, the coagulation time and the maximum allowable spray speed.
所述监测反馈系统的反馈频率为1/10s。The feedback frequency of the monitoring feedback system is 1/10s.
所述喷射实施参数包括:喷射时间、喷射角度、喷射速度以及喷头位置。The injection implementation parameters include: injection time, injection angle, injection speed and nozzle position.
所述分三层完成衬砌的喷射施工,第一层为喷射混凝土,喷射实施后衬砌表面平整度达到3m靠尺偏差100mm~200mm;The spraying construction of the lining is completed in three layers. The first layer is sprayed concrete. After spraying, the surface smoothness of the lining reaches 3m and the deviation of the ruler is 100mm-200mm;
第二层为喷射砂浆,喷射实施后衬砌表面平整度达到3m靠尺偏差3mm~5mm;The second layer is sprayed mortar. After spraying, the surface smoothness of the lining reaches 3m, and the deviation of the ruler is 3mm~5mm;
第三层为喷射高分子聚合物,喷射实施后衬砌表面平整度达到3m靠尺偏差<3mm。The third layer is sprayed high molecular polymer. After spraying, the surface smoothness of the lining reaches 3m and the deviation of the ruler is less than 3mm.
一种基于监测反馈技术的单层衬砌智能喷射施工装置,包括:An intelligent injection construction device for single-layer lining based on monitoring and feedback technology, including:
控制系统、监测反馈系统、喷射系统、供料系统、驱动系统,其中,所述的控制系统包括输入装置、采集装置、计算装置和输出装置;A control system, a monitoring feedback system, an injection system, a feeding system, and a drive system, wherein the control system includes an input device, an acquisition device, a computing device, and an output device;
所述输入装置用于输入预先设定的衬砌内径参数和喷射材料参数;The input device is used for inputting preset inner diameter parameters of the lining and injection material parameters;
所述采集装置用于记录监测反馈系统实时拾取的围岩或衬砌表面三维坐标、喷射系统位置以及整个喷射施工装置位置;The acquisition device is used to record the three-dimensional coordinates of the surrounding rock or lining surface picked up in real time by the monitoring feedback system, the position of the spraying system and the position of the entire spraying construction device;
所述的计算装置用于计算采集装置记录的围岩或衬砌表面三维坐标与预先设定的衬砌内断面对应点之间的差异,并计算出喷射系统下一步移动的位置坐标、喷射速度、喷射时间以及驱动系统下一步移动的位置坐标;The calculation device is used to calculate the difference between the three-dimensional coordinates of the surrounding rock or the lining surface recorded by the acquisition device and the corresponding points of the preset inner section of the lining, and calculate the position coordinates, injection speed, and injection system for the next step of the injection system. Time and the position coordinates of the next move of the drive system;
所述的输出装置用于将计算装置计算所得的参数转化成电信号并输入给喷射系统、供料系统和驱动系统;The output device is used to convert the parameters calculated by the computing device into electrical signals and input them to the injection system, the feeding system and the driving system;
所述监测反馈系统包括定位装置、惯性坐标装置和激光测距装置,其中,所述定位装置用于实时监控测量整个喷射施工装置的位置,确定其与工作线的误差,当误差超过允许值时,将误差反馈至控制系统,由控制系统经计算装置-输出装置将调整指令输出至驱动系统,以调整整个喷射施工装置的位置,使其位于工作线上,并满足误差控制的要求;The monitoring feedback system includes a positioning device, an inertial coordinate device and a laser distance measuring device, wherein the positioning device is used for real-time monitoring and measurement of the position of the entire spraying construction device, to determine its error with the working line, when the error exceeds the allowable value , the error is fed back to the control system, and the control system outputs the adjustment command to the drive system through the calculation device-output device, so as to adjust the position of the entire spraying construction device so that it is located on the working line and meets the requirements of error control;
所述惯性坐标装置用于实时反馈喷射系统、当前喷射的目标围岩点或衬砌表面点与隧洞轴线的相对位置;The inertial coordinate device is used for real-time feedback of the injection system, the relative position of the target surrounding rock point or lining surface point of the current injection and the tunnel axis;
所述激光测距装置固定于喷射系统上,用于实时监控测量喷射目标点与隧道轴线、预先设定的衬砌断面内表面对应点之间的相对位置关系。The laser distance measuring device is fixed on the injection system, and is used for real-time monitoring and measurement of the relative positional relationship between the injection target point, the tunnel axis, and the preset corresponding point on the inner surface of the lining section.
所述的喷射系统包括混凝土喷射机、砂浆喷射机和聚合物喷射机三部分。The spraying system includes three parts: a concrete spraying machine, a mortar spraying machine and a polymer spraying machine.
有益效果:Beneficial effect:
本发明与已有技术项目,具有以下优点:The present invention and prior art project have the following advantages:
1、实现智能化喷射施工。本发明喷射施工装置的移动、喷射系统的喷射速度调整、喷头位置的移动等均根据监测反馈系统实时测得的围岩上的目标喷射点与设计断面衬砌表面对应点的坐标之间的差异自动调整。1. Realize intelligent jetting construction. The movement of the spraying construction device, the spraying speed adjustment of the spraying system, and the movement of the nozzle position of the present invention are all automatically based on the difference between the target spraying point on the surrounding rock measured in real time by the monitoring feedback system and the coordinates of the corresponding point on the lining surface of the designed section. Adjustment.
2、施工精度高。本发明通过先喷混凝土、再喷砂浆、最后喷聚合物的方式,实现粗喷、细喷、精喷的优化组合,提高了喷射衬砌表面平整度的控制精度。2. High construction precision. The invention realizes the optimized combination of coarse spraying, fine spraying and fine spraying by spraying concrete first, then mortar spraying and finally polymer spraying, and improves the control accuracy of the surface smoothness of the spray lining.
3、效率高。本发明采用监测反馈技术,实现喷射施工的智能化控制,减少喷射施工操作人员数量,提高了喷射施工效率。3. High efficiency. The invention adopts the monitoring and feedback technology to realize the intelligent control of spraying construction, reduce the number of spraying construction operators, and improve the spraying construction efficiency.
附图说明Description of drawings
图1为本发明水工隧洞衬砌施工方法功能框图。Fig. 1 is a functional block diagram of the hydraulic tunnel lining construction method of the present invention.
图2为本发明所述激光定位装置示意图。Fig. 2 is a schematic diagram of the laser positioning device of the present invention.
其中,1为激光测距装置;2为喷射系统的喷头;3为预设衬砌表面;4为实时衬砌表面。Among them, 1 is the laser distance measuring device; 2 is the nozzle of the injection system; 3 is the preset lining surface; 4 is the real-time lining surface.
具体实施方式detailed description
下面结合附图给出实施例并对本发明进行具体描述。有必要在此指出的是,以下实施例只用于对本发明作进一步说明,不能理解为对本发明保护范围的限制,该领域的专业技术人员根据上述本发明的内容做出的一些非本质的改进和调整,仍属于本发明的保护范围。Embodiments are given below in conjunction with the accompanying drawings and the present invention is described in detail. It is necessary to point out that the following examples are only used to further illustrate the present invention, and can not be interpreted as limiting the protection scope of the present invention, some non-essential improvements made by those skilled in the art according to the content of the present invention above And adjustments still belong to the protection scope of the present invention.
将本发明所述一种水工隧洞衬砌施工装置驱动进入待施工隧道轴线位置,设置好惯性坐标装置。The hydraulic tunnel lining construction device described in the present invention is driven into the axial position of the tunnel to be constructed, and the inertial coordinate device is set.
如图1所示,第一步,在控制系统中输入衬砌完成后的内表面参数和喷射材料参数,例如圆形隧洞半径8m,喷射材料为混凝土,最大粒径15mm,一次喷层厚度200mm,凝结时间2min,最大允许喷射速度4m3/h;As shown in Figure 1, the first step is to input the inner surface parameters and spray material parameters after the lining is completed into the control system, for example, the radius of the circular tunnel is 8m, the spray material is concrete, the maximum particle size is 15mm, and the thickness of the primary spray layer is 200mm. The coagulation time is 2min, and the maximum allowable injection velocity is 4m 3 /h;
第二步,监测反馈系统启动,定位装置获得整个设备的实时位置,经惯性坐标装置偏移修正,得到喷射系统的相对位置;激光测距系统获得围岩或衬砌表面距喷射系统喷头的距离及其在惯性坐标装置中的相对位置;监测反馈系统的反馈频率为1/10s。In the second step, the monitoring feedback system is started, the positioning device obtains the real-time position of the entire equipment, and the relative position of the injection system is obtained through the offset correction of the inertial coordinate device; the laser ranging system obtains the distance between the surrounding rock or the lining surface and the nozzle of the injection system and Its relative position in the inertial coordinate device; the feedback frequency of the monitoring feedback system is 1/10s.
第三步,监测反馈系统将获得的上述参数反馈至控制系统的采集装置,与输入装置中输入的参数一起,进入计算装置,计算装置通过比较预设衬砌表面目标点位置坐标和输入装置、采集装置获得的实时参数,得出喷射时间、喷射角度、喷射速度、喷头位置等喷射实施参数;In the third step, the monitoring and feedback system feeds back the above parameters obtained to the acquisition device of the control system, together with the parameters input in the input device, enter the calculation device, and the calculation device compares the coordinates of the target point position on the preset lining surface with the input device, collects The real-time parameters obtained by the device can be used to obtain injection implementation parameters such as injection time, injection angle, injection speed, and nozzle position;
第四步,计算装置得到的喷射实施参数传输至喷射系统,喷射系统按照一定的次序实施喷射混凝土作业;In the fourth step, the spraying implementation parameters obtained by the computing device are transmitted to the spraying system, and the spraying system performs spraying concrete operations in a certain order;
第五步,监测反馈系统的激光测距装置采集到喷射施作后的衬砌表面,经计算装置计算距预设衬砌表面在100mm~200mm范围内,则控制系统通过输出装置向驱动装置发出前进的驱动指令;In the fifth step, the laser distance measuring device of the monitoring feedback system collects the lining surface after spraying, and the calculation device calculates that the distance from the preset lining surface is within 100mm to 200mm, and then the control system sends a forward direction to the driving device through the output device. drive command;
第六步,整个装置进入新位置后,循环执行第一步~第五步,直至喷射混凝土作业完成一定距离;In the sixth step, after the whole device enters the new position, the first step to the fifth step are executed in a cycle until the sprayed concrete operation is completed for a certain distance;
第七步,等待一定时间后,实施砂浆喷射作业,步骤同第一步~第五步,将喷射材料换为砂浆,控制精度调整为3mm~5mm;The seventh step, after waiting for a certain period of time, implement the mortar spraying operation, the steps are the same as the first step to the fifth step, replace the spraying material with mortar, and adjust the control accuracy to 3mm to 5mm;
第八步,等待一定时间后,实施聚合物喷射作业,步骤同第一步~第五步,将喷射材料换为聚合物,控制精度调整为<3mm;The eighth step, after waiting for a certain period of time, implement the polymer injection operation, the steps are the same as the first step to the fifth step, replace the injection material with polymer, and adjust the control accuracy to <3mm;
所述基于监测反馈技术的单层衬砌喷射施工装置,包括控制系统、监测反馈系统、喷射系统、供料系统、驱动系统。将预先设定的衬砌断面参数、喷射材料参数输入控制系统,该系统即可自动运行,通过喷射施工形成完整衬砌。The single-layer lining injection construction device based on monitoring and feedback technology includes a control system, a monitoring and feedback system, an injection system, a feeding system, and a driving system. Input the preset lining section parameters and spray material parameters into the control system, and the system can run automatically to form a complete lining through spray construction.
所述控制系统包括输入装置、采集装置、计算装置、输出装置。输入装置用于输入预先设定的衬砌断面参数和喷射材料参数;采集装置用于记录监测反馈系统实时拾取的围岩或衬砌表面上目标点的三维坐标、喷射系统位置以及整个喷射施工装置位置;计算装置用于计算采集装置记录的围岩或衬砌表面上的目标点的三维坐标与预先设定的衬砌断面对应点坐标之间的差异,并计算出喷射系统下一步移动的三维坐标、喷射速度、喷射时间以及驱动系统下一步移动的三维坐标;输出装置用于将计算装置计算所得的参数转化成电信号并输入给喷射系统、供料系统和驱动系统。The control system includes an input device, a collection device, a computing device, and an output device. The input device is used to input the preset lining section parameters and spray material parameters; the acquisition device is used to record the three-dimensional coordinates of the surrounding rock or the target point on the lining surface picked up in real time by the monitoring feedback system, the position of the spray system and the position of the entire spray construction device; The calculation device is used to calculate the difference between the three-dimensional coordinates of the surrounding rock or the target point on the lining surface recorded by the acquisition device and the preset coordinates of the corresponding points on the lining section, and calculate the three-dimensional coordinates and injection speed of the next step of the injection system. , injection time and the three-dimensional coordinates of the next step of the drive system; the output device is used to convert the parameters calculated by the calculation device into electrical signals and input them to the injection system, the feeding system and the drive system.
所述监测反馈系统包括定位装置、惯性坐标装置、激光测距装置。其特征在于,所述定位装置可以实时监控测量整个喷射施工装置的位置,确定其与工作线(工作线是喷射系统的工作位置线,其与隧洞轴线的位置关系可预先设定。)的误差,当误差超过允许值时,将误差反馈至控制系统,由控制系统经计算装置-输出装置将调整指令输出至驱动系统,以调整整个喷射施工装置的位置,使其位于工作线上,并满足误差控制的要求;所述惯性坐标装置,实时反馈喷射系统、围岩或衬砌表面与隧洞轴线的相对位置;所述激光测距装置固定于喷射系统上,实时监控测量喷射点与隧道轴线、预先设定的衬砌表面之间的相对位置关系。The monitoring feedback system includes a positioning device, an inertial coordinate device, and a laser distance measuring device. It is characterized in that the positioning device can monitor and measure the position of the entire spraying construction device in real time, and determine its error with the working line (the working line is the working position line of the spraying system, and its positional relationship with the tunnel axis can be preset.) , when the error exceeds the allowable value, the error is fed back to the control system, and the control system outputs the adjustment command to the drive system through the calculation device-output device, so as to adjust the position of the entire spraying construction device so that it is located on the working line and meets the requirements Requirements for error control; the inertial coordinate device provides real-time feedback on the relative position of the injection system, surrounding rock or lining surface, and the tunnel axis; the laser distance measuring device is fixed on the injection system to monitor and measure the injection point and the tunnel axis in real time. The relative positional relationship between the set lining surfaces.
所述喷射系统分为混凝土喷射机、砂浆喷射机、聚合物喷射机三部分,各部分的喷射速度、喷头位置、行进速度、开关等均由控制系统输出装置发出的指令自动控制。The spraying system is divided into three parts: concrete spraying machine, mortar spraying machine and polymer spraying machine. The spraying speed, nozzle position, traveling speed and switch of each part are all automatically controlled by the commands issued by the output device of the control system.
所述供料系统根据喷射实施的需求,分别供应混凝土、砂浆、聚合物至混凝土喷射机、砂浆喷射机、聚合物喷射机。The feeding system supplies concrete, mortar, and polymer to the concrete spraying machine, mortar spraying machine, and polymer spraying machine respectively according to the requirements of spraying implementation.
所述驱动系统可根据控制系统发出的指令,牵引整个喷射施工装置实现位置变化,驱动系统可在设置的轨道上运行。The driving system can pull the entire spraying construction device to realize position change according to the instructions issued by the control system, and the driving system can run on the set track.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710664215.7A CN107237641B (en) | 2017-08-07 | 2017-08-07 | Single shell lining intelligence sprayed construction method and device based on monitoring feedback technique |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710664215.7A CN107237641B (en) | 2017-08-07 | 2017-08-07 | Single shell lining intelligence sprayed construction method and device based on monitoring feedback technique |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107237641A true CN107237641A (en) | 2017-10-10 |
CN107237641B CN107237641B (en) | 2018-12-07 |
Family
ID=59989519
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710664215.7A Active CN107237641B (en) | 2017-08-07 | 2017-08-07 | Single shell lining intelligence sprayed construction method and device based on monitoring feedback technique |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107237641B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107939418A (en) * | 2017-11-24 | 2018-04-20 | 中铁十局集团第四工程有限公司 | A kind of gunite concrete automated construction device and its construction method |
CN110836120A (en) * | 2019-11-07 | 2020-02-25 | 山东大学 | Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults |
CN111520163A (en) * | 2020-04-30 | 2020-08-11 | 中铁工程装备集团有限公司 | Mixed spraying method of intelligent mixed spraying robot |
CN114893212A (en) * | 2022-04-14 | 2022-08-12 | 青岛市地铁六号线有限公司 | Shotcrete equipment and method capable of realizing intelligent control of particle size |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN88101510A (en) * | 1987-03-16 | 1988-09-28 | 铁建建设株式会社 | The moving die plate of tunnel-liner device |
CN101974971A (en) * | 2010-11-01 | 2011-02-16 | 河海大学 | Full automatic wall facing concrete injection system |
CN201826508U (en) * | 2010-11-01 | 2011-05-11 | 河海大学 | Uneven-wall cement-based material equivalent-thickness spraying device |
CN202380748U (en) * | 2011-07-15 | 2012-08-15 | 长沙科达建设机械制造有限公司 | Automatic injection system of concrete injection manipulator |
JP2013023923A (en) * | 2011-07-21 | 2013-02-04 | Kajima Corp | Spraying method and spraying apparatus |
CN102929290A (en) * | 2012-10-10 | 2013-02-13 | 中联重科股份有限公司 | Control system, method and device of sprayer applied to tunnel concrete spraying |
CN203383834U (en) * | 2013-08-06 | 2014-01-08 | 安徽佳乐建设机械有限公司 | Intelligent integrated wet shotcreting trolley |
CN103713647A (en) * | 2013-12-23 | 2014-04-09 | 中联重科股份有限公司 | Concrete sprayer and control method, device and system thereof |
CN104533457A (en) * | 2014-12-17 | 2015-04-22 | 陈映宏 | Concrete shotcreting robot |
CN104818999A (en) * | 2015-04-16 | 2015-08-05 | 浙江大学 | Concrete spraying and painting integration tunnel construction device |
-
2017
- 2017-08-07 CN CN201710664215.7A patent/CN107237641B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN88101510A (en) * | 1987-03-16 | 1988-09-28 | 铁建建设株式会社 | The moving die plate of tunnel-liner device |
CN101974971A (en) * | 2010-11-01 | 2011-02-16 | 河海大学 | Full automatic wall facing concrete injection system |
CN201826508U (en) * | 2010-11-01 | 2011-05-11 | 河海大学 | Uneven-wall cement-based material equivalent-thickness spraying device |
CN202380748U (en) * | 2011-07-15 | 2012-08-15 | 长沙科达建设机械制造有限公司 | Automatic injection system of concrete injection manipulator |
JP2013023923A (en) * | 2011-07-21 | 2013-02-04 | Kajima Corp | Spraying method and spraying apparatus |
CN102929290A (en) * | 2012-10-10 | 2013-02-13 | 中联重科股份有限公司 | Control system, method and device of sprayer applied to tunnel concrete spraying |
CN203383834U (en) * | 2013-08-06 | 2014-01-08 | 安徽佳乐建设机械有限公司 | Intelligent integrated wet shotcreting trolley |
CN103713647A (en) * | 2013-12-23 | 2014-04-09 | 中联重科股份有限公司 | Concrete sprayer and control method, device and system thereof |
CN104533457A (en) * | 2014-12-17 | 2015-04-22 | 陈映宏 | Concrete shotcreting robot |
CN104818999A (en) * | 2015-04-16 | 2015-08-05 | 浙江大学 | Concrete spraying and painting integration tunnel construction device |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107939418A (en) * | 2017-11-24 | 2018-04-20 | 中铁十局集团第四工程有限公司 | A kind of gunite concrete automated construction device and its construction method |
CN110836120A (en) * | 2019-11-07 | 2020-02-25 | 山东大学 | Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults |
CN111520163A (en) * | 2020-04-30 | 2020-08-11 | 中铁工程装备集团有限公司 | Mixed spraying method of intelligent mixed spraying robot |
CN111520163B (en) * | 2020-04-30 | 2021-11-05 | 中铁工程装备集团有限公司 | Mixed spraying method of intelligent mixed spraying robot |
CN114893212A (en) * | 2022-04-14 | 2022-08-12 | 青岛市地铁六号线有限公司 | Shotcrete equipment and method capable of realizing intelligent control of particle size |
Also Published As
Publication number | Publication date |
---|---|
CN107237641B (en) | 2018-12-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107237641B (en) | Single shell lining intelligence sprayed construction method and device based on monitoring feedback technique | |
CN102102522B (en) | Track and posture composite control method in shield tunneling process | |
US20150239148A1 (en) | Spray Printing Construction | |
CN107939418A (en) | A kind of gunite concrete automated construction device and its construction method | |
CN100491697C (en) | Method for autocontrolling for excavation direction of underground excavator using virtual track | |
CN109026065A (en) | A kind of Tunnel Second Lining zero-fault construction method | |
CN101598023B (en) | Control method for shield tunnel axis having underground structure on adjacent side | |
CN106438591A (en) | Proportional-control high-precision propelling hydraulic system for earth pressure balance shield tunneling machine and control method | |
CN109595007A (en) | A kind of full-automatic wet shot control method and full-automatic wet shot system | |
CN113931649B (en) | Position and posture regulating and controlling method of tunnel boring machine | |
CN102021908A (en) | Mechanical connection structure and construction method for splicing precast square piles | |
CN103286440A (en) | Fast positioning method of laser cutting part | |
CN114995452A (en) | Concrete pouring path planning and control system and method for concrete conveying pump truck | |
CN106703823A (en) | Posture error correction system and method of large driving equipment | |
CN107168338B (en) | Inertial guided vehicle navigation method based on millimeter wave radar and inertial guided vehicle | |
CN207123231U (en) | A kind of positioning rule of embedded sleeve barrel and reserving hole channel after being used for prefabricated part hanging | |
CN102865087B (en) | Embedded grout pipe device in lining concrete of chamber and construction method | |
CN104731015A (en) | Fast centering method | |
CN207686734U (en) | A kind of gunite concrete automated construction device | |
CN214836403U (en) | Movable tunnel lining repairing device based on 3D printing technology | |
CN209925010U (en) | Shield constructs section of jurisdiction position control device based on machine vision | |
CN108798704B (en) | An Active Underpinning Method for Underground Engineering Construction | |
CN111271080A (en) | Pipe shed construction method for soft surrounding rock section of tunnel portal | |
CN103953194A (en) | Construction method of variable section variable grade large volume concrete diversion trench | |
CN117090599A (en) | Tunnel inverted arch precast block and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |