CN107218179B - Construction method for split installation of offshore wind turbines - Google Patents
Construction method for split installation of offshore wind turbines Download PDFInfo
- Publication number
- CN107218179B CN107218179B CN201710618852.0A CN201710618852A CN107218179B CN 107218179 B CN107218179 B CN 107218179B CN 201710618852 A CN201710618852 A CN 201710618852A CN 107218179 B CN107218179 B CN 107218179B
- Authority
- CN
- China
- Prior art keywords
- auxiliary
- platform
- tower
- auxiliary platform
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
- F03D13/25—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors specially adapted for offshore installation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/727—Offshore wind turbines
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
- Y02P70/50—Manufacturing or production processes characterised by the final manufactured product
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Wind Motors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
本发明涉及一种海上风力发电机分体安装的施工方法,所述风力发电机位于风机基础的承台上,其中所述风力发电机包括塔架以及位于所述塔架上方的风机,通过辅助平台将所述风力发电机分体吊装在风机基础上,从而实现所述风力发电机的分体安装。本发明利用所述辅助平台将风机分体式进行安装,有效减小了风浪对风机安装施工的影响,提高了安装工效。
The present invention relates to a construction method for the split installation of an offshore wind turbine. The wind turbine is located on a foundation, comprising a tower and a wind turbine located above the tower. The wind turbine is separately hoisted onto the foundation via an auxiliary platform, thereby achieving the split installation of the wind turbine. The present invention utilizes the auxiliary platform to perform split installation of the wind turbine, effectively reducing the impact of wind and waves on wind turbine installation and improving installation efficiency.
Description
技术领域technical field
本发明涉及风力发电技术领域,尤其是指一种海上风力发电机分体安装的施工方法。The invention relates to the technical field of wind power generation, in particular to a construction method for split installation of offshore wind power generators.
背景技术Background technique
我国海域面积辽阔,海上风能资源丰富,利用海风风力发电的潜能极大,但是我国的海上风能开发较晚,自东海大桥海上风电场的落成标志着我国正式开始海上风力发电。my country has a vast sea area and abundant offshore wind energy resources. The potential of utilizing sea wind wind power is great. However, the development of offshore wind energy in my country is relatively late. The completion of the Donghai Bridge Offshore Wind Farm marks the official start of offshore wind power generation in my country.
海上风电作为一种新型能源,目前国内选址均为离岸超过10海里的外海环境,目前海上风力发电机组安装施工主要有两种方式,一种是采用大型浮吊直接进行整体吊装,二是采用风机安装专用大型设备。由于海况恶劣,尤其是施工区域风、浪、流等自然条件对船机施工的影响,无论采用上述哪种方案,都存在以下缺点:由于风力发电机整体海上运输重心高,导致倾翻风险大;而且在运输时,不仅要大幅度提高运输和吊装设备的能力,还要在风力发电机设计中考虑整体安装缓冲装置以减少海运和海装的碰损率,由此导致海上大型风力发电机的安装施工难度大。As a new type of energy, offshore wind power is currently located in the offshore environment of more than 10 nautical miles offshore. At present, there are two main ways to install and construct offshore wind turbines. One is to use large floating cranes for direct overall hoisting. Special large-scale equipment is used for fan installation. Due to the harsh sea conditions, especially the influence of natural conditions such as wind, waves and currents in the construction area on the construction of ships and machinery, no matter which of the above schemes is adopted, there are the following disadvantages: due to the high center of gravity of the overall sea transportation of wind turbines, the risk of overturning is high. ; And during transportation, not only should the capacity of transportation and hoisting equipment be greatly improved, but also the overall installation of buffer devices should be considered in the design of wind turbines to reduce the collision rate of marine and marine installations, resulting in large offshore wind turbines. The installation and construction are difficult.
为了克服上述问题,中国发明专利(CN101985917A)公开了一种海上风力发电机组分体安装施工方法,将塔机在陆地上组装好,利用浮吊吊至方驳上,再由浮吊把塔机安装在墩台上后并将其固定在墩台上;塔吊在墩台上安装完成后,顺序安装风机的三节塔筒,吊装风机主机、轮毂和叶片;利用抱紧装置松开风机的塔筒,翻转到垂直位置,收回臂架和塔柱,用浮吊将塔机吊装到运输驳船上。上述海上风力发电机组分体安装施工方法,虽然减小了自重,降低了成本,方便了塔机的整体安装,但是由于风机安装的精度要求高,导致对起重设备的要求也很高,仍旧存在安装时易受海浪影响导致降低施工效率的问题。In order to overcome the above-mentioned problems, the Chinese invention patent (CN101985917A) discloses a construction method for the assembly of offshore wind turbines. The tower crane is assembled on the land, and the floating crane is used to hoist it to the square barge, and then the tower crane is lifted by the floating crane. After installing on the pier and fixing it on the pier; after the tower is installed on the pier, install the three-section tower of the fan in sequence, hoist the fan main engine, the hub and the blade; use the clamping device to loosen the tower of the fan , flip to the vertical position, retract the boom and tower column, and use the floating crane to hoist the tower crane to the transport barge. The above-mentioned offshore wind turbine assembly installation and construction method reduces the dead weight, reduces the cost, and facilitates the overall installation of the tower crane. However, due to the high precision requirements of the fan installation, the requirements for the lifting equipment are also very high. There is a problem that it is easily affected by waves during installation, which reduces construction efficiency.
发明内容SUMMARY OF THE INVENTION
为此,本发明所要解决的技术问题在于克服现有技术中风电机组安装易受海况影响,导致施工效率低的问题从而提供一种受海况影响小,最大程度上保证风电机组安装稳定性的海上风力发电机分体安装的施工方法。Therefore, the technical problem to be solved by the present invention is to overcome the problem that the installation of wind turbines in the prior art is easily affected by sea conditions, resulting in low construction efficiency, so as to provide an offshore wind turbine that is less affected by sea conditions and ensures the installation stability of wind turbines to the greatest extent. The construction method of wind turbine split installation.
为解决上述技术问题,本发明的一种海上风力发电机分体安装的施工方法,所述风力发电机位于风机基础的承台上,其中所述风力发电机包括塔架以及位于所述塔架上方的风机,包括如下步骤:步骤S1:对所述风机基础的桩基进行沉桩;步骤S2:制造辅助平台,并将所述辅助平台安装在所述风机基础旁,使所述辅助平台靠近所述风机基础;步骤S3:在所述辅助平台上设置吊具,并在所述吊具配合下继续对所述风机基础的电缆管、靠船设施、防撞结构安装以及承台钢筋、模板和混凝土结构进行施工;步骤S4:在所述辅助平台上利用所述吊具先将所述塔架吊装至所述承台上并进行安装,然后再将所述风机吊装至所述塔架上并进行安装。In order to solve the above-mentioned technical problems, the present invention provides a construction method for the split installation of an offshore wind turbine, wherein the wind turbine is located on the bearing platform of the fan foundation, wherein the wind turbine includes a tower and is located on the tower. The fan above includes the following steps: step S1: pile-driving the pile foundation of the fan foundation; step S2: manufacturing an auxiliary platform, and installing the auxiliary platform beside the fan foundation, so that the auxiliary platform is close to the fan foundation The fan foundation; Step S3: Set up a spreader on the auxiliary platform, and continue to install the cable pipes, ship-receiving facilities, anti-collision structure, and steel reinforcement and formwork of the fan base with the cooperation of the spreader. and the concrete structure for construction; Step S4: on the auxiliary platform, the tower is first hoisted to the bearing platform by using the hanger and installed, and then the fan is hoisted to the tower. and install it.
在本发明的一个实施例中,所述辅助平台采用导管架结构,整体拼接成型。In an embodiment of the present invention, the auxiliary platform adopts a jacket structure and is integrally formed by splicing.
在本发明的一个实施例中,所述辅助平台安装时,在所述辅助平台的下端设置防沉加强杆,且使所述防沉加强杆深入泥内。In an embodiment of the present invention, when the auxiliary platform is installed, an anti-sinking reinforcing rod is provided at the lower end of the auxiliary platform, and the anti-settling reinforcing rod is made to penetrate deep into the mud.
在本发明的一个实施例中,所述辅助平台的节点位置处安装有辅助桩,且安装所述辅助桩的方法为:先在所述辅助平台的四个角点处的套管内竖直插入四根辅助桩,通过振动锤将所述四根辅助桩打至设计标高,提升所述辅助平台至设计标高并将所述四根辅助桩固定在所述辅助桩套管内,然后吊打剩余辅助桩并将剩余辅助桩固定在所述套管上。In an embodiment of the present invention, auxiliary piles are installed at the node positions of the auxiliary platform, and the method for installing the auxiliary piles is: first, vertically inserting the auxiliary piles into the casings at the four corner points of the auxiliary platform Four auxiliary piles are driven to the design level by vibrating hammer, the auxiliary platform is lifted to the design level and the four auxiliary piles are fixed in the auxiliary pile casing, and then the remaining auxiliary piles are hoisted pile and attach the remaining auxiliary piles to the casing.
在本发明的一个实施例中,在所述辅助平台的四个角点处的套管内竖直插入四根辅助桩的方法为:通过起重船吊起辅助桩,将所述辅助桩依次插入所述辅助平台套管内,然后起重船吊起振动锤,使所述振动锤的夹具靠近所述辅助桩的顶部,将所述夹具卡入桩顶并夹紧,最后启动所述振动锤将所述辅助桩依次振沉至设计标高。In an embodiment of the present invention, the method of vertically inserting four auxiliary piles into the casing at the four corners of the auxiliary platform is as follows: lifting the auxiliary piles by a crane, and inserting the auxiliary piles in sequence Inside the casing of the auxiliary platform, then the crane ship lifts the vibrating hammer, makes the clamp of the vibrating hammer close to the top of the auxiliary pile, clamps the clamp into the top of the pile and clamps it, and finally starts the vibrating hammer to The auxiliary piles vibrate and sink to the design elevation in sequence.
在本发明的一个实施例中,提升所述辅助平台至设计标高并将所述四根辅助桩固定在所述辅助平台套管内的方法为:所述辅助平台提升至设计标高后,在所述辅助平台的套管上的通孔内插入搁置梁,使所述四根辅助桩位于所述搁置梁的下方。In an embodiment of the present invention, the method for lifting the auxiliary platform to the design level and fixing the four auxiliary piles in the auxiliary platform casing is: after the auxiliary platform is lifted to the design level, after the auxiliary platform is lifted to the design level The resting beam is inserted into the through hole on the casing of the auxiliary platform, so that the four auxiliary piles are located under the resting beam.
在本发明的一个实施例中,将剩余辅助桩固定在所述辅助平台上的方法为:在所述剩余辅助桩上均开孔形成安装孔,且使所述剩余辅助桩上的安装孔对准所述辅助平台套管上的通孔,再将对应的搁置梁穿过所述安装孔,使剩余所述辅助桩固定在所述辅助平台上。In an embodiment of the present invention, the method for fixing the remaining auxiliary piles on the auxiliary platform is as follows: holes are formed on the remaining auxiliary piles to form installation holes, and the installation holes on the remaining auxiliary piles are aligned with each other. Align the through holes on the auxiliary platform casing, and then pass the corresponding resting beams through the installation holes, so that the remaining auxiliary piles are fixed on the auxiliary platform.
在本发明的一个实施例中,所述辅助平台安装时,利用起重船将所述辅助平台吊至预先作好标记的位置,使所述辅助平台靠近定位船的右舷,当所述辅助平台上的中心线位置与所述定位船的船舷外沿中心线重合时,将所述辅助平台调平后缓慢下放至设计高程,待所述辅助平台稳定后脱钩,然后进入辅助桩施工阶段。In an embodiment of the present invention, when the auxiliary platform is installed, a crane is used to lift the auxiliary platform to a pre-marked position, so that the auxiliary platform is close to the starboard side of the positioning ship. When the position of the center line on the top of the positioning vessel coincides with the center line along the outboard of the positioning vessel, the auxiliary platform is leveled and then slowly lowered to the design elevation.
在本发明的一个实施例中,所述塔架包括位于最下方的塔筒、位于所述塔筒上方的中塔以及位于所述中塔上方的顶塔,所述风机基础的承台施工完成后,在所述辅助平台上将所述塔筒吊装至所述承台上并进行安装,然后顺序吊装所述中塔以及顶塔。In an embodiment of the present invention, the tower includes a lowermost tower, a middle tower above the tower, and a top tower above the middle tower, and the construction of the cap for the fan foundation is completed Afterwards, the tower is hoisted on the support platform and installed on the auxiliary platform, and then the middle tower and the top tower are hoisted in sequence.
在本发明的一个实施例中,所述风机包括位于所述塔架上方的机舱、位于所述机舱上的轮毂以及位于所述轮毂上的三片叶片,安装完塔架后,在所述辅助平台上利用吊具先吊装所述机舱和轮毂的组合,然后再对所述三片叶片依此进行吊装。In an embodiment of the present invention, the wind turbine includes a nacelle located above the tower, a hub located on the nacelle, and three blades located on the hub. After the tower is installed, the auxiliary The combination of the nacelle and the hub is first hoisted on the platform by a hoist, and then the three blades are hoisted accordingly.
本发明的上述技术方案相比现有技术具有以下优点:The above-mentioned technical scheme of the present invention has the following advantages compared with the prior art:
本发明所述的海上风力发电机分体安装的施工方法,通过所述辅助平台上的起重设备既可安全高效进行风机承台电缆管、靠船设施、防撞结构的安装以及钢筋、模板和混凝土施工,又可将所述风力发电机分体进行安装,减少了海上风浪对施工的影响,实现了对所述承台上部风机安装的“陆上施工”,有效减小了风浪对风机安装施工的影响,显著提高安装工效。In the construction method for the split installation of the offshore wind turbine according to the present invention, the lifting equipment on the auxiliary platform can be used to safely and efficiently perform the installation of the fan platform cable pipe, the ship berthing facility, the anti-collision structure, and the reinforcement and formwork. The wind turbine can be installed separately, which reduces the impact of offshore wind and waves on the construction, realizes the "land construction" of the fan installation on the upper part of the cap, and effectively reduces the impact of wind and waves on the fan. The impact of installation and construction significantly improves the installation efficiency.
附图说明Description of drawings
为了使本发明的内容更容易被清楚的理解,下面根据本发明的具体实施例并结合附图,对本发明作进一步详细的说明,其中In order to make the content of the present invention easier to understand clearly, the present invention will be described in further detail below according to specific embodiments of the present invention and in conjunction with the accompanying drawings, wherein
图1是本发明海上风力发电机分体安装的施工方法流程图;Fig. 1 is the construction method flow chart of the split installation of the offshore wind turbine of the present invention;
图2是本发明所述风机承台和所述辅助平台的俯视图;Fig. 2 is the top view of the fan bearing platform of the present invention and the auxiliary platform;
图3是本发明所述辅助平台的侧视图。Figure 3 is a side view of the auxiliary platform of the present invention.
具体实施方式Detailed ways
如图1和图2所示,本实施例提供一种海上风力发电机分体安装的施工方法,所述风力发电机位于风机基础10的承台上,其中所述风力发电机包括塔架以及位于所述塔架上方的风机,包括如下步骤:步骤S1:对所述风机基础10的桩基进行沉桩;步骤S2:制造辅助平台20,并将所述辅助平台20安装在所述风机基础10旁,使所述辅助平台20靠近所述风机基础10;步骤S3:在所述辅助平台20上设置吊具,并在所述吊具配合下继续对所述风机基础10的电缆管、靠船设施、防撞结构安装以及承台钢筋、模板和混凝土结构进行施工;步骤S4:在所述辅助平台20上利用所述吊具先将所述塔架吊装至所述承台上并进行,然后再将所述风机吊装至所述塔架上并进行安装。As shown in FIG. 1 and FIG. 2 , the present embodiment provides a construction method for the split installation of an offshore wind turbine, the wind turbine is located on the bearing platform of the wind turbine foundation 10 , wherein the wind turbine includes a tower and The fan located above the tower includes the following steps: step S1: driving the pile foundation of the fan foundation 10; step S2: manufacturing an auxiliary platform 20, and installing the auxiliary platform 20 on the fan foundation Next to 10, make the auxiliary platform 20 close to the fan foundation 10; Step S3: set a sling on the auxiliary platform 20, and continue to align the cable pipes and leanings of the fan foundation 10 with the cooperation of the sling. Installation of ship facilities, anti-collision structure, and construction of the reinforcing steel, formwork and concrete structure of the cap; Step S4: firstly hoist the tower on the cap by using the sling on the auxiliary platform 20 and carry out, The fan is then hoisted to the tower and installed.
本实施例所述海上风力发电机分体安装的施工方法,所述风力发电机位于风机基础10的承台上,其中所述风力发电机包括塔架以及位于所述塔架上方的风机,其中所述塔架位于所述承台上,所述步骤S1中,对所述风机基础10的桩基进行沉桩,从而将所述风机基础10固定在海上;所述步骤S2中,制造辅助平台20,并将所述辅助平台20安装在所述风机基础10旁,使所述辅助平台20靠近所述风机基础10,从而有利于后续通过所述辅助平台20对所述风力发电机进行施工,实现了对所述承台上部风机安装的“陆上施工”,有效减小了风浪对风机安装施工的影响,显著提高了安装效率;所述步骤S3中,在所述辅助平台20上设置吊具,并在所述吊具配合下继续对所述风机基础10的电缆管、靠船设施、防撞结构安装以及承台钢筋、模板和混凝土结构进行施工,此时通过所述辅助平台20也加快了所述电缆管、靠船设施、防撞结构的安装以及承台钢筋、模板和混凝土施工,有效减小了风浪对上部承台施工的影响;所述步骤S4中,在所述辅助平台20上利用所述吊具先将所述塔架吊装至所述承台上并进行安装,从而有利于将所述塔架安装在所述承台上,然后在所述辅助平台20上将所述风机吊装至所述塔架上并进行安装,通过所述辅助平台有利于将所述风机安装在所述塔架上。In the construction method for the split installation of the offshore wind turbine in this embodiment, the wind turbine is located on the platform of the wind turbine foundation 10, wherein the wind turbine includes a tower and a fan located above the tower, wherein The tower is located on the bearing platform. In the step S1, the pile foundation of the wind turbine foundation 10 is piled to fix the wind turbine foundation 10 on the sea; in the step S2, an auxiliary platform is manufactured 20, and install the auxiliary platform 20 beside the wind turbine foundation 10, so that the auxiliary platform 20 is close to the wind turbine foundation 10, so as to facilitate the subsequent construction of the wind turbine through the auxiliary platform 20, The "land construction" of the fan installation on the upper part of the platform is realized, the impact of wind and waves on the fan installation and construction is effectively reduced, and the installation efficiency is significantly improved; in the step S3, a crane is installed on the auxiliary platform 20. The installation of the cable duct, the ship berthing facility, the anti-collision structure, the reinforcing steel plate, the formwork and the concrete structure of the fan foundation 10 will continue to be carried out with the cooperation of the spreader. At this time, the auxiliary platform 20 will also Speeding up the installation of the cable duct, the ship-berthing facility, the anti-collision structure, and the construction of the reinforcing steel, formwork and concrete for the cap, effectively reducing the impact of wind and waves on the construction of the upper cap; in the step S4, in the auxiliary platform 20 , the tower is first hoisted to the platform and installed by using the spreader, so as to facilitate the installation of the tower on the platform, and then the auxiliary platform 20 is used to hoist the tower on the platform. The fan is hoisted to and installed on the tower, and the auxiliary platform facilitates the installation of the fan on the tower.
请参考图3所示,所述辅助平台20采用导管架结构,整体拼接成型,不但厂内施工便利,作业条件好,而且加工进度能有效把控,保证质量。具体地,所述辅助平台20包括导管架21,所述导管架21在竖直方向上由上往下依此设置有第一横杆22、第二横杆23以及第三横杆24,其中所述第二横杆23处于设计低水位以下,以使所述导管架21的桩承载力、浮力、浮容重上托力均正好与自重平衡;所述第三横杆24是防沉加强杆,设置在所述导管架21的下端,且使所述防沉加强杆深入泥内,通过所述防沉加强杆有利于保证安装时的稳定性。另外,所述导管架21与所述第一横杆22之间还设有斜撑,所述斜撑采用钢管。Please refer to FIG. 3 , the auxiliary platform 20 adopts a jacket structure and is integrally formed by splicing, which not only facilitates the construction in the factory, and has good working conditions, but also can effectively control the processing progress and ensure the quality. Specifically, the auxiliary platform 20 includes a jacket 21 . The jacket 21 is provided with a first cross bar 22 , a second cross bar 23 and a third cross bar 24 from top to bottom in the vertical direction, wherein The second cross bar 23 is below the designed low water level, so that the pile bearing capacity, buoyancy, and buoyancy lifting force of the jacket 21 are just balanced with their own weight; the third cross bar 24 is an anti-sinking reinforcement bar , is arranged at the lower end of the jacket 21, and makes the anti-settling reinforcing rod go deep into the mud, and the anti-settling reinforcing rod is beneficial to ensure the stability during installation. In addition, a diagonal brace is also provided between the jacket 21 and the first cross bar 22, and the diagonal brace is made of steel pipes.
为了保证所述辅助平台20的稳定,所述辅助平台20的9个节点位置处分别安装有辅助桩25,且安装所述辅助桩25的方法如下:即在节点1、节点2至节点9处均设有套管,每个所述套管内安装辅助桩25,其中所述套管安装时均触底。具体地,先在所述所述辅助平台20的四个角点处的套管内竖直插入四根辅助桩25,即在节点1、节点3、节点7和节点9处的套管内分别插入四根辅助桩25,通过振动锤将所述四根辅助桩25打至设计标高,提升所述辅助平台20至设计标高并将所述四根辅助桩25固定在所述辅助平台20套管内,然后吊打剩余辅助桩25并将剩余辅助桩25固定在所述辅助平台20的套管上,通过先安装四个角点处的辅助桩25,再安装其它位置处的辅助桩25,即可以防止所述辅助平台20上提时所述辅助桩25与所述套管发生蹩牢,而且有利于降低施工难度,从而加快施工的进度,下面详细说明。In order to ensure the stability of the auxiliary platform 20, auxiliary piles 25 are respectively installed at 9 node positions of the auxiliary platform 20, and the method for installing the auxiliary piles 25 is as follows: namely, at node 1, node 2 to node 9 Each of the casings is provided with a casing, and an auxiliary pile 25 is installed in each of the casings, wherein the casings are all bottomed out when they are installed. Specifically, first vertically insert four auxiliary piles 25 into the casings at the four corners of the auxiliary platform 20, that is, insert four auxiliary piles 25 into the casings at the nodes 1, 3, 7 and 9 respectively. Auxiliary piles 25, the four auxiliary piles 25 are driven to the design level by a vibrating hammer, the auxiliary platform 20 is lifted to the design level and the four auxiliary piles 25 are fixed in the casing of the auxiliary platform 20, and then Lifting the remaining auxiliary piles 25 and fixing the remaining auxiliary piles 25 on the casing of the auxiliary platform 20, by first installing the auxiliary piles 25 at the four corner points, and then installing the auxiliary piles 25 at other positions, it can prevent When the auxiliary platform 20 is lifted up, the auxiliary piles 25 and the casing are tightly connected, which is beneficial to reduce the difficulty of construction, thereby speeding up the progress of construction, which will be described in detail below.
在所述辅助平台20的四个角点处的套管内竖直插入四根辅助桩25的方法如下:通过起重船吊起所述辅助桩25,将所述辅助桩插入所述辅助平台20套管内,然后起重船吊起振动锤,使所述振动锤的夹具靠近所述辅助桩25的顶部,将所述夹具卡入桩顶并夹紧,最后启动振动锤将所述辅助桩25依次振沉至设计标高。为了使所述辅助桩25固定在所述辅助平台20内,提升所述辅助平台20平台至设计标高并将所述四根辅助桩25固定在所述辅助平台20内的方法如下:所述辅助平台20提升至设计标高后,在所述辅助平台20的套管上的通孔内插入搁置梁,使所述四根辅助桩25位于所述搁置梁的下方,从而保证了辅助桩25始终位于所述套管内。The method of vertically inserting four auxiliary piles 25 into the casings at the four corners of the auxiliary platform 20 is as follows: the auxiliary piles 25 are lifted by a crane ship, and the auxiliary piles are inserted into the auxiliary platform 20 Inside the casing, then the crane ship lifts the vibratory hammer, makes the clamp of the vibratory hammer close to the top of the auxiliary pile 25, clamps the clamp into the top of the pile and clamps, and finally starts the vibratory hammer to move the auxiliary pile 25. Vibrate and sink to the design elevation in turn. In order to fix the auxiliary piles 25 in the auxiliary platform 20, the method of lifting the auxiliary platform 20 to the design elevation and fixing the four auxiliary piles 25 in the auxiliary platform 20 is as follows: After the platform 20 is elevated to the design elevation, insert a resting beam into the through hole on the casing of the auxiliary platform 20, so that the four auxiliary piles 25 are located under the resting beam, thereby ensuring that the auxiliary piles 25 are always located at the bottom of the resting beam. inside the casing.
将剩余辅助桩25固定在所述辅助平台20上的方法如下:在所述剩余辅助桩25上均开孔形成安装孔,且使所述剩余辅助桩25上的安装孔对准所述辅助平台20内套管上的通孔,即将在节点2、节点8、节点4、节点5和节点6位置处的套管上的通孔对准每个所述辅助桩25上的安装孔,再将对应的搁置梁穿过所述安装孔,使剩余所述辅助桩25固定在所述辅助平台20上。由于四个角点处的四根辅助桩25不需要开孔,通过提升所述辅助平台20至设计标高,将所述四根辅助桩25固定在所述搁置梁的下方,因此减少了开孔时间以及两孔对准的时间,使得施工简单,有效提高了施工效率。其中所述搁置梁和孔道之间存在的高差缝隙处可以利用钢板垫牢,从而保证所述辅助桩25的稳定性。The method for fixing the remaining auxiliary piles 25 on the auxiliary platform 20 is as follows: holes are formed on the remaining auxiliary piles 25 to form installation holes, and the installation holes on the remaining auxiliary piles 25 are aligned with the auxiliary platform 20 The through holes on the inner casing, that is, the through holes on the casing at the positions of node 2, node 8, node 4, node 5 and node 6 are aligned with the installation holes on each of the auxiliary piles 25, and then The corresponding resting beams pass through the mounting holes, so that the remaining auxiliary piles 25 are fixed on the auxiliary platform 20 . Since the four auxiliary piles 25 at the four corners do not need openings, the four auxiliary piles 25 are fixed under the resting beams by raising the auxiliary platform 20 to the design elevation, thus reducing the openings The time and the time for the alignment of the two holes make the construction simple and effectively improve the construction efficiency. Wherein, the height difference gap between the resting beam and the tunnel can be fastened with steel plates, so as to ensure the stability of the auxiliary pile 25 .
所述辅助平台20安装时,利用起重船将所述辅助平台20吊至预先作好标记的位置,使所述辅助平台20靠近定位船的右舷,当所述辅助平台20上的中心线位置与所述定位船的船舷外沿中心线重合时,将所述辅助平台20调平后缓慢下放至设计高程,待所述辅助平台20稳定后脱钩,然后进入辅助桩25施工阶段,从而有利于保证所述辅助平台20的稳定。另外,在所述辅助平台20的两侧还设置有牵引缆风绳,用于在安装时防止辅助平台20发生大幅度的晃动。其中在所述辅助平台20安装前,需要对所述辅助平台20进行定位,具体定位方法为:将两台GPS仪器流动站在定位船(所述定位船靠所述辅助平台20的下海侧)的甲板上测放出所述辅助平台20的两个安装边线,且两台GPS仪器中心构成的直线与船舷外沿平行,仪器间距大于稳桩平台尺寸,测量所述两个安装边线与船舷外沿的垂直距离,使定位船舷与所述辅助平台20边平行,在两台GPS仪器居中的位置,标记出与船舷外沿相垂直的刻画线,分别测量两台GPS仪器中心至所述刻画线的垂直距离。When the auxiliary platform 20 is installed, use a crane to lift the auxiliary platform 20 to the pre-marked position, so that the auxiliary platform 20 is close to the starboard side of the positioning ship. When it is coincident with the center line of the outboard of the positioning vessel, the auxiliary platform 20 is leveled and then slowly lowered to the design elevation. After the auxiliary platform 20 is stabilized, it is decoupled, and then enters the construction stage of the auxiliary pile 25, which is beneficial to The stability of the auxiliary platform 20 is guaranteed. In addition, traction cables are also provided on both sides of the auxiliary platform 20 to prevent the auxiliary platform 20 from shaking greatly during installation. Wherein, before the auxiliary platform 20 is installed, the auxiliary platform 20 needs to be positioned. The specific positioning method is as follows: two GPS instruments are roved on the positioning ship (the positioning ship is on the sea-going side of the auxiliary platform 20) The two installation edges of the auxiliary platform 20 are measured and released on the deck, and the straight line formed by the centers of the two GPS instruments is parallel to the outboard edge of the ship, and the distance between the instruments is larger than the size of the stabilizing platform. Measure the two installation edge lines and the outboard edge of the ship. The vertical distance of the locating ship's side is parallel to the 20 side of the auxiliary platform. At the center position of the two GPS instruments, mark the profiling line perpendicular to the outer edge of the ship's side, and measure the distance from the center of the two GPS instruments to the profiling line. vertical distance.
本实施例中,所述塔架包括位于最下方的塔筒、位于所述塔筒上方的中塔以及位于所述中塔上方的顶塔,所述风机基础的承台施工完成后,在所述辅助平台20上利用吊具将所述塔筒吊装至所述承台上并进行安装,然后顺序吊装所述中塔以及顶塔,将所述中塔固定在所述塔筒上,将所述顶塔固定在所述中塔上。In this embodiment, the tower includes a lowermost tower, a middle tower above the tower, and a top tower above the middle tower. On the auxiliary platform 20, the tower is hoisted to the bearing platform with a sling, and then the middle tower and the top tower are hoisted in sequence, the middle tower is fixed on the tower, and the The top tower is fixed on the middle tower.
所述风机包括位于所述塔架上方的机舱、位于所述机舱上的轮毂以及位于所述轮毂上的三片叶片,安装完塔架后,在所述辅助平台20上利用吊具先吊装所述机舱和轮毂的组合,将所述机舱和轮毂固定在所述顶塔上,然后再对所述三片叶片依此进行吊装,将所述三片叶片分别固定在所述轮毂上,从而完成所述风力发电机的安装。The fan includes a nacelle located above the tower, a hub located on the nacelle, and three blades located on the hub. After the tower is installed, the auxiliary platform 20 is first hoisted with a spreader. The combination of the nacelle and the hub, the nacelle and the hub are fixed on the top tower, and then the three blades are hoisted accordingly, and the three blades are respectively fixed on the hub, so as to complete Installation of the wind turbine.
所述风力发电机安装完成后,再安装电气系统以及警示系统,配合风电机组系统调试,并验收合格后,就完成了整个风力发电机的安装。另外,所述辅助平台20上设置有大型起重设备,通过所述起重设备提供起重能力及保证施工安全性,实现对所述风力发电机的起吊。After the wind turbine is installed, the electrical system and the warning system are installed, and after the wind turbine system is debugged, and the acceptance is passed, the installation of the entire wind turbine is completed. In addition, the auxiliary platform 20 is provided with a large-scale hoisting device, and the hoisting device is used to provide the hoisting capacity and ensure the construction safety, so as to realize the hoisting of the wind turbine.
本实施例中,所述吊具是大型履带吊。In this embodiment, the spreader is a large crawler crane.
综上,本发明所述技术方案具有以下优点:To sum up, the technical solution of the present invention has the following advantages:
1.本发明所述海上风力发电机分体安装的施工方法,所述风力发电机位于风机基础的承台上,其中所述风力发电机包括塔架以及位于所述塔架上方的风机,其中所述塔架位于所述承台上,所述步骤S1中,对所述风机基础的桩基进行沉桩,从而将所述风机基础固定在海上;所述步骤S2中,制造辅助平台,并将所述辅助平台安装在所述风机基础旁,使所述辅助平台靠近所述风机基础,从而有利于后续通过所述辅助平台对所述风力发电机进行施工,实现了对所述承台上部风机安装的“陆上施工”,有效减小了风浪对风机安装施工的影响,显著提高了安装效率;所述步骤S3中,在所述辅助平台上设置吊具,并在所述吊具配合下继续对所述风机基础的电缆管、靠船设施、防撞结构安装以及承台钢筋、模板和混凝土结构进行施工,此时通过所述辅助平台也加快了所述电缆管、靠船设施、防撞结构的安装以及承台钢筋、模板和混凝土施工,有效减小了风浪对上部承台施工的影响;所述步骤S4中,在所述辅助平台上利用所述吊具先将所述风力发电机的塔架吊装至所述承台上并进行安装,从而有利于将所述塔架安装在所述承台上;然后在所述辅助平台上将所述风力发电机的风机吊装至所述塔架上并进行安装,通过所述辅助平台有利于将所述风机安装在所述塔架上。1. The construction method for the split installation of the offshore wind turbine according to the present invention, the wind turbine is located on the bearing platform of the fan foundation, wherein the wind turbine comprises a tower and a fan located above the tower, wherein The tower is located on the bearing platform. In the step S1, the pile foundation of the wind turbine foundation is piled to fix the wind turbine foundation on the sea; in the step S2, the auxiliary platform is manufactured, and the The auxiliary platform is installed next to the wind turbine foundation, so that the auxiliary platform is close to the wind turbine foundation, so as to facilitate the subsequent construction of the wind turbine through the auxiliary platform, and realize the upper part of the bearing platform. The "land construction" of the fan installation effectively reduces the impact of wind and waves on the fan installation and construction, and significantly improves the installation efficiency; in the step S3, a spreader is set on the auxiliary platform, and the spreader is matched with the spreader. Continue to carry out the construction of the cable ducts, ship berthing facilities, anti-collision structure installation, and the steel cap, formwork and concrete structure of the fan foundation. At this time, the cable ducts, ship berthing facilities, The installation of the anti-collision structure and the construction of the reinforcing bars, formwork and concrete of the capping platform effectively reduce the impact of wind and waves on the construction of the upper capping platform; in the step S4, use the spreader on the auxiliary platform to first displace the wind force The tower of the generator is hoisted and installed on the platform, so as to facilitate the installation of the tower on the platform; and then the fan of the wind generator is hoisted to the supporting platform on the auxiliary platform. The auxiliary platform is used to facilitate the installation of the fan on the tower.
2.本发明所述海上风力发电机分体安装的施工方法,四个角点处的四根辅助桩不需要开孔,通过提升所述辅助平台至设计标高,将所述四根辅助桩固定在所述搁置梁的下方,因此减少了开孔时间以及两孔对准的时间,使得施工简单,有效提高了施工效率。2. The construction method for the split installation of the offshore wind turbine according to the present invention, the four auxiliary piles at the four corners do not need to be opened, and the four auxiliary piles are fixed by lifting the auxiliary platform to the design elevation Below the resting beam, the time for opening the hole and the time for aligning the two holes are reduced, the construction is simple, and the construction efficiency is effectively improved.
显然,上述实施例仅仅是为清楚地说明所作的举例,并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本发明创造的保护范围之中。Obviously, the above-mentioned embodiments are only examples for clear description, and are not intended to limit the implementation manner. For those of ordinary skill in the art, other different forms of changes or modifications can also be made on the basis of the above description. There is no need and cannot be exhaustive of all implementations here. And the obvious changes or changes derived from this are still within the protection scope of the present invention.
Claims (8)
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201711116097.2A CN107795438B (en) | 2017-07-26 | 2017-07-26 | A kind of construction method of assistance platform |
| CN201710618852.0A CN107218179B (en) | 2017-07-26 | 2017-07-26 | Construction method for split installation of offshore wind turbines |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710618852.0A CN107218179B (en) | 2017-07-26 | 2017-07-26 | Construction method for split installation of offshore wind turbines |
Related Child Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201711116097.2A Division CN107795438B (en) | 2017-07-26 | 2017-07-26 | A kind of construction method of assistance platform |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN107218179A CN107218179A (en) | 2017-09-29 |
| CN107218179B true CN107218179B (en) | 2019-07-16 |
Family
ID=59953914
Family Applications (2)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710618852.0A Active CN107218179B (en) | 2017-07-26 | 2017-07-26 | Construction method for split installation of offshore wind turbines |
| CN201711116097.2A Active CN107795438B (en) | 2017-07-26 | 2017-07-26 | A kind of construction method of assistance platform |
Family Applications After (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201711116097.2A Active CN107795438B (en) | 2017-07-26 | 2017-07-26 | A kind of construction method of assistance platform |
Country Status (1)
| Country | Link |
|---|---|
| CN (2) | CN107218179B (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109838351B (en) * | 2017-11-24 | 2020-09-11 | 黄灿光 | Multi-wind turbine floating automatic wind power generation equipment on feng shui |
| CN109737013A (en) * | 2019-01-25 | 2019-05-10 | 中国能源建设集团广东省电力设计研究院有限公司 | Marine frame structure and assemble method |
| CN112921937A (en) * | 2021-01-27 | 2021-06-08 | 中交第三航务工程局有限公司宁波分公司 | Self-stabilizing offshore operation platform |
| CN115306645B (en) * | 2022-08-30 | 2024-11-01 | 中国电建集团河南工程有限公司 | Wind power generation concrete tower barrel installation construction method |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2008084971A1 (en) * | 2007-01-11 | 2008-07-17 | Dong Taek Suh | Method of establishing sea wind power generator using the leading rail |
| CN102535510A (en) * | 2012-02-27 | 2012-07-04 | 广东明阳风电产业集团有限公司 | Offshore fan jacket foundation installation method and integrated jacket device |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000073349A (en) * | 1998-09-02 | 2000-03-07 | Nippon Steel Corp | Jacket using rotary press-fit steel pipe pile and its construction method |
| US7530780B2 (en) * | 2006-05-22 | 2009-05-12 | General Electric Company | Method and apparatus for wind power foundation |
| CN103850885B (en) * | 2012-11-28 | 2016-08-24 | 财团法人船舶暨海洋产业研发中心 | Offshore installation method and assembly structure of wind power generator |
| CN105672317B (en) * | 2014-11-21 | 2017-11-14 | 上海勘测设计研究院有限公司 | Underwater jacket piling interpolation type positioner |
| CN106677995B (en) * | 2016-07-12 | 2018-12-18 | 中交第三航务工程局有限公司 | The construction method of off-lying sea blower partial installation |
| CN206034408U (en) * | 2016-07-29 | 2017-03-22 | 中国电建集团华东勘测设计研究院有限公司 | A back pitching pile formula jacket structure for marine booster station |
-
2017
- 2017-07-26 CN CN201710618852.0A patent/CN107218179B/en active Active
- 2017-07-26 CN CN201711116097.2A patent/CN107795438B/en active Active
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2008084971A1 (en) * | 2007-01-11 | 2008-07-17 | Dong Taek Suh | Method of establishing sea wind power generator using the leading rail |
| CN102535510A (en) * | 2012-02-27 | 2012-07-04 | 广东明阳风电产业集团有限公司 | Offshore fan jacket foundation installation method and integrated jacket device |
Also Published As
| Publication number | Publication date |
|---|---|
| CN107218179A (en) | 2017-09-29 |
| CN107795438A (en) | 2018-03-13 |
| CN107795438B (en) | 2019-06-14 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6039097B2 (en) | Floating transport and installation structure, and floating wind turbine | |
| EP2837554A1 (en) | Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method | |
| CN109629568A (en) | The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating | |
| CN107218179B (en) | Construction method for split installation of offshore wind turbines | |
| CN101837929B (en) | Operation method for lifting fan for barge in shoal area | |
| CN104727336A (en) | Construction method of large single-pipe pile foundation of shallow-sea wind power plant | |
| JP2004001750A (en) | Construction of special work boats and offshore structures | |
| CN110453709A (en) | A large-diameter single pile driving technology for offshore wind power | |
| CN209178967U (en) | The split type jacket structure of Large marine platform of support method installation is floated suitable for shallow sea water | |
| CN109853567A (en) | A kind of pile sinking process of offshore wind farm steel tube pile embeded in rock | |
| CN115787645A (en) | Quick pile sinking construction process for four-pile jacket foundation by offshore wind power deepwater pile-first method | |
| CN106965906A (en) | A kind of marine three basic formula wind-powered electricity generation whole machine installation ships and its single step construction method | |
| CN115788782A (en) | A floating wind turbine offshore installation process | |
| JP2012112370A (en) | Ship for installing offshore wind turbine and method for installing offshore wind turbine using the same | |
| CN203844964U (en) | Mother-child dual-float integrated vessel for overall transportation and installation of offshore wind generating sets | |
| KR101724593B1 (en) | Construction method for marine wind generator using exclusive barge ship | |
| CN204455847U (en) | The marine positioning guiding device of the prefabricated pier of large-tonnage | |
| CN102587340A (en) | Installation platform of bottom-supported fan and method for installing fan equipment | |
| CN204456044U (en) | Mixing floating offshore booster station structure | |
| CN104047289B (en) | Pile position disperse splicing and single hammer disperse hitting technology for lattice type steel sheet pile large cylinder auxiliary lattice | |
| CN202966598U (en) | A new type of bottom-mounted offshore wind turbine installation barge | |
| CN205046567U (en) | Marine wind turbine foundation structure | |
| CN105443311A (en) | Tidal current energy generating device fixed to water bottom | |
| CN204226097U (en) | Be fixed on water-bed tidal current energy generating equipment | |
| CN211849435U (en) | Seat bottom pile inserting type single pile stabilizing frame |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20230913 Address after: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road Patentee after: CCCC THIRD HARBOR ENGINEERING Co.,Ltd. Patentee after: NINGBO BRANCH, CCCC NO.3 HARBOR ENGINEERING CO.,LTD. Address before: No.462, Yanjiang East Road, Zhenhai District, Ningbo, Zhejiang 315000 Patentee before: NINGBO BRANCH, CCCC NO.3 HARBOR ENGINEERING CO.,LTD. |
|
| TR01 | Transfer of patent right |