[go: up one dir, main page]

CN107090804B - A kind of flexible net debris flow dam and its construction method - Google Patents

A kind of flexible net debris flow dam and its construction method Download PDF

Info

Publication number
CN107090804B
CN107090804B CN201710383716.8A CN201710383716A CN107090804B CN 107090804 B CN107090804 B CN 107090804B CN 201710383716 A CN201710383716 A CN 201710383716A CN 107090804 B CN107090804 B CN 107090804B
Authority
CN
China
Prior art keywords
debris flow
flexible net
concrete
ladder
length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710383716.8A
Other languages
Chinese (zh)
Other versions
CN107090804A (en
Inventor
王飞
栗帅
陈晓清
游勇
陈剑刚
陈华勇
周公旦
刘兴荣
李云
王道正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Institute of Mountain Hazards and Environment IMHE of CAS
Original Assignee
Institute of Mountain Hazards and Environment IMHE of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Institute of Mountain Hazards and Environment IMHE of CAS filed Critical Institute of Mountain Hazards and Environment IMHE of CAS
Priority to CN201710383716.8A priority Critical patent/CN107090804B/en
Publication of CN107090804A publication Critical patent/CN107090804A/en
Application granted granted Critical
Publication of CN107090804B publication Critical patent/CN107090804B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B5/00Artificial water canals, e.g. irrigation canals
    • E02B5/08Details, e.g. gates, screens
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B5/00Artificial water canals, e.g. irrigation canals
    • E02B5/08Details, e.g. gates, screens
    • E02B5/085Arresting devices for waterborne materials, e.g. gratings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/02Sediment base gates; Sand sluices; Structures for retaining arresting waterborne material
    • E02B8/023Arresting devices for waterborne materials

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种柔性网泥石流拦砂坝及其施工方法,拦砂坝包括若干用于将宽阔的泥石流沟道分割为若干柔性网适合的宽度范围的混凝土支墩,混凝土支墩呈台阶型上升并由下至上依次设置为第一级阶梯、第二级阶梯和第三级阶梯;每个混凝土支墩在具有相邻混凝土支墩的那一侧纵向中部均设置有侧向齿槛;混凝土支墩的底部设置有水平承台,水平承台底部设置有防滑齿槛和若干钢管桩。本发明结构施工简单、节约投资,可用于大型宽阔沟道的泥石流拦挡中。泥石流来临时泥石流由混凝土支墩分为多股,然后在相邻第一级阶梯之间的柔性网拦挡作用下堆积,随着堆积高度超过本段柔性网,泥石流依次在更高水平柔性网拦挡作用下堆积,实现对泥石流的治理。

The invention discloses a debris flow sand retaining dam with a flexible mesh and a construction method thereof. The sand retaining dam includes several concrete buttresses for dividing a wide mud and rock flow channel into a number of suitable width ranges for the flexible mesh, and the concrete buttresses are stepped. Rise up and set in sequence from bottom to top as the first step, the second step and the third step; each concrete buttress is provided with a lateral tooth sill in the longitudinal middle of the side with the adjacent concrete buttress; the concrete The bottom of the pier is provided with a horizontal cap, and the bottom of the horizontal cap is provided with anti-slip tooth sills and several steel pipe piles. The structure of the invention is simple in construction and saves investment, and can be used for blocking mud-rock flows in large and wide ditches. When the debris flow comes, the debris flow is divided into multiple strands by the concrete pier, and then accumulates under the action of the flexible net barrier between the adjacent first steps. Accumulate under the action to realize the control of debris flow.

Description

一种柔性网泥石流拦砂坝及其施工方法A flexible net debris flow sand retaining dam and its construction method

技术领域technical field

本发明涉及泥石流沟道治理工程领域,具体涉及一种柔性网泥石流拦砂坝及其施工方法。The invention relates to the field of mud-rock flow ditch control engineering, in particular to a flexible mesh mud-rock flow sand retaining dam and a construction method thereof.

背景技术Background technique

泥石流是指在山区或者其他沟谷深壑、地形险峻的地区,因为暴雨、暴雪或其他自然灾害引发的山体滑坡并携带有大量泥沙以及石块的特殊洪流。泥石流具有突然性以及流速快,流量大,物质容量大和破坏力强等特点。发生泥石流常常会冲毁公路铁路等交通设施甚至村镇等,造成巨大损失。Debris flow refers to a special torrent carrying a large amount of sediment and stones due to landslides caused by heavy rain, snowstorm or other natural disasters in mountainous areas or other areas with deep valleys and steep terrain. Debris flow has the characteristics of suddenness, fast flow rate, large flow rate, large material capacity and strong destructive force. Debris flows often destroy highways, railways and other transportation facilities and even villages and towns, causing huge losses.

泥石流是暴雨、洪水将含有沙石且松软的土质山体经饱和稀释后形成的洪流,它的面积、体积和流量都较大,而滑坡是经稀释土质山体小面积的区域,典型的泥石流由悬浮着粗大固体碎屑物并富含粉砂及粘土的粘稠泥浆组成。在适当的地形条件下,大量的水体浸透流水山坡或沟床中的固体堆积物质,使其稳定性降低,饱含水分的固体堆积物质在自身重力作用下发生运动,就形成了泥石流。泥石流是一种灾害性的地质现象。通常泥石流爆发突然、来势凶猛,可携带巨大的石块。因其高速前进,具有强大的能量,因而破坏性极大。因此,治理与防护泥石流有着不言而喻的重要性。Debris flow is a torrent formed by heavy rain and floods after saturation and dilution of soft soil mountains containing sand and rocks. Its area, volume and flow are large, while landslides are areas of small areas of diluted soil mountains. Typical debris flows are caused by suspended It is composed of viscous mud rich in silt and clay with coarse solid clastics. Under appropriate terrain conditions, a large amount of water soaks the solid accumulations in the flowing water hillside or ditch bed, reducing its stability, and the solid accumulations saturated with water move under their own gravity, forming a debris flow. Debris flow is a disastrous geological phenomenon. Mudslides usually erupt suddenly and violently, and can carry huge rocks. Because of its high speed and powerful energy, it is extremely destructive. Therefore, it is self-evidently important to control and prevent debris flow.

在泥石流沟道中,一般采用混凝土拦砂坝,并在坝身上设置排泄孔、坝顶上设置溢流口。一方面,大体积混凝土拦砂坝对于沟谷岸坡基础要求较高,基坑开挖大,增加了固体物源量;另一方面混凝土坝基础易发生变形且施工周期长、造价高。因此有必要设计一种简单实用的拦砂坝结构对泥石流沟道进行治理。In debris flow channels, concrete sand retaining dams are generally used, and discharge holes are set on the dam body and overflow ports are set on the dam crest. On the one hand, large-volume concrete sand check dams have higher requirements for the foundation of valley slopes, and the excavation of foundation pits is large, which increases the amount of solid matter; on the other hand, the foundation of concrete dams is prone to deformation, and the construction period is long and the cost is high. Therefore, it is necessary to design a simple and practical sand retaining dam structure to control the debris flow channel.

泥石流柔性网防护结构广泛应用于西方国家的泥石流治理工程中,具有节约投资,景观性好,便于安装等特点。但由于柔性网易于变形,结构不稳定,限制了其使用的宽度,柔性网强度也限制了拦挡高度。因此,如何改进柔性网扩大其使用范围,将柔性网应用于宽阔泥石流沟道对泥石流防治工程类型选择具有一定参考价值。Debris flow flexible mesh protection structure is widely used in debris flow control projects in western countries. It has the characteristics of saving investment, good landscape and easy installation. However, because the flexible net is easy to deform and its structure is unstable, the width of its use is limited, and the strength of the flexible net also limits the blocking height. Therefore, how to improve the flexible net to expand its application range and apply the flexible net to wide debris flow channels has certain reference value for the selection of debris flow prevention and control projects.

发明内容Contents of the invention

针对现有技术中的上述不足,本发明提供的一种柔性网泥石流拦砂坝及其施工方法将柔性网应用于泥石流治理工程中,结构设计简便、施工便捷不会对原沟道底床产生大量破坏,为泥石流的治理提供了良好的解决方案。Aiming at the above-mentioned deficiencies in the prior art, the present invention provides a flexible mesh debris flow sand control dam and its construction method. The flexible mesh is applied to the debris flow control project. The structure design is simple and the construction is convenient without causing damage to the original channel bed A large amount of damage has provided a good solution for the control of debris flow.

为了达到上述发明目的,本发明采用的技术方案为:In order to achieve the above-mentioned purpose of the invention, the technical scheme adopted in the present invention is:

提供一种柔性网泥石流拦砂坝,其包括若干用于将泥石流沟道分割为适合柔性网宽度范围的混凝土支墩,混凝土支墩呈台阶型上升,且由下至上依次设置为第一级阶梯、第二级阶梯和第三级阶梯;相邻两个混凝土支墩之间的第一级阶梯中部两侧设置有使混凝土支墩在泥石流堆积过程中更加稳固的侧向齿槛;相邻两个混凝土支墩的第一级阶梯、第二级阶梯和第三级阶梯之间均布设有柔性网;Provided is a flexible mesh debris flow sand retaining dam, which includes several concrete buttresses for dividing the debris flow channel into suitable for the width range of the flexible mesh. The concrete buttresses rise in a step-like manner, and are arranged as the first step from bottom to top , the second step and the third step; the two sides of the middle part of the first step between two adjacent concrete piers are provided with lateral tooth sills to make the concrete pier more stable during the accumulation of debris flow; A flexible net is evenly distributed between the first step, the second step and the third step of each concrete pier;

混凝土支墩的底部设置有水平承台,水平承台下游底部设置有防滑齿槛;水平承台的上游底部设置有若干钢管桩。The bottom of the concrete pier is provided with a horizontal cap, and the downstream bottom of the horizontal cap is provided with an anti-slip tooth sill; the upstream bottom of the horizontal cap is provided with several steel pipe piles.

进一步地,混凝土支墩的第一级阶梯、第二级阶梯和第三级阶梯内均设置有从底部贯通到顶部的若干配筋;配筋包括若干直径为20mm的钢筋和若干直径为12mm的箍筋,相邻两根钢筋的间距为20cm,相邻两根箍筋的间距为40cm。Further, the first step, the second step and the third step of the concrete pier are provided with several reinforcements penetrating from the bottom to the top; the reinforcements include several steel bars with a diameter of 20mm and several steel bars with a diameter of 12mm. Stirrups, the distance between two adjacent steel bars is 20cm, and the distance between two adjacent stirrups is 40cm.

进一步地,相邻两个第一级阶梯和第二级阶梯之间的柔性网均布设在下游侧,相邻两个第三级阶梯之间的柔性网均布设在上游侧。Further, the flexible nets between two adjacent first and second steps are all arranged on the downstream side, and the flexible nets between two adjacent third steps are all arranged on the upstream side.

进一步地,每个水平承台的横向长度为8m,纵向长度为13m,高度为2m。Further, the transverse length of each horizontal platform is 8m, the longitudinal length is 13m, and the height is 2m.

进一步地,每个防滑齿槛均设置成梯形,防滑齿槛两底面的纵向长度分别为1.5m和2.5m,防滑齿槛的高度为2m,横向长度为8m。Further, each anti-skid sill is set in a trapezoidal shape, the longitudinal lengths of the two bottom surfaces of the anti-slip sill are 1.5m and 2.5m respectively, the height of the anti-slip sill is 2m, and the transverse length is 8m.

进一步地,若干钢管桩设置成梅花形,每根钢管桩内均填充有水泥浆;两两相邻钢管桩的间距为0.8m,每根钢管桩的长度为10m,公称直径为10cm,壁厚4mm;每根钢管桩上均设置有若干孔距为50cm、孔径为10mm的开孔。Furthermore, a number of steel pipe piles are arranged in a quincunx shape, and each steel pipe pile is filled with cement slurry; the distance between two adjacent steel pipe piles is 0.8m, the length of each steel pipe pile is 10m, and the nominal diameter is 10cm, wall thickness 4mm; each steel pipe pile is provided with a number of openings with a distance of 50cm and a diameter of 10mm.

进一步地,每组相邻混凝土支墩的间距为20m;每个混凝土支墩的第一级阶梯、第二级阶梯和第三级阶梯内均设置有从底部到顶部的若干配筋。Further, the distance between each group of adjacent concrete piers is 20m; the first step, the second step and the third step of each concrete pier are provided with several reinforcements from the bottom to the top.

进一步地,每个第一级阶梯的纵向长度为4.5m,高度为5m,横向长度为5m;每个第二级阶梯的纵向长度为1m,高度为5m,横向长度为5m;每个第三级阶梯的纵向长度为3.5米,高度为5m,横向长度为5m;Further, the longitudinal length of each first step is 4.5m, the height is 5m, and the transverse length is 5m; the longitudinal length of each second step is 1m, the height is 5m, and the transverse length is 5m; each third The vertical length of the steps is 3.5 meters, the height is 5 meters, and the horizontal length is 5 meters;

第一级阶梯内配筋的横向长度为5m,纵向长度为2m,高度为5m;第二级阶梯内配筋的横向长度为5m,纵向长度为1.5m,高度为10m;第三级阶梯内配筋的横向长度为5m,纵向长度为1.5m,高度为15m。The transverse length of reinforcement in the first step is 5m, the longitudinal length is 2m, and the height is 5m; the transverse length of the reinforcement in the second step is 5m, the longitudinal length is 1.5m, and the height is 10m; The transverse length of reinforcement is 5m, the longitudinal length is 1.5m, and the height is 15m.

进一步地,每个侧向齿槛均设置成梯形,侧向齿槛两底面的纵向长度分别为1m和1.5m,横向长度为1.5m。Further, each lateral sill is set in a trapezoidal shape, the longitudinal lengths of the two bottom surfaces of the lateral sills are 1m and 1.5m respectively, and the transverse length is 1.5m.

提供一种柔性网泥石流拦砂坝的施工方法,其包括以下步骤:A construction method for a flexible net debris flow sand dam is provided, which includes the following steps:

S1、在若干长度为10m、直径为10cm的钢管桩(3)上设置若干间距为10cm、直径为1cm的开孔,将钢管桩(3)以两两间距为0.8m的规格呈梅花形深入基底2-3m,并向每根钢管桩(3)内填充水泥浆;S1. Set a number of openings with a distance of 10 cm and a diameter of 1 cm on several steel pipe piles (3) with a length of 10 m and a diameter of 10 cm, and place the steel pipe piles (3) in a plum blossom shape with a distance of 0.8 m in pairs 2-3m deep into the base, and fill each steel pipe pile (3) with cement slurry;

S2、在钢管桩上浇筑水平承台和防滑齿槛,并按照钢筋间距20cm、箍筋间距40cm的规格在水平承台上设置配筋;S2. Pouring horizontal caps and anti-skid sills on the steel pipe piles, and setting reinforcement on the horizontal caps according to the specifications of 20cm between steel bars and 40cm between stirrups;

S3、在水平承台凝固至设计强度后,由下至上依次在水平承台上浇筑第一级阶梯、第二级阶梯和第三级阶梯,形成混凝土支墩,并在相邻两个混凝土支墩之间的第一级阶梯中部两侧设置纵向长度分别为1m和1.5m、横向长度为1.5m的梯形侧向齿槛;S3. After the horizontal bearing platform is solidified to the design strength, pour the first step, the second step and the third step on the horizontal bearing platform from bottom to top to form a concrete support pier, and place two adjacent concrete supports The two sides of the middle part of the first step between the piers are provided with trapezoidal lateral sills with longitudinal lengths of 1m and 1.5m and transverse lengths of 1.5m;

S4、在相邻的两个第一级阶梯、相邻的两个第二级阶梯和相邻的两个第三级阶梯之间各布置一层柔性网。S4. Arranging a layer of flexible net between two adjacent first steps, two adjacent second steps and two adjacent third steps.

本发明的有益效果为:The beneficial effects of the present invention are:

1、本发明将连续式的拦砂坝坝体改进为由数个规则的支墩结构,并且在相邻的支墩间设置柔性防护网成为含有过滤系统的透水体,这样在施工本发明所述的拦砂坝时便可以减少对沟谷、沟道基础的开挖量。1. The present invention improves the continuous sand control dam body into several regular buttress structures, and arranges a flexible protective net between adjacent buttresses to become a water-permeable body containing a filtration system. Just can reduce the amount of excavation to valley, ditch foundation when using the above-mentioned sand retaining dam.

2、通过布设混凝土支墩,使相邻两个混凝土支墩的间隔小于单个泥石流柔性网宽度的使用范围,在高度方向柔性网布设呈阶梯上升,突破了单个柔性网宽度的使用限制,使现有柔性网强度符合实际需求。本发明结构施工简单、节约投资,可用于大型宽阔沟道的泥石流拦挡中。泥石流来临时泥石流由混凝土支墩分为多股,然后在相邻第一级阶梯之间的柔性网拦挡作用下堆积,随着堆积高度超过本段柔性网,泥石流依次在更高水平柔性网拦挡作用下堆积,实现对泥石流的治理。2. By arranging concrete buttresses, the interval between two adjacent concrete buttresses is smaller than the use range of the width of a single debris flow flexible net, and the deployment of flexible nets in the height direction rises in steps, breaking through the limit of the use of a single flexible net width. The strength of the flexible net meets the actual needs. The structure of the invention is simple in construction and saves investment, and can be used for blocking mud-rock flows in large and wide ditches. When the debris flow comes, the debris flow is divided into multiple strands by the concrete pier, and then accumulates under the action of the flexible net barrier between the adjacent first steps. Accumulate under the action to realize the control of debris flow.

3、本发明所述的混凝土支墩对沟谷、沟道基础要求相对较低,而且不会对原沟道基础产生大量破坏,施工周期较短且节约投资。在加上两相邻支墩间含有过滤系统的柔性网,既满足了拦挡固体物质的要求,又能透水和过流,结构设计简单且减少了工程风险,是一种安全可靠的泥石流沟道治理工程,特别适应于大型宽阔沟道的泥石流拦挡中。3. The concrete pier of the present invention has relatively low requirements on valleys and channel foundations, and will not cause a lot of damage to the original channel foundations, and the construction period is short and investment is saved. In addition, the flexible net with filtration system between two adjacent piers not only meets the requirements of blocking solid matter, but also can permeate water and flow. The structure design is simple and reduces engineering risks. It is a safe and reliable debris flow channel Treatment engineering, especially suitable for blocking debris flow in large and wide ditches.

4、防滑齿槛可以限制钢筋混凝土支墩沿沟道方向的位移。4. The anti-slip tooth sill can limit the displacement of the reinforced concrete pier along the direction of the channel.

5、侧向齿槛使得钢筋混凝土支墩在泥石流堆积过程中侧向更加的稳固。5. The lateral sill makes the reinforced concrete pier more stable laterally during the accumulation of debris flow.

6、在混凝土中进行配筋,可以增加混凝土的强度和刚度。纵向受力钢筋的主要作用是承受外力作用下梁内产生的拉力。架立钢筋的主要作用是固定箍筋保证其正确位置,并形成一定刚度的钢筋骨架。同时,架立钢筋还能承受因温度变化和混凝土收缩而产生的应力,防止裂缝产生。箍筋的主要作用是承受剪力。此外,箍筋与其他钢筋通过绑扎或焊接形成一个整体性良好的空间骨架。6. Reinforcement in concrete can increase the strength and rigidity of concrete. The main function of the longitudinally stressed steel bar is to bear the tension generated in the beam under the action of external force. The main function of erecting steel bars is to fix the stirrup to ensure its correct position and form a steel skeleton with a certain rigidity. At the same time, the erecting steel bars can also withstand the stress caused by temperature changes and shrinkage of concrete to prevent cracks. The main function of the stirrup is to bear the shear force. In addition, stirrups and other steel bars form a well-integrated space skeleton by binding or welding.

7、梅花形布置的承载支撑点呈多角形分布,因而桩基的稳定性好,不均匀沉降小,不会随时间倾斜或者有裂缝。7. The bearing support points arranged in a quincunx shape are distributed in a polygonal shape, so the stability of the pile foundation is good, the uneven settlement is small, and it will not tilt or crack over time.

8、钢管桩上设置的若干开孔便于水泥浆与周围底层固结为一体,提高钢管桩的固定效果。8. A number of openings set on the steel pipe pile facilitate the consolidation of the cement slurry with the surrounding bottom layer and improve the fixing effect of the steel pipe pile.

9、钢管桩可以防止水平承台下部土层被冲刷,提高本发明的耐用稳固性。9. The steel pipe pile can prevent the soil layer at the lower part of the horizontal cap from being scoured, improving the durability and stability of the present invention.

附图说明Description of drawings

图1为本发明设置三个混凝土支墩的立体结构示意图。Fig. 1 is a three-dimensional structural schematic diagram of setting three concrete buttresses according to the present invention.

其中:1、混凝土支墩;2、水平承台;3、钢管桩;4、防滑齿槛;5、柔性网;6、侧向齿槛;7、第一级阶梯;8、第二级阶梯;9、第三级阶梯。Among them: 1. Concrete buttress; 2. Horizontal cap; 3. Steel pipe pile; 4. Anti-skid sill; 5. Flexible mesh; 6. Lateral sill; 7. The first step; 8. The second level ladder; 9, the third ladder.

具体实施方式Detailed ways

下面对本发明的具体实施方式进行描述,以便于本技术领域的技术人员理解本发明,但应该清楚,本发明不限于具体实施方式的范围,对本技术领域的普通技术人员来讲,只要各种变化在所附的权利要求限定和确定的本发明的精神和范围内,这些变化是显而易见的,一切利用本发明构思的发明创造均在保护之列。The specific embodiments of the present invention are described below so that those skilled in the art can understand the present invention, but it should be clear that the present invention is not limited to the scope of the specific embodiments. For those of ordinary skill in the art, as long as various changes Within the spirit and scope of the present invention defined and determined by the appended claims, these changes are obvious, and all inventions and creations using the concept of the present invention are included in the protection list.

如图1所示(本发明具有延续性,图中仅画出了3个水平承台2以及对应的其他部件,若需要将水平承台2设置为其他数量,只需在图1的基础上向两侧增加水平承台2以及对应的其他部件即可),该柔性网泥石流拦砂坝包括若干用于将泥石流沟道分割为适合柔性网5宽度范围的混凝土支墩1,混凝土支墩1呈台阶型上升,且由下至上依次设置为第一级阶梯7、第二级阶梯8和第三级阶梯9;相邻两个混凝土支墩1之间的第一级阶梯7中部两侧设置有使混凝土支墩1在泥石流堆积过程中更加稳固的侧向齿槛6;相邻两个混凝土支墩1的第一级阶梯7、第二级阶梯8和第三级阶梯9之间均布设有柔性网5;As shown in Figure 1 (the present invention has continuity, only draw 3 horizontal bearing platforms 2 and other corresponding parts among the figure, if need horizontal bearing platform 2 be set to other numbers, only need on the basis of Fig. 1 Just add horizontal caps 2 and other corresponding components to both sides), the flexible net debris flow sand retaining dam includes several concrete buttresses 1 for dividing the debris flow channel into the width range of the flexible net 5, and the concrete buttresses 1 It rises in the form of steps, and is set in sequence from bottom to top as the first step 7, the second step 8 and the third step 9; the first step 7 between two adjacent concrete piers 1 is set on both sides of the middle There are lateral tooth sills 6 that make the concrete buttress 1 more stable during the accumulation of debris flow; the first step 7, the second step 8 and the third step 9 of two adjacent concrete buttresses 1 are all laid out There is a flexible net 5;

混凝土支墩1的底部设置有水平承台2,水平承台2下游底部设置有防滑齿槛4;水平承台2的上游底部设置有若干钢管桩3。The bottom of the concrete pier 1 is provided with a horizontal cap 2 , and the downstream bottom of the horizontal cap 2 is provided with an anti-skid sill 4 ; the upstream bottom of the horizontal cap 2 is provided with several steel pipe piles 3 .

混凝土支墩1的第一级阶梯7、第二级阶梯8和第三级阶梯9内均设置有从底部贯通到顶部的若干配筋。The first step 7, the second step 8 and the third step 9 of the concrete pier 1 are provided with a number of reinforcements penetrating from the bottom to the top.

相邻两个第一级阶梯7和第二级阶梯8之间的柔性网5均布设在下游侧,相邻两个第三级阶梯9之间的柔性网5均布设在上游侧。The flexible nets 5 between two adjacent first steps 7 and the second steps 8 are arranged on the downstream side, and the flexible nets 5 between two adjacent third steps 9 are arranged on the upstream side.

每个水平承台2的横向长度为8m,纵向长度为13m,高度为2m。The transverse length of each horizontal platform 2 is 8m, the longitudinal length is 13m, and the height is 2m.

每个防滑齿槛4均设置成梯形,防滑齿槛4两底面的纵向长度分别为1.5m和2.5m,防滑齿槛4的高度为2m,横向长度为8m。Each anti-slip tooth sill 4 is all set to trapezoidal, the longitudinal length of the two bottom surfaces of the anti-slip tooth sill 4 is 1.5m and 2.5m respectively, the height of the anti-slip tooth sill 4 is 2m, and the transverse length is 8m.

若干钢管桩3设置成梅花形,每根钢管桩3内均填充有水泥浆;两两相邻钢管桩3的间距为0.8m,每根钢管桩3的长度为10m,公称直径为10cm,壁厚4mm;每根钢管桩3上均设置有若干孔距为50cm、孔径为10mm的开孔。Several steel pipe piles 3 are arranged in a quincunx shape, and each steel pipe pile 3 is filled with cement slurry; the distance between two adjacent steel pipe piles 3 is 0.8m, the length of each steel pipe pile 3 is 10m, and the nominal diameter 10cm, wall thickness 4mm; each steel pipe pile 3 is provided with a number of openings with a pitch of 50cm and a diameter of 10mm.

每组相邻混凝土支墩1的间距为20m;每个混凝土支墩1的第一级阶梯7、第二级阶梯8和第三级阶梯9内均设置有从底部到顶部的若干配筋。The distance between each group of adjacent concrete pier 1 is 20m; the first step 7, the second step 8 and the third step 9 of each concrete pier 1 are provided with several reinforcements from the bottom to the top.

每个第一级阶梯7的纵向长度为4.5m,高度为5m,横向长度为5m;每个第二级阶梯8的纵向长度为1m,高度为5m,横向长度为5m;每个第三级阶梯9的纵向长度为3.5米,高度为5m,横向长度为5m。The longitudinal length of each first-order ladder 7 is 4.5m, the height is 5m, and the transverse length is 5m; the longitudinal length of each second-order ladder 8 is 1m, the height is 5m, and the transverse length is 5m; each third-level The vertical length of the ladder 9 is 3.5 meters, the height is 5 m, and the horizontal length is 5 m.

配筋设置为三组并分别设置在第一级阶梯7、第二级阶梯8和第三级阶梯9内;第一级阶梯7内配筋的横向长度为5m,纵向长度为2m,高度为5m;第二级阶梯8内配筋的横向长度为5m,纵向长度为1.5m,高度为10m(第二级阶梯8内的配筋已部分进入第三级阶梯9中);第三级阶梯9内配筋的横向长度为5m,纵向长度为1.5m,高度为15m;配筋包括若干直径为20mm的二级钢筋和若干直径为12mm的二级箍筋,相邻两根钢筋的间距为20cm,相邻两根箍筋的间距为40cm。The reinforcements are set in three groups and are respectively arranged in the first step 7, the second step 8 and the third step 9; the horizontal length of the reinforcement in the first step 7 is 5m, the longitudinal length is 2m, and the height is 5m; the horizontal length of the reinforcement in the second step 8 is 5m, the longitudinal length is 1.5m, and the height is 10m (the reinforcement in the second step 8 has partially entered the third step 9); the third step 9. The horizontal length of the internal reinforcement is 5m, the longitudinal length is 1.5m, and the height is 15m; the reinforcement includes several secondary steel bars with a diameter of 20mm and several secondary stirrups with a diameter of 12mm, and the distance between two adjacent steel bars is 20cm, and the distance between two adjacent stirrups is 40cm.

每个侧向齿槛6均设置成梯形,侧向齿槛6两底面的纵向长度分别为1m和1.5m,横向长度为1.5m。Each lateral tooth sill 6 is arranged in a trapezoidal shape, the longitudinal lengths of the two bottom surfaces of the lateral tooth sills 6 are respectively 1m and 1.5m, and the transverse length is 1.5m.

该柔性网泥石流拦砂坝的施工方法包括以下步骤:The construction method of the flexible net debris flow sand retaining dam comprises the following steps:

S1、基底的开挖:根据拟建拦砂坝的基底应力和坝基天然地基承载力等要求来设计开挖基坑至所需高程;S1. Excavation of the base: design and excavate the foundation pit to the required elevation according to the base stress of the proposed sand control dam and the bearing capacity of the natural foundation of the dam foundation;

S2、钢管桩3的布设:结合拦砂坝所处的地形条件,将直径为10cm的钢管桩3打入基底以下2-3米,呈梅花形布置,间距为0.8m。钢管桩3内注入水泥浆,使得钢管与管内水泥浆结合为一体,构成复合钢管桩基;S2. Layout of steel pipe piles 3: Combined with the topographical conditions of the sand retaining dam, the steel pipe piles 3 with a diameter of 10cm are driven into 2-3 meters below the base, arranged in a plum blossom shape with a spacing of 0.8m. Cement slurry is injected into the steel pipe pile 3, so that the steel pipe and the cement slurry in the pipe are integrated to form a composite steel pipe pile foundation;

S3、防滑齿槛4的布设:防滑齿槛4布设在水平承台2的坡脚处,深度2-5米,长度与宽度和水平承台2尺寸保持一致;S3. Arrangement of the anti-slip tooth sill 4: the anti-slip tooth sill 4 is arranged at the slope foot of the horizontal bearing platform 2, the depth is 2-5 meters, and the length and width are consistent with the size of the horizontal bearing platform 2;

S4、钢筋混凝土水平承台2的施工:水平承台2的施工要与钢管桩3和防滑齿槛4衔接牢固,按照设计要求选定相应的混凝土标号和钢筋规格;S4. Construction of the reinforced concrete horizontal bearing platform 2: the construction of the horizontal bearing platform 2 shall be firmly connected with the steel pipe pile 3 and the anti-skid tooth sill 4, and the corresponding concrete label and steel bar specification shall be selected according to the design requirements;

S5、钢筋混凝土支墩1的施工:根据工程勘察报告,确定土体内摩擦角、粘聚力等土力学参数,考虑拦砂坝在不同运行情况下的受力状态,进行拦砂坝支墩的抗滑、抗倾覆稳定性计算。以水平承台2为基础,当水平承台2达到设计强度后,开始由下往上逐级分层施工支墩阶梯直到完成整个支墩的施工工作,混凝土标号采用C20,主筋采用直径20mm二级钢筋,钢筋间距20cm,箍筋采用12mm二级钢筋,间距40cm;S5. Construction of reinforced concrete pier 1: According to the engineering survey report, determine the soil mechanical parameters such as friction angle and cohesion in the soil, and consider the stress state of the sand control dam under different operating conditions to carry out the construction of the sand control dam support pier Calculation of anti-skid and anti-overturning stability. Based on the horizontal bearing platform 2, when the horizontal bearing platform 2 reaches the design strength, start to construct the buttress ladder layer by layer from bottom to top until the construction of the entire buttress is completed. The concrete label is C20, and the main reinforcement is 20mm in diameter. The first-grade steel bar, the steel bar spacing is 20cm, and the stirrup adopts 12mm second-level steel bar, the spacing is 40cm;

S6、侧向齿槛6的施工:施工支墩最底部阶梯的同时,在支墩的外侧面一并进行梯形侧向齿槛6的施工,侧向齿槛6两底面的纵向长度分别为1m和1.5m,横向长度为1.5m;S6. Construction of the lateral tooth sill 6: while constructing the bottom step of the pier, the construction of the trapezoidal lateral tooth sill 6 is carried out on the outer surface of the buttress. The longitudinal lengths of the two bottom surfaces of the lateral tooth sill 6 are 1m respectively and 1.5m, the transverse length is 1.5m;

S7、柔性网5的布设:在两相邻的支墩间布设多个柔性防护网,且柔性防护网在水平方向随着高度增高依次向上游布置。下游、中间部分柔性防护网布置于支墩第一、二级阶梯的下游侧,最上游端柔性防护网布置于支墩第三级的上游侧。S7. Arrangement of the flexible net 5: a plurality of flexible protective nets are laid between two adjacent piers, and the flexible protective nets are arranged upstream in the horizontal direction as the height increases. The downstream and middle part of the flexible protective net is arranged on the downstream side of the first and second steps of the buttress, and the most upstream flexible protective net is arranged on the upstream side of the third level of the buttress.

在本发明的一个实施例中,柔性网5的设置层数可以根据泥石流规模、沟道的深度等需要进行取舍。In one embodiment of the present invention, the number of layers of the flexible net 5 can be selected according to the scale of the debris flow, the depth of the channel, and the like.

本发明通过布设混凝土支墩1,使相邻两个混凝土支墩1的间隔小于单个泥石流柔性网5长度的使用范围,在高度方向柔性网5布设呈阶梯上升,使现有柔性网5高度符合实际需求。本发明结构施工简单、节约投资,可用于大型宽阔沟道的泥石流拦挡中。泥石流来临时泥石流由混凝土支墩1分为多股,然后在相邻第一级阶梯7之间的柔性网5拦挡作用下堆积,随着堆积高度超过本段柔性网5,泥石流依次在更高水平柔性网5拦挡作用下堆积,实现对泥石流的治理。In the present invention, by arranging concrete buttresses 1, the interval between two adjacent concrete buttresses 1 is smaller than the use range of the length of a single debris flow flexible net 5, and the arrangement of flexible nets 5 in the height direction rises in steps, so that the height of the existing flexible nets 5 conforms to Actual demand. The structure of the invention is simple in construction and saves investment, and can be used for blocking mud-rock flows in large and wide ditches. When the debris flow comes, the debris flow is divided into multiple strands by the concrete support pier 1, and then accumulates under the blocking effect of the flexible net 5 between the adjacent first steps 7. As the accumulation height exceeds the flexible net 5 in this section, the debris flow is successively higher. The horizontal flexible net 5 is piled up under the blocking effect to realize the control of debris flow.

Claims (10)

1. a kind of flexible net debris flow dam, it is characterised in that:Including it is several for mud-rock flow channel is divided into be suitble to it is soft Property net (5) width range concrete buttress (1), the concrete buttress (1) rises in stepped ramp type, and successively sets from the bottom to top It is set to first order ladder (7), second level ladder (8) and third level ladder (9);Between the two neighboring concrete buttress (1) First order ladder (7) on both sides of the middle be provided with and keep the concrete buttress (1) more firm during Debris Flow Deposition Lateral notched sill (6);First order ladder (7), second level ladder (8) and the third level rank of the two neighboring concrete buttress (1) The flexible net (5) are laid between terraced (9);
The bottom of the concrete buttress (1) is provided with horizontal cushion cap (2), and horizontal cushion cap (2) downstream base portion is provided with anti- Slip teeth sill (4);The upstream bottom of the horizontal cushion cap (2) is provided with several steel-pipe piles (3).
2. flexible net debris flow dam according to claim 1, it is characterised in that:The of the concrete buttress (1) Several arrangements of reinforcement that top is penetrated into from bottom are provided in step (7), second level ladder (8) and third level ladder (9); The stirrup that the arrangement of reinforcement includes the reinforcing bar that several diameters are 20mm and several diameters are 12mm, the spacing of adjacent two reinforcing bars For 20cm, the spacing of adjacent two stirrups is 40cm.
3. flexible net debris flow dam according to claim 1, it is characterised in that:Two neighboring first order ladder (7) Flexible net (5) between second level ladder (8) is laid in downstream side, the flexibility between two neighboring third level ladder (9) Net (5) is laid in upstream side.
4. flexible net debris flow dam according to claim 1, it is characterised in that:Each horizontal cushion cap (2) Lateral length is 8m, longitudinal length 13m, is highly 2m.
5. flexible net debris flow dam according to claim 1, it is characterised in that:Each anti-skidding notched sill (4) is equal It is arranged to trapezoidal, the longitudinal length of anti-skidding (4) two bottom surface of notched sill is respectively 1.5m and 2.5m, and the height of anti-skidding notched sill (4) is 2m, Lateral length is 8m.
6. flexible net debris flow dam according to claim 1, it is characterised in that:Several steel-pipe pile (3) settings At quincunx, cement slurry is filled in the every steel-pipe pile (3);The spacing of the adjacent steel-pipe pile (3) is 0.8m two-by-two, The length of the every steel-pipe pile (3) is 10m, nominal diameter 10cm, wall thickness 4mm;It is respectively provided on the every steel-pipe pile (3) There are several holes away from the aperture for being 10mm for 50cm, aperture.
7. flexible net debris flow dam according to claim 1, it is characterised in that:Every group of adjacent concrete buttress (1) Spacing be 20m.
8. flexible net debris flow dam according to claim 2, it is characterised in that:Each first order ladder (7) Longitudinal length be 4.5m, be highly 5m, lateral length 5m;The longitudinal length of each second level ladder (8) is 1m, high Degree is 5m, lateral length 5m;The longitudinal length of each third level ladder (9) is 3.5 meters, is highly 5m, lateral length For 5m;
The lateral length of the interior arrangement of reinforcement of the first order ladder (7) is 5m, longitudinal length 2m, is highly 5m;The second level rank The lateral length of terraced (8) interior arrangement of reinforcement is 5m, longitudinal length 1.5m, is highly 10m;The interior arrangement of reinforcement of the third level ladder (9) Lateral length is 5m, longitudinal length 1.5m, is highly 15m.
9. flexible net debris flow dam according to claim 1, it is characterised in that:Each lateral notched sill (6) is equal It is arranged to trapezoidal, the longitudinal length of lateral (6) two bottom surface of notched sill is respectively 1m and 1.5m, lateral length 1.5m.
10. a kind of construction method of flexible net debris flow dam, which is characterized in that include the following steps:
S1, it is arranged that several spacing are 10cm, diameter is 1cm's on the steel-pipe pile (3) that several length are 10m, diameter is 10cm Steel-pipe pile (3) is goed deep into substrate 2-3m in quincunx for the specification of 0.8m with spacing two-by-two by aperture, and to every steel-pipe pile (3) Interior filling concrete slurry;
S2, horizontal cushion cap (2) and anti-skidding notched sill (4) are poured on steel-pipe pile (3), and according to bar spacing 20cm, stirrup spacing Arrangement of reinforcement is arranged on horizontal cushion cap (2) in the specification of 40cm;
S3, in horizontal cushion cap (2), solidification to after design strength, successively pours first order rank on horizontal cushion cap (2) from the bottom to top Terraced (7), second level ladder (8) and third level ladder (9) are formed concrete buttress (1), and in two neighboring concrete buttress (1) between first order ladder (7) on both sides of the middle setting longitudinal length be respectively 1m and 1.5m, lateral length be 1.5m it is trapezoidal Lateral notched sill (6);
S4, in two adjacent first order ladders (7), two adjacent second level ladders (8) and two adjacent third level ranks One layer of flexible net (5) is respectively arranged between terraced (9).
CN201710383716.8A 2017-05-26 2017-05-26 A kind of flexible net debris flow dam and its construction method Expired - Fee Related CN107090804B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710383716.8A CN107090804B (en) 2017-05-26 2017-05-26 A kind of flexible net debris flow dam and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710383716.8A CN107090804B (en) 2017-05-26 2017-05-26 A kind of flexible net debris flow dam and its construction method

Publications (2)

Publication Number Publication Date
CN107090804A CN107090804A (en) 2017-08-25
CN107090804B true CN107090804B (en) 2018-11-20

Family

ID=59639597

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710383716.8A Expired - Fee Related CN107090804B (en) 2017-05-26 2017-05-26 A kind of flexible net debris flow dam and its construction method

Country Status (1)

Country Link
CN (1) CN107090804B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109667246A (en) * 2019-02-12 2019-04-23 中交第四航务工程勘察设计院有限公司 A kind of nuclear power plant's water intaking open channel sewage blocking device
CN110004882A (en) * 2019-04-19 2019-07-12 西南交通大学 Debris flow multi-level dissipative retaining structure
CN111420963A (en) * 2020-04-24 2020-07-17 北京市市政工程设计研究总院有限公司 Garbage anti-flying net
CN111608139B (en) * 2020-06-20 2021-10-29 中国科学院、水利部成都山地灾害与环境研究所 Super-large-scale flood and gravel flow prevention methods
CN119041359B (en) * 2024-11-04 2025-01-24 中国科学院、水利部成都山地灾害与环境研究所 Assembled debris flow comprehensive sand blocking dam system and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201165666Y (en) * 2008-03-11 2008-12-17 陈莉 Flexible Mesh Valley Square
CN103526722A (en) * 2013-10-16 2014-01-22 中国科学院、水利部成都山地灾害与环境研究所 Debris flow gabion prevention and control structural body and design method thereof
CN203475447U (en) * 2013-08-28 2014-03-12 布鲁克(成都)工程有限公司 Flexible blocking net
CN103696402A (en) * 2014-01-01 2014-04-02 中国科学院-水利部成都山地灾害与环境研究所 Wire mesh bottom protection type debris flow drain and guide ditch and application and construction methods thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001342618A (en) * 2000-05-31 2001-12-14 Yoshida Kouzou Design:Kk Transmission type erosion control dam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201165666Y (en) * 2008-03-11 2008-12-17 陈莉 Flexible Mesh Valley Square
CN203475447U (en) * 2013-08-28 2014-03-12 布鲁克(成都)工程有限公司 Flexible blocking net
CN103526722A (en) * 2013-10-16 2014-01-22 中国科学院、水利部成都山地灾害与环境研究所 Debris flow gabion prevention and control structural body and design method thereof
CN103696402A (en) * 2014-01-01 2014-04-02 中国科学院-水利部成都山地灾害与环境研究所 Wire mesh bottom protection type debris flow drain and guide ditch and application and construction methods thereof

Also Published As

Publication number Publication date
CN107090804A (en) 2017-08-25

Similar Documents

Publication Publication Date Title
CN107090804B (en) A kind of flexible net debris flow dam and its construction method
CN103526722B (en) Debris flow gabion prevention structure and design method thereof
CN201722704U (en) Pre-stressed cantilever counter rib holding retaining wall
US20150050086A1 (en) Methods of and systems for controlling water flow, breaking water waves and reducing surface erosion along rivers, streams, waterways and coastal regions
US7377726B2 (en) Method and apparatus for building reinforced sea walls and levees
RU2358063C1 (en) Device for slope surface grouting
CN101899839A (en) A kind of prestressed cantilever opposite tension retaining wall with reinforcement
EA037484B1 (en) Retaining wall method of precast block to prevent landslide
CN101215815A (en) Construction method of composite road with integral cantilever structure suitable for steep mountainous areas
CN110004882A (en) Debris flow multi-level dissipative retaining structure
CN103556602A (en) Structural body for preventing starting of gully debris flows and design method of structural body
CN108005094B (en) Pier and pier top beam section construction method in naked rock river bed water
CN110629770B (en) A kind of anti-seepage-slope protection structure and construction method of slope ebb and flow zone in reservoir area
CN108951335A (en) A kind of light-duty escarpment road structure
CN109594530B (en) Novel structure of fine sand stratum flood control dykes and dams
CN101824809B (en) Large-gradient gravel river bank protective structure and river washout-resistant controlling method thereof
CN111945657B (en) A dock upgrading and reconstruction structure and a dock upgrading and reconstruction construction method
CN104963323A (en) Scour-preventing groove for chain precast block protective surface
CN107326791A (en) Improvement method and structure of flooding bridge
JP2017082441A (en) Dam structure
CN114232666B (en) Multi-span prestressed elastic foundation beam structure for spanning complex karst cave group and construction method
CN209989781U (en) Novel structure of silty-fine sand stratum flood control dam
CN211947887U (en) a water-filled bridge
RU2377363C1 (en) Soil non-homogenuous fill dam
JP6669435B2 (en) Construction method of dam and dam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181120

Termination date: 20210526