CN107083993B - The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head - Google Patents
The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head Download PDFInfo
- Publication number
- CN107083993B CN107083993B CN201611146690.7A CN201611146690A CN107083993B CN 107083993 B CN107083993 B CN 107083993B CN 201611146690 A CN201611146690 A CN 201611146690A CN 107083993 B CN107083993 B CN 107083993B
- Authority
- CN
- China
- Prior art keywords
- tunnel
- monitoring
- instrument
- embedment
- high water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/18—Special adaptations of signalling or alarm devices
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/102—Removable shuttering; Bearing or supporting devices therefor
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
- Geophysics And Detection Of Objects (AREA)
Abstract
本发明公开了一种高水头长隧洞中安全监测仪器的埋设安装结构及其具体的安装方法,其中埋设安装结构包括若干隧洞监测断面埋设安装单元,隧洞监测断面埋设安装单元包括临时保护木箱以及若干光纤光栅监测仪器,各光纤光栅监测仪器均连接有线缆,临时保护木箱为梯形,其顶部具有可打开的盖板,一侧具有隧洞中长渠侧面相适应的斜面,箱体上设置有开口,各光纤光栅监测仪器接出的线缆均通过所述开口引入至临时保护木箱内,线缆用于连接临时光缆或主传输光缆。本发明方案能够有效保护监测仪器引出尾缆,提高仪器埋设完好率和监测资料的完整性,且同一个监测断面的光纤光栅仪器的波长测值尽量不重复,提高系统波分复用效率。
The invention discloses a buried installation structure of a safety monitoring instrument in a long tunnel with high water head and a specific installation method thereof. The buried installation structure includes a plurality of buried installation units in tunnel monitoring sections, and the buried installation units in the tunnel monitoring section include temporary protection wooden boxes and Several fiber grating monitoring instruments, each fiber grating monitoring instrument is connected with a cable, the temporary protective wooden box is trapezoidal, the top has an openable cover, and one side has a slope suitable for the side of the long canal in the tunnel, and the box is provided with There are openings through which the cables connected by each fiber grating monitoring instrument are introduced into the temporary protective wooden box, and the cables are used to connect the temporary optical cables or the main transmission optical cables. The solution of the invention can effectively protect the tail cable of the monitoring instrument, improve the integrity rate of the instrument burial and the integrity of the monitoring data, and try not to repeat the wavelength measurement value of the fiber grating instrument on the same monitoring section, thereby improving the system wavelength division multiplexing efficiency.
Description
技术领域technical field
本发明属于岩土工程安全监测技术领域,具体涉及高水头长隧洞中安全监测仪器的埋设安装结构及其安装方法。The invention belongs to the technical field of geotechnical engineering safety monitoring, and in particular relates to a buried installation structure of a safety monitoring instrument in a long tunnel with high water head and an installation method thereof.
背景技术Background technique
在岩土工程中必须安装安全监测仪器对现场的各个环节进行监测,以便在出现异常时进行预警从而及时采取对应手段。安全监测仪器如钢筋计、应变计、渗压计等一般采用差动电阻式、振弦式等电式传感器。近年来,随着长距离输调水工程的实施以及光纤光栅传感及解调技术的发展,基于光纤Bragg光栅(Fiber Bragg Grating,简称FBG)传感器在引水工程中逐步得到应用,这是由于光纤光栅仪器具有长距离信号传输、灵活组网、抗电磁干扰、绝缘要求低等等优势。In geotechnical engineering, safety monitoring instruments must be installed to monitor all aspects of the site, so as to give early warning in case of abnormality and take corresponding measures in time. Safety monitoring instruments such as rebar gauges, strain gauges, and piezometers generally use differential resistance, vibrating wire and other electrical sensors. In recent years, with the implementation of long-distance water transfer projects and the development of fiber Bragg grating sensing and demodulation technology, sensors based on Fiber Bragg Grating (FBG) have been gradually applied in water diversion projects. Grating instruments have the advantages of long-distance signal transmission, flexible networking, anti-electromagnetic interference, and low insulation requirements.
在隧道施工中安装监测仪器一直属于施工中的难点,因为隧道距离长、空间小、施工也较粗放,这就导致隧道施工对安全监测仪器的安装、保护难度相对其他工程来说要大,甚至根本无法安装,有时即使安装到位,但在隧洞浇筑过程中,也易对监测仪器造成损坏。而且,隧洞衬砌浇筑过程中的数据完全无法采集。The installation of monitoring instruments in tunnel construction has always been a difficult point in construction, because the tunnel distance is long, the space is small, and the construction is relatively extensive, which makes the installation and protection of safety monitoring instruments in tunnel construction more difficult than other projects, and even It is impossible to install at all, and sometimes even if it is installed in place, it is easy to cause damage to the monitoring equipment during the tunnel pouring process. Moreover, the data during the tunnel lining pouring process cannot be collected at all.
发明内容SUMMARY OF THE INVENTION
为解决上述问题,本发明公开了一种高水头长隧洞中安全监测仪器的埋设安装结构及其具体的安装方法,能够实现在长隧洞之中对安全监测仪器的快速稳定安装。In order to solve the above problems, the present invention discloses a buried installation structure of a safety monitoring instrument in a long tunnel with high water head and a specific installation method thereof, which can realize the fast and stable installation of the safety monitoring instrument in the long tunnel.
为了达到上述目的,本发明提供如下技术方案:In order to achieve the above object, the present invention provides the following technical solutions:
高水头长隧洞中安全监测仪器的埋设安装方法,包括如下步骤:The method for burying and installing safety monitoring instruments in long tunnels with high water head includes the following steps:
步骤一,开挖清基完成后,开始绑扎钢筋,在钢筋绑扎完成前在本仓内同步安装模板台车轨道,同时模板台车在邻仓混凝土位置装配完成,在同一隧洞监测断面钢筋上沿圆周方向安装多个光纤光栅监测仪器,在隧洞底部钢筋上固定易拆除的临时保护木箱,所述多个光纤光栅监测仪器接出的尾缆自临时保护木箱开口处引入临时保护木箱内;Step 1: After the excavation and clearing of the foundation are completed, start to bind the steel bars. Before the steel bars are bound, the formwork trolley tracks are installed in the warehouse synchronously. At the same time, the formwork trolleys are assembled at the concrete position of the adjacent warehouse, and the upper edge of the steel bars on the monitoring section is monitored in the same tunnel. A plurality of fiber grating monitoring instruments are installed in the circumferential direction, and a temporary protective wooden box that is easy to remove is fixed on the steel reinforcement at the bottom of the tunnel. ;
步骤二,监测仪器尾缆进入临时保护木箱后,将这些尾缆逐个串联起来,保护木箱开口处与线缆之间的空隙采用膨胀泡沫密封,避免混凝土砂浆进入;Step 2: After the monitoring instrument pigtail cable enters the temporary protective wooden box, connect these pigtail cables one by one, and seal the gap between the opening of the protective wooden box and the cable with expanded foam to prevent the entry of concrete mortar;
步骤三,将各光纤光栅监测仪器串接后与引到下仓混凝土的临时光缆连接,采用便携式光纤光栅解调仪测试是否能正常采集连接的全部监测仪器波长,如有波长重叠,则调整串接方式,直至正常测量;Step 3: Connect each fiber grating monitoring instrument in series with the temporary optical cable leading to the lower warehouse concrete, and use a portable fiber grating demodulator to test whether the wavelengths of all the connected monitoring instruments can be collected normally. If the wavelengths overlap, adjust the string. connection method until normal measurement;
步骤四,模板台车沿隧道轴向方向的轨道移入混凝土浇筑部位,在各项工作完后,模板台车展开,在其他异形部位用木模封闭后浇筑混凝土,在模板台车进入仓面后浇筑混凝土时,按要求的数据采集频次测量;Step 4: The formwork trolley is moved into the concrete pouring site along the track in the axial direction of the tunnel. After each work is completed, the formwork trolley is unfolded, and the other special-shaped parts are sealed with wooden molds and then poured into concrete. After the formwork trolley enters the warehouse surface When pouring concrete, measure according to the required data collection frequency;
步骤五,混凝土完成初凝后,移走模板台车,将预埋的保护木箱挖出,连接仪器的引出尾缆直接在监测断面的仰拱部位逐个采集数据;Step 5, after the concrete completes the initial setting, remove the formwork trolley, dig out the pre-embedded protective wooden box, and directly collect data one by one at the inverted arch part of the monitoring section, which is connected to the outgoing tail cable of the instrument;
步骤六,衬砌施工完成后,拆除临时保护木箱并将其取出,将光缆熔接保护盒安装在临时保护木箱在衬砌内留下的空间,将光纤光栅监测仪器串联或并联后熔接到主光缆,调试完成后最后全部用混凝土回填。Step 6: After the lining construction is completed, remove the temporary protective wooden box and take it out, install the optical cable splicing protection box in the space left by the temporary protective wooden box in the lining, connect the fiber grating monitoring instruments in series or in parallel and then spliced to the main optical cable. , and finally backfill with concrete after the commissioning is completed.
进一步的,同一个监测断面的同一组内的光纤光栅仪器的波长测值不重复。Further, the wavelength measurement values of the fiber grating instruments in the same group of the same monitoring section are not repeated.
进一步的,光纤光栅监测仪器设至少1个光栅,当设置2个及以上光栅时,每2个光栅间设缓冲区0.5nm。Further, the fiber grating monitoring instrument is provided with at least one grating, and when two or more gratings are provided, a buffer zone of 0.5 nm is set between every two gratings.
进一步的,所述步骤二中串联数量小于5个传感器或10个波长。Further, in the second step, the number of series connected sensors is less than 5 sensors or 10 wavelengths.
高水头长隧洞中安全监测仪器的埋设安装结构,包括若干隧洞监测断面埋设安装单元,所述隧洞监测断面埋设安装单元包括临时保护木箱以及若干埋设在同一隧洞监测断面圆周上的光纤光栅监测仪器,各光纤光栅监测仪器均连接有尾缆,各光纤光栅仪器彼此串联或并联,所述临时保护木箱为梯形,其顶部具有可打开的盖板,一侧具有隧洞中长渠侧面相适应的斜面,箱体上设置有开口,各光纤光栅监测仪器接出的线缆均通过所述开口引入至临时保护木箱内,所述线缆用于连接临时光缆或主传输光缆。The buried installation structure of safety monitoring instruments in long tunnels with high water head includes several buried installation units in tunnel monitoring sections, and the buried installation units in tunnel monitoring sections include temporary protection wooden boxes and several fiber grating monitoring instruments buried on the circumference of the same tunnel monitoring section , each fiber grating monitoring instrument is connected with a pigtail cable, and each fiber grating instrument is connected in series or in parallel with each other, the temporary protection wooden box is trapezoidal, the top has an openable cover, and one side has a long canal in the tunnel. The box is provided with an opening on the inclined plane, and the cables connected by each fiber grating monitoring instrument are introduced into the temporary protective wooden box through the opening, and the cables are used to connect the temporary optical cable or the main transmission optical cable.
进一步的,所述线缆外套设有保护管。Further, the cable jacket is provided with a protective tube.
进一步的,所述保护管为PE管。Further, the protection tube is a PE tube.
进一步的,所述临时保护木箱埋设在隧洞底部平台内,其顶面高度小于或等于平台顶面高度。Further, the temporary protection wooden box is embedded in the platform at the bottom of the tunnel, and the height of its top surface is less than or equal to the height of the top surface of the platform.
进一步的,所述开口设置在保护盒底面上。Further, the opening is provided on the bottom surface of the protection box.
进一步的,同一隧洞断面埋设安装单元内各光纤光栅监测仪器通过法兰串联用于进行施工期观测。Further, each fiber grating monitoring instrument in the buried installation unit of the same tunnel section is connected in series through the flange for observation during the construction period.
与现有技术相比,本发明具有如下优点和有益效果:Compared with the prior art, the present invention has the following advantages and beneficial effects:
1.有效保护监测仪器引出尾缆,提高仪器埋设完好率,同时可采集到衬砌浇筑后至模板台车移走这段时间内的监测数据,提高了监测资料的完整性,准确取得基准值,大大提高了其后数据监测的精确性。1. Effectively protect the tail cable of the monitoring instrument, improve the burial integrity rate of the instrument, and collect the monitoring data during the period after the lining is poured and the formwork trolley is removed, which improves the integrity of the monitoring data and accurately obtains the reference value. The accuracy of subsequent data monitoring is greatly improved.
2.同一个监测断面的光纤光栅仪器的波长测值尽量不重复,提高系统波分复用效率。2. The wavelength measurement value of the fiber grating instrument of the same monitoring section should not be repeated as much as possible, so as to improve the system wavelength division multiplexing efficiency.
附图说明Description of drawings
图1为本发明隧洞立体示意图。FIG. 1 is a three-dimensional schematic diagram of a tunnel according to the present invention.
图2为隧洞监测断面示意图。Figure 2 is a schematic diagram of the tunnel monitoring section.
图3为临时保护木箱结构示意图。Figure 3 is a schematic diagram of the structure of the temporary protection wooden box.
图4为模板台车展开状态下隧洞断面示意图。Figure 4 is a schematic cross-sectional view of the tunnel in the unfolded state of the formwork trolley.
图5为光纤光栅传感器串联波长分布示意图,图中:①:应变波长区;②:缓冲区;③:温度波长区;④:缓冲区。Figure 5 is a schematic diagram of the wavelength distribution of fiber grating sensors in series, in the figure: ①: strain wavelength region; ②: buffer zone; ③: temperature wavelength zone; ④: buffer zone.
附图标记列表:List of reference numbers:
1-隧洞,2-临时光缆,3-监测断面,4-临时保护木箱,401-开口,402-斜面,403-盖板,5-光纤光栅监测仪器,6-尾缆,7-模板台车,8-模板台车支撑,9-混凝土衬砌,10-便携式光纤光栅解调仪,11-长渠。1-tunnel, 2-temporary optical cable, 3-monitoring section, 4-temporary protection wooden box, 401-opening, 402-slope, 403-cover plate, 5-fiber grating monitoring instrument, 6-pigtail cable, 7-template table cart, 8-formwork trolley support, 9-concrete lining, 10-portable fiber grating demodulator, 11-long channel.
具体实施方式Detailed ways
以下将结合具体实施例对本发明提供的技术方案进行详细说明,应理解下述具体实施方式仅用于说明本发明而不用于限制本发明的范围。The technical solutions provided by the present invention will be described in detail below with reference to specific embodiments. It should be understood that the following specific embodiments are only used to illustrate the present invention and not to limit the scope of the present invention.
本发明提供的高水头长隧洞中安全监测仪器的埋设安装方法,包括如下步骤:The method for burying and installing a safety monitoring instrument in a long tunnel with high water head provided by the present invention includes the following steps:
步骤一,开挖清基完成后,开始绑扎钢筋用于浇筑隧洞1,在钢筋绑扎完成前在本仓内同步安装模板台车轨道,同时模板台车7在邻仓混凝土位置装配完成,在同一隧洞监测断面3钢筋上沿圆周方向捆扎多个光纤光栅监测仪器5,这些仪器接出的尾缆6外套设PE管(也可采用其他具有一定强度的材料替换PE)作为保护,PE管用塑料扎带绑扎而不用铅丝,避免混凝土振捣时铅丝割断保护管及仪器引出尾缆,确保尾缆不受损伤。隧洞监测断面3大部分为扇形,隧洞底部为平台,平台中部设置有贯通整个隧洞的长渠11,长渠内用于设置主传输光缆,长渠截面为上大下小的梯形。在隧洞底部钢筋上捆扎临时保护木箱4。临时保护木箱截面为梯形,顶部宽30cm,底部宽40cm,高度为25cm,长度为100cm。临时保护木箱顶部设置有可打开的盖板403,底部设置有开口401,开口尺寸为20×30cm。上述多个光纤光栅监测仪器5接出的尾缆6沿断面扇形钢筋绕行后牵引向断面底部(如图2所示),并自开口处引入临时保护木箱内。临时保护木箱为木制,在隧洞断面浇筑完成后容易拆除取出。固定后的临时保护木箱的顶面高度应等于或略小于隧洞底部将要成型的混凝土平台的顶面高度,方便挖出临时保护木箱。需要说明的是,本发明所指隧洞监测断面沿隧洞轴向具有一定长度,通常为1至2m。Step 1: After the excavation and clearing of the foundation are completed, start to bind the steel bars for pouring the tunnel 1. Before the binding of the steel bars is completed, the formwork trolley tracks are installed in this warehouse synchronously, and the formwork trolley 7 is assembled at the concrete position of the adjacent warehouse. On the tunnel monitoring section 3, a plurality of fiber grating monitoring instruments 5 are bundled along the circumferential direction on the steel bars. The tail cables 6 connected by these instruments are covered with PE pipes (other materials with certain strength can also be used to replace PE) as protection, and the PE pipes are bound with plastic. The belt is bound instead of lead wire, to avoid the lead wire from cutting off the protection tube and the pigtail cable of the instrument when the concrete is vibrated, so as to ensure that the pigtail cable is not damaged. The tunnel monitoring section 3 is mostly fan-shaped, the bottom of the tunnel is a platform, and a long canal 11 is arranged in the middle of the platform that runs through the entire tunnel. The long canal is used to set the main transmission optical cable. A temporary protective wooden box 4 is bundled on the reinforcement bars at the bottom of the tunnel. The cross-section of the temporary protection wooden box is trapezoidal, the top width is 30cm, the bottom width is 40cm, the height is 25cm, and the length is 100cm. The top of the temporary protection wooden box is provided with an openable cover plate 403, and the bottom is provided with an opening 401, and the size of the opening is 20×30 cm. The tail cables 6 connected by the above-mentioned multiple fiber grating monitoring instruments 5 are drawn along the section fan-shaped steel bars and then pulled to the bottom of the section (as shown in FIG. 2 ), and are introduced into the temporary protective wooden box from the opening. The temporary protective wooden box is made of wood, which can be easily removed and taken out after the tunnel section is poured. The height of the top surface of the fixed temporary protection wooden box should be equal to or slightly less than the top surface height of the concrete platform to be formed at the bottom of the tunnel, so as to facilitate the excavation of the temporary protection wooden box. It should be noted that the tunnel monitoring section referred to in the present invention has a certain length along the tunnel axis, usually 1 to 2 m.
串联的FBG传感器阵列包含多个传感光栅,解调仪通过反射光波长“寻址”每一个光栅,因此串联的光栅波长应该具有唯一性,即传感器的波长在整个量程内要避免重叠,订货时要求同一个监测断面中同一组内的光纤光栅仪器的波长测值不重复,提高系统波分复用效率。光纤光栅应变计或钢筋计内一般设2个光栅(应变、温度光栅各1个),应变、温度光栅在传感器量程范围内波长变化幅度在1~3nm间。当然,也可以根据需要仅设置一个或设置更多数量的光栅。为提高解调仪根据波长寻址的可靠性,在每2个光栅间建议设缓冲区0.5nm,避免相邻的光栅在传感器量程范围内变化时波长重叠,波长分布一般如图5所示。The series-connected FBG sensor array contains multiple sensing gratings, and the demodulator "addresses" each grating by the wavelength of the reflected light. Therefore, the wavelengths of the series-connected gratings should be unique, that is, the wavelengths of the sensors should avoid overlapping in the entire range. At the same time, it is required that the wavelength measurement values of the fiber grating instruments in the same group in the same monitoring section are not repeated, and the efficiency of the system wavelength division multiplexing is improved. There are generally two gratings (one for strain and one for temperature grating) in the fiber grating strain gauge or steel bar gauge, and the wavelength of the strain and temperature grating within the range of the sensor is between 1 and 3 nm. Of course, only one grating or a larger number of gratings can be set as required. To improve the reliability of the demodulator based on wavelength addressing, it is recommended to set a buffer zone of 0.5 nm between every two gratings to avoid overlapping wavelengths when adjacent gratings change within the sensor range. The wavelength distribution is generally shown in Figure 5.
步骤二,监测仪器尾缆进入临时保护木箱后,打开盖板403,这些监测仪器应分成若干组,同一组中监测仪器的尾缆逐个用法兰进行串联从而串联各个监测仪器,一般串联数量小于5个传感器或10个波长,同一组内的光纤光栅仪器的波长测值不重复。各组串联后的监测仪器尾缆自木箱缝隙或木箱开孔引出木箱外,盖上盖板并进行固定,临时保护木箱箱体缝隙及其开口、开孔与尾缆之间的空隙均采用膨胀泡沫密封,避免混凝土砂浆进入。Step 2: After the monitoring instrument tail cable enters the temporary protective wooden box, open the cover 403. These monitoring instruments should be divided into several groups. The tail cables of the monitoring instruments in the same group are connected in series with flanges one by one to connect each monitoring instrument in series. Generally, the number of series connections is less than For 5 sensors or 10 wavelengths, the wavelength measurements of the fiber grating instruments in the same group are not repeated. The tail cables of the monitoring instruments connected in series in each group are led out of the wooden box from the gaps of the wooden box or the openings of the wooden box, and the cover is covered and fixed to temporarily protect the gaps and openings of the wooden box, the openings and the tail cables. The voids are sealed with expanding foam to avoid the entry of concrete mortar.
步骤三,将各光纤光栅监测仪器分组串接后的尾缆接上临时光缆2,将临时光缆引到本仓混凝土之外,临时光缆与便携式光纤光栅解调仪10连接,如图1所示,这样在混凝土衬砌施工时可以正常进行数据采集。采用便携式光纤光栅解调仪能够测试是否能正常采集连接的全部监测仪器波长,如有波长重叠,则调整串接方式,直至正常测量。Step 3: Connect the temporary optical cable 2 to the tail cable after the grouping and concatenation of the fiber grating monitoring instruments, lead the temporary optical cable out of the concrete of the warehouse, and connect the temporary optical cable to the portable fiber grating demodulator 10, as shown in Figure 1. , so that data collection can be carried out normally during the construction of concrete lining. Using a portable fiber grating demodulator can test whether the wavelengths of all connected monitoring instruments can be collected normally. If the wavelengths overlap, adjust the serial connection mode until the normal measurement.
经过上述步骤之后,高水头长隧洞中安全监测仪器的埋设安装结构已安装完成。如图1、图2所示,该结构包括若干隧洞监测断面埋设安装单元,每个断面埋设安装单元包括临时保护木箱4以及多个埋设在同一隧洞监测断面圆周上的光纤光栅监测仪器5,各光纤光栅监测仪器5均连接有线缆,各光纤光栅监测仪器5彼此串联或并联。如图3所示,临时保护木箱4为梯形,顶部设置有可打开的盖板403,其一侧具有隧洞中长渠侧面11相适应的斜面402,箱体上设置有开口401(开口以设置在底部为佳,但根据需要也可改变开口设置的具体位置),各光纤光栅监测仪器接出的线缆均通过该开口引入至临时保护木箱内,各光纤光栅监测仪器接出的线缆用于连接临时光缆或主传输光缆。After the above steps, the buried installation structure of the safety monitoring instrument in the long tunnel with high water head has been installed. As shown in Figures 1 and 2, the structure includes a number of tunnel monitoring section buried installation units, each section buried installation unit includes a temporary protection wooden box 4 and a plurality of fiber grating monitoring instruments 5 buried on the circumference of the same tunnel monitoring section, Each fiber grating monitoring instrument 5 is connected with a cable, and each fiber grating monitoring instrument 5 is connected in series or in parallel with each other. As shown in FIG. 3 , the temporary protection wooden box 4 is trapezoidal, with an openable cover plate 403 on the top, one side of which has a slope 402 adapted to the side surface 11 of the long canal in the tunnel, and an opening 401 (the opening is It is better to set it at the bottom, but the specific position of the opening can also be changed as needed), the cables connected by each fiber grating monitoring instrument are introduced into the temporary protective wooden box through this opening, and the cables connected by each fiber grating monitoring instrument The cable is used to connect the temporary fiber optic cable or the main transmission fiber optic cable.
步骤四,模板台车沿隧道轴向方向的轨道移入混凝土浇筑部位,在各项工作完后,模板台车展开,如图4所示形成一个完整的扇形。在其他异形部位用木模封闭后浇筑混凝土。在模板台车进入仓面后浇筑混凝土时,应按要求的数据采集频次利用光纤光栅解调仪进行测量。浇筑完成后,断面埋设安装单元中的临时保护木箱以及光纤光栅监测仪器都被埋入混凝土中。Step 4: The formwork trolley is moved into the concrete pouring site along the track in the axial direction of the tunnel. After each work is completed, the formwork trolley is unfolded to form a complete fan shape as shown in Figure 4. Concrete is poured after other special-shaped parts are closed with wooden formwork. When pouring concrete after the formwork trolley enters the warehouse surface, the fiber grating demodulator should be used for measurement according to the required data collection frequency. After the pouring is completed, the temporary protective wooden box in the section buried installation unit and the fiber grating monitoring instrument are buried in the concrete.
上述浇筑混凝土的步骤如下:The above steps of pouring concrete are as follows:
采用钢管泵送方式,从模板台车的活动窗口将混凝土送入。混凝土采用水平分层、对称泵送入仓浇筑。混凝土模板台车振捣采用附着式振捣器振捣,进料窗周边插入式振捣器振捣辅助。混凝土泵送软管从模板台车的进料窗口(从最底一级窗口逐渐上移)处注入混凝土。仓内薄层平铺,两侧边墙对称下料,单侧一次连续浇筑高度不超过1m,防止模板整体变形,认真平仓,防止骨料分离,确保连续浇筑,避免出现冷缝。Concrete is delivered from the movable window of the formwork trolley by means of steel pipe pumping. Concrete is poured into the silo by horizontal layering and symmetrical pumping. The concrete formwork trolley is vibrated by an attached vibrator, which is assisted by an inserted vibrator around the feed window. The concrete pumping hose injects concrete from the feeding window of the formwork trolley (moving up gradually from the bottom window). The thin layer in the warehouse is laid flat, the side walls on both sides are symmetrically cut, and the height of one continuous pouring on one side is not more than 1m to prevent the overall deformation of the formwork.
作为优选,混凝土振捣采用人工振捣棒和平板振捣器相结合的振捣方式,底部第2层窗口以下采用人工振捣,以上部位采用均匀布置的8个平板振捣器振捣。这样混凝土浇筑更为均匀。Preferably, the concrete vibrator adopts a combination of artificial vibrators and plate vibrators. Manual vibrators are used below the second floor window at the bottom, and 8 evenly arranged plate vibrators are used for vibrating the above parts. This way the concrete is poured more evenly.
步骤五,一般在混凝土浇筑后2-3天,混凝土完成初凝,模板台车移走,将预埋的保护木箱挖出,露出仪器的引出尾缆就可直接在监测断面的仰拱部位逐个采集数据。Step 5, generally 2-3 days after the concrete is poured, the initial setting of the concrete is completed, the formwork trolley is removed, the pre-embedded protective wooden box is dug out, and the tail cable of the instrument is exposed, which can be directly in the inverted arch of the monitoring section. Collect data one by one.
步骤六,混凝土衬砌9施工完成后,光纤光栅监测仪器需要串联或并联后熔接到主光缆,此时可以拆除临时保护木箱并将其取出,将光缆熔接保护盒安装在临时保护木箱在衬砌内留下的空间,原有临时保护木箱内的线缆置入光缆熔接保护盒内,并根据需要对各线缆进行串联或并联,调试完成后最后全部用混凝土回填。Step 6. After the construction of the concrete lining 9 is completed, the fiber grating monitoring instrument needs to be spliced to the main optical cable in series or in parallel. At this time, the temporary protection wooden box can be removed and taken out, and the optical cable fusion protection box can be installed in the temporary protection wooden box. In the space left in the original temporary protection wooden box, the cables in the original temporary protection wooden box are placed in the optical cable fusion protection box, and the cables are connected in series or parallel according to the needs. After the debugging is completed, all the cables are backfilled with concrete.
本发明方案所公开的技术手段不仅限于上述实施方式所公开的技术手段,还包括由以上技术特征任意组合所组成的技术方案。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也视为本发明的保护范围。The technical means disclosed in the solution of the present invention are not limited to the technical means disclosed in the above embodiments, but also include technical solutions composed of any combination of the above technical features. It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, several improvements and modifications can be made, and these improvements and modifications are also regarded as the protection scope of the present invention.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611146690.7A CN107083993B (en) | 2016-12-13 | 2016-12-13 | The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611146690.7A CN107083993B (en) | 2016-12-13 | 2016-12-13 | The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107083993A CN107083993A (en) | 2017-08-22 |
CN107083993B true CN107083993B (en) | 2019-06-28 |
Family
ID=59614040
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611146690.7A Active CN107083993B (en) | 2016-12-13 | 2016-12-13 | The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107083993B (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107460861B (en) * | 2017-08-29 | 2023-03-31 | 云南农业大学 | Tubular monitoring instrument repair equipment |
CN107421671A (en) * | 2017-09-08 | 2017-12-01 | 浙江省水利水电勘测设计院 | A kind of pressure gauge placing device for gentle slope inclined shaft |
CN111024778A (en) * | 2018-10-10 | 2020-04-17 | 中铁一局集团有限公司 | Tunnel secondary lining preventive cavity detection system and operation control method thereof |
CN109269568A (en) * | 2018-10-29 | 2019-01-25 | 上海英斯泊物联网有限公司 | A kind of structural healthy monitoring system and its application method |
CN110485388B (en) * | 2019-05-30 | 2021-06-25 | 水利部南京水利水文自动化研究所 | Hydraulic tunnel dynamic water pressure monitoring structure and method based on flow velocity water head correction |
CN110595377A (en) * | 2019-09-25 | 2019-12-20 | 武汉理工大学 | A spatial three-dimensional system for long-term monitoring of underground cavern lining deformation |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5952094A (en) * | 1982-09-14 | 1984-03-26 | 株式会社竹中工務店 | Method of measuring and controlling upper section of spray concrete covering work and excavating forward ground propertyin tunnel construction by method of natomu construction |
CN2890345Y (en) * | 2006-01-25 | 2007-04-18 | 吴江 | Pre-warning device capable of real-time monitoring |
CN201202496Y (en) * | 2008-06-05 | 2009-03-04 | 中铁西南科学研究院有限公司 | On-line monitoring early warning apparatus of tunnel water burst mud projecting burst geologic hazard |
CN104965477A (en) * | 2015-01-29 | 2015-10-07 | 中铁建大桥工程局集团第一工程有限公司 | Tunnel automatic monitoring system and method |
CN204436476U (en) * | 2015-02-16 | 2015-07-01 | 大连海事大学 | Automatic monitoring device for tunnel collapse based on lining strain |
CN206338092U (en) * | 2016-12-13 | 2017-07-18 | 水利部南京水利水文自动化研究所 | The Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head |
-
2016
- 2016-12-13 CN CN201611146690.7A patent/CN107083993B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN107083993A (en) | 2017-08-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107083993B (en) | The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head | |
CN108825304B (en) | A shield tunnel formation stability and long-term health monitoring system of tunnel structure | |
CN101713691B (en) | Health-monitoring system of distributed sensing fiber tunnel | |
CN111636898A (en) | Force testing device for shield segments during construction of connecting passages of shield tunnels | |
CN105780752B (en) | A kind of foundation pit enclosure structure horizontal displacement distributed optical fiber sensing method | |
CN107131862B (en) | Rock-fill dam panel deformation monitoring device and construction method | |
CN100389300C (en) | Monitoring method and device for faceplate deflection of large dam or internal deformation of dam body | |
CN104374433A (en) | Tunnel structure monitoring system and tunnel structure monitoring method based on distributed long-gauge fiber bragg grating | |
CN103604384A (en) | Distributed fiber monitoring method and system for strains and stresses of ship lock structure | |
CN112857988A (en) | Asymmetric load loading test system and test method for full-scale test of pipe piece | |
CN105547364A (en) | Splicing-type distributed optical fiber sensing system used for monitoring in internal portion of roadbed | |
CN110987039A (en) | A method for testing the failure depth of coal seam roof and floor after mining in working face | |
CN105910545A (en) | Optical fiber sensing technology and system for monitoring deformation of high earth-rock dam | |
CN101900533A (en) | Fiber Bragg grating measurement method for subsidence monitoring of embankment section | |
De Battista et al. | Strain monitoring using embedded distributed fibre optic sensors in a sprayed concrete tunnel lining during the excavation of cross-passages | |
CN116289969A (en) | Anti-leakage construction method of occlusal piles for deep foundation pit enclosure structure based on sonar detection technology | |
CN204286495U (en) | Based on the tunnel structure monitoring system of distributed long gauge length optical fibre grating | |
CN116677453A (en) | Round TBM tunnel surrounding rock stability monitoring method and system | |
CN206772242U (en) | A kind of tunnel wall rock deformation distributed optical fiber sensing device based on pipe shed support | |
CN113776450B (en) | Ground deformation monitoring system and monitoring method based on optical fiber technology | |
CN206338092U (en) | The Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head | |
CN115201456A (en) | Indoor experimental device and experimental method for operating subway micro-disturbance grouting technology | |
CN107326942A (en) | PHC tube pile structure loading detection devices and installation method | |
CN206529812U (en) | A kind of direct burial test system | |
JP6396710B2 (en) | Filling status detector |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |