- Publication number
- CN1068187A CN1068187A CN 91104541 CN91104541A CN1068187A CN 1068187 A CN1068187 A CN 1068187A CN 91104541 CN91104541 CN 91104541 CN 91104541 A CN91104541 A CN 91104541A CN 1068187 A CN1068187 A CN 1068187A
- Authority
- CN
- China
- Prior art keywords
- stemming
- coating
- explosion
- coat
- blasting efficiency
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Soil Conditioners And Soil-Stabilizing Materials (AREA)
- Curing Cements, Concrete, And Artificial Stone (AREA)
Abstract
The method that the present invention relates to be used for the coating stemming of plugged perforation in the blasting engineering and improve blasting efficiency.The present invention adopts the fast hard material of rapid hardening to pack into and coats in the bag, and mechanization is produced series of products and used for explosion, and its intensity height can reach the 80-200 kilograms per centimeter 4-10 minute stemming intensity
2The plugged perforation packing is good, can make full use of explosive energy, simultaneously work out the explosion chart automatically and combine, make blast hole utilization factor reach 95-100%, if be example to tunnel 13 square metres tunnel with the HXTBT-IBM program, each myriametre tunnel compared with prior art, can save ten thousand yuan of engineering cost 50-60, if promote the use of in the whole nation, economic benefit is very considerable.
Description
The invention belongs to the blasting engineering field, be specially adapted to tunnel and tunnelling.
Prior art in this technical field generally adopts yellow mud or water stemming material as the plugged perforation material, and this material belongs to inert material, and its obstruction intensity is low or filling speed is slow, influences construction speed and efficient.In addition, the parameter that influences explosion is more, determine that for these years blasting parameter is mainly by experience, be the formula that has some to calculate blasting parameter, but all more scattered complexity is difficult to promote the use of, the blast hole utilization factor of blasting engineering is generally all about 85% at present, thereby waste explosive and detonator have increased construction costs, can not realize building the mine with getting twice the result with half the effort.
The objective of the invention is to improve the mud material and the structure of plugged perforation, and utilize program to work out the explosion chart automatically, to realize comprehensive guiding construction.
Technical scheme of the present invention is achieved like this: loose, have water-swellable material scleroma or rapid solidification and pack into and coat the coating stemming of making cylindrical or multi-edge column-shaped in the bag, utilize this coating stemming and in conjunction with the HXTBT-IBM computer program to the roadway blasting parameter automatically the explosion chart of establishment carry out explosion, it coats, and mud material comprises that yellow mud, resin, cement, sand, gypsum, calcium oxide, three second ammoniums, cyanogen coagulate, aluminium powder, T31 coagulating agent, accelerator; When make coating stemming, available homogenous material make mix with two kinds of materials at least or more than three kinds material be composited; Its mud material by weight, filler is 20-50%, cementing material is 25-50%, additive is 25-30%; The clad material that is used for the mud material external packing is plastic products, polyvinyl alcohol paper, bafta, a kind of sealing bag that all can be made in the chemical ﹠ blended fabric.Its method that improves blasting efficiency is to combine with the explosion chart of the automatic establishment that comprises a computer program with coating the stemming plugged perforation, lack one and all can not reach higher blasting efficiency, computer program is according to by the section size of explosion, section configuration, formation hardness, explosive kind, borehole depth waits and calculates each parameter of explosion, automatically work out the explosion chart according to the blasting parameter that calculates, the reliever proximate coefficients in its explosion chart is 1.15-2.65.
Blast hole utilization factor is generally about 85% in the prior art, explosive consumption is at 2.0-4.5 kilogram/cubic meter, detonator consumes at 5.0-7.3/cubic meter, and the main cause that causes explosive, detonator consumption to surpass national standard is that the of poor quality and explosion Graphic Design of the obstruction of borehole is not optimized.Show according to test, the explosion chart that adopts coating stemming of the present invention and work out automatically with the HXTBT-IBM program, blast hole utilization factor is all at 95-100% or about to 110%, its explosive consumption reduces about 30%, and 10-15% is saved in detonator consumption, is example with regard to one 13 square meters of horizontal tunnel, 100 meters long tunnels of every driving, can many drilling depths 10-15 rice, save about 1 ton in explosive, more than 1400 in detonator.If deduction stemming cost, per 100 meters tunnel saving investments are more than 5000 yuan, as if a mineral bureau annual advance ten thousand metres tunnel, ten thousand yuan of year saving investment 50-60 will be very considerable if popularize its economic benefit of use in an all-round way in national mining industry.
For realizing task of the present invention, existing the invention will be further described in conjunction with the embodiments:
Have water-swellable material scleroma or rapid solidification and fully mix or compound branch bag the sealing of φ 10-45mm that polyvinyl alcohol paper or other clad materials make and long 100-1000mm of packing into through mechanical agitation loose in the embodiment ratio, during on-the-spot the use, to coat stemming immerses in the clear water, fill in the borehole with wooden stick coating stemming again after waiting to coat stemming and being soaked into, coat stemming through hydration reaction and setting expansion this moment, the stemming intensity that stemming and borehole wall form one generation 80-200 kg/cm blocks borehole, gases at high pressure behind the explosive charge are difficult for leaking from the heel of a shot, the explosive charge energy can be fully used, thereby has improved the utilization rate of borehole.According to task of the present invention, its specific embodiment is as follows:
Embodiment 1: formation hardness Protodyakonov coefficient f=5-10(sandstone)
Special cement 80-90%
Sand 5-13%
Aluminium powder 5-7%
Embodiment 2: formation hardness Protodyakonov coefficient f=8-12(calcareous sandstone and other hard rocks)
Resin 60-80%
T31 coagulating agent 20-40%
Embodiment 3: formation hardness Protodyakonov coefficient f=6-7(limestone)
Cyanogen coagulates 65-80%
Three second ammonium 20-35%
Embodiment 4: formation hardness Protodyakonov coefficient f=4-6(argillaceous sandstone)
Ordinary cement 50-70%
Calcium oxide 5-10%
Gypsum 20-35%
Aluminium powder 1-2%
Accelerator 2-3%
Claims (6)
1, a kind of method that is used for the coating stemming of plugged perforation and improves blasting efficiency, it is characterized in that loose, have water-swellable material scleroma or rapid solidification and pack into and coat in the bag, make the coating stemming of cylindrical or multi-edge column-shaped, utilize this coating stemming and carry out explosion in conjunction with the explosion chart of working out automatically with the blasting parameter of HXTBT-IBM programming.
2, coating stemming according to claim 1 and improve the method for blasting efficiency is characterized in that coating that material in the stemming comprises that resin, cement, sand, gypsum, calcium oxide, three second ammoniums, cyanogen coagulate, aluminium powder, T31 coagulating agent and accelerator.
3, coating mud material according to claim 2, it is characterized in that coating stemming can make or two kinds of materials mix and make or material is compound more than three kinds makes with homogenous material at least, its mud material by weight, filler is 20-50%, cementing material is 25-50%, and additive is 25-30%.
4, coating stemming according to claim 1 and 2 and improve the method for blasting efficiency, the coating bag material that it is characterized in that coating stemming is plastic products, polyvinyl alcohol paper, bafta, chemical ﹠ blended fabric.
5, according to claim 1 or 2 or 3 or 4 described coating stemmings with improve the method for blasting efficiency, it is characterized in that comprising the HXTBT-IBM computer program automatic establishment the explosion chart with coat stemming and interdepend.
6, coat the method for stemming and raising blasting efficiency according to claim 1 or 5, it is characterized in that the reliever proximate coefficients in the explosion chart is 1.15-2.65.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN91104541A CN1039602C (en) | 1991-07-03 | 1991-07-03 | Method for wrapping booster charge and increasing explosive efficiency |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN91104541A CN1039602C (en) | 1991-07-03 | 1991-07-03 | Method for wrapping booster charge and increasing explosive efficiency |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1068187A true CN1068187A (en) | 1993-01-20 |
CN1039602C CN1039602C (en) | 1998-08-26 |
Family
ID=4906684
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN91104541A Expired - Fee Related CN1039602C (en) | 1991-07-03 | 1991-07-03 | Method for wrapping booster charge and increasing explosive efficiency |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN1039602C (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102786269A (en) * | 2012-08-24 | 2012-11-21 | 山东矿业管理技术服务集团有限公司 | Preparation method of sandy stemming |
CN104692727A (en) * | 2015-02-13 | 2015-06-10 | 中国长江三峡集团公司 | Blast-hole plugging jelling material with characteristics of rapid solidification, early strength and micro-expansion |
CN106167370A (en) * | 2016-03-11 | 2016-11-30 | 任旭明 | A kind of colliery expands breakage-proof yellow mud stemming manufacture method |
CN106478014A (en) * | 2016-09-28 | 2017-03-08 | 贵州大学 | Special stemming and preparation method are removed in a kind of structure demolition |
CN107314724A (en) * | 2017-08-11 | 2017-11-03 | 中铁隧道集团有限公司 | A kind of loading method for being used to improve periphery weak surrounding rock explosion stability |
CN107014264B (en) * | 2017-04-28 | 2018-05-29 | 东北大学 | It is a kind of for drilling tamponade device of drillhole blasting and preparation method thereof |
CN110260740A (en) * | 2019-06-12 | 2019-09-20 | 黑龙江科技大学 | A kind of mining borehole high-efficient homogeneous aggregate cladding sealing material |
CN110926292A (en) * | 2019-12-16 | 2020-03-27 | 安徽理工大学 | A leak-proof water-sand-sealing bag for coal mine blasting and using method thereof |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN85200084U (en) * | 1985-04-01 | 1985-11-10 | 李起山 | Water seal and water pressure water case for shot hole blasting |
-
1991
- 1991-07-03 CN CN91104541A patent/CN1039602C/en not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102786269A (en) * | 2012-08-24 | 2012-11-21 | 山东矿业管理技术服务集团有限公司 | Preparation method of sandy stemming |
CN104692727A (en) * | 2015-02-13 | 2015-06-10 | 中国长江三峡集团公司 | Blast-hole plugging jelling material with characteristics of rapid solidification, early strength and micro-expansion |
CN106167370A (en) * | 2016-03-11 | 2016-11-30 | 任旭明 | A kind of colliery expands breakage-proof yellow mud stemming manufacture method |
CN106478014A (en) * | 2016-09-28 | 2017-03-08 | 贵州大学 | Special stemming and preparation method are removed in a kind of structure demolition |
CN107014264B (en) * | 2017-04-28 | 2018-05-29 | 东北大学 | It is a kind of for drilling tamponade device of drillhole blasting and preparation method thereof |
CN107314724A (en) * | 2017-08-11 | 2017-11-03 | 中铁隧道集团有限公司 | A kind of loading method for being used to improve periphery weak surrounding rock explosion stability |
CN107314724B (en) * | 2017-08-11 | 2018-11-23 | 中铁隧道集团有限公司 | It is a kind of for improving the loading method of periphery weak surrounding rock explosion stability |
CN110260740A (en) * | 2019-06-12 | 2019-09-20 | 黑龙江科技大学 | A kind of mining borehole high-efficient homogeneous aggregate cladding sealing material |
CN110926292A (en) * | 2019-12-16 | 2020-03-27 | 安徽理工大学 | A leak-proof water-sand-sealing bag for coal mine blasting and using method thereof |
CN110926292B (en) * | 2019-12-16 | 2021-09-10 | 淮南矿业(集团)有限责任公司 | Water-leakage-proof sand hole sealing bag for coal mine blasting and using method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN1039602C (en) | 1998-08-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA1200566A (en) | Reactivatable set-inhibited cementitious compositions | |
CN104481560B (en) | Back water-bearing layer administering method | |
CN103525383B (en) | Film-forming drilling fluid suitable for coal-bed gas well and preparation method thereof | |
CN103291325B (en) | The preventing control method of Coal-mining Above Confined-water floor strata gushing water | |
CN107035405B (en) | One kind cutting top pressure relief method for the double filling wall constructions of gob side entry retaining | |
CN112593853B (en) | Construction method for coal mine waste filling and water-reducing mining | |
CN103626435B (en) | A kind of coal and rock inorganic filler enclosed material | |
CN102603220B (en) | Preparation of polymer composite gelling agent for grouting and application method thereof | |
CN110540395A (en) | Spraying material for coal mine underground roadway and preparation method | |
CN102757206A (en) | Mine fracture grouting material and usage method thereof | |
CN109026011B (en) | waterproof curtain control grouting process for dolomite vertical shaft with huge-thickness rich water lamp shadow group | |
CN105523729A (en) | Efficient fast-setting bentonite-compounded waterproof plugging agent | |
CN103821538A (en) | Ground preliminary grouting method for J-shaped horizontal wing-shaped branch holes | |
CN1068187A (en) | Coat the method for stemming and raising blasting efficiency | |
CN109057798A (en) | A kind of wall type filling mining method suitable for gently inclined phosphate body bed | |
CN103319123B (en) | Fly ash-based cemented filling material and preparation method thereof | |
CN113622993B (en) | Mineralization ecological protective coal mining method utilizing CO2 waste gas | |
CN102432266A (en) | Manufacturing method and application of baking-free coal gangue concrete | |
CN105776911A (en) | Gel material for ultra-fine tailing filling and dry heaping | |
CN103880365A (en) | Specific gravity composite material slurry for filling and consolidating annular space of kilometer-deep freezing pipe | |
CN103333667A (en) | Formula and preparation method of low-pressure-coefficient gas reservoir protection drilling fluid | |
CN105731948A (en) | Cementing agent for micro-fine-particle tailing cementing filling | |
WO1986001795A1 (en) | Foamed cement compositions for stowing cavities | |
CN103396066B (en) | A kind of fast gravity die compaction material and its preparation method and application | |
CN108191365A (en) | A kind of method using ardealite material cementing fill metal mine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |