CN106759463A - A kind of hypogee and its construction method - Google Patents
A kind of hypogee and its construction method Download PDFInfo
- Publication number
- CN106759463A CN106759463A CN201710037690.1A CN201710037690A CN106759463A CN 106759463 A CN106759463 A CN 106759463A CN 201710037690 A CN201710037690 A CN 201710037690A CN 106759463 A CN106759463 A CN 106759463A
- Authority
- CN
- China
- Prior art keywords
- wall
- chain
- construction
- tunnel
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 86
- 239000002689 soil Substances 0.000 claims abstract description 65
- 239000011435 rock Substances 0.000 claims abstract description 63
- 238000009412 basement excavation Methods 0.000 claims abstract description 32
- 238000009415 formwork Methods 0.000 claims abstract description 27
- 230000005540 biological transmission Effects 0.000 claims abstract description 18
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 46
- 238000000034 method Methods 0.000 claims description 17
- 230000002787 reinforcement Effects 0.000 claims description 9
- 230000032258 transport Effects 0.000 claims description 8
- 229910000831 Steel Inorganic materials 0.000 claims description 6
- 239000010959 steel Substances 0.000 claims description 6
- 230000011218 segmentation Effects 0.000 claims description 5
- 238000009417 prefabrication Methods 0.000 claims description 4
- 238000011065 in-situ storage Methods 0.000 claims description 2
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 230000007547 defect Effects 0.000 abstract description 3
- 238000005516 engineering process Methods 0.000 abstract description 2
- 239000000203 mixture Substances 0.000 abstract description 2
- 230000002093 peripheral effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 33
- 238000010516 chain-walking reaction Methods 0.000 description 4
- 238000004140 cleaning Methods 0.000 description 2
- 239000011440 grout Substances 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F5/00—Dredgers or soil-shifting machines for special purposes
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
本发明提出的是一种地下建筑及其施工法,其周边承重墙1的底部设有轨道,施工时,轨道上安装有挖掘岩土的链刀,链刀由链条和固定于链条上的刀具组成,链刀和传动装置组成了链式挖掘装置,传动装置位于地面以上由链轮和驱动装置等组成,驱动装置驱动链刀,链刀沿着轨道运行,墙1底部的刀具挖掘岩土,由底部向上运行的链刀将已挖掘的岩土带至上方,墙1底部的链刀和墙1一起下降。优点:克服了现有技术存在的缺陷,可以在工厂分块预制,也可以在现场的固定模板中边浇筑边下降,施工简单;利用墙和顶盖构成挡水围堰,在干地环境中清除建筑物内部的岩土,浇筑楼板或者底板;另外墙自身结构的施工周期短,成本低。
What the present invention proposes is a kind of underground building and its construction method, and the bottom of its peripheral load-bearing wall 1 is provided with track, and during construction, the chain cutter for excavating rock and soil is installed on the track, and the chain cutter consists of a chain and a cutter fixed on the chain Composition, the chain cutter and the transmission device constitute the chain excavation device, the transmission device is located above the ground and consists of a sprocket and a driving device, etc., the driving device drives the chain cutter, and the chain cutter runs along the track, and the cutter at the bottom of the wall 1 excavates rock and soil, The chain cutter running upwards from the bottom brings the excavated rock and soil to the top, and the chain cutter at the bottom of the wall 1 and the wall 1 descend together. Advantages: It overcomes the defects of the existing technology. It can be prefabricated in blocks in the factory, or it can be poured and lowered in the fixed formwork on site. The construction is simple; the wall and the roof are used to form a water-retaining cofferdam. The rock and soil inside the building are removed, and the floor or bottom slab is poured; in addition, the construction period of the wall itself is short and the cost is low.
Description
技术领域technical field
本发明涉及的是一种地下建筑及其施工法,属于土木工程基础施工技术领域。The invention relates to an underground building and its construction method, belonging to the technical field of civil engineering foundation construction.
背景技术Background technique
现有地下建筑建设一般采用整体开挖施工的方式,基坑支护一般采用放坡、坡体加固、排桩和地下连续墙技术。采用放坡、坡体加固的施工方式存在有开挖的面积大、对周边环境要求高、基坑降排水难度大的问题;采用排桩支护基坑开挖需预制排桩,对底部土壤要求较高,支护工程量庞大,安全系数低;采用地下连续墙护壁后开挖,其槽内水下施工质量难以控制和检测、施工周期长、槽段之间的接口施工困难且易渗水。Existing underground building construction generally adopts the method of integral excavation, and foundation pit support generally adopts slope setting, slope reinforcement, pile row and underground diaphragm wall technology. The construction method of slope grading and slope reinforcement has the problems of large excavation area, high requirements on the surrounding environment, and difficulty in drainage of the foundation pit; the excavation of the foundation pit using row pile support requires prefabricated row piles, which will affect the bottom soil The requirements are high, the amount of supporting work is huge, and the safety factor is low; the excavation after the underground diaphragm wall is used, the underwater construction quality in the tank is difficult to control and detect, the construction period is long, and the interface between the tank sections is difficult to construct and easy to seepage .
发明内容Contents of the invention
本发明提出的是一种地下建筑及其施工法,其目的旨在克服现有技术存在的缺陷。其主要优点:利用墙和顶盖构成挡水围堰,排水后形成干地施工环境,然后在干地环境中清除建筑物内部的岩土,浇筑楼板或者底板;另外墙自身结构的施工周期短,成本低,施工简单。What the present invention proposes is an underground building and its construction method, and its purpose aims at overcoming the defect existing in the prior art. Its main advantages: use the wall and roof to form a water retaining cofferdam, and form a dry construction environment after drainage, and then remove the rock and soil inside the building in the dry environment, and pour the floor or bottom slab; in addition, the construction period of the wall itself is short , low cost and simple construction.
本发明的技术解决方案 : 地下建筑周边承重墙1的底部设有轨道,施工时,轨道上安装有挖掘岩土的链刀,链刀由链条和固定于链条上的刀具组成,链刀和传动装置组成了链式挖掘装置,传动装置位于地面以上由链轮和驱动装置等组成,驱动装置驱动链刀,链刀沿着轨道运行,墙1底部的刀具挖掘岩土,由底部向上运行的链刀将已挖掘的岩土带至上方,墙1底部的链刀和墙1一起下降。Technical solution of the present invention: The bottom of the load-bearing wall 1 around the underground building is equipped with a track. During construction, a chain cutter for excavating rock and soil is installed on the track. The chain cutter is composed of a chain and a cutter fixed on the chain. The chain cutter and transmission The device constitutes a chain excavation device. The transmission device is located above the ground and consists of a sprocket and a driving device. The driving device drives the chain cutter, and the chain cutter runs along the track. The cutter at the bottom of the wall 1 digs rock and soil, and the chain running from the bottom upward The knife brings the excavated rock and soil to the top, and the chain knife at the bottom of the wall 1 and the wall 1 descend together.
预制法,分如下步骤:The prefabrication method is divided into the following steps:
1)在工场分块或整体预制墙1;1) Block or integral prefabricated wall 1 in the workshop;
2)运至现场拼装墙1并蹲位,并在其底部的轨道上安装链刀; 2) Transport to the on-site assembled wall 1 and squat down, and install the chain knife on the track at the bottom;
3)安装链条驱动等装置,连接安装有挖掘刀的链条; 3) Install chain drives and other devices, and connect the chains with excavating knives;
4)驱动链条,链刀挖掘底部的岩土,经岩土输送装置送至上方,墙1随之下降; 4) Drive the chain, and the chain knife excavates the rock and soil at the bottom, and sends it to the top through the rock and soil conveying device, and the wall 1 descends accordingly;
5)墙1下降至设计深度拆除链刀后灌浆。 5) Wall 1 is lowered to the design depth and grouted after the chain knife is removed.
墙1除预制底部外,均在现场的固定模板中浇筑,施工时固定模板不动,随着底部岩土的挖掘,墙1边浇筑边下沉;链式挖掘装置由底部的轨道、中间机架和上部装置组成,底部轨道与墙1的底部固连成一体;中间机架的底部与墙1的预制底部相连,中间机架的顶部与上部装置相连,中间机架内安装有链条运行的轨道,中间机架同时也是墙1钢筋笼的组成部分;由底部向上运行的链条和中间机架的封闭腔组成了链式岩土垂直输送机,随着墙1底部的下沉,中间机架也同步下沉;上部装置固定于作业平台上或固定于中间机架的顶部,上部装置安装有链条驱动装置和张紧装置,底部轨道的链条通过中间机架与上部装置内驱动装置、张紧装置相连;具体施工分如下步骤:Except for the prefabricated bottom, wall 1 is poured in the fixed formwork on site. The fixed formwork does not move during construction. With the excavation of the bottom rock and soil, wall 1 sinks while being poured; The bottom rail is fixedly connected with the bottom of the wall 1; the bottom of the middle frame is connected with the prefabricated bottom of the wall 1, the top of the middle frame is connected with the upper device, and the chain running is installed in the middle frame. The track and the middle frame are also part of the reinforcement cage of wall 1; the chain vertical conveyor of rock and soil is formed by the chain running upwards from the bottom and the closed cavity of the middle frame. With the sinking of the bottom of wall 1, the middle frame It also sinks synchronously; the upper device is fixed on the working platform or on the top of the middle frame, the upper device is equipped with a chain drive device and a tensioning device, and the chain on the bottom track passes through the middle frame and the drive device in the upper device, tensioning device The devices are connected; the specific construction is divided into the following steps:
1)清理现场,搭建作业平台; 1) Clean up the site and build a working platform;
2)墙1底部蹲位,并在其底部的轨道上安装链刀; 2) Squat at the bottom of wall 1, and install a chain knife on the track at the bottom;
3)组装中间机架、上部装置和浇筑模板; 3) Assemble the middle frame, upper device and pouring formwork;
4)安装链条驱动装置、张紧装置,将底部轨道、中间机架、上部装置的链刀连接成一体,组成链式挖掘装置; 4) Install the chain driving device and the tensioning device, and connect the bottom track, the middle frame, and the chain knife of the upper device into one body to form a chain excavating device;
5)制作钢筋笼,在模板中浇筑混凝土; 5) Make reinforcement cages and pour concrete in formwork;
6)驱动链条,链刀挖掘墙1底部的岩土,并将已挖掘的岩土经中间机架输送至上方,墙1随之下降; 6) Drive the chain, the chain knife excavates the rock and soil at the bottom of the wall 1, and transports the excavated rock and soil to the top through the middle frame, and the wall 1 descends accordingly;
7)随着墙1底部的下降,模板中的墙1边浇筑边下降; 7) As the bottom of wall 1 descends, wall 1 in the formwork descends while pouring;
8)墙1下降至设计深度拆除链刀后灌浆,拆除浇筑模板。 8) The wall 1 is lowered to the design depth, the chain knife is removed, grouted, and the pouring formwork is removed.
本发明的优点:克服了现有技术存在的缺陷,由于墙自身带有挖掘装置,所以即可以在工厂分块预制,也可以在现场的固定模板中边浇筑边下降,施工简单;利用墙和顶盖构成挡水围堰,排水后形成干地施工环境,然后在干地环境中清除建筑物内部的岩土,浇筑楼板或者底板;另外墙自身结构的施工周期短,成本低。The present invention has the advantages of overcoming the defects of the prior art, because the wall itself has an excavating device, so it can be prefabricated in blocks in the factory, or it can be lowered while pouring in the fixed formwork on site, and the construction is simple; using the wall and The top cover constitutes a water-retaining cofferdam, and after drainage, a dry construction environment is formed, and then the rock and soil inside the building are removed in the dry environment, and the floor or bottom slab is poured; in addition, the construction period of the wall itself is short and the cost is low.
附图说明Description of drawings
图1是墙1的结构示意图,也是链式挖掘装置2挖掘基础底部岩土时的结构示意图,也是组成链式挖掘装置2的传动装置2-1和链刀3的结构示意图,也是组成传动装置2-1的驱动装置2-1-1、链轮2-1-2和张紧装置2-1-3的结构示意图;Fig. 1 is a schematic diagram of the structure of the wall 1, and also a schematic diagram of the structure of the chain excavation device 2 when excavating the rock and soil at the bottom of the foundation. Schematic diagram of the structure of the driving device 2-1-1, the sprocket 2-1-2 and the tensioning device 2-1-3 of 2-1;
图2是图1的A向视图;Fig. 2 is the A direction view of Fig. 1;
图3是图1的B-B剖视图,也是链刀3在基础底部既挖掘岩土又是岩土水平输送的结构示意图,也是墙1内设有泥浆管路6,管路6的端部是喷嘴6-1的结构示意图;Fig. 3 is a B-B sectional view of Fig. 1, and it is also a structural schematic diagram of the chain knife 3 excavating rock and soil at the bottom of the foundation and horizontally transporting the rock and soil, and also a mud pipeline 6 is provided in the wall 1, and the end of the pipeline 6 is a nozzle 6 Schematic diagram of the structure of -1;
图4是图1的C-C剖视图,也是由链刀3和侧面罩1-3组成的垂直岩土输送装置7的结构示意图;Fig. 4 is the C-C sectional view of Fig. 1, also is the structural representation of the vertical rock and earth conveying device 7 that is made up of chain knife 3 and side cover 1-3;
图5是链刀3的结构示意图,(a)是链条3-1和刀具3-2的结构示意图,也是由A十字节3-1-1和B十字节3-1-2组成的链条3-1的十字节的结构示意图;也是链条3-1实现空间弯曲的结构示意图。(b)是链刀由绳索3-1B和刀具3-2B组成的结构示意图;也是绳索3-1B和刀具3-2B的结构示意图;Fig. 5 is a schematic diagram of the structure of the chain knife 3, (a) is a schematic diagram of the structure of the chain 3-1 and the knife 3-2, which is also composed of A ten-byte 3-1-1 and B ten-byte 3-1-2 The schematic diagram of the ten-byte structure of the chain 3-1; it is also the schematic diagram of the space bending realized by the chain 3-1. (b) is a schematic structural diagram of a chain knife composed of a rope 3-1B and a cutter 3-2B; it is also a schematic structural diagram of a rope 3-1B and a cutter 3-2B;
图6是墙1的A法施工示意图;Fig. 6 is the A method construction schematic diagram of wall 1;
图7是墙1的B法施工示意图,也是底部轨道B-1、浇筑模板B-4的结构示意图,是上部装置B-3固定于作业平台不升降的结构示意图;Fig. 7 is a schematic diagram of the B-method construction of the wall 1, which is also a schematic structural diagram of the bottom rail B-1 and the pouring formwork B-4, and is a structural schematic diagram of the upper device B-3 fixed on the working platform without lifting;
图8是图7的A向视图,也是中间机架B-2和上部装置B-3的结构示意图;Fig. 8 is a view from direction A of Fig. 7, and is also a structural schematic diagram of the middle frame B-2 and the upper device B-3;
图9中的a是B法施工时的初始状态示意图,也是上部装置B-3固定于中间机架B-2的顶部的结构示意图,b是底部开始挖掘上部开始浇筑的示意图;A in Fig. 9 is a schematic diagram of the initial state during method B construction, and it is also a schematic diagram of the structure of the upper device B-3 fixed on the top of the middle frame B-2, and b is a schematic diagram of the excavation at the bottom and the pouring of the upper part;
图10中的c是基础1下沉至一定深度时的B法施工示意图,d是基础1达到设计深度拆除施工设备后的示意图;c in Figure 10 is a schematic diagram of method B construction when the foundation 1 sinks to a certain depth, and d is a schematic diagram of the construction equipment removed after the foundation 1 reaches the design depth;
图11是地铁车站或多层建筑物周边承重墙1的结构示意图,也是周边墙是相互嵌入的结构示意图;Fig. 11 is a structural schematic diagram of a load-bearing wall 1 around a subway station or a multi-storey building, and is also a structural schematic diagram in which the surrounding walls are embedded in each other;
图12是图11的A-A视图,也是地铁车站和隧道两侧承重墙1达到设计深度后的示意图,也是墙1上的挡土墙1-4和墙1上对应每层楼板的接口位置处的预制凹槽1-7的结构示意图;Fig. 12 is the A-A view of Fig. 11, which is also a schematic diagram of the load-bearing walls 1 on both sides of the subway station and the tunnel after reaching the design depth, and also the position of the interface between the retaining walls 1-4 on the wall 1 and the corresponding floor slabs on the wall 1 Schematic diagram of the structure of prefabricated grooves 1-7;
图13是清理上层岩土,安装预制顶盖4或现浇顶盖4的示意图;Fig. 13 is the schematic diagram of cleaning the upper rock and soil and installing the prefabricated top cover 4 or the cast-in-place top cover 4;
图14是回填顶盖4上的岩土后,施工上方路面,挖掘负一层的岩土,拆除凹槽盖板1-7后现浇楼板5的示意图;Fig. 14 is after backfilling the rock and soil on the top cover 4, constructing the upper road surface, excavating the rock and soil of the negative layer, and removing the groove cover plate 1-7 after the schematic diagram of the cast-in-place floor slab 5;
图15是地铁车站或多层建筑物内的岩土清除后,楼板5全部现浇完的结构示意图;Fig. 15 is after the rock and soil in the subway station or the multi-storey building is removed, the structural schematic diagram of floor slab 5 being all cast in place;
图16是水底隧道的俯视图,也是由两侧挡水墙1-4(含其底部的隧道墙1)和横挡水墙1-5围成的封闭区域排水后成为施工隧道的作业区的结构示意图;Figure 16 is a top view of the underwater tunnel, which is also the structure of the closed area surrounded by the water retaining walls 1-4 on both sides (including the tunnel wall 1 at the bottom) and the transverse water retaining walls 1-5, which becomes the work area of the construction tunnel after drainage schematic diagram;
图17是由两侧挡水墙1-4(含其底部的隧道墙1)和横挡水墙1-5形成作业区域的结构示意图;Figure 17 is a schematic structural view of the operation area formed by the retaining walls 1-4 on both sides (including the tunnel wall 1 at the bottom) and the transverse retaining walls 1-5;
图18是两边纵向挡土墙或者挡水墙1-5的支撑1-6的结构示意图,也是利用挡水墙形成作业区域后,清除隧道墙1内上部的部分岩土的结构示意图;Fig. 18 is a schematic structural view of the supports 1-6 of the longitudinal retaining walls or water retaining walls 1-5 on both sides, and it is also a structural schematic view of clearing part of the rock and soil in the upper part of the tunnel wall 1 after the water retaining wall is used to form an operation area;
图19是隧道的顶盖4施工完成后,挡水墙1-4与隧道墙1分离后岩土回填的结构示意图;Fig. 19 is a schematic diagram of the rock-soil backfill after the construction of the roof 4 of the tunnel is completed, and the water retaining wall 1-4 is separated from the tunnel wall 1;
图20是清理隧道墙1和隧道的顶盖4内的岩土后,施工隧道的底部楼板5的结构示意图;Fig. 20 is a structural schematic diagram of the bottom floor 5 of the construction tunnel after cleaning the rock and soil in the tunnel wall 1 and the roof 4 of the tunnel;
图21是墙1的底部链刀轨道和侧面链刀轨道的结构示意图,轨道的类型包括A1、A2、B、C和D 共5种,其中A1、A2是凹型,B是平面型,C是凸型;Figure 21 is a structural schematic diagram of the bottom chain knife track and the side chain knife track of wall 1. There are five types of track including A1, A2, B, C and D, where A1 and A2 are concave, B is flat, and C is Convex;
图22是D为纵向多排轨道错开成锥型的结构示意图;Fig. 22 is a structural schematic diagram of D being a tapered structure in which vertical rows of tracks are staggered;
图23是墙1的D型轨道和多排链刀的结构示意图。Fig. 23 is a schematic structural view of the D-shaped track of the wall 1 and multiple rows of chain knives.
图中的1是隧道两侧承重墙和地铁车站周边承重墙;1-1是墙1底部运行链刀3的轨道;1-2是墙1侧面运行链刀3的轨道;1-3是底部带刃角的墙1的侧面罩;1-4是墙1上部的纵向挡土墙或者挡水墙;1-5是垂直于隧道长度方向的横挡水墙;1-6是两边纵向挡土墙或者挡水墙1-4的支撑;1-7是墙1在对应每层楼板的接口位置处的预制凹槽;2是链式挖掘装置;2-1是链式挖掘装置2的传动装置;2-1-1是传动装置2-1的驱动装置;2-1-2是传动装置2-1的链轮;2-1-3是传动装置2-1的张紧装置;3是组成链式挖掘装置2的链刀;3-1是组成链刀3的链条,包括履带、绳索和柔性带;3-1-1是组成链条十字节的A十字节;3-1-2是组成链条十字节的B十字节;3-1B是组成链刀3的钢索;3-2是固定在链条3-1上的挖掘岩土的刀具;3-2B是固定在钢索3-1B上的挖掘岩土的刀具;4是隧道或者地铁车站的顶盖;5是隧道或者地铁车站的楼板;6是墙1内的泥浆管路;6-1是管路泥浆6的端部的喷嘴;7是垂直岩土输送装置;B-1是B法中的底部轨道;B-2是B法中的中间机架;B-3是B法中的上部装置;B-4是B法中的浇筑模板。1 in the figure is the load-bearing walls on both sides of the tunnel and the surrounding walls of the subway station; 1-1 is the track on which the chain knife 3 runs at the bottom of wall 1; 1-2 is the track on which the chain knife 3 runs on the side of wall 1; 1-3 is the bottom The side cover of wall 1 with bevels; 1-4 is the longitudinal retaining wall or water retaining wall on the upper part of wall 1; 1-5 is the transverse water retaining wall perpendicular to the length direction of the tunnel; 1-6 is the longitudinal retaining wall on both sides The support of the wall or water retaining wall 1-4; 1-7 is the prefabricated groove of the wall 1 at the interface position corresponding to each floor; 2 is the chain excavation device; 2-1 is the transmission device of the chain excavation device 2 ; 2-1-1 is the driving device of the transmission device 2-1; 2-1-2 is the sprocket wheel of the transmission device 2-1; 2-1-3 is the tensioning device of the transmission device 2-1; 3 is the composition The chain cutter of the chain excavation device 2; 3-1 is the chain forming the chain cutter 3, including crawler belts, ropes and flexible belts; 3-1-1 is the A ten-byte forming the chain ten-byte; 3-1-2 3-1B is the steel cable that forms the chain knife 3; 3-2 is the tool for excavating rock and soil fixed on the chain 3-1; 3-2B is fixed on the steel cable 3-1B is the tool for excavating rock and soil; 4 is the roof of the tunnel or subway station; 5 is the floor of the tunnel or subway station; 6 is the mud pipeline in the wall 1; 6-1 is the end of the pipeline mud 6 7 is the vertical rock and soil conveying device; B-1 is the bottom track in B method; B-2 is the middle frame in B method; B-3 is the upper device in B method; B-4 is Pour formwork in Method B.
具体实施方式detailed description
一种地下建筑周边承重墙1的底部设有轨道,施工时,轨道上安装有挖掘岩土的链刀,链刀由链条和固定于链条上的刀具组成,链刀和传动装置组成了链式挖掘装置,传动装置位于地面以上由链轮和驱动装置等组成,驱动装置驱动链刀,链刀沿着轨道运行,墙1底部的刀具挖掘岩土,由底部向上运行的链刀将已挖掘的岩土带至上方,墙1底部的链刀和墙1一起下降。A track is provided at the bottom of the load-bearing wall 1 around an underground building. During construction, a chain knife for excavating rock and soil is installed on the track. The chain knife is composed of a chain and a knife fixed on the chain. The chain knife and the transmission device form a chain The excavating device, the transmission device is located above the ground and consists of a sprocket and a driving device. The driving device drives the chain cutter, and the chain cutter runs along the track. The rock soil is brought to the top, and the chain knife at the bottom of the wall 1 and the wall 1 descend together.
所述的墙1的施工法是预制法,分如下步骤:The construction method of described wall 1 is prefabrication method, divides following steps:
1)在工场分块或整体预制墙1;1) Block or integral prefabricated wall 1 in the workshop;
2)运至现场拼装墙1并蹲位,并在其底部的轨道上安装链刀;2) Transport to the on-site assembled wall 1 and squat down, and install the chain knife on the track at the bottom;
3)安装链条驱动等装置,连接安装有挖掘刀的链条;3) Install chain drives and other devices, and connect the chains with excavating knives;
4)驱动链条,链刀挖掘底部的岩土,经岩土输送装置送至上方,墙1随之下降;4) Drive the chain, and the chain knife excavates the rock and soil at the bottom, and sends it to the top through the rock and soil conveying device, and the wall 1 descends accordingly;
5)墙1下降至设计深度拆除链刀后灌浆。5) Wall 1 is lowered to the design depth and grouted after the chain knife is removed.
所述的墙1除预制底部外,均在现场的固定模板中浇筑,施工时固定模板不动,随着底部岩土的挖掘,墙1边浇筑边下沉;链式挖掘装置由底部的轨道、中间机架和上部装置组成,底部轨道与墙1的底部固连成一体;中间机架的底部与墙1的预制底部相连,中间机架的顶部与上部装置相连,中间机架内安装有链条运行的轨道,中间机架同时也是墙1钢筋笼的组成部分;由底部向上运行的链条和中间机架的封闭腔组成了链式岩土垂直输送机,随着墙1底部的下沉,中间机架也同步下沉;上部装置固定于作业平台上或固定于中间机架的顶部,上部装置安装有链条驱动装置和张紧装置,底部轨道的链条通过中间机架与上部装置内驱动装置、张紧装置相连;具体施工分如下步骤:Except for the prefabricated bottom, the wall 1 is poured in the fixed formwork on site, and the fixed formwork does not move during construction. With the excavation of the rock and soil at the bottom, the wall 1 sinks while being poured; , the middle frame and the upper device, the bottom track is fixedly connected with the bottom of the wall 1; the bottom of the middle frame is connected with the prefabricated bottom of the wall 1, the top of the middle frame is connected with the upper device, and the middle frame is installed with The track on which the chain runs, the middle frame is also an integral part of the reinforcement cage of wall 1; the chain-type rock-soil vertical conveyor is composed of the chain running upwards from the bottom and the closed cavity of the middle frame. With the sinking of the bottom of wall 1, The middle frame also sinks synchronously; the upper device is fixed on the working platform or on the top of the middle frame, the upper device is equipped with a chain drive device and a tensioning device, and the chain on the bottom track passes through the middle frame and the drive device in the upper device , and the tensioning device are connected; the specific construction is divided into the following steps:
1)清理现场,搭建作业平台;1) Clean up the site and build a working platform;
2)墙1底部蹲位,并在其底部的轨道上安装链刀;2) Squat at the bottom of wall 1, and install a chain knife on the track at the bottom;
3)组装中间机架、上部装置和浇筑模板;3) Assemble the middle frame, upper device and pouring formwork;
4)安装链条驱动装置、张紧装置,将底部轨道、中间机架、上部装置的链刀连接成一体,组成链式挖掘装置;4) Install the chain driving device and the tensioning device, and connect the bottom track, the middle frame, and the chain knife of the upper device into one body to form a chain excavating device;
5)制作钢筋笼,在模板中浇筑混凝土;5) Make reinforcement cages and pour concrete in formwork;
6)驱动链条,链刀挖掘墙1底部的岩土,并将已挖掘的岩土经中间机架输送至上方,墙1随之下降;6) Drive the chain, the chain knife excavates the rock and soil at the bottom of the wall 1, and transports the excavated rock and soil to the top through the middle frame, and the wall 1 descends accordingly;
7)随着墙1底部的下降,模板中的墙1边浇筑边下降;7) As the bottom of wall 1 descends, wall 1 in the formwork descends while pouring;
8)墙1下降至设计深度拆除链刀后灌浆,拆除浇筑模板。8) The wall 1 is lowered to the design depth, the chain knife is removed, grouted, and the pouring formwork is removed.
所述的墙1施工时,当顶部低于地面(或水面)时,顶部安装有高于地面(或水面)临时的挡土墙(或档水墙)。During the construction of the wall 1, when the top is lower than the ground (or water surface), a temporary retaining wall (or water retaining wall) higher than the ground (or water surface) is installed on the top.
所述的挡水墙(或挡土墙)在宽度方向是超出墙1的,且是低于水底(或地面)的,则此部分的底部安装有链刀。The water retaining wall (or earth retaining wall) exceeds the wall 1 in the width direction and is lower than the water bottom (or ground), and a chain knife is installed at the bottom of this part.
所述的墙1施工时,墙1内或墙1的上部设有车辆通行的临时车道。During the construction of the wall 1, a temporary lane for vehicles is provided in the wall 1 or on the top of the wall 1.
所述的墙1在对应每层楼板的接口位置处有一预制凹槽,凹槽内预留有墙1与楼板连接用的钢筋或焊接钢板或连接件。The wall 1 has a prefabricated groove at the interface position corresponding to each floor slab, and steel bars or welded steel plates or connectors for connecting the wall 1 and the floor slab are reserved in the groove.
所述的墙1下沉到设计深度后先施工顶盖,顶盖施工结束后再施工顶盖以下部分。After the wall 1 sinks to the design depth, the top cover is constructed first, and then the part below the top cover is constructed after the construction of the top cover is completed.
所述的地下建筑是地铁车站或多层地下建筑,具体施工法分如下步骤:Described underground building is subway station or multi-storey underground building, and concrete construction method is divided into following steps:
1)施工四周承重墙1;1) Construction of surrounding load-bearing walls 1;
2)安装预制顶盖或现浇顶盖;2) Install prefabricated roof or cast-in-place roof;
3)施工顶盖上方路面,挖掘负一层的岩土;3) Construction of the road above the roof, and excavation of the rock and soil of the negative layer;
4)拆除凹槽盖板,现浇负一层楼板;4) Remove the groove cover plate, and cast in-situ negative floor slab;
5)挖掘负二层的岩土;5) Excavate the rock and soil of the negative second floor;
6)拆除凹槽盖板,现浇负二层楼板;6) Remove the groove cover and cast-in-place negative second-floor slab;
重复步骤3)、4)作业,从上往下施工直至地下楼层全部完工。Repeat steps 3) and 4) to work from top to bottom until all underground floors are completed.
所述的地下建筑是水底隧道,隧道两侧的挡水墙之间设有若干连接支撑,支撑的底部平面高于隧道顶的上平面,其中一端是垂直于两侧墙的横挡水墙,由两侧挡水墙(含其底部的隧道墙)和横挡水墙围成的封闭区域排水后成为施工隧道的作业区。The underground building is an underwater tunnel, and several connecting supports are provided between the water retaining walls on both sides of the tunnel. The closed area surrounded by the water retaining walls on both sides (including the tunnel wall at the bottom) and the transverse water retaining wall becomes the operation area of the construction tunnel after drainage.
所述的横挡水墙的底部和施工前下平面低于水底的支撑的底部设有轨道,轨道上安装有挖掘岩土的链刀,链刀由链条和固定于链条上的刀具组成,链刀和传动装置组成了链式挖掘装置,传动装置位于水面以上由链轮和驱动装置等组成;施工时驱动装置驱动链条,链条带动刀具沿着轨道运行,底部的刀具挖掘岩土,垂直向上运行的链刀将已挖掘的岩土带至上方,隧道墙(含侧挡水墙)和横挡水墙一起下降至设计深度,两侧挡水墙(含其底部的隧道墙)和横挡水墙形成封闭区域,在此区域内排水、挖土、施工隧道;具体施工分如下步骤:The bottom of the horizontal water retaining wall and the bottom of the support whose lower plane is lower than the water bottom before construction are provided with a track on which a chain cutter for excavating rock and soil is installed. The chain cutter is composed of a chain and a cutter fixed on the chain. The chain The knife and the transmission device form a chain excavation device. The transmission device is located above the water surface and consists of a sprocket and a drive device. During construction, the drive device drives the chain, and the chain drives the cutter to run along the track. The cutter at the bottom excavates the rock and runs vertically upwards. The chain knife will bring the excavated rock and soil to the top, the tunnel wall (including the side water retaining wall) and the horizontal water retaining wall will drop to the design depth together, and the water retaining walls on both sides (including the tunnel wall at the bottom) and the horizontal water retaining wall will The wall forms a closed area, in which drainage, excavation, and tunnel construction are carried out; the specific construction is divided into the following steps:
1)用两侧挡水墙(含其底部的隧道墙)和横挡水墙形成一个或若干作业区域;1) Form one or several work areas with water retaining walls on both sides (including the tunnel wall at the bottom) and transverse water retaining walls;
2)把作业区域分为隧道墙(含侧挡水墙)、支撑和横挡水墙施工段、排水段、挖土段、隧道施工段和挡水墙拆除段,在各功能段进行相应的功能作业;2) Divide the operation area into tunnel wall (including side retaining wall), support and transverse retaining wall construction section, drainage section, excavation section, tunnel construction section and retaining wall demolition section, and carry out corresponding work in each functional section functional work;
3)挡水墙拆除段位于隧道顶施工完成后,将挡水墙与隧道墙分离;3) The water retaining wall removal section is located at the tunnel roof and after the construction is completed, the water retaining wall will be separated from the tunnel wall;
4)将拆除的挡水墙移至前端,形成新的作业区域;4) Move the removed retaining wall to the front to form a new work area;
5)重复上述1)~4)循环施工,直至完成;5) Repeat the above 1) ~ 4) cycle construction until complete;
上述2)中的分段,当只有一个区域时,按时间分段;当有若干个区域时,按空间分段。For the segmentation in 2) above, when there is only one area, it is segmented by time; when there are several areas, it is segmented by space.
所述的地下建筑是陆地隧道,两侧挡土墙(含其底部的隧道墙)之间的区域是施工隧道的作业区。 其特征是分如下步骤:The said underground building is a land tunnel, and the area between the retaining walls on both sides (including the tunnel wall at the bottom) is the operation area for constructing the tunnel. It is characterized by the following steps:
1)施工两侧隧道墙和挡土墙形成若干作业区域;1) The tunnel walls and retaining walls on both sides of the construction form several work areas;
2)把作业区域分为两侧墙和挡土墙施工段、挖土段、隧道施工段和挡土墙拆除段,在各功能段进行相应的功能作业;2) Divide the operation area into two side walls and retaining wall construction section, excavation section, tunnel construction section and retaining wall demolition section, and carry out corresponding functional operations in each functional section;
3)挡土墙拆除段位于隧道顶施工完成之后,将挡土墙与隧道墙体分离;3) The removal section of the retaining wall is located after the construction of the tunnel roof is completed, and the retaining wall is separated from the tunnel wall;
4)将拆除的挡土墙移至前端,形成新的作业区域;4) Move the removed retaining wall to the front to form a new work area;
5)重复上述1)~4)循环施工,直至完成;5) Repeat the above 1) ~ 4) cycle construction until complete;
上述2)中的分段,当只有一个区域时,按时间分段;当有若干个区域时,按空间分段。For the segmentation in 2) above, when there is only one area, it is segmented by time; when there are several areas, it is segmented by space.
下面结合附图进一步描述本发明:Further describe the present invention below in conjunction with accompanying drawing:
如图1~图5所示,隧道两侧承重墙和地铁车站周边承重墙1的底部设有轨道1-1,施工时,轨道上安装有挖掘岩土的链刀3,链刀3由链条3-1和固定于链条上的刀具3-2组成,链刀3和传动装置2-1组成了链式挖掘装置2,传动装置2-1位于地面以上由驱动装置2-1-1和链轮2-1-2等组成,驱动装置2-1-1驱动链条3-1,链条3-1带动刀具3-2沿着轨道运行,墙1底部的刀具3-2挖掘岩土,垂直向上运行的链刀3将已挖掘的岩土带至上方,墙1底部的链刀3和墙1一起下降。As shown in Figures 1 to 5, the load-bearing walls on both sides of the tunnel and the bottom of the load-bearing walls 1 around the subway station are provided with a track 1-1. During construction, a chain cutter 3 for excavating rock and soil is installed on the track. 3-1 and the cutter 3-2 fixed on the chain, the chain cutter 3 and the transmission device 2-1 form the chain excavation device 2, and the transmission device 2-1 is located above the ground by the drive device 2-1-1 and the chain Wheel 2-1-2 etc., drive device 2-1-1 drives chain 3-1, chain 3-1 drives cutter 3-2 to run along the track, cutter 3-2 at the bottom of wall 1 excavates rock and soil, vertically upward The chain cutter 3 of operation brings the excavated rock and soil to the top, and the chain cutter 3 at the bottom of the wall 1 and the wall 1 descend together.
如图6所示墙1采用A法预制法分如下步骤:As shown in Figure 6, the wall 1 adopts the A method prefabrication method and divides the following steps:
1)在工场分块预制墙1,运至现场拼装墙1并蹲位,并在其底部的轨道1-1上安装链刀3,安装链条驱动装置2-1-1等装置,连接安装有挖掘刀3的链条3-1,如图中的a所示;1) Block the prefabricated wall 1 in the workshop, transport it to the site to assemble the wall 1 and squat down, and install the chain knife 3 on the track 1-1 at the bottom, install the chain drive device 2-1-1 and other devices, connect and install the The chain 3-1 of digging knife 3, as shown in a among the figure;
2)驱动链条3-1,链刀挖掘底部的岩土,经链刀3送至上方,墙1随之下降,如图中b所示;2) Drive the chain 3-1, the chain knife excavates the rock and soil at the bottom, and sends it to the top through the chain knife 3, and the wall 1 descends accordingly, as shown in b in the figure;
3)下降至一定深度后,在地面拼装墙1的预制件,也可边下沉边拼装,如图中c所示;3) After descending to a certain depth, the prefabricated parts of wall 1 assembled on the ground can also be assembled while sinking, as shown in c in the figure;
4)下降至设计深度后灌浆,或拆除链刀3后再灌浆,如图中d所示。4) Grout after descending to the design depth, or remove the chain knife 3, as shown in figure d.
图 7~图10所示,墙1采用B法现浇法分如下步骤 :As shown in Figures 7 to 10, the wall 1 is divided into the following steps by adopting the method B cast-in-place method:
1)清理现场,搭建作业平台;1) Clean up the site and build a working platform;
2)组装底部轨道B-1和浇筑模板B-4,即墙1的底部蹲位,并在其底部的轨道上安装链刀3;2) Assemble the bottom track B-1 and pouring formwork B-4, that is, the bottom squat position of the wall 1, and install the chain knife 3 on the bottom track;
3)组装中间机架B-2、上部装置B-3;3) Assemble the middle frame B-2 and the upper device B-3;
4)安装链条驱动装置2-1-1、张紧装置2-1-3,将底部轨道B-1、中间机架B-2、上部装置B-3和链条3-1连接成一体,组成链式挖掘装置2;4) Install the chain driving device 2-1-1 and the tensioning device 2-1-3, and connect the bottom rail B-1, the middle frame B-2, the upper device B-3 and the chain 3-1 into one body to form a chain excavation device 2;
5)制作钢筋笼,将中间机架B-2与钢筋笼焊接成一体,中间机架B-2同时也是浇筑模板的组成部分;5) Make a reinforcement cage, weld the middle frame B-2 and the reinforcement cage into one, and the middle frame B-2 is also a component of the pouring formwork;
6)在模板B-4中浇筑混凝土;6) Pouring concrete in formwork B-4;
7)驱动链条3-1,链刀3挖掘底部的岩土,并将已挖掘的岩土经中间机架B-2输送至上方,墙1随之下降;7) Drive the chain 3-1, the chain knife 3 excavates the rock and soil at the bottom, and transports the excavated rock and soil to the top through the middle frame B-2, and the wall 1 descends accordingly;
8)随着墙1底部的挖掘,模板B-4中的墙1边浇筑边下降;8) With the excavation of the bottom of wall 1, wall 1 in formwork B-4 descends while pouring;
9)下降至设计深度拆除链刀3后灌浆;9) Descend to the design depth and remove the chain knife 3 and then grout;
10)拆除上部装置和中间机架高于墙1的部分,拆除浇筑模板。10) Remove the upper device and the part of the middle frame higher than wall 1, and remove the pouring formwork.
如图12~图15所示,地铁车站或多层地下建筑施工法分如下步骤:As shown in Figures 12 to 15, the construction method of a subway station or multi-storey underground building is divided into the following steps:
1)施工地铁车站承重墙1;1) Construction of the bearing wall 1 of the subway station;
2)安装预制顶盖4或现浇顶盖4;2) Install prefabricated roof 4 or cast-in-place roof 4;
3)施工顶盖上方路面,挖掘负一层的岩土;3) Construct the road above the roof, and excavate the rock and soil of the negative layer;
4)拆除凹槽盖板,现浇负一层楼板5;4) Remove the groove cover plate and cast-in-place negative floor slab 5;
5)挖掘负二层的岩土;5) Excavate the rock and soil of the negative second floor;
6)拆除凹槽盖板,现浇负二层楼板5;6) Remove the groove cover and cast-in-place negative second floor slab 5;
重复步骤3)、4)作业,从上往下施工直至地下楼层全部完工。Repeat steps 3) and 4) to work from top to bottom until all underground floors are completed.
如图16所示,水底隧道两侧的挡水墙1-4之间设有若干连接支撑1-6,支撑的底部平面高于隧道顶的上平面,其中一端是垂直于两侧墙的横挡水墙1-5,由两侧挡水墙1-4(含其底部的隧道墙1)和横挡水墙1-5围成的封闭区域排水后成为施工隧道的作业区。As shown in Figure 16, a number of connecting supports 1-6 are provided between the water retaining walls 1-4 on both sides of the underwater tunnel. The water retaining walls 1-5, the closed area surrounded by the water retaining walls 1-4 on both sides (including the tunnel wall 1 at the bottom) and the transverse water retaining walls 1-5 become the operation area of the construction tunnel after drainage.
如图16~图20所示,墙1的底部和施工前下平面低于水底的支撑的底部设有轨道,轨道上安装有挖掘岩土的链刀3,底部的刀具3-2挖掘岩土,垂直向上运行的链刀3将已挖掘的岩土带至上方,隧道墙1(含侧挡水墙1-4)和横挡水墙1-5一起下降至设计深度,两侧挡水墙1-4(含其底部的隧道墙1)和横挡水墙1-5形成封闭区域,在此区域内排水、挖土、施工隧道;具体施工分如下步骤:As shown in Figures 16 to 20, the bottom of the wall 1 and the bottom of the support whose lower plane is lower than the water bottom before construction are provided with rails, and chain cutters 3 for excavating rock and soil are installed on the rails, and the cutter 3-2 at the bottom excavates rock and soil , the chain knife 3 running vertically upwards brings the excavated rock and soil to the top, the tunnel wall 1 (including the side retaining walls 1-4) and the horizontal retaining walls 1-5 descend to the design depth together, and the retaining walls on both sides 1-4 (including the tunnel wall 1 at the bottom) and the horizontal retaining wall 1-5 form a closed area, in which drainage, excavation, and tunnel construction are carried out; the specific construction is divided into the following steps:
1)用两侧挡水墙1-4(含其底部的隧道墙1)和横挡水墙1-5形成一个或若干作业区域;1) Use retaining walls 1-4 on both sides (including the tunnel wall 1 at the bottom) and transverse retaining walls 1-5 to form one or several work areas;
2)把作业区域分为隧道墙1(含侧挡水墙1-4)、支撑1-6和横挡水墙1-5施工段、排水段、挖土段、隧道施工段和挡水墙拆除段,在各功能段进行相应的功能作业;2) Divide the operation area into tunnel wall 1 (including side retaining wall 1-4), support 1-6 and transverse retaining wall 1-5 construction section, drainage section, excavation section, tunnel construction section and retaining wall Remove the section, and carry out corresponding functional operations in each functional section;
3)挡水墙1-4拆除段位于隧道顶4施工完成后,将挡水墙与隧道墙分离;3) The removal section of the water retaining wall 1-4 is located at the tunnel roof 4. After the construction is completed, the water retaining wall will be separated from the tunnel wall;
4)将拆除的挡水墙1-4移至前端,形成新的作业区域;4) Move the removed retaining wall 1-4 to the front end to form a new work area;
5)重复上述1)~4)循环施工,直至完成;5) Repeat the above 1) ~ 4) cycle construction until complete;
上述2)中的分段,当只有一个区域时,按时间分段;当有若干个区域时,按空间分段。For the segmentation in 2) above, when there is only one area, it is segmented by time; when there are several areas, it is segmented by space.
Claims (12)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710037690.1A CN106759463A (en) | 2017-01-18 | 2017-01-18 | A kind of hypogee and its construction method |
PCT/CN2018/072520 WO2018133740A1 (en) | 2017-01-18 | 2018-01-13 | Underground building and construction method for same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710037690.1A CN106759463A (en) | 2017-01-18 | 2017-01-18 | A kind of hypogee and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106759463A true CN106759463A (en) | 2017-05-31 |
Family
ID=58943377
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710037690.1A Pending CN106759463A (en) | 2017-01-18 | 2017-01-18 | A kind of hypogee and its construction method |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN106759463A (en) |
WO (1) | WO2018133740A1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2018133739A1 (en) * | 2017-01-18 | 2018-07-26 | 王燏斌 | Foundation having chain cutter at base during construction and construction method of same |
WO2018133740A1 (en) * | 2017-01-18 | 2018-07-26 | 王燏斌 | Underground building and construction method for same |
CN109778909A (en) * | 2019-03-06 | 2019-05-21 | 王燏斌 | A kind of subsidence construction method for basement and its construction device |
CN110056003A (en) * | 2019-03-06 | 2019-07-26 | 王燏斌 | A kind of integral sinking construction method and its constructing device for basement |
CN114164929A (en) * | 2021-10-21 | 2022-03-11 | 王树生 | A sunken wall foundation and its construction device |
WO2023066325A1 (en) * | 2021-10-21 | 2023-04-27 | 王树生 | Sunken frame foundation and ground prefabricating equipment and sinking device thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5985021A (en) * | 1982-11-05 | 1984-05-16 | Kajima Corp | Method and apparatus for construction of underground continuous wall |
JPS62233328A (en) * | 1986-04-01 | 1987-10-13 | Fusao Sakano | Method and apparatus for setting retaining wall by excavator |
CN2260103Y (en) * | 1996-08-05 | 1997-08-20 | 郭同元 | Pile |
CN103334422A (en) * | 2013-06-26 | 2013-10-02 | 中国建筑股份有限公司 | Assembled embedded type prefabricated hollow underground continuous wall and construction method thereof |
CN103741714A (en) * | 2013-12-09 | 2014-04-23 | 中国建筑第二工程局有限公司 | Full-cover excavation top-down construction method for underground engineering |
CN104343131A (en) * | 2013-07-27 | 2015-02-11 | 廖河山 | Semi-prefabricated semi-cast-in-situ underground continuous wall and construction process |
CN105887806A (en) * | 2016-06-13 | 2016-08-24 | 上海强劲地基工程股份有限公司 | Prefabricated underground diaphragm wall and its construction method |
Family Cites Families (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1024029C (en) * | 1989-08-19 | 1994-03-16 | 陆祖荫 | Direct sink-and-insert method and equipment for constructing underground building with combined and interlocked prefabricated concrete components |
JP2007247208A (en) * | 2006-03-15 | 2007-09-27 | Shimizu Corp | Wide rectangular continuous hole drilling machine |
CN202466660U (en) * | 2012-03-15 | 2012-10-03 | 中国铁建重工集团有限公司 | Chain knife type continuous wall chain wheel transmission mechanism |
CN102535559A (en) * | 2012-03-15 | 2012-07-04 | 中国铁建重工集团有限公司 | Chain cutter type mixing pile wall forming equipment |
CN106120723A (en) * | 2016-06-25 | 2016-11-16 | 张永忠 | Underground wall forming machine |
CN106759418A (en) * | 2017-01-18 | 2017-05-31 | 王燏斌 | A kind of pier footing and its construction method |
CN106759486A (en) * | 2017-01-18 | 2017-05-31 | 王燏斌 | A kind of underground structure being made up of stake and wall and its construction method |
CN106703079A (en) * | 2017-01-18 | 2017-05-24 | 王燏斌 | Inverted-U-shaped component for underwater tunnel and construction method of inverted-U-shaped component |
CN106759463A (en) * | 2017-01-18 | 2017-05-31 | 王燏斌 | A kind of hypogee and its construction method |
CN106759464A (en) * | 2017-01-18 | 2017-05-31 | 王燏斌 | A kind of hypogee and its construction method |
CN107059877A (en) * | 2017-01-18 | 2017-08-18 | 王燏斌 | Basis and its construction method of the bottom with chain knife during a kind of construction |
-
2017
- 2017-01-18 CN CN201710037690.1A patent/CN106759463A/en active Pending
-
2018
- 2018-01-13 WO PCT/CN2018/072520 patent/WO2018133740A1/en active Application Filing
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5985021A (en) * | 1982-11-05 | 1984-05-16 | Kajima Corp | Method and apparatus for construction of underground continuous wall |
JPS62233328A (en) * | 1986-04-01 | 1987-10-13 | Fusao Sakano | Method and apparatus for setting retaining wall by excavator |
CN2260103Y (en) * | 1996-08-05 | 1997-08-20 | 郭同元 | Pile |
CN103334422A (en) * | 2013-06-26 | 2013-10-02 | 中国建筑股份有限公司 | Assembled embedded type prefabricated hollow underground continuous wall and construction method thereof |
CN104343131A (en) * | 2013-07-27 | 2015-02-11 | 廖河山 | Semi-prefabricated semi-cast-in-situ underground continuous wall and construction process |
CN103741714A (en) * | 2013-12-09 | 2014-04-23 | 中国建筑第二工程局有限公司 | Full-cover excavation top-down construction method for underground engineering |
CN105887806A (en) * | 2016-06-13 | 2016-08-24 | 上海强劲地基工程股份有限公司 | Prefabricated underground diaphragm wall and its construction method |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2018133739A1 (en) * | 2017-01-18 | 2018-07-26 | 王燏斌 | Foundation having chain cutter at base during construction and construction method of same |
WO2018133740A1 (en) * | 2017-01-18 | 2018-07-26 | 王燏斌 | Underground building and construction method for same |
CN109778909A (en) * | 2019-03-06 | 2019-05-21 | 王燏斌 | A kind of subsidence construction method for basement and its construction device |
CN110056003A (en) * | 2019-03-06 | 2019-07-26 | 王燏斌 | A kind of integral sinking construction method and its constructing device for basement |
CN114164929A (en) * | 2021-10-21 | 2022-03-11 | 王树生 | A sunken wall foundation and its construction device |
WO2023066325A1 (en) * | 2021-10-21 | 2023-04-27 | 王树生 | Sunken frame foundation and ground prefabricating equipment and sinking device thereof |
Also Published As
Publication number | Publication date |
---|---|
WO2018133740A1 (en) | 2018-07-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106759463A (en) | A kind of hypogee and its construction method | |
US9322137B2 (en) | Method for building structures, particularly passages under operating railways or the like | |
AU2019439324B2 (en) | Wall sinking construction method | |
CN103306289B (en) | Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof | |
WO2018133739A1 (en) | Foundation having chain cutter at base during construction and construction method of same | |
CN103741714A (en) | Full-cover excavation top-down construction method for underground engineering | |
CN103670446B (en) | Circular diversion tunnel 2/3 circle concrete-liner construction method | |
CN207003499U (en) | A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit | |
CN110863498A (en) | Deep foundation pit combined supporting construction method next to subway station | |
WO2018133746A1 (en) | Underground building formed of piles and walls, and method for constructing same | |
WO2018133711A1 (en) | Pier foundation and construction method therefor | |
CN103866787B (en) | A kind of spacious reverse masonry method concrete cut that digs builds construction technology | |
WO2018177304A1 (en) | Fabricated underground building and construction method thereof | |
CN211285658U (en) | Structure capable of carrying out deep water area hollowing repair in rapid stream state | |
CN114164861A (en) | Construction method for underground building composed of wall-sinking foundation | |
CN207228156U (en) | A kind of underground structure being made of stake and wall | |
CN110258600B (en) | Vertical cofferdam construction method suitable for deepwater area | |
CN107542065A (en) | Suddenly let out the small punching block of groove turns over a liter construction method to a kind of height | |
CN104878774B (en) | Movable cofferdam open-cutting method | |
CN117569263A (en) | Dam impervious wall and construction method thereof | |
CN203373753U (en) | Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches | |
CN207228106U (en) | A kind of footing excavation device for casting | |
WO2018133748A1 (en) | Construction ship for underwater tunnel and construction method therefor | |
KR102171437B1 (en) | Construction method of panel for pedestrian block | |
CN116876518A (en) | Construction method suitable for foundation pit supporting of assembled subway entrance and exit in soft soil area |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 214000 No. 226, Xi Da Road, Mei Cun town, Xin Wu District, Wuxi, Jiangsu Applicant after: Wang Yubin Address before: 214000 Xinhua Road 121, Meishan Town, Wuxi New District, Jiangsu Applicant before: Wang Yubin |
|
CB02 | Change of applicant information | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170531 |
|
WD01 | Invention patent application deemed withdrawn after publication |