CN106545035A - The construction method of late poured band antipriming - Google Patents

The construction method of late poured band antipriming Download PDF

Info

Publication number
CN106545035A
CN106545035A CN201510610245.0A CN201510610245A CN106545035A CN 106545035 A CN106545035 A CN 106545035A CN 201510610245 A CN201510610245 A CN 201510610245A CN 106545035 A CN106545035 A CN 106545035A
Authority
CN
China
Prior art keywords
post
cast strip
sheath
rubber water
proof plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510610245.0A
Other languages
Chinese (zh)
Inventor
杨前
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201510610245.0A priority Critical patent/CN106545035A/en
Publication of CN106545035A publication Critical patent/CN106545035A/en
Pending legal-status Critical Current

Links

Landscapes

  • Building Environments (AREA)

Abstract

The present invention relates to use sealing apron to keep the sealing device field that underground foundation location or other areas are dried, specially a kind of construction method of late poured band antipriming.A kind of construction method of late poured band antipriming, is characterized in that:Implement successively as follows:A. set catch pit;B. cut sheath;C. install;D. pour concrete;E. clear up post-cast strip;F. pour post-cast strip concrete.The invention has the beneficial effects as follows:Technological principle is simple, is easy to operation, and water resistance is good.

Description

The construction method of late poured band antipriming
Technical field
The present invention relates to use sealing apron to keep the sealing device field that underground foundation location or other areas are dried, specially a kind of construction method of late poured band antipriming.
Background technology
After late poured band indwelling, construction joint seepy question annoyings unit in charge of construction and operating personnel always, steel plate water-stopping plate is all adopted during the indwelling of post-cast strip typically, when there is subtle flow or sedimentation in xoncrete structure, separate can the binding face between xoncrete structure and steel seal plate, cause late poured band construction joint to seep water;When extension over time, the deformation of adjacent concrete structure construction seam or settling amount are reached to a certain degree, late poured band steel seal plate can be caused to fail, the phenomenon of the serious leak of xoncrete structure.
The content of the invention
In order to overcome the defect of prior art, there is provided a kind of simple structure, the easy to use, waterproof technology of protective good airproof performance, the invention discloses a kind of construction method of late poured band antipriming.
The present invention reaches goal of the invention by following technical solution:
A kind of construction method of late poured band antipriming, is characterized in that:Implement successively as follows:
A. set catch pit:Catch pit is set in the bottom at the post-cast strip position of bed course, catchments or concentrate rubbish to use in the scale removal process before post-cast strip concrete is poured, to clear up;
B. cut sheath:By the indwelling length cutting sheath of post-cast strip, sheath is bonded on rubber water-proof plate;
C. install:Rubber water-proof plate and steel seal plate are installed;
D. pour concrete:Pouring structure concrete, in one rubber water-proof plate steel seal plate with together with of post-cast strip position indwelling when pouring, rubber water-proof plate is retained in the outside of structural concrete construction joint, by the indwelling length cutting sheath of post-cast strip, sheath of the circle more than resistance to deformation hole is wrapped up in during indwelling rubber water-proof plate on the outside of the resistance to deformation hole of rubber water-proof plate, by sheath glue bonding on rubber water-proof plate, sheath is retained in the construction joint position of post-cast strip;
E. clear up post-cast strip:The rubber water-proof plate and steel seal plate that post-cast strip position is cleaned after finishing is poured, the reinforcing bar at post-cast strip position is cleared up;
F. pour post-cast strip concrete.
The construction method of described late poured band antipriming, is characterized in that:Sheath is from the hard polyethylene chloride tube that section is semi-circular shape.
When the present invention is used, when the concrete construction joint of structure deformation occurs or settles, rubber water-proof plate and steel seal plate play waterproof effect simultaneously;When the concrete deformation or settling amount of structure are excessive, after causing the failure of steel seal plate, now rubber water-proof plate continues to play resistance to deformation and waterproof effect under the guard space that sheath is formed, it is ensured that the waterproof seal of post-cast strip concrete construction joint.
The present invention overcomes the seepy question of post-cast strip concrete construction joint by setting up rubber water-proof plate, and sheath can form deformation space when post-cast strip concrete construction joint deforms, and protection rubber water-proof plate is not damaged by structure.
The invention has the beneficial effects as follows:1. technological principle is simple, is easy to operation;2. water resistance is good.
Description of the drawings
Fig. 1 is the structural representation after present invention construction is finished;
Fig. 2 is the structural representation of sheath, rubber water-proof plate and steel seal plate in the present invention.
Specific embodiment
The present invention is further illustrated below by way of specific embodiment.
Embodiment 1
A kind of construction method of late poured band antipriming, implements as follows successively:
A. set catch pit:Catch pit is set in the bottom at 1 position of post-cast strip of bed course 11, catchments or concentrate rubbish to use in the scale removal process before 1 concrete of post-cast strip is poured, to clear up;
B. cut sheath:By the indwelling length cutting sheath 2 of post-cast strip 1, sheath 2 is bonded on rubber water-proof plate 31;
C. install:Rubber water-proof plate 31 and steel seal plate 32 are installed;
D. pour concrete:12 concrete of pouring structure, in 1 position indwelling of post-cast strip, one rubber water-proof plate 31 steel seal plate 32 with together with when pouring, rubber water-proof plate 31 is retained in the outside of 12 concrete construction joint of structure, by the indwelling length cutting sheath 2 of post-cast strip 1, sheath 2 selects the RPVC for cuing open into that section is semi-circular shape(That is Unplasticised Poly Vinyl Chloride, abbreviation UPVC)Pipe, on the outside of the resistance to deformation hole of rubber water-proof plate 31 wraps up in sheath 2 of the circle more than resistance to deformation hole during indwelling rubber water-proof plate 31, uses glue bonding on rubber water-proof plate 31 sheath 2, and sheath 2 is retained in the construction joint position of post-cast strip 1;
E. clear up post-cast strip:The rubber water-proof plate 31 and steel seal plate 32 that 1 position of post-cast strip is cleaned after finishing is poured, the reinforcing bar at 1 position of post-cast strip is cleared up;
F. pour post-cast strip concrete.
The present embodiment is constructed after finishing as depicted in figs. 1 and 2.
When the present embodiment is used, when the concrete construction joint of structure 12 deformation occurs or settles, rubber water-proof plate 31 and steel seal plate 32 play waterproof effect simultaneously;When the concrete deformation or settling amount of structure 12 are excessive, after causing steel seal plate 32 to fail, now rubber water-proof plate 31 under the guard space that sheath 2 is formed continues to play resistance to deformation and waterproof effect, it is ensured that the waterproof seal of 1 concrete construction joint of post-cast strip.

Claims (2)

1. a kind of construction method of late poured band antipriming, is characterized in that:Implement successively as follows:
A. set catch pit:Catch pit is set in the bottom at post-cast strip (1) position of bed course (11), catchments or concentrate rubbish to use in the scale removal process before post-cast strip (1) concrete is poured, to clear up;
B. cut sheath:By indwelling length cutting sheath (2) of post-cast strip (1), sheath (2) is bonded on rubber water-proof plate (31);
C. install:Rubber water-proof plate (31) and steel seal plate (32) are installed;
D. pour concrete:Pouring structure (12) concrete, in one rubber water-proof plate (31) of post-cast strip (1) position indwelling and steel seal plate (32) together when pouring, rubber water-proof plate (31) is retained in the outside of structure (12) concrete construction joint, by indwelling length cutting sheath (2) of post-cast strip (1), sheath (2) of the circle more than resistance to deformation hole is wrapped up in during indwelling rubber water-proof plate (31) on the outside of the resistance to deformation hole of rubber water-proof plate (31), by sheath (2) with glue bonding on rubber water-proof plate (31), sheath (2) is retained in the construction joint position of post-cast strip (1);
E. clear up post-cast strip:The rubber water-proof plate (31) and steel seal plate (32) that post-cast strip (1) position is cleaned after finishing is poured, the reinforcing bar at post-cast strip (1) position is cleared up;
F. pour post-cast strip concrete.
2. the construction method of late poured band antipriming as claimed in claim 1, is characterized in that:Sheath (2) is from the hard polyethylene chloride tube that section is semi-circular shape.
CN201510610245.0A 2015-09-23 2015-09-23 The construction method of late poured band antipriming Pending CN106545035A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510610245.0A CN106545035A (en) 2015-09-23 2015-09-23 The construction method of late poured band antipriming

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510610245.0A CN106545035A (en) 2015-09-23 2015-09-23 The construction method of late poured band antipriming

Publications (1)

Publication Number Publication Date
CN106545035A true CN106545035A (en) 2017-03-29

Family

ID=58365112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510610245.0A Pending CN106545035A (en) 2015-09-23 2015-09-23 The construction method of late poured band antipriming

Country Status (1)

Country Link
CN (1) CN106545035A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960771A (en) * 2022-06-27 2022-08-30 中国十九冶集团有限公司 Waterproof construction method for construction joint

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4041665A (en) * 1975-11-22 1977-08-16 Vredestein N.V. Injection sealable waterstop and method of installing same
CN2446192Y (en) * 2000-09-27 2001-09-05 全日升工程有限公司 Protective structure of waterstop
CN202500159U (en) * 2012-03-21 2012-10-24 叶小钗 Waterproof structure for post-cast strip of concrete floor

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4041665A (en) * 1975-11-22 1977-08-16 Vredestein N.V. Injection sealable waterstop and method of installing same
CN2446192Y (en) * 2000-09-27 2001-09-05 全日升工程有限公司 Protective structure of waterstop
CN202500159U (en) * 2012-03-21 2012-10-24 叶小钗 Waterproof structure for post-cast strip of concrete floor

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
万绍联: "浅谈混凝土结构后浇带施工方法", 《科技资讯》 *
张强: "衢州时代广场地下室后浇带的施工实例", 《浙江建筑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960771A (en) * 2022-06-27 2022-08-30 中国十九冶集团有限公司 Waterproof construction method for construction joint

Similar Documents

Publication Publication Date Title
CN204000956U (en) A kind of basement bottom plate rear pouring tape structure
CN204552818U (en) The drainage system of ditch, side, anti-tunnel bottom leaky
CN107326868A (en) A kind of large reservoir concrete dam body fracture plugging method
CN207193996U (en) A kind of precipitation pipe well well-sealing device
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN104929143A (en) Well sealing method of dewatering well at bottom of foundation pit
CN104846849B (en) A kind of method for preventing basement bottom plate rear pouring tape seepage
CN103362542A (en) Sectionalized hole sealing method for bedding gas extraction drilled holes
CN106761919A (en) A kind of high pressure water enrichment tunnel automatic Regulation sluicing control device
CN105696522B (en) Grouting gallery permanent expansion joint water seepage treatment method
CN109139059A (en) A kind of osmotic grouting suitable for shield tunnel integrates stick and construction method
CN106988440A (en) A kind of waterproof construction and its construction method at subway station main body and accessory interface
CN103821114B (en) A kind of reservoir culvert method for blocking discarded under seepage pressure effect
CN205917593U (en) Bridge expansion joint drainage device
CN106545035A (en) The construction method of late poured band antipriming
CN110359470B (en) Corrugated pipe intercepting ditch construction process
CN202073148U (en) Novel anti-seepage floor drain system
CN207144967U (en) A kind of tunnel side wall waterproof structure for deformation seams
CN203334285U (en) Underground concrete structure engineering seam waterproof preparation grouting system
CN206616711U (en) A kind of waterproof construction at subway station main body and accessory interface
CN204023592U (en) The advanced quick blocking structure of a kind of foundation ditch drainage well
CN209603277U (en) Basement waterproof structure
CN209703677U (en) Replacement of not cutting off the water supply passes in and out the device of sluice gate
CN206956791U (en) A kind of new-old concrete interface waterproof sealing structure
WO2019237908A1 (en) Blocking and drainage combined treatment method for water leakage at construction joint of secondary lining of tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170329