[go: up one dir, main page]

CN106451200A - London tower bridge type non-powercut spanning system and spanning method of power transmission line - Google Patents

London tower bridge type non-powercut spanning system and spanning method of power transmission line Download PDF

Info

Publication number
CN106451200A
CN106451200A CN201610503552.3A CN201610503552A CN106451200A CN 106451200 A CN106451200 A CN 106451200A CN 201610503552 A CN201610503552 A CN 201610503552A CN 106451200 A CN106451200 A CN 106451200A
Authority
CN
China
Prior art keywords
supporting rack
line
spanning
ground
line supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610503552.3A
Other languages
Chinese (zh)
Inventor
丁小蔚
陈飞
龚坚刚
卞荣
刘燕平
徐世泽
周文俊
章李刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610503552.3A priority Critical patent/CN106451200A/en
Publication of CN106451200A publication Critical patent/CN106451200A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Electric Cable Installation (AREA)

Abstract

一种伦敦塔桥式输电线路不停电跨越系统及跨越方法,所述的系统主要由位于被跨线路一侧的跨越架和另一侧座地液压提升抱杆组成,跨越塔架的中部通过一辅助横担铰接有一副可上下摆动的铝合金抱杆,在该铝合金抱杆上安装有多排托线杆并组成一朝向被跨线路一侧平置的组合托线架;座地液压提升抱杆的中部也通过一辅助横担铰接有一副可上下摆动的铝合金抱杆。

A tower bridge type power transmission line spanning system without power failure and a spanning method. The system is mainly composed of a spanning frame on one side of the spanned line and a hydraulic lifting pole on the other side. The middle part of the spanning tower passes through a The auxiliary cross arm is hinged with a pair of aluminum alloy holding rods that can swing up and down. Multiple rows of wire supporting rods are installed on the aluminum alloy holding rods to form a combined wire supporting frame that is placed flat on the side of the crossed line; the ground is hydraulically lifted The middle part of the holding pole is also hinged with a pair of aluminum alloy holding poles that can swing up and down through an auxiliary cross arm.

Description

一种伦敦塔桥式不停电输电线路跨越系统及跨越方法A tower bridge type non-stop power transmission line spanning system and spanning method

技术领域technical field

本发明涉及的是一种伦敦塔桥式输电线路不停电跨越系统及跨越方法,属于输电线路施工技术领域。The invention relates to a system and method for crossing a Tower Bridge type power transmission line without power failure, and belongs to the technical field of power transmission line construction.

背景技术Background technique

目前,输电线路跨越施工采用搭设跨越架、临时停电封网等传统方法,这些方法对人力、财力及工器具的投入较大,效率低,经济效益差,危险因素较多。随着国民经济的高速发展,传统的停电施工跨越方式已经无法满足优质可靠供电的需求,特别是针对供电可靠性要求高低跨越线路。At present, traditional methods such as setting up spanning frames and sealing the network during temporary power outages are used in the spanning construction of transmission lines. These methods require a large investment in manpower, financial resources, and tools, with low efficiency, poor economic benefits, and many risk factors. With the rapid development of the national economy, the traditional power outage construction spanning method has been unable to meet the demand for high-quality and reliable power supply, especially for high and low crossing lines that require power supply reliability.

随着全国电网的大力发展,高压线路越来越多,新建线路的跨越越来越复杂,供电的安全性、可靠性要求越来越高,线路停电难度越来越大;若新建线路时对被跨线路进行停电施工将会极大地影响供电的可靠性,也将给用户带来重大损失。With the vigorous development of the national power grid, there are more and more high-voltage lines, and the spanning of new lines is becoming more and more complicated. The power outage construction carried out across the line will greatly affect the reliability of power supply, and will also bring heavy losses to users.

发明内容Contents of the invention

本发明的目的在于克服现有技术存在的不足,而提供一种结构简单,使用可靠,能节省大量时间和费用,施工效率高且安全性好的伦敦塔桥式输电线路不停电跨越系统及跨越方法。The purpose of the present invention is to overcome the deficiencies in the prior art, and provide a simple structure, reliable use, can save a lot of time and cost, high construction efficiency and good safety London Tower Bridge type transmission line non-stop across the system and span method.

为实现上述目的,本发明采用了以下技术方案:一种伦敦塔桥式输电线路不停电跨越系统,它主要由位于被跨线路一侧的跨越架和另一侧座地液压提升抱杆组成,其特征在于所述跨越塔架的中部通过一辅助横担铰接有一副可上下摆动的铝合金抱杆,在该铝合金抱杆上安装有多排托线杆并组成一朝向被跨线路一侧平置的组合托线架;In order to achieve the above object, the present invention adopts the following technical solutions: a London Tower Bridge type power transmission line spanning system without power failure, which is mainly composed of a spanning frame on one side of the spanned line and a hydraulic lifting pole on the other side. It is characterized in that the middle part of the spanning tower is hinged with a pair of aluminum alloy holding poles that can swing up and down through an auxiliary cross arm, and multiple rows of wire support poles are installed on the aluminum alloy holding poles to form a bridge facing the side of the spanned line. Horizontal combined wire support frame;

所述座地液压提升抱杆的中部也通过一辅助横担铰接有一副可上下摆动的铝合金抱杆,在该铝合金抱杆上安装有多排托线杆并组成一朝向被跨线路一侧平置的组合托线架;The middle part of the ground hydraulic lifting pole is also hinged with a pair of aluminum alloy poles that can swing up and down through an auxiliary cross arm. Multiple rows of wire support poles are installed on the aluminum alloy poles and form a direction towards the crossed line. Combined wire support frame placed horizontally on the side;

在被跨线路两侧的组合托线架之间通过导引绳的牵引、安装有经展放后的导线。Between the combined wire support racks on both sides of the crossed line, the wire after being deployed is installed through the traction of the guide rope.

作为优选:所述跨越塔架上的组合托线架前端通过一起吊线经过安装在一根起吊抱杆上端部滑轮后反向固定连接于另一侧的地面上,并在组合托线架的两侧分别通过一根浪风绳固定在跨越塔架上端部;As a preference: the front end of the combined wire support frame on the spanning tower is reversely fixedly connected to the ground on the other side through a suspension wire through a pulley installed on the upper end of a lifting pole, and the two sides of the combined wire support frame The sides are respectively fixed on the upper end of the spanning tower by a wave and wind rope;

所述座地液压提升抱杆上的组合托线架前端也通过一起吊线经过安装在座地液压提升抱杆上端部滑轮后反向固定连接于另一侧的地面上,并在组合托线架的两侧分别通过一根稳定浪风绳固定在座地液压提升抱杆上段部。The front end of the combined wire support frame on the ground hydraulic lifting pole is also reversely fixedly connected to the ground on the other side through a suspension wire through a pulley installed on the upper end of the ground hydraulic lifting pole, and on the combined wire support frame. The two sides are respectively fixed to the upper part of the ground hydraulic lifting pole through a stable wave and wind rope.

一种利用所述的伦敦塔桥式输电线路不停电跨越系统进行输电线路不停电跨越方法,该方法是:在被跨线路两侧的组合托线架前端部设置有滑车,用导引绳绕过组合托线架前端部顶的滑车后,连接重力沙袋,在两侧组合托线架从上慢慢向下倒落后,两侧组合托线架上由导引绳连接的重力沙袋滑落至地面,再由人工将重力沙袋解开,将两侧的导引绳连接为一体后,至少从一侧收紧并提升导引绳,完成导引绳展放;导引绳展放后,再用导引绳尾端牵引导线通过悬吊平置的组合托线架来完成导线展放。A method for crossing a power transmission line without a power failure using the London Tower Bridge type power transmission line crossing system without a power failure. After passing the pulley at the top of the front end of the combined wire support frame, connect the gravity sandbag, and after the combined wire support frame on both sides slowly falls from top to bottom, the gravity sandbags connected by the guide rope on the combined wire support frame on both sides slide to the ground , and then manually untie the gravity sandbags, connect the guide ropes on both sides as a whole, tighten and lift the guide ropes from at least one side, and complete the deployment of the guide ropes; after the guide ropes are deployed, use The tail end of the guide rope pulls the conductor through the suspended horizontal combined wire support frame to complete the conductor deployment.

作为优选:所述的组合托线架先在地面组装完成,然后由小抱杆或其它起吊机构进行垂直起吊,当组合托线架至少升至跨越塔架和座地液压提升抱杆中部位置时,用两根浪风绳固定连接并稳定组合托线架以防止其左右摆动;当组合托线架升至辅助横担处时,组合托线架的底部与跨越塔架或座地液压提升抱杆上的辅助横担铰接;待两侧组合托线架慢慢倒落并平置后,各自端部下接的重力沙袋便会随之滑落至地面。As a preference: the combined wire support frame is assembled on the ground first, and then vertically lifted by a small pole or other lifting mechanism, when the combined wire support frame is at least raised to the middle position of the hydraulic lifting pole spanning the tower and the ground seat , use two wave and wind ropes to fix the connection and stabilize the combined wire support frame to prevent it from swinging left and right; The auxiliary cross arm on the pole is hinged; after the combined wire support racks on both sides slowly fall down and lie flat, the gravity sandbags connected to each end will slide down to the ground accordingly.

以往架线施工时,一般要求2回220kV线路同时停电,待导线架设完毕后恢复送电;由于该两回线路向同一个变电站送电,若同时停电将对一侧变电站的可靠供电产生较大影响;为了避免架线施工时被跨的两回线路同时停电,本发明考虑在220kV线路附近分别设置跨越塔架,并在跨越塔架上悬吊组合托线架的形式,实现全过程零停电封网跨越架线;本发明具有结构简单,使用可靠,能节省大量时间和费用,施工效率高且安全性好等特点。In the past, during wire erection construction, it was generally required that the two circuits of 220kV lines were cut off at the same time, and the power transmission was resumed after the wire erection was completed; since the two circuits sent power to the same substation, a simultaneous power failure would have a great impact on the reliable power supply of one side of the substation. Influence; in order to avoid simultaneous power outages of the two spanned lines during the wiring construction, the present invention considers setting spanning towers near the 220kV line respectively, and suspending the form of the combined support line frame on the spanning towers to realize zero power failure in the whole process The network is sealed across the wire; the invention has the characteristics of simple structure, reliable use, can save a lot of time and cost, high construction efficiency and good safety.

附图说明Description of drawings

图1是本发明的结构示意图。Fig. 1 is a structural schematic diagram of the present invention.

图2是本发明所述的跨越塔架正面结构示意图。Fig. 2 is a schematic diagram of the front structure of the spanning tower according to the present invention.

图3是本发明所述输电线路不停电跨越示意图。Fig. 3 is a schematic diagram of crossing without interruption of power transmission line according to the present invention.

具体实施方式detailed description

下面将结合附图对本发明作详细的介绍:图1所示,本发明所述的一种伦敦塔桥式输电线路不停电跨越系统,它主要由位于被跨线路一侧的跨越塔架1和另一侧座地液压提升抱杆2组成,所述跨越塔架1的中部通过一辅助横担3铰接有一副可上下摆动的铝合金抱杆4,在该铝合金抱杆4上安装有多排托线杆5并组成一朝向被跨线路6一侧平置的组合托线架7,见图2所示;The present invention will be described in detail below in conjunction with accompanying drawing: As shown in Fig. 1, a kind of London Tower Bridge type power transmission line of the present invention is crossed without interruption system, and it is mainly by being positioned at crossing tower 1 and spanning one side of crossed line The other side is composed of a hydraulic lifting pole 2, and the middle part of the spanning tower 1 is hinged to a pair of aluminum alloy poles 4 that can swing up and down through an auxiliary cross arm 3. Arrange the wire support rods 5 and form a combined wire support rack 7 that is placed horizontally towards the side of the crossed line 6, as shown in Figure 2;

本发明所述座地液压提升抱杆2的中部也通过一辅助横担3铰接有一副可上下摆动的铝合金抱杆4,在该铝合金抱杆4上安装有多排托线杆5并组成一朝向被跨线路6一侧平置的组合托线架7;也即本实施例所述的左右两侧的组合托线架7的结构相同。The middle part of the ground hydraulic lifting holding pole 2 of the present invention is also hinged with a pair of aluminum alloy holding poles 4 that can swing up and down through an auxiliary cross arm 3, and multiple rows of wire support poles 5 are installed on the aluminum alloy holding poles 4. A combined wire support frame 7 that is horizontally placed towards the side of the crossed line 6 is formed; that is, the structures of the combined wire support frames 7 on the left and right sides described in this embodiment are the same.

在被跨线路6两侧的组合托线架7之间通过导引绳8的牵引、安装有经展放后的导线。Between the combined wire holders 7 on both sides of the crossed line 6, the wires after deployment are installed through the traction of the guide rope 8.

图中所示,本发明所述跨越塔架1上的组合托线架7前端通过一起吊线9经过安装在一根起吊抱杆10上端部滑轮后反向固定连接于另一侧的地面上,并在组合托线架7的两侧分别通过一根浪风绳11固定在跨越塔架1上端部;As shown in the figure, the front end of the combined wire support frame 7 spanning the tower 1 of the present invention is reversely and fixedly connected to the ground on the other side through a suspension wire 9 after being installed on a pulley at the upper end of a lifting pole 10. And on both sides of the combined wire support frame 7, they are respectively fixed on the upper end of the spanning tower 1 by a wave and wind rope 11;

所述座地液压提升抱杆2上的组合托线架7前端也通过一起吊线9经过安装在座地液压提升抱杆2上端部滑轮后反向固定连接于另一侧的地面上,并在组合托线架7的两侧分别通过一根稳定浪风绳11固定在座地液压提升抱杆2上段部。The front end of the combined wire support frame 7 on the ground hydraulic lifting pole 2 is also reversely fixedly connected to the ground on the other side through a suspension wire 9 after passing through the pulley at the upper end of the ground hydraulic lifting pole 2. Both sides of the wire support frame 7 are respectively fixed on the upper part of the seat hydraulically lifting the pole 2 by a stable wave and wind rope 11.

图3所示,一种利用所述伦敦塔桥式输电线路不停电跨越系统进行输电线路不停电跨越方法,该方法是:在被跨线路6两侧的组合托线架7前端部设置有滑车,用导引绳8绕过组合托线架7前端部顶的滑车后,连接一重力沙袋12,在两侧组合托线架7从上慢慢向下倒落后,两侧组合托线架7上由导引绳8连接的重力沙袋12滑落至地面,再由人工将重力沙袋12解开,将两侧的导引绳8连接为一体后,至少从一侧收紧并提升导引绳8,完成导引绳展放;导引绳8展放后,再用导引绳8尾端牵引导线通过悬吊平置的组合托线架7来完成导线展放,见图1所示。As shown in Fig. 3, a method for crossing a power transmission line without a power failure using the Tower Bridge type power transmission line crossing system without a power failure, the method is: a pulley is arranged at the front end of the combined support frame 7 on both sides of the crossed line 6 After bypassing the pulley at the front end of the combination wire support frame 7 with the guide rope 8, a gravity sandbag 12 is connected, and after the combination wire support frame 7 on both sides falls slowly from top to bottom, the combination wire support frame 7 on both sides The gravity sandbag 12 connected by the guide rope 8 slides to the ground, and then the gravity sandbag 12 is untied manually, and after the guide rope 8 on both sides is connected as one, tighten and lift the guide rope 8 at least from one side. , to complete the deployment of the guide rope; after the deployment of the guide rope 8, use the tail end of the guide rope 8 to pull the wire through the suspended and flat combined wire support frame 7 to complete the deployment of the wire, as shown in Figure 1.

本发明所述的组合托线架7先在地面组装完成,然后由小抱杆或其它起吊机构进行垂直起吊,当组合托线架7至少升至跨越塔架1和座地液压提升抱杆2中部位置时,用两根浪风绳11固定连接并稳定组合托线架7以防止其左右摆动;当组合托线架7升至辅助横担3处时,组合托线架7的底部与跨越塔架1或座地液压提升抱杆2上的辅助横担3铰接;待两侧组合托线架7慢慢倒落并平置后,各自端部下接的重力沙袋12便会随之滑落至地面。The combined wire support frame 7 described in the present invention is firstly assembled on the ground, and then vertically lifted by a small pole or other lifting mechanism. In the middle position, use two waves and wind ropes 11 to connect and stabilize the combined wire support frame 7 to prevent it from swinging left and right; The auxiliary cross-arm 3 on the tower 1 or the ground-seat hydraulic lifting pole 2 is hinged; after the combined support frame 7 on both sides slowly falls down and is placed flat, the gravity sandbags 12 connected to the respective ends will slide down to the ground.

实施例:本发明利用靠近被跨线路的跨越塔(或者就近临时组立的自立式塔架)上悬吊铝合金抱杆,倒落后形成组合托线架。Embodiment: The present invention utilizes an aluminum alloy pole to be suspended on a spanning tower (or a temporary self-supporting tower erected nearby) close to the spanned line, and then falls to form a combined wire support frame.

图1、2所示,伦敦塔桥式跨越架由一副铝合金抱杆上安装多排托线架组成,组合托线架在地面组装完成,由小抱杆起吊。托线架顶部设置滑车,用牵引绳绕过架顶滑车连接重力沙袋。托线架升至地线顶架时,用2根浪风绳稳定托架左右摆动。托线架升至临时辅助横担处时,底部与塔上的临时辅助横担铰接。由于另一基跨越塔距离被跨线路较远,不能被直接利用作悬吊托线架。故考虑在另一回被跨线的外侧,采用座地液压提升抱杆替代跨越塔悬吊托线架。托线架顶部同样设置滑车,用牵引绳绕过架顶滑车连接重力沙袋。待两侧托线架慢慢倒落后,将两侧的重力沙袋滑落至地面,再由人工将重力沙袋解开,将两侧的导引绳连接为一体后,收紧提升导引绳,完成导引绳展放。导引绳展放后,再用导引绳尾端牵引导线通过悬吊的托线架来完成导线展放。As shown in Figures 1 and 2, the London Tower Bridge spanning frame is composed of a pair of aluminum alloy poles with multiple rows of wire support frames. The combined wire support frames are assembled on the ground and lifted by small poles. A pulley is set on the top of the wire support frame, and a pull rope is used to bypass the top block of the frame to connect the gravity sandbag. When the wire support frame rises to the top frame of the ground wire, use 2 waves and wind ropes to stabilize the bracket from swinging left and right. When the wire support frame rises to the temporary auxiliary cross arm, the bottom is hinged with the temporary auxiliary cross arm on the tower. Since the other base spanning tower is far away from the spanned line, it cannot be directly used as a suspension wire rack. Therefore, it is considered to use ground-mounted hydraulic lifting poles to replace the spanning tower suspension wire support on the outside of the other crossed line. A pulley is also set on the top of the wire support frame, and a pull rope is used to bypass the top block of the frame to connect the gravity sandbag. After the wire support racks on both sides slowly fall down, slide the gravity sandbags on both sides to the ground, then untie the gravity sandbags manually, connect the guide ropes on both sides as a whole, tighten and lift the guide ropes, and complete The guide rope is deployed. After the guide rope is deployed, use the tail end of the guide rope to pull the wire through the suspended wire holder to complete the wire deployment.

由于另一基跨越塔距离被跨线路较远,不能被直接利用作悬吊托线架。故考虑在另一回被跨线的外侧,采用座地液压提升抱杆替代跨越塔悬吊托线架。托线架顶部同样设置滑车,用牵引绳绕过架顶滑车连接重力沙袋。待两侧托线架慢慢倒落后,将两侧的重力沙袋滑落至地面,再由人工将重力沙袋解开,将两侧的导引绳连接为一体后,收紧提升导引绳,完成导引绳展放。导引绳展放后,再用导引绳尾端牵引导线通过悬吊的托线架来完成导线展放。Since the other base spanning tower is far away from the spanned line, it cannot be directly used as a suspension wire rack. Therefore, it is considered to use ground-mounted hydraulic lifting poles to replace the spanning tower suspension wire support frame on the outside of the line being spanned in another round. A pulley is also set on the top of the wire support frame, and the gravity sandbag is connected to the pulley on the top of the frame with a traction rope. After the wire support racks on both sides slowly fall down, slide the gravity sandbags on both sides to the ground, then untie the gravity sandbags manually, connect the guide ropes on both sides as a whole, tighten and lift the guide ropes, and complete The guide rope is deployed. After the guide rope is deployed, use the tail end of the guide rope to pull the wire through the suspended wire holder to complete the wire deployment.

本发明采用伦敦塔桥式不停电跨越系统展放导线,充分利用跨越塔和现有的架线施工机具,节省大量搭设常规跨越架、封网架的时间和费用,架线完毕后可全部回收跨越设备,提高跨越带电线路施工效率约20%。The invention adopts the London Tower Bridge type non-stop spanning system to spread out the wires, makes full use of the spanning tower and the existing construction equipment for stringing, saves a lot of time and cost for setting up conventional spanning frames and grid sealing frames, and can be completely recycled after the stringing is completed Spanning equipment, improving the construction efficiency of crossing live lines by about 20%.

Claims (4)

1. a kind of Tower of London bridge-type transmission line of electricity does not have a power failure leap system, it mainly by being located at by the crossing frame of cross-line road side and Opposite side seat ground hydraulic pressure lift pole composition is it is characterised in that the described middle part crossing over pylon is hinged with one by an auxiliary cross-arm The aluminium alloy pole that pair can swing up and down, is provided with many evacuating pus and expelling toxin line bar on this aluminium alloy pole and forms one towards by cross-line road The combination line supporting rack of side horizontal;
The middle part of described seat ground hydraulic pressure lift pole is hinged with, also by an auxiliary cross-arm, the aluminum alloy holding that a pair can swing up and down Bar, is provided with many evacuating pus and expelling toxin line bar on this aluminium alloy pole and forms one towards by the combination line supporting rack of cross-line road side horizontal;
By the traction of guide rope between the combination line supporting rack by cross-line road both sides, the wire after unfolding is installed.
2. Tower of London bridge-type transmission line of electricity according to claim 1 does not have a power failure leap system it is characterised in that described leap Combination line supporting rack front end on pylon is reversely fixed after being arranged on a lifting pole upper end pulley by messenger wire together It is connected on the ground of opposite side, and respectively leap pylon upper end is fixed on by a unrestrained wind rope in the both sides of combination line supporting rack Portion;
Combination line supporting rack front end on described seat ground hydraulic pressure lift pole carries through installing present ground hydraulic pressure also by messenger wire together Reversely it is fixedly connected on the ground of opposite side after rising pole upper end pulley, and pass through one respectively in the both sides of combination line supporting rack Root stable wave wind rope fixing present ground hydraulic pressure lift pole epimere portion.
3. a kind of carry out transmission line of electricity using the leap system that do not have a power failure of the Tower of London bridge-type transmission line of electricity described in claim 1 or 2 Do not have a power failure crossing construction method it is characterised in that the method is:Arrange in the combination line supporting rack leading section by cross-line road both sides Have coaster, with guide rope bypass combination line supporting rack leading section top coaster after, connect gravity sandbag, both sides combination line supporting rack from On slowly fall downwards after, the gravity sandbag landing that connected by guide rope is combined on line supporting rack to ground in both sides, then by manually Gravity sandbag is untied, and after the guide rope of both sides is connected as one, at least tightens up from side and lifts guide rope, complete guide rope Unfolding;After guide rope unfolding, then complete wire exhibition with guide rope tail end traction wire by suspending the combination line supporting rack of horizontal in midair Put.
4. Tower of London bridge-type transmission line of electricity according to claim 3 do not have a power failure leap system carry out transmission line of electricity do not have a power failure across The method more constructed is it is characterised in that described combination line supporting rack elder generation is completed on ground, then by little pole or other Loop wheel machine structure carries out vertical lifting, when combining line supporting rack with least rising to leap pylon and seat hydraulic pressure lift pole medium position, It is fixedly connected with two unrestrained wind ropes and stably combine line supporting rack to prevent from swinging around;When combination line supporting rack rises to auxiliary cross-arm During place, the bottom of combination line supporting rack is hinged with the auxiliary cross-arm crossed on pylon or seat ground hydraulic pressure lift pole;Treat that both sides are combined Line supporting rack slowly fall and horizontal after, the gravity sandbag that connects under respective end will therewith landing to ground.
CN201610503552.3A 2016-07-01 2016-07-01 London tower bridge type non-powercut spanning system and spanning method of power transmission line Pending CN106451200A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610503552.3A CN106451200A (en) 2016-07-01 2016-07-01 London tower bridge type non-powercut spanning system and spanning method of power transmission line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610503552.3A CN106451200A (en) 2016-07-01 2016-07-01 London tower bridge type non-powercut spanning system and spanning method of power transmission line

Publications (1)

Publication Number Publication Date
CN106451200A true CN106451200A (en) 2017-02-22

Family

ID=58183321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610503552.3A Pending CN106451200A (en) 2016-07-01 2016-07-01 London tower bridge type non-powercut spanning system and spanning method of power transmission line

Country Status (1)

Country Link
CN (1) CN106451200A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158936A (en) * 2019-05-23 2019-08-23 国家电网有限公司 A kind of shared steel tower communication antenna inspection platform of folding power communication
CN111864635A (en) * 2020-07-24 2020-10-30 天津送变电工程有限公司 Multi-roller combined spanning device
CN117526156A (en) * 2023-10-30 2024-02-06 国网四川省电力公司自贡供电公司 Crossing construction platform for power transmission line and installation method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1216117A (en) * 1996-04-12 1999-05-05 西门子公司 Process and device for mounting optical cable on aerial line
CN101847844A (en) * 2010-05-14 2010-09-29 何姗姗 Intelligent spanning frame with uninterrupted operation
CN102082400A (en) * 2009-12-01 2011-06-01 河南省电力公司南阳供电公司 Simple line spanning frame
JP2013176263A (en) * 2012-02-27 2013-09-05 Toshiba Corp Cable laying system, laying method, and laying tool
CN203813323U (en) * 2014-04-29 2014-09-03 国家电网公司 Folding support frame for power line spanning frame
CN105226560A (en) * 2015-10-21 2016-01-06 三一汽车起重机械有限公司 A kind of crossing frame and construction method thereof
CN205123121U (en) * 2015-11-24 2016-03-30 国家电网公司 Action bars is strideed across to electric wire
CN105470862A (en) * 2015-12-30 2016-04-06 国网山西供电工程承装公司 Span construction equipment of high-speed rail under operation
CN105529648A (en) * 2016-01-18 2016-04-27 国家电网公司 Hydraulic fabricated crossing structure
CN205985947U (en) * 2016-07-01 2017-02-22 浙江浙电经济技术研究院 Tower of london bridge type transmission line leap system that does not have a power failure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1216117A (en) * 1996-04-12 1999-05-05 西门子公司 Process and device for mounting optical cable on aerial line
CN102082400A (en) * 2009-12-01 2011-06-01 河南省电力公司南阳供电公司 Simple line spanning frame
CN101847844A (en) * 2010-05-14 2010-09-29 何姗姗 Intelligent spanning frame with uninterrupted operation
JP2013176263A (en) * 2012-02-27 2013-09-05 Toshiba Corp Cable laying system, laying method, and laying tool
CN203813323U (en) * 2014-04-29 2014-09-03 国家电网公司 Folding support frame for power line spanning frame
CN105226560A (en) * 2015-10-21 2016-01-06 三一汽车起重机械有限公司 A kind of crossing frame and construction method thereof
CN205123121U (en) * 2015-11-24 2016-03-30 国家电网公司 Action bars is strideed across to electric wire
CN105470862A (en) * 2015-12-30 2016-04-06 国网山西供电工程承装公司 Span construction equipment of high-speed rail under operation
CN105529648A (en) * 2016-01-18 2016-04-27 国家电网公司 Hydraulic fabricated crossing structure
CN205985947U (en) * 2016-07-01 2017-02-22 浙江浙电经济技术研究院 Tower of london bridge type transmission line leap system that does not have a power failure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
董春利: "《建筑智能化系统工程设计手册》", 31 March 2012 *
铁道部第三工程局: "《铁路桥架机架梁手册》", 31 March 2000 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158936A (en) * 2019-05-23 2019-08-23 国家电网有限公司 A kind of shared steel tower communication antenna inspection platform of folding power communication
CN111864635A (en) * 2020-07-24 2020-10-30 天津送变电工程有限公司 Multi-roller combined spanning device
CN117526156A (en) * 2023-10-30 2024-02-06 国网四川省电力公司自贡供电公司 Crossing construction platform for power transmission line and installation method

Similar Documents

Publication Publication Date Title
CN205985947U (en) Tower of london bridge type transmission line leap system that does not have a power failure
CN101582572B (en) Method of extra-high voltage tension stringing
CN204386221U (en) A kind of three layers of association type outlet framework for the outdoor GIS transformer station of 220kV
CN106451200A (en) London tower bridge type non-powercut spanning system and spanning method of power transmission line
CN107834434A (en) Crossing method for the construction of transmission line of electricity tension stringing
CN104577875A (en) Construction method of block crossover frame cable of power circuit
CN203352051U (en) Insulation protective umbrella
CN106099757A (en) A kind of transmission line insulator crosses over crane span structure and construction technology thereof
CN106368495B (en) One kind is novel to wear straight line narrow base tower
CN106207885B (en) The short circuit fixture and method of charged for replacement 220kV pipe bus telescoping wire clamps
CN206060035U (en) A kind of releasing pulley hanger
CN205577567U (en) Two return circuits double T connects steel pipe pole
CN103311844A (en) Method for erecting mountainous-terrain cross charged high-voltage lines
CN201438396U (en) A double I-type and V-type tension insulator string for UHV substation
CN204407790U (en) A kind of insulation gin pole for getting out wire jumper
CN103532042A (en) Portable simple crossing frame for power distribution network
CN106532557B (en) Across 10KV line construction platform tools devices
CN205646634U (en) Device is strideed across with highway to electric wire netting construction
CN107346873A (en) A kind of New insulated crossing frame
CN205000711U (en) Style of calligraphy horizontal arrangement strain insulator tower is done in 220kV single loop heavy ice district
CN206908250U (en) A kind of power transmission and transformation line apparatus for fixing cord
CN206091530U (en) Big leap iron tower of single loop
CN202633869U (en) Wind deviation prevention structure of phase drainage wire in 110 kV line YJ-shaped iron tower
CN106129898B (en) One kind changes ground wire and crosses over servicing unit
CN214659238U (en) Novel 110kV single-loop T connects tower

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170222

RJ01 Rejection of invention patent application after publication