CN106437876B - A kind of cogeneration units depth peak regulation system and its operation method - Google Patents
A kind of cogeneration units depth peak regulation system and its operation method Download PDFInfo
- Publication number
- CN106437876B CN106437876B CN201610738334.8A CN201610738334A CN106437876B CN 106437876 B CN106437876 B CN 106437876B CN 201610738334 A CN201610738334 A CN 201610738334A CN 106437876 B CN106437876 B CN 106437876B
- Authority
- CN
- China
- Prior art keywords
- heat
- steam
- valve
- peak regulation
- regenerative apparatus
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000033228 biological regulation Effects 0.000 title claims abstract description 55
- 238000000034 method Methods 0.000 title claims abstract description 27
- 230000001172 regenerating effect Effects 0.000 claims abstract description 46
- 230000005540 biological transmission Effects 0.000 claims abstract description 23
- 238000001816 cooling Methods 0.000 claims abstract description 18
- 238000000605 extraction Methods 0.000 claims abstract description 16
- 230000003247 decreasing effect Effects 0.000 claims description 17
- 238000010438 heat treatment Methods 0.000 claims description 16
- 238000009825 accumulation Methods 0.000 claims description 14
- 230000005619 thermoelectricity Effects 0.000 claims description 13
- 238000001704 evaporation Methods 0.000 claims description 6
- 230000008020 evaporation Effects 0.000 claims description 6
- 230000007423 decrease Effects 0.000 claims description 5
- 238000003303 reheating Methods 0.000 claims description 4
- 238000005516 engineering process Methods 0.000 abstract description 2
- 238000010276 construction Methods 0.000 description 2
- 238000009510 drug design Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000005611 electricity Effects 0.000 description 2
- 230000012447 hatching Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 238000007639 printing Methods 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F01—MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
- F01D—NON-POSITIVE DISPLACEMENT MACHINES OR ENGINES, e.g. STEAM TURBINES
- F01D17/00—Regulating or controlling by varying flow
- F01D17/10—Final actuators
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F01—MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
- F01D—NON-POSITIVE DISPLACEMENT MACHINES OR ENGINES, e.g. STEAM TURBINES
- F01D15/00—Adaptations of machines or engines for special use; Combinations of engines with devices driven thereby
- F01D15/10—Adaptations for driving, or combinations with, electric generators
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F01—MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
- F01K—STEAM ENGINE PLANTS; STEAM ACCUMULATORS; ENGINE PLANTS NOT OTHERWISE PROVIDED FOR; ENGINES USING SPECIAL WORKING FLUIDS OR CYCLES
- F01K11/00—Plants characterised by the engines being structurally combined with boilers or condensers
- F01K11/02—Plants characterised by the engines being structurally combined with boilers or condensers the engines being turbines
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D11/00—Central heating systems using heat accumulated in storage masses
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Control Of Eletrric Generators (AREA)
- Control Of Steam Boilers And Waste-Gas Boilers (AREA)
Abstract
The present invention relates to a kind of cogeneration units depth peak regulation system and its operation method.At present also without the effective technology for carrying out fired power generating unit power peak regulation.The present invention includes boiler, steam turbine, generator, heat exchange station, heat user, heat supply extraction steam pipe and heat supply pipeline, steam turbine and connected with generator, and heat exchange station is connected by heat supply pipeline with heat user, is characterized in:Also include heat transmission equipment, regenerative apparatus, main steam pipe, reheated steam pipe and reducing-and-cooling plant, boiler connects with main steam pipe, main steam pipe is divided into two branch roads and is connected respectively with steam turbine and reducing-and-cooling plant, steam turbine connects with reheated steam pipe, reheated steam pipe is divided into two branch roads and is connected respectively with boiler and reducing-and-cooling plant, reducing-and-cooling plant, heat transmission equipment and regenerative apparatus are sequentially connected by pipeline, and regenerative apparatus is connected by pipeline with heat supply pipeline.Reasonable in design, the dependable performance of the present invention, is advantageously implemented unit power peak regulation and thermic load peak load shifting.
Description
Technical field
The invention belongs to heat supply thermal power plant accumulation of heat peak regulation technique field, and in particular to a kind of cogeneration units depth peak regulation
System and its operation method, it is particularly suitable for use in and carries out the thermal power plant of heat supply and peak load regulation network.
Background technology
At present, China's policy gradually payes attention to the popularization of new energy, reduces the ratio of fired power generating unit.Ended for the end of the year 2012, I
The existing 44.8GW of state installed capacity of wind-driven power.But wind-powered electricity generation has very strong randomness, intermittence, uncontrollability and demodulates peak spy
Property, this carries out the difficulty of peak load regulation network with regard to gradually increasing fired power generating unit.In order to effectively dissolve new forms of energy resource, country by
The policy requirement of fired power generating unit peak regulation is gradually increased, if northeast Supervision Bureau of National Energy Board is on printing and distributing《Tohoku Electric Power peak regulation
Assisted hatching supervisory method(It is tentative)》And its supplementary provisions requirement should lift clean energy resource consumption space, ensure again
Resident's heating quality." staged " compensation mechanism is defined simultaneously, divides third gear making up price, i.e., first grade according to peak regulation rate:48%
<Thermal power plant's peak regulation rate≤55%, compensation valency are 0.4 yuan/kWh;Second gear:55%<Thermal power plant's peak regulation rate≤60%, compensation valency are 0.4
~0.6 yuan/kWh;Third gear:Thermal power plant's peak regulation rate>60%, compensation valency is 0.6~0.8 yuan/kWh.
As can be seen here, national policy is just progressively increasing the compensation dynamics to fired power generating unit peak modulation capacity;Require thermoelectricity simultaneously
Unit must ensure the heating quality of resident when peak load regulation network is carried out, and this just further increases fired power generating unit peak regulation
Difficulty.Therefore, how fired power generating unit power peak regulation is effectively carried out, and does not influence resident's heating quality, thermal power plant is come
Say, play vital effect.Publication date is on 01 19th, 2011, Publication No. CN101950964A Chinese patent
In, disclosed a kind of system and dispatching method comprising cogeneration units and pure condensed steam formula fired power generating unit also could not be really real
Now lift the function of unit flexibility.
The content of the invention
It is an object of the invention to overcome above shortcomings in the prior art, and provide a kind of reasonable in design, performance
Reliably, unit power peak regulation and the cogeneration units depth peak regulation system of thermic load peak load shifting and its operation are advantageously implemented
Method.
Technical scheme is used by the present invention solves the above problems:The cogeneration units depth peak regulation system includes pot
Stove, steam turbine, generator, heat exchange station, heat user, heat supply extraction steam pipe and heat supply pipeline, the steam turbine connect with generator, institute
State generator to connect with power network, the steam turbine is connected by heat supply extraction steam pipe with heat exchange station, and the heat exchange station passes through heating tube
Road connects with heat user, and its design feature is:Also include heat transmission equipment, regenerative apparatus, main steam pipe, reheated steam pipe and subtract
Warm decompressor, the boiler connect with main steam pipe, the main steam pipe be divided into two branch roads respectively with steam turbine and desuperheat
Decompressor connects, and the steam turbine connects with reheated steam pipe, the reheated steam pipe be divided into two branch roads respectively with boiler
Connected with reducing-and-cooling plant, the reducing-and-cooling plant, heat transmission equipment and regenerative apparatus are sequentially connected by pipeline, the storage
Thermal is connected by pipeline with heat supply pipeline.
Preferably, present invention additionally comprises valve A and valve B, the valve A and valve B to be separately mounted to main steam pipe
Two branch roads on.
Preferably, present invention additionally comprises valve C, the valve C, which is arranged on, to be used to connect heat transmission equipment and regenerative apparatus
Pipeline on.
Preferably, present invention additionally comprises valve D and valve E, the valve D and valve E are installed on heat supply pipeline,
The both sides for the tie point that valve D and valve E is connected positioned at regenerative apparatus with heat supply pipeline respectively.
Preferably, present invention additionally comprises valve F, the valve F, which is arranged on, to be used to connect regenerative apparatus and heat supply pipeline
Pipeline on.
To be arranged on preferably, present invention additionally comprises valve H, the valve H on reheated steam pipe.
Preferably, present invention additionally comprises valve G and valve J, the valve G and valve J to be separately mounted to reheated steam
On two branch roads of pipe.
Preferably, steam turbine of the present invention is extraction condensing type thermal power plant unit or back pressure type thermal power plant unit.
A kind of operation method of described cogeneration units depth peak regulation system, it is characterised in that:The operation method
The step of it is as follows:
1)When steam turbine is back pressure type thermal power plant unit, by the operating condition, main steam or the reheated steam that adjust boiler
The flow of steam turbine and heat transmission equipment and the operating condition of regenerative apparatus are respectively enterd to meet peak regulation demand;
When electrical load requirement is decreased or increased, by increaseing or decreasing the method for reheated steam flow reducing or
Improve the generation load of thermoelectricity unit, furthermore with regenerative apparatus by the storage of the reheated steam increased or decreased this partial heat or
Discharge, to reach the matching of electric load and thermic load;And/or the evaporation capacity of boiler is reduced or increases, to decrease or increase
Main steam enters the flow of steam turbine to meet power peak regulation demand, while balances steamer using regenerative apparatus accumulation of heat or heat release
The supply-demand difference of thermic load between the two needed for machine heating demand and heat user;If both the above method still can not meet electricity
Power peak regulation demand, then by the way that a part of main steam is introduced into heat transmission equipment, further to reduce the throttle flow of steam turbine, with depth
The generation load of thermoelectricity unit is reduced, and the heat of main steam release is supplied directly to heat supply network, or heat is deposited using regenerative apparatus
Storage is got up;
2)When steam turbine is extraction condensing type thermal power plant unit, by the operation work for adjusting the operating condition of boiler, regenerative apparatus
Condition, main steam or reheated steam respectively enter the flow of steam turbine and heat transmission equipment and the operating condition of steam turbine to meet to adjust
Peak demand;
When electrical load requirement is decreased or increased, drawn gas by increaseing or decreasing heating or the side of reheated steam flow
Method reduces or improved the generation load of thermoelectricity unit, and the heating that increases or decreases is drawn gas or reheating furthermore with regenerative apparatus
The storage of this partial heat of steam discharges, to reach the matching of electric load and thermic load;And/or reduce or increase boiler
Evaporation capacity, to decrease or increase main steam into the flow of steam turbine to meet power peak regulation demand, while filled using accumulation of heat
Accumulation of heat or heat release are put to balance the supply-demand difference of thermic load between the two needed for steam turbine heating demand and heat user;More than if
Two methods still can not meet power peak regulation demand, then by the way that a part of main steam is introduced into heat transmission equipment, further to subtract
The throttle flow of few steam turbine, the generation load of thermoelectricity unit being reduced with depth, the heat of main steam release is supplied directly to heat supply network,
Or heat is stored using regenerative apparatus.
Preferably, the present invention is heat user progress heat supply using steam caused by cogeneration units or filled using accumulation of heat
Put when carrying out accumulation of heat, the steam that prioritizing selection heat supply extraction steam pipe provides, the steam secondly provided for reheated steam pipe, it is last based on
The steam that steam pipe provides.
The present invention compared with prior art, has advantages below and effect:It is simple in construction, reasonable in design, dependable performance, base
In accumulation of heat peak regulation system, rational design realizes that thermal power plant meets the power peak regulation requirement of power network, can also realize Cogeneration Heat
The purpose of load peak load shifting;After having used the present invention, it is possible to achieve fired power generating unit meets the needs of supplying heat and generating power simultaneously,
It is worth with higher practice.
Brief description of the drawings
Fig. 1 is the structural representation of cogeneration units depth peak regulation system in the embodiment of the present invention.
In figure:1-boiler, 2-steam turbine, 3-generator, 4-heat exchange station, 5-heat user, 6-heat transmission equipment, 7-
Regenerative apparatus, 8-valve A, 9-valve B, 10-valve C, 11-valve D, 12-valve E, 13-valve F, 14-valve G,
15-valve H, 16-valve J, 17-main steam pipe, 18-reheated steam pipe, 19-heat supply extraction steam pipe, 20-heat supply pipeline,
21-reducing-and-cooling plant.
Embodiment
Below in conjunction with the accompanying drawings and the present invention is described in further detail by embodiment, and following examples are to this hair
Bright explanation and the invention is not limited in following examples.
Embodiment.
Referring to Fig. 1, the cogeneration units depth peak regulation system in the present embodiment includes boiler 1, steam turbine 2, generator
3rd, heat exchange station 4, heat user 5, heat transmission equipment 6, regenerative apparatus 7, valve A8, valve B9, valve C10, valve D11, valve E12,
Valve F13, valve G14, valve H15, valve J16, main steam pipe 17, reheated steam pipe 18, heat supply extraction steam pipe 19, heat supply pipeline
20 and reducing-and-cooling plant 21, wherein, steam turbine 2 can be extraction condensing type thermal power plant unit or back pressure type thermal power plant unit.
Steam turbine 2 and generator 3 in the present embodiment connect, and generator 3 connects with power network, and steam turbine 2 is taken out by heat supply
Steam pipe 19 and heat exchange station 4 are connected, and heat exchange station 4 is connected by heat supply pipeline 20 and heat user 5, and boiler 1 and main steam pipe 17 connect.
Main steam pipe 17 is divided into two branch roads and is connected respectively with steam turbine 2 and reducing-and-cooling plant 21, i.e., main steam pipe 17 separate two
In bar branch road, a branch road is connected with steam turbine 2, and another branch road is connected with reducing-and-cooling plant 21.
Steam turbine 2 and reheated steam pipe 18 in the present embodiment connect, reheated steam pipe 18 be divided into two branch roads respectively with
Boiler 1 and reducing-and-cooling plant 21 are connected, i.e., in two branch roads that reheated steam pipe 18 separates, a branch road is connected with boiler 1,
Another branch road is connected with reducing-and-cooling plant 21.Reducing-and-cooling plant 21, heat transmission equipment 6 and regenerative apparatus 7 by pipeline according to
Secondary connection, regenerative apparatus 7 are connected by pipeline and heat supply pipeline 20.
Valve A8 and valve B9 in the present embodiment are separately mounted on two branch roads of main steam pipe 17, wherein, valve
A8 is arranged on the branch road being connected with steam turbine 2, and valve B9 is arranged on the branch road being connected with reducing-and-cooling plant 21.Valve C10
Installed in the pipeline for connecting heat transmission equipment 6 and regenerative apparatus 7.Valve D11 and valve E12 are installed in heat supply pipeline 20
On, the both sides for the tie point that valve D11 and valve E12 are connected positioned at regenerative apparatus 7 with heat supply pipeline 20 respectively, i.e. valve
D11, the tie point and valve E12 of regenerative apparatus 7 and heat supply pipeline 20 are arranged in order along heat supply pipeline 20.Valve F13 is installed
In the pipeline for connecting regenerative apparatus 7 and heat supply pipeline 20.Valve H15 is arranged on reheated steam pipe 18.Valve G14 and
Valve J16 is separately mounted on two branch roads of reheated steam pipe 18, wherein, valve G14 is arranged on the branch road being connected with boiler 1
On, valve J16 is arranged on the branch road being connected with reducing-and-cooling plant 21.
The step of operation method of cogeneration units depth peak regulation system in the present embodiment, is as follows.
1)When steam turbine 2 is back pressure type thermal power plant unit, steamed by the operating condition, main steam or the reheating that adjust boiler 1
Vapour respectively enters the flow of steam turbine 2 and heat transmission equipment 6 and the operating condition of regenerative apparatus 7 to meet peak regulation demand.
When electrical load requirement is decreased or increased, by increaseing or decreasing the method for reheated steam flow reducing or
The generation load of thermoelectricity unit is improved, this partial heat stores by the reheated steam increased or decreased furthermore with regenerative apparatus 7
Or discharge, to reach the matching of electric load and thermic load;And/or reduce or the evaporation capacity of increase boiler 1, reducing or
Increase main steam into the flow of steam turbine 2 to meet power peak regulation demand, while put down using the accumulation of heat of regenerative apparatus 7 or heat release
Weigh the supply-demand difference of thermic load between the two needed for the heating demand of steam turbine 2 and heat user 5;If both the above method still without
Method meets power peak regulation demand, then by the way that a part of main steam is introduced into heat transmission equipment 6, further to reduce entering for steam turbine 2
Vapour amount, the generation load of thermoelectricity unit is reduced with depth, the heat of main steam release is supplied directly to heat supply network, or is filled using accumulation of heat
7 are put to store heat.
2)When steam turbine 2 is extraction condensing type thermal power plant unit, the operation of operating condition, regenerative apparatus 7 by adjusting boiler 1
The operating condition of flow and steam turbine 2 that operating mode, main steam or reheated steam respectively enter steam turbine 2 and heat transmission equipment 6 comes
Meet peak regulation demand.
When electrical load requirement is decreased or increased, drawn gas by increaseing or decreasing heating or the side of reheated steam flow
Method reduces or improved the generation load of thermoelectricity unit, furthermore with regenerative apparatus 7 heating increased or decreased is drawn gas or again
The storage of this partial heat of vapours discharges, to reach the matching of electric load and thermic load;And/or reduce or increase pot
The evaporation capacity of stove 1, to decrease or increase main steam into the flow of steam turbine 2 to meet power peak regulation demand, while utilize storage
The accumulation of heat of thermal 7 or heat release balance the supply-demand difference of thermic load between the two needed for the heating demand of steam turbine 2 and heat user 5;
If both the above method still can not meet power peak regulation demand, by the way that a part of main steam is introduced into heat transmission equipment 6, come
The throttle flow of steam turbine 2 is further reduced, the generation load of thermoelectricity unit is reduced with depth, the heat of main steam release directly supplies
Heat supply network is given to, or is stored heat using regenerative apparatus 7.
It is the progress heat supply of heat user 5 using steam caused by cogeneration units in the present embodiment or utilizes regenerative apparatus 7
Carry out accumulation of heat when, prioritizing selection heat supply extraction steam pipe 19 provide steam, secondly for reheated steam pipe 18 provide steam, finally for
The steam that main steam pipe 17 provides.
The present invention is based on regenerative apparatus 7, and rational design realizes that the power peak regulation of cogeneration units is filled out with thermic load peak clipping
Paddy, after the present invention, it can not only realize that unit meets the needs of supplying heat and generating power, can also realize that boiler is located for a long time simultaneously
In preferable operating condition, there is higher practice to be worth.
Furthermore, it is necessary to illustrate, the specific embodiment described in this specification, the shape of its parts and components, it is named
Title etc. can be different, and the above content described in this specification is only to structure example explanation of the present invention.It is all according to
The equivalence changes or simple change done according to the construction described in inventional idea of the present invention, feature and principle, are included in this hair
In the protection domain of bright patent.Those skilled in the art can do various to described specific embodiment
The modification of various kinds or supplement are substituted using similar mode, without departing from structure of the invention or surmount present claims
Scope defined in book, protection scope of the present invention all should be belonged to.
Claims (10)
1. a kind of cogeneration units depth peak regulation system, including boiler(1), steam turbine(2), generator(3), heat exchange station(4)、
Heat user(5), heat supply extraction steam pipe(19)And heat supply pipeline(20), the steam turbine(2)And generator(3)Connection, the steamer
Machine(2)Pass through heat supply extraction steam pipe(19)And heat exchange station(4)Connection, the heat exchange station(4)Pass through heat supply pipeline(20)And heat user
(5)Connection, it is characterised in that:Also include heat transmission equipment(6), regenerative apparatus(7), main steam pipe(17), reheated steam pipe(18)
And reducing-and-cooling plant(21), the boiler(1)And main steam pipe(17)Connection, the main steam pipe(17)It is divided into two branch roads
Respectively with steam turbine(2)And reducing-and-cooling plant(21)Connection, the steam turbine(2)With reheated steam pipe(18)Connection, it is described
Reheated steam pipe(18)Be divided into two branch roads respectively with boiler(1)And reducing-and-cooling plant(21)Connection, the pressure and temperature reducing dress
Put(21), heat transmission equipment(6)And regenerative apparatus(7)It is sequentially connected by pipeline, the regenerative apparatus(7)Pass through pipeline and heat supply
Pipeline(20)Connection.
2. cogeneration units depth peak regulation system according to claim 1, it is characterised in that:Also include valve A(8)With
Valve B(9), the valve A(8)With valve B(9)It is separately mounted to main steam pipe(17)Two branch roads on.
3. cogeneration units depth peak regulation system according to claim 1, it is characterised in that:Also include valve C(10),
The valve C(10)Installed in for connecting heat transmission equipment(6)And regenerative apparatus(7)Pipeline on.
4. cogeneration units depth peak regulation system according to claim 1, it is characterised in that:Also include valve D(11)
With valve E(12), the valve D(11)With valve E(12)It is installed in heat supply pipeline(20)On, valve D(11)With valve E
(12)It is located at regenerative apparatus respectively(7)With heat supply pipeline(20)The both sides of the tie point of connection.
5. cogeneration units depth peak regulation system according to claim 1, it is characterised in that:Also include valve F(13),
The valve F(13)Installed in for connecting regenerative apparatus(7)And heat supply pipeline(20)Pipeline on.
6. cogeneration units depth peak regulation system according to claim 1, it is characterised in that:Also include valve H(15),
The valve H(15)Installed in reheated steam pipe(18)On.
7. cogeneration units depth peak regulation system according to claim 1, it is characterised in that:Also include valve G(14)
With valve J(16), the valve G(14)With valve J(16)It is separately mounted to reheated steam pipe(18)Two branch roads on.
8. cogeneration units depth peak regulation system according to claim 1, it is characterised in that:The steam turbine(2)For
Extraction condensing type thermal power plant unit or back pressure type thermal power plant unit.
9. a kind of operation method of cogeneration units depth peak regulation system as described in claim 1~8 any claim,
It is characterized in that:The step of operation method, is as follows:
1)Work as steam turbine(2)For back pressure type thermal power plant unit when, by adjusting boiler(1)Operating condition, main steam or reheating steam
Vapour respectively enters steam turbine(2)With heat transmission equipment(6)Flow and regenerative apparatus(7)Operating condition meet peak regulation need
Ask;
When electrical load requirement is decreased or increased, reduces or improve by increaseing or decreasing the method for reheated steam flow
The generation load of thermoelectricity unit, furthermore with regenerative apparatus(7)By the storage of the reheated steam increased or decreased this partial heat or
Discharge, to reach the matching of electric load and thermic load;And/or reduce or increase boiler(1)Evaporation capacity, reducing or
Increase main steam enters steam turbine(2)Flow to meet power peak regulation demand, while utilize regenerative apparatus(7)Accumulation of heat or heat release
To balance steam turbine(2)Heating demand and heat user(5)The supply-demand difference of required thermic load between the two;If both the above side
Method still can not meet power peak regulation demand, then by the way that a part of main steam is introduced into heat transmission equipment(6), further to reduce vapour
Turbine(2)Throttle flow, with depth reduce thermoelectricity unit generation load, main steam release heat be supplied directly to heat supply network,
Or utilize regenerative apparatus(7)Heat is stored;
2)Work as steam turbine(2)For extraction condensing type thermal power plant unit when, by adjusting boiler(1)Operating condition, regenerative apparatus(7)Fortune
Row operating mode, main steam or reheated steam respectively enter steam turbine(2)With heat transmission equipment(6)Flow and steam turbine(2)Fortune
Row operating mode meets peak regulation demand;
When electrical load requirement is decreased or increased, drawn gas by increaseing or decreasing heating or the method for reheated steam flow come
The generation load of thermoelectricity unit is reduced or improves, furthermore with regenerative apparatus(7)The heating increased or decreased is drawn gas or reheating
The storage of this partial heat of steam discharges, to reach the matching of electric load and thermic load;And/or reduce or increase boiler
(1)Evaporation capacity, enter steam turbine to decrease or increase main steam(2)Flow to meet power peak regulation demand, utilize simultaneously
Regenerative apparatus(7)Accumulation of heat or heat release balance steam turbine(2)Heating demand and heat user(5)The confession of required thermic load between the two
Need difference;If both the above method still can not meet power peak regulation demand, exchanged heat by the way that a part of main steam is introduced
Equipment(6), further to reduce steam turbine(2)Throttle flow, with depth reduce thermoelectricity unit generation load, main steam release
Heat be supplied directly to heat supply network, or utilize regenerative apparatus(7)Heat is stored.
10. the operation method of cogeneration units depth peak regulation system according to claim 9, it is characterised in that:Utilize
Steam caused by cogeneration units is heat user(5)Carry out heat supply or utilize regenerative apparatus(7)When carrying out accumulation of heat, prioritizing selection
Heat supply extraction steam pipe(19)The steam of offer, it is secondly reheated steam pipe(18)The steam of offer, it is finally main steam pipe(17)Carry
The steam of confession.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610738334.8A CN106437876B (en) | 2016-08-29 | 2016-08-29 | A kind of cogeneration units depth peak regulation system and its operation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610738334.8A CN106437876B (en) | 2016-08-29 | 2016-08-29 | A kind of cogeneration units depth peak regulation system and its operation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106437876A CN106437876A (en) | 2017-02-22 |
CN106437876B true CN106437876B (en) | 2018-03-27 |
Family
ID=58182338
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610738334.8A Active CN106437876B (en) | 2016-08-29 | 2016-08-29 | A kind of cogeneration units depth peak regulation system and its operation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106437876B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2757521C1 (en) * | 2021-04-02 | 2021-10-18 | Общество с ограниченной ответственностью «Ракурс-инжиниринг» | System and method for regulating fuel consumption for steam boiler |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106968734A (en) * | 2017-03-07 | 2017-07-21 | 赫普热力发展有限公司 | The accumulation of heat peak regulation system that a kind of turbine by pass and across season natural water are combined |
CN108023360B (en) * | 2017-12-27 | 2020-09-22 | 浙江大学 | Thermoelectric peak shifting and heat supply network heat storage based power grid peak regulation participating thermal power plant and peak regulation method |
CN108302549A (en) * | 2018-02-02 | 2018-07-20 | 重庆富燃科技股份有限公司 | A kind of oxygen-enriched combusting depth peak regulation and energy-saving and emission-reduction integrated system and method |
CN108302548A (en) * | 2018-02-02 | 2018-07-20 | 重庆富燃科技股份有限公司 | A kind of oxygen-enriched combusting energy-saving and emission-reduction system and method |
CN108592137A (en) * | 2018-07-13 | 2018-09-28 | 大连亨利测控仪表工程有限公司 | A kind of thermal power plant's flexibility transformation twin-tub decoupling depth peak regulation system |
CN108592136B (en) * | 2018-07-13 | 2023-10-31 | 大连亨利测控仪表工程有限公司 | Double-cylinder decoupling depth peak shaving system for thermal power plant flexible transformation |
CN109139153B (en) * | 2018-07-27 | 2023-12-26 | 国能龙源蓝天节能技术有限公司 | Heat storage type auxiliary peak shaving heat supply system and method for coal-fired generator set |
CN109113813B (en) * | 2018-10-23 | 2024-01-02 | 赫普能源环境科技股份有限公司 | Heat accumulation power generation system |
CN109538317B (en) * | 2018-11-12 | 2021-04-06 | 东北电力大学 | A regenerative system capable of improving the peak shaving capacity of the unit and a dynamic calculation method for the steam temperature of the heat storage tank of the regenerative system |
CN109193808A (en) * | 2018-11-13 | 2019-01-11 | 国网河北能源技术服务有限公司 | Peak load regulation network energy force prediction method and device |
CN109798157B (en) * | 2019-02-02 | 2024-03-08 | 华电电力科学研究院有限公司 | Condensing and back-pumping coupled steam extraction integrated system for thermoelectric unit power peak regulation and operation method thereof |
CN111520809B (en) * | 2020-03-09 | 2021-04-13 | 华电电力科学研究院有限公司 | Heat and power cogeneration coupling heat supply load adjusting method based on heat supply network heat load prediction |
CN111503718B (en) * | 2020-03-09 | 2021-06-15 | 华电电力科学研究院有限公司 | Cogeneration heating load prediction method based on multi-factor influence and heating system |
CN115749985B (en) * | 2022-11-11 | 2024-07-23 | 东方电气集团东方汽轮机有限公司 | Seasonal variable parameter operation method of extraction back type steam turbine |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4428190A (en) * | 1981-08-07 | 1984-01-31 | Ormat Turbines, Ltd. | Power plant utilizing multi-stage turbines |
JPS63113103A (en) * | 1986-10-31 | 1988-05-18 | Mitsubishi Heavy Ind Ltd | Leak preventing device for steam valve |
JPH0598908A (en) * | 1991-10-09 | 1993-04-20 | Mitsubishi Heavy Ind Ltd | Power generating device utilizing combustion gas of combustion furnace |
CN201448132U (en) * | 2009-08-19 | 2010-05-05 | 刘绍允 | Cogeneration closed cycle phase change heating device |
CN104791876A (en) * | 2014-04-14 | 2015-07-22 | 中北大学 | Cogeneration system allowing heat to be fully used |
KR101587256B1 (en) * | 2015-03-17 | 2016-01-20 | (주)거나백 | A combined heat and power system with a double layered reservoir |
CN205047259U (en) * | 2015-09-25 | 2016-02-24 | 华电电力科学研究院 | System for be used for turbine unit extraction steam for factories to subtract temperature |
CN205477785U (en) * | 2016-01-29 | 2016-08-17 | 华电电力科学研究院 | Peak regulation storage system of condensing steam turbine group |
CN206054009U (en) * | 2016-08-29 | 2017-03-29 | 华电电力科学研究院 | A kind of cogeneration units depth peak regulation system |
-
2016
- 2016-08-29 CN CN201610738334.8A patent/CN106437876B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4428190A (en) * | 1981-08-07 | 1984-01-31 | Ormat Turbines, Ltd. | Power plant utilizing multi-stage turbines |
JPS63113103A (en) * | 1986-10-31 | 1988-05-18 | Mitsubishi Heavy Ind Ltd | Leak preventing device for steam valve |
JPH0598908A (en) * | 1991-10-09 | 1993-04-20 | Mitsubishi Heavy Ind Ltd | Power generating device utilizing combustion gas of combustion furnace |
CN201448132U (en) * | 2009-08-19 | 2010-05-05 | 刘绍允 | Cogeneration closed cycle phase change heating device |
CN104791876A (en) * | 2014-04-14 | 2015-07-22 | 中北大学 | Cogeneration system allowing heat to be fully used |
KR101587256B1 (en) * | 2015-03-17 | 2016-01-20 | (주)거나백 | A combined heat and power system with a double layered reservoir |
CN205047259U (en) * | 2015-09-25 | 2016-02-24 | 华电电力科学研究院 | System for be used for turbine unit extraction steam for factories to subtract temperature |
CN205477785U (en) * | 2016-01-29 | 2016-08-17 | 华电电力科学研究院 | Peak regulation storage system of condensing steam turbine group |
CN206054009U (en) * | 2016-08-29 | 2017-03-29 | 华电电力科学研究院 | A kind of cogeneration units depth peak regulation system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2757521C1 (en) * | 2021-04-02 | 2021-10-18 | Общество с ограниченной ответственностью «Ракурс-инжиниринг» | System and method for regulating fuel consumption for steam boiler |
Also Published As
Publication number | Publication date |
---|---|
CN106437876A (en) | 2017-02-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106437876B (en) | A kind of cogeneration units depth peak regulation system and its operation method | |
CN106401659B (en) | A kind of step peak regulation system and its operation method for improving thermoelectricity unit thermoelectricity flexibility | |
CN105863758B (en) | Heating system and intelligent control method for the double load peak regulations of cogeneration units | |
CN101042058B (en) | Novel steam-electric generating set | |
CN208982124U (en) | The heat and power system of unit fast lifting load is realized in a kind of combination heat supply | |
CN209558305U (en) | Vapour vapor extractor combination thermal storage electric boiler peak regulation system is penetrated by a kind of thermal power plant | |
CN102140938B (en) | Double-cylinder coaxial combined cycle heat supply gas turbine | |
CN206054009U (en) | A kind of cogeneration units depth peak regulation system | |
CN106640237B (en) | A kind of system and its operation method improving thermoelectricity pure condensate unit flexibility | |
CN104314628A (en) | Coal-fired unit and gas turbine combined type power generation system | |
CN202002081U (en) | Steam secondary reheating system | |
CN106991515A (en) | A kind of E grades of gas combustion-gas vapor combined cycle unit power consumption analysis method | |
CN102997309A (en) | Classification heating system with high-temperature heat source heater bypass pipe | |
CN206054008U (en) | A kind of step peak regulation system for improving thermoelectricity unit thermoelectricity motility | |
CN107542506A (en) | Steam turbine extraction condensing back pressure gradient utilization system and its application | |
CN103696816A (en) | Intermediate reheating small-capacity split axle type steam-turbine generator set | |
CN206054015U (en) | A kind of system for improving thermoelectricity pure condensate unit motility | |
CN204225940U (en) | A kind of coal unit and gas turbine combined power generation system | |
CN113217127A (en) | Multistage steam extraction back pressure type small steam turbine stage heat regeneration and heating system and method | |
CN108644858A (en) | A kind of gas and steam combined cycle cogeneration unit heat consumption distribution method | |
CN103982252A (en) | Novel process combination of high-speed and efficient single reheating steam turbine and power generation of small power plant | |
CN206092088U (en) | Matching unit of coal -fired power unit heat supply parameter | |
CN102393004A (en) | Fuel gas-steam combined cycle heat power plant | |
CN201037429Y (en) | Novel steamer generating set | |
CN206144612U (en) | Utilize supercritical unit to realize high pressure cylinder steam extracting and heat supplying combined heat and power generation system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 310030 No. 10 West Garden Road, West Lake science and technology economic Park, Xihu District, Hangzhou, Zhejiang Patentee after: HUADIAN ELECTRIC POWER RESEARCH INSTITUTE Co.,Ltd. Address before: 310030 No. 10 West Garden Road, West Lake science and technology economic Park, Xihu District, Hangzhou, Zhejiang Patentee before: Huadian Electric Power Research Institute |