CN106436736A - Fan foundation large-size concrete construction method - Google Patents

Fan foundation large-size concrete construction method Download PDF

Info

Publication number
CN106436736A
CN106436736A CN201610598478.8A CN201610598478A CN106436736A CN 106436736 A CN106436736 A CN 106436736A CN 201610598478 A CN201610598478 A CN 201610598478A CN 106436736 A CN106436736 A CN 106436736A
Authority
CN
China
Prior art keywords
concrete
temperature
days
less
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610598478.8A
Other languages
Chinese (zh)
Inventor
董俊顺
朱家直
田伟
张军有
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ceec Anhui Electric Power Construction First Engineering Co Ltd
Original Assignee
Ceec Anhui Electric Power Construction First Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ceec Anhui Electric Power Construction First Engineering Co Ltd filed Critical Ceec Anhui Electric Power Construction First Engineering Co Ltd
Priority to CN201610598478.8A priority Critical patent/CN106436736A/en
Publication of CN106436736A publication Critical patent/CN106436736A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Wind Motors (AREA)

Abstract

The invention discloses a fan foundation large-size concrete construction method for curing after casting. Concrete is quickly cast, and cannot generate the layered cracking problem after casting. After the concrete is cast, the curing time is reasonably designed; and the temperature/humidity detection is performed in the curing period to guarantee the temperature and the humidity to reach set requirements in the curing period, so that the cured concrete is fully watered, the strength of the concrete is gradually improved, the shrinkage crack of the concrete caused by wind and sun is prevented, and the cast concrete is guaranteed to reach the designed strength in the stated age.

Description

A kind of construction method of blower foundation mass concrete
Technical field
The present invention relates to Construction of Wind Power field, specifically a kind of construction method of blower foundation mass concrete.
Background technology
It is known that the Chinese government makes promise to international community in Copenhagen climate change conference in 2009 arriving The year two thousand twenty unit GDP CO2 emissions declined 40%~50% than 2005, and non-fossil energy will meet this The energy demand of state 15%, this is proposed unprecedented expectation to China's future development scale of wind-powered electricity generation and progress etc., accelerates wind Can resource using with exploitation will become the Important Action realizing the strategy of sustainable development in China's considerably long one period, arrive The wind-powered electricity generation installation of the year two thousand twenty China reaches 2.3 hundred million KW;Provide development environment good greatly and opportunity for our Wind Power Developments.
The core of wind-powered electricity generation conversion is blower fan, and the support of blower fan is supported using tower, and the base support of tower adopts base Plinth ring is supported, and the most important step of foundation ring construction is the pouring construction of base mass concrete.
Content of the invention
The technical problem to be solved in the present invention is to provide a kind of construction method of blower foundation mass concrete it is ensured that pouring Build the abundant aquation of the concrete after maintenance, concrete strength gradually increases, it is to avoid concrete is exposed to the weather etc. and to be produced drying shrinkage and split Seam is it is ensured that the concrete pouring reaches design requirement intensity within regulation age.
The technical scheme is that:
A kind of construction method of blower foundation mass concrete, includes following steps:When blower foundation ring bed course reaches To after some strength, snap the line, formwork lay reinforcing bar thereon, then casting concrete, concrete continuous pour, first once Pour to base plate top, exceed the beam of bottom parts and middle pier placement layer by layer, every layer of ponding depths are less than 300mm, upper and lower two Layer concrete pours time interval and cannot be greater than the lower-layer concrete presetting period former 1 hour, when pouring top layer concrete, thickness Cannot be less than 300mm;To concrete in addition plastic covering thin film cover moisturizing and support within 12h after concreting finishes Sheath, removes plastic sheeting after 7 days, more again covers moisture-keeping maintaining layer, it is to avoid the sun is exposed to the sun, and the concrete curing time is no less than 14 days, in concrete during maintenance, the table temperature difference was not more than 25 DEG C, and surface is not more than 20 DEG C with the temperature difference of air, any portion of concrete No more than 70 DEG C of the temperature divided.
During described concreting, the personnel of pouring should enter in steel reinforcement cage is vibrated, when single blower foundation pours Vibrate no less than 4 vibrators, spacing of vibrating adopts 60cm at no-reinforcing-bar simultaneously, have at reinforcing bar and adopt 40cm, vibrator must More than lower-layer concrete 10cm must be inserted.
Described moisture-keeping maintaining layer adopts water seasoning:To using portland cement, Portland cement or slag silicon The concrete of acid salt cement mixing, the water seasoning time must not be less than 7 days;To mixing retarding additive or have seepage resistance demand Concrete, the water seasoning time must not be less than 14 days;Under wet weather depletion of YANG light direct beam, when temperature is constant at 5~10 DEG C, pour The water curing time is no less than 14 days;When temperature is constant at 10~20 DEG C, the water seasoning time is no less than 10 days, has in strong wind drying Under direct sunlight weather, when temperature is constant at 5~10 DEG C, the water seasoning time is no less than 21 days;Temperature is constant at 10~20 DEG C When, the water seasoning time is no less than 14 days;When temperature is more than 20 DEG C, the water seasoning time is no less than 10 days.
Carry out thermometric record, every piece of base mass concrete arranges 4 thermometer holes during described concrete curing, one Individual on foundation girder, three are located inside foundation ring, and thermometric record will continue 14 days, and first three sky was at interval of measurement in two hours Temperature, at interval of temperature of measurement in four hours, temperature of measurement in last 7 days every six hours, pours for the 4th day to the 7th day Temperature rise value after building is not more than 50 DEG C, and in concrete, the table temperature difference is not more than 25 DEG C, and surface is not more than 20 DEG C with the temperature difference of air, mixes Coagulate no more than 70 DEG C of native any portion of temperature.
Pouring of concrete of the present invention is quick, and the concrete after pouring is not in the problem of delamination splitting;The present invention Concrete after pouring, its curing time of appropriate design, and carry out Temperature and Humidity during maintenance it is ensured that during maintenance Temperature and humidity reaches the requirement of setting, makes the abundant aquation of the concrete after maintenance, and concrete strength gradually increases, it is to avoid coagulation Soil by expose to the weather wait generation desciccation crack it is ensured that the concrete pouring reaches design requirement intensity within regulation age.
Specific embodiment
The enforcement it is clear that described will be clearly and completely described to the technical scheme in the embodiment of the present invention below Example is only a part of embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, this area is common The every other embodiment that technical staff is obtained under the premise of not making creative work, broadly falls into the model of present invention protection Enclose.
A kind of construction method of blower foundation mass concrete, includes following steps:When blower foundation ring bed course reaches To after some strength, snap the line, formwork lay reinforcing bar thereon, then casting concrete, concrete continuous pour, first once Pour to base plate top, exceed the beam of bottom parts and middle pier placement layer by layer, every layer of ponding depths are less than 300mm, upper and lower two Layer concrete pours time interval and cannot be greater than the lower-layer concrete presetting period former 1 hour, when pouring top layer concrete, thickness Cannot be less than 300mm, and in concreting, the personnel of pouring should enter in steel reinforcement cage is vibrated, and single blower foundation pours Vibrate no less than 4 vibrators when building, spacing of vibrating adopts 60cm at no-reinforcing-bar, has and adopts 40cm at reinforcing bar, vibrates simultaneously Device must be inserted into more than lower-layer concrete 10cm;To concrete plastic covering in addition within 12h after concreting finishes Thin film simultaneously covers moisture-keeping maintaining layer, removes plastic sheeting, more again covers moisture-keeping maintaining layer, it is to avoid the sun is exposed to the sun, coagulation after 7 days Carry out thermometric record, every piece of base mass concrete arranges 4 thermometer holes, one is located on foundation girder during native maintenance, Three are located inside foundation ring, and thermometric record will continue 14 days, and at interval of temperature of measurement in two hours, the 4th day arrives in first three sky At interval of temperature of measurement in four hours, temperature of measurement in last 7 days every six hours, the temperature rise value after pouring is little within 7th day In 50 DEG C, in concrete, the table temperature difference is not more than 25 DEG C, and surface is not more than 20 DEG C with the temperature difference of air, any portion of temperature of concrete No more than 70 DEG C of degree.
Wherein, moisture-keeping maintaining layer adopts water seasoning:To using portland cement, Portland cement or slag silicate The concrete of salt cement mixing, the water seasoning time must not be less than 7 days;To mixing retarding additive or have seepage resistance demand to mix Solidifying soil, the water seasoning time must not be less than 14 days;Under wet weather depletion of YANG light direct beam, when temperature is constant at 5~10 DEG C, water Curing time is no less than 14 days;When temperature is constant at 10~20 DEG C, the water seasoning time is no less than 10 days, has sun in strong wind drying Under light direct beam weather, when temperature is constant at 5~10 DEG C, the water seasoning time is no less than 21 days;When temperature is constant at 10~20 DEG C, The water seasoning time is no less than 14 days;When temperature is more than 20 DEG C, the water seasoning time is no less than 10 days.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, permissible Understand and can carry out multiple changes, modification, replacement to these embodiments without departing from the principles and spirit of the present invention And modification, the scope of the present invention be defined by the appended.

Claims (4)

1. a kind of construction method of blower foundation mass concrete it is characterised in that:Include following steps:Work as blower foundation After ring bed course reaches some strength, snap the line, formwork lay reinforcing bar thereon, then casting concrete, concrete continuous are poured Build, first one-time-concreting to base plate top, exceed the beam of bottom parts and middle pier placement layer by layer, every layer of ponding depths are less than 300mm, upper and lower two-layer concreting time interval cannot be greater than the lower-layer concrete presetting period former 1 hour, pours top layer During concrete, thickness cannot be less than 300mm;Within 12h after concreting finishes, to concrete, plastic covering is thin in addition Film simultaneously covers moisture-keeping maintaining layer, removes plastic sheeting, more again covers moisture-keeping maintaining layer, it is to avoid the sun is exposed to the sun, concrete after 7 days Curing time is no less than 14 days, and in concrete during maintenance, the table temperature difference is not more than 25 DEG C, and surface is not more than 20 with the temperature difference of air DEG C, no more than 70 DEG C of any portion of temperature of concrete.
2. a kind of blower foundation mass concrete according to claim 1 construction method it is characterised in that:Described During concreting, the personnel of pouring should enter in steel reinforcement cage is vibrated, and is no less than 4 vibrators when single blower foundation pours Vibrate, spacing of vibrating adopts 60cm at no-reinforcing-bar simultaneously, have at reinforcing bar and adopt 40cm, vibrator must be inserted into lower-layer concrete More than 10cm.
3. a kind of blower foundation mass concrete according to claim 1 construction method it is characterised in that:Described Moisture-keeping maintaining layer adopts water seasoning:To using portland cement, Portland cement or portland slag cement mixing Concrete, the water seasoning time must not be less than 7 days;To mixing retarding additive or the concrete having seepage resistance demand, water foster The shield time must not be less than 14 days;Under wet weather depletion of YANG light direct beam, when temperature is constant at 5~10 DEG C, the water seasoning time is not Less than 14 days;When temperature is constant at 10~20 DEG C, the water seasoning time is no less than 10 days, has direct sunlight weather in strong wind drying Under, when temperature is constant at 5~10 DEG C, the water seasoning time is no less than 21 days;When temperature is constant at 10~20 DEG C, during water seasoning Between be no less than 14 days;When temperature is more than 20 DEG C, the water seasoning time is no less than 10 days.
4. a kind of blower foundation mass concrete according to claim 1 construction method it is characterised in that:Described Carry out thermometric record, every piece of base mass concrete arranges 4 thermometer holes, and one is located at foundation girder during concrete curing On, three be located at foundation ring inside, thermometric record will continue 14 days, first three sky at interval of two hours measurement temperature, the 4th It is by the 7th day at interval of temperature of measurement in four hours, temperature of measurement in last 7 days every six hours, the temperature rise value after pouring It is not more than 50 DEG C, in concrete, the table temperature difference is not more than 25 DEG C, surface is not more than 20 DEG C with the temperature difference of air, concrete any part No more than 70 DEG C of temperature.
CN201610598478.8A 2016-07-27 2016-07-27 Fan foundation large-size concrete construction method Pending CN106436736A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610598478.8A CN106436736A (en) 2016-07-27 2016-07-27 Fan foundation large-size concrete construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610598478.8A CN106436736A (en) 2016-07-27 2016-07-27 Fan foundation large-size concrete construction method

Publications (1)

Publication Number Publication Date
CN106436736A true CN106436736A (en) 2017-02-22

Family

ID=58184224

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610598478.8A Pending CN106436736A (en) 2016-07-27 2016-07-27 Fan foundation large-size concrete construction method

Country Status (1)

Country Link
CN (1) CN106436736A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109812034A (en) * 2019-01-31 2019-05-28 青岛一建集团有限公司 A kind of cooling for large volume casting concrete structural body, moisture retention construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202064369U (en) * 2011-05-11 2011-12-07 北京中水恒信环境科技发展有限公司 Multi-ribbed-slab type foundation structure
CN202099811U (en) * 2011-05-10 2012-01-04 上海勘测设计研究院 Spokewise blower foundation structure for onshore wind farm
CA2588497C (en) * 2006-05-22 2015-02-17 General Electric Company Method and apparatus for wind power foundation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2588497C (en) * 2006-05-22 2015-02-17 General Electric Company Method and apparatus for wind power foundation
CN202099811U (en) * 2011-05-10 2012-01-04 上海勘测设计研究院 Spokewise blower foundation structure for onshore wind farm
CN202064369U (en) * 2011-05-11 2011-12-07 北京中水恒信环境科技发展有限公司 Multi-ribbed-slab type foundation structure

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
吴光帅: ""珠海高栏岛风电场工程风机基础施工方法介绍"", 《中国高新技术企业》 *
杨国立主编: "《土木工程施工》", 31 March 2013, 中国电力出版社 *
陈绍峰: ""风力发电场工程风机基础混凝土施工方案"", 《中国西部科技》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109812034A (en) * 2019-01-31 2019-05-28 青岛一建集团有限公司 A kind of cooling for large volume casting concrete structural body, moisture retention construction method

Similar Documents

Publication Publication Date Title
CN207954218U (en) A kind of folded assembling die for beating precast concrete laminated floor slab
CN104790436B (en) Basement in high rise building top board pouring after settlement advance water stop construction method
CN109518864A (en) A kind of inversion steel bar girder concrete folding plate and its construction method
CN105239718A (en) Integral heat insulation wallboard building system
CN109706954A (en) One-time integral forming structure and forming method for cup-shaped foundation integral mold segmented casting
CN103615076B (en) The oblique roofing concrete construction method of a kind of heavy grade
CN216196782U (en) Single-layer multi-loop water cooling system for super-thick large-volume concrete
CN102296570A (en) Construction method of large cast-in-place reinforced concrete water inlet channel
CN103938649B (en) A kind of construction method on high-rise building cavity basis
CN106436736A (en) Fan foundation large-size concrete construction method
CN107938907B (en) A kind of inclined roof exempts from formwork construction method
CN208138090U (en) A kind of wind power generating set concrete tower
CN105822068B (en) Ultralong thin walled concrete walls under hot environment pour and maintenance process
CN101260726A (en) Prestressed concrete wide goose plate construction method
CN109914667A (en) A kind of superimposed prefabricated hollow floor slab and preparation method thereof
CN209509007U (en) Raft foundation integral quick-mounting communication tower
CN208415928U (en) A kind of prefabricated lining being used in combination with aluminum dipping form
CN203412143U (en) Wall body structure of integrally poured building house
CN203174902U (en) Water storage roof allowing people to stand
CN109630364A (en) The blower foundation and its manufacturing method of wind power generating set, wind power generating set
CN109930726A (en) A kind of concreting process applied in hollow floor construction
CN104805966B (en) Roof waterproofing construction method
CN105421780B (en) A kind of construction method of prefabricated concrete structure
CN204001480U (en) A kind of heat insulation house surface of producing with building waste
CN210562268U (en) Portable grouting groove structure in fan anchor bolt foundation secondary grouting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170222

RJ01 Rejection of invention patent application after publication