CN106400844A - Whole assembly type multifunctional inspection well - Google Patents
Whole assembly type multifunctional inspection well Download PDFInfo
- Publication number
- CN106400844A CN106400844A CN201610414573.8A CN201610414573A CN106400844A CN 106400844 A CN106400844 A CN 106400844A CN 201610414573 A CN201610414573 A CN 201610414573A CN 106400844 A CN106400844 A CN 106400844A
- Authority
- CN
- China
- Prior art keywords
- cover plate
- well
- assembled multifunctional
- prefabricated
- multifunctional examining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
- E02D29/121—Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
- E02D29/14—Covers for manholes or the like; Frames for covers
- E02D29/1409—Covers for manholes or the like; Frames for covers adjustable in height or inclination
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明公开了一种整体装配式多功能检查井,包括预制的井筒、预制的盖板和预制的高度调节环;所述井筒上端开口;所述盖板安装在所述井筒的上端开口处;所述盖板上设有与所述高度调节环的直径相匹配的孔;所述高度调节环下端固定安装在所述盖板上;所述高度调节环的上缘设置有用于固定井圈或井盖的预埋螺栓。本发明的有益效果为:检查井整体预制,施工现场只需建设地基和井坑,大大缩短工期,同时由于检查井为整体预制浇注,不存在现场砌制常见的泄露问题。该整体装配式多功能检查井可适用于供热检查井、污水井、自来水消防井和强弱电通信井等诸多不同领域。
The invention discloses an integrally assembled multifunctional inspection well, which comprises a prefabricated wellbore, a prefabricated cover plate and a prefabricated height adjustment ring; the upper end of the wellbore is open; the cover plate is installed at the upper end opening of the wellbore; The cover plate is provided with a hole matching the diameter of the height adjustment ring; the lower end of the height adjustment ring is fixedly installed on the cover plate; the upper edge of the height adjustment ring is provided with a Embedded bolts for well covers. The beneficial effects of the invention are: the inspection well is integrally prefabricated, only the foundation and the well pit need to be constructed on the construction site, and the construction period is greatly shortened. At the same time, since the inspection well is integrally prefabricated and poured, there is no common leakage problem in on-site masonry. The integrally assembled multifunctional inspection well can be applied to many different fields such as heating inspection wells, sewage wells, running water fire-fighting wells, and strong and weak current communication wells.
Description
技术领域technical field
本发明涉及建筑领域,特别涉及一种整体装配式多功能检查井。The invention relates to the construction field, in particular to an integrally assembled multifunctional inspection well.
背景技术Background technique
现有的检查井都是现场砌制,存在施工周期长和容易泄漏的问题。针对此情况,本发明人研究了一种采用混凝土等材料制造预制检查井的技术方案,只需在施工现场合适的位置布设孔洞,将预制的检查井放置后再进行其他工序即可。Existing inspection wells are built on-site, which has the problems of long construction period and easy leakage. In view of this situation, the inventors have studied a technical solution of using concrete and other materials to manufacture prefabricated inspection wells. It is only necessary to arrange holes at suitable positions on the construction site, place the prefabricated inspection wells, and then proceed to other processes.
由于检查井为预制,现场施工时预留的井坑深度不是恰好似的检查井的井口与路面平齐,当投入使用时车辆经过会发生颠簸的情况,不利于交通安全。Since the inspection well is prefabricated, the depth of the pit reserved during on-site construction is not exactly the same. The wellhead of the inspection well is flush with the road surface. When it is put into use, vehicles will bump when passing by, which is not conducive to traffic safety.
有鉴于此,特提出本发明。In view of this, the present invention is proposed.
发明内容Contents of the invention
本发明要解决的技术问题在于克服现有技术的不足,提供一种整体装配式多功能检查井,缩短施工周期。The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art, provide an integrally assembled multifunctional inspection well, and shorten the construction period.
为解决上述技术问题,本发明采用技术方案的基本构思是:In order to solve the problems of the technologies described above, the present invention adopts the basic idea of technical solution to be:
整体装配式多功能检查井,包括预制的井筒、预制的盖板和预制的高度调节环;所述井筒上端开口;所述盖板安装在所述井筒的上端开口处;所述盖板上设有与所述高度调节环的直径相匹配的孔;所述高度调节环下端固定安装在所述盖板上;所述高度调节环的上缘设置有用于固定井圈或井盖的预埋螺栓。The integrally assembled multifunctional inspection well includes a prefabricated shaft, a prefabricated cover plate and a prefabricated height adjustment ring; the upper end of the shaft is open; the cover is installed at the upper opening of the shaft; There are holes matching the diameter of the height adjustment ring; the lower end of the height adjustment ring is fixedly installed on the cover plate; the upper edge of the height adjustment ring is provided with embedded bolts for fixing well rings or well covers.
上述整体装配式多功能检查井,所述井筒上设置有管道孔,所述井筒可以以管道孔的水平直径所在的面为界分为可拆卸的上下两部分。In the aforementioned integrally assembled multifunctional inspection well, the wellbore is provided with pipe holes, and the wellbore can be divided into detachable upper and lower parts with the surface where the horizontal diameter of the pipe holes is located as the boundary.
上述整体装配式多功能检查井,所述井筒上缘靠近所述井筒中心部分可以向下凹陷形成凹陷部,所述井筒上缘远离所述井筒中心部分形成凸起部,所述凹陷部和凸起部形成台阶状;所述凸起部的内缘与所述盖板的外缘相匹配。In the above-mentioned integrally assembled multifunctional inspection well, the upper edge of the wellbore close to the central part of the wellbore can be recessed downward to form a concave part, and the upper edge of the wellbore is away from the central part of the wellbore to form a convex part, and the concave part and the convex part The raised portion is stepped; the inner edge of the raised portion matches the outer edge of the cover plate.
上述整体装配式多功能检查井,所述高度调节环的高度为盖板上端与路面的距离。For the integrally assembled multifunctional inspection well, the height of the height adjustment ring is the distance between the upper end of the cover plate and the road surface.
上述整体装配式多功能检查井,所述盖板与所述高度调节环可以通过现场浇注的方式固定,也可以通过插拔连接的方式进行固定For the integrally assembled multifunctional inspection well, the cover plate and the height adjustment ring can be fixed by casting on site, or by plug-in connection.
上述整体装配式多功能检查井,所述盖板上设有预埋钢筋,所述高度调节环上设有预留孔和与所述预留孔相通的灌浆孔,所述预埋钢筋与所述预留孔相互配合。In the above-mentioned integrally assembled multifunctional inspection well, the cover plate is provided with pre-embedded steel bars, the height adjustment ring is provided with reserved holes and grouting holes communicating with the reserved holes, and the pre-embedded steel bars are connected to the The above-mentioned reserved holes cooperate with each other.
上述整体装配式多功能检查井,所述井筒内壁上设置有扶手。In the aforementioned integrally assembled multifunctional inspection well, handrails are provided on the inner wall of the well shaft.
上述整体装配式多功能检查井,所述盖板与所述井筒之间可以设置有密封圈。For the integrally assembled multifunctional inspection well, a sealing ring may be provided between the cover plate and the well shaft.
上述整体装配式多功能检查井,所述高度调节环与所述盖板之间页可以设置有密封圈。For the integrally assembled multifunctional inspection well, a sealing ring may be provided between the height adjustment ring and the cover plate.
采用上述技术方案后,本发明与现有技术相比具有以下有益效果:After adopting the above technical solution, the present invention has the following beneficial effects compared with the prior art:
1、检查井整体预制,施工现场只需建设地基和井坑,大大缩短工期,同时由于检查井为整体预制浇注,不存在现场砌制常见的泄露问题;1. The inspection well is prefabricated as a whole. The construction site only needs to build the foundation and well pit, which greatly shortens the construction period. At the same time, because the inspection well is prefabricated and poured as a whole, there is no leakage problem that is common in on-site masonry;
2、根据检查井埋入地下的深度,采用高度调节环调节井口高度,可使井口与路面平齐,解决车辆行驶经过时的颠簸问题;2. According to the depth of the inspection well buried underground, the height adjustment ring is used to adjust the height of the wellhead, which can make the wellhead flush with the road surface and solve the problem of bumps when vehicles pass by;
3、井筒由管道孔水平直径处分为可拆卸的两部分,在安装管道时将上半部分吊起以便管道安装在下半部分的半个管道孔上,便于管道安装;3. The wellbore is divided into two detachable parts by the horizontal diameter of the pipe hole. When installing the pipe, lift the upper half so that the pipe can be installed on the half pipe hole in the lower part, which is convenient for pipe installation;
4、盖板与井筒上缘的台阶状结构配合,提高密封效果和防止移位;4. The cover plate cooperates with the stepped structure on the upper edge of the shaft to improve the sealing effect and prevent displacement;
5、盖板与高度调节环通过预埋钢筋浇注的方式固定,提高安装可靠性;5. The cover plate and the height adjustment ring are fixed by pre-embedded steel bar pouring, which improves the reliability of installation;
6、井筒内部设置有扶手,利于人员检修;6. There are handrails inside the shaft, which is convenient for personnel maintenance;
7、密封圈保证各个部分密封完好,进一步避免泄漏;7. The sealing ring ensures that all parts are sealed well to further avoid leakage;
8、预埋螺栓上设置异型螺母以固定井圈或井盖,非专业工具不能拧下螺母,一定程度上起到了防盗的作用。8. Special-shaped nuts are set on the pre-embedded bolts to fix the well ring or well cover. Non-professional tools cannot unscrew the nuts, which plays a role in preventing theft to a certain extent.
附图说明Description of drawings
图1是本发明整体装配式多功能检查井的俯视结构透视图。Fig. 1 is a top structural perspective view of the integrally assembled multifunctional inspection well of the present invention.
图2是图1中A-A方向的剖面示意图。Fig. 2 is a schematic cross-sectional view along A-A direction in Fig. 1 .
图3是本发明整体装配式多功能检查井设有两个井口实施例的剖面图。Fig. 3 is a cross-sectional view of an embodiment of an integrally assembled multifunctional inspection well provided with two wellheads of the present invention.
图4是本发明整体装配式多功能检查井用作强弱电检查井的俯视图。Fig. 4 is a top view of the integrally assembled multifunctional inspection well of the present invention used as a strong and weak electric inspection well.
图5是图4中B-B方向的剖面示意图。Fig. 5 is a schematic cross-sectional view along the B-B direction in Fig. 4 .
图6是本发明整体装配式多功能检查井的高度调节环的结构示意图。Fig. 6 is a structural schematic diagram of the height adjustment ring of the integrally assembled multifunctional inspection well of the present invention.
图7是图3中整体装配式多功能检查井作为主井时的副井的结构示意图。Fig. 7 is a schematic structural diagram of the auxiliary well when the integrally assembled multifunctional inspection well in Fig. 3 is used as the main well.
上述附图中,1、井筒;2、盖板;3、高度调节环;4、预埋螺栓;5、井圈;6、管道孔;7、预埋钢筋;8、预留孔;9、灌浆孔;10、密封圈;11、扶手;101、上半部分;102、下半部分。In the above drawings, 1. wellbore; 2. cover plate; 3. height adjustment ring; 4. embedded bolt; 5. well ring; 6. pipe hole; 7. embedded steel bar; Grouting hole; 10, sealing ring; 11, handrail; 101, upper half; 102, lower half.
具体实施方式detailed description
下面结合附图和一个具体实施例,对本发明作进一步说明,以助于理解本发明的内容。The present invention will be further described below in conjunction with the accompanying drawings and a specific embodiment, so as to help understand the content of the present invention.
如图1-图7所示,整体装配式多功能检查井,包括预制的井筒1、预制的盖板2和预制的高度调节环3;所述井筒1上端开口;所述盖板2安装在所述井筒1的上端开口处;所述盖板2上设有与所述高度调节环3的直径相匹配的孔;所述高度调节环3下端固定安装在所述盖板2上;所述高度调节环3的上缘设置有用于固定井圈5或井盖的预埋螺栓4。在预埋螺栓4上设置异型螺母以固定井圈5或井盖,非专业工具不能拧下螺母,一定程度上起到了防盗的作用。检查井整体预制,施工现场只需建设地基和井坑,大大缩短工期,同时由于检查井为整体预制浇注,不存在现场砌制常见的泄露问题。根据检查井埋入地下的深度,采用高度调节环3调节井口高度,可使井口与路面平齐,解决车辆行驶经过时的颠簸问题;本实施例中,高度调节环3的高度为盖板2上端与路面的距离。As shown in Figures 1-7, the integrally assembled multifunctional inspection well includes a prefabricated shaft 1, a prefabricated cover plate 2 and a prefabricated height adjustment ring 3; the upper end of the well shaft 1 is open; the cover plate 2 is installed on The upper end opening of the shaft 1; the cover plate 2 is provided with a hole matching the diameter of the height adjustment ring 3; the lower end of the height adjustment ring 3 is fixedly installed on the cover plate 2; The upper edge of the height adjustment ring 3 is provided with embedded bolts 4 for fixing the well ring 5 or the well cover. Special-shaped nuts are set on the pre-embedded bolts 4 to fix the well ring 5 or the well cover, and non-professional tools can not unscrew the nuts, which has played an anti-theft effect to a certain extent. The inspection well is prefabricated as a whole, and the construction site only needs to build the foundation and well pit, which greatly shortens the construction period. At the same time, because the inspection well is prefabricated as a whole, there is no leakage problem that is common in on-site masonry. According to the depth of the inspection well buried underground, the height of the wellhead is adjusted by the height adjustment ring 3, which can make the wellhead flush with the road surface and solve the bumping problem when the vehicle passes by; The distance between the upper end and the road surface.
井筒1上设置有管道孔6,所述井筒1以管道孔6的水平直径所在的面为界分为可拆卸的上下两部分。在安装管道时将上半部分101吊起以便管道安装在下半部分102的半个管道孔6上,便于管道安装,管道安装好后将上半部分101与下半部分102对齐安装,管道恰能够处于在上下两部分拼合的管道孔6内。如此,避免了将很长的管道向管道孔6塞入不便的弊端。A pipe hole 6 is arranged on the shaft 1, and the shaft 1 is divided into two detachable upper and lower parts by the surface where the horizontal diameter of the pipe hole 6 is located. When installing the pipeline, the upper half 101 is lifted so that the pipeline is installed on the half pipeline hole 6 of the lower half 102, which is convenient for pipeline installation. After the pipeline is installed, the upper half 101 and the lower half 102 are aligned and installed, and the pipeline can just It is in the pipe hole 6 that is assembled in the upper and lower parts. In this way, the inconvenience of stuffing a very long pipeline into the pipeline hole 6 is avoided.
所述井筒1上缘靠近所述井筒1中心部分向下凹陷形成凹陷部,所述井筒1上缘远离所述井筒1中心部分形成凸起部,所述凹陷部和凸起部形成台阶状;所述凸起部的内缘与所述盖板2的外缘相匹配。盖板2与井筒1上缘的台阶状结构配合,提高密封效果和防止移位。The upper edge of the wellbore 1 is depressed downward near the central part of the wellbore 1 to form a depression, and the upper edge of the wellbore 1 is away from the central part of the wellbore 1 to form a convex part, and the concave part and the convex part form a stepped shape; The inner edge of the protrusion matches the outer edge of the cover plate 2 . The cover plate 2 cooperates with the stepped structure on the upper edge of the shaft 1 to improve the sealing effect and prevent displacement.
所述盖板2与所述高度调节环3通过现场浇注的方式固定;具体方式为在盖板2上设有预埋钢筋7,高度调节环3上设有预留孔8和与所述预留孔8相通的灌浆孔9,所述预埋钢筋7与所述预留孔8相互配合。预埋钢筋7伸入所述预留孔8中的,由灌浆孔9向预留孔8中灌入水泥砂浆,固化后则盖板2与高度调节环3形成位置相对固定的一体。The cover plate 2 and the height adjustment ring 3 are fixed by on-site casting; the specific method is that the cover plate 2 is provided with a pre-embedded steel bar 7, and the height adjustment ring 3 is provided with a reserved hole 8 and the pre-installed The grouting holes 9 communicated with the reserved holes 8, and the embedded steel bars 7 cooperate with the reserved holes 8. If the pre-embedded steel bar 7 extends into the reserved hole 8, cement mortar is poured into the reserved hole 8 from the grouting hole 9. After solidification, the cover plate 2 and the height adjustment ring 3 form a relatively fixed body.
为便于人员检修,井筒1内壁上设置有扶手11。For the convenience of personnel maintenance, handrails 11 are provided on the inner wall of the well shaft 1 .
此外,盖板2与所述井筒1之间可以设置有密封圈10。高度调节环3与所述盖板2之间也可以设置有密封圈10。密封圈10保证各个部分密封完好,进一步避免泄漏。In addition, a sealing ring 10 may be provided between the cover plate 2 and the shaft 1 . A sealing ring 10 may also be provided between the height adjustment ring 3 and the cover plate 2 . The sealing ring 10 ensures that each part is well sealed to further avoid leakage.
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。The above is only a preferred embodiment of the present invention, it should be pointed out that, for those of ordinary skill in the art, without departing from the principle of the present invention, some improvements and modifications can also be made, and these improvements and modifications can also be made. It should be regarded as the protection scope of the present invention.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610414573.8A CN106400844A (en) | 2016-06-13 | 2016-06-13 | Whole assembly type multifunctional inspection well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610414573.8A CN106400844A (en) | 2016-06-13 | 2016-06-13 | Whole assembly type multifunctional inspection well |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106400844A true CN106400844A (en) | 2017-02-15 |
Family
ID=58006478
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610414573.8A Pending CN106400844A (en) | 2016-06-13 | 2016-06-13 | Whole assembly type multifunctional inspection well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106400844A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111088817A (en) * | 2019-12-30 | 2020-05-01 | 江苏东尚住宅工业有限公司 | Prefabricated assembled cable well and construction method thereof |
WO2020248264A1 (en) * | 2019-06-14 | 2020-12-17 | 胡永生 | Fabricated-type building drainage pipe shaft |
CN112211225A (en) * | 2020-09-17 | 2021-01-12 | 中建三局安装工程有限公司 | Split type municipal well and construction method thereof |
CN112252135A (en) * | 2020-10-30 | 2021-01-22 | 济南城建集团有限公司 | A kind of prefabricated integrated pipeline combined side form and construction method |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100604449B1 (en) * | 2006-04-13 | 2006-07-28 | 주식회사 한국종합기술 | Adjustable height manhole |
CN202208931U (en) * | 2011-08-04 | 2012-05-02 | 杜萍 | Individual combination type inspection well |
CN102587419A (en) * | 2012-03-01 | 2012-07-18 | 安徽省方大水泥制品有限公司 | Assembly type manhole |
CN202390856U (en) * | 2011-11-29 | 2012-08-22 | 福建利新德塑胶制品有限公司 | Combination type inspection well |
CN102817375A (en) * | 2012-08-27 | 2012-12-12 | 安徽建川市政工程有限公司 | Assembly type precast reinforced concrete inspection well system |
CN204510265U (en) * | 2015-01-05 | 2015-07-29 | 贾传东 | Adjustable height inspection well cover |
KR20150117847A (en) * | 2014-04-11 | 2015-10-21 | 주식회사 한국미터택 | Height adjusting apparatus for manhole cover |
CN105386506A (en) * | 2015-12-19 | 2016-03-09 | 徐水县华光市政建材有限公司 | Inspection well |
CN205688463U (en) * | 2016-06-13 | 2016-11-16 | 朱凤起 | Overall assembled multifunctional examining well |
-
2016
- 2016-06-13 CN CN201610414573.8A patent/CN106400844A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100604449B1 (en) * | 2006-04-13 | 2006-07-28 | 주식회사 한국종합기술 | Adjustable height manhole |
CN202208931U (en) * | 2011-08-04 | 2012-05-02 | 杜萍 | Individual combination type inspection well |
CN202390856U (en) * | 2011-11-29 | 2012-08-22 | 福建利新德塑胶制品有限公司 | Combination type inspection well |
CN102587419A (en) * | 2012-03-01 | 2012-07-18 | 安徽省方大水泥制品有限公司 | Assembly type manhole |
CN102817375A (en) * | 2012-08-27 | 2012-12-12 | 安徽建川市政工程有限公司 | Assembly type precast reinforced concrete inspection well system |
KR20150117847A (en) * | 2014-04-11 | 2015-10-21 | 주식회사 한국미터택 | Height adjusting apparatus for manhole cover |
CN204510265U (en) * | 2015-01-05 | 2015-07-29 | 贾传东 | Adjustable height inspection well cover |
CN105386506A (en) * | 2015-12-19 | 2016-03-09 | 徐水县华光市政建材有限公司 | Inspection well |
CN205688463U (en) * | 2016-06-13 | 2016-11-16 | 朱凤起 | Overall assembled multifunctional examining well |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020248264A1 (en) * | 2019-06-14 | 2020-12-17 | 胡永生 | Fabricated-type building drainage pipe shaft |
CN111088817A (en) * | 2019-12-30 | 2020-05-01 | 江苏东尚住宅工业有限公司 | Prefabricated assembled cable well and construction method thereof |
CN112211225A (en) * | 2020-09-17 | 2021-01-12 | 中建三局安装工程有限公司 | Split type municipal well and construction method thereof |
CN112252135A (en) * | 2020-10-30 | 2021-01-22 | 济南城建集团有限公司 | A kind of prefabricated integrated pipeline combined side form and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106400844A (en) | Whole assembly type multifunctional inspection well | |
CN202124865U (en) | Quick plugging device for dewatering wellhead of sand-free cement pipe deep well | |
CN103498486B (en) | A kind of sleeve pipe that adopts implements the method for shutoff to ater-casting precipitation pipe well | |
CN106245526A (en) | The splicing structure of mining under railways protecting wall, straight wall and shield and construction method | |
CN103774687A (en) | Single-pipe tower prefabricated spiral steel pipe pile foundation | |
CN104631507B (en) | A kind of manufacture method of concrete combined manhole cover | |
CN208121807U (en) | A kind of matched benzvalene form interface prefabrication type reinforced concrete water collection well of pipe gallery | |
KR101660400B1 (en) | Manhole capable of regulating height of cover and construction method thereof | |
CN205688463U (en) | Overall assembled multifunctional examining well | |
CN108360570A (en) | Bituminous paving inspection shaft gug construction method | |
CN203514332U (en) | Casing for blocking dewatering tube well of post-cast strip | |
CN2509250Y (en) | Integral one-time forming reinforced concrete manhole with climbing ladder | |
CN205576973U (en) | Circular inspection shaft of prefabricated formula | |
CN211340839U (en) | Lamp pole base structure | |
CN210266220U (en) | Water leakage-proof type embedded water stop joint device | |
CN204456202U (en) | Fire valve well | |
CN211621876U (en) | Assembled inspection shaft with prevent falling, explosion-proof function | |
CN107724419A (en) | A kind of equipment prefabricated foundation locator and its application method | |
CN203905061U (en) | Municipal anti-theft well lid | |
CN209508995U (en) | One kind closing water valve device and its shut-in well structure | |
KR100936097B1 (en) | Manhole height adjusting device | |
CN207392239U (en) | A kind of prefabricated piping lane of two-piece unit formula | |
CN208685671U (en) | A kind of height-adjustable casting iron well lid of fitting town road | |
CN211395767U (en) | Safety well cover | |
CN219364714U (en) | Novel rainwater-proof well cover plate assembly for inspection and repair |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170215 |