CN106400789A - Pile toe formwork fixing process - Google Patents

Pile toe formwork fixing process Download PDF

Info

Publication number
CN106400789A
CN106400789A CN201610345287.0A CN201610345287A CN106400789A CN 106400789 A CN106400789 A CN 106400789A CN 201610345287 A CN201610345287 A CN 201610345287A CN 106400789 A CN106400789 A CN 106400789A
Authority
CN
China
Prior art keywords
formwork
supports
support
pile
pile toe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610345287.0A
Other languages
Chinese (zh)
Inventor
蔡灿
蔡一灿
芦刚
付建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201610345287.0A priority Critical patent/CN106400789A/en
Publication of CN106400789A publication Critical patent/CN106400789A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a pile toe formwork fixing process. The pile toe formwork fixing process comprises the following operating steps of 1, making four supports the same in length from square steel; 2, bending the position, 45mm away from each end, of each support into a 135-degree angle; 3, machining a hole with the diameter being 20mm in the position, 25mm away from each end, of each support, wherein each hole can allow an M16 bolt to pass through smoothly; 4, welding three of the supports to the lower portion, the left side and the right side of a pile toe formwork correspondingly, and welding the remaining support to the upper portion of the pile toe formwork; and 5, fixedly fastening the four supports with the M16 bolts, wherein the specification of the square steel is 30mm*30mm*2.5mm, and the pile toe formwork is located in the center of the four supports. According to the pile toe formwork fixing process, the pile toe formwork is fixed to the middle of a square frame spliced by the square steel and the bolts; support rigidity is enhanced; and the problems that support force is insufficient, the formwork is loosened, and the contact face between a pile toe and a pile body is not tight, so that slurry leakage and slab staggering are caused are solved.

Description

Pile top template technique for fixing
Technical field
The invention belongs to building field, more particularly, to a kind of pile top template technique for fixing.
Background technology
Precast prestressed square pile pile top prefabricated using rear formwork casting craft, traditional pile top formwork support process includes mould Plate is fixing and support top two parts, template technique for fixing by means of the round steel cuff of a diameter of 20mm of HPB300, By the timber wedge extruding of four direction, traditional handicraft tedious process, the auxiliary material of employing is more, takes longer Work quality is difficult to ensure that, round steel cuff is yielding, and timber wedge is fragile, and template is easy with the contact position of timber wedge Slip, component easily occurs running the Appearance quality defects such as mould, spillage, and bottom adopts flitch supporting process, steadiness Poor, work progress easily causes pile top skewness, timber wedge often reaches pile top surface, to pile top Obstacle is caused in surface receipts face, faulting of slab ends or pitted skin easily, more using timber wedge, easily causes live debris Many, dirty and messy disorder phenomenon, template steadiness is poor, and personnel of vibrating dare not be vibrated, and easily causes leakage is shaken, bubble etc. Problem, affects pile top density.
Content of the invention
The present invention is exactly directed to above technical problem, provides a kind of pile top template technique for fixing.
The present invention for achieving the above object, employs the following technical solutions:Pile top template technique for fixing, including following Operating procedure:
(1), square steel is done four isometric supports;
(2), each support is bent into 135 ° of angles at the 45mm of termination;
(3), each support turns the hole of an a diameter of 20mm, this Kong Nengrang M16 at the 25mm of termination Bolt pass through;
(4), three supports are respectively welded at below pile top template, the left side and the right side, a root bead is connected on stake Above sharp template;
(5), four supports are fixed tight with the bolt of M16.
The specification of described square steel is 30mm × 30mm × 2.5mm.
Described pile top template is in the center of four supports.
Compared with prior art, the invention has the beneficial effects as follows:
(1), the square bearer that the reinforcing bar cuff improvement of a diameter of for HPB235 20mm is spliced into by square steel bolt, Increased the rigidity of support, solve that support force is not enough, template loosens, pile top and pile body contact surface imprecision, Produce the problem of spillage faulting of slab ends;
(2), support and template are welded together, improve template and the rigidity of pile body overall connection, keep away The problem having exempted to form sand line due to some areas laminating spillage closely not caused in casting process;
(3), the extrusion process of timber wedge is improved square steel bolt tight technique, enhance the adjustability that template fixes With steadiness it is therefore prevented that because the timber wedge of generation of vibrating loosens, spillage runs the problem of mould in work progress.
Brief description
Fig. 1 is the structural representation of the present invention;
In figure:1st, support;2nd, bolt;3rd, pile top template.
Specific embodiment
The invention will be further described with reference to the accompanying drawings and examples:
As illustrated, pile top template technique for fixing, including following operating procedure:
(1), square steel is done four isometric supports 1;
(2), each support 1 is bent into 135 ° of angles at the 45mm of termination;
(3), each support 1 turns the hole of an a diameter of 20mm, this Kong Nengrang M16 at the 25mm of termination Bolt 2 pass through;
(4), three supports 1 are respectively welded at below pile top template 3, the left side and the right side, a root bead connects Above pile top template 3;
(5), four supports 1 are used the bolt 2 of M16 fixing tight.
The specification of described square steel is 30mm × 30mm × 2.5mm.
Described pile top template 3 is in the center of four supports 1.
Pile top template of the present invention is fixed on the centre position of the square bearer being spliced into by square steel bolt 2, increased and props up The rigidity of support, solves that support force is not enough, and template loosens, pile top and pile body contact surface imprecision, produces spillage The problem of faulting of slab ends.
Above in conjunction with accompanying drawing, the present invention is exemplarily described it is clear that the present invention implement be not subject to above-mentioned The restriction of mode, as long as employing the various improvement that method of the present invention design and technical scheme are carried out, or without Improve and directly apply to other occasions, all within protection scope of the present invention.

Claims (3)

1. pile top template technique for fixing is it is characterised in that include following operating procedure:
1., square steel is done four isometric supports (1);
2., each support (1) is bent into 135 ° of angles at the 45mm of termination;
3., each support (1) turns the hole of an a diameter of 20mm, this Kong Nengrang at the 25mm of termination The bolt (2) of M16 passes through;
4., three supports (1) are respectively welded at below pile top template (3), the left side and the right side, one Root bead is connected on above pile top template (3);
5., four supports (1) are used the bolt (2) of M16 fixing tight.
2. pile top template technique for fixing according to claim 1 is it is characterised in that the rule of described square steel Lattice are 30mm × 30mm × 2.5mm.
3. pile top template technique for fixing according to claim 1 is it is characterised in that described pile top template (3) it is in the center of four supports (1).
CN201610345287.0A 2016-05-23 2016-05-23 Pile toe formwork fixing process Pending CN106400789A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610345287.0A CN106400789A (en) 2016-05-23 2016-05-23 Pile toe formwork fixing process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610345287.0A CN106400789A (en) 2016-05-23 2016-05-23 Pile toe formwork fixing process

Publications (1)

Publication Number Publication Date
CN106400789A true CN106400789A (en) 2017-02-15

Family

ID=58006742

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610345287.0A Pending CN106400789A (en) 2016-05-23 2016-05-23 Pile toe formwork fixing process

Country Status (1)

Country Link
CN (1) CN106400789A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0581688A1 (en) * 1992-07-31 1994-02-02 Bouygues Offshore Method and device for forcing a pipe into the soil by ramming, especially for making a pile
CN102776879A (en) * 2012-08-01 2012-11-14 天津建城基业集团有限公司 Concrete centrifugal square pile and forming mold thereof
CN203834474U (en) * 2014-04-30 2014-09-17 江苏山海建设工程有限公司 Pile tip special-purpose formwork
CN104480933A (en) * 2014-11-14 2015-04-01 福建建华管桩有限公司 Manufacturing method of pencil type pipe pile
CN104695434A (en) * 2015-02-25 2015-06-10 洛阳理工学院 Combined pile toe for steel pipe pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0581688A1 (en) * 1992-07-31 1994-02-02 Bouygues Offshore Method and device for forcing a pipe into the soil by ramming, especially for making a pile
CN102776879A (en) * 2012-08-01 2012-11-14 天津建城基业集团有限公司 Concrete centrifugal square pile and forming mold thereof
CN203834474U (en) * 2014-04-30 2014-09-17 江苏山海建设工程有限公司 Pile tip special-purpose formwork
CN104480933A (en) * 2014-11-14 2015-04-01 福建建华管桩有限公司 Manufacturing method of pencil type pipe pile
CN104695434A (en) * 2015-02-25 2015-06-10 洛阳理工学院 Combined pile toe for steel pipe pile

Similar Documents

Publication Publication Date Title
CN104594500B (en) Integrated slab column formwork structure system and construction method
CN204703498U (en) Wall of High-building deformation joint template construction structure
CN201627381U (en) Composite concrete-filled steel tube buckling-resistant bracing member
CN102433988A (en) Wall column formwork on two sides of expansion joint and construction method thereof
CN101086184A (en) Annular closure structure formwork support method
CN104264984A (en) Formwork for concrete structure pouring and pouring construction method
CN103603494B (en) A kind of ultra-thin steel truss sloping core construction method and formwork structure
CN103452319A (en) Chiseling-free device for concrete splicing interface and construction method for chiseling-free device
CN205976468U (en) Shear force wall structural distortion seam construction formwork assembly
CN209482709U (en) A kind of in-situ concrete wall subsiding crack typified form
CN206448272U (en) Roadbed side slope arched framework one-time-shaped mould
CN206625553U (en) For pouring the formwork bracing system of high-low bay structure simultaneously
CN202467184U (en) Novel opposite-pull screw for reinforcing edge beam side form
CN106400789A (en) Pile toe formwork fixing process
CN105155838B (en) A kind of quick detachable high-strength building formwork
CN112144865A (en) Early-dismantling formwork support system
CN105317146A (en) Steel structure earthquake-resistant floor for construction and manufacturing method
CN104912333B (en) wall construction system and construction method
CN208235940U (en) One kind is for reinforcing mold between the sinking of cast-in-situ floor combined type
CN213683188U (en) Early-dismantling formwork support system
CN211817957U (en) Full-automatic hydraulic walking dragging mold
CN102587653A (en) Novel reinforcing tie bolt for side form of side beam
CN204703499U (en) Wall of High-building deformation joint template
CN208792765U (en) The fixed keel of the template of filled wall collar tie beam
CN210976608U (en) Can have enough to meet need latticed beam formwork of stereotyping and prop up and establish system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170215

RJ01 Rejection of invention patent application after publication