[go: up one dir, main page]

CN106368605B - A kind of top drive formula rock-core borer - Google Patents

A kind of top drive formula rock-core borer Download PDF

Info

Publication number
CN106368605B
CN106368605B CN201510744834.8A CN201510744834A CN106368605B CN 106368605 B CN106368605 B CN 106368605B CN 201510744834 A CN201510744834 A CN 201510744834A CN 106368605 B CN106368605 B CN 106368605B
Authority
CN
China
Prior art keywords
power head
tower
integrated form
drive formula
core borer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510744834.8A
Other languages
Chinese (zh)
Other versions
CN106368605A (en
Inventor
欧阳志强
沈博智
谭颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENGYANG ZHONGDI EQUIPMENT PROSPECTING ENGINEERING MACHINERY Co Ltd
Original Assignee
HENGYANG ZHONGDI EQUIPMENT PROSPECTING ENGINEERING MACHINERY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENGYANG ZHONGDI EQUIPMENT PROSPECTING ENGINEERING MACHINERY Co Ltd filed Critical HENGYANG ZHONGDI EQUIPMENT PROSPECTING ENGINEERING MACHINERY Co Ltd
Priority to CN201510744834.8A priority Critical patent/CN106368605B/en
Publication of CN106368605A publication Critical patent/CN106368605A/en
Application granted granted Critical
Publication of CN106368605B publication Critical patent/CN106368605B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

A kind of top drive formula rock-core borer, including boring tower (1), tower top pulley blocks (2), tower seat (3), integrated form power head (4), drilling rod (5), master winch (6), main lifting rope (7), leading block (8) and guide cords (9);Tower top pulley blocks (2) are located at the top of boring tower (1), and main lifting rope (7) is stretched out from master winch (6), pass through tower top pulley blocks (2) and connect with integrated form power head (4);Guide cords (8) are located at integrated form power head (4) two sides, and upper and lower ends, which are fixedly connected with, tightens it;Leading block (9) is mounted on integrated form power head (4) two sides, and the top and bottom of every side are respectively there are two pulley, the two pulleys are to be arranged in juxtaposition, and guide cords (8) are clipped between the two pulleys.The present invention is by adopting the above-described technical solution, compared with prior art, so that drilling machine can once be packed into more drilling rods, easy to operate, power waste is few, and working efficiency greatly improves, integrated control easy to accomplish.

Description

A kind of top drive formula rock-core borer
Technical field
The invention belongs to geological prospecting apparatus fields, it particularly relates to a kind of top drive formula rock-core borer.
Background technique
Fig. 1 is shown to be surveyed industry use to obtain a kind of rock-core borer the most universal now, is mainly consisted of the following parts: Input power 101, rack 103, elevator 104, power distributor box 105, drilling rod 106, power head 107, gives oil inlet at gearbox 102 Cylinder 108, guide rod 109 and bevel gear box 111.
The effect of existing rock-core borer each section is following (input power 101, gearbox 102, rack 103 are not described herein):
1, the boring tower that elevator 104 is generally built with construction site on the spot is used cooperatively, and is mainly used for lifting by crane drilling rod 106, with Drilling rod 106 is facilitated to be fitted into power head 107 or retract out from power head 107.
2, the power that power distributor box 105 is used to be transmitted through gearbox 103 is assigned to bevel gear box 111 and elevator 104.
3, power distributor box 105 is transmitted through after the power come turns and is transmitted to main shaft 108 by bevel gear box 111.
4, main shaft 108 is hollow, and to be packed into drilling rod 106, the upper end of main shaft 108 is connected with power head 107, can will bore tooth Roller box 111 is transmitted through the power come and is transmitted to power head 107.
5, power head 107 receive bevel gear box 111 by main shaft 108 be transmitted through come power drive drilling rod 106 rotate.
6, feed oil cylinder 110 makes power head 107 move up and down.
7, drilling rod 106 generates rotary motion under the action of power head 107, generates under the action of being fed oil cylinder 110 Lower movement is downwards drilling, is then upwards taking-up.
8, the direction that guide rod 109 guarantees that power head 107 moves up and down is consistent.
The course of work of existing rock-core borer is as follows: opening common rock-core borer, runs the elevator of common rock-core borer 104, it is matched with tower top pulley and lifting rope, slings the drilling rod 106 for not entering working condition, be encased in the dynamic of common rock-core borer In power head 107, lifting rope is unclamped;Power head 107 and feed oil cylinder 110 are run, creeps into drilling rod 106 down;When drilling rod It effectively pierces after length all pierces underground, just operation elevator 104 is packed into another drilling rod and has been drilled into underground with front again Drilling rod be connected, continue to creep into, until reaching target and piercing depth.After reaching target and piercing depth, stop drilling, according to The process of above-mentioned loading drilling rod operates in turn, takes out drilling rod by root, that is, completes entire drilling operation process.
Common rock-core borer has following some shortcomings:
1, cumbersome, working efficiency is lower.The distance that power head moves upwards is limited by feed oil cylinder stroke, up and down Move distance is limited, and move upwards also can be such that the stability of power head becomes very poor apart from excessive, so a drilling rod all bores Enter underground, power head needs up and down reciprocatingly to run could complete several times;And when being packed into drilling rod, one can only be once filled.
2, power waste is larger.Input power becomes vertical rotation fortune by repeatedly transmitting, and by lateral rotation movement It is dynamic, cause a large amount of power wastes.
3, limited strength is crept into.In drilling, feed oil cylinder is shunk, and is pressing against drilling rod drilling machine, but is fed the pressure that oil cylinder is formed Power leans on the weight of power head one end itself mainly from common rock-core borer, when drilling rod is when ground end encounters harder rock matter, very Extremely common rock-core borer can be jacked up by one end of power head.
4, it is difficult to realize integrated control.
Summary of the invention
To solve the problems in background technique, the present invention provides a kind of top drive formula rock-core borers.
The technical scheme is that a kind of top drive formula rock-core borer, including boring tower, tower top pulley blocks, tower seat, integrated form Power head, drilling rod, master winch, main lifting rope, leading block and guide cords;Tower top pulley blocks are located at the top of boring tower, main lifting rope from Master winch stretches out, and passes through tower top pulley blocks and connect with integrated form power head;Guide cords are located at integrated form power both sides of head, Upper and lower ends, which are fixedly connected with, tightens it;Leading block is mounted on integrated form power both sides of head, and the top and bottom of every side are each There are two pulley, the two pulleys are to be arranged in juxtaposition, and guide cords are clipped between the two pulleys.
As an improvement the top drive formula rock-core borer further includes secondary elevator and secondary lifting rope, for lifting by crane drilling rod or rock Heart sample block.
The further technical solution of the present invention is: the integrated form power head of the top drive formula rock-core borer include whole case, Power head, gearbox, input power and clump weight;Power head, gearbox and input power are installed in whole case;Power head It is connect positioned at whole bottom portion, and with the drilling rod of lower section;Gearbox is located at right above power head and the two is connected, input power position Right above gearbox and the two is connected;Clump weight is located inside whole case, and it is dynamic to adjust integrated form suitably to increase and decrease its quantity The weight of power head.
Further technical solution is the present invention: the top drive formula rock-core borer further includes hydraulic cylinder;Hydraulic cylinder One end be fixedly connected with tower seat;Be fixedly connected at the top of the upper end of guide cords and boring tower, lower end bypass fixed pulley after with liquid The other end of compressing cylinder connects.
The further technical solution of the present invention is: the top drive formula rock-core borer further includes that hydraulic cylinder and oil cylinder are hung Ear;Oil cylinder hangers is located at the two sides of suspension hook, and two sides are respectively equipped with a secondary hydraulic cylinder, and the lower end of hydraulic cylinder is with integrated form power head It is connected.
By adopting the above-described technical solution, compared with prior art, the invention enables drilling machine can once be packed into it is more Root drilling rod (depending on the technological parameter of top drive formula rock-core borer), it is easy to operate;The distance that integrated form power head moves upwards It is significantly promoted, makes its round trip that can pierce more drilling rods;Input power transmittance process shortens, and does not change the transmitting of power Direction, power waste is few, and working efficiency greatly improves;Creeping into strength can be by changing the clump weight in integrated form power head Quantity and change;Integrated control easy to accomplish;The structure that Guide rollers clamp guide cords makes its steering capability become more excellent, And guide cords will not be caused to damage when integrated form power head forms reverse rotation;It is added in guide cords end hydraulic The structure of oil cylinder designs, and not only can guarantee that the guide cords moment was in tensioned state, but also can guarantee that guide cords will not be because tightening power It is caused to snap beyond its tolerance range;The structure design that hydraulic cylinder is added between suspension hook and integrated form power head, can It effectively avoids top from driving churn the screw thread of main shaft and drilling rod is caused to damage when dismounting drilling rod.
Detailed description of the invention
Fig. 1 is existing structural schematic diagram;
Fig. 2 is structural schematic diagram of the invention;
Fig. 3 is the structural schematic diagram of component 4 in Fig. 2;
Fig. 4 is the partial enlargement structural representation of part A in Fig. 2;
Fig. 5 is the partial enlargement structural representation of part B in Fig. 2.
Specific embodiment
Embodiment
As shown in Fig. 2, a kind of top drive formula rock-core borer, including boring tower 1, tower top pulley blocks 2, tower seat 3, integrated form power head 4, drilling rod 5, master winch 6, main lifting rope 7, leading block 8 and guide cords 9;Tower top pulley blocks 2 are located at 1 top of boring tower, main lifting rope 7 It stretches out from master winch 6, pass through tower top pulley blocks 2 and is connect with integrated form power head 4;Guide cords 8 are located at integrated form power head 4 Two sides, upper and lower ends, which are fixedly connected with, tightens it;Leading block 9 is mounted on 4 two sides of integrated form power head, every side it is upper End and lower end are respectively there are two pulley, the two pulleys are to be arranged in juxtaposition, and guide cords 8 are clipped between the two pulleys;The top Drive formula rock-core borer further includes secondary elevator 10 and secondary lifting rope 11, for lifting by crane drilling rod or core sample block.
As shown in figure 3, the integrated form power head 4 of the top drive formula rock-core borer includes whole case 401, power head 402, becomes Fast case 403, input power 404 and clump weight 206;Power head 402, gearbox 403 and input power 404 are installed in whole case In 401;Power head 402 is located at 401 bottom of whole case, and connect with the drilling rod of lower section;Gearbox 403 is being located at power head 402 just Top and the two are connected, and input power 404 is located at right above gearbox 403 and the two is connected;Clump weight 206 is located at whole case Inside 201, its quantity can be increased and decreased suitably to adjust the weight of integrated form power head 4.
As shown in figure 4, the top drive formula rock-core borer further includes hydraulic cylinder 12;One end of hydraulic cylinder 12 and tower seat 3 It is fixedly connected;The upper end of guide cords 9 is fixedly connected with the top of boring tower 1, lower end bypass fixed pulley 13 after with hydraulic cylinder 12 The other end connection.
As shown in figure 5, the top drive formula rock-core borer further includes hydraulic cylinder 14 and oil cylinder hangers 15;Oil cylinder hangers 15 In the two sides of suspension hook 16, two sides are respectively equipped with a secondary hydraulic cylinder 14, and the lower end of hydraulic cylinder 14 is connected with integrated form power head 4.
When work, master winch 6 is opened, integrated form power head 4 is parked in by appropriate position by main lifting rope 7 and tower top pulley blocks 2 It sets;Start secondary elevator 10, sling the drilling rod 5 for not entering working condition by secondary lifting rope 11 and tower top pulley blocks 2, under drilling rod 5 It holds and is connected with the drilling rod for having been drilled into ground end, unclamping secondary lifting rope 11 (can also be again loaded into drilling rod, drilling rod is packed into quantity and drives according to top Depending on the technological parameter of formula rock-core borer), the upper end of drilling rod 5 is connected with integrated form power head 4;Open integrated form power head 4, it drives drilling rod 5 to rotate, gradually unclamps master winch 6, integrated form power head 4 is pressing against drilling rod 5 under the effect of gravity and is being rotated down brill It ensure that each drilling direction of integrated form power head 4 is consistent into, guiding device (i.e. leading block 8 with guide cords 9).When Reach after target pierces depth, starts master winch 6, integrated form power head 4 is allowed to be parked in appropriate location, that is, stop drilling.According to upper The process for stating loading drilling rod operates in turn, takes out drilling rod by root, that is, completes entire drilling operation process.
The present invention is not limited to above-mentioned preferred embodiment, and anyone should learn that is made under the inspiration of the present invention Structure change, it is all that there is same or similar technical solution with of the invention, it all belongs to the scope of protection of the present invention.

Claims (2)

1. a kind of top drive formula rock-core borer, it is characterised in that: including boring tower, tower top pulley blocks, tower seat, integrated form power head, bore Bar, master winch, main lifting rope, leading block and guide cords;Boring tower and master winch are set on tower seat, and tower top pulley blocks, which are located at, to be bored Top of tower, main lifting rope are stretched out from master winch, are passed through tower top pulley blocks and are connect with integrated form power head;Leading block is mounted on collection Accepted way of doing sth power both sides of head, the top and bottom of every side are respectively there are two pulley, the two pulleys are to be arranged in juxtaposition, and guide cords are clipped in Between the two pulleys;The top drive formula rock-core borer further includes hydraulic cylinder;One end of hydraulic cylinder is fixedly connected with tower seat; It is fixedly connected at the top of the upper end of guide cords and boring tower, lower end is connect after bypassing fixed pulley with the other end of hydraulic cylinder;Institute The integrated form power head for stating top drive formula rock-core borer includes whole case, power head, gearbox, input power and clump weight;Power Head, gearbox and input power are installed in whole case;Power head is located at whole bottom portion, and connect with the drilling rod of lower section; Gearbox is located at right above power head and the two is connected, and input power is located at right above gearbox and the two is connected;Clump weight position Inside whole case, its quantity can be increased and decreased suitably to adjust the weight of integrated form power head;The top drive formula rock-core borer also wraps Include hydraulic cylinder and oil cylinder hangers;Oil cylinder hangers is located at the two sides of suspension hook, and two sides are respectively equipped with a secondary hydraulic cylinder, hydraulic cylinder Lower end is connected with integrated form power head.
2. drive formula rock-core borer in top according to claim 1, it is characterised in that: the top drive formula rock-core borer further includes pair Elevator and secondary lifting rope, for lifting by crane drilling rod or core sample block.
CN201510744834.8A 2015-11-05 2015-11-05 A kind of top drive formula rock-core borer Active CN106368605B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510744834.8A CN106368605B (en) 2015-11-05 2015-11-05 A kind of top drive formula rock-core borer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510744834.8A CN106368605B (en) 2015-11-05 2015-11-05 A kind of top drive formula rock-core borer

Publications (2)

Publication Number Publication Date
CN106368605A CN106368605A (en) 2017-02-01
CN106368605B true CN106368605B (en) 2019-01-15

Family

ID=57880206

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510744834.8A Active CN106368605B (en) 2015-11-05 2015-11-05 A kind of top drive formula rock-core borer

Country Status (1)

Country Link
CN (1) CN106368605B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111577150A (en) * 2020-06-18 2020-08-25 广西中岩实业发展有限公司 Multifunctional drilling tower

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6675915B2 (en) * 2001-09-25 2004-01-13 Ingersoll-Rand Company Drilling machine having a rotary head guide
CN101392629B (en) * 2008-09-18 2010-08-11 山东正元地质资源勘查有限责任公司烟台分公司 Portable all-hydraulic core drilling rig
CN201351465Y (en) * 2009-01-20 2009-11-25 郑州海来能源科技有限公司 Fixing device of floating oil cylinder base on top drive lifting ring
CN102213076B (en) * 2011-05-25 2013-04-10 张勇斌 Vertical shaft type drilling machine with long feeding travel
CN202073513U (en) * 2011-05-26 2011-12-14 上海城地建设发展有限公司 Verticality control device for drill rod
CN102505920B (en) * 2011-12-07 2013-08-28 中交第三航务工程勘察设计院有限公司 Two-winch hydraulic lifting drill tower
CN102536224A (en) * 2012-02-22 2012-07-04 上海艾都能源科技有限公司 Convenient sampling drill bit
CN203685020U (en) * 2014-01-14 2014-07-02 铁道第三勘察设计院集团有限公司 Super-light shallow hole sampling drill
CN204060556U (en) * 2014-08-11 2014-12-31 上海中联重科桩工机械有限公司 Pile driver machine and power head pressurizing and pulling device thereof
CN206144459U (en) * 2015-11-05 2017-05-03 衡阳中地装备探矿工程机械有限公司 Formula core drill is driven on top

Also Published As

Publication number Publication date
CN106368605A (en) 2017-02-01

Similar Documents

Publication Publication Date Title
CN105275415B (en) Full-automatic continuous drilling rig
CN205840770U (en) A kind of impact type rotary drilling rig device being applicable to heavy caliber construction
CN103183293B (en) Rope coring and arranging winch with heavy hook falling freely
CN201310342Y (en) Continuous-tube well logging machine
CN205977096U (en) Hydraulic pressure gallery rig for coal mine
CN203655147U (en) Power head for deep-hole core drilling machine
CN202832296U (en) Drill rod lifting device on drilling equipment
CN106368605B (en) A kind of top drive formula rock-core borer
CN205949909U (en) Special rig of table bracket
CN112360364A (en) Automatic discharging device for drilling drill rods
CN103291210B (en) Gate-type double-tower gear-driven drilling machine
CN202300240U (en) Single-guide rail dual-hydraulic cylinder high-accuracy bit feeding system
CN107420041B (en) Full hydraulic power head core drill without drilling tower
CN206144459U (en) Formula core drill is driven on top
CN202531020U (en) Long earth auger using hydraulic main hoist
CN201103342Y (en) Shallow-stratum drilling machine
CN108756744B (en) Shield type casing internal under-balance gas reverse circulation drilling equipment
CN203008822U (en) Multifunctional power tongs
CN202866653U (en) Drilling machine double-main-rod guide rail type hydraulic lifting mechanism
CN110359446A (en) Revolve expanding steel tube pile rotary drilling rig and its construction method
CN204827281U (en) Non - excavation rig centre gripping, loading and unloading drilling rod device
CN115711086A (en) Deep hole core drilling machine
CN108755686A (en) The pile-driving system of piling machine
CN206972168U (en) A kind of drilling cramp lift structure of boring mechanic
CN203114166U (en) Medium-and-large hole type engineering driller

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant