CN106320162A - Prefabricated assembly cap beam structure with steel shear keys and construction method - Google Patents
Prefabricated assembly cap beam structure with steel shear keys and construction method Download PDFInfo
- Publication number
- CN106320162A CN106320162A CN201610704462.0A CN201610704462A CN106320162A CN 106320162 A CN106320162 A CN 106320162A CN 201610704462 A CN201610704462 A CN 201610704462A CN 106320162 A CN106320162 A CN 106320162A
- Authority
- CN
- China
- Prior art keywords
- concrete
- prefabricated
- steel
- shear key
- shear
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/30—Metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及一种采用钢剪力键的预制拼装盖梁结构及施工方法,预制拼装盖梁的钢剪力键采用公母配对式剪力键,材料为球墨铸铁或优质碳素结构钢铸造而成。将盖梁划分三段分别预制的构件,在两外挂段拼接处预埋母型剪力键,中间段拼接处预埋公型剪力键;用起重机分别吊装中间段构件,两外侧段构件,在校准位置后,穿放并张拉第一阶段预应力筋使三段结构连接成整体,完成预应力孔道注浆封闭并封锚;通过预留的注浆孔道,对母型钢剪力键内部高压注浆,处理公、母剪力键之间的接缝,本发明与现有技术相比,减小了传统大、小剪力键在预制阶段模板制作的复杂程度;采用公母配对的方式,不仅方便吊装过程中的位置确定,而且更加有效地促进构件之间的咬合。
The invention relates to a prefabricated assembled cover beam structure and construction method using steel shear keys. The steel shear keys of the prefabricated assembled cover beam adopt male-female paired shear keys, and the material is cast from ductile iron or high-quality carbon structural steel. become. Divide the cover beam into three prefabricated components, pre-embed the female shear key at the joint of the two external hanging sections, and pre-embed the male shear key at the joint of the middle section; use a crane to hoist the middle section and the two outer section components separately, After the position is calibrated, the first-stage prestressed tendons are threaded and stretched to connect the three sections of the structure into a whole, and the prestressed channel is closed and anchored by grouting; High-pressure grouting to deal with the joint between the male and female shear keys. Compared with the prior art, the present invention reduces the complexity of traditional large and small shear keys in the prefabrication stage; This method not only facilitates the determination of the position during the hoisting process, but also more effectively promotes the engagement between components.
Description
技术领域technical field
本发明涉及一种预制盖梁结构,尤其是一种采用钢剪力键的预制盖梁结构及施工方法。The invention relates to a prefabricated cover beam structure, in particular to a prefabricated cover beam structure and a construction method using steel shear keys.
背景技术Background technique
混凝土桥梁的现浇施工,需要大量的模板和支撑系统,在不良施工条件下,搭设满堂支架方案不可行。盖梁施工属于高空作业,现浇大量混凝土,施工风险大。采用预制拼装盖梁的方式可以加快施工速度,保证质量,同时考虑到规模效应具有很好的经济性。The cast-in-place construction of concrete bridges requires a large number of formwork and support systems. Under unfavorable construction conditions, it is not feasible to erect a full-height bracket. The construction of the cover beam belongs to high-altitude operations, and a large amount of concrete is poured on site, so the construction risk is high. The method of prefabricated and assembled cover beams can speed up the construction speed and ensure the quality, and at the same time, it is very economical considering the scale effect.
现阶段,在预制桥梁拼装方面的抗剪设计主要采用的是键齿式的剪力键,具体分为大剪力键和小剪力键。其不足在于预制模板时需要做凹凸棱角造型,施工复杂,且咬合匹配度不高。因此,需要一种新型公母配对钢剪力键,熔锻钢铁易成型,构件精度可到毫米,匹配程度高,预埋处理无需模板特殊细致处理,可以避免以上问题。At this stage, the shear design of prefabricated bridge assembly mainly adopts toothed shear keys, which are specifically divided into large shear keys and small shear keys. The disadvantage is that the prefabricated formwork needs to be shaped with concave-convex edges and corners, the construction is complicated, and the degree of occlusal matching is not high. Therefore, there is a need for a new male-female paired steel shear key. Melted and forged steel is easy to form, the precision of the components can reach millimeters, and the matching degree is high. The pre-embedded treatment does not require special and careful treatment of the formwork, which can avoid the above problems.
发明内容Contents of the invention
本发明提出一种采用钢剪力键的预制拼装盖梁结构及施工方法,该结构采用新型公母配对的钢剪力键,并应用于盖梁的预制拼装施工中。该构造不仅方便拼装定位,而且可以提高拼接面的抗剪能力。The invention proposes a prefabricated assembled cover beam structure and a construction method using steel shear keys. The structure adopts a new male-female paired steel shear key and is applied to the prefabricated assembled construction of the cover beam. This structure not only facilitates assembly and positioning, but also improves the shear resistance of the spliced surface.
为实现上述目的,本发明的技术方案是:一种采用钢剪力键的预制拼装盖梁结构,包括钢剪力键、预制盖梁的混凝土构件,预制盖梁的混凝土构件之间通过预埋的钢剪力键连接,每个钢剪力键由公型剪力键和母型剪力键配对使用构成;公型剪力键和母型剪力键与混凝土接触面上设有月牙纹,用于与预制盖梁的混凝土构件之间产生机械咬合力;所述母型剪力键尾端处设有注浆孔,注浆孔通过PVC管连接至预制盖梁的混凝土构件的外侧,方便注浆封闭公母型剪力键之间接缝。In order to achieve the above object, the technical solution of the present invention is: a prefabricated assembled cover beam structure using steel shear keys, including steel shear keys, concrete components of the prefabricated cover beam, and the concrete components of the prefabricated cover beam are pre-embedded The steel shear key is connected, and each steel shear key is composed of a male shear key and a female shear key in pairs; the male shear key and the female shear key are provided with crescent patterns on the contact surface with the concrete, It is used to generate mechanical bite force between the concrete components of the prefabricated cover beam; the tail end of the female shear key is provided with a grouting hole, and the grouting hole is connected to the outside of the concrete component of the prefabricated cover beam through a PVC pipe, which is convenient Grouting seals the joints between male and female shear keys.
所述钢剪力键由球墨铸铁或优质碳素结构钢铸造而成。The steel shear key is cast from ductile iron or high-quality carbon structural steel.
一种采用钢剪力键的预制拼装盖梁的施工方法,具体步骤为:A construction method for prefabricated assembled cap beams using steel shear keys, the specific steps are:
步骤一,预制盖梁的模板制作Step 1: Template making of prefabricated cover beams
将预制盖梁划分为三段混凝土构件A、B、C,并分别架设预制模板;Divide the prefabricated cover beam into three sections of concrete components A, B, and C, and erect prefabricated formwork respectively;
步骤二,预埋钢剪力键和浇筑混凝土Step 2, pre-embedded steel shear key and pouring concrete
在两个外挂的混凝土构件A、C的预制模板的拼接处预埋母型剪力键2中间段的混凝土构件B的预制模板的拼接处预埋公型剪力键,用水平仪对水平方向位置校准,使公型剪力键和母型剪力键配对并吻合,再用钢筋位置固定,防止混凝土浇筑时发生错位;然后混凝土浇筑,混凝土浇筑时从钢剪力键处开始,分段匹配浇筑,保证预制盖梁构件质量;Pre-embed the female type shear key at the joint of the prefabricated formwork of the two external concrete components A and C 2. Embed the male type shear key at the joint of the prefabricated formwork of the concrete component B in the middle section, and use a level to check the horizontal position Calibrate, make the male shear key and the female shear key match and match, and then fix the position with the steel bar to prevent misalignment during concrete pouring; then pour concrete, start from the steel shear key when pouring concrete, and pour in sections , to ensure the quality of prefabricated cap beam components;
步骤三,吊装预制盖梁的混凝土构件Step 3, hoisting the concrete components of the prefabricated cap beam
1)吊装混凝土构件B:起重机吊装中间段的混凝土构件B,按照预定的桥墩7与中间段拼装方案,缓慢安放直至与桥墩7完全接触,撤回起重机,在拼装接口位置注射水泥浆液封闭;1) Hoisting concrete component B: The concrete component B in the middle section is hoisted by the crane, according to the predetermined assembly plan of the pier 7 and the middle section, slowly placed until it is in full contact with the pier 7, the crane is withdrawn, and cement grout is injected at the assembly interface to seal it;
2)吊装混凝土构件A、C:起重机同时吊装混凝土构件A、C,在三段构件交界面处涂刷环氧树脂,以公、母型钢剪力键为校准点,将母型剪力键与公型剪力键对接安插,对接完成后,停止起重机的升降工作;2) Hoisting concrete components A and C: The crane hoists concrete components A and C at the same time, and paints epoxy resin at the interface of the three sections of components. Taking the male and female steel shear keys as calibration points, the female shear key and the The male type shear key is docked and inserted, and after the docking is completed, stop the lifting work of the crane;
步骤四,张拉第一阶段预应力筋Step 4: Stretch the first stage prestressed tendons
将预先准备好的预应力筋沿混凝土构件中孔洞穿放,采用后张法两端张拉钢筋,张拉第一阶段预应力筋并锚固,使混凝土构件A、C与混凝土构件B紧密贴合,然后撤除起重机,对第一阶段的预应力孔道注浆封闭;Put the pre-prepared prestressed tendons along the hole in the concrete member, use the post-tensioning method to stretch the steel bars at both ends, stretch the prestressed tendons in the first stage and anchor them, so that the concrete members A and C are closely attached to the concrete member B , and then remove the crane, and close the prestressed tunnel in the first stage by grouting;
步骤五,剪力键接缝处理利用小皮管将压浆机与PVC管道连接,接口处用卡具固定防止高压状态下皮管与管道脱离,启动压浆机开向管道内高压注射环氧树脂,直到浆液沿混凝土构件A与混凝土构件B、混凝土构件A与混凝土构件C的接缝处渗出,关闭压浆机,取下小皮管,对渗出的树脂液做擦除清理;Step 5, shear key joint treatment Use a small leather tube to connect the grouting machine to the PVC pipe, fix the interface with clamps to prevent the leather tube from detaching from the pipe under high pressure, start the grouting machine to inject epoxy into the pipe under high pressure until the grout oozes out along the joints between concrete component A and concrete component B, concrete component A and concrete component C, close the grouting machine, remove the small leather tube, and wipe and clean the oozing resin solution;
步骤六,张拉第二阶段预应力筋Step 6, stretching the second-stage prestressed tendons
在混凝土构件A、C上安放挡块,混凝土构件A、B、C上安放箱梁支座垫板,然后张拉第二阶段预应力筋,最后完成预应力孔洞注浆封闭、封锚及接接缝,完成整个拼装过程。Blocks are placed on concrete members A and C, box girder support pads are placed on concrete members A, B and C, and then prestressed tendons are stretched in the second stage, and the prestressed hole is finally closed by grouting, anchoring and joint Seams complete the entire assembly process.
本发明的有益效果是:预制拼装盖梁上采用新型公母配对钢剪力键,在盖梁预制拼装技术抗剪构造方面是首创。与一般预制拼装桥梁采用的键齿式大、小剪力键不同点在于:本发明中的剪力键需要预埋,减小了传统大、小剪力键在预制阶段模板制作的复杂程度;采用公母配对的方式,不仅方便吊装过程中的位置确定,而且更加有效地促进构件之间的咬合。The beneficial effects of the invention are: the prefabricated assembled cover beam adopts a new type of male-female paired steel shear key, which is the first in terms of the shear resistance structure of the prefabricated assembled cover beam. The difference from the tooth-type large and small shear keys used in general prefabricated assembled bridges is that the shear keys in the present invention need to be pre-embedded, which reduces the complexity of the traditional large and small shear keys in the prefabrication stage; The method of male-female pairing not only facilitates the determination of the position during the hoisting process, but also more effectively promotes the engagement between components.
本发明在实际工程应用中有以下优势:钢剪力键结构铸造易成型,尺寸精度高,吊装拼接的匹配度高;在结构设计合理情况下,可采用球墨铸铁或优质碳素结构钢铸造而成;剪力键直接预埋在拼装构件内,对模板细化制作的要求低,在批量生产工作中节约模板材料和大量人力资源;预应力筋张拉锚固方式,缩短传统现浇盖梁所需工作时间,在全程、大、中长线立交桥梁工程上,极大缩短了工程总工期,提升时效性能;公母配对的剪力键对接,不仅起到临时支点的作用,同时有键齿咬合的功能,大大提高拼接面抗剪可靠性。The present invention has the following advantages in practical engineering applications: steel shear key structure casting is easy to form, high dimensional accuracy, and high matching degree for hoisting and splicing; in the case of reasonable structural design, ductile cast iron or high-quality carbon structural steel can be used for casting. The shear key is directly embedded in the assembled component, which has low requirements for the detailed production of the formwork, and saves formwork materials and a large amount of human resources in mass production; the prestressed tendon tension and anchorage method shortens the cost of traditional cast-in-place cover beams. It requires working time. In the whole, large, and medium-to-long-term overpass bridge projects, the total construction period of the project is greatly shortened, and the timeliness performance is improved; the shear key of the male and female pairs not only plays the role of a temporary fulcrum, but also has the key teeth occluded The function greatly improves the shear reliability of the splicing surface.
附图说明Description of drawings
图1为公母配对式钢剪力键结构示意图;Figure 1 is a schematic diagram of the structure of a male-female paired steel shear key;
图2为图1的俯视图;Fig. 2 is the top view of Fig. 1;
图3为预制拼装盖梁整体结构示意图;Fig. 3 is a schematic diagram of the overall structure of the prefabricated assembled cover beam;
图4为图3中圈点处局部放大示意图;Figure 4 is a partially enlarged schematic diagram of the circled point in Figure 3;
图5为混凝土构件A、B交界面处俯视图;Fig. 5 is the top view of the interface of concrete members A and B;
图6为混凝土构件A交界面示意图;Fig. 6 is the schematic diagram of interface of concrete member A;
图7为本发明的采用钢剪力键的预制拼装盖梁的施工方法的流程框图。Fig. 7 is a flowchart of the construction method of the prefabricated assembled cap beam using steel shear keys according to the present invention.
具体实施方式detailed description
下面结合附图与实施例对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
如图1至图6所示,本发明的采用钢剪力键的预制拼装盖梁结构,包括预制盖梁的混凝土构件、钢剪力键、注浆孔4、PVC管5等。预制盖梁的混凝土构件之间通过预埋的钢剪力键连接,单个钢剪力键分为公型剪力键1和母型剪力键2,公型剪力键1上的凸台与母型剪力键2上的凹槽公母配对连接,钢剪力键由球墨铸铁或优质碳素结构钢铸造而成;公型剪力键1和母型剪力键2与混凝土接触面上有月牙纹3,目的是与混凝土构件A、B、C之间产生机械咬合力;在母型剪力键2尾端处有注浆孔4,注浆孔4通过PVC管5连接至混凝土构件A、C外侧,方便注浆封闭公母剪力键之间接缝6。As shown in Figures 1 to 6, the prefabricated assembled cover beam structure using steel shear keys of the present invention includes concrete components of the prefabricated cover beam, steel shear keys, grouting holes 4, PVC pipes 5, and the like. The concrete components of the prefabricated cover beams are connected by pre-embedded steel shear keys. A single steel shear key is divided into a male shear key 1 and a female shear key 2. The boss on the male shear key 1 is connected to the The grooves on the female shear key 2 are paired and connected, and the steel shear key is cast from ductile iron or high-quality carbon structural steel; the male shear key 1 and the female shear key 2 are on the contact surface with the concrete There are crescent patterns 3, the purpose of which is to generate mechanical engagement with concrete components A, B, and C; there is a grouting hole 4 at the end of the female shear key 2, and the grouting hole 4 is connected to the concrete component through a PVC pipe 5 The outer side of A and C is convenient for grouting to close the joint 6 between the male and female shear keys.
如图7所示,本发明的采用钢剪力键的预制拼装盖梁的施工方法, 以纵向总长31m的预制盖梁为例,本发明中的预制盖梁由混凝土构件A、B、C三段构件(图3),施工步骤及要求如下:As shown in Figure 7, the construction method of the prefabricated assembled cover beam that adopts steel shear key of the present invention, take the prefabricated cover beam of 31m of longitudinal total length as example, the prefabricated cover beam among the present invention is made of concrete members A, B, C three Section components (Figure 3), the construction steps and requirements are as follows:
a、将预制盖梁划分为混凝土构件A、B、C三成段,三成段分别架设模板预制,混凝土构件A、C为两外挂段,拼接处预埋母型剪力键2,混凝土构件B为中间段,拼接处预埋公型剪力键1,预埋位置只在构件受压区域;钢剪力键在预埋时需要用水平仪对水平方向位置校准,母型剪力键2尾端注浆孔4处与PVC管5连接,用钢筋对钢剪力键和PVC管固定位置,防止混凝土浇筑时发生错位;浇筑时从钢剪力键处开始,分段匹配浇筑,保证预制盖梁构件质量;构件在预制过程中均留有如图6所示三层对称预应力筋孔道S,预应力筋套管使用塑料波纹管。a. Divide the prefabricated cover beam into three sections of concrete components A, B, and C. The three sections are respectively erected for precast formwork. The concrete components A and C are two external hanging sections. The female shear key 2 is pre-embedded at the joint, and the concrete component B is In the middle section, the male shear key 1 is pre-embedded at the joint, and the pre-embedded position is only in the compression area of the component; when the steel shear key is pre-embedded, it is necessary to use a level to calibrate the horizontal position, and the end of the female shear key 2 Note The grout hole 4 is connected to the PVC pipe 5, and steel bars are used to fix the position of the steel shear key and the PVC pipe to prevent misalignment during concrete pouring; when pouring, start from the steel shear key and pour in sections to ensure that the prefabricated cover beam components Quality: During the prefabrication process, there are three layers of symmetrical prestressing tendon channels S shown in Figure 6, and plastic corrugated tubes are used for the prestressing tendon sleeves.
b、构件运输至拼装施工现场后,先用起重机吊装中间段的混凝土构件B,与桥墩交界面涂刷环氧树脂作粘结层,找准拼装位置后,缓慢安放直至与桥墩7完全拼装,撤回起重装置,在接口位置注射水泥浆液封闭。b. After the components are transported to the assembly construction site, use a crane to hoist the concrete component B in the middle section first, and apply epoxy resin on the interface with the pier as a bonding layer. After identifying the assembly position, slowly place it until it is completely assembled with the pier 7, Withdraw the lifting device and inject cement slurry at the interface to seal it.
c、使用起重机同时吊装混凝土构件A、C,在三段构件交界面处涂刷环氧树脂,以公、母型剪力键1,2为校准点,将母型剪力键2与公型剪力键1对接安插,对接完成后,停止起重机的升降工作;c. Use a crane to hoist concrete components A and C at the same time, paint epoxy resin at the interface of the three sections, take the male and female shear keys 1 and 2 as calibration points, and align the female shear key 2 with the male shear key The shear key 1 is docked and inserted, and after the docking is completed, stop the lifting work of the crane;
d、沿三层对称预应力筋孔道S的孔洞穿插预应力钢绞线,钢束规格统一采用15-фs15.20钢绞线,采用后张法两端张拉,张拉第一阶段预应力筋,锚垫板必须与钢束中线垂直,两端对称张拉,双向控制张拉应力与伸长度,固定锚具,使混凝土构件A、C与混凝土构件B紧密贴合,撤除起重装置,对第一阶段的预应力孔道注浆封闭,水泥浆强度为C45;d. Prestressed steel strands are inserted along the holes of the three-layer symmetrical prestressed tendon channel S. The specifications of the steel strands are uniformly 15-фs15.20 steel strands. Both ends are stretched by post-tensioning, and the first stage of tension is prestressed. The anchor plate must be perpendicular to the center line of the steel beam, the two ends should be tensioned symmetrically, the tensile stress and elongation should be controlled in both directions, the anchorage should be fixed so that the concrete members A, C and the concrete member B are closely attached, and the lifting device should be removed. The prestressed channel of the first stage is closed by grouting, and the strength of the grout is C45;
e、利用橡皮管将小型压浆机与PVC管道5连接,接口处用卡具固定防止高压状态下皮管与管道5脱离,启动压浆机开向管道5内高压注射环氧树脂,直到浆液沿混凝土构件A,B、混凝土构件A,C接缝处渗出,关闭压浆机,取下小皮管,对渗出的树脂液做擦除清理; e. Use a rubber tube to connect the small grouting machine to the PVC pipe 5, and fix the interface with a fixture to prevent the leather tube from detaching from the pipe 5 under high pressure. Start the grouting machine and inject epoxy resin into the pipe 5 under high pressure until the slurry Seep along the joints of concrete components A, B, concrete components A, C, close the grouting machine, remove the small leather tube, and wipe and clean the oozing resin solution;
f、安放如图3所示中的挡块8和抗震橡胶支座9,在挡块8完成拼装后,安装抗震橡胶支座需要从结构中心往两侧对称安装,随后张拉第二阶段预应力筋,即图6所示中最上层预应力筋,锚垫板必须与钢束中线垂直,两端对称张拉,双向控制张拉应力与伸长度,预应力达到设计要求值后固定锚具,拆除起重装置,孔道内压浆,水泥浆强度为C45,表面接缝口涂刷环氧树脂封闭并封锚。 f. Place the stopper 8 and the anti-seismic rubber bearing 9 as shown in Figure 3. After the assembly of the stopper 8 is completed, the installation of the anti-seismic rubber bearing needs to be installed symmetrically from the center of the structure to both sides, and then the second stage of pre-tensioning is carried out. Stress tendons, that is, the uppermost prestressed tendons shown in Figure 6, the anchor plate must be perpendicular to the center line of the steel bundle, the two ends of the tension should be symmetrical, the tensile stress and elongation can be controlled in both directions, and the anchorage should be fixed after the prestress reaches the design requirements , Remove the lifting device, grout in the tunnel, the grout strength is C45, and the surface joints are sealed and anchored with epoxy resin.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610704462.0A CN106320162B (en) | 2016-08-22 | 2016-08-22 | Prefabricated assembled cover beam structure and construction method using steel shear key |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610704462.0A CN106320162B (en) | 2016-08-22 | 2016-08-22 | Prefabricated assembled cover beam structure and construction method using steel shear key |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106320162A true CN106320162A (en) | 2017-01-11 |
CN106320162B CN106320162B (en) | 2018-01-26 |
Family
ID=57741491
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610704462.0A Expired - Fee Related CN106320162B (en) | 2016-08-22 | 2016-08-22 | Prefabricated assembled cover beam structure and construction method using steel shear key |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106320162B (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108560819A (en) * | 2018-05-30 | 2018-09-21 | 中国建筑第八工程局有限公司 | Box beam is adjustable Alveolus type connecting node and its construction method |
CN109853362A (en) * | 2019-03-29 | 2019-06-07 | 上海应用技术大学 | A kind of interim prestress anchoraging prefabricated bent cap of segmentation and interim method for applying prestressing force |
CN110106779A (en) * | 2019-05-05 | 2019-08-09 | 北京市市政专业设计院股份公司 | A kind of prefabrication type bent cap and its construction method |
CN111172855A (en) * | 2020-03-20 | 2020-05-19 | 重庆市轨道交通设计研究院有限责任公司 | Upper bearing type longitudinal block prefabricated box girder |
CN111172856A (en) * | 2020-03-20 | 2020-05-19 | 重庆市轨道交通设计研究院有限责任公司 | Half-through type longitudinal block prefabricated box girder |
CN111608266A (en) * | 2020-05-22 | 2020-09-01 | 宁波交通工程建设集团有限公司 | A kind of steel tenon key and assembling method for improving the shear strength of prefabricated beam segment assembly |
CN111827093A (en) * | 2020-06-29 | 2020-10-27 | 中国国家铁路集团有限公司 | A cluster grouting sleeve assembled pier connected with a prefabricated platform and its construction method |
CN111851323A (en) * | 2020-07-07 | 2020-10-30 | 汕头大学 | A new type of concrete joint structure and construction technology |
CN111893870A (en) * | 2020-08-31 | 2020-11-06 | 福州大学 | Structure and construction method of prefabricated assembled cover beam connected by shear key |
CN112458925A (en) * | 2020-12-02 | 2021-03-09 | 中交路桥建设有限公司 | Segment precast beam structure and construction method for splicing and combining bridge thereof |
CN113684751A (en) * | 2021-08-16 | 2021-11-23 | 北京市市政一建设工程有限责任公司 | Prefabricated bridge and construction process thereof |
CN113931057A (en) * | 2021-03-19 | 2022-01-14 | 宁波市政工程建设集团股份有限公司 | Tenon-and-mortise connected prefabricated small box girder type hidden cover beam and construction method thereof |
CN114990983A (en) * | 2022-06-20 | 2022-09-02 | 上海建工集团股份有限公司 | Bridge segment assembling joint structure and construction method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5771518A (en) * | 1989-06-16 | 1998-06-30 | Roberts; Michael Lee | Precast concrete bridge structure and associated rapid assembly methods |
CN1704537A (en) * | 2004-05-27 | 2005-12-07 | 同济大学 | Totally assembled type prefabricated concrete structure system |
CN103194983A (en) * | 2013-04-26 | 2013-07-10 | 上海市城市建设设计研究总院 | Segmental precast assembly method and segmental precast assembly structure for cantilever arm of large capping beam |
CN203451986U (en) * | 2013-09-13 | 2014-02-26 | 上海市城市建设设计研究总院 | Full-prefabricated assembly bent cap |
CN103603435A (en) * | 2013-12-06 | 2014-02-26 | 金陵科技学院 | Assembled concrete seismic beam-column frame and construction method thereof |
CN105484109A (en) * | 2015-11-21 | 2016-04-13 | 隔而固(青岛)振动控制有限公司 | Easy-to-assemble floating track bed precast slab and application thereof |
CN205329526U (en) * | 2016-01-19 | 2016-06-22 | 张正东 | Pier is assembled to precast concrete |
-
2016
- 2016-08-22 CN CN201610704462.0A patent/CN106320162B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5771518A (en) * | 1989-06-16 | 1998-06-30 | Roberts; Michael Lee | Precast concrete bridge structure and associated rapid assembly methods |
CN1704537A (en) * | 2004-05-27 | 2005-12-07 | 同济大学 | Totally assembled type prefabricated concrete structure system |
CN103194983A (en) * | 2013-04-26 | 2013-07-10 | 上海市城市建设设计研究总院 | Segmental precast assembly method and segmental precast assembly structure for cantilever arm of large capping beam |
CN203451986U (en) * | 2013-09-13 | 2014-02-26 | 上海市城市建设设计研究总院 | Full-prefabricated assembly bent cap |
CN103603435A (en) * | 2013-12-06 | 2014-02-26 | 金陵科技学院 | Assembled concrete seismic beam-column frame and construction method thereof |
CN105484109A (en) * | 2015-11-21 | 2016-04-13 | 隔而固(青岛)振动控制有限公司 | Easy-to-assemble floating track bed precast slab and application thereof |
CN205329526U (en) * | 2016-01-19 | 2016-06-22 | 张正东 | Pier is assembled to precast concrete |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108560819A (en) * | 2018-05-30 | 2018-09-21 | 中国建筑第八工程局有限公司 | Box beam is adjustable Alveolus type connecting node and its construction method |
CN109853362A (en) * | 2019-03-29 | 2019-06-07 | 上海应用技术大学 | A kind of interim prestress anchoraging prefabricated bent cap of segmentation and interim method for applying prestressing force |
CN109853362B (en) * | 2019-03-29 | 2021-02-26 | 上海应用技术大学 | Temporary prestressed anchoring segmented prefabricated cover beam and temporary prestressing method |
CN110106779A (en) * | 2019-05-05 | 2019-08-09 | 北京市市政专业设计院股份公司 | A kind of prefabrication type bent cap and its construction method |
CN111172855A (en) * | 2020-03-20 | 2020-05-19 | 重庆市轨道交通设计研究院有限责任公司 | Upper bearing type longitudinal block prefabricated box girder |
CN111172856A (en) * | 2020-03-20 | 2020-05-19 | 重庆市轨道交通设计研究院有限责任公司 | Half-through type longitudinal block prefabricated box girder |
CN111608266B (en) * | 2020-05-22 | 2025-07-15 | 宁波交通工程建设集团有限公司 | Steel tenon key and assembly method for improving shear strength of prefabricated beam segment assembly |
CN111608266A (en) * | 2020-05-22 | 2020-09-01 | 宁波交通工程建设集团有限公司 | A kind of steel tenon key and assembling method for improving the shear strength of prefabricated beam segment assembly |
CN111827093A (en) * | 2020-06-29 | 2020-10-27 | 中国国家铁路集团有限公司 | A cluster grouting sleeve assembled pier connected with a prefabricated platform and its construction method |
CN111851323A (en) * | 2020-07-07 | 2020-10-30 | 汕头大学 | A new type of concrete joint structure and construction technology |
CN111893870A (en) * | 2020-08-31 | 2020-11-06 | 福州大学 | Structure and construction method of prefabricated assembled cover beam connected by shear key |
CN112458925A (en) * | 2020-12-02 | 2021-03-09 | 中交路桥建设有限公司 | Segment precast beam structure and construction method for splicing and combining bridge thereof |
CN113931057A (en) * | 2021-03-19 | 2022-01-14 | 宁波市政工程建设集团股份有限公司 | Tenon-and-mortise connected prefabricated small box girder type hidden cover beam and construction method thereof |
CN113684751A (en) * | 2021-08-16 | 2021-11-23 | 北京市市政一建设工程有限责任公司 | Prefabricated bridge and construction process thereof |
CN113684751B (en) * | 2021-08-16 | 2022-12-30 | 北京市市政一建设工程有限责任公司 | Prefabricated bridge and construction process thereof |
CN114990983A (en) * | 2022-06-20 | 2022-09-02 | 上海建工集团股份有限公司 | Bridge segment assembling joint structure and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN106320162B (en) | 2018-01-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106320162B (en) | Prefabricated assembled cover beam structure and construction method using steel shear key | |
CN106320164B (en) | Large-scale prefabricated assembled cover beam with "corbel" structure and its construction method | |
CN104727441B (en) | Prestress assembled concrete beam column joint structure and construction method thereof | |
CN110468694A (en) | Spigot-and-socket Self-resetting multi-segmental precast pier and its assembly method | |
CN107849831B (en) | For using prefabricated panel and steel-pipe concrete truss to carry out pushing tow/construction bridge method | |
CN104233942B (en) | Method for enhancing overall stress on assembled type heterotropic pre-stress hollow slab beam bridge | |
CN104947603B (en) | Reinforcement structure and reinforcement method of main girder of reinforced concrete girder bridge | |
CN105926440A (en) | Steel-concrete combined continuous beam bridge deck as well as manufacturing method and application thereof | |
CN106522561A (en) | Long-span concrete frame beam bonded prestressed post-cast strip inside stretching construction method | |
CN109853362B (en) | Temporary prestressed anchoring segmented prefabricated cover beam and temporary prestressing method | |
CN108316131A (en) | A kind of precast block formula full prestressing pier structure and its method of construction | |
CN103590324B (en) | Transverse shear resisting section type self-resetting pier and construction method thereof | |
CN104080977A (en) | Joint structure for steel bridge pier and concrete pile foundation | |
CN105714673A (en) | A self-resetting FRP-steel-concrete composite structure pier column and its construction method | |
CN109137727B (en) | Dry-wet combined segment prefabrication and splicing joint system and method based on early strength UHPC | |
CN105970803B (en) | Shear-resistant energy dissipation device of assembled pier and construction method | |
CN110846997A (en) | A kind of prefabricated prestressed steel and concrete splicing continuous composite beam and construction method | |
CN211645913U (en) | Prefabricated prestressed steel and concrete spliced continuous combination beam | |
CN108951399A (en) | A kind of Single-box multi-chamber box beam bridge and its construction method | |
CN103018115A (en) | Device for testing shear strength of joint of external prestressing prefabrication and assembly concrete member | |
CN205662838U (en) | Prestressing force joint construction of pier is assembled to prefabricated segment | |
CN106087692A (en) | A kind of Simply supported non-uniform T negative moment of girder section structure and construction method | |
CN111851564A (en) | An assembled type cap plate structure and construction method connected with pile foundation | |
CN107984610A (en) | A kind of prestressing force small box girder production method | |
CN111827095A (en) | Prefabricated and assembled hollow pier with built-in ribs and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180126 Termination date: 20200822 |