CN106245679B - Across subway shallow embedding open cut zero unloads common pipe trench construction method - Google Patents

Across subway shallow embedding open cut zero unloads common pipe trench construction method Download PDF

Info

Publication number
CN106245679B
CN106245679B CN201610764069.0A CN201610764069A CN106245679B CN 106245679 B CN106245679 B CN 106245679B CN 201610764069 A CN201610764069 A CN 201610764069A CN 106245679 B CN106245679 B CN 106245679B
Authority
CN
China
Prior art keywords
subway
groove
pipe trench
unloads
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610764069.0A
Other languages
Chinese (zh)
Other versions
CN106245679A (en
Inventor
陈建国
赵凯
李鹏辉
黄力
李洪侠
尤靖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
Third Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Third Engineering Division filed Critical Third Construction Co Ltd of China Construction Third Engineering Division
Priority to CN201610764069.0A priority Critical patent/CN106245679B/en
Publication of CN106245679A publication Critical patent/CN106245679A/en
Application granted granted Critical
Publication of CN106245679B publication Critical patent/CN106245679B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The present invention discloses a kind of across subway shallow embedding open cut zero and unloads common pipe trench construction method, it passes through segmentation prefabricating pipe trench structure;The pre-groove of cell across subway section is carried out jumping storehouse excavation, and same pre-groove is also carried out and jumps storehouse excavation;Monitor the section deformation quantity of subway in real time at the same time, construction speed is controlled according to the section deformation quantity of subway, install prefabricated pipe fitting before section deformation is fast-developing and implement to compensate return load rapidly.The construction method that across the subway shallow embedding open cut zero unloads, it excavates pre-groove by jumping storehouse in the away minor segment, installs segmentation prefabricating pipe trench structure prefabricated pipe fitting before section deformation is fast-developing and implements compensation return load rapidly;So that subway segment incremental deformation final after the construction of across subway common pipe trench, less than 2mm, Deformation control effect is preferable, far below agreing value 10mm, and the subway protection requirement of zero load during across subway shallow embedding open-cut is met.

Description

Across subway shallow embedding open cut zero unloads common pipe trench construction method
Technical field
The present invention relates to technical field of building construction, more particularly to a kind of across subway shallow embedding open cut zero unloads common pipe trench and applies Work method.
Background technology
With the fast development of urban construction, the engineering construction project of near-earth iron is always difficult to avoid, and track traffic is in itself Particularity determine the high susceptibility of its safety problem, by taking Soviet Union, Shanghai area as an example, in the range of 50 meters of subway line both sides Base pit engineering will include track safety supervision management and control scope, and Gui Jiao departments will intervene each ring of engineering design and construction overall process comprehensively Section monitoring.It is then more rare directly across the pit slot excavation above subway line for excavation of foundation pit compared to track both sides, Because design link generally has sought to avoid this difficulty, but this engineering demand is existing for reality.For so Engineering project, it is necessary to which a set of special construction method could control the deformation extent of ground iron pipe conduit agreing in value, so as to obtain The construction permits of get Gui Jiao safety supervisions department.
The content of the invention
In view of this, it is necessary to which a kind of subway protection for meeting zero load during across subway shallow embedding open-cut is provided It is required that across subway shallow embedding open cut zero unloading common pipe trench construction method.
A kind of across subway shallow embedding open cut zero unloads common pipe trench construction method, and across the subway shallow embedding open cut zero unloads jointly Drainage construction method includes the following steps:
S1, segmentation prefabricating pipe trench structure;
S2, the pre-groove to cell across subway section carry out jumping storehouse excavation, and also carry out jump to same pre-groove Excavate in storehouse;
The section deformation quantity of S3, in real time monitoring subway, controls construction speed according to the section deformation quantity of subway, becomes in section Prefabricated pipe fitting is installed before shape is fast-developing and implements compensation return load rapidly.
Preferably, the pipe trench structure includes prefabricated U type groove and prefabricated cover board, and the U-type groove and prefabricated cover board surround shape Into a rectangular enclosure.
Preferably, when being equipped with overall U-type groove in the spaced pre-groove in left and right, then be arranged at left and right pre-groove it Between intermediate prefabricated groove in U-type groove by adjacent overall U-type groove cell wall and one piece of prefabricated panel being arranged between cell wall Form.
Preferably, in the digging process for carrying out pre-groove, excavation pipeline first is more, the larger prefabricated ditch of width Groove.
Preferably, each pre-groove is segmented, and segment trench is carried out to jump storehouse cyclic ordering, same sequence number Segmentation must excavate at the same time.
Preferably, the hanging device of the pipe trench structure is arranged on the position of subway upper vertical regions both sides.
Preferably, the silt weight of the compensation return load is equal to the weight after the silt deduction component dug.
Preferably, the standard construction period using the daily subway stoppage in transit phase as the common pipe trench, each standard construction Cycle accurately completes a standard operation section of planning.
Preferably, the hanging device lifts U-type groove using a lifting shoulder pole, and the lifting shoulder pole includes a length The degree central shaft rod equal with U-type groove body length, and the branch sunpender at central shaft rod both ends is vertical at, the length of the branch sunpender Spacing between the same side hole for hoist of U-type groove is identical, and the U-type groove passes through the steel wire rope and branch sunpender for passing through hole for hoist Both ends connection.
Preferably, the both ends of the central shaft rod are arranged with multiple spacing screw holes, and the branch sunpender is bolted on In central shaft rod, by adjusting the cooperation of bolt and screw hole, the spacing between the branch sunpender of both ends is adjusted.
The construction method that across subway shallow embedding open cut zero of the present invention unloads, it is excavated in advance by jumping storehouse in the away minor segment Groove processed, installs segmentation prefabricating pipe trench structure prefabricated pipe fitting before section deformation is fast-developing and implements compensation return load rapidly; So that subway segment incremental deformation final after across subway common pipe trench construction, less than 2mm, Deformation control effect is preferable, far Less than agreing value 10mm, and meet the subway protection requirement of zero load during across subway shallow embedding open-cut.Present invention hair The construction method that bright across the subway shallow embedding open cut zero unloads is easy to operate, has saved construction cost and cycle, real suitable for promoting OK.
Brief description of the drawings
Fig. 1 is the FB(flow block) that across subway shallow embedding open cut zero described in the embodiment of the present invention unloads common pipe trench construction method;
Fig. 2 is the structure diagram of pipe trench structure described in the embodiment of the present invention;
Fig. 3 jumps storehouse for away minor segment of the present invention and excavates pre-groove plane block plan;
Fig. 4 is segmentation prefabricating pipe trench structural plan block plan of the present invention;
Fig. 5 for it is of the present invention install prefabricated pipe fitting before section deformation is fast-developing and implement compensation return load rapidly show It is intended to;
Fig. 6 is segmentation prefabricating pipe trench detail of construction schematic diagram of the present invention;
Fig. 7 is the structure diagram of lifting shoulder pole of the present invention.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to the accompanying drawings and embodiments, it is right The present invention is further elaborated, it will be appreciated that and the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
The Engineering Projects that patent of the present invention is relied on is certain large size city synthesis, and 14 Wan ㎡ of floor space, one is runed In subway line pass through in the middle part of the plot, the underground space of whole engineering is separated into two independent foundation pits, because function is set Needs on meter, it is necessary to a common pipe trench is set to connect the synthetic pipe network system of two independent foundation pit both sides, and track is pacified It is necessary " zero unloading " to supervise the pit slot excavation project carried out above goal track.Such case there is no precedent in the whole nation.
As shown in Figure 1, the embodiment of the present invention, which provides a kind of across subway shallow embedding open cut zero, unloads common pipe trench construction method, institute Across the subway unloading of shallow embedding open cut zero common pipe trench construction method is stated to include the following steps:
S1, segmentation prefabricating pipe trench structure 10.
Specifically, as shown in Fig. 2, the pipe trench structure 10 includes U-type groove 101 and prefabricated cover board 103, the U-type groove 101 Surround to form a rectangular enclosure with prefabricated cover board 103.Meanwhile to save construction cost, if left and right is spaced prefabricated Overall U-type groove 101 is equipped with groove, then is arranged at the U-type groove 101 in the intermediate prefabricated groove between the pre-groove of left and right by phase The cell wall and one piece of prefabricated panel 102 being arranged between cell wall of adjacent entirety U-type groove 101 are formed.
S2, the pre-groove to cell across subway section carry out jumping storehouse excavation, and also carry out jump to same pre-groove Excavate in storehouse;
Carry out pre-groove digging process in, carry out pre-groove digging process in, first excavate pipeline compared with It is more, the larger pre-groove of width.I.e. as shown in Figure 3 and Figure 4, A storehouses, B storehouses, C storehouses, D storehouses, totally 5, E storehouses are included in the present embodiment Pre-groove, wherein, to set the pre-groove of power pipe, B storehouses, C storehouses, D storehouses, E storehouses are the prefabricated ditch of waterway pipe in A storehouses Groove, due to having more pipeline in A storehouses, and the width in A storehouses is larger, therefore A storehouses are excavated first, is set according to storehouse is jumped It is fixed, C storehouses, B storehouses, E storehouses, D storehouses are excavated successively after having been dug in A storehouses.
Meanwhile, it is necessary to be segmented to the pre-groove while being excavated to same pre-groove, and to point Section groove carries out jumping storehouse cyclic ordering, and the segmentation of same sequence number must excavate at the same time.I.e. as shown in Figure 3 and Figure 4, A storehouses are divided into Eight sections, and the numbering cycle of 1-4 is carried out successively, finally, first segment and the 5th section are same sequence number, and second segment is phase with the 6th section Same sequence number, the 3rd section be same sequence number with the 7th section, the 4th section and the 8th section be same sequence number, then first segment and the 5th section at the same time Excavate, second segment and the 6th section are excavated at the same time successively afterwards, the 3rd section is excavated at the same time with the 7th section, and the 4th section same with the 8th section When excavate.Preferably, in geological conditions allowed band, when the segmentation of same sequence number excavate at the same time, also can Segmentation to adjacent sequence number excavate at the same time.
While being excavated to segment trench, based on the reverse design of construction demand progress, storehouse is jumped according to the away minor segment Pipe trench structure 10 is accordingly split in the segmentation for excavating pre-groove.Since the hanging device of pipe trench structure 10 is large-scale device Tool, its weight is larger, and to avoid causing the influence to subway, the hanging device of the pipe trench structure 10 is necessarily placed on subway The position of square vertical area both sides.Preferably, set the position of the hanging device and subway upper vertical regions border it Between distance be 20-40m, according to practice of construction demand, the hanging device used in the present embodiment is crawler crane.
The section deformation quantity of S3, in real time monitoring subway, controls construction speed according to the section deformation quantity of subway, becomes in section Prefabricated pipe fitting is installed before shape is fast-developing and implements compensation return load rapidly.
The basic principle of subway protection is zero unloading, and after 10 rigging out of pipe trench structure and time soil, hollow pipeline exists There is loss in terms of load or compared with undisturbed soil, the present invention takes the mode of compensation preloading to handle, and specific method will be as shown in figure 5, will Packed sand hill is previously placed in special reinforced cage, implements directly to be transported with fork truck during preloading.
After single channel pipeline installs, open cover board and be directly backfilling into bagged sand when compensating return load within pipeline. Easy to Miniature digging machine and navy barrow operation can be turned, institute as the Active workings for closing on pipeline in order to which the terrestrial path finished will be backfilled Stating backfilling working will be interspersed among overall excavation assembling work progress.
Specifically, the silt weight of the compensation return load, which is equal to the silt dug, deducts the weight after component.
The normal range (NR) of the section deformation quantity of the subway is 5mm-10mm, when the section deformation quantity of subway is in 5mm-10mm In the range of, then construct according to normal progress, when the section deformation quantity of subway exceeds the scope of 5mm-10mm, then need Accelerate construction progress, it is necessary to which peace completes the work for setting prefabricated pipe fitting and implementing compensation return load rapidly before section deformation is fast-developing Make.
To avoid the normal operation of subway, in the present embodiment the time of engineering construction be using daily subway stop transport the phase as The standard construction period of the common pipe trench, and each standard construction period accurately completes a standard operation section of planning.I.e. Daily subway night is constructed in limited time after stopping transport, and excavation point is recovered original appearance before next day metro operation, that is, returns soil, heap Carry, load restores, as follows to the reasonable arrangement longitudinally excavated of same pre-groove as principle:In the prefabricated ditch of same On groove, it can at most carry out excavating work while two segmentations every night.Each segmentation is advisable with including 2-section pipe section, is controlled from the time System, from losing in short-term, load coverage control angle is proper.
The construction method that across subway shallow embedding open cut zero of the present invention unloads, it is excavated in advance by jumping storehouse in the away minor segment Groove processed, installs 10 prefabricated pipe fitting of segmentation prefabricating pipe trench structure before section deformation is fast-developing and implements to compensate back rapidly Carry;So that subway segment incremental deformation final after across subway common pipe trench construction is less than 2mm, Deformation control effect reason Think, far below agreing value 10mm, and meet the subway protection requirement of zero load during across subway shallow embedding open-cut.This hair The construction method that across subway shallow embedding open cut zero described in bright invention unloads is easy to operate, construction cost and cycle has been saved, suitable for pushing away It is wide to carry out.
In the construction method that above-mentioned across subway shallow embedding open cut zero unloads, when being lifted to pipe trench structure 10, Since the cell wall hardness of U-type groove 101 is relatively low, if there are larger angle between the steel wire rope and cell wall of lifting, cell wall is subject to partially Tiltedly in the power on vertical direction, then easily it is broken, therefore, to avoid in lifting U-type groove 101 easy stress from concentrating Breakage, as shown in Figure 6 and Figure 7, the present invention also provides a kind of lifting lifted suitable for hanging device to U-type groove 101 is flat Load 20, the lifting shoulder pole 20 include the length central shaft rod 201 equal with 101 body length of U-type groove, and is vertical at The branch sunpender 202 at 201 both ends of axostylus axostyle, the spacing between the length of the branch sunpender 202 and the same side hole for hoist of U-type groove 101 Identical, the U-type groove 101 passes through the steel wire rope of hole for hoist to be connected with the both ends of branch sunpender 202 by one.
Further, the both ends of the central shaft rod 201 are arranged with multiple spacing screw holes 203, and the branch sunpender 202 passes through Bolt is fixed in central shaft rod 201, by adjusting the cooperation of bolt and spacing screw hole 203, between both ends branch sunpender 202 Away from being adjusted, so as to lift various sizes of U-type groove 101.
Case described above is only the implementation that is relied on of the present invention by example, is not intended to limit the invention, all in the present invention Spirit and principle within, any modification, equivalent replacement, improvement and so on, should be included in protection scope of the present invention it It is interior.

Claims (7)

1. a kind of across subway shallow embedding open cut zero unloads common pipe trench construction method, it is characterised in that across the subway shallow embedding open cut Zero unloading common pipe trench construction method includes the following steps:
S1, segmentation prefabricating pipe trench structure;
S2, the pre-groove to cell across subway section carry out jumping storehouse excavation, and also carry out same pre-groove jump storehouse and open Dig;
The section deformation quantity of S3, in real time monitoring subway, construction speed is controlled according to the section deformation quantity of subway, fast in section deformation Prefabricated pipe fitting is installed before speed development and implements compensation return load rapidly;
Wherein, the hanging device of the pipe trench structure is arranged on the position of subway upper vertical regions both sides;
The hanging device lifts U-type groove using a lifting shoulder pole, and the lifting shoulder pole includes a length and U-type groove sheet The equal central shaft rod of body length, and be vertical at the branch sunpender at central shaft rod both ends, the length of the branch sunpender and U-type groove it is same Spacing between the hole for hoist of side is identical, and the U-type groove passes through the steel wire rope of hole for hoist to be connected with the both ends of branch sunpender by one;
The both ends of the central shaft rod are arranged with multiple spacing screw holes, and the branch sunpender is bolted in central shaft rod, lead to The cooperation of adjustment bolt and screw hole is crossed, the spacing between the branch sunpender of both ends is adjusted.
2. across subway shallow embedding open cut zero unloads common pipe trench construction method according to claim 1, it is characterised in that the pipe Ditch structure (10) includes prefabricated U type groove (101) and prefabricated cover board (103), and the U-type groove (101) and prefabricated cover board (103) surround Form a rectangular enclosure.
3. across subway shallow embedding open cut zero unloads common pipe trench construction method according to claim 2, it is characterised in that works as left and right Overall U-type groove, the then U being arranged in the intermediate prefabricated groove between the pre-groove of left and right are equipped with spaced pre-groove Type groove is made of the cell wall and one piece of prefabricated panel (102) being arranged between cell wall of adjacent overall U-type groove.
4. across subway shallow embedding open cut zero unloads common pipe trench construction method according to claim 1, it is characterised in that is carrying out In the digging process of pre-groove, excavation pipeline first is more, the larger pre-groove of width.
5. across subway shallow embedding open cut zero unloads common pipe trench construction method according to claim 1, it is characterised in that to each Bar pre-groove is segmented, and segment trench is carried out to jump storehouse cyclic ordering, and the segmentation of same sequence number must excavate at the same time.
6. across subway shallow embedding open cut zero unloads common pipe trench construction method according to claim 1, it is characterised in that the benefit The silt weight for repaying return load is equal to the weight after the silt deduction component dug.
7. across subway shallow embedding open cut zero unloads common pipe trench construction method according to claim 1, it is characterised in that will be daily Subway stop transport standard construction period of the phase as the common pipe trench, each standard construction period accurately completes one of planning Standard operation section.
CN201610764069.0A 2016-08-30 2016-08-30 Across subway shallow embedding open cut zero unloads common pipe trench construction method Active CN106245679B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610764069.0A CN106245679B (en) 2016-08-30 2016-08-30 Across subway shallow embedding open cut zero unloads common pipe trench construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610764069.0A CN106245679B (en) 2016-08-30 2016-08-30 Across subway shallow embedding open cut zero unloads common pipe trench construction method

Publications (2)

Publication Number Publication Date
CN106245679A CN106245679A (en) 2016-12-21
CN106245679B true CN106245679B (en) 2018-04-17

Family

ID=57597875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610764069.0A Active CN106245679B (en) 2016-08-30 2016-08-30 Across subway shallow embedding open cut zero unloads common pipe trench construction method

Country Status (1)

Country Link
CN (1) CN106245679B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778904A (en) * 2017-11-15 2019-05-21 北京建工路桥集团有限公司 A kind of construction method of multi-storey road frame structure jumping warehouse
CN108374421A (en) * 2018-02-08 2018-08-07 合肥市市政设计研究总院有限公司 Municipal road construction and pipelining subregion discharging method are used for above existing tunnel
CN110282579A (en) * 2019-07-05 2019-09-27 中国建筑第八工程局有限公司 The Lift-on/Lift-off System and hanging method of prefabricated pipe trench in height-limited small space

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232328A (en) * 2003-01-30 2004-08-19 Taisei Corp Structure of semi-precast arch culvert and its construction method
JP4303512B2 (en) * 2003-04-11 2009-07-29 大成建設株式会社 Construction method of large section tunnel
CN104895111A (en) * 2015-06-16 2015-09-09 中建五局土木工程有限公司 Construction method of integrated pipe trench in soft soil
CN105625469A (en) * 2016-02-06 2016-06-01 青岛润国生态科技发展有限公司 Construction method for assembly type prefabricated comprehensive pipe gallery
CN105672356A (en) * 2016-03-25 2016-06-15 中船第九设计研究院工程有限公司 Underground structure of municipal pipeline group spanning tunnel and construction method for underground structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232328A (en) * 2003-01-30 2004-08-19 Taisei Corp Structure of semi-precast arch culvert and its construction method
JP4303512B2 (en) * 2003-04-11 2009-07-29 大成建設株式会社 Construction method of large section tunnel
CN104895111A (en) * 2015-06-16 2015-09-09 中建五局土木工程有限公司 Construction method of integrated pipe trench in soft soil
CN105625469A (en) * 2016-02-06 2016-06-01 青岛润国生态科技发展有限公司 Construction method for assembly type prefabricated comprehensive pipe gallery
CN105672356A (en) * 2016-03-25 2016-06-15 中船第九设计研究院工程有限公司 Underground structure of municipal pipeline group spanning tunnel and construction method for underground structure

Also Published As

Publication number Publication date
CN106245679A (en) 2016-12-21

Similar Documents

Publication Publication Date Title
CN108397201A (en) The safe construction method of rock tunnel(ling) machine
CN104775817A (en) All-negative pressure continuous-mining continuous-filling step-by-step replacement mining method for coal underneath cities and towns, industrial buildings, railways and other buildings
CN106245679B (en) Across subway shallow embedding open cut zero unloads common pipe trench construction method
CN103321230A (en) Excavation method for deep and big foundation pit in long-distance crossing field for shallow-buried subway
CN104847364B (en) A kind of shield continuous cutting pile foundation passes through residential building group construction method
CN107664035A (en) The construction method of well after shield piping lane elder generation shield
US10486717B2 (en) Hydro-electric site and method for constructing a penstock
CN111412002B (en) Construction method of anchor cable opposite-pulling type supporting structure system
CN103993885A (en) Construction method for underground excavation tunnel side-direction hole opening supporting system
CN109113092A (en) Construction method is protected in underground large-diameter pipeline original position water flowing
CN203822311U (en) Advanced detection and pre-reinforcing structure for shield tunnel crossing existing station construction
CN107514262A (en) The construction method of shield piping lane
CN108193671A (en) For the weight dangerous region super-large diameter pile foundation drilling construction method of alpine terrain landforms
CN110106867A (en) Manual digging pile construction method between railcar station track
CN104863183B (en) Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction
CN206785388U (en) Anchor cable removes system in a kind of tunnel
CN110439011B (en) Side slope anti-slip supporting structure and construction method thereof
CN109356193B (en) Prefabricated piping lane propelling movement construction equipment
CN113187507B (en) Grouting reinforcement method for deformation control of underground excavation tunnel underpass operation subway section
CN202731927U (en) Tunnel construction device
CN111425664A (en) Large-diameter concrete pipeline jacking pipe construction method
CN109797717A (en) The construction method for having subway tunnel is worn on a kind of river
CN205475323U (en) Municipal administration pipeline crowd stridees across underground structure in tunnel
CN203922510U (en) A kind of simple and easy cable machine that is arranged in slope
CN208441846U (en) A kind of vertical shaft shield machine constructed upwards by underground

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Chen Jianguo

Inventor after: Zhao Kai

Inventor after: Yang Weiguo

Inventor after: Li Penghui

Inventor after: Huang Li

Inventor after: Li Hongxia

Inventor after: You Jing

Inventor after: Zhu Cunbing

Inventor before: Chen Jianguo

Inventor before: Zhao Kai

Inventor before: Li Penghui

Inventor before: Huang Li

Inventor before: Li Hongxia

Inventor before: You Jing