[go: up one dir, main page]

CN106192670B - Place basis - Google Patents

Place basis Download PDF

Info

Publication number
CN106192670B
CN106192670B CN201610767347.8A CN201610767347A CN106192670B CN 106192670 B CN106192670 B CN 106192670B CN 201610767347 A CN201610767347 A CN 201610767347A CN 106192670 B CN106192670 B CN 106192670B
Authority
CN
China
Prior art keywords
foundation
retaining wall
site
module
modules
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610767347.8A
Other languages
Chinese (zh)
Other versions
CN106192670A (en
Inventor
陆大伟
刘丽欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan U Crown Sports Material Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610767347.8A priority Critical patent/CN106192670B/en
Priority to PCT/CN2016/101674 priority patent/WO2018040228A1/en
Publication of CN106192670A publication Critical patent/CN106192670A/en
Application granted granted Critical
Publication of CN106192670B publication Critical patent/CN106192670B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C13/00Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
    • E01C13/02Foundations, e.g. with drainage or heating arrangements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明提出一种场地基础,包括多个基础模块,基础模块包括第一基础模块和第二基础模块,多个第一基础模块拼接成具有弧度的基础,多个第二基础模块拼接成矩形基础,基础模块内部镂空且设有可供人进入的空间,并在内侧设有排水通道。本发明将场地基础设计为预制的多个基础模块,基础模块内部镂空且设有空间可供检修人员进入基础内部进行检修,并且具有良好的通气性,在基础模块内设有排水通道,提高了基础的降排水能力,其具有施工简单、缩短施工周期、基础的回弹统一等优点,延长了基础结构的使用寿命,解决了现有场地基础中存在的施工周期长、排气性和疏水性能比较差、抗冻胀性能低、冻裂、鼓包、基础维修困难等问题。

The present invention proposes a field foundation, including a plurality of foundation modules, the foundation module includes a first foundation module and a second foundation module, a plurality of first foundation modules are spliced into a foundation with a radian, and a plurality of second foundation modules are spliced into a rectangular foundation , the interior of the basic module is hollowed out and has a space for people to enter, and a drainage channel is provided on the inside. In the present invention, the site foundation is designed as a plurality of prefabricated basic modules. The inside of the basic modules is hollowed out and there is a space for maintenance personnel to enter the inside of the foundation for maintenance, and has good air permeability. Drainage channels are provided in the basic modules, which improves the The drainage capacity of the foundation has the advantages of simple construction, shortened construction period, and uniform rebound of the foundation, which prolongs the service life of the foundation structure and solves the problems of long construction period, air drainage and hydrophobic performance in the existing site foundation Relatively poor, low frost heave resistance, frost cracks, bulges, difficult foundation maintenance and other problems.

Description

场地基础site foundation

技术领域technical field

本发明涉及基础设施技术领域,具体涉及一种应用在跑道、足球场、篮球场、道路等的场地基础。The invention relates to the technical field of infrastructure, in particular to a field foundation applied to runways, football fields, basketball courts, roads and the like.

背景技术Background technique

随着生产力水平的发展,人民生活水平的提高,人们的休闲时间也越来越多,体育运动便是人们闲暇时间喜爱的活动之一,因此,体育设施科学、人性化直接关系着运动者的人身安全,现已得到广泛的推广应用,但是目前的场地基础在生产和施工方面存在以下缺陷:With the development of productivity and the improvement of people's living standards, people have more and more leisure time. Sports is one of the activities that people like in their spare time. Therefore, the scientific and humanized sports facilities are directly related to the sportsman's life. Personal safety has been widely promoted and applied, but the current site foundation has the following defects in production and construction:

传统的场地基础的施工与公路路基施工大体相同,步骤包括:土方挖掘---素土夯实碾压----回填砂石料碾压-----回填三灰土碾压----回填水泥稳定层碾压---混凝土面层,以上步骤施工周期长,基础通常利用当地的土质再进行捣紧来实现的,其排气性和疏水性能比较差,抗冻胀性能低,在人造跑道施工以后,例如当下雨或用水清洗人造跑道时,往往因为基础层排水、排气困难使基础层与人造跑道之间产生积水、积气、沉降等,又如在冬季时,跑道基础由于冻胀系数不一致而发生冻裂等问题,严重时还出现鼓泡现象,影响跑道的使用,甚至造成跑道的损坏,而且基础的老化问题严重,例如水泥混凝土的基础长期经日晒、雨水侵袭等,容易出现风化起砂现象,造成基础卷材面层与基础脱层,严重时造成整个场地的瘫痪,需要重新铺设施工,大大的浪费人力物力,总之,传统基础十分容易出现损坏,例如鼓包、断裂、塌陷等现象,而且传统基础是在浪费资源,新建需要很多无机矿物原料,拆除产生大量建筑垃圾。施工过程中污染太大。The construction of the traditional site foundation is roughly the same as that of the highway roadbed. The steps include: earthwork excavation---plain soil tamping and rolling---backfilling sand and gravel rolling------backfilling three-lime soil rolling---backfilling Cement stabilization layer rolling---concrete surface layer, the construction period of the above steps is long, and the foundation is usually realized by using the local soil quality and then compacted. After the construction of the runway, for example, when it rains or when the artificial runway is cleaned with water, water, air, and settlement between the base layer and the artificial runway are often caused by the difficulty of drainage and exhaust of the base layer. Inconsistent frost heave coefficients lead to problems such as frost cracking, and in severe cases, bubbling occurs, affecting the use of the runway, and even causing damage to the runway, and the aging problem of the foundation is serious, such as the cement concrete foundation has been exposed to the sun and rain for a long time, etc. , prone to weathering and sanding, causing delamination of the surface layer of the foundation coil and the foundation. Fractures, subsidence and other phenomena, and the traditional foundation is a waste of resources. New construction requires a lot of inorganic mineral raw materials, and demolition produces a large amount of construction waste. There is too much pollution during the construction process.

有鉴于此,特提出本发明。In view of this, the present invention is proposed.

发明内容Contents of the invention

本发明旨在至少在一定程度上解决相关技术中的技术问题之一。The present invention aims to solve one of the technical problems in the related art at least to a certain extent.

为此本发明提供了一种场地基础。其具体技术方案如下:For this reason the present invention provides a kind of site foundation. Its specific technical scheme is as follows:

一种场地基础,包括多个基础模块,所述基础模块包括第一基础模块和第二基础模块,多个所述第一基础模块拼接成具有弧度的基础,多个所述第二基础模块拼接成矩形基础,所述基础模块内部镂空且设有可供人进入的空间,并在内侧设有排水通道。A site foundation, comprising a plurality of basic modules, the basic modules include a first basic module and a second basic module, a plurality of the first basic modules are spliced into a foundation with a radian, and a plurality of the second basic modules are spliced It forms a rectangular foundation, the interior of the foundation module is hollowed out and a space for people to enter is provided, and a drainage channel is provided on the inside.

根据本发明提供的预制塑胶跑道,将跑道基础进行整体结构上的改进,将其设计为预制的多个基础模块,基础模块内部镂空且设有可供人进入的空间,检修人员可以进入基础内部进行检修,并且具有良好的通气性,在基础模块内设有排水通道,提高了基础的降排水能力,其具有施工简单、缩短施工周期、基础的回弹统一、施工污染小、二次重复拆除可换位置组装等优点,延长了基础结构的使用寿命,解决了现有场地基础中存在的施工周期长、排气性和疏水性能比较差、抗冻胀性能低、冻裂、鼓包、基础维修困难等问题。According to the prefabricated plastic runway provided by the present invention, the overall structure of the runway foundation is improved, and it is designed as a plurality of prefabricated basic modules. The inside of the basic module is hollowed out and there is a space for people to enter, so that maintenance personnel can enter the interior of the foundation It is overhauled and has good ventilation. There are drainage channels in the foundation module, which improves the drainage capacity of the foundation. It has the advantages of simple construction, shortened construction period, uniform rebound of the foundation, small construction pollution, and repeated demolition twice The advantages of interchangeable position assembly prolong the service life of the foundation structure, and solve the problems of long construction period, poor air drainage and hydrophobic performance, low frost heaving resistance, frost cracking, bulging, and foundation maintenance existing in the foundation of the site. difficulties etc.

根据本发明的一个示例,所述基础面板上设置有多个与场地卷材面层的凸起相配合的凹槽,或,所述基础面板上设置有多个与场地卷材面层上的凹槽相配合的凸起。According to an example of the present invention, the base panel is provided with a plurality of grooves matching with the protrusions of the field coiled surface layer, or, the base panel is provided with a plurality of grooves that match with the field coiled material surface layer. The grooves match the protrusions.

根据本发明的一个示例,所述基础模块包括基础面板、挡土墙及承重立柱,所述基础面板的侧边设置有橡胶条,所述挡土墙包括外围挡土墙和内侧挡土墙,所述外围挡土墙和内侧挡土墙分别设置在所述基础面板下部的两侧并与基础面板相连接,所述承重立柱设置在所述外围挡土墙和内侧挡土墙之间,所述内侧挡土墙与所述承重立柱之间形成有排水通道,所述基础面板位于所述排水通道上方的位置设有多个排水口,排水通道与基础面板可拆卸连接,所述承重立柱形成排水通道的内壁,所述排水通道底部还设置有底板,所述底板分别与所述内侧挡土墙和所述内壁相连接,所述底板通过开口工具开设有排水口,所述排水口临近主下水井,并有与排水口配套口径的连接件与底板相连接,连接件下部连接有排水管线。According to an example of the present invention, the foundation module includes a foundation panel, a retaining wall and load-bearing columns, rubber strips are provided on the sides of the foundation panel, and the retaining wall includes a peripheral retaining wall and an inner retaining wall, The outer retaining wall and the inner retaining wall are respectively arranged on both sides of the lower part of the foundation panel and connected with the foundation panel, and the load-bearing column is arranged between the outer retaining wall and the inner retaining wall, so A drainage channel is formed between the inner retaining wall and the load-bearing column, and the base panel is located above the drainage channel. The inner wall of the drainage channel, the bottom of the drainage channel is also provided with a bottom plate, the bottom plate is respectively connected with the inner retaining wall and the inner wall, and the bottom plate is provided with a drainage port through an opening tool, and the drainage port is adjacent to the main The drain well is connected with the bottom plate by a connecting piece with a supporting diameter of the drain outlet, and the lower part of the connecting piece is connected with a drainage pipeline.

根据本发明的一个示例,所述外围挡土墙的顶部还设置有挡水部。According to an example of the present invention, a water retaining portion is further provided on the top of the peripheral retaining wall.

根据本发明的一个示例,所述挡水部为设置在外围挡土墙顶部的牙石。According to an example of the present invention, the water retaining part is calculus arranged on the top of the peripheral retaining wall.

根据本发明的一个示例,所述承重立柱底端向外延伸有支撑臂,所述支撑臂上安装有调平装置,所述调平装置安装在枕木上。According to an example of the present invention, a support arm extends outward from the bottom end of the load-bearing column, and a leveling device is installed on the support arm, and the leveling device is installed on a sleeper.

根据本发明的一个示例,所述调平装置包括连接板,所述承重立柱安装在所述连接板上,所述连接板上设有安装孔,所述安装孔上安装有螺杆,所述螺杆上安装有两个调平螺母,两个调平螺母分别位于支撑臂的上下两侧,所述螺杆的一端安装在所述枕木上,另一端通过所述调平螺母安装在所述连接板上。According to an example of the present invention, the leveling device includes a connecting plate, the load-bearing column is installed on the connecting plate, the connecting plate is provided with a mounting hole, and a screw is installed in the mounting hole, and the screw Two leveling nuts are installed on the top, and the two leveling nuts are respectively located on the upper and lower sides of the support arm. One end of the screw rod is installed on the sleeper, and the other end is installed on the connecting plate through the leveling nut. .

根据本发明的一个示例,所述调平螺母与所述支撑臂的之间还设置有弹性减震装置。According to an example of the present invention, an elastic damping device is further provided between the leveling nut and the support arm.

根据本发明的一个示例,所述弹性减震装置包括减震橡胶墩。According to an example of the present invention, the elastic damping device includes a damping rubber pier.

根据本发明的一个示例,所述基础模块的基础面板设有纵坡i,纵坡的坡度范围是:0.3%<i<0.6%。According to an example of the present invention, the foundation panel of the foundation module is provided with a longitudinal slope i, and the gradient range of the longitudinal slope is: 0.3%<i<0.6%.

根据本发明的一个示例,所述第一基础模块的横截面呈楔形状或扇形块,所述第二基础模块的横截面呈矩形状。According to an example of the present invention, the cross-section of the first basic module is wedge-shaped or sector-shaped, and the cross-section of the second basic module is rectangular.

本发明的一些附加方面和优点将在下面的描述中部分给出,部分将从下面的描述中变得明显,或通过本发明的实践了解到。Additional aspects and advantages of the invention will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of the invention.

附图说明Description of drawings

图1为本发明实施例的场地基础的跑道基础的示意图;Fig. 1 is the schematic diagram of the runway foundation of the field foundation of the embodiment of the present invention;

图2为本发明实施例的场地基础的多功能运动场地的场地基础的示意图;Fig. 2 is the schematic diagram of the field foundation of the multifunctional sports ground of the field foundation of the embodiment of the present invention;

图3为本发明实施例的场地基础的场地基础与基础卷材面层的一种配合关系示意图;Fig. 3 is a schematic diagram of a cooperative relationship between the site foundation and the foundation coil surface layer of the site foundation of the embodiment of the present invention;

图4为本发明实施例的场地基础的场地基础与基础卷材面层的另一种配合关系示意图;4 is a schematic diagram of another cooperative relationship between the site foundation and the base coil surface layer of the site foundation in the embodiment of the present invention;

图5本发明实施例的第一基础模块的结构示意图(一);Fig. 5 is a schematic structural view (1) of the first basic module of the embodiment of the present invention;

图6本发明实施例的第一基础模块的结构示意图(二);Fig. 6 is a schematic structural diagram (2) of the first basic module of the embodiment of the present invention;

图7本发明实施例的基础模块的结构示意图(一);Fig. 7 is a schematic structural view (1) of the basic module of the embodiment of the present invention;

图8本发明实施例的基础模块的结构示意图(二);Fig. 8 is a schematic structural diagram (2) of the basic module of the embodiment of the present invention;

图9本发明实施例的基础模块的下部结构示意图;Fig. 9 is a schematic diagram of the lower structure of the basic module of the embodiment of the present invention;

图10本发明实施例的基础模块的弹性减震装置与其他部件的连接关系示意图。Fig. 10 is a schematic diagram of the connection relationship between the elastic damping device of the basic module and other components in the embodiment of the present invention.

图中:1、第一基础模块;2、第二基础模块;3、基础面板;31、橡胶条;4、凹槽;5、凸起;6、挡土墙;61、外围挡土墙;62、内侧挡土墙;7、承重立柱;71、支撑臂;8、排水通道;9、排水口;10、底板;101、排水口;102、连接件;103、开口工具;104、排水管;11、挡水部;12、调平装置;121、连接板;1210、安装孔;122、螺杆;123、调平螺母;124、固定螺母;13、枕木;14、减震装置。In the figure: 1. First basic module; 2. Second basic module; 3. Basic panel; 31. Rubber strip; 4. Groove; 5. Protrusion; 6. Retaining wall; 61. Peripheral retaining wall; 62. Inner retaining wall; 7. Load-bearing column; 71. Support arm; 8. Drainage channel; 9. Drainage outlet; 10. Floor; 101. Drainage outlet; 11, water retaining part; 12, leveling device; 121, connecting plate; 1210, installation hole;

具体实施方式Detailed ways

下面详细描述本发明的实施例,所述实施例的示例在附图中示出,其中自始至终相同或类似的标号表示相同或类似的元件或具有相同或类似功能的元件。下面通过参考附图描述的实施例是示例性的,旨在用于解释本发明,而不能理解为对本发明的限制。Embodiments of the present invention are described in detail below, examples of which are shown in the drawings, wherein the same or similar reference numerals designate the same or similar elements or elements having the same or similar functions throughout. The embodiments described below by referring to the figures are exemplary and are intended to explain the present invention and should not be construed as limiting the present invention.

结合附图1-10所示,本实施例提供了一种场地基础,本发明的技术方案可以应用在跑道、球场、道路、机场等公共设施。申请人在施工过程及使用过程中发现,现有技术中场地基础的施工一致沿用路基施工工序,不仅施工工序复杂,施工工期较长,而且大多无法满足跑道基础的防水、防侵蚀功能,当部分基础发生排水不畅或冻胀问题时,基础会发生的积水、沉降、鼓泡、断裂等现象,不仅无法将其调整到原有的水平面,而且当鼓包、裂缝等现象严重时会造成整个跑道设施的瘫痪,因此申请人在跑道基础上进行了整体性的改进,把基础由将原来需要层层施工的路基结构改进为多个可拼接的基础模块,基础模块包括多个第一基础模块1和多个第二基础模块2,多个第一基础模块1拼接成具有弧度的基础,多个第二基础模块2拼接成矩形基础,第一基础模块1和第二基础模块2的截面形状可以根据场地进行定做、调整,基础模块内部镂空且设有可供人进入的空间,检修人员可以进入基础内部进行检修,并且具有良好的通气性,并在基础模块的内侧设有排水通道,提高了基础的降排水能力,其具有施工简单、缩短施工周期、基础的回弹统一等优点,延长了基础结构的使用寿命,并且每个基础模块的回弹、力学性能均相同,且结构稳定,解决了现有场地基础中存在的施工周期长、排气性和疏水性能比较差、抗冻胀性能低、冻裂、鼓包、基础维修困难等问题。需要说明的是,这里的“内”、“外”指的是跑道整体的内外方向。As shown in Figures 1-10, this embodiment provides a field foundation, and the technical solution of the present invention can be applied to public facilities such as runways, courts, roads, and airports. During the construction and use process, the applicant found that the construction of the ground foundation in the prior art is consistent with the subgrade construction process, which is not only complicated in construction procedures, but also has a long construction period, and most of them cannot meet the waterproof and anti-erosion functions of the runway foundation. When the foundation has poor drainage or frost heave, the foundation will have water accumulation, subsidence, bubbling, fracture, etc., which not only cannot be adjusted to the original level, but also will cause the entire The runway facilities were paralyzed, so the applicant made an overall improvement on the basis of the runway, improving the foundation from the subgrade structure that originally required layer-by-layer construction to multiple basic modules that can be spliced, and the basic modules include multiple first basic modules 1 and a plurality of second basic modules 2, a plurality of first basic modules 1 are spliced into a foundation with a radian, and a plurality of second basic modules 2 are spliced into a rectangular foundation, the cross-sectional shape of the first basic module 1 and the second basic module 2 It can be customized and adjusted according to the site. The interior of the basic module is hollowed out and there is a space for people to enter. Maintenance personnel can enter the interior of the foundation for maintenance. It has the advantages of simple construction, shortened construction period, uniform rebound of the foundation, etc., which prolongs the service life of the foundation structure, and the rebound and mechanical properties of each foundation module are the same, and the structure is stable. It solves the problems of long construction period, poor air-gassing and water-repelling properties, low frost-heaving resistance, frost cracks, bulges, and difficult foundation maintenance in the existing site foundation. It should be noted that the "inner" and "outer" here refer to the inner and outer directions of the runway as a whole.

例如图1所示的一种跑道场地基础,第一基础模块1的横截面呈楔形状,它包括多个B1块、C1块和C2块,第二基础模块2的横截面呈矩形状,其包括多个A1块和A2块,多个基础模块拼接成为一个整体的跑道基础,当然具体的形状和数量等可变量在本发明中不做过多限定,例如第一基础模块可以拼接成一个与场地卷材面层形状相类似的弧形即可。For example, a kind of runway site foundation shown in Fig. 1, the cross section of the first base module 1 is wedge-shaped, and it comprises a plurality of B1 block, C1 block and C2 block, and the cross section of the second base module 2 is rectangular, and its Including a plurality of A1 blocks and A2 blocks, a plurality of basic modules are spliced into a whole runway foundation. Of course, the variable variables such as specific shapes and quantities are not too limited in the present invention. For example, the first basic module can be spliced into one and The surface of the coiled material on the site is similar to the arc shape.

又例如图2所示的一种多功能运动场地,其具有跑道、球场、各种运动区域等,该多功能运动场地的场地基础,在工厂只需要生产A1、A2、B1、B2、C1、C2六种模块,之后运到现场组装就可以了;而一个完整的足球场只需要生产E1一种模块就可以了;多功能区由D1模块和D2模块组装而成,组装成后内部设有跳远沙坑,铅球区等多功能区。Another example is a multifunctional sports field shown in Figure 2, which has a runway, a court, various sports areas, etc., the field foundation of this multifunctional sports field only needs to produce A1, A2, B1, B2, C1, Six modules of C2 can be transported to the site for assembly; and a complete football field only needs to produce one module of E1; the multi-functional area is assembled by D1 module and D2 module. Long jump bunker, shot put area and other multi-functional areas.

除了上述改进之处,本发明的场地基础与场地卷材面层的结合方式也有多种,如图3所示,可以是现有技术中的使用环保胶水进行粘接,或者,如图4所示,在场地基础的基础面板3上均匀间隔分布有多个凹槽4,场地卷材面层的底面设有与凹槽相配合的凸起5,凸起5与凹槽4相咬合卡接,其结构稳定牢固且易于拆卸,又例如,可以在场地卷材面层的底面上均匀间隔分布有多个安装槽,基础面板上设有与安装槽相配合的凸起(未示出),其配合方式与上一种方案大体相同。需要说明的是,该凸起与凹槽或安装槽的形状任意,例如长条状、圆形、椭圆形等等均在本发明的保护范围之内。In addition to the above-mentioned improvements, there are many ways to combine the field foundation and the surface layer of the field coil of the present invention. As shown in Figure 3, it can be bonded using environmentally friendly glue in the prior art, or, as shown in Figure 4 As shown, there are a plurality of grooves 4 evenly distributed on the foundation panel 3 of the site foundation, and the bottom surface of the coiled material surface layer of the site is provided with a protrusion 5 matching with the groove, and the protrusion 5 is engaged with the groove 4 , its structure is stable and firm and easy to disassemble. For another example, a plurality of installation grooves can be evenly spaced on the bottom surface of the field coil surface, and the base panel is provided with protrusions (not shown) that match the installation grooves. Its matching mode is roughly the same as the previous scheme. It should be noted that the shape of the protrusion and the groove or the mounting groove is arbitrary, such as strip shape, circle shape, ellipse shape, etc., all fall within the protection scope of the present invention.

具体的,在本实施例中,基础模块的实施方式也可以有多种,如图5、6所示,基础模块包括基础面板3、挡土墙6及承重立柱7,基础面板3的侧边贴有防水作用的橡胶条31,挡土墙6包括外围挡土墙61和内侧挡土墙62,需要说明的是,这里的“内”、“外”也指的是跑道整体的内外方向,外围挡土墙61和内侧挡土墙62分别设置在基础面板3下部的两侧并与基础面板3相连接,承重立柱7设置在外围挡土墙61和内侧挡土墙62之间,内侧挡土墙62与承重立柱7之间形成有排水通道8,基础面板位于排水通道8上方的位置设有多个排水口9,本实施例中为两个,承重立柱7形成排水通道8的内壁,排水通道8底部还设置有底板10,底板10分别与内侧挡土墙62和内壁(即承重立柱)相连接。底板10通过开口工具103开设有排水口101,排水口101临近主下水井,并有配套口径的连接件102与底板相连接,连接件下部连接有排水管104。Specifically, in this embodiment, the implementation of the foundation module can also have multiple forms, as shown in Figures 5 and 6, the foundation module includes a foundation panel 3, a retaining wall 6 and a load-bearing column 7, and the side of the foundation panel 3 A rubber strip 31 with a waterproof effect is attached, and the retaining wall 6 includes a peripheral retaining wall 61 and an inner retaining wall 62. It should be noted that the "inner" and "outer" here also refer to the inner and outer directions of the runway as a whole. The outer retaining wall 61 and the inner retaining wall 62 are respectively arranged on both sides of the lower part of the foundation panel 3 and connected with the foundation panel 3, and the load-bearing column 7 is arranged between the outer retaining wall 61 and the inner retaining wall 62, and the inner retaining wall A drainage channel 8 is formed between the earth wall 62 and the load-bearing column 7. The base panel is located above the drainage channel 8 and is provided with a plurality of drainage outlets 9, two in this embodiment. The load-bearing column 7 forms the inner wall of the drainage channel 8. A bottom plate 10 is also provided at the bottom of the drainage channel 8, and the bottom plate 10 is respectively connected with the inner retaining wall 62 and the inner wall (ie, the load-bearing column). The bottom plate 10 is provided with a drain port 101 through an opening tool 103, and the drain port 101 is adjacent to the main drain well, and a connecting piece 102 of a matching diameter is connected to the bottom plate, and a drain pipe 104 is connected to the bottom of the connecting piece.

具体的,在本实施例中,可以将基础面板3、挡土墙6、承重立柱7及底板10等结构一体成型,也可分体组装成型,优选为分装成型,分装成型便于运输,一体成型可以增加结构稳定性,并且利于施工中的安装与拆卸。Specifically, in this embodiment, the structures such as the foundation panel 3, the retaining wall 6, the load-bearing column 7, and the bottom plate 10 can be integrally formed, or can be assembled separately, preferably in separate packaging, which is convenient for transportation. One-piece molding can increase structural stability and facilitate installation and disassembly during construction.

具体的,在本实施例中,为了进一步实现本发明的防排水功能,在外围挡土墙的顶部还设置有挡水部11,挡水部11的水平高度高于基础面板3的水平高度,该挡水部11可以是设置在外侧,作用是挡住外侧的泥水进入跑道内,弄脏跑道。挡土墙顶部的牙石,牙石可以与外围挡土墙一体成型,提高整体结构强度。有利的,本实施例的基础模块的基础面板设有纵坡i,纵坡的倾斜方向由外向内,纵坡的坡度范围是:0.3%<i<0.6%,该坡度的数值是基础面板的倾斜内外两端倾斜高度差除以基础面板的截面宽度,优选的,在本实施例中如图6所示,该坡度为0.5%。例如在塑胶跑道上,其纵坡方向是从跑道内圈从排水通道位置向跑道外圈逐渐升高(如剖面状类似于“碗”状),在足球场上,其纵坡方向是从球场外向球场中部逐渐升高(如剖面状类似于“龟背”状)。Specifically, in this embodiment, in order to further realize the waterproof and drainage function of the present invention, a water retaining portion 11 is also provided on the top of the peripheral retaining wall, and the level of the water retaining portion 11 is higher than that of the foundation panel 3. The water retaining part 11 can be arranged on the outside, and its effect is to block the muddy water on the outside from entering the runway and making the runway dirty. The calculus on the top of the retaining wall can be integrally formed with the surrounding retaining wall to improve the overall structural strength. Advantageously, the foundation panel of the foundation module of this embodiment is provided with a longitudinal slope i, the inclination direction of the longitudinal slope is from outside to inside, and the slope range of the longitudinal slope is: 0.3%<i<0.6%, and the value of the slope is the value of the foundation panel The slope height difference between the inner and outer ends of the slope is divided by the section width of the foundation panel. Preferably, as shown in FIG. 6 in this embodiment, the slope is 0.5%. For example, on a plastic runway, the direction of its longitudinal slope is gradually rising from the inner circle of the runway from the position of the drainage channel to the outer circle of the runway (such as the profile shape is similar to a "bowl" shape). The middle part of the outer court gradually rises (for example, the profile shape is similar to the "turtle back" shape).

具体的,在本实施例中,如图8所示,作为本发明的进一步改进,申请人为了实现基础的高度可以调整这一目的,在承重立柱7的底端向外延伸有支撑臂71,支撑臂上安装有调平装置12,调平装置12安装在枕木13上。有利的,在本实施例中,调平装置12的结构包括连接板121,承重立柱11安装在连接板121上,连接板121上设有安装孔1210,安装孔1210上安装有螺杆122,螺杆122上安装有两个调平螺母123,两个调平螺母123分别位于支撑臂71的上下两侧,螺杆122的一端安装在枕木13上,其可穿过下方的枕木13,并通过固定螺母124固定,另一端通过调平螺母123安装在连接板121上,当需要调整基础面板的高度和倾斜度时,可以通过调节调平螺母123在螺杆122上的竖直位置来进行操作。Specifically, in this embodiment, as shown in FIG. 8 , as a further improvement of the present invention, in order to achieve the purpose of adjusting the height of the foundation, the applicant has a support arm 71 extending outward from the bottom end of the load-bearing column 7, A leveling device 12 is installed on the support arm, and the leveling device 12 is installed on the crossties 13 . Advantageously, in this embodiment, the structure of the leveling device 12 includes a connecting plate 121, the load-bearing column 11 is installed on the connecting plate 121, the connecting plate 121 is provided with a mounting hole 1210, and a screw rod 122 is installed on the mounting hole 1210. Two leveling nuts 123 are installed on 122, and two leveling nuts 123 are positioned at the upper and lower sides of support arm 71 respectively, and one end of screw rod 122 is installed on the sleeper 13, and it can pass through the sleeper 13 below, and through fixing nut 124 is fixed, and the other end is installed on the connecting plate 121 through the leveling nut 123. When the height and inclination of the foundation panel need to be adjusted, it can be operated by adjusting the vertical position of the leveling nut 123 on the screw rod 122.

具体的,在本实施例中,如图9所示,申请人发现,大多数场地基础比较坚硬,为了提高人们运动时的舒适度,作为本发明的进一步改进,申请人在调平螺母123与支撑臂71的之间还设置有弹性减震装置14,弹性减震装置14可以作为一个缓冲的部件,大大提高运动者在运动过程中的舒适程度,具体的在本实施例中,该弹性减震装置优选为减震橡胶墩,橡胶垫除了减震以外,还有一个特殊作用:方便后期检查枕木是否上下移动了,如胶垫变形过大说明枕木被地面鼓起向上动了,如变形过小或出现间隙,说明枕木下沉。当然该弹性减震装置也可以是其他结构,例如为一个骨架结构的弹性件,又或者如桥梁结构的墩柱减震台等等,只要能起到减震缓冲效果即可。Specifically, in this embodiment, as shown in Figure 9, the applicant found that most of the grounds are relatively hard, in order to improve people's comfort when exercising, as a further improvement of the present invention, the applicant added the leveling nut 123 and An elastic shock absorber 14 is also arranged between the support arms 71, and the elastic shock absorber 14 can be used as a cushioning part to greatly improve the comfort level of the athlete during exercise. Specifically, in this embodiment, the elastic shock absorber 14 The vibration device is preferably a shock-absorbing rubber pier. In addition to shock absorption, the rubber pad has a special function: it is convenient to check whether the sleeper has moved up and down in the later stage. Small or gaps appear, indicating that the sleepers are sinking. Of course, the elastic damping device can also be other structures, such as an elastic member of a skeleton structure, or a pier column shock absorber of a bridge structure, etc., as long as it can play a shock absorbing and buffering effect.

具体的,在本实施例中,为了体现本发明的智能与系统全面化,申请人还设计有参数信息储存系统,其用于储存铺装跑道的场地的参数信息,该参数信息包括场地尺寸参数、土质参数、各模块信息等等,根据不同场地,工厂在定制生产的时候会将该场地的信息储存起来,便于后期调取使用。Specifically, in this embodiment, in order to reflect the intelligence and comprehensiveness of the system of the present invention, the applicant also designed a parameter information storage system, which is used to store parameter information of the site where the runway is paved, and the parameter information includes site size parameters , Soil parameters, information of each module, etc. According to different sites, the factory will store the information of the site when customizing production, so that it can be retrieved and used later.

下面结合本发明的制作生产工艺作进一步的阐述:Further elaboration is made below in conjunction with the production process of the present invention:

模块化基础的生产:根据场地尺寸,将场地基础及排水沟设计在一体,将基础分成便于运输为目的的若干小块,内部镂空,同时在单一小块上设计出各种功能性连接件及预留功能性孔位。Production of modular foundation: According to the size of the site, design the site foundation and drainage ditch together, divide the foundation into several small pieces for the purpose of transportation, hollow out the inside, and design various functional connectors and Reserve functional holes.

模块化塑胶跑道/球场的施工工艺:Construction technology of modular plastic runway/court:

1、现场按照初期设计好的尺寸,进行挖土,深度以模块化跑道的模块高度一致,平整土层,素土夯实。1. The site shall be excavated according to the initially designed size. The depth shall be the same as the module height of the modular runway. The soil layer shall be leveled and the plain soil shall be compacted.

2、用级配碎石埋设枕木,枕木上配有标准承重螺栓,枕木按照设计尺寸用专用的规格控制卡尺,确定位置及间距。2. Use graded crushed stones to bury the sleepers. The sleepers are equipped with standard load-bearing bolts. The sleepers are controlled with special specifications to control the calipers according to the design size to determine the position and spacing.

3、组装模块化的基础,枕木上有一个控制调平的螺丝,及一个加固螺丝,在两个螺丝之上安装模块化基础,并且在连接板与调节螺母之间设有弹性橡胶墩,模块化基础上有预留的孔位可穿过枕木上的螺栓,调整好高度后,紧好螺栓,继续安装下一片模块化基础,在两个模块化基础的链接处有预留的孔位,可用螺丝固定好,最终使整个运动场的模块化基础连接成为一个整体。3. Assemble the modular foundation. There is a control leveling screw and a reinforcement screw on the sleeper. The modular foundation is installed on the two screws, and there is an elastic rubber pier between the connecting plate and the adjusting nut. The module There are reserved holes on the modular foundation that can pass through the bolts on the sleepers. After adjusting the height, tighten the bolts and continue to install the next piece of modular foundation. There are reserved holes at the link between the two modular foundations. It can be fixed with screws, finally making the modular foundation connection of the entire sports field a whole.

4、安装模块化塑胶面层。按照序号依次安装好模块化面层。初期产品塑胶面层与基础质检采用环保胶水粘接,产品升级后,无需胶水,模块化基础和塑胶面层均设计出连接用的固件,比如公母扣,基础为母,塑胶面层为公,相互咬合连接。4. Install the modular plastic surface. Install the modular surface layer in sequence according to the serial number. The plastic surface layer of the initial product and the basic quality inspection are bonded with environmentally friendly glue. After the product is upgraded, no glue is needed. Both the modular foundation and the plastic surface layer are designed with fasteners for connection, such as male and female buckles, the foundation is the female, and the plastic surface layer is Male, interlocking connection.

5、清扫场地,嘱咐使用方的注意事项,并交代使用方如何巡检,如何调平。5. Clean the site, instruct the user to pay attention, and explain how to inspect and level the user.

6、派人定期现场巡检,经使用方允许,从检查口进入跑道基础内部,检查是否有因枕木下沉而产生的悬空现象,是否有因枕木鼓胀而产生的基础鼓胀现象。6. Send people to conduct regular on-site inspections. With the permission of the user, enter the interior of the runway foundation from the inspection port to check whether there is any suspension caused by the sinking of the sleepers and whether there is any foundation bulging caused by the bulging of the sleepers.

综上所述,结合以上对技术方案的制作工艺及施工过程的描述,本实施例提供的场地基础具有以下有益效果:In summary, combined with the above description of the manufacturing process and construction process of the technical solution, the site foundation provided by this embodiment has the following beneficial effects:

1、场地基础在工厂模块化生产,不在现场调配原材料,现场无施工垃圾、灰尘等,减少环境污染。1. The site foundation is modularized in the factory, and raw materials are not deployed on site. There is no construction waste, dust, etc. on site, reducing environmental pollution.

2、车间规范化生产,避免产品质量参差不齐。2. Standardized production in the workshop to avoid uneven product quality.

3、基础平整度好,坡度整体统一,有效防积水。接缝少,整体美观度增强。3. The flatness of the foundation is good, the slope is uniform as a whole, and it can effectively prevent stagnant water. Fewer seams enhance overall aesthetics.

4、基础回弹性统一,避免因为软硬不均而对运动员造成损伤。4. The basic resilience is uniform to avoid damage to athletes due to uneven hardness.

5、环保系数高,规模化生产有效防止劣质原材料掺入,有效控制质量把关。5. High environmental protection factor, large-scale production can effectively prevent the mixing of inferior raw materials, and effectively control the quality.

6、工厂模块化生产,标准化程度高,精密程度高,规格统一,标志线精准,尺寸精确,有效减少人为误差。6. Modular production in the factory, high degree of standardization, high degree of precision, uniform specifications, accurate marking lines, accurate dimensions, effectively reducing human errors.

7、模块化面层和场地基础可用环保胶水粘接,亦可无需胶水,采用公母连接件的形式组装连接,减少污染的同时,减低了安装过程中人为因素的影响。7. The modular surface layer and the site foundation can be bonded with environmentally friendly glue, or they can be assembled and connected in the form of male and female connectors without glue, which reduces pollution and reduces the influence of human factors in the installation process.

8、调平装置有效防冻胀,有效防沉降。8. The leveling device can effectively prevent frost heave and subsidence.

9、减少资源浪费,减少人力物力浪费,无需根据不同地质结构单独设计,减少设计成本,有效节约成本。9. Reduce the waste of resources, reduce the waste of manpower and material resources, do not need to design separately according to different geological structures, reduce design costs, and effectively save costs.

10、减少砂石及混凝土等不可回收的材料用量,基础镂空化的设计降低重量,运输方便,模块化后只需半成品运输,无需单独运输砂石、混凝土等材料,以及各种单独辅材,节约运输成本,变相减少二氧化碳排放量,有效保护环境。10. Reduce the amount of non-recyclable materials such as sand, gravel and concrete. The hollowed-out design of the foundation reduces weight and is convenient for transportation. Save transportation costs, reduce carbon dioxide emissions in disguise, and effectively protect the environment.

11、基础模块化后预留的检查口,人可进入,随时检查跑道底部结构是否有破损,做到提前预防,和随时调平,避免悬空和鼓胀现象发生。11. The inspection port reserved after the basic modularization can be entered by people to check whether the bottom structure of the runway is damaged at any time, so as to prevent it in advance and level it at any time to avoid the occurrence of suspension and bulging.

12.、可工厂化量产,亦可个性定制生产。12. It can be mass-produced in a factory or customized.

13、后期维护方便,无需大面积拆除,基础模块出现个别区域破损,均可根据编号调取早期数据后,按照数据重新生产此编号的产品,单独更换此编号产品即可。避免整体拆除造成经济和资源的浪费。13. It is easy to maintain in the later stage, without large-scale dismantling, and if the basic module is damaged in some areas, you can retrieve the early data according to the number, re-produce the product with this number according to the data, and replace the product with this number alone. Avoid the waste of economy and resources caused by the overall demolition.

14、使用年限长,使用年限比原有砂石混凝土基础增加数倍使用年限。14. The service life is long, and the service life is several times longer than that of the original sandstone concrete foundation.

15、可回收,模块化基础的材质使用可回收材料,避免了因拆除而造成的环境污染。15. Recyclable, the material of the modular base uses recyclable materials, which avoids environmental pollution caused by demolition.

16、应用领域广,跑道,足球场,篮球场、道路等各种场地均可模块化生产后现场组装。减少了现场地面土层施工而造成的环境污染。16. It has a wide range of applications, and various venues such as runways, football fields, basketball courts, and roads can be modularized and assembled on site. The environmental pollution caused by the ground soil layer construction on site is reduced.

17、模块大块生产,大块拼装,接缝少,整体美观度增强。17. The modules are produced in large blocks, assembled in large blocks, with fewer seams, and the overall aesthetics are enhanced.

18、拆装方便,可更换场地重新组装即可。18. It is easy to disassemble and assemble, and the site can be replaced and reassembled.

19、无需下挖土层或浅挖土层,根据已生产好的或预生产的模块化跑道及现场情况挖基础,减少挖掘及运输成本。19. No need to excavate the soil layer or shallow excavate the soil layer, and dig the foundation according to the produced or pre-produced modular runway and the site conditions, reducing excavation and transportation costs.

20、施工周期短、速度快,无需养护期,施工完毕可立刻投入使用20. The construction period is short, the speed is fast, no maintenance period is required, and it can be put into use immediately after construction

21、可全年施工,春夏秋冬、雨季均不影响施工。21. It can be constructed throughout the year, and the construction will not be affected in spring, summer, autumn, winter and rainy season.

22、具有可预见性,在铺装之前使用方可提前预知未来做出的场地性能和模样,避免传统的基础在铺装之前使用方无法准确预测。22. It is predictable, and the user can predict the future site performance and appearance in advance before paving, so as to avoid the inability to accurately predict the traditional foundation before paving.

需要说明的是,在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”、“顺时针”、“逆时针”、“轴向”、“径向”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。It should be noted that, in the description of the present invention, it should be understood that the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "Front", "Back", "Left", "Right", "Vertical", "Horizontal", "Top", "Bottom", "Inner", "Outer", "Clockwise", "Counterclockwise", The orientations or positional relationships indicated by "axial", "radial", and "circumferential" are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying the It should not be construed as limiting the invention that a device or element must have a particular orientation, be constructed, and operate in a particular orientation.

此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,“多个”的含义是两个以上,除非另有明确具体的限定。In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be interpreted as indicating or implying relative importance or implicitly specifying the quantity of indicated technical features. Thus, a feature defined as "first" and "second" may explicitly or implicitly include one or more of these features. In the description of the present invention, "plurality" means two or more, unless otherwise specifically defined.

在本发明中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the present invention, unless otherwise clearly specified and limited, terms such as "installation", "connection", "connection" and "fixation" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection , or integrated; it can be mechanically connected or electrically connected; it can be directly connected or indirectly connected through an intermediary, and it can be the internal communication of two components or the interaction relationship between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention according to specific situations.

在本发明中,除非另有明确的规定和限定,第一特征在第二特征“上”或“下”可以是第一和第二特征直接接触,或第一和第二特征通过中间媒介间接接触。而且,第一特征在第二特征“之上”、“上方”和“上面”可是第一特征在第二特征正上方或斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”可以是第一特征在第二特征正下方或斜下方,或仅仅表示第一特征水平高度小于第二特征。In the present invention, unless otherwise clearly specified and limited, the first feature may be in direct contact with the first feature or the first and second feature may be in direct contact with the second feature through an intermediary. touch. Moreover, "above", "above" and "above" the first feature on the second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. "Below", "beneath" and "beneath" the first feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is less horizontally than the second feature.

在本说明书的描述中,参考术语“一个实施例”、“一些实施例”、“示例”、“具体示例”、或“一些示例”等的描述意指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。而且,描述的具体特征、结构、材料或者特点可以在任一个或多个实施例或示例中以合适的方式结合。此外,在不相互矛盾的情况下,本领域的技术人员可以将本说明书中描述的不同实施例或示例以及不同实施例或示例的特征进行结合和组合。In the description of this specification, descriptions referring to the terms "one embodiment", "some embodiments", "example", "specific examples", or "some examples" mean that specific features described in connection with the embodiment or example , structure, material or characteristic is included in at least one embodiment or example of the present invention. Furthermore, the described specific features, structures, materials or characteristics may be combined in any suitable manner in any one or more embodiments or examples. In addition, those skilled in the art can combine and combine different embodiments or examples and features of different embodiments or examples described in this specification without conflicting with each other.

尽管上面已经示出和描述了本发明的实施例,可以理解的是,上述实施例是示例性的,不能理解为对本发明的限制,本领域的普通技术人员在本发明的范围内可以对上述实施例进行变化、修改、替换和变型。Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and should not be construed as limiting the present invention, and those skilled in the art can make the above-mentioned The embodiments are subject to changes, modifications, substitutions and variations.

Claims (10)

1.一种场地基础,其特征在于,包括多个基础模块,所述基础模块包括第一基础模块和第二基础模块,多个所述第一基础模块拼接成具有弧度的基础,多个所述第二基础模块拼接成矩形基础,所述基础模块内部镂空且设有可供人进入的空间,并在内侧设有排水通道。1. A site foundation, characterized in that it includes a plurality of foundation modules, the foundation modules include a first foundation module and a second foundation module, a plurality of the first foundation modules are spliced into a foundation with a radian, and a plurality of the foundation modules The second basic module is spliced into a rectangular foundation, and the interior of the basic module is hollowed out and provided with a space for people to enter, and a drainage channel is provided inside. 2.根据权利要求1所述的场地基础,其特征在于,所述基础模块上设置有多个与场地卷材面层的凸起相配合的凹槽,或,所述基础模块上设置有多个与场地卷材面层上的凹槽相配合的凸起。2. The site foundation according to claim 1, characterized in that, the base module is provided with a plurality of grooves that cooperate with the protrusions of the site coil surface, or, the base module is provided with multiple A protrusion that fits into a groove on the field's membrane surface. 3.根据权利要求1所述的场地基础,其特征在于,所述基础模块包括基础面板、挡土墙及承重立柱,所述基础面板的侧边设置有橡胶条,所述挡土墙包括外围挡土墙和内侧挡土墙,所述外围挡土墙和内侧挡土墙分别设置在所述基础面板下部的两侧并与基础面板相连接,所述承重立柱设置在所述外围挡土墙和内侧挡土墙之间,所述内侧挡土墙与所述承重立柱之间形成有排水通道,所述基础面板位于所述排水通道上方的位置设有多个排水口,排水通道与基础面板可拆卸连接,所述承重立柱形成排水通道的内壁,所述排水通道底部还设置有底板,所述底板分别与所述内侧挡土墙和所述内壁相连接,所述底板通过开口工具开设有排水口,所述排水口临近主下水井,并有与排水口配套口径的连接件与底板相连接,连接件下部连接有排水管。3. The site foundation according to claim 1, wherein the foundation module includes a foundation panel, a retaining wall and a load-bearing column, rubber strips are provided on the side of the foundation panel, and the retaining wall includes a peripheral A retaining wall and an inner retaining wall, the peripheral retaining wall and the inner retaining wall are respectively arranged on both sides of the lower part of the foundation panel and connected with the foundation panel, and the load-bearing columns are arranged on the outer retaining wall Between the inner retaining wall and the inner retaining wall, a drainage channel is formed between the inner retaining wall and the load-bearing column, and the foundation panel is provided with a plurality of drainage outlets above the drainage channel, and the drainage channel and the foundation panel The connection is detachable, the load-bearing column forms the inner wall of the drainage channel, the bottom of the drainage channel is also provided with a bottom plate, and the bottom plate is respectively connected with the inner retaining wall and the inner wall, and the bottom plate is opened with an opening tool. A drain, the drain is adjacent to the main well, and a connector with a matching diameter of the drain is connected to the bottom plate, and the lower part of the connector is connected with a drain pipe. 4.根据权利要求3所述的场地基础,其特征在于,所述外围挡土墙的顶部还设置有挡水部。4. The site foundation according to claim 3, characterized in that, a water retaining portion is further provided on the top of the peripheral retaining wall. 5.根据权利要求4所述的场地基础,其特征在于,所述挡水部为设置在外围挡土墙顶部的牙石。5. The site foundation according to claim 4, characterized in that, the water retaining part is calculus arranged on the top of the outer retaining wall. 6.根据权利要求3所述的场地基础,其特征在于,所述承重立柱底端向外延伸有支撑臂,所述支撑臂上安装有调平装置,所述调平装置安装在枕木上。6 . The site foundation according to claim 3 , wherein a support arm extends outward from the bottom end of the load-bearing column, and a leveling device is installed on the support arm, and the leveling device is installed on a sleeper. 7.根据权利要求6所述的场地基础,其特征在于,所述调平装置包括连接板,所述承重立柱安装在所述连接板上,所述连接板上设有安装孔,所述安装孔上安装有螺杆,所述螺杆上安装有两个调平螺母,两个调平螺母分别位于支撑臂的上下两侧,所述螺杆的一端安装在所述枕木上,另一端通过所述调平螺母安装在所述连接板上。7. The site foundation according to claim 6, wherein the leveling device includes a connecting plate, the load-bearing column is installed on the connecting plate, and the connecting plate is provided with a mounting hole, and the mounting A screw rod is installed on the hole, and two leveling nuts are installed on the screw rod. The two leveling nuts are respectively located on the upper and lower sides of the support arm. One end of the screw rod is installed on the sleeper, and the other end passes through the A flat nut is installed on the connecting plate. 8.根据权利要求7所述的场地基础,其特征在于,所述调平螺母与所述支撑臂的之间还设置有弹性减震装置。8 . The site foundation according to claim 7 , wherein an elastic damping device is further provided between the leveling nut and the support arm. 9.根据权利要求8所述的场地基础,其特征在于,所述弹性减震装置包括减震橡胶墩。9. The site foundation according to claim 8, characterized in that, the elastic damping device comprises a damping rubber pier. 10.根据权利要求3所述的场地基础,其特征在于,所述基础模块的基础面板设有纵坡i,纵坡的坡度范围是:0.3%<i<0.6%。10. The site foundation according to claim 3, wherein the foundation panel of the foundation module is provided with a longitudinal slope i, and the gradient range of the longitudinal slope is: 0.3%<i<0.6%.
CN201610767347.8A 2016-08-29 2016-08-29 Place basis Active CN106192670B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201610767347.8A CN106192670B (en) 2016-08-29 2016-08-29 Place basis
PCT/CN2016/101674 WO2018040228A1 (en) 2016-08-29 2016-10-10 Site foundation and modular rubberized site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610767347.8A CN106192670B (en) 2016-08-29 2016-08-29 Place basis

Publications (2)

Publication Number Publication Date
CN106192670A CN106192670A (en) 2016-12-07
CN106192670B true CN106192670B (en) 2018-07-03

Family

ID=58089093

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610767347.8A Active CN106192670B (en) 2016-08-29 2016-08-29 Place basis

Country Status (1)

Country Link
CN (1) CN106192670B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111270582A (en) * 2020-01-22 2020-06-12 哈尔滨工业大学 Large-scale intelligent temporary detachable runway system
CN112681059B (en) * 2020-12-03 2024-09-06 中建六局土木工程有限公司 Large-area variable-curvature football field construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2395135A (en) * 2002-11-06 2004-05-19 Malcolm John Dorman Artificial sports surface
CN201473850U (en) * 2009-05-05 2010-05-19 欧阳鹰湘 Prefabricated concrete member for playground drainage ditch
CN205205612U (en) * 2015-12-02 2016-05-04 福建路港(集团)有限公司 Synthetic track
CN206157522U (en) * 2016-08-29 2017-05-10 陆大伟 Place basis

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9631328B2 (en) * 2014-03-12 2017-04-25 Permavoid Limited Sports field structure and modules and method for forming the same

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2395135A (en) * 2002-11-06 2004-05-19 Malcolm John Dorman Artificial sports surface
CN201473850U (en) * 2009-05-05 2010-05-19 欧阳鹰湘 Prefabricated concrete member for playground drainage ditch
CN205205612U (en) * 2015-12-02 2016-05-04 福建路港(集团)有限公司 Synthetic track
CN206157522U (en) * 2016-08-29 2017-05-10 陆大伟 Place basis

Also Published As

Publication number Publication date
CN106192670A (en) 2016-12-07

Similar Documents

Publication Publication Date Title
CN109972659B (en) Novel municipal inspection well structure and construction method
CN111576127B (en) Highway engineering new and old pavement splicing structure and construction method thereof
WO2018040228A1 (en) Site foundation and modular rubberized site
CN111962350A (en) Geocell Reinforced Cement Concrete Pavement Structure and Surface Slab Thickness Calculation Method
CN103758010B (en) Construction method of ecological pavement
CN108316089A (en) It is a kind of that road surface method is repaired using plain concrete and reinforced concrete
CN106939541A (en) A kind of semi-rigid semi-flexible Widening of Freeway pavement structure and method
CN207714057U (en) A kind of anti-settling road structure
CN106192670B (en) Place basis
CN106192671B (en) Modularization synthetic court
CN202220319U (en) Unidirectional water permeable sidewalk base course
CN214992786U (en) Municipal administration road design road surface domatic structure
CN206157522U (en) Place basis
CN210507176U (en) Road and bridge crack reinforced structure
CN205329446U (en) Upper and lower staggered floor precast reinforced concrete basic unit of permeating water
CN207958949U (en) Asphalt road surface local repairs structure
CN204589746U (en) A kind of composite road surface structure being applicable to saturated dredger soft soil area Heavy Traffic condition
CN110886378A (en) Construction method of water storage vibration reduction device installed under greening road and sidewalk
CN201746757U (en) Bidirectional interlocking brick and road surface thereby
CN206127789U (en) Structure of making an uproar falls in highway tunnel driving damping
CN114687263A (en) Prefabricated assembly type roadbed widening structure and construction method
KR20140114711A (en) Improvement Method for Base Ground of Pavement Block using Light-Weighted Foam Soil
CN204401373U (en) For structure under the prefabricated assembled rail of tram
CN202849886U (en) Concrete slab road surface structure
CN206457692U (en) A kind of road side stone mounting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220915

Address after: 414400 south of sanjiaotang road and west of Xintang Road (Miluo Industrial Park, Changsha Economic Development Zone), Bishi Town, Miluo City, Yueyang City, Hunan Province

Patentee after: HUNAN U-CROWN SPORTS MATERIAL Co.,Ltd.

Address before: No. 2, Tonggang Street, Daowai District, Harbin, Heilongjiang, 150010

Patentee before: Lu Dawei

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Site foundation

Granted publication date: 20180703

Pledgee: Hunan Miluo rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN U-CROWN SPORTS MATERIAL Co.,Ltd.

Registration number: Y2024980054726