[go: up one dir, main page]

CN106088305A - Greenery patches and construction method thereof with underground conservation pool - Google Patents

Greenery patches and construction method thereof with underground conservation pool Download PDF

Info

Publication number
CN106088305A
CN106088305A CN201610629867.2A CN201610629867A CN106088305A CN 106088305 A CN106088305 A CN 106088305A CN 201610629867 A CN201610629867 A CN 201610629867A CN 106088305 A CN106088305 A CN 106088305A
Authority
CN
China
Prior art keywords
cistern
greenery patches
central controller
plc central
plantation layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610629867.2A
Other languages
Chinese (zh)
Inventor
张平
许静
徐建华
刘潇
刘崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU ARCHITECTURE GARDENS LANDSCAPE PLANNING DESIGN Co Ltd
Original Assignee
SUZHOU ARCHITECTURE GARDENS LANDSCAPE PLANNING DESIGN Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU ARCHITECTURE GARDENS LANDSCAPE PLANNING DESIGN Co Ltd filed Critical SUZHOU ARCHITECTURE GARDENS LANDSCAPE PLANNING DESIGN Co Ltd
Priority to CN201610629867.2A priority Critical patent/CN106088305A/en
Publication of CN106088305A publication Critical patent/CN106088305A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G25/00Watering gardens, fields, sports grounds or the like
    • A01G25/02Watering arrangements located above the soil which make use of perforated pipe-lines or pipe-lines with dispensing fittings, e.g. for drip irrigation
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • E03F5/102Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins using already existing parts of the sewer system for runoff-regulation
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/05Programmable logic controllers, e.g. simulating logic interconnections of signals according to ladder diagrams or function charts

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Water Supply & Treatment (AREA)
  • Health & Medical Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Soil Sciences (AREA)
  • Environmental Sciences (AREA)
  • Cultivation Of Plants (AREA)

Abstract

The invention belongs to environmental greening technical field, it is specifically related to a kind of greenery patches with underground conservation pool and construction method thereof, described greenery patches includes planting layer and cistern, in the middle of described plantation layer, low both sides are gradually increased, and are provided with flat ditch at lowest part, and the lowest part of flat ditch is provided with inspection shaft, or plantation layer surrounding height gradually reduces to centre, being provided with inspection shaft at lowest part, described inspection shaft is to having sewer, and described sewer connects following cistern.The greenery patches of this invention is provided with underground conservation pool, rainwater storage application and later arid pouring, it addition, its greenery patches planting groove is with hygrosensor, can actively be opened spray pump when humidity is less than lower limit and watered meadow, use manpower and material resources sparingly.

Description

Greenery patches and construction method thereof with underground conservation pool
Technical field
The invention belongs to environmental greening technical field, be specifically related to a kind of greenery patches with underground conservation pool and construction party thereof Method.
Background technology
At present, the green grassland in city relies on natural rain pouring, can cause waterlogging phenomenon when rainfall is bigger, and weather Manual watering to be relied on during arid, labor intensive material resources, rainwater is the most well utilized.
Summary of the invention
In order to solve the problems referred to above, the construction in response to sponge city simultaneously needs, and urban lawn greenery patches with cistern is Inevitable trend, it is an object of the invention to provide a kind of greenery patches with underground conservation pool and construction method thereof, on solving State the problem proposed in background technology.
The technical scheme that the present invention provides is as follows: a kind of greenery patches with underground conservation pool, including plantation layer and cistern, It is characterized in that in the middle of described plantation layer, low both sides are gradually increased, and are provided with flat ditch at lowest part, the lowest part of flat ditch is provided with inspection shaft, Or plantation layer surrounding height gradually reduces to centre, is provided with inspection shaft at lowest part, and described inspection shaft is to having sewer, described Sewer connect following cistern.
Further preferred version, described cistern is provided with conical bottom, and what described conical bottom was provided with sludge pump enters dirt Mouthful, the upper side wall of described cistern is provided with drain pipe, the river near drain pipe connection.
Further preferred version, described inspection shaft is provided with the grid of comb mouth or reinforcement welding, the lower water below comb mouth Road sidewall is provided with in the cistern of cat ladder connection bottom, in order to convenient construction and maintenance.
Further preferred version, another sidewall of described sewer is provided with the control room of sealing, or by control room Arrange on the ground, in described control room, be provided with spray pump, sludge pump and PLC central controller.
Further preferred version, described spray pump is provided with water inlet pipe and outlet pipe, the water inlet of described water inlet pipe Being arranged on the bottom sidewall of cistern, described outlet pipe is embedded in plantation layer, and connects on outlet pipe as required Going out multiple shower, shower upper end is provided with spray head;Also can connect drip irrigation pipe on outlet pipe, drip irrigation pipe circulation is laid in On greenery patches.
Further preferred version, described sludge pump is provided with dirt inlet and sewage draining exit, and described dirt inlet is arranged on institute The bottommost of the conical bottom of the cistern stated, described sewage outfalls setting ground more than plantation layer.
Further preferred version, described plantation layer is provided with hygrosensor, can be arranged as required to multiple, described Hygrosensor connect PLC central controller, hygrosensor detect plantation layer humidity reach set lower limit time, will Signal passes to PLC central controller, and PLC central controller starts spray pump and supplies water shower, spray head to greenery patches be Flowers and plants carry out spray pouring, when hygrosensor detect plantation layer in moisture reach set the upper limit time, by signal pass Passing PLC central controller, PLC central controller closes spray pump.
Further preferred version, the bottom sidewall of described cistern is provided with mud search switch, described mud detection Switch connects PLC central controller, when in mud search switch detects conical bottom, precipitating sludge reaches the upper limit, is passed by signal Passing PLC central controller, PLC central controller starts sludge pump and is arranged in thick grass earthward by mud.
The invention also discloses the construction method in a kind of greenery patches with underground conservation pool, comprise the steps:
(1) arranging plantation layer: according to the shape in greenery patches with need to arrange, the plantation layer in rectangle greenery patches is designed to middle low The shape that both sides are gradually increased, arranges flat ditch at middle lowest part, arranges flat ditch at middle lowest part, and the lowest part at flat ditch digs The foundation ditch of cistern;The plantation layer in strip greenery patches is then designed to the tilted shape that low side, side is high, sets at lower side Putting flat ditch, the lowest part at flat ditch digs the foundation ditch of cistern;And the greenery patches in plot circular, square, then it is designed between surrounding senior middle school The shape being gradually lowered, digs the foundation ditch of cistern at middle lowest part.
(2) cistern is built: cistern is embedded in underground, sets the volume of cistern, every 3-5 according to the area in greenery patches Greenery patches sets 1m3Cistern volume, pile up construction cistern with concrete prefabricated or masonry, columns base is arranged to taper The end, the lowest part in conical bottom arranges the dirt inlet of sludge pump, at cistern upper portion side wall horizontally set drain pipe, on cistern Portion sets up rectangle sewer along sidewall, arranges cat ladder connection columns base, sewer upper on the sidewall of sewer Face is catch pit port, and described catch pit port is provided with the grid of comb mouth or reinforcement welding.
(3) control room is set: another sidewall at sewer arranges the control room of sealing or in ground arrangement above control Room processed, arranges spray pump, sludge pump and PLC central controller in control room;The water inlet of described spray pump is arranged on storage On the bottom sidewall in pond, the outlet pipe of spray pump is embedded in plantation layer, and connects multiple as required on outlet pipe Shower, arranges spray head in shower upper end;Or connecting drip irrigation pipe on outlet pipe, drip irrigation pipe circulation is laid in greenery patches In flowers and plants;The water inlet pipe of described sludge pump connects the dirt inlet of columns base, and the sewage outfalls setting of sludge pump is at plantation layer Above ground.
(4) arranging detector: the bottom sidewall at cistern arranges mud search switch, described mud search switch is even Connect PLC central controller;Arranging multiple hygrosensor at plantation layer, described hygrosensor connects PLC central controller.
(5) greenery patches plantation and daily management: sow flowers and plants seed or plant into flowers and plants on plantation layer, plant drought-enduring aloft Plant, plants waterlogging plant in lower, opens spray pump pouring or utilizes natural rain to water, and rainwater penetrates into ground through plantation layer Under, when rainwater is excessive, in the inspection shaft of the lowest part that rainwater can flow into greenery patches, and enter the cistern being located in the ground, cistern Man Hou, rainwater enters river along drain pipe;When many days fine days in summer, hygrosensor detects that plantation layer humidity reaches to set During fixed lower limit, signal passing to PLC central controller, PLC central controller starts spray pump and supplies water shower, by spraying Drench head or flowers and plants are sprayed or water by drip irrigation pipe, when hygrosensor detect plantation layer in moisture reach set During the upper limit, signal passing to PLC central controller, PLC central controller closes spray pump;Sink through long mud Form sediment, when precipitating sludge reaches the upper limit in mud search switch detects conical bottom, signal passed to PLC central controller, PLC central controller starts sludge pump and is arranged in thick grass earthward by mud;In greenery patches flowers and plants grow, also can be in cistern Add water soluble fertilizer or pesticide.
The technique effect of the present invention and advantage: the greenery patches of this invention is provided with underground conservation pool, can apply rainwater storage With later arid pouring, it addition, its greenery patches planting groove is with hygrosensor, actively open spray when humidity is less than lower limit Being watered in meadow by pump, uses manpower and material resources sparingly.
Accompanying drawing explanation
Fig. 1 is the cross section structure schematic diagram of the present invention.
In figure: 1-kind plants layer, 2-control room, 3-spray pump, 4-inspection shaft, 5-sewer, 6-spray head, 7-shower, 8- Drain pipe, 9-water inlet, 10-mud search switch, 11-cistern, 12-conical bottom, 13-dirt inlet, 14-sludge pump, 15-arranges Dirty mouth, 16-hygrosensor.
Detailed description of the invention
Below in conjunction with accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described.
A kind of greenery patches with underground conservation pool, including low both sides in the middle of plantation layer 1 and cistern 11, described plantation layer 1 Being gradually increased, be provided with flat ditch at lowest part, the lowest part of flat ditch is provided with inspection shaft 4, or plantation layer 1 surrounding height gradually drops to centre Low, it is provided with inspection shaft 4 at lowest part, described inspection shaft 4 is to having sewer 5, and described sewer 5 connects following cistern 11。
Further preferred version, described cistern 11 is provided with conical bottom 12, and described conical bottom 12 is provided with sludge pump The dirt inlet 13 of 14, the upper side wall of described cistern 11 is provided with drain pipe 8, and drain pipe 8 connects neighbouring river.
Further preferred version, described inspection shaft 4 is provided with the grid of comb mouth or reinforcement welding, the lower water below comb mouth Road sidewall is provided with in the cistern of cat ladder connection bottom, in order to convenient construction and maintenance.
Further preferred version, another sidewall of described sewer 5 is provided with the control room 2 of sealing, or will control Room 2 arranges on the ground, is provided with spray pump 3, sludge pump 14 and PLC central controller in described control room 2.
Further preferred version, described spray pump 3 is provided with water inlet pipe and outlet pipe, the water inlet of described water inlet pipe 9 are arranged on the bottom sidewall of cistern 11, and described outlet pipe is embedded in plantation layer, and connects on outlet pipe as required Picking out multiple shower 7, shower 7 upper end is provided with spray head 6;Also can connect drip irrigation pipe on outlet pipe, drip irrigation pipe is circulated It is laid on greenery patches.
Further preferred version, described sludge pump 14 is provided with dirt inlet 13 and sewage draining exit 15, described dirt inlet 13 Being arranged on the bottommost of the conical bottom 12 of described cistern, described sewage draining exit 15 is arranged on the ground of more than plantation layer.
Further preferred version, described plantation layer is provided with hygrosensor 16, can be arranged as required to multiple, institute The hygrosensor 16 stated connects PLC central controller, detects that plantation layer humidity reaches the lower limit set at hygrosensor Time, signal is passed to PLC central controller, PLC central controller starts spray pump 3 and supplies water shower 7, by spray head 6 The flowers and plants being to greenery patches carry out spray pouring, when the moisture in hygrosensor detects plantation layer reaches the upper limit set, Signal passes to PLC central controller, and PLC central controller closes spray pump.
Further preferred version, the bottom sidewall of described cistern 11 is provided with mud search switch 10, described mud Search switch 10 connects PLC central controller, and in mud search switch 10 detects conical bottom 12, precipitating sludge reaches the upper limit Time, signal is passed to PLC central controller, PLC central controller starts sludge pump 14 and is arranged in thick grass earthward by mud.
The present embodiment also discloses the construction method in a kind of greenery patches with underground conservation pool, comprises the steps:
(1) arranging plantation layer 1: according to the shape in greenery patches with need to arrange, the plantation layer in rectangle greenery patches is designed to centre The shape that low both sides are gradually increased, arranges flat ditch at middle lowest part, arranges flat ditch, at the lowest part of flat ditch at middle lowest part Dig the foundation ditch of cistern 11;The plantation layer 1 in strip greenery patches is then designed to the tilted shape that low side, side is high, in lower side While arrange flat ditch, the lowest part at flat ditch digs the foundation ditch of cistern 11;And the greenery patches in plot circular, square, then it is designed to surrounding The shape being gradually lowered between senior middle school, digs the foundation ditch of cistern at middle lowest part.
(2) cistern 11 is built: cistern 11 is embedded in underground, sets the volume of cistern 11 according to the area in greenery patches, Every 3-5 greenery patches sets 1m3Cistern 11 volume, with concrete prefabricated or masonry pile up construction cistern 11, cistern 11 Bottom is arranged to conical bottom 12, and the lowest part in conical bottom 12 arranges the dirt inlet 13 of sludge pump 14, in cistern 11 upper side Wall horizontally set drain pipe 9, cistern top sets up rectangle sewer 5 along sidewall, arranges and climb on the sidewall of sewer 5 Bottom ladder connection cistern 11, sewer 5 above for inspection shaft 4 mouthfuls, described inspection shaft 4 mouthfuls is provided with the net of comb mouth or reinforcement welding Lattice.
(3) control room 2 is set: another sidewall at sewer 5 arranges the control room 2 of sealing or in ground arrangement above Control room 2, arranges spray pump 3, sludge pump 14 and PLC central controller in control room 2;The water inlet of described spray pump 3 13 are arranged on the bottom sidewall of cistern 11, and the outlet pipe of spray pump 3 is embedded in plantation layer 1, and as required in water outlet Connect multiple shower 7 on pipe, spray head 6 is set in shower 7 upper end;Or on outlet pipe, connect drip irrigation pipe, drip irrigation Pipe circulation is laid in the flowers and plants in greenery patches;The water inlet pipe of described sludge pump 14 connects the dirt inlet 13 of columns base, spoil disposal The sewage draining exit 15 of pump is arranged on the ground of more than plantation layer.
(4) arranging detector: the bottom sidewall at cistern 11 arranges mud search switch 10, described mud detection is opened Close 10 connection PLC central controller;Arranging multiple hygrosensor 16 at plantation layer 1, described hygrosensor 16 connects PLC Central controller.
(5) greenery patches plantation and daily management: sow flowers and plants seed or plant into flowers and plants on plantation layer 1, plant resistance to aloft Drought plant, plants waterlogging plant in lower, opens spray pump pouring or utilizes natural rain to water, and rainwater oozes through plantation layer 1 Entering underground, when rainwater is excessive, rainwater can flow in the inspection shaft 4 of the lowest part in greenery patches, and enters the cistern 11 being located in the ground, After cistern 11 is full, rainwater enters river along drain pipe 9;When many days fine days in summer, hygrosensor 16 detects plantation When layer 1 humidity reaches the lower limit set, signal passing to PLC central controller, it is right that PLC central controller starts spray pump 3 Shower 7 supplies water, spray head 6 or drip irrigation pipe flowers and plants sprayed or water, when hygrosensor 16 detects plantation layer When interior moisture reaches the upper limit set, signal passing to PLC central controller, PLC central controller closes spray pump 3; Through long sludge settling, when in mud search switch 10 detects conical bottom 12, precipitating sludge reaches the upper limit, will letter Number passing to PLC central controller, PLC central controller starts sludge pump 14 by mud row thick grass earthward;In greenery patches In flowers and plants growth, it is also possible to add water soluble fertilizer or pesticide as required in cistern 11.
Finally it is noted that the foregoing is only the preferred embodiments of the present invention, it is not limited to the present invention, Although being described in detail the present invention with reference to previous embodiment, for a person skilled in the art, it still may be used So that the technical scheme described in foregoing embodiments to be modified, or wherein portion of techniques feature is carried out equivalent, All within the spirit and principles in the present invention, any modification, equivalent substitution and improvement etc. made, should be included in the present invention's Within protection domain.

Claims (9)

1. with a greenery patches for underground conservation pool, including plantation layer and cistern, it is characterised in that low in the middle of described plantation layer Both sides are gradually increased, and are provided with flat ditch at lowest part, and the lowest part of flat ditch is provided with inspection shaft, or plantation layer surrounding height is gradually to centre Reducing, be provided with inspection shaft at lowest part, described inspection shaft is to having sewer, and described sewer connects cistern.
Greenery patches with underground conservation pool the most according to claim 1, it is characterised in that described cistern is provided with taper The end, described conical bottom is provided with the dirt inlet of sludge pump, and the upper side wall of described cistern is provided with drain pipe.
Greenery patches with underground conservation pool the most according to claim 2, it is characterised in that described inspection shaft is provided with comb mouth, combs Sewer sidewall below mouthful is provided with in the cistern of cat ladder connection bottom.
Greenery patches with underground conservation pool the most according to claim 3, it is characterised in that the opposite side of described sewer Wall sets Packed control room, is provided with spray pump, sludge pump and PLC central controller in described control room.
Greenery patches with underground conservation pool the most according to claim 4, it is characterised in that described spray pump is provided with into water Pipe and outlet pipe, the water inlet of described water inlet pipe is arranged on the bottom sidewall of cistern, and described outlet pipe is embedded in kind Planting in layer, and connect multiple shower as required on outlet pipe, shower upper end is provided with spray head.
Greenery patches with underground conservation pool the most according to claim 4, it is characterised in that described sludge pump is provided with into dirt Mouth and sewage draining exit, described dirt inlet is arranged on the bottommost of the conical bottom of described cistern, and described sewage outfalls setting exists Ground more than plantation layer.
Greenery patches with underground conservation pool the most according to claim 6, it is characterised in that described plantation layer is provided with humidity Detector, described hygrosensor connects PLC central controller, detects that plantation layer humidity reaches to set at hygrosensor Lower limit time, signal is passed to PLC central controller, PLC central controller starts spray pump and supplies water shower, by spraying The flowers and plants that greenery patches is by head carry out spray pouring, and the moisture in hygrosensor detects plantation layer reaches the upper limit set Time, signal is passed to PLC central controller, PLC central controller closes spray pump.
Greenery patches with underground conservation pool the most according to claim 6, it is characterised in that: the bottom sidewall of described cistern Being provided with mud search switch, described mud search switch connects PLC central controller, taper detected at mud search switch When precipitating sludge reaches the upper limit at the end, signal passing to PLC central controller, PLC central controller starts sludge pump by dirt In mud row thick grass earthward.
9., according to the construction method in the greenery patches with underground conservation pool described in claim 1-8, comprise the steps:
1) arranging plantation layer: according to the shape in greenery patches with need to arrange, the plantation layer in rectangle greenery patches is designed to middle low both sides The shape being gradually increased, arranges flat ditch at middle lowest part, and the lowest part at flat ditch digs the foundation ditch of cistern;And circle plot Greenery patches, then be designed between surrounding senior middle school the shape being gradually lowered, and digs the foundation ditch of cistern at middle lowest part;
2) cistern is built: cistern is embedded in underground, sets the volume of cistern, every 3-5 greenery patches according to the area in greenery patches Set 1m3Cistern volume, pile up construction cistern with concrete prefabricated or masonry, columns base is arranged to conical bottom, Lowest part in conical bottom arranges the dirt inlet of sludge pump, on cistern upper portion side wall horizontally set drain pipe, cistern top Set up rectangle sewer, the sidewall of sewer arranges cat ladder connection columns base, sewer above for inspection shaft Mouthful, described catch pit port is provided with the grid of comb mouth or reinforcement welding;
3) control room is set: another sidewall at sewer arranges the control room of sealing or at ground arrangement above control room, Spray pump, sludge pump and PLC central controller are set in control room;The water inlet of described spray pump is arranged on cistern On the sidewall of bottom, the outlet pipe of spray pump is embedded in plantation layer, and connects multiple shower as required on outlet pipe, In shower upper end, spray head is set;The water inlet pipe of described sludge pump connects the dirt inlet of columns base, the row of sludge pump Dirty mouth is arranged on the ground of more than plantation layer;
4) arranging detector: the bottom sidewall at cistern arranges mud search switch, described mud search switch connects PLC Central controller;Arranging hygrosensor at plantation layer, described hygrosensor connects PLC central controller;
5) greenery patches plantation and daily management: sow flowers and plants seed or plant into flowers and plants on plantation layer, plant drought-enduring plant aloft, Planting waterlogging plant in lower, open spray pump pouring or utilize natural rain to water, rainwater permeates the ground through plantation layer, When rainwater is excessive, in the inspection shaft of the lowest part that rainwater can flow into greenery patches, and enter the cistern being located in the ground, after cistern is full, Rainwater enters river along drain pipe;When many days fine days in summer, hygrosensor detects that plantation layer humidity reaches setting During lower limit, signal passing to PLC central controller, PLC central controller starts spray pump and supplies water shower, by spray head Flowers and plants are carried out spray pouring, when the moisture in hygrosensor detects plantation layer reaches the upper limit set, signal is passed Passing PLC central controller, PLC central controller closes spray pump;Through long sludge settling, at mud search switch Detecting when precipitating sludge reaches the upper limit in conical bottom, signal passes to PLC central controller, and PLC central controller starts Mud is arranged in thick grass earthward by sludge pump;In greenery patches flowers and plants grow, in cistern, also add water soluble fertilizer or agriculture Medicine.
CN201610629867.2A 2016-08-04 2016-08-04 Greenery patches and construction method thereof with underground conservation pool Pending CN106088305A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610629867.2A CN106088305A (en) 2016-08-04 2016-08-04 Greenery patches and construction method thereof with underground conservation pool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610629867.2A CN106088305A (en) 2016-08-04 2016-08-04 Greenery patches and construction method thereof with underground conservation pool

Publications (1)

Publication Number Publication Date
CN106088305A true CN106088305A (en) 2016-11-09

Family

ID=57454665

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610629867.2A Pending CN106088305A (en) 2016-08-04 2016-08-04 Greenery patches and construction method thereof with underground conservation pool

Country Status (1)

Country Link
CN (1) CN106088305A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106884471A (en) * 2017-03-08 2017-06-23 浙江双林机械股份有限公司 A kind of sponge urban rainwater is regulated and stored pipe network system and its construction method
CN107347591A (en) * 2017-08-01 2017-11-17 河南城建学院 A kind of urban landscape or ecological garden greening system
CN107447839A (en) * 2017-09-15 2017-12-08 广州普邦园林股份有限公司 A kind of environmental Rain Garden
CN108029522A (en) * 2017-12-22 2018-05-15 福建省春天生态科技股份有限公司 A kind of method for reconstructing in bogginess greenery patches habitat
CN108086438A (en) * 2017-12-15 2018-05-29 芜湖德司节能科技有限公司 A kind of construction method of the new greenery patches structure based on sponge city
CN115492224A (en) * 2022-11-17 2022-12-20 四川坤睿泽智慧科技有限公司 Automatic inspection system and inspection method for pressure drainage

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008245553A (en) * 2007-03-29 2008-10-16 Ihi Corp Greening method for construction site of low-temperature liquid storing tank, and greening apparatus
CN103306359A (en) * 2012-03-15 2013-09-18 北京泰宁科创雨水利用技术股份有限公司 Rainwater regulation and drainage and storage and utilization multifunctional integrated system and construction method thereof
CN104480994A (en) * 2014-11-20 2015-04-01 陈磊 Rainwater collecting and recycling system for urban green land and plaza
CN104521693A (en) * 2014-12-10 2015-04-22 贵州远方园林建设有限公司 Water storage and intelligent irrigation device in garden
CN204443448U (en) * 2015-02-13 2015-07-08 北京颐达兆祥科技有限公司 A kind of urban afforestation collection rain irrigation system
CN205894257U (en) * 2016-08-04 2017-01-18 苏州筑园景观规划设计股份有限公司 Greenery patches with underground cistern

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008245553A (en) * 2007-03-29 2008-10-16 Ihi Corp Greening method for construction site of low-temperature liquid storing tank, and greening apparatus
CN103306359A (en) * 2012-03-15 2013-09-18 北京泰宁科创雨水利用技术股份有限公司 Rainwater regulation and drainage and storage and utilization multifunctional integrated system and construction method thereof
CN104480994A (en) * 2014-11-20 2015-04-01 陈磊 Rainwater collecting and recycling system for urban green land and plaza
CN104521693A (en) * 2014-12-10 2015-04-22 贵州远方园林建设有限公司 Water storage and intelligent irrigation device in garden
CN204443448U (en) * 2015-02-13 2015-07-08 北京颐达兆祥科技有限公司 A kind of urban afforestation collection rain irrigation system
CN205894257U (en) * 2016-08-04 2017-01-18 苏州筑园景观规划设计股份有限公司 Greenery patches with underground cistern

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106884471A (en) * 2017-03-08 2017-06-23 浙江双林机械股份有限公司 A kind of sponge urban rainwater is regulated and stored pipe network system and its construction method
CN106884471B (en) * 2017-03-08 2019-11-26 浙江双林机械股份有限公司 A kind of sponge urban rainwater is regulated and stored pipe network system and its construction method
CN107347591A (en) * 2017-08-01 2017-11-17 河南城建学院 A kind of urban landscape or ecological garden greening system
CN107447839A (en) * 2017-09-15 2017-12-08 广州普邦园林股份有限公司 A kind of environmental Rain Garden
CN108086438A (en) * 2017-12-15 2018-05-29 芜湖德司节能科技有限公司 A kind of construction method of the new greenery patches structure based on sponge city
CN108029522A (en) * 2017-12-22 2018-05-15 福建省春天生态科技股份有限公司 A kind of method for reconstructing in bogginess greenery patches habitat
CN115492224A (en) * 2022-11-17 2022-12-20 四川坤睿泽智慧科技有限公司 Automatic inspection system and inspection method for pressure drainage
CN115492224B (en) * 2022-11-17 2023-03-07 四川坤睿泽智慧科技有限公司 Automatic inspection system and inspection method for pressure drainage

Similar Documents

Publication Publication Date Title
WO2017067426A1 (en) Perforated subirrigation/drainage pipe and sealed fully automatically irrigated rainwater-recycling comprehensive planter
CN106088305A (en) Greenery patches and construction method thereof with underground conservation pool
CN101091448B (en) Irrigation and drainage pipes
CN108571058A (en) A kind of novel town road rainwater diversion device
CN105804198A (en) Greenbelt structure integrating rainwater storage and utilization
Pradhan et al. Smart rainwater management: New technologies and innovation
CN104521693B (en) Water storage and intelligent irrigation device in garden
CN101967812A (en) Dewatering installation of planting roof of horizontal underground garage
CN107447930A (en) Water collection type Green Roof structure
CN109618884A (en) A kind of phreatic water seepage flow catchments hidden pipe structure
CN210395880U (en) Take afforestation roof structure that rainwater was collected
CN101213925B (en) Drought resisting method for man-made forest construction and foster
CN209134931U (en) A kind of water-saving ecological roof greening system
CN104631561B (en) The moisturizing pond, underground of the Afforestation Landscape of automatic liquid level control
CN204676572U (en) A kind of ecological slope protection device of rock side slope
CN208650210U (en) A kind of hillside fields grass planting ditch
CN213268306U (en) Greening roof for sponge city
CN106258557A (en) There is lawn and the construction method thereof collecting rainwater function
CN205894257U (en) Greenery patches with underground cistern
CN206821528U (en) A kind of photovoltaic water-saving irrigation system using highway afflux canal
CN212561003U (en) Greening environment-friendly efficient water control ground system
CN1169422C (en) Sucking irrigation method with mulching under soil
CN108086438A (en) A kind of construction method of the new greenery patches structure based on sponge city
CN209643503U (en) A kind of irrigation system for greenbelt
CN207783869U (en) A kind of self-priming tree root water system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109

RJ01 Rejection of invention patent application after publication