CN105986761A - Double-stand-column, large-torque and long-spiral rock-socketed drilling machine and construction method thereof - Google Patents

Double-stand-column, large-torque and long-spiral rock-socketed drilling machine and construction method thereof Download PDF

Info

Publication number
CN105986761A
CN105986761A CN201510076932.9A CN201510076932A CN105986761A CN 105986761 A CN105986761 A CN 105986761A CN 201510076932 A CN201510076932 A CN 201510076932A CN 105986761 A CN105986761 A CN 105986761A
Authority
CN
China
Prior art keywords
double
rock
long
column
chassis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510076932.9A
Other languages
Chinese (zh)
Inventor
钱圣德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WENZHOU CHANGCHENG FOUNDATION ENGINEERING Co Ltd
Original Assignee
WENZHOU CHANGCHENG FOUNDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WENZHOU CHANGCHENG FOUNDATION ENGINEERING Co Ltd filed Critical WENZHOU CHANGCHENG FOUNDATION ENGINEERING Co Ltd
Priority to CN201510076932.9A priority Critical patent/CN105986761A/en
Publication of CN105986761A publication Critical patent/CN105986761A/en
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

A double-stand-column, large-torque and long-spiral rock-socketed drilling machine is characterized in that a chassis is erected on a walking-type or walking-crawler type traveling device; double stand columns are erected on the chassis and are fixed by double inclined struts; the chassis is further provided with an undercarriage, a control box and two to four winches; a power head is hung on a pulley set on the tops of the double stand columns; the power head is composed of four variable frequency motors of 75-110 kW, a frequency converter, a speed reducer, a driving pinion, a driven gearwheel and a hexagonal connector; the output rotating speed of the power head is 1-60 rpm, and the output torque of the power head is 20-100 tons/m; and the lower portion of the power head is connected with a long-spiral drilling rod, and the lower portion of the drilling rod is connected with a rock-socketed drilling bit. Compared with the prior art, the double-stand-column, large-torque and long-spiral rock-socketed drilling machine has obvious excellent, can output large-tonnage torque, can drive the spiral drilling rod and the hard-alloy drilling bit to move in stratums with hard rock or gravel-cobble layers of 60-120 MPa, can quickly construct high bearing capacity engineering piles, further can lower foundation engineering cost, and avoids mud contamination in construction.

Description

A kind of double embedding rock drilling machine of column high pulling torque long spire and construction method thereof
Technical field
The present invention relates to building machinery field, particularly relate to a kind of double embedding rock drilling machine of column high pulling torque long spire and construction thereof Method.
Background technology
It is known that long-spiral drilling machine is mainly used in northern China and west area, preferably native in soil mechanical properties Complete in Ceng to creep into-concrete perfusion-rear inserts steel reinforcement cage pile, has that speed of application is fast, mud-less pollution and engineering are made The advantages such as valency is relatively low.But, existing long-spiral drilling machine all uses single or double driven by motor, power of motor 45-75kw, turns round Square 3.5-8 ton rice.So, long-spiral drilling machine can only creep into soil layer or the compression strength value soft rock less than 20MPa.
At the building of China coast soft clay area, when upper soil horizon mechanical property is poor, designer can be by work Journey stake stake end embeds 1-3 times of stake footpath of the hard rock that compression strength value is 60-120MPa, to improve the bearing capacity of stake and antiskid Move.Embedding the hard rock more than 60MPa, cannot being constructed by existing long-spiral drilling machine, this type of pile foundation existing can only use Cost is high, have a percussive drill of mud contamination, or construction cost is higher, the down-hole hammer drilling machine construction that more consumes energy.
Content of the invention
The present invention provides a kind of double embedding rock drilling machine of column high pulling torque long spire, and its unit head can export large-tonnage moment of torsion, soon Speed, low cost complete a footpath 0.6-2 rice, the bored concrete pile piercing block stone gravel layer or hard rock of stake long 20-100 rice Construction.The compression strength value of hard rock described herein is 60-120MPa, mud-less pollution in construction.China's soft clay area stake End supporting course buried depth is in the majority with 50-80m, and the double pillar construction of employing can be after the drilling rod construction on earth of a column, separately Continuing construction on the drilling rod connecting of one column, it is to avoid single stand column pile machine extension bar, workman must up to pile frame top anchor tip.
The technical solution used in the present invention is: a kind of double embedding rock drilling machines of column high pulling torque long spire, it is characterised in that On walking or stride-cterpillar drive, setting up chassis, chassis being established double column, double column diclinics support Adjustable fixing, chassis is additionally provided with undercarriage, control cabinet and 2-4 platform hoist engine;Double column tops top sheave group hangs power Head, unit head is by 4 75-110 kilowatt of variable-frequency motors, frequency converter, reductor, driver pinion, driven gear wheel With hexagonal jointing composition;Power head device output speed is 1-60 rev/min, and output moment of torsion is 20-100 ton rice; Connect long screw drill rod under unit head, under drilling rod, connect embedding rock drill bit.Stride-cterpillar drive described herein is to protect Staying the long stride of walking, being replaced short stride by crawler unit, the action of purer walking is rapider.Compared with crawler belt Formula device, because contact area increases, pile frame construction is safer stable.
The construction method of the embedding rock drilling machine of a kind of pair of column high pulling torque long spire, comprises the following steps:
1. each for rig of the present invention parts are transported to job site to assemble;
2. by running gear mobile drill to stake position;
3. starting frequency converter and 2 motors, frequency converter leaves to 50HZ, and the rotating speed of motor is 960 revs/min, passes through Reductor, the little moment of torsion height rotating speed of unit head output, drive long screw drill rod and drill bit, creep in soil layer;
4., when drill bit gravel layer to be entered, gradually turn down frequency converter to 40-30HZ, the rotating speed of motor from 50HZ Also being gradually reduced, through reductor, unit head output moment of torsion increases, and drives long screw drill rod and drill bit, to boulder and cobble Layer creeps into;
5., when entering the hard rock of 60-120MPa, increase and start another 2 motors, then turn down frequency converter HZ, make rotating speed Being down to 2-4 rev/min, unit head output moment of torsion reaches 60-100 ton rice, it is ensured that drill bit creeps into hard rock until projected depth;
6. high slump concrete is pumped, from pump truck through conveying pipe, then through drilling rod center cavity, finally, from drill bit valve Door injects stake holes, bores the high slump concrete irrigating in stake holes to ground with carrying;
7. after auger stem and carbide drill lift-off stake holes, stake machine moves next position and goes round and begins again, and continues the 3. To 6. step construction;
8. hang steel reinforcement cage and be inserted into setting absolute altitude from the vibration of concrete center vibration hammer, i.e. complete this engineering long spire embedding Rock filling pile is constructed.
A kind of double embedding rock drilling machine of column high pulling torque long spire compared with prior art, has obvious superiority, can export big The moment of torsion of tonnage, drives auger stem and carbide drill on the stratum of 60-120MPa ragstone or gravel layer In, high-bearing capacity engineering pile of comparatively fast constructing out, also reduces mud-less pollution in foundation engineering cost and construction.
Brief description
Fig. 1 is embodiment of the present invention generalized section, and a. side elevational cross-section schematic diagram, b. faces generalized section.
Drawing illustrates: 1 top pulleys group, 2 columns, 3 unit head lifting wire ropes, 4 open frame steel wire rope, and 5 is oblique Support, 6 undercarriages, 7 hoist engines, 8 switch boards, 9 chassis, 10 long stride oil cylinders, 11 long strides, 12 short stride oil Cylinder, 13 short strides, 14 assembly pulleys, 15 embedding rock drill bits, 16 locators, 17 auger stems, 18 unit heads.
Detailed description of the invention
The invention will be further described below in conjunction with the accompanying drawings: the structure of the embedding rock drilling machine of a kind of pair of column high pulling torque long spire Composition and construction procedure are very clearly for those skilled in the art, comprise the following steps:
1. each for rig of the present invention parts are transported to job site to assemble, at field boundary on the ground, be first well placed the long stride of two pieces (11) Short stride (13) with two pieces, installation chassis (9) on it, install on chassis (9) double column (2), undercarriage (6), Diagonal brace (5), hoist engine (7), switch board (8), and column (2) is erected, by top pulleys group (1) With assembly pulley (14) and hoist engine (7), unit head (18), long screw drill rod (17) and drill bit (15) are hung over column (2) On;
2. walked by long stride (11) and short stride (13), on mobile drill to stake position;
3. starting frequency converter and 2 motors, frequency converter leaves to 50HZ, and the rotating speed of motor is 960 revs/min, through over subtraction Speed machine, unit head (18) exports little moment of torsion height rotating speed, drives long screw drill rod (17) and drill bit (15), creeps into soil layer;
4. when drill bit (15) gravel layer to be entered, gradually turning down frequency converter from 50HZ, the rotating speed of motor is also gradually Reducing, through reductor, unit head output moment of torsion increases, and drives long screw drill rod and drill bit, creeps into gravel layer;
5., when entering the hard rock of 60-120MPa, increase and start another 2 motors and turn down frequency converter, make rotating speed be down to 2-4 rev/min, the output of unit head moment of torsion reaches 60-100 ton rice, it is ensured that drill bit creeps into hard rock until projected depth;
6. pump high slump concrete and enter stake holes from drilling rod center cavity and by drill bit valve, bore to stake holes with carrying Irrigate high slump concrete to ground;
7. after auger stem and carbide drill lift-off stake holes, stake machine moves next position and goes round and begins again, and continues the 3. To 6. step construction;
8. hang steel reinforcement cage and be inserted into setting absolute altitude from the vibration of concrete center vibration hammer, i.e. complete this engineering long spire embedding Rock filling pile is constructed.

Claims (2)

1. double embedding rock drilling machine of column high pulling torque long spire, it is characterised in that on walking or stride-cterpillar drive, set up chassis, establishing double column on chassis, it is fixing that the support of double column diclinics is adjustable, and chassis is additionally provided with undercarriage, control cabinet and 2-4 platform hoist engine;Double column tops top sheave group hangs unit head, and unit head is made up of 4 75-110 kilowatt of variable-frequency motors, frequency converter, reductor, driver pinion, driven gear wheel and hexagonal jointing;Power head device output speed is 1-60 rev/min, and output moment of torsion is 20-100 ton rice;Connect long screw drill rod under unit head, under drilling rod, connect embedding rock drill bit.
2. a construction method for double embedding rock drilling machines of column high pulling torque long spire, comprises the following steps:
1. each for rig of the present invention parts are transported to job site to assemble;
2. by running gear mobile drill to stake position;
3. starting frequency converter and 2 motors, frequency converter leaves to 50HZ, and the rotating speed of motor is 960 revs/min, through reductor, the little moment of torsion height rotating speed of unit head output, drives long screw drill rod and drill bit, creeps in soil layer;
4. when drill bit gravel layer to be entered, gradually turning down frequency converter from 50HZ to 40-30HZ, the rotating speed of motor is also gradually reduced, and through reductor, unit head output moment of torsion increases, and drives long screw drill rod and drill bit, creeps into gravel layer;
5. when entering the hard rock of 60-120MPa, increasing and starting another 2 motors, then turn down frequency converter HZ, make rotating speed be down to 2-4 rev/min, unit head output moment of torsion reaches 60-100 ton rice, it is ensured that drill bit creeps into hard rock until projected depth;
6. pump high slump concrete, from pump truck through conveying pipe, then through drilling rod center cavity, finally, inject stake holes from drill bit valve, bore the high slump concrete irrigating in stake holes to ground with carrying;
7. after auger stem and carbide drill lift-off stake holes, stake machine moves next position and goes round and begins again, and continues the 3. to 6. step construction;
8. hang steel reinforcement cage and be inserted into setting absolute altitude from the vibration of concrete center vibration hammer, i.e. complete the construction of this engineering long spire piles set into rock.
CN201510076932.9A 2015-01-31 2015-01-31 Double-stand-column, large-torque and long-spiral rock-socketed drilling machine and construction method thereof Pending CN105986761A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510076932.9A CN105986761A (en) 2015-01-31 2015-01-31 Double-stand-column, large-torque and long-spiral rock-socketed drilling machine and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510076932.9A CN105986761A (en) 2015-01-31 2015-01-31 Double-stand-column, large-torque and long-spiral rock-socketed drilling machine and construction method thereof

Publications (1)

Publication Number Publication Date
CN105986761A true CN105986761A (en) 2016-10-05

Family

ID=57042274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510076932.9A Pending CN105986761A (en) 2015-01-31 2015-01-31 Double-stand-column, large-torque and long-spiral rock-socketed drilling machine and construction method thereof

Country Status (1)

Country Link
CN (1) CN105986761A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201050308Y (en) * 2007-06-13 2008-04-23 马宝安 Frame for driller for coal mine tunnel
CN202000342U (en) * 2011-02-18 2011-10-05 史政 High air pressure pneumatic impact rock penetrating and inserting device for continuous flight auger
CN102322056A (en) * 2011-07-04 2012-01-18 湖南德邦重工机械有限公司 Super-large-torque spiral hole-boring and pile-pouring machine
EP2495388A1 (en) * 2011-03-02 2012-09-05 CASAGRANDE SpA Drilling head for drilling machines
CN202882776U (en) * 2012-10-17 2013-04-17 镇江煤安矿用设备有限责任公司 Frame column type drilling machine support for mining
CN204511293U (en) * 2015-01-31 2015-07-29 温州长城基础工程有限公司 A kind of two embedding rock drilling machine of column high pulling torque long spire

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201050308Y (en) * 2007-06-13 2008-04-23 马宝安 Frame for driller for coal mine tunnel
CN202000342U (en) * 2011-02-18 2011-10-05 史政 High air pressure pneumatic impact rock penetrating and inserting device for continuous flight auger
EP2495388A1 (en) * 2011-03-02 2012-09-05 CASAGRANDE SpA Drilling head for drilling machines
CN102322056A (en) * 2011-07-04 2012-01-18 湖南德邦重工机械有限公司 Super-large-torque spiral hole-boring and pile-pouring machine
CN202882776U (en) * 2012-10-17 2013-04-17 镇江煤安矿用设备有限责任公司 Frame column type drilling machine support for mining
CN204511293U (en) * 2015-01-31 2015-07-29 温州长城基础工程有限公司 A kind of two embedding rock drilling machine of column high pulling torque long spire

Similar Documents

Publication Publication Date Title
CN102852457B (en) Follow-up drilling machine for down-hole hammer casing pipe
CN110374500B (en) Grouped drilling and pile planting construction method
CN205840770U (en) A kind of impact type rotary drilling rig device being applicable to heavy caliber construction
CN110331936B (en) Combined drilling bottom-expanding pile-planting construction method
CN210530738U (en) Pile system is planted in drilling in groups
CN104989272A (en) Upward inverse well drilling process
CN102182180B (en) Rotary extrusion sleeve anchor rod and construction method thereof
CN105780776B (en) A kind of spinning steel-pipe pile construction equipment
CN102628336A (en) Batter pile construction drilling machine and construction method
CN107620574A (en) A kind of full circle swinging all casing drill main body and full circle swinging all casing drill
CN101914915A (en) Construction method for anti-floating anchor rod and special long auger
CN102373705A (en) Pile sinking device and method for outer digging pre-stressed centrifugal pipe pile and square pile
CN105113982A (en) Resonance-free and full-bush long spiral drilling machine and construction method
CN103195357A (en) Full-casing type special drilling machine
CN108468334B (en) Gravel stratum dry-excavation clay dado pore-forming bored concrete pile construction device
CN202039369U (en) Multifunctional pilling machine for jet grouting pile sinking
CN202788610U (en) Down-hole hammer sleeve follow-up drilling machine
CN204511293U (en) A kind of two embedding rock drilling machine of column high pulling torque long spire
CN209339143U (en) A kind of concrete pipe pile construction equipment
CN105840092A (en) Rotary drilling machine double-column structure
CN105986761A (en) Double-stand-column, large-torque and long-spiral rock-socketed drilling machine and construction method thereof
CN202990848U (en) Drilling-rod-free geological drilling device
CN201288500Y (en) Rotary drilling hydraulic power head with vibrator
CN109339044A (en) A kind of concrete pipe pile construction equipment
CN205934924U (en) A pile sinking device that in being used for, bores vibration major diameter PHC tubular pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161005

WD01 Invention patent application deemed withdrawn after publication