CN105973082B - The bore distribution method of reinforced concrete brace demolition blasting in a kind of foundation ditch - Google Patents
The bore distribution method of reinforced concrete brace demolition blasting in a kind of foundation ditch Download PDFInfo
- Publication number
- CN105973082B CN105973082B CN201610392625.6A CN201610392625A CN105973082B CN 105973082 B CN105973082 B CN 105973082B CN 201610392625 A CN201610392625 A CN 201610392625A CN 105973082 B CN105973082 B CN 105973082B
- Authority
- CN
- China
- Prior art keywords
- reinforced concrete
- pipe
- mrow
- arc
- curved pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F42—AMMUNITION; BLASTING
- F42D—BLASTING
- F42D1/00—Blasting methods or apparatus, e.g. loading or tamping
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F42—AMMUNITION; BLASTING
- F42D—BLASTING
- F42D3/00—Particular applications of blasting techniques
- F42D3/02—Particular applications of blasting techniques for demolition of tall structures, e.g. chimney stacks
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明涉及一种基坑内钢筋混凝土支撑梁爆破拆除的布孔方法。其技术方案是:在所述基坑内钢筋混凝土支撑梁(3)内沿纵向方向预埋有弧形管组(1),弧形管组(1)中的弧形管为1根或3根,每根弧形管的两端管口向上,两端管口间的直线距离L=1800~2300mm,弧形管组(1)中的每根弧形管的同端管口的中心连线垂直于钢筋混凝土支撑梁(3)的长边。在弧形管组(1)间的中间位置处还预埋2根直管(2),每根直管(2)垂直于钢筋混凝土支撑梁(3)的上平面,每根直管(2)上端管口与两侧邻近的弧形管上端管口的距离相等。本发明具有施工方便、工期短、成本低、能提高爆破拆除的安全可靠性和能增强爆破拆除效果的特点。
The invention relates to a hole layout method for blasting demolition of a reinforced concrete support beam in a foundation pit. The technical solution is: an arc-shaped tube group (1) is pre-embedded in the reinforced concrete support beam (3) in the foundation pit along the longitudinal direction, and the arc-shaped tubes in the arc-shaped tube group (1) are 1 or 3 , the nozzles at both ends of each arc-shaped tube are upward, the straight-line distance between the two ends of the nozzles L=1800~2300mm, the center line of the same-end nozzles of each arc-shaped tube in the arc-shaped tube group (1) perpendicular to the long side of the reinforced concrete support beam (3). Two straight pipes (2) are pre-buried in the middle of the arc pipe groups (1), each straight pipe (2) is perpendicular to the upper plane of the reinforced concrete support beam (3), each straight pipe (2 ) The distance between the upper end nozzle and the upper end nozzle of the adjacent arc tubes on both sides is equal. The invention has the characteristics of convenient construction, short construction period, low cost, can improve the safety and reliability of blasting demolition, and can enhance the effect of blasting demolition.
Description
技术领域technical field
本发明属于钢筋混凝土支撑梁爆破拆除的布孔技术领域。尤其涉及一种基坑内钢筋混凝土支撑梁爆破拆除的布孔方法。The invention belongs to the technical field of hole layout for blasting demolition of reinforced concrete support beams. In particular, it relates to a hole layout method for blasting demolition of reinforced concrete support beams in foundation pits.
背景技术Background technique
随着建筑施工技术的发展,各种大型深基坑随之增多,基坑内钢筋混凝土支撑梁拆除量逐渐增大。目前所使用的拆除方法主要有:爆破拆除法、机械拆除法和人工凿除法。相比于后两种拆除方法,爆破拆除法具有拆除工期短、出渣快、可回收废旧钢筋和节约资源的特点,因此目前在钢筋混凝土支撑梁拆除时应用最为广泛。With the development of construction technology, various large deep foundation pits have increased, and the amount of reinforced concrete support beams in the foundation pits has gradually increased. The currently used demolition methods mainly include: blasting demolition method, mechanical demolition method and manual chisel removal method. Compared with the latter two demolition methods, the blasting demolition method has the characteristics of short demolition period, fast slag discharge, recyclable waste steel bars and resource saving, so it is currently the most widely used in the demolition of reinforced concrete support beams.
爆破拆除法通常是在浇注钢筋混凝土支撑梁过程中预制垂直向炮孔,待拆除时将炸药埋到钢筋混凝土支撑梁的预制垂直向炮孔中,通过爆破破碎的方法进行拆除。这种沿钢筋混凝土支撑梁纵向方向依次垂直向布置炮孔的方法增加了预制炮孔数目和布孔的工作量,通常使得施工工期延长,爆破拆除成本偏高;且由于钢筋混凝土支撑梁截面尺寸因素使得炮孔深度受到限制,往往造成单孔炸药量偏小或炮孔堵塞长度不足,导致钢筋混凝土支撑梁爆破破碎不够充分或冲炮事件发生,增加机械二次破碎和拆除成本。The blasting demolition method is usually to prefabricate vertical blastholes in the process of pouring reinforced concrete support beams. When demolishing, explosives are buried in the prefabricated vertical blastholes of reinforced concrete support beams, and the demolition is carried out by blasting and fragmentation. This method of vertically arranging the blastholes along the longitudinal direction of the reinforced concrete support beam increases the number of prefabricated blastholes and the workload of hole layout, which usually prolongs the construction period and increases the cost of demolition by blasting; and due to the size factor of the reinforced concrete support beam section The depth of the blast hole is limited, often resulting in a small amount of single-hole explosive or insufficient plugging length of the blast hole, resulting in insufficient blasting and fragmentation of the reinforced concrete support beam or the occurrence of blasting incidents, increasing the cost of mechanical secondary crushing and demolition.
发明内容Contents of the invention
本发明旨在克服现有技术缺陷。目的在于提供一种施工方便、工期短、成本低、能提高爆破拆除的安全可靠性和能增强爆破拆除效果的基坑内钢筋混凝土支撑梁爆破拆除的布孔方法。The present invention aims to overcome the disadvantages of the prior art. The purpose is to provide a hole layout method for blasting demolition of reinforced concrete support beams in foundation pits which is convenient in construction, short in construction period, low in cost, can improve the safety and reliability of blasting demolition, and can enhance the effect of blasting demolition.
为实现上述任务,本发明采用的技术方案是:基坑内钢筋混凝土支撑梁浇筑前,在所述基坑内钢筋混凝土支撑梁内沿纵向方向预埋有弧形管组,弧形管组中的每根弧形管所构成的平面均平行于所述钢筋混凝土支撑梁侧面,每根弧形管的两端管口向上,两端管口间的直线距离L=1800~2300mm;弧形管组中的每根弧形管的同端管口的中心连线横线垂直于钢筋混凝土支撑梁的长边。In order to achieve the above tasks, the technical solution adopted by the present invention is: before the reinforced concrete support beam in the foundation pit is poured, an arc-shaped tube group is pre-embedded in the reinforced concrete support beam in the foundation pit along the longitudinal direction, and each arc-shaped tube group The planes formed by the arc-shaped tubes are all parallel to the side of the reinforced concrete support beam, the nozzles at both ends of each arc-shaped pipe are upward, and the straight-line distance between the two ends of the nozzles is L=1800~2300mm; The horizontal line connecting the centers of the nozzles at the same end of each arc-shaped pipe is perpendicular to the long side of the reinforced concrete support beam.
弧形管组间的距离r=0.38H~0.42H。The distance between the arc tube groups r=0.38H~0.42H.
弧形管组间的中间位置处预埋有2根直管,每根直管垂直于钢筋混凝土支撑梁的上平面,每根直管上端管口与两侧邻近的弧形管上端管口的距离相等,每根直管的上端管口与弧形管组的两端管口平齐,均高出钢筋混凝土支撑梁上平面40~60mm。Two straight pipes are pre-embedded in the middle of the arc-shaped pipe groups, each straight pipe is perpendicular to the upper plane of the reinforced concrete support beam, and the upper end of each straight pipe is connected to the upper end of the adjacent arc-shaped pipes on both sides. The distance is equal, the upper end of each straight pipe is flush with the two ends of the arc pipe group, and they are all 40-60mm higher than the upper plane of the reinforced concrete support beam.
所述弧形管组的预埋数是:a)当钢筋混凝土支撑梁的宽度R小于700mm时,弧形管在钢筋混凝土支撑梁内为单根布置;b)当钢筋混凝土支撑梁的宽度R大于或等于700mm时,弧形管在钢筋混凝土支撑梁内为3根布置,中间弧形管两侧的弧形管管口间距a=0.35R~0.4R。The pre-embedded number of the arc tube group is: a) when the width R of the reinforced concrete support beam is less than 700mm, the arc tube is arranged as a single piece in the reinforced concrete support beam; b) when the width R of the reinforced concrete support beam When it is greater than or equal to 700mm, the arc tubes are arranged in three in the reinforced concrete support beam, and the distance between the arc tubes on both sides of the middle arc tube is a=0.35R~0.4R.
所述弧形管组为3根布置时的中间弧形管的曲率半径ρ1 The radius of curvature ρ1 of the middle arc tube when the arc tube group is arranged in three
所述弧形管组为3根布置时的两侧弧形管或为单根布置时的弧形管的曲率半径ρ2 The radius of curvature ρ2 of the arc tubes on both sides when the arc tube group is three arranged or a single arc tube
式(ⅰ)和式(ⅱ)中:L表示弧形管两端管口间的直线距离,mm;In formula (i) and formula (ii): L represents the linear distance between the two ends of the arc tube, mm;
H表示钢筋混凝土支撑梁的高度,mm。H represents the height of the reinforced concrete support beam, mm.
所述弧形管组中的弧形管材质为PVC,每根弧形管的孔径为40~50mm。The arc tubes in the arc tube group are made of PVC, and the diameter of each arc tube is 40-50mm.
所述直管的下端口与钢筋混凝土支撑梁下表面的距离为2H/9~3H/9;所述直管的材质为PVC,直管的孔径为40~50mm。The distance between the lower port of the straight pipe and the lower surface of the reinforced concrete support beam is 2H/9-3H/9; the material of the straight pipe is PVC, and the diameter of the straight pipe is 40-50mm.
由于采用上述技术方案,本发明与现有技术相比具有如下积极效果:Owing to adopting above-mentioned technical scheme, the present invention has following positive effect compared with prior art:
本发明在钢筋混凝土支撑梁3浇筑前,沿钢筋混凝土支撑梁3纵向方向预埋有不同曲率半径的弧形管组1,在相邻弧形管组1的弧形管间设有垂直于钢筋混凝土支撑梁3上平面的横向直管2,所述弧形管组1和直管2即为预制炮孔。这种预埋弧形管组1和直管2的协同布置形式使得各预制炮孔内炸药爆炸后的能量相互耦合,使所述钢筋混凝土支撑梁3内的爆炸荷载分布更加均匀,能有效避免钢筋混凝土支撑梁3的实体过度粉碎或破碎不充分等状况发生。且沿支撑梁纵向方向埋设不同曲率半径的弧形管能大幅减少垂直向炮孔埋设数量,降低施工成本,缩短施工工期和能增强爆破拆除效果等特点。In the present invention, before the reinforced concrete support beam 3 is poured, arc-shaped tube groups 1 with different curvature radii are pre-buried along the longitudinal direction of the reinforced concrete support beam 3, and arc-shaped tubes 1 perpendicular to the steel bars are arranged between adjacent arc-shaped tube groups 1. The horizontal straight pipe 2 on the plane of the concrete support beam 3, the arc pipe group 1 and the straight pipe 2 are prefabricated blastholes. The coordinated arrangement of the pre-buried arc tube group 1 and the straight tube 2 makes the energy after the explosion of the explosives in each prefabricated blasthole coupled to each other, makes the explosion load distribution in the reinforced concrete support beam 3 more uniform, and can effectively avoid The entity of the reinforced concrete support beam 3 is excessively crushed or insufficiently crushed, and the like occurs. Moreover, embedding arc-shaped pipes with different curvature radii along the longitudinal direction of the support beam can greatly reduce the number of embedding vertical blastholes, reduce construction costs, shorten the construction period, and enhance the effect of blasting demolition.
本发明能够大幅降低钢筋混凝土支撑梁3爆破拆除的炮孔预埋数目及预制炮孔的材料成本;能有效避免冲炮事件发生概率,减小对周边环境的安全威胁;使得钢筋混凝土支撑梁3爆破破碎充分,能有效缩短爆破拆除施工工期,提高经济效益。本发明不仅适用于基坑内钢筋混凝土支撑梁的爆破拆除,还可广泛应用于框架结构楼房、厂房和高架桥等爆破拆除工程。The invention can greatly reduce the number of pre-embedded blastholes and the material cost of the prefabricated blastholes for demolition of the reinforced concrete support beam 3; can effectively avoid the occurrence probability of blasting incidents, and reduce the safety threat to the surrounding environment; make the reinforced concrete support beam 3 The blasting is fully broken, which can effectively shorten the construction period of blasting demolition and improve economic benefits. The invention is not only applicable to the blasting demolition of reinforced concrete support beams in foundation pits, but also can be widely used in blasting demolition projects such as frame structure buildings, factory buildings and viaducts.
因此,本发明具有施工方便、工期短、成本低、能提高爆破拆除的安全可靠性和能增强爆破拆除效果的特点。Therefore, the present invention has the characteristics of convenient construction, short construction period, low cost, improved safety and reliability of blasting demolition, and enhanced effect of blasting demolition.
附图说明Description of drawings
图1为本发明的一种布孔方法的俯视图;Fig. 1 is the top view of a kind of method for laying holes of the present invention;
图2为图1的A-A阶梯剖的剖面示意图。FIG. 2 is a schematic cross-sectional view of the A-A step section in FIG. 1 .
具体实施方式detailed description
下面结合附图和具体实施方式对本发明做进一步描述,并非对其保护范围的限制。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments, which is not intended to limit its protection scope.
实施例1Example 1
一种基坑内钢筋混凝土支撑梁爆破拆除的布孔方法。本实施例所述基坑内钢筋混凝土支撑梁的横断面的尺寸是:宽度R为800mm;高度H为600mm。The invention discloses a hole layout method for the blasting demolition of reinforced concrete support beams in foundation pits. The size of the cross-section of the reinforced concrete support beam in the foundation pit described in this embodiment is: the width R is 800 mm; the height H is 600 mm.
本实施例所述布孔方法如图1和图2所示:基坑内钢筋混凝土支撑梁3浇筑前,在所述基坑内钢筋混凝土支撑梁3内沿纵向方向预埋有弧形管组1,弧形管组1中的每根弧形管所构成的平面平行于所述钢筋混凝土支撑梁3侧面,每根弧形管的两端管口向上,两端管口间的直线距离L=2000mm;弧形管组1中的每根弧形管的同端管口中心连线垂直于钢筋混凝土支撑梁3的长边。The hole layout method described in this embodiment is shown in Figure 1 and Figure 2: before the reinforced concrete support beam 3 in the foundation pit is poured, an arc-shaped pipe group 1 is pre-embedded in the reinforced concrete support beam 3 in the foundation pit along the longitudinal direction, The plane formed by each arc tube in the arc tube group 1 is parallel to the side of the reinforced concrete support beam 3, the nozzles at both ends of each arc tube are upward, and the straight-line distance between the two ends L=2000mm ; The line connecting the centers of the nozzles at the same end of each arc tube in the arc tube group 1 is perpendicular to the long side of the reinforced concrete support beam 3 .
如图1所示:弧形管组1间的距离r=0.38H~0.42HAs shown in Figure 1: the distance between arc tube groups 1 r=0.38H~0.42H
=(0.38~0.42)×600mm=(0.38~0.42)×600mm
=228~252mm。=228~252mm.
如图1和图2所示:弧形管组1间的中间位置处预埋有2根直管,每根直管2垂直于钢筋混凝土支撑梁3的上平面,每根直管2上端管口与两侧邻近的弧形管上端管口的距离相等,每根直管2的上端管口与弧形管组1的两端管口平齐,均高出钢筋混凝土支撑梁3上平面40mm。As shown in Figure 1 and Figure 2: 2 straight pipes are pre-buried in the middle of the arc pipe group 1, each straight pipe 2 is perpendicular to the upper plane of the reinforced concrete support beam 3, and each straight pipe 2 upper end pipe The distance between the mouth and the upper end of the adjacent arc tubes on both sides is equal, the upper end of each straight pipe 2 is flush with the two ends of the arc tube group 1, and they are all 40mm higher than the upper plane of the reinforced concrete support beam 3 .
如图1所示,所述弧形管组1的预埋数是:由于钢筋混凝土支撑梁3的宽度R=800mm大于700mm,故弧形管在钢筋混凝土支撑梁3为3根布置。As shown in FIG. 1 , the pre-embedded number of the arc tube group 1 is: since the width R=800mm of the reinforced concrete support beam 3 is greater than 700mm, three arc tubes are arranged on the reinforced concrete support beam 3 .
如图1和图2所示,所述弧形管组1为3根布置时的两侧弧形管管口间的距离aAs shown in Figures 1 and 2, the distance a between the nozzles of the curved tubes on both sides when the arc tube group 1 is arranged in three
a=(0.35~0.4)×Ra=(0.35~0.4)×R
=(0.35~0.4)×800=(0.35~0.4)×800
=280~320mm。=280~320mm.
如图1和图2所示,所述弧形管组1为3根布置时的中间弧形管的曲率半径ρ1 As shown in Fig. 1 and Fig. 2, the radius of curvature ρ 1 of the middle arc tube when the said arc tube group 1 is three arranged
如图1和图2所示,所述弧形管组1为3根布置时的两侧弧形管的曲率半径ρ2 As shown in Figures 1 and 2, the radius of curvature p2 of the arc tubes on both sides when the arc tube group 1 is three arranged
式(ⅰ)和式(ⅱ)中:L表示弧形管两端管口间的直线距离,mm;In formula (i) and formula (ii): L represents the linear distance between the two ends of the arc tube, mm;
H表示钢筋混凝土支撑梁3的高度,mm。H represents the height of the reinforced concrete support beam 3, mm.
将L=2000mm和H=600mm分别代入式(ⅰ)和式(ⅱ),则Substitute L=2000mm and H=600mm into formula (i) and formula (ii) respectively, then
ρ1=2203mm;ρ 1 =2203mm;
ρ2=1450mm。ρ 2 =1450 mm.
所述弧形管组1中的弧形管材质为PVC,每根弧形管的孔径为40mm。The material of the arc tubes in the arc tube group 1 is PVC, and the aperture of each arc tube is 40mm.
所述直管2的下端口与钢筋混凝土支撑梁3下表面的距离为2H/9~3H/9=600(2/9~3/9)=133~200mm;所述直管2的材质为PVC,直管2的孔径为40mm。The distance between the lower port of the straight pipe 2 and the lower surface of the reinforced concrete support beam 3 is 2H/9~3H/9=600(2/9~3/9)=133~200mm; the material of the straight pipe 2 is PVC, the hole diameter of the straight pipe 2 is 40mm.
实施例2Example 2
一种基坑内钢筋混凝土支撑梁爆破拆除的布孔方法。本实施例所述基坑内钢筋混凝土支撑梁的横断面的尺寸是:宽度R为1000mm;高度H为800mm。The invention discloses a hole layout method for the blasting demolition of reinforced concrete support beams in foundation pits. The size of the cross-section of the reinforced concrete support beam in the foundation pit described in this embodiment is: the width R is 1000mm; the height H is 800mm.
本实施例所述布孔方法如图1和图2所示:基坑内钢筋混凝土支撑梁3浇筑前,在所述基坑内钢筋混凝土支撑梁3内沿纵向方向预埋有弧形管组1,弧形管组1中的每根弧形管所构成的平面平行于所述钢筋混凝土支撑梁3侧面,每根弧形管的两端管口向上,两端管口间的直线距离L=2300mm;弧形管组1中的每根弧形管的同端管口中心连线垂直于钢筋混凝土支撑梁3的长边。The hole layout method described in this embodiment is shown in Figure 1 and Figure 2: before the reinforced concrete support beam 3 in the foundation pit is poured, an arc-shaped pipe group 1 is pre-embedded in the reinforced concrete support beam 3 in the foundation pit along the longitudinal direction, The plane formed by each arc tube in the arc tube group 1 is parallel to the side of the reinforced concrete support beam 3, the nozzles at both ends of each arc tube are upward, and the straight-line distance between the two ends L=2300mm ; The line connecting the centers of the nozzles at the same end of each arc tube in the arc tube group 1 is perpendicular to the long side of the reinforced concrete support beam 3 .
位于所述钢筋混凝土支撑梁3上平面与对应的横断面的相交线处。It is located at the intersection line between the upper plane of the reinforced concrete support beam 3 and the corresponding cross section.
如图1所示,弧形管组1间的距离r=(0.38~0.42)HAs shown in Figure 1, the distance r=(0.38~0.42)H between arc tube groups 1
=(0.38~0.42)×800mm=(0.38~0.42)×800mm
=304~336mm。=304~336mm.
如图1和图2所示:弧形管组1间的中间位置处预埋有2根直管,每根直管2垂直于钢筋混凝土支撑梁3的上平面,每根直管2上端管口与两侧邻近的弧形管上端管口的距离相等,每根直管2的上端管口与弧形管组1的两端管口平齐,均高出钢筋混凝土支撑梁3上平面50mm。As shown in Figure 1 and Figure 2: 2 straight pipes are pre-buried in the middle of the arc pipe group 1, each straight pipe 2 is perpendicular to the upper plane of the reinforced concrete support beam 3, and each straight pipe 2 upper end pipe The distance between the mouth and the upper end of the adjacent arc tubes on both sides is equal, the upper end of each straight pipe 2 is flush with the two ends of the arc tube group 1, and they are all 50mm higher than the upper plane of the reinforced concrete support beam 3 .
如图1所示,所述弧形管组1的预埋数是:由于钢筋混凝土支撑梁3的宽度R=1000mm大于700mm,故弧形管在钢筋混凝土支撑梁3内为3根布置。As shown in Fig. 1, the pre-embedded number of the arc tube group 1 is: since the width R=1000mm of the reinforced concrete support beam 3 is greater than 700mm, three arc tubes are arranged in the reinforced concrete support beam 3.
如图1和图2所示,所述弧形管组1为3根布置的两侧弧形管管口间的距离aAs shown in Figures 1 and 2, the arc tube group 1 is the distance a between the nozzles of three arc tubes arranged on both sides
a=0.35R~0.4Ra=0.35R~0.4R
=(0.35~0.4)×1000=(0.35~0.4)×1000
=350~400mm。=350~400mm.
如图1和图2所示,所述弧形管组1为3根布置中的中间弧形管的曲率半径ρ1 As shown in Figures 1 and 2, the arc tube group 1 is the radius of curvature ρ1 of the middle arc tubes in the arrangement of three
如图1和图2所示,所述弧形管组1为3根布置中的两侧弧形管的曲率半径ρ2 As shown in Figures 1 and 2, the arc tube group 1 is the curvature radius ρ2 of the arc tubes on both sides in the arrangement of three
式(ⅰ)和式(ⅱ)中:L表示弧形管两端管口间的直线距离,mm;In formula (i) and formula (ii): L represents the linear distance between the two ends of the arc tube, mm;
H表示钢筋混凝土支撑梁3的高度,mm。H represents the height of the reinforced concrete support beam 3, mm.
将L=2300mm和H=800mm分别代入式(ⅰ)和式(ⅱ),则Substitute L=2300mm and H=800mm into formula (i) and formula (ii) respectively, then
ρ1=2226mm;ρ 1 =2226mm;
ρ2=1506mm。ρ 2 =1506mm.
所述弧形管组1中的弧形管材质为PVC,每根弧形管的孔径为50mm。The arc tubes in the arc tube group 1 are made of PVC, and the aperture of each arc tube is 50 mm.
所述直管2的下端口与钢筋混凝土支撑梁3下表面的距离为2H/9~3H/9=800(2/9~3/9)=178~267;所述直管2的材质为PVC,直管2的孔径为50mm。The distance between the lower port of the straight pipe 2 and the lower surface of the reinforced concrete support beam 3 is 2H/9~3H/9=800(2/9~3/9)=178~267; the material of the straight pipe 2 is PVC, the hole diameter of the straight pipe 2 is 50mm.
实施例3Example 3
一种基坑内钢筋混凝土支撑梁爆破拆除的布孔方法。本实施例所述基坑内钢筋混凝土支撑梁的横断面的尺寸是:宽度R为600mm;高度H为400mm。The invention discloses a hole layout method for the blasting demolition of reinforced concrete support beams in foundation pits. The size of the cross-section of the reinforced concrete support beam in the foundation pit described in this embodiment is: the width R is 600mm; the height H is 400mm.
本实施例所述布孔方法是:在基坑内钢筋混凝土支撑梁3浇筑前,在所述基坑内钢筋混凝土支撑梁3内沿纵向方向预埋有弧形管组1,弧形管组1中的每根弧形管所构成的平面平行于所述钢筋混凝土支撑梁3侧面,每根弧形管的两端管口向上,两端管口间的直线距离L=1800mm;弧形管组1中的每根弧形管的同端管口中心连线垂直于钢筋混凝土支撑梁3的长边。The hole layout method described in this embodiment is: before the reinforced concrete support beam 3 in the foundation pit is poured, an arc-shaped tube group 1 is pre-embedded in the reinforced concrete support beam 3 in the foundation pit along the longitudinal direction, and the arc-shaped tube group 1 The plane formed by each arc-shaped tube is parallel to the side of the reinforced concrete support beam 3, the two ends of each arc-shaped tube are upward, and the straight-line distance between the two ends of the tube is L=1800mm; the arc-shaped tube group 1 The line connecting the centers of the nozzles at the same end of each arc-shaped pipe is perpendicular to the long side of the reinforced concrete support beam 3.
如图1所示,弧形管组1间的距离r=0.38H~0.42HAs shown in Figure 1, the distance between arc tube groups 1 r=0.38H~0.42H
=(0.38~0.42)×400mm=(0.38~0.42)×400mm
=152~168mm。=152~168mm.
如图1所示:弧形管组1间的中间位置处预埋有2根直管,每根直管2垂直于钢筋混凝土支撑梁3的上平面,每根直管2上端管口与两侧邻近的弧形管上端管口的距离相等,每根直管2的上端管口与弧形管组1的两端管口平齐,均高出钢筋混凝土支撑梁3上平面60mm。As shown in Figure 1: two straight pipes are pre-buried in the middle of the arc pipe group 1, each straight pipe 2 is perpendicular to the upper plane of the reinforced concrete support beam 3, and the upper end of each straight pipe 2 is connected to the two The distances between the upper end nozzles of the adjacent arc tubes are equal, and the upper end nozzles of each straight pipe 2 are flush with the two ends of the arc tube group 1, and are all higher than the reinforced concrete support beam 3 upper plane 60mm.
所述弧形管组1的预埋数是:由于当钢筋混凝土支撑梁3的宽度R=600小于700mm,则弧形管在钢筋混凝土支撑梁3内为单根布置。The pre-embedded number of the arc tube group 1 is: when the width R=600 of the reinforced concrete support beam 3 is less than 700 mm, the arc tubes are arranged as a single piece in the reinforced concrete support beam 3 .
所述单根布置的弧形管的曲率半径ρThe radius of curvature ρ of the single arranged arc tube
式(ⅰ)中:L表示弧形管两端管口间的直线距离,mm;In formula (ⅰ): L represents the linear distance between the two ends of the arc tube, mm;
H表示钢筋混凝土支撑梁3的高度,mm。H represents the height of the reinforced concrete support beam 3, mm.
将L=1800mm和H=400mm代入式(ⅰ),则Substitute L=1800mm and H=400mm into formula (i), then
ρ=1652mm。ρ=1652mm.
所述单根弧形管材质为PVC,每根弧形管的孔径为40mm。The material of the single arc tube is PVC, and the aperture of each arc tube is 40mm.
所述直管2的下端口距离钢筋混凝土支撑梁3下表面的距离为2H/9~3H/9=400(2/9~3/9)=130;所述直管2的材质为PVC,直管2的孔径为40mm。The distance between the lower port of the straight pipe 2 and the lower surface of the reinforced concrete support beam 3 is 2H/9~3H/9=400(2/9~3/9)=130; the material of the straight pipe 2 is PVC, The diameter of the straight pipe 2 is 40mm.
本具体实施方式与现有技术相比具有如下积极效果:Compared with the prior art, this specific embodiment has the following positive effects:
本具体实施方式在钢筋混凝土支撑梁3浇筑前,沿钢筋混凝土支撑梁3纵向方向预埋有不同曲率半径的弧形管组1,在相邻弧形管组1的弧形管间设有垂直于钢筋混凝土支撑梁3上平面的横向直管2,所述弧形管组1和直管2即为预制炮孔。这种预埋弧形管组1和直管2的协同布置形式使得各预制炮孔内炸药爆炸后的能量相互耦合,使所述钢筋混凝土支撑梁3内的爆炸荷载分布更加均匀,能有效避免钢筋混凝土支撑梁3的实体过度粉碎或破碎不充分等状况发生。且沿支撑梁纵向方向埋设不同曲率半径的弧形管能大幅减少垂直向炮孔埋设数量,降低施工成本,缩短施工工期和能增强爆破拆除效果等特点。In this specific embodiment, before the reinforced concrete support beam 3 is poured, arc-shaped tube groups 1 with different curvature radii are pre-buried along the longitudinal direction of the reinforced concrete support beam 3, and vertical The horizontal straight pipe 2 on the plane of the reinforced concrete support beam 3, the arc pipe group 1 and the straight pipe 2 are prefabricated blastholes. The coordinated arrangement of the pre-buried arc tube group 1 and the straight tube 2 makes the energy after the explosion of the explosives in each prefabricated blasthole coupled to each other, makes the explosion load distribution in the reinforced concrete support beam 3 more uniform, and can effectively avoid The entity of the reinforced concrete support beam 3 is excessively crushed or insufficiently crushed, and the like occurs. Moreover, embedding arc-shaped pipes with different curvature radii along the longitudinal direction of the support beam can greatly reduce the number of embedding vertical blastholes, reduce construction costs, shorten the construction period, and enhance the effect of blasting demolition.
本具体实施方式能够大幅降低钢筋混凝土支撑梁3爆破拆除的炮孔预埋数目及预制炮孔的材料成本;能有效避免冲炮事件发生概率,减小对周边环境的安全威胁;使得钢筋混凝土支撑梁3爆破破碎充分,能有效缩短爆破拆除施工工期,提高经济效益。本具体实施方式不仅适用于基坑内钢筋混凝土支撑梁的爆破拆除,还可广泛应用于框架结构楼房、厂房和高架桥等爆破拆除工程。This specific embodiment can significantly reduce the number of pre-embedded blastholes and the material cost of prefabricated blastholes for demolition of the reinforced concrete support beam 3; it can effectively avoid the probability of blasting incidents, and reduce the security threat to the surrounding environment; make the reinforced concrete support Beam 3 is sufficiently broken by blasting, which can effectively shorten the construction period of blasting demolition and improve economic benefits. This specific embodiment is not only applicable to the blasting demolition of reinforced concrete support beams in foundation pits, but also can be widely used in blasting demolition projects such as frame structure buildings, factory buildings and viaducts.
因此,本具体实施方式具有施工方便、工期短、成本低、能提高爆破拆除的安全可靠性和能增强爆破拆除效果的特点。Therefore, this specific embodiment has the characteristics of convenient construction, short construction period, low cost, and can improve the safety and reliability of blasting demolition and can enhance the effect of blasting demolition.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610392625.6A CN105973082B (en) | 2016-06-03 | 2016-06-03 | The bore distribution method of reinforced concrete brace demolition blasting in a kind of foundation ditch |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610392625.6A CN105973082B (en) | 2016-06-03 | 2016-06-03 | The bore distribution method of reinforced concrete brace demolition blasting in a kind of foundation ditch |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105973082A CN105973082A (en) | 2016-09-28 |
CN105973082B true CN105973082B (en) | 2017-10-03 |
Family
ID=57010283
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610392625.6A Expired - Fee Related CN105973082B (en) | 2016-06-03 | 2016-06-03 | The bore distribution method of reinforced concrete brace demolition blasting in a kind of foundation ditch |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105973082B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106759526B (en) * | 2016-12-16 | 2018-10-26 | 武汉科技大学 | A kind of purlin before Brace in Deep Footing Groove beam demolition blasting protects preprocess method |
CN106592602B (en) * | 2016-12-16 | 2018-07-03 | 武汉科技大学 | For the pre-groove to be blasted for removing deep foundation pit reinforced concrete supporting beam |
CN106592604B (en) * | 2017-01-04 | 2018-06-19 | 武汉科技大学 | Fender post reserves the determining method of protective layer optimum thickness in deep basal pit blast working |
CN110067581B (en) * | 2019-05-13 | 2020-10-02 | 湖北工业大学 | Arrangement and construction method of pre-buried holes in reinforced concrete supporting layers at tunnel or roadway forks or openings |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2461251C3 (en) * | 1974-12-23 | 1982-10-07 | Bochumer Eisenhütte Heintzmann GmbH & Co, 4630 Bochum | Device for pre-assembly, transport and installation of a route or tunnel extension |
CN104404965A (en) * | 2014-11-05 | 2015-03-11 | 浙江海洋学院 | Method for removing reinforced concrete support beams in foundation pit support |
CN104669449B (en) * | 2015-02-17 | 2016-09-14 | 上海建工集团股份有限公司 | A kind of drilling equipment and the cutting method of reinforced concrete brace |
CN105369814B (en) * | 2015-10-14 | 2017-05-31 | 河海大学 | A kind of prefabricated prestressing concrete support and its erection method |
CN105569377A (en) * | 2016-02-29 | 2016-05-11 | 上海建工五建集团有限公司 | Method for demounting reinforced concrete supporting beam |
-
2016
- 2016-06-03 CN CN201610392625.6A patent/CN105973082B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN105973082A (en) | 2016-09-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
LU102302B1 (en) | Steel reinforcement cage for use in ventilation shaft diaphragm wall, and usage method | |
CN105973082B (en) | The bore distribution method of reinforced concrete brace demolition blasting in a kind of foundation ditch | |
CN105823386B (en) | The blasting demolishing method of reinforced concrete brace in a kind of foundation ditch | |
CN113654423B (en) | Green demolition method of mechanical cutting and off-site blasting of embedded holes in reinforced concrete beams and columns | |
CN103967210A (en) | Square steel pipe waste concrete core spiral hoop stiffening composite column with T-shaped ribbed stiffeners | |
CN104061004A (en) | Steel bar construction for secondary lining of tunnel | |
CN102535849B (en) | Constructional column top concreting method | |
CN102926504A (en) | Connecting steel construction member for steel and concrete overlapped beam combined part and construction method thereof | |
CN104358356A (en) | High-enhanced regenerative mixed steel-tubular concrete-filled anti-shock column with built-in local restraint and construction technology thereof | |
CN208816125U (en) | Shield inspection-pit maintenance backfill support construction | |
CN111561318A (en) | Artificial false roof construction method capable of realizing pre-supporting effect | |
CN111441802A (en) | Temporary inverted arch dismantling replacement structure and process in tunnel constructed by CRD method | |
CN205662931U (en) | A reinforced concrete supporting beam in foundation ditch in multi -curvature switching -over coupling cloth hole | |
CN205532716U (en) | Block structure of ore bin bottom | |
CN106049503B (en) | The preprocess method of reinforced concrete brace demolition blasting in a kind of foundation ditch | |
CN113356223A (en) | Asynchronous decoupling construction method for large foundation pit coupling inner support system | |
CN104908150B (en) | A kind of piping shaft making template and the method based on factorial praluction piping shaft | |
CN106759526B (en) | A kind of purlin before Brace in Deep Footing Groove beam demolition blasting protects preprocess method | |
CN110894748A (en) | Connecting structure of security door and main wall and installation method of security door | |
CN106381956A (en) | Concrete prefabricated shell-regenerated mixed concrete combination column and preparation method thereof | |
CN202810867U (en) | Secondary tunnel lining structure formed by combining profiled steel sheets with concrete | |
CN213574129U (en) | Roadway repair vault empty field treatment device | |
CN205477640U (en) | Safety support device to collecting space area roof cutting release | |
CN211500660U (en) | Urban comprehensive pipe gallery and underground shallow buried underground excavation tunnel combined supporting system | |
CN212105897U (en) | Replacement structure is demolishd to interim invert in CRD method construction tunnel hole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171003 |