CN105952162B - A kind of round-the-clock truss assembling method - Google Patents
A kind of round-the-clock truss assembling method Download PDFInfo
- Publication number
- CN105952162B CN105952162B CN201610295295.9A CN201610295295A CN105952162B CN 105952162 B CN105952162 B CN 105952162B CN 201610295295 A CN201610295295 A CN 201610295295A CN 105952162 B CN105952162 B CN 105952162B
- Authority
- CN
- China
- Prior art keywords
- moulding bed
- truss
- tarpaulin
- vertical rod
- clock
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 13
- 238000000465 moulding Methods 0.000 claims abstract description 69
- 238000003466 welding Methods 0.000 claims abstract description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 11
- 239000010959 steel Substances 0.000 claims description 11
- 239000004744 fabric Substances 0.000 claims 1
- 230000001681 protective effect Effects 0.000 claims 1
- 238000007596 consolidation process Methods 0.000 abstract description 6
- 238000010276 construction Methods 0.000 description 2
- 210000001015 abdomen Anatomy 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/162—Handles to carry construction blocks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a kind of round-the-clock truss assembling method, it is characterised in that the 1st step, using truck crane assembly moulding bed;2nd step, using truck crane chord member of truss is lifted on moulding bed;3rd step, drawing, which are set up defences, protects tarpaulin;4th step, using truck crane truss web is deposited in the range of the driving lifting of moulding bed side, then using the assembled truss web of driving a vehicle;5th step, complete truss welding;6th step, protection tarpaulin is removed, hung out truss using truck crane, assembled next truss structure.The present invention is easy to operate, and on-site consolidation can be avoided to be influenceed by boisterous, while can reduce the use of assembled machinery.
Description
Technical field:
The present invention relates to construction steel structure technical field, specifically a kind of round-the-clock truss assembling method.
Background technology:
Because its processing and fabricating is completed in workshop, quality is easily controlled steel construction, but due to truss often size
It is larger, can not be in the assembled integral rear delivery of factory, scene is there is still a need for carry out largely assembly work.In general is assembled at present
Method is:Assembled moulding bed is set up, on-site consolidation is carried out using truck crane, and is outdoor progress mostly, even if there is provided go along with sb. to guard him to arrange
Apply, otherwise it is very simple and crude, it is difficult to bad weather is dealt with, otherwise cost is high, it is difficult to popularization and application.
The content of the invention:
The first aspect of the present invention purpose is to provide a kind of easy to operate, can avoid on-site consolidation by boisterous
Influence, while the truss assembling method that assembled machinery uses can be reduced.
To achieve these goals, the present invention is achieved through the following technical solutions:
A kind of round-the-clock truss assembling method, it is characterised in that comprise the following steps:
1st step, using truck crane assembly moulding bed;
2nd step, using truck crane chord member of truss is lifted on moulding bed;
3rd step, drawing, which are set up defences, protects tarpaulin;
4th step, using truck crane by truss web be deposited in moulding bed side driving lifting in the range of, then using driving
Assembled truss web;
5th step, complete truss welding;
6th step, protection tarpaulin is removed, hung out truss using truck crane, assembled next truss structure.
Further it is provided in:
The assembled moulding bed of step 1, jig structure are as follows:Including moulding bed cross bar, two moulding bed vertical rods are arranged at tire in opposition
On frame cross bar, the side of moulding bed vertical rod is provided with moulding bed support bar, moulding bed bracket is provided with the inside of moulding bed vertical rod, drives a vehicle
Beam is arranged at the upper end of moulding bed vertical rod, and driving is installed on crane beam, and can be moved back and forth along crane beam, in the upper of moulding bed vertical rod
Side is provided with tarpaulin hanger, and tarpaulin is loaded on tarpaulin hanger.
The moulding bed support bar is arranged at the outside of moulding bed vertical rod.
The moulding bed cross bar, moulding bed vertical rod, moulding bed bracket are made using H steel, and moulding bed support bar is made using angle steel, OK
Bicycle beam is made using H steel, and tarpaulin hanger is made using scaffold tubes.
The driving is driven a vehicle for planer-type small-sized movable.
The drawing of step 3, which is set up defences, protects tarpaulin, and tarpaulin is opened or closed according to live weather condition.
Compared with prior art, following advantages be present in the present invention:
1st, substantial amounts of truss web is assembled is carried out using driving, without using other loop wheel machines, saves machinery cost;
2nd, assembled using driving, trussmember from upper air installing without being put into moulding bed so that assembled moulding bed top can be sealed
Close, realize round-the-clock consolidation service, progress can be accelerated, avoid personnel's work holdup;
3rd, by protecting the setting of tarpaulin, rain-proof, sun-proof, improvement operating environment, assembled, welding, painting can effectively be carried out
Packing quality can greatly improve.
Below in conjunction with Figure of description and specific embodiment, the present invention will be described in detail.
Brief description of the drawings:
Fig. 1 is the structural representation of assembled moulding bed of the present invention;
Fig. 2 is the assembled operating diagram of truss of the present invention.
Embodiment:
As Figure 1-Figure 2, a kind of round-the-clock truss assembly moulding bed, including:Moulding bed cross bar 1, moulding bed vertical rod 2, moulding bed branch
Strut 3, moulding bed bracket 4, crane beam 5, driving 6, tarpaulin hanger 7, tarpaulin 8 form, wherein:Two moulding bed vertical rods 2 are set in opposition
It is placed on moulding bed cross bar 1, the side of moulding bed vertical rod 2 is provided with moulding bed support bar 3, fixation is supported to moulding bed vertical rod 2, it is excellent
Choosing, the moulding bed support bar 3 is arranged at the outside of moulding bed vertical rod 2, the inner side of moulding bed vertical rod 2 is provided with moulding bed bracket 4, OK
Bicycle beam 5 is arranged at the upper end of moulding bed vertical rod 2, and driving 6 is installed on crane beam 5, and can be moved back and forth along crane beam 5.
Tarpaulin hanger 7 is also equipped with the top of moulding bed vertical rod 2, tarpaulin 8 is set on tarpaulin hanger 7, can be effective
Sun-proof, rain-proof etc. is carried out, the influence for avoiding bad weather from bringing, is effectively improved operating environment.
The moulding bed cross bar 1, moulding bed vertical rod 2, moulding bed bracket 4 are made using H steel, and moulding bed support bar 3 uses angle steel system
Make, crane beam 5 is made using H steel, and tarpaulin hanger 7 is made using scaffold tubes, and crane beam 5 is used as moulding bed simultaneously with tarpaulin hanger 7
The plane outer support of vertical rod, effectively improve the stability of structure.
Fig. 1 shows a kind of embodiment of the assembled English truss of the present invention.
It is a kind of using above-mentioned assembled moulding bed come the method for assembled truss, comprise the following steps:
1st step, using truck crane assembly moulding bed;
2nd step, using truck crane chord member of truss is lifted on moulding bed;
3rd step, drawing, which are set up defences, protects tarpaulin;
4th step, truss web is deposited in the range of the driving lifting of moulding bed side, then using assembled truss abdomen of driving a vehicle
Bar;
5th step, complete truss welding, paint;
6th step, protection tarpaulin is removed, hung out truss using truck crane, assembled next truss structure.
The present invention can adjust consolidation service mode and progress according to weather condition:, can not if weather condition is good
Draw and tarpaulin is set, consolidation service is carried out together with driving using truck crane, accelerates assembled speed;
During work, bundled truss web is transported within the range of operation of driving using truck crane, then using driving
Assembled truss web;
Fig. 1 shows a kind of embodiment of the assembled English truss of the present invention, but the invention is not limited in assembled triangle purlin
Frame, it is only necessary to be adjusted to the position of moulding bed bracket, be equally applicable to the spelling of the various truss such as plane girder, space truss
Dress.
Claims (5)
1. a kind of round-the-clock truss assembling method, it is characterised in that comprise the following steps:
1st step, using truck crane assembly moulding bed;The jig structure is as follows:Including moulding bed cross bar, two moulding bed vertical rods are in opposition
It is arranged on moulding bed cross bar, the side of moulding bed vertical rod is provided with moulding bed support bar, moulding bed is provided with the inside of moulding bed vertical rod
Bracket, crane beam are arranged at the upper end of moulding bed vertical rod, and driving is installed on crane beam, and is moved back and forth along crane beam, in moulding bed
Tarpaulin hanger is installed, tarpaulin is loaded on tarpaulin hanger above vertical rod;
2nd step, using truck crane chord member of truss is lifted on moulding bed;
3rd step, drawing, which are set up defences, protects tarpaulin;
4th step, using truck crane truss web is deposited in the range of the driving lifting of moulding bed side, it is then assembled using driving
Truss web;
5th step, complete truss welding;
6th step, protection tarpaulin is removed, hung out truss using truck crane, assembled next truss structure.
A kind of 2. round-the-clock truss assembling method according to claim 1, it is characterised in that:The drawing of step 3 sets protective awning
Cloth, tarpaulin is opened or closed according to live weather condition.
A kind of 3. round-the-clock truss assembling method according to claim 1, it is characterised in that:The moulding bed support bar is set
In the outside of moulding bed vertical rod.
A kind of 4. round-the-clock truss assembling method according to claim 1, it is characterised in that:The moulding bed cross bar, moulding bed
Vertical rod, moulding bed bracket are made using H steel, and moulding bed support bar is made using angle steel, and crane beam is made using H steel, tarpaulin hanger
Made using scaffold tubes.
A kind of 5. round-the-clock truss assembling method according to claim 1, it is characterised in that:The driving is small for planer-type
Type movement driving.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610295295.9A CN105952162B (en) | 2016-05-06 | 2016-05-06 | A kind of round-the-clock truss assembling method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610295295.9A CN105952162B (en) | 2016-05-06 | 2016-05-06 | A kind of round-the-clock truss assembling method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105952162A CN105952162A (en) | 2016-09-21 |
CN105952162B true CN105952162B (en) | 2018-02-06 |
Family
ID=56914185
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610295295.9A Active CN105952162B (en) | 2016-05-06 | 2016-05-06 | A kind of round-the-clock truss assembling method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105952162B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113202280A (en) * | 2021-04-21 | 2021-08-03 | 中交第四公路工程局有限公司 | Conversion bracket type steel structure for steel structure high-altitude construction and construction method thereof |
CN114412196B (en) * | 2022-02-25 | 2023-05-09 | 中建八局新型建造工程有限公司 | High-altitude safety assembling jig frame device of pipe truss and construction method thereof |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06330635A (en) * | 1993-05-25 | 1994-11-29 | Marufuji Shiitopairu Kk | Unloading device for temporarily pitch tent |
CN101725255A (en) * | 2009-11-13 | 2010-06-09 | 高申甫 | Segmental slipping and assembling process of overhead large-span steel structure |
CN202925957U (en) * | 2012-12-17 | 2013-05-08 | 南通市达欣工程股份有限公司 | Instrumentalized extension-type safety protection shed |
CN103821372A (en) * | 2014-02-26 | 2014-05-28 | 中天建设集团有限公司 | Method for installing trusses with different heights |
CN103899093A (en) * | 2014-04-28 | 2014-07-02 | 江苏南通六建建设集团有限公司 | Step-by-step hoisting construction method of mega-frame steel truss beam |
CN205152802U (en) * | 2015-11-22 | 2016-04-13 | 中铁十八局集团有限公司 | Improve structure of arched bridge strength nature skeleton building -site preparation precision |
-
2016
- 2016-05-06 CN CN201610295295.9A patent/CN105952162B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06330635A (en) * | 1993-05-25 | 1994-11-29 | Marufuji Shiitopairu Kk | Unloading device for temporarily pitch tent |
CN101725255A (en) * | 2009-11-13 | 2010-06-09 | 高申甫 | Segmental slipping and assembling process of overhead large-span steel structure |
CN202925957U (en) * | 2012-12-17 | 2013-05-08 | 南通市达欣工程股份有限公司 | Instrumentalized extension-type safety protection shed |
CN103821372A (en) * | 2014-02-26 | 2014-05-28 | 中天建设集团有限公司 | Method for installing trusses with different heights |
CN103899093A (en) * | 2014-04-28 | 2014-07-02 | 江苏南通六建建设集团有限公司 | Step-by-step hoisting construction method of mega-frame steel truss beam |
CN205152802U (en) * | 2015-11-22 | 2016-04-13 | 中铁十八局集团有限公司 | Improve structure of arched bridge strength nature skeleton building -site preparation precision |
Also Published As
Publication number | Publication date |
---|---|
CN105952162A (en) | 2016-09-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104773671A (en) | Foldable radar antenna lifting mechanism based on space link multi-oil-cylinder coordinated drive | |
CN202358849U (en) | Small-size suspension crane | |
CN105952162B (en) | A kind of round-the-clock truss assembling method | |
CN105926959A (en) | All-weather truss splicing bed-jig | |
CN204571478U (en) | Stockyard, building site dust guard | |
CN105298139A (en) | Modular mounting method of large space division cooling box steel structure | |
CN105986664A (en) | Hanging basket and roof reverse hanging plate operation platform with same | |
CN105986684A (en) | Mobile type multifunctional component machining workshop | |
CN207343138U (en) | A kind of telescopic paint spray booth | |
CN206752318U (en) | A kind of bridge coping template fast dismounting device | |
CN202719016U (en) | Haff hinge capable of adjusting trolley level angle and lateral displacement | |
CN214885399U (en) | Adjustable operation construction equipment of steel column | |
CN206029069U (en) | Suspension type welding jobs canopy | |
CN206279555U (en) | Purlin vehicle type closure construction system | |
CN205779497U (en) | Wind power blade tip lightening operation bracket | |
CN209259164U (en) | A kind of inverted arch trestle convenient for whole Transporting | |
CN102701064A (en) | Hanging basket for aluminum profiles | |
CN211888358U (en) | Movable rack | |
CN107829061A (en) | Full-automatic smallclothes galvanization production line turning manipulator | |
CN208584091U (en) | A kind of Welding steel truss abat-vent | |
CN206705328U (en) | Time saving and energy saving safety dress film machine | |
CN203319589U (en) | Hoisting machine for installing air hose | |
CN206927501U (en) | The gantry crane of standby suspender is installed | |
CN206987042U (en) | A kind of green building steel structure frame | |
CN206395222U (en) | A kind of tank case armrest system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||