[go: up one dir, main page]

CN105863286A - Wide-post double-beam structure and building body structure underpinning modification method - Google Patents

Wide-post double-beam structure and building body structure underpinning modification method Download PDF

Info

Publication number
CN105863286A
CN105863286A CN201610180462.5A CN201610180462A CN105863286A CN 105863286 A CN105863286 A CN 105863286A CN 201610180462 A CN201610180462 A CN 201610180462A CN 105863286 A CN105863286 A CN 105863286A
Authority
CN
China
Prior art keywords
underpinning
wall
wide
original
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610180462.5A
Other languages
Chinese (zh)
Inventor
曹大富
张颖
包季军
王琨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangzhou University
Original Assignee
Yangzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangzhou University filed Critical Yangzhou University
Priority to CN201610180462.5A priority Critical patent/CN105863286A/en
Publication of CN105863286A publication Critical patent/CN105863286A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开一种宽柱双梁结构及砌体结构托换改造方法。宽柱双梁结构包括宽柱(1)、托换梁(2),每根托换梁(2)两端分别搭接在宽柱(1)上,还包括一端浇筑在托换梁(2)内,另一端浇筑在楼板(4)内的多个传剪器(3);砌体结构托换改造方法包括:(10)在原构造柱基础上,四周围加宽,形成宽柱(1);(20)在原有墙体两侧各设置一托换梁(2);(30)在托换梁(2)上方的楼板开浇筑孔,将传剪器一端浇筑在托换梁(2)内,另一端浇筑在楼板(4)内;(40)在难以拆除墙体内设置连接筋(4),一端浇筑在托换梁(2)内,另一端与浇筑在未拆除墙体(5)内。本发明的宽柱双梁结构及托换改造方法,在砌体结构改造时无需先拆除原有墙体。

The invention discloses an underpinning transformation method for a wide-column double-beam structure and a masonry structure. The wide-column double-beam structure includes a wide column (1) and an underpinning beam (2). ), the other end is poured into multiple shearers (3) in the floor slab (4); the masonry structure underpinning transformation method includes: (10) on the basis of the original structural column, the surroundings are widened to form a wide column (1 ); (20) an underpinning beam (2) is respectively arranged on both sides of the original body of wall; (30) a pouring hole is opened on the floor above the underpinning beam (2), and one end of the shearer is poured on the underpinning beam (2) ), the other end is poured in the floor (4); (40) the connecting rib (4) is set in the difficult-to-remove wall, one end is poured in the underpinning beam (2), and the other end is poured in the undemolished wall ( 5) inside. The wide-column double-beam structure and the underpinning transformation method of the present invention do not need to dismantle the original wall body during the transformation of the masonry structure.

Description

宽柱双梁结构及砌体结构托换改造方法Underpinning Reconstruction Method of Wide Column Double Beam Structure and Masonry Structure

技术领域technical field

本发明属于砌体结构改造技术领域,特别是一种宽柱双梁结构及砌体结构托换改造方法。The invention belongs to the technical field of transformation of masonry structures, in particular to a method for underpinning and transformation of a wide-column double-beam structure and a masonry structure.

背景技术Background technique

随着城乡建设不断发展,大部分砌体结构的房屋受限于幵间小、进深小,不能满足人们日益增长的对建筑物的使用要求。近年来,旧城改造是我国各地政府普遍关注的热点问题。鉴于对旧建筑的保护,规划部门往往要求“修旧如旧”,即原有的建筑风貌不容改变,但内部的使用功能要随着经济发展的需要加以改变(如宾馆变商场),这就要求结构工程师对原有的结构进行合理的托换和加固改造。With the continuous development of urban and rural construction, most masonry structures are limited by small bays and small depths, which cannot meet people's growing requirements for buildings. In recent years, the reconstruction of old cities has been a hot issue that governments in various parts of our country have generally paid attention to. In view of the protection of old buildings, the planning department often requires "repairing the old as the old", that is, the original architectural style cannot be changed, but the internal use function must be changed according to the needs of economic development (such as changing a hotel into a shopping mall), which is Structural engineers are required to carry out reasonable underpinning and reinforcement reformation on the original structure.

对于托换技术,在《建(构)筑物托换技术规程》(CECS 295:2011)等一些技术规范规程中都对其提出了有关的设计规定及构造要求。但是在改造过程中,往往需先拆除墙体,然后浇筑混凝土托换体系,从而对原结构造成了一定的损伤。或者原砌体墙体不易拆除。For the underpinning technology, relevant design regulations and structural requirements are put forward in some technical regulations such as the "Technical Regulations for Underpinning of Buildings (Structures)" (CECS 295:2011). However, in the process of renovation, it is often necessary to demolish the wall first, and then pour the concrete underpinning system, thus causing certain damage to the original structure. Or the original masonry wall is not easy to remove.

总之,现有技术存在的问题是:砌体结构改造时需先拆除原有墙体,导致原结构受到损伤,或原墙体不易拆除,改造工作无法进行。In a word, the problems existing in the prior art are: the original wall body needs to be removed first when the masonry structure is reconstructed, resulting in damage to the original structure, or the original wall body is difficult to remove, and the reconstruction work cannot be carried out.

发明内容Contents of the invention

本发明的目的在于提供一种宽柱双梁结构,可使砌体结构改造时无需先拆除原有墙体,既不会损伤原有结构,也不受阻于不易拆除的墙体。The purpose of the present invention is to provide a wide-column double-beam structure, which can make the masonry structure remodel without demolishing the original wall first, neither damage the original structure nor be hindered by the difficult-to-remove wall.

本发明的另一目的在于提供一种砌体结构托换改造方法,不受原有墙体影响,对原有结构无损伤。Another object of the present invention is to provide a method for underpinning a masonry structure, which is not affected by the original wall and does not damage the original structure.

实现本发明目的的技术解决方案为:The technical solution that realizes the object of the present invention is:

一种宽柱双梁结构,包括由原有构造柱经四周加宽而成的宽柱、分别位于墙体两侧的托换梁,所述每根托换梁两端分别搭接在宽柱上,还包括多个传剪器,所述传剪器一端浇筑在托换梁内,另一端浇筑在楼板内。A wide-column double-beam structure, including wide columns formed by widening the original structural columns and underpinning beams respectively located on both sides of the wall, and the two ends of each underpinning beam are respectively lapped on the wide columns It also includes a plurality of shear transmission devices, one end of which is poured in the underpinning beam, and the other end is poured in the floor slab.

实现本发明另一目的的技术解决方案为:The technical solution that realizes another object of the present invention is:

一种砌体结构托换改造方法,包括如下步骤:A method for underpinning a masonry structure, comprising the steps of:

(10)将原有构造柱四周围浇筑钢筋混凝土,形成相对于普通柱宽度较大的宽柱(1);(10) Pour reinforced concrete around the original structural column to form a wider column (1) with a larger width than the ordinary column;

(20)在原有墙体两侧各设置一托换梁,使托换梁两端分别搭接在宽柱上;(20) Set an underpinning beam on both sides of the original wall, so that the two ends of the underpinning beam are respectively lapped on the wide column;

(30)在托换梁上方的楼板上开设混凝土浇筑孔,并将传剪器一端浇筑在托换梁内,另一端浇筑在楼板内;(30) Open a concrete pouring hole on the floor above the underpinning beam, pour one end of the shearer into the underpinning beam, and pour the other end into the floor;

(40)拆除原有墙体,如有难以拆除部分,则设置连接筋,使其一端浇筑在托换梁内,另一端与浇筑在未拆除墙体内。(40) Remove the original wall. If there is a part that is difficult to remove, set the connecting rib so that one end is poured in the underpinning beam, and the other end is poured in the unremoved wall.

本发明与现有技术相比,其显著优点为为:Compared with the prior art, the present invention has the remarkable advantages of:

可使砌体结构改造时无需先拆除原有墙体,既不会损伤原有结构,也不受阻于不易拆除的墙体。若保持原有安全等级,基础底板及楼面板,一般不需置换和加固,与拆除重建同样的结构相比,可节省工程造价40-50%。因此该结构体系在旧城改造中的推广运用,可产生良好的经济效益。The masonry structure can be reconstructed without demolishing the original wall first, and the original structure will not be damaged, nor will it be hindered by the difficult-to-remove wall. If the original safety level is maintained, the base plate and floor plate generally do not need to be replaced or reinforced. Compared with demolishing and rebuilding the same structure, the project cost can be saved by 40-50%. Therefore, the popularization and application of this structural system in the reconstruction of old cities can produce good economic benefits.

下面结合附图和具体实施方式对本发明作进一步的详细描述。The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

附图说明Description of drawings

图1为本发明宽柱双梁结构的平面图。Fig. 1 is the plane view of the wide column double beam structure of the present invention.

图2-4为图1中局部剖视图。2-4 are partial sectional views in FIG. 1 .

图5为改造前的砌体结构建筑平面图。Figure 5 is a plan view of the masonry structure building before renovation.

图6为采用本发明方法改造后的砌体结构建筑平面图。Fig. 6 is a building plan view of a masonry structure transformed by the method of the present invention.

图中,1 宽柱,2 托换梁,3 传剪器,4 楼板,5 未拆除墙体,6 连接筋。In the figure, 1 is a wide column, 2 is an underpinning beam, 3 is a shear passer, 4 is a floor slab, 5 is an undemolished wall, and 6 is a connecting bar.

具体实施方式detailed description

如图1-4所示,本发明宽柱双梁结构,其包括由原有构造柱经四周加宽而成的宽柱1、分别位于墙体两侧的托换梁2,所述每根托换梁2两端分别搭接在宽柱1上,还包括多个传剪器3,所述传剪器3一端浇筑在托换梁2内,另一端浇筑在楼板4内。As shown in Figures 1-4, the wide-column double-beam structure of the present invention includes a wide column 1 formed by widening the original structural column and underpinning beams 2 respectively located on both sides of the wall. The two ends of the underpinning beam 2 are overlapped on the wide column 1 respectively, and a plurality of shear transmission devices 3 are also included.

传剪器为放置在混凝土浇筑孔内,起到连接板与梁的作用的钢构件,它能抵抗原有楼板与新增梁之间的滑移;The shearing device is placed in the concrete pouring hole and plays the role of connecting the slab and the beam. It can resist the slippage between the original slab and the newly added beam;

分别浇筑在砌体墙体两侧的两根梁,两端分别搭接在宽柱上,先浇筑梁柱混凝土,后拆除墙体,对原结构损伤较小;The two beams are respectively poured on both sides of the masonry wall, and the two ends are respectively lapped on the wide column. The beam and column concrete is poured first, and then the wall is removed, which will cause less damage to the original structure;

宽柱为在砌体结构改造过程中,在原有构造柱周围再增加一定宽度,用以搁置新增的梁,相对于普通柱宽度较大的钢筋混凝土柱。The wide column is a reinforced concrete column with a larger width than the ordinary column, which is added a certain width around the original structural column during the transformation of the masonry structure to accommodate the newly added beam.

还包括连接筋4,所述连接筋4一端浇筑在托换梁2内,另一端与浇筑在未拆除墙体5内。It also includes connecting ribs 4, one end of which is poured into the underpinning beam 2, and the other end is poured into the undemolished wall body 5.

在改造过程中,先浇筑梁和柱,后拆除双梁间的砌体墙体,剩下不易拆除的部分留在双梁内部,合理设置连接筋,保证双梁与未拆除墙体共同工作,增强结构性。During the transformation process, the beams and columns are poured first, and then the masonry walls between the double beams are removed, and the remaining parts that are not easy to be removed are left inside the double beams, and the connecting bars are reasonably arranged to ensure that the double beams and the unremoved walls work together to strengthen the structure sex.

所述位于墙体两侧的托换梁2之间以连接筋6相连。这样可增加整个宽柱双梁结构的整体性能。The underpinning beams 2 on both sides of the wall are connected by connecting ribs 6 . This increases the overall performance of the entire wide column double beam structure.

本发明砌体结构托换改造方法,包括如下步骤:The masonry structure underpinning reconstruction method of the present invention comprises the following steps:

(10)将原有构造柱四周围浇筑钢筋混凝土,形成相对于普通柱宽度较大的宽柱(1);(10) Pour reinforced concrete around the original structural column to form a wider column (1) with a larger width than the ordinary column;

(20)在原有墙体两侧各设置一托换梁2,使托换梁2两端分别搭接在宽柱1上;(20) An underpinning beam 2 is respectively arranged on both sides of the original wall, so that the two ends of the underpinning beam 2 are lapped on the wide column 1 respectively;

(30)在托换梁2上方的楼板上开设混凝土浇筑孔,并将传剪器一端浇筑在托换梁2内,另一端浇筑在楼板4内;(30) Concrete pouring holes are provided on the floor above the underpinning beam 2, and one end of the shearer is poured in the underpinning beam 2, and the other end is poured in the floor 4;

(40)拆除原有墙体,如有难以拆除部分,则设置连接筋4,使其一端浇筑在托换梁2内,另一端与浇筑在未拆除墙体5内。(40) Remove the original body of wall, if there is a part that is difficult to remove, then set the connecting rib 4 so that one end is poured in the underpinning beam 2, and the other end is poured in the undemolished body of wall 5.

图5为改造前的砌体结构建筑平面图。图6为采用本发明方法改造后的砌体结构建筑平面图。Figure 5 is a plan view of the masonry structure building before renovation. Fig. 6 is a building plan view of a masonry structure transformed by the method of the present invention.

对比图5、图6可以看出:Comparing Figure 5 and Figure 6, it can be seen that:

本发明的方法可广泛应用于砌体结构或混凝土结构的住宅、旅馆、医院等改造中,尤为适用于小空间改造成大空间的旧建筑物改造,支托原结构时不改变其受力性能。The method of the present invention can be widely used in the transformation of houses, hotels, hospitals, etc. with masonry or concrete structures, and is especially suitable for the transformation of old buildings from small spaces to large spaces, and the original structure does not change its mechanical performance when supporting .

如有难以拆除部分,则设置连接筋4,使其一端浇筑在托换梁2内,另一端与浇筑在未拆除墙体5内,从而托换后形成的结构体系亦不改变未置换构件的受力特征,在整个改造过程中,结构体系的转换自然流畅,受力合理。If there is a part that is difficult to remove, set the connecting rib 4 so that one end is poured in the underpinning beam 2, and the other end is poured in the unremoved wall 5, so that the structural system formed after the underpinning does not change the structure of the unreplaced member. Stress characteristics, in the whole transformation process, the transformation of the structural system is natural and smooth, and the stress is reasonable.

在维持原有安全等级的情况下,基础底板及楼面板,一般不需置换和加固,与拆除重建同样的结构相比,可节省工程造价40-50%。因此该结构体系在旧城改造中的推广运用,可产生良好的经济效益。In the case of maintaining the original safety level, the base plate and floor slab generally do not need to be replaced or reinforced, which can save 40-50% of the project cost compared with demolishing and rebuilding the same structure. Therefore, the popularization and application of this structural system in the reconstruction of old cities can produce good economic benefits.

Claims (4)

1. one kind wide post twin-spar construction, it is characterised in that: the wide post (1) that includes being widened through surrounding by original constructional column, Laying respectively at the transform beams (2) of body of wall both sides, described every transform beams (2) two ends are overlapped on wide post (1) respectively, Also including that multiple biography cuts device (3), described biography is cut device (3) one end and is cast in transform beams (2), and the other end is cast in building In plate (4).
Wide post twin-spar construction the most according to claim 1, it is characterised in that: also include dowel (4), described company Connecing muscle (4) one end to be cast in transform beams (2), the other end is not removed in body of wall (5) with being cast in.
Wide post twin-spar construction the most according to claim 1 and 2, it is characterised in that be positioned at the torr of body of wall both sides described in: Change and be connected with dowel (6) between beam (2).
4. a masonry structure Underpinning method, it is characterised in that comprise the steps:
(10) by original constructional column pouring reinforcement concrete all around, the wide post bigger relative to common post width is formed (1);
(20) one transform beams (2) is respectively set in original body of wall both sides, makes transform beams (2) two ends be overlapped on wide post respectively (1) on;
(30) on the floor of transform beams (2) top, offer concreting hole, and biography is cut device one end be cast in torr Changing in beam (2), the other end is cast in floor (4);
(40) remove original body of wall, if any being difficult to dismounting part, then dowel (4) is set so that it is one end is cast in torr Changing in beam (2), the other end is not removed in body of wall (5) with being cast in.
CN201610180462.5A 2016-04-27 2016-04-27 Wide-post double-beam structure and building body structure underpinning modification method Pending CN105863286A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610180462.5A CN105863286A (en) 2016-04-27 2016-04-27 Wide-post double-beam structure and building body structure underpinning modification method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610180462.5A CN105863286A (en) 2016-04-27 2016-04-27 Wide-post double-beam structure and building body structure underpinning modification method

Publications (1)

Publication Number Publication Date
CN105863286A true CN105863286A (en) 2016-08-17

Family

ID=56626229

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610180462.5A Pending CN105863286A (en) 2016-04-27 2016-04-27 Wide-post double-beam structure and building body structure underpinning modification method

Country Status (1)

Country Link
CN (1) CN105863286A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106245931A (en) * 2016-09-30 2016-12-21 合肥工业大学 The underpinning device of load bearing wall and construction method in brick mix structure
CN110230410A (en) * 2019-06-20 2019-09-13 同济大学建筑设计研究院(集团)有限公司 A kind of dual beam configuration underpins node

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007162288A (en) * 2005-12-13 2007-06-28 Asahi Kasei Homes Kk Extension beam and method of reinforcing floor panel
CN101956465A (en) * 2010-09-06 2011-01-26 华侨大学 Reinforcing method for improving earthquake resistance of stone structure buildings
JP4969152B2 (en) * 2006-05-23 2012-07-04 太平洋セメント株式会社 Reinforcement structure and reinforcement method for concrete building

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007162288A (en) * 2005-12-13 2007-06-28 Asahi Kasei Homes Kk Extension beam and method of reinforcing floor panel
JP4969152B2 (en) * 2006-05-23 2012-07-04 太平洋セメント株式会社 Reinforcement structure and reinforcement method for concrete building
CN101956465A (en) * 2010-09-06 2011-01-26 华侨大学 Reinforcing method for improving earthquake resistance of stone structure buildings

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
焦建华等: "利用宽柱双梁框架结构改造加固砌体结构", 《排灌机械工程学报》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106245931A (en) * 2016-09-30 2016-12-21 合肥工业大学 The underpinning device of load bearing wall and construction method in brick mix structure
CN110230410A (en) * 2019-06-20 2019-09-13 同济大学建筑设计研究院(集团)有限公司 A kind of dual beam configuration underpins node
CN110230410B (en) * 2019-06-20 2024-03-19 同济大学建筑设计研究院(集团)有限公司 Double-column structure underpinning node

Similar Documents

Publication Publication Date Title
CN105804283B (en) Full assembly concrete-filled steel tube frame combined shear wall construction
CN104032869B (en) A kind of Prefabricated stacking floor and precast construction method thereof
Buitrago et al. Structural failures in cast-in-place reinforced concrete building structures under construction
CN204343459U (en) The parapet node structure of overlaid plate type concrete shear wall system
CN103422606A (en) Structural column erecting-free block and construction method thereof
CN104314213B (en) A kind of hollow groined slab floor of large span assembled
CN105965672B (en) A kind of fabricated shear wall model structure unitary mould
CN106759462A (en) A kind of prefabricated piping lane and its construction method suitable for narrow construction site
CN103410265A (en) Splicing structure of laminated floor slab
CN101435232A (en) Common concrete frame column restricted type regeneration concrete shear force wall and manufacturing method thereof
CN105937277A (en) Connection Structure of L-shaped Shear Wall Edge Members
CN108824676B (en) Bottom joint structure of double-sided superimposed shear wall and installation construction method thereof
CN203808292U (en) Assembly type gridded shear wall structure system
CN105863286A (en) Wide-post double-beam structure and building body structure underpinning modification method
CN101012655A (en) Construction method of carrying out underground space rigid connection by stages
CN113898102A (en) A ribbed concrete laminate
CN104234418A (en) Early removal formwork for fabrication of reinforced concrete beams and construction method thereof
KR102132674B1 (en) Non-bearing wall system with seismic-proofing construction
CN206681262U (en) A kind of prefabricated Concrete-Filled Square Steel Tube coupling beam of multilayer
CN204475886U (en) A kind of protective cover plate of reserved opening
CN205776901U (en) The connecting structure of L-type shear wall edge member
CN105625717A (en) Shear wall waist beam concrete casting formwork plug tool and plugging method thereof
CN205742988U (en) The explosion-proof membrane module of template one word piece
CN204876620U (en) Peripheral hardware concrete frame reinforced structure
CN110258819B (en) Connecting node of reinforced concrete column and flat slab and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160817

RJ01 Rejection of invention patent application after publication