CN105672664A - Integral heat insulation wallboard building system - Google Patents

Integral heat insulation wallboard building system Download PDF

Info

Publication number
CN105672664A
CN105672664A CN201511008191.7A CN201511008191A CN105672664A CN 105672664 A CN105672664 A CN 105672664A CN 201511008191 A CN201511008191 A CN 201511008191A CN 105672664 A CN105672664 A CN 105672664A
Authority
CN
China
Prior art keywords
bar
heat insulation
floor
wallboard
watt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201511008191.7A
Other languages
Chinese (zh)
Inventor
张领然
张前
李悦雯
张政
马兆龙
徐科化
李俊强
张利敏
张利宁
王新萍
张利静
张利振
职敏玲
郝桂芝
李昊梁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of CN105672664A publication Critical patent/CN105672664A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/50Producing shaped prefabricated articles from the material specially adapted for producing articles of expanded material, e.g. cellular concrete
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D1/00Roof covering by making use of tiles, slates, shingles, or other small roofing elements
    • E04D1/28Roofing elements comprising two or more layers, e.g. for insulation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D1/00Roof covering by making use of tiles, slates, shingles, or other small roofing elements
    • E04D1/36Devices for sealing the spaces or joints between roof-covering elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Building Environments (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides an integral heat insulation wallboard building system, which comprises work procedures including integral heat insulation wallboard production and construction, floor slab production and construction, universal tile production and construction and the like. According to the integral heat insulation wallboard building system, big wallboards, big floor slabs and universal tile boards are produced in scales in factories, and are hoisted by machinery in construction sites; a building block stacking type house building mode is adopted; the building heat insulation and structure integration can be realized; the service life of the building heat insulation is identical to the service life of the structure; wallboards and floor slabs are combined by upright posts and ring beam casting; the whole house is a cast whole, so that the earthquake-resistant and quakeproof performance is improved; and the occurrence of people injury disaster due to wall and house collapse in the earthquake is prevented The integral heat insulation wallboard building system has the advantages that the building speed is high; a three-storey residential building being 400m<2> can be built in 10 days by 6 workers; the building period can be shortened by 3/4; and about half manufacturing cost of the house is saved. According to the integral heat insulation wallboard building system, green wall materials, green construction and green building are used, so that huge economic benefits and social benefits can be generated in the great courses of saving the energy, reducing the emission and building the beautiful China.

Description

Integral heat insulation wallboard building system
One, technical field
The present invention relates to building field, particularly to integral heat insulation wallboard building system.
Two, background technology
Present construction is generally adopted framework construction system and brick mixed building system, and common construction method is all build beam column, roofing, build a wall, plaster wall, do the operations such as external thermal insulation. Such architectural mode has very big defect: 1, construction also rests on Qin brick and Han tile, removes brick and carry the rough formula construction epoch of mud, construction period length, take a lot of work, require great effort, Fei Cai, contaminated environment, the building-site that workload of its building 90% all scrapes Exposure to Sunlight at wind completes. 2, building heat preservation needs secondary to construct, and service life only has 20 years, of poor quality, and often having is blown off by strong wind pounds people's phenomenon and occur. 3, roofing precoated plate affects house overall structure, easily causes hidden danger during earthquake, takes a lot of work with cast-in-place top, takes template, cost height. 4, no matter roofing construction complex procedures, be flat roof deck or pitched roof, drainage all easily occur.
Three, summary of the invention
In order to overcome above walling and the existing defect of construction, the present invention proposes integral heat insulation wallboard building system, including integral heat insulation wallboard produce with construction, floor produce with construction, all-round watt produce and the composition such as a construction.
The present invention is achieved in that and first produces integral heat insulation wallboard, its height is the distance between building grade beam and collar tie beam, length is that column is to the distance between column between another between this for building, and wallboard two surface layer is concrete, inside has bar-mat reinforcement, intermediate layer is foam cement, reinforcing bar connects two-layer bar-mat reinforcement through foam cement, and door and window mouth, water, electrical conduits can be made in the lump, and surrounding is fluted, having bar connecting head, hole for hoist is arranged at top.
Floor be adopt bulk burr precoated plate, its length is the interior clean length between house, can micro-length, its width is generally adopted the width being slightly less than room half. Being typically in more than 3.5 meters because room is wide, make monoblock burr precast floor slab such as floor and be then inconvenient to transport, burr end face has the reinforcing bar extended, and wherein the every 0.8 meter of reinforcing bar having a root length to go out two wallboard thickness of upper row, has four pre-buried suspension ring above precast floor slab.
The lifting mounting process of integral heat insulation wallboard building system is: integral heat insulation wallboard carries out Unified number after carrying out, mark on ground by number and should put position, the one layer of mortar in stand on position should put, first block of wallboard to select after one block of wallboard at angle in wall, wallboard hangs on basis, place by line, the suitable power tension of suspension hook simultaneously, push-pull bar is regulated with a set of or two sets, the gripping mechanism clamping panel tops on top, push-and-pull adjusting rod and wallboard are oblique pull shape in about 45° angle, bottom base weight fastens, regulate middle part push-pull device at fixed, wallboard perpendicularity is corrected with vertical guiding rule, chock is stamped on both sides, wallboard bottom surface, complete, remove suspension hook, hang rectangular that block wallboard adjacent with first block of wallboard again, with a set of push-and-pull adjusting rod, after wallboard correction, bar connecting firm welding drift angle bar connecting head Φ 16 adjacent for two blocks of wallboards, first block of wallboard just can remove a set of adjustment push-pull bar, then the wallboard that lifting is adjacent with two blocks of corner wallboards, after fixing weldering is finished, the push-and-pull adjusting rod of previous block of wallboard can all remove, the integral heat insulation wallboard lifting of flood, vertical welding are put into column steel reinforcement cage, and whole bar connecting heads of two wallboard end faces are welded, the bar connecting head of wall bottom face is welded, upper pillar stand template after fixing between two wallboard end faces. the integral heat insulation wallboard of integral heat insulation wallboard building system, the big floor of burr, column, collar tie beam construction process adopt one to water the technique connected more and carry out, ring beam template on wallboard upper end, in exterior wall, face die plate and inside wall formwork will lower than the thickness of one floor of exterior sheathing, inner formword plank to thicken, and to have sufficient amount of wood to support below inner formword simultaneously. the deep groove of 1cm width 3cm is outputed by the distance of 0.8 meter above exterior sheathing. after ring beam template completion, put into ring beam reinforcing steel bar cage, lift bulk burr floor, floor is placed on collar tie beam inner formword and inside wall formwork top, underfloor placing of reinforcement inserts in the steel reinforcement cage of collar tie beam respectively simultaneously, and upper platoon leader's muscle puts into the groove on exterior sheathing, is used for drawing solid model plate top. putting into spacer in ring beam reinforcing steel bar cage, hang on top wall panel, the reinforcing bar of top wall panel lower surface and bottom wall panel upper surface inserts in ring beam reinforcing steel bar cage respectively. the reinforcing bar of wallboard end face can bending or triangular in shape in order to strengthen adhesion. wider gap is had between two pieces of floors after floor lifting completion, end face reinforcement welding or bending interconnection, with the plank exceeding gap width, long long with floor, on top bore some row's apertures, wear reinforcing bar, prop up on two floors with some trapezes, gap formwork also can be undertaken by the method for lower Zhi Mu, builds column, collar tie beam, floor gap, and such once-cast integral heat insulation wallboard, column, lintel, floor just become the entirety built entirely.
The production technology of floor, can use the technique that mobile flat-die or ground flat-die add baffle plate to carry out, first produce floor bar cage by dimensional requirement; lie against on mould or on ground flat-die, surrounding overhead gage, does some little iron sheets; upper boring, the same floor bar of diameter, it is advisable with good perforation; baffle plate bores macropore, is twice than floor bar, be advisable can be covered by iron sheet; first wear small iron plate, after wear baffle plate, template completion after; inject concrete, vibration, leveling, after initial set, namely go baffle plate, surrounding plucking, maintenance.
Integral heat insulation wallboard building system includes all-round watt of roofing, integrates waterproof, insulation, structure, has waterproof corrugated layer, heat-insulation layer and bottom surface layer, and two surface layers are concrete, and heat-insulation layer is foam cement. Bar frame connects three layers as a whole, its length is the overall length of half pitched roof and eaves, it wide within 3 meters, top end face is acute angle, has embedded bar union joint, and both sides end face has bar connecting head, while there being coverage row of tiles on a roof, while there being obscured row of tiles on a roof, waterproof corrugated layer surface is hydrophobic color layers, glass fiber mesh, inside has bar-mat reinforcement.The interval of purlin can be about 2 meters, during construction from one, house, two pitched roofs lift simultaneously and lay, beating husky ash on wallboard, welded together for the bar connecting head on two pieces of all-round watt tops, the coverage row of tiles on a roof of a piece all-round watt is covered with the obscured row of tiles on a roof of another block, envelope filled out by gap fluid sealant, each union joint welds with slope, room, purlin etc., upper husky ash, then detains ridge tiles and upholstery border watt.
All can watt production technology: watt all can use wave flat-die, surrounding has baffle plate, first the method for hydrophobic, the spraying of colored cement mortar is sprayed at wave template surface, paving glass grid cloth, slightly stop, cast certain thickness concrete, and shake, pre-ready-made bar frame is put into template, lower net plate also shakes in concrete, without when precipitating out water on concrete surface, put into certain thickness foam cement, to be foamed the cement solidifies after, pour into a mould concrete again and vibrate, after initial set, remove baffle plate, and maintain. All can there be underwater paint or glazed colour layer in a watt wave surface.
Integral heat insulation wallboard building system has following characteristics:
1, building heat preservation and structure-integrated, building heat preservation and structure same life-span, overall structure is strong simultaneously, and anti-seismic performance highlights. The surface layer of integral heat insulation wallboard is concrete, does load-bearing, and intermediate layer is foam cement, is incubated, and bar frame is a firmly entirety triplicity. General about the 10cm of heat-insulation layer, heat conductivity 0.88, heat bridge 1 ‰, heat insulation effect is splendid, and two facing concrete layers are about 10cm altogether, compressive load 5.6 MPas, and the wall of 3.5 meters can load-bearing hundreds of ton together. Construction deadlight surrounding bar connecting head respectively with post, grade beam, collar tie beam, floor interconnection, be integrally forming through concreting, whole house is exactly the entirety built, it is therefore prevented that earthquake wall falls the collapse tragedy hurted sb.'s feelings of room and occurs.
2, construction speed is fast
Integral heat insulation wallboard building system is all adopt big wallboard, big floor, big shoe plate mechanical hoisting, open the pattern that builds a house of the formula of playing with building blocks, within every 20 minutes, just can lift and fix one block of wallboard, every 10 minutes with regard to can lift place one piece of floor, all can watt, construction speed is exceedingly fast. As built the three-storey building of 400 square metres, with artificial 6 people, within 10 days, just building up, it can shorten the completion time of project of 3/4ths.
3, four joint one environmental protection
Integral heat insulation wallboard building system is producing and is saving many operations in construction; bulk materials, template are saved; as: every 100 square metres of buildings can save cement 10 tons; economize on water 4 tons, economize on electricity 100 degree, save template 100 square metres; than laying bricks, wall saves land 1/4th; not only vivid accomplish energy-conservation, water saving, material-saving, saved land, and reduced by the garbage emission of 90%, protect environment, this invention achieves: green wall materials-green construction-green building.
4, cost is reduced
Integral heat insulation building system, owing to changing the mode of production, changing form of construction work, thus eliminate many traditional construction operations, and as built a wall construction, white washed wall construction, construction of exterior insulation system etc., save material, improve efficiency, thus reduce cost, according to calculating, save construction cost nearly 1/2nd than traditional handicraft.
5, industrialization is conducive to
Integral heat insulation wallboard building system, its wallboard, floor, roofing tile, stair etc. are all complete in factory, even column can wall band post, finish coat all can be made in factory, its workload accounts for the 90% of building, and putting up a house as making automobile in factory becomes a reality.
In a word, integral heat insulation wallboard building system, from green wall materials green construction green building, in energy-saving and emission-reduction, build in the great cause of beautiful China, huge economic benefit and social benefit will be produced.
Four, accompanying drawing explanation
Accompanying drawing 1 is integral heat insulation wallboard building system construction cross-sectional view: (1) integral heat insulation wallboard, (2) floor, (3) floor bar, (4) ring beam reinforcing steel bar cage, (5) collar tie beam exterior sheathing, (6) collar tie beam inner formword, (7) inner formword Zhi Mu, (8) template clamping, (9) exterior sheathing fixes reinforcing bar. (19) cornice sheathing, (20) cornice sheathing lower surface reinforcing bar, (21) wainscot sheathing upper surface reinforcing bar.
Accompanying drawing 2 be two floors in conjunction with direct-view figure: (2) floor, (3) floor bar, (10) template, (11) template trapeze and block, (12) two floor gaps.
Accompanying drawing 3 is all-round watt cross-sectional view: (13) all-round watt, (14) all-round watt waterproof layer, (15) all-round watt heat-insulation layer, (16) all-round watt bottom surface layer, (17) obscured row of tiles on a roof, (18) cover row of tiles on a roof.
Five, specific implementation method
After ground completion, on ground, line is also numbered integral heat insulation wallboard, position cloth mortar should be put, the vertical fixing welding of lifting integral heat insulation wallboard wainscot sheathing (1) correction, column steel reinforcement cage is placed between two wallboards, welding end surface bar connecting head is connected with steel reinforcement cage again, upper pillar stand template, collar tie beam exterior sheathing (5) and inner formword (6) on integral heat insulation wallboard (1) upper end, tighten fixture (8), the lower Zhi Mu (7) of inner formword (6), put into ring beam reinforcing steel bar cage (4), lifting floor (2), reinforcing bar (3) inserts in ring beam reinforcing steel bar cage (4), reinforcing bar (9) blocks exterior sheathing (5), hang on cornice sheathing (19), cornice sheathing end face reinforcing bar (20) intersects in ring beam reinforcing steel bar cage (4) with wainscot sheathing end face reinforcing bar (21), (12) cope match-plate pattern (10) between two floors (2) gap, block (11) is propped up at floor (2) trapeze, reinforcing bar (3) between gap is welded or bending cross-connection, cast column, gap (12) concrete between collar tie beam (4) two floor (2). after the completion of bed rearrangement roof truss, collar tie beam is beaten mortar lifting roofing all-round watt (13), two domatic carry out simultaneously, all can watt (13) push up bar connecting head welding, the coverage row of tiles on a roof (18) of watt (13) the obscured row of tiles on a roof (17) of front all-round watt (13) all can be hidden, sealant sealing all can be filled out in the gap of watt (13) at top two, the bar connecting head of watt adjacent face is welded, with slope, room, purlins etc. weld, break mortar simultaneously and buckle ridge tiles, button limit decorative tile, house builds up.

Claims (10)

1. an integral heat insulation wallboard building system, including integral heat insulation wallboard: the height of wallboard is building grade beam to the distance between collar tie beam, length be building between this column to the distance of column between another, the pre-buried bar connecting head of wallboard surrounding respectively with column, collar tie beam, grade beam, the steel reinforcement cage of floor connects, through column, collar tie beam, the concrete cast of grade beam and integral heat insulation wallboard are integrally forming naturally, wallboard two surface layer is concrete, inside there is bar-mat reinforcement, centre is heat-insulation layer, reinforcing bar welds the bar-mat reinforcement in two surface layers through heat-insulation layer, its lifting mounting process is characterized in that: integral heat insulation wallboard is numbered after carrying out, mark on basis by number and should put position, wallboard hangs on basis and places by number, the suitable power tension of suspension hook simultaneously, with the gripping mechanism clamping panel tops regulating push-pull bar top, regulating push-pull bar with wall is oblique pull shape, regulate and fasten with weight bottom push-pull bar, regulate middle part push-pull device at fixed, with vertical guiding rule correct wallboard perpendicularity, after remove hoist lifting hook.
2. integral heat insulation wallboard according to claim 1 lifting mounting process is characterized in that: slurry of plastering bottom the wallboard placed, and chock is stamped on both sides, is welded to connect head;When, after adjacent two pieces of panel tops reinforcement welding, the adjustment push-pull bar of previous block of wallboard can remove; Between two wallboards, put into column steel reinforcement cage, welding end surface union joint cope match-plate pattern.
3. integral heat insulation wallboard building system according to claim 1 includes burr bulk floor, it is characterised in that: the length of floor is the clean long of room, and the width of floor is slightly smaller than the width of room half, surrounding end face burr, has the reinforcing bar extending end face.
4. burr bulk floor according to claim 3; its production technology is characterised by: removable flat-die or ground flat-die add the technique of baffle plate to carry out; first produce floor bar cage by dimensional requirement; lie against on mould or on ground flat-die, surrounding overhead gage, does some little iron sheets; upper boring; the same floor bar of diameter, is advisable with good perforation, bores macropore on baffle plate; it is twice than floor bar; with can by iron sheet cover be advisable, first wear small iron plate, after wear baffle plate; after template completion; inject concrete, vibration, leveling, after initial set, namely go baffle plate, surrounding plucking, maintenance.
5. integral heat insulation wallboard building system according to claim 1, including integral heat insulation wallboard, the construction process of burr bulk floor, column and collar tie beam waters full connection with one to carry out, it is characterized in that: after completion installed by the integral heat insulation wallboard of ground floor, ring beam template on wallboard upper end, in exterior wall, face die plate and inside wall formwork will lower than the thickness of one floor of exterior wall exterior sheathing, put into ring beam reinforcing steel bar cage, lifting floor, being placed on collar tie beam inner formword and inside wall formwork, the reinforcing bar that floor end face stretches out simultaneously inserts in ring beam reinforcing steel bar cage respectively; Putting into same collar tie beam in ring beam reinforcing steel bar cage with high spacer, namely hang on top wall panel, the reinforcing bar of cornice sheathing and wainscot sheathing end face intersects in ring beam reinforcing steel bar cage.
6. the construction process of integral heat insulation wallboard building system according to claim 5, its sign is in that: the reinforcing bar that wallboard upper and lower end face is extended is bending shape or triangle; The steel bar end of floor end face is bending-like, the every 0.8 meter of reinforcing bar having a root length to go out outer wall template of placing of reinforcement on floor, exterior sheathing is opened the deep 3 centimetres wide grooves of 1 centimetre, its reinforcing bar enters the groove fixing exterior sheathing of fixing mother, there is very wide gap between every two floors, the reinforcement welding of end face or bending interconnection, exceed the plank holder with floor of the gap length below two floor gaps with wide, method with Zhi Mufa or with reinforcing bar trapeze is propped up on two floors, pours into a mould concrete.
7. integral heat insulation wallboard building system according to claim 1, including all-round watt of roofing, it is characterized in that: all can watt long be the house half way up the mountain length with edge, wide is within 3 meters, divide waterproof layer, heat-insulation layer, bottom surface layer three layers, waterproof layer is wave tiling, it is made up of concrete and bar-mat reinforcement, watt while there being coverage row of tiles on a roof, another side has obscured row of tiles on a roof, and moderate soak layer is foam cement, and bottom surface layer is concrete, built-in bar-mat reinforcement, reinforcing bar welds waterproof layer through heat-insulation layer with the bar-mat reinforcement of bottom surface layer.
8. all-round watt according to claim 7, it is characterised in that: there are underwater paint, water-repellent layer or glaze layer in waterproof layer surface, under have cracking resistance glass fiber mesh, a watt top end face is acute angle, has steel bar welding joint; Lower surface waterproof layer to be longer than heat-insulation layer and bottom surface layer, and both sides end face has steel bar welding joint.
9. all-round watt according to claim 7, its production technology is characterized in that: watt all can use wave flat-die, surrounding has baffle plate, first the method for hydrophobic, the spraying of colored cement mortar is sprayed at wave template surface, paving glass grid cloth, pour into a mould certain thickness concrete, and shake, pre-ready-made bar frame is put into template, lower net plate also shakes in concrete, without when precipitating out water on concrete surface, put into certain thickness foam cement, to be foamed the cement solidifies after pour into a mould bottom surface layer concrete again.
10. all-round watt according to claim 7, architectural construction technology is characterized in that: watt all can join roof truss purlin within two meters, all can watt place from two slopes, one, room simultaneously, the row of tiles on a roof of covering of one piece watt pushes down the obscured row of tiles on a roof of another block watt, two top, slope watt bar connecting head welding, adjacent Habenaria dipionema Sohltr is welded, gap sealant sealing, upper husky ash, button ridge tiles and upholstery border watt, weld a watt bottom surface steel bar welding joint with purlin, slope, room, collar tie beam.
CN201511008191.7A 2015-10-28 2015-12-22 Integral heat insulation wallboard building system Pending CN105672664A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2015107048720 2015-10-28
CN201510704872.0A CN105239718A (en) 2015-10-28 2015-10-28 Integral heat insulation wallboard building system

Publications (1)

Publication Number Publication Date
CN105672664A true CN105672664A (en) 2016-06-15

Family

ID=55037516

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201510704872.0A Pending CN105239718A (en) 2015-10-28 2015-10-28 Integral heat insulation wallboard building system
CN201511008191.7A Pending CN105672664A (en) 2015-10-28 2015-12-22 Integral heat insulation wallboard building system

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201510704872.0A Pending CN105239718A (en) 2015-10-28 2015-10-28 Integral heat insulation wallboard building system

Country Status (1)

Country Link
CN (2) CN105239718A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019678A (en) * 2015-07-29 2015-11-04 北京中联天盛建材有限公司 Energy-saving and environment-friendly type waterproof construction method of existing roof
CN109736427A (en) * 2019-01-24 2019-05-10 浙江立恒建设有限公司 A kind of Antiseismic house builds structure
CN114108833A (en) * 2021-12-13 2022-03-01 深圳市湛艺建设集团有限公司 Assembled wallboard connecting structure and construction method thereof

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760098A (en) * 2016-11-28 2017-05-31 张领然 Assembled bulk tooth form floor and its production construction process
CN106592842B (en) * 2016-11-28 2021-08-17 张领然 Assembled large light floor slab and its production and construction process and bearing fixture
CN107035046A (en) * 2017-05-04 2017-08-11 胡德 A kind of floor quick structure for assembling and its assemble method
CN110397268B (en) * 2019-07-20 2021-08-31 山东金城建设有限公司 Integrated design and construction method of back-cast ring beam formwork and slab support for prefabricated shear wall

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2410352Y (en) * 2000-01-21 2000-12-13 纪勇 Novel heat-insulating roof tile
CN2873922Y (en) * 2005-11-21 2007-02-28 张领然 Heat insulation cement color tile
CN103352537A (en) * 2013-07-09 2013-10-16 张领然 Integral load-bearing heat-insulating wall plate and production and construction technology thereof
CN103669905A (en) * 2013-12-31 2014-03-26 吕燕 Lightweight composite prefabricated panel combined type house and building method thereof
US9151065B1 (en) * 2012-09-27 2015-10-06 A.L. Patterson, Inc. Precast concrete lift anchor assembly
CN204715762U (en) * 2015-04-22 2015-10-21 邱过门石 A kind of wall support device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2410352Y (en) * 2000-01-21 2000-12-13 纪勇 Novel heat-insulating roof tile
CN2873922Y (en) * 2005-11-21 2007-02-28 张领然 Heat insulation cement color tile
US9151065B1 (en) * 2012-09-27 2015-10-06 A.L. Patterson, Inc. Precast concrete lift anchor assembly
CN103352537A (en) * 2013-07-09 2013-10-16 张领然 Integral load-bearing heat-insulating wall plate and production and construction technology thereof
CN103669905A (en) * 2013-12-31 2014-03-26 吕燕 Lightweight composite prefabricated panel combined type house and building method thereof
CN204715762U (en) * 2015-04-22 2015-10-21 邱过门石 A kind of wall support device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019678A (en) * 2015-07-29 2015-11-04 北京中联天盛建材有限公司 Energy-saving and environment-friendly type waterproof construction method of existing roof
CN105019678B (en) * 2015-07-29 2018-03-13 北京中联天盛建材有限公司 A kind of energy-saving environment-protecting type waterproof construction method for having roofing
CN109736427A (en) * 2019-01-24 2019-05-10 浙江立恒建设有限公司 A kind of Antiseismic house builds structure
CN114108833A (en) * 2021-12-13 2022-03-01 深圳市湛艺建设集团有限公司 Assembled wallboard connecting structure and construction method thereof
CN114108833B (en) * 2021-12-13 2023-08-22 深圳市湛艺建设集团有限公司 Assembled wallboard connecting structure and construction method thereof

Also Published As

Publication number Publication date
CN105239718A (en) 2016-01-13

Similar Documents

Publication Publication Date Title
CN104947788B (en) A kind of modular assembly formula building systems and its method of construction
CN105672664A (en) Integral heat insulation wallboard building system
CN101818539B (en) Assembled integral building and construction method thereof
CN101818527B (en) Assembled integral shear wall structure system and construction method thereof
CN201738600U (en) Assembled integrated type building
CN106436893A (en) Fully-prefabricated structure and construction method thereof
WO2016062224A1 (en) Integrated column-equipped heat insulation wallboard, manufacturing and building processes and corollary equipment thereof
CN103374986A (en) Multifunctional combined lightweight concrete curtain wall and constructing method thereof
CN111926910A (en) Installation method of fabricated building
CN105133755B (en) A kind of construction method and shear wall structure of reinforcement welding rack composite shear wall
CN104074305B (en) A kind of self-heat conserving decoration integrated Multi-function light concrete composite plates and curtain wall
CN103352569A (en) Construction method of integrally-poured architecture building
CN110387954A (en) A kind of assembled energy-saving New Residence structure and preparation method thereof
CN204781575U (en) A large-scale prefabricated external wall panel integrated with structural insulation and decoration
CN110005104A (en) A kind of fabricated heat preservation decoration integrative laminated floor slab and its construction method
CN103362307B (en) Construction method for modularizing insulation wall boards and pouring integrated house building
CN210178013U (en) Fully-prefabricated assembled house
CN215907293U (en) Rendering-free exhaust flue and assembly type flue mounting structure
CN111119368A (en) Construction method for externally-hung metal rock wool sandwich board of autoclaved sand aerated concrete wallboard
CN103362235B (en) Integrally-poured building house with wallboards integrating thermal insulating and templates
CN110593440B (en) Construction method of prefabricated wall structure
CN203412143U (en) Wall body structure of integrally poured building house
CN203412312U (en) Thermal-insulating integrated template wallboard construction building
CN111287311A (en) Construction method of cold-formed thin-wall light steel structure building
CN116104224A (en) A kind of external wall thermal insulation integrated gap assembly structure node and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160615

WD01 Invention patent application deemed withdrawn after publication