CN105645249A - Balance crane used for hoisting box girders of steel bridge - Google Patents
Balance crane used for hoisting box girders of steel bridge Download PDFInfo
- Publication number
- CN105645249A CN105645249A CN201610192556.4A CN201610192556A CN105645249A CN 105645249 A CN105645249 A CN 105645249A CN 201610192556 A CN201610192556 A CN 201610192556A CN 105645249 A CN105645249 A CN 105645249A
- Authority
- CN
- China
- Prior art keywords
- hanging beam
- steel bridge
- balance hanging
- balance crane
- balance
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 30
- 239000010959 steel Substances 0.000 title claims abstract description 30
- 238000005304 joining Methods 0.000 claims description 3
- 238000007667 floating Methods 0.000 abstract description 3
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000010276 construction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002372 labelling Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
- B66C1/16—Slings with load-engaging platforms or frameworks
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
The invention discloses a balance crane used for hoisting box girders of a steel bridge. The balance crane can accommodate different weights and special structures of box girders. The technical scheme includes that through combination of two balance crane parts and lifting lugs on the balance crane, hoisting stability is greatly improved, and the balance crane is applicable to various hoisting facilities such as big floating cranes and portal cranes; in different production and operation areas, the hoisting advantages can be used maximally, and problems of limited model selection of the balance crane and unbalance loading are avoided. In addition, lifting lugs in different size can be selected according to different specifications of box girders of the steel bridge, slings are reasonably distributed, and therefore different tons of box girders can be hoisted.
Description
Technical field
The present invention relates to large-scale steel structure lifting field, particularly for the balance hanging beam of lifting steel bridge box beam.
Background technology
In hoisting process, in order to keep being hung the balance of component, reasonable distribution, balance the load of each suspension centre, reduce the unbalance loading that crane bears, select or to make suitable balance hanging beam most important. For Scotland FOX steel bridge project that Shanghai Zhenhua heavy industry is undertaken the construction of, this steel bridge typical case's section box girder length is about 16.2m, width is about 30.3m, deck-molding is about 4.5m, gross weight is about 200T, special section box girder length has 11.45m, 12.15m, 17.9m, 19.9m etc., single box beam not to weigh about as 140T��390T not etc. Owing to box beam dimensions, weight differ, if adopting traditional single balance hanging beam, it is impossible to meet lifting requirements, the selection of crane be there has also been restriction simultaneously; If the combination of single hanging beam used simply, lifting stability can be reduced, increasing potential safety hazard, being greatly increased construction cost.
Summary of the invention
The brief overview of one or more aspect given below is to provide the basic comprehension to these aspects. This summarizes the extensive overview of the not all aspect contemplated, and is both not intended to identify the key or decisive key element also non-scope attempting to define any or all aspect of all aspects. Its some concepts being uniquely intended to provide in simplified form one or more aspect think the sequence of more detailed description given later.
It is an object of the invention to solve the problems referred to above, it is provided that a kind of balance hanging beam for lifting steel bridge box beam, the weight being suitable for each box beam of steel bridge does not wait and box beam special structure form.
The technical scheme is that and present invention is disclosed a kind of balance hanging beam for lifting steel bridge box beam, described balance hanging beam is made up of two balance hanging beam single-pieces, is wherein welded to connect between two balance hanging beam single-pieces.
One embodiment of the balance hanging beam for lifting steel bridge box beam according to the present invention, is welded by four stay tubes and gusset plate between described two balance hanging beam single-pieces.
One embodiment of the balance hanging beam for lifting steel bridge box beam according to the present invention, described four stay tubes are square tubes.
One embodiment of the balance hanging beam for lifting steel bridge box beam according to the present invention, in described four stay tubes two are perpendicular to the direction of described balance hanging beam single-piece and place, all the other two intersections in described four stay tubes are placed, and weld each through described gusset plate on the cross point of two stay tubes that intersection is placed and with the joining place of described balance hanging beam.
One embodiment of the balance hanging beam for lifting steel bridge box beam according to the present invention, the top and bottom of described two balance hanging beam single-pieces are equipped with at least one hanger.
One embodiment of the balance hanging beam for lifting steel bridge box beam according to the present invention, the size of described hanger is depending on rigging size.
The present invention contrasts prior art following beneficial effect: the present invention is by the mode of the combination of double joint balance hanging beam single-piece and the hanger on balance hanging beam, substantially increase lifting stability, it is applicable to the various hanging device such as large-scale floating crane, gantry crane, in different production operation regions, all can play maximum lifting advantage, avoid the problem such as hanging beam type selecting, equipment unbalance loading simultaneously. And the different size according to steel bridge box beam selects different hanger sizes, reasonable Arrangement rigging, it is achieved the box beam of the different tonnage of lifting.
Accompanying drawing explanation
Fig. 1 illustrates the overall structure schematic diagram of the preferred embodiment of the balance hanging beam for lifting steel bridge box beam of the present invention.
Fig. 2 illustrates the top view of the preferred embodiment of the balance hanging beam for lifting steel bridge box beam of the present invention.
Fig. 3 illustrates the hanger scattergram of the preferred embodiment of the balance hanging beam for lifting steel bridge box beam of the present invention.
Fig. 4 to Fig. 6 illustrates the use schematic diagram that balance hanging beam lifts.
Detailed description of the invention
After reading the detailed description that embodiment of the disclosure in conjunction with the following drawings, it is possible to be more fully understood that features described above and the advantage of the present invention. In the accompanying drawings, each assembly is not necessarily drawn to scale, and the assembly with similar correlation properties or feature is likely to be of same or like accompanying drawing labelling.
Fig. 1 illustrates the overall structure of the preferred embodiment of the balance hanging beam for lifting steel bridge box beam of the present invention, and Fig. 2 illustrates its top view, and Fig. 3 illustrates its hanger scattergram. Referring to Fig. 1 to Fig. 3, the balance hanging beam of the present embodiment is made up of two balance hanging beam single-pieces 11 and 12, is wherein welded to connect between two balance hanging beam single-pieces 11 and 12. Specifically, it is welded by four stay tubes 21��24 and gusset plate 31��35 between these two balance hanging beam single-pieces 11 and 12.
These four stay tubes 21��24 are square tubes, and two 21,22 directions being perpendicular to balance hanging beam single-piece therein are placed, and two other root 23,24 intersects to be placed. The joining place of the cross point of stay tube 23,24 and itself placed and balance hanging beam single-piece of intersecting is to be welded by gusset plate 31��35. Lifting stability can be improved, it is adaptable to the various hanging device such as large-scale floating crane, gantry crane, in different production operation regions, all can play maximum lifting advantage, avoid the problem such as hanging beam type selecting, equipment unbalance loading simultaneously.
Additionally, the top and bottom of two balance hanging beam single-pieces 11,12 are equipped with at least one hanger 4, a grade size of opening for these hangers 4 all differs, and is depending on rigging size, is so conducive to reasonable Arrangement rigging, it is achieved the different tonnage box beam of lifting.
Fig. 4 to Fig. 6 illustrates the use procedure that balance hanging beam lifts. As shown in Figures 4 to 6, the dimensions of steel bridge box beam 6 according to required lifting, weight select suitable shackle 8, wire line thimble 71��73, according to steel bridge box beam dimensions, weight, balance hanging beam 5 selects suitable hanger, arrange shackle 8, wire line thimble 71��73. Then adopt with hanging device single hook or double hook to be connected, lift steel bridge box beam 6.
Thering is provided of this disclosure being previously described is for making any person skilled in the art all can make or use the disclosure. Various amendment of this disclosure all will be apparent from for a person skilled in the art, and the generic principles defined herein can be applied to other variants spirit or scope without departing from the disclosure. Thus, the disclosure is not intended to be limited to example described herein and design, but with disclosed herein principle and novel features consistent the widest scope should be awarded.
Claims (6)
1. the balance hanging beam being used for lifting steel bridge box beam, it is characterised in that described balance hanging beam is made up of two balance hanging beam single-pieces, is wherein welded to connect between two balance hanging beam single-pieces.
2. the balance hanging beam for lifting steel bridge box beam according to claim 1, it is characterised in that be welded by four stay tubes and gusset plate between described two balance hanging beam single-pieces.
3. the balance hanging beam for lifting steel bridge box beam according to claim 2, it is characterised in that described four stay tubes are square tubes.
4. the balance hanging beam for lifting steel bridge box beam according to claim 2, it is characterized in that, in described four stay tubes two are perpendicular to the direction of described balance hanging beam single-piece and place, all the other two intersections in described four stay tubes are placed, and weld each through described gusset plate on the cross point of two stay tubes that intersection is placed and with the joining place of described balance hanging beam.
5. the balance hanging beam for lifting steel bridge box beam according to claim 1, it is characterised in that the top and bottom of described two balance hanging beam single-pieces are equipped with at least one hanger.
6. the balance hanging beam for lifting steel bridge box beam according to claim 5, it is characterised in that the size of described hanger is depending on rigging size.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610192556.4A CN105645249B (en) | 2016-03-30 | 2016-03-30 | A kind of balance hanging beam for being used to lift steel bridge box beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610192556.4A CN105645249B (en) | 2016-03-30 | 2016-03-30 | A kind of balance hanging beam for being used to lift steel bridge box beam |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105645249A true CN105645249A (en) | 2016-06-08 |
CN105645249B CN105645249B (en) | 2017-12-12 |
Family
ID=56496551
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610192556.4A Active CN105645249B (en) | 2016-03-30 | 2016-03-30 | A kind of balance hanging beam for being used to lift steel bridge box beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105645249B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108423534A (en) * | 2017-02-14 | 2018-08-21 | 江西昌河航空工业有限公司 | A kind of automobile lifting device and its method |
CN109052154A (en) * | 2018-09-28 | 2018-12-21 | 中石化重型起重运输工程有限责任公司 | A kind of hydraulic self-adjustable lifting balance fine strain of millet |
CN111877167A (en) * | 2020-07-16 | 2020-11-03 | 中国一冶集团有限公司 | Installation and construction method for curved variable cross-section fish-bellied steel box girder bottom plate |
CN112875538A (en) * | 2021-01-05 | 2021-06-01 | 上海市机械施工集团有限公司 | Prefabricated assembly type overhead box girder hoisting process |
CN113071984A (en) * | 2021-04-27 | 2021-07-06 | 中国铁建重工集团股份有限公司 | Hoisting device and hoisting method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201439475U (en) * | 2009-08-11 | 2010-04-21 | 渤海船舶重工有限责任公司 | Multifunctional balance hanging beam |
CN202704795U (en) * | 2012-06-28 | 2013-01-30 | 上海宝冶集团有限公司 | Lifting tool for large equipment |
JP2013028419A (en) * | 2011-07-27 | 2013-02-07 | Wakachiku Construction Co Ltd | Lifting tool of concrete block |
CN203128002U (en) * | 2012-12-19 | 2013-08-14 | 中国核工业第五建设有限公司 | Hanger system for nuclear power equipment and pipeline module |
CN103318747A (en) * | 2012-11-03 | 2013-09-25 | 芜湖合建路桥机械有限公司 | Damage prevention hoisting equipment used for deflecting weight |
CN203781656U (en) * | 2014-01-09 | 2014-08-20 | 无锡沃特力材料科技有限公司 | Lifting appliance beam structure of crane |
CN205634613U (en) * | 2016-03-30 | 2016-10-12 | 上海振华重工(集团)股份有限公司 | A balanced hanging beam for hoisting steel bridge box girder |
-
2016
- 2016-03-30 CN CN201610192556.4A patent/CN105645249B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201439475U (en) * | 2009-08-11 | 2010-04-21 | 渤海船舶重工有限责任公司 | Multifunctional balance hanging beam |
JP2013028419A (en) * | 2011-07-27 | 2013-02-07 | Wakachiku Construction Co Ltd | Lifting tool of concrete block |
CN202704795U (en) * | 2012-06-28 | 2013-01-30 | 上海宝冶集团有限公司 | Lifting tool for large equipment |
CN103318747A (en) * | 2012-11-03 | 2013-09-25 | 芜湖合建路桥机械有限公司 | Damage prevention hoisting equipment used for deflecting weight |
CN203128002U (en) * | 2012-12-19 | 2013-08-14 | 中国核工业第五建设有限公司 | Hanger system for nuclear power equipment and pipeline module |
CN203781656U (en) * | 2014-01-09 | 2014-08-20 | 无锡沃特力材料科技有限公司 | Lifting appliance beam structure of crane |
CN205634613U (en) * | 2016-03-30 | 2016-10-12 | 上海振华重工(集团)股份有限公司 | A balanced hanging beam for hoisting steel bridge box girder |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108423534A (en) * | 2017-02-14 | 2018-08-21 | 江西昌河航空工业有限公司 | A kind of automobile lifting device and its method |
CN109052154A (en) * | 2018-09-28 | 2018-12-21 | 中石化重型起重运输工程有限责任公司 | A kind of hydraulic self-adjustable lifting balance fine strain of millet |
CN111877167A (en) * | 2020-07-16 | 2020-11-03 | 中国一冶集团有限公司 | Installation and construction method for curved variable cross-section fish-bellied steel box girder bottom plate |
CN112875538A (en) * | 2021-01-05 | 2021-06-01 | 上海市机械施工集团有限公司 | Prefabricated assembly type overhead box girder hoisting process |
CN112875538B (en) * | 2021-01-05 | 2022-05-24 | 上海市机械施工集团有限公司 | Prefabricated overhead box girder hoisting process |
CN113071984A (en) * | 2021-04-27 | 2021-07-06 | 中国铁建重工集团股份有限公司 | Hoisting device and hoisting method |
Also Published As
Publication number | Publication date |
---|---|
CN105645249B (en) | 2017-12-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105645249A (en) | Balance crane used for hoisting box girders of steel bridge | |
CN101830392B (en) | Special lifting tool for steel containment vessel of nuclear power station and lifting method | |
CN202080812U (en) | Dedicated sling system for large-scaled reinforcing cage | |
CN201882763U (en) | Special carrying pole type beam of double-machine lifting crane | |
CN106744257A (en) | A kind of method of kiloton adjustable combined sling, assemble method and lifting caisson | |
CN103241644A (en) | Assembly method of large-scale thin-wall steel containment vessel and auxiliary hoisting pieces | |
CN205634613U (en) | A balanced hanging beam for hoisting steel bridge box girder | |
CN206872270U (en) | A kind of device of across the railway cluster lifting of large-tonnage railway single freely-supported trough girder | |
CN205973410U (en) | Special cross hanging beam structure of reactor core shell hoist and mount | |
CN206088728U (en) | Novel large -scale gallows of taking a trial run | |
CN205802749U (en) | Heap core shell upper backup pad lifts special 3 hanging beam structures | |
CN103086254B (en) | Crawler crane combined lifting appliance | |
CN208980155U (en) | A kind of suspender of mill housing installation | |
CN209555867U (en) | A kind of pile cover bed die support construction of monoblock type installation | |
CN216971705U (en) | Steel box girder sling | |
CN203095397U (en) | Trial run cradle of heavy-duty crane | |
CN206735623U (en) | Framework of steel reinforcement hanging apparatus | |
CN205662256U (en) | High rises pergola side and hangs a semi -portal bridge crane | |
CN206142648U (en) | Supplementary support body of heavy panel hoist and mount | |
CN203199869U (en) | Combined lifting tool of crawler crane | |
CN210655872U (en) | Suspension hook swinging limiting device of crane | |
CN202558449U (en) | Lifting appliance for vertical lifting of rolling mill memorial archway | |
CN105398934B (en) | A kind of large-scale test run hanger for container counterweight | |
CN206751238U (en) | A kind of hoist base fixing device | |
CN205222430U (en) | A large -scale gallows of taking a trial run for container counter weight |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||