CN105484732B CN201510995039.6A CN201510995039A CN105484732B CN 105484732 B CN105484732 B CN 105484732B CN 201510995039 A CN201510995039 A CN 201510995039A CN 105484732 B CN105484732 B CN 105484732B
Authority
CN
China
Prior art keywords
well depth
value
parameter
well
depth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510995039.6A
Other languages
Chinese (zh)
Other versions
CN105484732A (en
Inventor
陆永钢
李�荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Shen Kai Petroleum Measurement and Control Technology Co., Ltd.
Shanghai SK Petroleum Chemical Equipment Corp Ltd
Shanghai SK Petroleum Equipment Co Ltd
Shanghai SK Petroleum Technology Co Ltd
Original Assignee
Shanghai SK Petroleum Chemical Equipment Corp Ltd
Shanghai SK Petroleum Equipment Co Ltd
Shanghai SK Petroleum Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai SK Petroleum Chemical Equipment Corp Ltd, Shanghai SK Petroleum Equipment Co Ltd, Shanghai SK Petroleum Technology Co Ltd filed Critical Shanghai SK Petroleum Chemical Equipment Corp Ltd
Priority to CN201510995039.6A priority Critical patent/CN105484732B/en
Publication of CN105484732A publication Critical patent/CN105484732A/en
Application granted granted Critical
Publication of CN105484732B publication Critical patent/CN105484732B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/02Determining slope or direction
    • E21B47/022Determining slope or direction of the borehole, e.g. using geomagnetism
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/04Measuring depth or liquid level

Landscapes

  • Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Geophysics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geophysics And Detection Of Objects (AREA)

Abstract

The invention discloses a kind of processing methods for horizontal well drilling geosteering work progress well depth, including:S1, setting carry out track according to current well depth data and draw required depth interval;S2 acquires current well depth data based on depth interval, and obtains parameter value and initial parameter well depth survey value corresponding with parameter value;S3, by initial parameter well depth survey value and current well depth data one by one compared with, determine the corresponding actual parameter well depth survey value of parameter value;S4, integration parameters value and actual parameter well depth survey value.For the present invention based on the current well depth that logging is measured, depth interval of the parameters such as gas survey, hole deviation, orientation, gamma, resistivity according to corresponding well depth survey value and setting carries out the integration of data point;Realize the accurate Drawing of well track.

Description

Processing method for horizontal well drilling geosteering work progress well depth
Technical field
The present invention relates to oil-gas exploration and development horizontal well drilling construction fields, more particularly to one kind for horizontal well drilling Matter is oriented to the processing method of work progress well depth.
Background technology
In the drilling process in oil-gas exploration and development field, using the more and more of horizontal well drilling construction method.Geology The engineering parameter values such as when guiding is the Gas Logging Values such as the total hydrocarbon acquired by compound logging during horizontal well drilling, methane, brill, The parameter values such as hole deviation, orientation, gamma, the resistivity of measurement while drilling acquisition, carry out hole trajectory control on the basis of well depth, it is ensured that Well track utmostly operates in destination layer.
Patent CN103046868A《A kind of horizontal well integration geosteering method》Describe a kind of horizontal well integration Geology guiding method establishes subtle three-dimensional geological model, in drilling well before brill using existing geology, well logging, well logging, state properties It is analyzed in the process with the data of brill, well logging by synchronous acquisition, and then controls track, pass through geosteering integrated software System platform realizes scene and remote visualization geosteering.
Patent CN102913237A《Measurement while drilling parameter and logging parameters Integral synchronous integrated conduct method》It describes Measurement while drilling parameter and logging parameters Integral synchronous integrated conduct method, the real time data to measurement while-drilling instrument and comprehensive record After carrying out anomaly parameter value processing respectively, data synchronization processing is carried out based on the identical condition of well depth for the real time data of well instrument.
Integrated application multiple parameters are needed in geosteering, and parameters are from different sensors, measured value Respective well depth value is corresponded to respectively;And well depth and its corresponding hole deviation, orientation values are the basic values that track is drawn.Due to record Well and measurement while drilling are two kinds of measurement method, and the sample frequency difference of valid data is larger;Each item data well depth is complete Identical data point is relatively fewer, to affect making full use of for data, and then influences accurately controlling for track.
Invention content
The object of the present invention is to provide a kind of processing method for horizontal well drilling geosteering work progress well depth, with Based on the current well depth that logging is measured, the parameters such as gas survey, hole deviation, orientation, gamma, resistivity are according to corresponding well depth survey The depth interval of value and setting, carries out the integration of data point;Realize the accurate Drawing of well track.
In order to achieve the goal above, the present invention is achieved by the following technical solutions:
A kind of processing method for horizontal well drilling geosteering work progress well depth, its main feature is that, including:
S1, setting carry out track according to current well depth data and draw required depth interval;
S2 acquires current well depth data based on the depth interval, and obtains parameter value and corresponding with parameter value Initial parameter well depth survey value;
S3, by the initial parameter well depth survey value and current well depth data one by one compared with, determine the parameter value Corresponding actual parameter well depth survey value;
S4, integration parameters value and actual parameter well depth survey value.
The step S2 includes specifically:
S2.1 acquires current well depth data based on the depth interval by logging, and the current well depth data is set It is i-th of current well depth data for D1, D2 ... Di ... Dn, wherein Di;
S2.2 acquires current well depth data based on the depth interval, obtains parameter value and corresponding with parameter value Initial parameter well depth survey value, the initial parameter well depth survey value is set as S1, at the beginning of S2 ... Sj ... Sn, wherein Sj are j-th Beginning parameter well depth measured value.
The step S3 is specially:By the initial parameter well depth survey value and current well depth data one by one compared with, As Sj >=Di, and when Sj < Di+1, the corresponding actual parameter well depth survey value of the parameter value is Di.
Also include after the step S4:
S5 checks whether there is corresponding parameter value, with previous if not since first current well depth data point Currently the corresponding parameter value of well depth data point is supplemented.
The parameter value includes one or more of Gas Logging Value, hole deviation, orientation, gamma or resistivity.
The depth interval is 0.1m ~ 30m.
Compared with prior art, the present invention haing the following advantages:
The present invention based on the current well depth that logging is measured, the parameters such as gas survey, hole deviation, orientation, gamma, resistivity according to According to the depth interval of corresponding well depth survey value and setting, the integration of data point is carried out;Realize the accurate Drawing of well track.
Description of the drawings
Fig. 1 is a kind of flow chart of processing method for horizontal well drilling geosteering work progress well depth of the invention.
Specific implementation mode
The present invention is further elaborated by the way that a preferable specific embodiment is described in detail below in conjunction with attached drawing.
As shown in Figure 1, a kind of processing method for horizontal well drilling geosteering work progress well depth, including:
S1, setting carry out track according to current well depth data and draw required depth interval, and depth interval is 0.1m ~ 30m;
S2 acquires current well depth data based on the depth interval, and obtains parameter value and corresponding with parameter value Initial parameter well depth survey value;
S3, by the initial parameter well depth survey value and current well depth data one by one compared with, determine the parameter value Corresponding actual parameter well depth survey value;
S4, integration parameters value and actual parameter well depth survey value.
Above-mentioned step S2 includes specifically:
S2.1 acquires current well depth data based on the depth interval by logging, and the current well depth data is set It is i-th of current well depth data for D1, D2 ... Di ... Dn, wherein Di;
S2.2 acquires current well depth data based on the depth interval, obtains parameter value and corresponding with parameter value Initial parameter well depth survey value, the initial parameter well depth survey value is set as S1, at the beginning of S2 ... Sj ... Sn, wherein Sj are j-th Beginning parameter well depth measured value.
Above-mentioned step S3 is specially:By the initial parameter well depth survey value and current well depth data one by one compared with, As Sj >=Di, and when Sj < Di+1, the corresponding actual parameter well depth survey value of the parameter value is Di.
Above-mentioned parameter value includes one or more of Gas Logging Value, hole deviation, orientation, gamma or resistivity.Wherein, gas is surveyed Value is the content of the gas components such as total hydrocarbon, methane, ethane, propane in the formation sample gas obtained measured by logging;Hole deviation, Orientation is:Well track location parameter at the measuring point obtained measured by steering tool;Gamma, resistivity are:Steering tool The parameter of stratum physical property is indicated at measured obtained measuring point.In the present embodiment, with sample frequency current well depth faster Based on;Gas Logging Value is based on late well depth survey value(It is that shaft bottom drilling strata substance returns to ground with drilling fluid that gas, which is surveyed, After measure, due to having the regular hour from shaft bottom back to ground, corresponding to well depth be less than currently practical brill and reach Well depth, i.e., late well depth), hole deviation, orientation, gamma, resistivity etc. are playbacked with parameter is bored with the measured value away from bit location It calculates.
Above-mentioned step S4 is specially:Gas survey, hole deviation, orientation, gamma, resistivity actual parameter well depth survey value is identical Point be attributed to same data point, the data point is by actual parameter well depth survey value, gas survey, hole deviation, orientation, gamma, resistivity Parameter forms, when drawing curve or data analysis, convenient for being compared under the conditions of same well depth.
In a particular embodiment, also include after above-mentioned step S4:
S5 checks whether there is corresponding parameter value, with previous if not since first current well depth data point Currently the corresponding parameter value of well depth data point is supplemented.
In conclusion a kind of processing method for horizontal well drilling geosteering work progress well depth of the invention, with record Based on the current well depth that well instrument is measured, the parameters such as gas survey, hole deviation, orientation, gamma, resistivity are according to corresponding well depth survey value With the depth interval of setting, the integration of data point is carried out;Realize the accurate Drawing of well track.
Although present disclosure is discussed in detail by above preferred embodiment, but it should be appreciated that above-mentioned Description is not considered as limitation of the present invention.After those skilled in the art have read the above, for the present invention's A variety of modifications and substitutions all will be apparent.Therefore, protection scope of the present invention should be limited to the appended claims.

Claims (4)

1. a kind of processing method for horizontal well drilling geosteering work progress well depth, which is characterized in that include:
S1, setting carry out track according to current well depth data and draw required depth interval;
S2 acquires current well depth data based on the depth interval, and obtains parameter value and corresponding with parameter value initial Parameter well depth measured value;
S3, by the initial parameter well depth survey value and current well depth data one by one compared with, determine that the parameter value corresponds to Actual parameter well depth survey value;
S4, integration parameters value and actual parameter well depth survey value;
The step S2 includes specifically:
S2.1 acquires current well depth data based on the depth interval by logging, and the current well depth data is set as D1, D2 ... Di ... Dn, wherein Di are i-th of current well depth data;
S2.2 acquires current well depth data based on the depth interval, obtains parameter value and corresponding with parameter value initial Parameter well depth measured value, the initial parameter well depth survey value are set as S1, and S2 ... Sj ... Sn, wherein Sj are j-th of initial ginseng Number well depth survey value;
The step S3 is specially:By the initial parameter well depth survey value and current well depth data one by one compared with, work as Sj >=Di, and when Sj < Di+1, the corresponding actual parameter well depth survey value of the parameter value is Di.
2. being used for the processing method of horizontal well drilling geosteering work progress well depth as described in claim 1, feature exists In also including after the step S4:
S5 checks whether there is corresponding parameter value since first current well depth data point, with previous current if not The corresponding parameter value of well depth data point is supplemented.
3. being used for the processing method of horizontal well drilling geosteering work progress well depth as described in claim 1, feature exists In the parameter value includes one or more of Gas Logging Value, hole deviation, orientation, gamma or resistivity.
4. being used for the processing method of horizontal well drilling geosteering work progress well depth as described in claim 1, feature exists In the depth interval is 0.1m ~ 30m.
CN201510995039.6A 2015-12-28 2015-12-28 Processing method for horizontal well drilling geosteering work progress well depth Active CN105484732B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510995039.6A CN105484732B (en) 2015-12-28 2015-12-28 Processing method for horizontal well drilling geosteering work progress well depth

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510995039.6A CN105484732B (en) 2015-12-28 2015-12-28 Processing method for horizontal well drilling geosteering work progress well depth

Publications (2)

Publication Number Publication Date
CN105484732A CN105484732A (en) 2016-04-13
CN105484732B true CN105484732B (en) 2018-10-12

Family

ID=55671977

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510995039.6A Active CN105484732B (en) 2015-12-28 2015-12-28 Processing method for horizontal well drilling geosteering work progress well depth

Country Status (1)

Country Link
CN (1) CN105484732B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482596B (en) * 2021-08-11 2023-09-15 江苏达坦智慧能源有限公司 Real-time three-dimensional gamma imaging data processing method based on LWD while-drilling instrument

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5019978A (en) * 1988-09-01 1991-05-28 Schlumberger Technology Corporation Depth determination system utilizing parameter estimation for a downhole well logging apparatus
WO2012173601A1 (en) * 2011-06-14 2012-12-20 Halliburton Energy Services, Inc. System, method, and computer program for predicting borehole geometry
CN102996114A (en) * 2011-09-14 2013-03-27 王维 Inclined hole correction method of logging information
CN102518433B (en) * 2011-12-31 2015-07-08 中国石油天然气股份有限公司 Target point adjusting method for horizontal well of thin carbonate reservoir
CN102913237B (en) * 2012-10-31 2015-12-16 中国石油集团川庆钻探工程有限公司 Integrated synchronous comprehensive processing method for measurement while drilling parameters and logging parameters
CN103046868B (en) * 2012-12-28 2014-10-22 中国石油集团川庆钻探工程有限公司 Integrated geosteering method for horizontal well
CN104121009B (en) * 2013-04-26 2017-02-01 中国石油天然气股份有限公司 Method and system for generating temperature and pressure curves
CN104481400B (en) * 2014-12-10 2016-08-10 中国石油化工股份有限公司 A kind of three-dimensional horizontal well track control method
CN104832161B (en) * 2015-04-20 2017-12-29 长江大学 Automatic depth bearing calibration and system based on double yardstick relevant comparatives
CN105156097A (en) * 2015-07-06 2015-12-16 中煤科工集团西安研究院有限公司 Method for processing hole drilling track measurement data

Also Published As

Publication number Publication date
CN105484732A (en) 2016-04-13

Similar Documents

Publication Publication Date Title
CN102031964B (en) Measured value is answered to extract the multi-stage process flow and method of resistivity anisotropy data from three-dimensional sense
US9678240B2 (en) Detecting boundary locations of multiple subsurface layers
CN105317431B (en) A method of for explaining and evaluating horizontal wellbore logging parameter
US8599643B2 (en) Joint structural dip removal
EP2895950B1 (en) System, method and computer program product for a rug plot for geosteering applications
EP2877690B1 (en) Methods and systems for borehole image forward modeling of formation properties
CN106894761B (en) Utilize the geosteering method of the geosteering model of time-domain seismic volume
CA2890150C (en) Passive magnetic ranging for sagd and relief wells via a linearized trailing window kalman filter
CN107784159B (en) Method for determining anisotropic coefficient of reservoir resistivity
CN104265279B (en) Logging-while-drilling curve prediction method under fault condition
CN103590828B (en) Method for evaluating formation pressure by logging dck index method
WO2018075007A1 (en) Improved mcilogging for processing downhole measurements
CN103790579B (en) Method and device for determining distance between drill bit and stratum interface in while-drilling geological steering
GB2476153A (en) Phase wellbore steering
CN104153768A (en) Granite reservoir stratum reservoir performance evaluation method
US11008835B2 (en) Horizontal reservoir description systems
CN108019207A (en) A kind of measuring method of SYMMETRIC ELECTROMAGNETIC ripple resistivity
CN105484732B (en) Processing method for horizontal well drilling geosteering work progress well depth
CA3017733C (en) Multipoint measurements for wellbore ranging
US11249218B2 (en) Horizontal reservoir description systems
CN105464650A (en) Interpretation method for well logging during drilling
NO346996B1 (en) Integrated well survey management and planning tool
US11592588B2 (en) Data interpretation quality control using data stacking
CN110454155A (en) A Method for Determining Quaternary Stratigraphic Age Using Magnetic Susceptibility Logging
CA2967266C (en) Attirbute-indexed multi-instrument logging of drill cuttings

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190315

Address after: Two Blocks 1769 Puxing Highway, Minhang District, Shanghai, 20114

Co-patentee after: Shanghai Shenkai Petroleum Equipment Co., Ltd.

Patentee after: Shanghai Shen Kai Petroleum Measurement and Control Technology Co., Ltd.

Co-patentee after: Shanghai Shenkai Petroleum & Chemical Equipment Corporation Ltd.

Co-patentee after: Shanghai Shenkai Petroleum Sci-Tech Co., Ltd.

Address before: 201114, Shanghai, Minhang District Pu Xing Road No. 1769

Co-patentee before: Shanghai Shenkai Petroleum & Chemical Equipment Corporation Ltd.

Patentee before: Shanghai Shenkai Petroleum Equipment Co., Ltd.

Co-patentee before: Shanghai Shenkai Petroleum Sci-Tech Co., Ltd.

TR01 Transfer of patent right