[go: up one dir, main page]

CN105350782A - Semi-mechanized steel strand laying method for circular silo - Google Patents

Semi-mechanized steel strand laying method for circular silo Download PDF

Info

Publication number
CN105350782A
CN105350782A CN201510687262.4A CN201510687262A CN105350782A CN 105350782 A CN105350782 A CN 105350782A CN 201510687262 A CN201510687262 A CN 201510687262A CN 105350782 A CN105350782 A CN 105350782A
Authority
CN
China
Prior art keywords
steel strand
steel
hoist engine
wire rope
semi
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510687262.4A
Other languages
Chinese (zh)
Other versions
CN105350782B (en
Inventor
吴建国
田永伟
张煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201510687262.4A priority Critical patent/CN105350782B/en
Publication of CN105350782A publication Critical patent/CN105350782A/en
Application granted granted Critical
Publication of CN105350782B publication Critical patent/CN105350782B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)

Abstract

The invention discloses a semi-mechanized steel strand laying method for a circular silo. The method comprises following steps: S1, refitting and reinforcing a slip-form platform frame; S2, installing winches; S3, installing cylinder wall steel strand fixing frames and performing alignment; S4, making steel wire ropes on the winches pre-pass through the steel strand fixing frames; S5, connecting the steel strands and the steel wire ropes; S6, retracting the steel wire ropes through the winches, manually making the steel strands be in place through a fine tuning manner, disconnecting the steel wire ropes and the steel strands, and fastening the steel strands and the steel strand fixing frames through fastening wires. By employing the laying method, the steel strands can be laid in a semi-mechanized manner through the winches, problems that the labor intensity of steel strand laying workers is large and the laying progress is slow during the slip-form construction are solved, the selected devices are economical and reasonable, the construction cost is reduced, and the operation time is saved.

Description

A kind of semi-mechanization steel strand laying method for round silo
Technical field
The present invention relates to steel strand and lay field, specifically relate to a kind of semi-mechanization steel strand laying method for round silo.
Background technology
At present, steel strand construction generally adopts artificial laying in the industry, and when steel strand are laid, front needs a people to adjust steel strand and wears direction, and rear personnel hold steel strand pushed forward with hand-tight.This construction method not only labor intensive, for 30m diameter silo, per tour steel strand are laid at least needs 12 workmans not stop operation; And be difficult to when large silo of constructing, steel strand are arranged intensive ensure that steel strand laying progress meets the construction speed of barrel, often occur to lay because of steel strand to occur the situations such as the work holdup not in time.And adopt semimechanized laying laying method, the labour intensity of operating personnel can be greatly reduced, improve the laying efficiency of steel strand; And utilize semi-automatic steel strand laying apparatus, decrease operating personnel, reduce the load of slip form platform during silo construction, improve the safety of slip form platform, the risk that reduction accident greatly occurs.
Summary of the invention
For the technical problem existed in prior art, the object of the present invention is to provide a kind of semi-mechanization steel strand laying method for round silo.
To achieve these goals, the technical solution adopted in the present invention is: a kind of semi-mechanization steel strand laying method for round silo, comprises the following steps:
S1, slip form platform support body are reequiped:
In the some steel strand tip position near barrel place, selected hoist engine installation site, carries out repacking to the slip form platform support body of installation site and reinforces;
S2, hoist engine are installed:
Slip form platform support body after repacking is reinforced installs hoist engine, and the stability of hoist engine must meet the dilatory work of follow-up steel strand;
S3, barrel steel strand fixed mount are installed, centering:
First steel strand on the estimation need the track laid to install some steel strand fixed mounts, and utilize steel strand fixed mount to replace the vertical distributing bar of part barrel;
Wearing in advance of S4, steel wire rope of windlass:
By the steel strand fixed mount of the cable wire end on hoist engine through round silo, until steel strand tip position;
The connection of S5, steel strand and wire rope:
Utilize steel cable clamp, by parallel with steel strand termination for cable wire end connection, the rubber pad that buckle and steel strand contact position pad prevent steel strand in pulling to be damaged;
S6, regain wire rope with hoist engine, artificial fine setting is in place to steel strand, unties the connection between wire rope and steel strand, steel strand and steel strand fixed mount tied silk is tightened.
Beneficial effect of the present invention shows:
The laying method that the present invention proposes utilizes hoist engine to achieve the object of semi-mechanization laying steel strand, solve the steel strand when slding form operation and lay the problem that operating personnel consumes greatly, progress is slow, the device economical rationality of selecting, reduces construction cost, has saved operation holding time.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of step S4.
Fig. 2 is the schematic diagram of step S5.
Detailed description of the invention
For further describing the present invention, below in conjunction with embodiment, it is described further.
For a semi-mechanization steel strand laying method for round silo, comprise the following steps:
S1, slip form platform support body 1 are reequiped:
In some steel strand 2 tip position near barrel place, selected hoist engine 3 installation site, carries out repacking to the slip form platform support body 1 of installation site and reinforces.
S2, hoist engine 3 are installed:
Slip form platform support body 1 after repacking is reinforced installs hoist engine 3, and the stability of hoist engine 3 must meet the dilatory work of follow-up steel strand 2.
S3, barrel steel strand fixed mount 4 are installed, centering:
First steel strand 2 on the estimation need the track laid to install some steel strand fixed mounts 4, and utilize steel strand fixed mount 4 to replace the vertical distributing bar of part barrel.
Wearing in advance of S4, hoist engine 3 wire rope 5:
As Fig. 1, by the steel strand fixed mount 4 of wire rope 5 fag end on hoist engine 3 through round silo, until steel strand 2 tip position.
The connection of S5, steel strand 2 and wire rope 5:
As Fig. 2, utilize steel cable clamp 6, by wire rope 5 fag end and the parallel connection in steel strand 2 termination, the rubber pad 7 that buckle 6 and steel strand 2 contact position pad prevent steel strand in pulling to be damaged.
S6, regain wire rope 5 with hoist engine 3, artificial fine setting is in place to steel strand 2, unties the connection between wire rope 5 and steel strand 2, steel strand 2 and steel strand fixed mount 4 is tightened by tied silk.
The present invention proposes a kind of semi-mechanization steel strand laying method for round silo, principle of the present invention is exactly that former should utilization is laid steel strand personnel thrust in the wings and changed into hoist engine 3 and tighten up wire rope 5 in front and the pulling force that brings steel strand 2; Hoist engine 3 should slowly tighten up; When tightening up, steel strand 2 are other establishes operating personnel to guard, and prevents steel strand 2 from causing damage with steel strand fixed mount 4 is stuck, and after steel strand 2 are in place, personnel remove steel strand 2 and the connection of wire rope 5 immediately, steel strand 2 and steel strand fixed mount 4 are tightened by tied silk.
Above content is only to design example of the present invention and explanation; affiliated those skilled in the art make various amendment to described specific embodiment or supplement or adopt similar mode to substitute; only otherwise depart from the design of invention or surmount this scope as defined in the claims, protection scope of the present invention all should be belonged to.

Claims (1)

1., for a semi-mechanization steel strand laying method for round silo, it is characterized in that, comprise the following steps:
S1, slip form platform support body (1) are reequiped:
In some steel strand (2) tip position near barrel place, selected hoist engine (3) installation site, carries out repacking to the slip form platform support body (1) of installation site and reinforces;
S2, hoist engine (3) are installed:
Slip form platform support body (1) after repacking is reinforced installs hoist engine (3), and the stability of hoist engine (3) must meet the dilatory work of follow-up steel strand (2);
S3, barrel steel strand fixed mount (4) are installed, centering:
First steel strand (2) on the estimation need the track laid to install some steel strand fixed mounts (4), and utilize steel strand fixed mount (4) to replace the vertical distributing bar of part barrel;
S4, the wearing in advance of hoist engine (3) wire rope (5):
By the steel strand fixed mount (4) of wire rope (5) fag end on hoist engine (3) through round silo, until steel strand (2) tip position;
The connection of S5, steel strand (2) and wire rope (5):
Utilize steel cable clamp (6), by wire rope (5) fag end and the parallel connection in steel strand (2) termination, the rubber pad (7) that buckle (6) and steel strand (2) contact position pad prevent steel strand in pulling to be damaged;
S6, regain wire rope (5) with hoist engine (3), artificial fine setting is in place to steel strand (2), unties the connection between wire rope (5) and steel strand (2), steel strand (2) and steel strand fixed mount (4) is tightened by tied silk.
CN201510687262.4A 2015-10-22 2015-10-22 A kind of semi-mechanization steel strand wires laying method for round silo Active CN105350782B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510687262.4A CN105350782B (en) 2015-10-22 2015-10-22 A kind of semi-mechanization steel strand wires laying method for round silo

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510687262.4A CN105350782B (en) 2015-10-22 2015-10-22 A kind of semi-mechanization steel strand wires laying method for round silo

Publications (2)

Publication Number Publication Date
CN105350782A true CN105350782A (en) 2016-02-24
CN105350782B CN105350782B (en) 2017-12-05

Family

ID=55326830

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510687262.4A Active CN105350782B (en) 2015-10-22 2015-10-22 A kind of semi-mechanization steel strand wires laying method for round silo

Country Status (1)

Country Link
CN (1) CN105350782B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112267688A (en) * 2020-11-24 2021-01-26 江苏新筑同创土木工程有限公司 Mechanical auxiliary penetrating method and system for annular unbonded prestressed tendon
CN115538704A (en) * 2022-09-19 2022-12-30 天津熙贝众合预应力工程有限公司 An installation process of unbonded prestressed steel strands for large-diameter silos with slipform construction
CN117605286A (en) * 2024-01-23 2024-02-27 中国电建集团山东电力建设第一工程有限公司 Wind power mixing tower prestress steel strand threading tool and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561706A (en) * 2012-03-19 2012-07-11 中冶天工集团有限公司 Internal threading method for spatial large-span prestressed steel structure steel strand
CN102635238A (en) * 2012-05-03 2012-08-15 中国十九冶集团有限公司 Large-scale coal bunker wall prestress anchor sealing construction method and structure
CN103669214A (en) * 2013-11-19 2014-03-26 中建三局建设工程股份有限公司 Superlong prestress strand combing, binding and strand pulling integrated device
JP2015101867A (en) * 2013-11-22 2015-06-04 株式会社竹中工務店 Manufacturing method for exterior panel unit
CN204475874U (en) * 2015-03-13 2015-07-15 中国土木工程集团有限公司 A kind of novel pre-stressed steel strand draw-gear

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561706A (en) * 2012-03-19 2012-07-11 中冶天工集团有限公司 Internal threading method for spatial large-span prestressed steel structure steel strand
CN102635238A (en) * 2012-05-03 2012-08-15 中国十九冶集团有限公司 Large-scale coal bunker wall prestress anchor sealing construction method and structure
CN103669214A (en) * 2013-11-19 2014-03-26 中建三局建设工程股份有限公司 Superlong prestress strand combing, binding and strand pulling integrated device
JP2015101867A (en) * 2013-11-22 2015-06-04 株式会社竹中工務店 Manufacturing method for exterior panel unit
CN204475874U (en) * 2015-03-13 2015-07-15 中国土木工程集团有限公司 A kind of novel pre-stressed steel strand draw-gear

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
韩斯明: "储配仓混凝土结构中无粘结预应力施工技术", 《安徽建筑》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112267688A (en) * 2020-11-24 2021-01-26 江苏新筑同创土木工程有限公司 Mechanical auxiliary penetrating method and system for annular unbonded prestressed tendon
CN115538704A (en) * 2022-09-19 2022-12-30 天津熙贝众合预应力工程有限公司 An installation process of unbonded prestressed steel strands for large-diameter silos with slipform construction
CN117605286A (en) * 2024-01-23 2024-02-27 中国电建集团山东电力建设第一工程有限公司 Wind power mixing tower prestress steel strand threading tool and method

Also Published As

Publication number Publication date
CN105350782B (en) 2017-12-05

Similar Documents

Publication Publication Date Title
CN102444086B (en) Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge
CN101967796B (en) Method for arranging parallel steel wire stay cable
CN103441451B (en) A kind of overhead transmission line crosses over wire laying device
CN104631329B (en) A kind of suspension bridge continuous way cat road integral linear method of adjustment
CN105350782A (en) Semi-mechanized steel strand laying method for circular silo
CN109973130B (en) Construction system and method for realizing one-time traction of extra-long tunnel anchor narrow space by main cable strand
CN210003305U (en) Construction system for achieving traction in place in narrow anchor space of ultra-long tunnel in modes
CN106401196A (en) Steel strand tensioning device for pre-stressed anchorage device
CN102659043B (en) Improved dismounting device for buttress rod of tower crane
CN105507149A (en) Arrangement method for cable-hanging of single parallel steel strand wires
CN103708371B (en) The Huan Sheng mechanism that rope drives
CN202412091U (en) Fixing and clamping device used in installation and vulcanization of adhesive tape
CN201171147Y (en) Clamp for vertically mounting ultra-high layer cable
CN204199734U (en) A kind of safe blanket net of automatic control movement
CN208416535U (en) A kind of coal-cutting machine towline protecting apparatus
CN107268439B (en) It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture
CN107313786B (en) Trolley trailer system
CN214660350U (en) Split initial tunneling pipeline extension supporting device of shield tunneling machine
CN104505771A (en) Overhead ground wire lifter
CN203602263U (en) Engineering machine and amplitude-variable pulley block fixing device
CN103708370B (en) The pneumatic lift rope supporting device of mining inclined tunnel
CN210238255U (en) Pushing construction anti-slip reverse-pulling device
CN209818062U (en) Cable dragging device of tunneling machine
CN207896560U (en) A kind of skyscraper cable-laying gear
CN205202161U (en) Rubber belt conveyor primer area laying apparatus

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant