CN105350782A - Semi-mechanized steel strand laying method for circular silo - Google Patents
Semi-mechanized steel strand laying method for circular silo Download PDFInfo
- Publication number
- CN105350782A CN105350782A CN201510687262.4A CN201510687262A CN105350782A CN 105350782 A CN105350782 A CN 105350782A CN 201510687262 A CN201510687262 A CN 201510687262A CN 105350782 A CN105350782 A CN 105350782A
- Authority
- CN
- China
- Prior art keywords
- steel strand
- steel
- hoist engine
- wire rope
- semi
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 96
- 239000010959 steel Substances 0.000 title claims abstract description 96
- 238000000034 method Methods 0.000 title claims abstract description 13
- 238000009434 installation Methods 0.000 claims description 6
- 238000012857 repacking Methods 0.000 claims description 6
- 230000000916 dilatatory effect Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 6
- 230000003014 reinforcing effect Effects 0.000 abstract 1
- 238000009751 slip forming Methods 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/12—Mounting of reinforcing inserts; Prestressing
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)
Abstract
The invention discloses a semi-mechanized steel strand laying method for a circular silo. The method comprises following steps: S1, refitting and reinforcing a slip-form platform frame; S2, installing winches; S3, installing cylinder wall steel strand fixing frames and performing alignment; S4, making steel wire ropes on the winches pre-pass through the steel strand fixing frames; S5, connecting the steel strands and the steel wire ropes; S6, retracting the steel wire ropes through the winches, manually making the steel strands be in place through a fine tuning manner, disconnecting the steel wire ropes and the steel strands, and fastening the steel strands and the steel strand fixing frames through fastening wires. By employing the laying method, the steel strands can be laid in a semi-mechanized manner through the winches, problems that the labor intensity of steel strand laying workers is large and the laying progress is slow during the slip-form construction are solved, the selected devices are economical and reasonable, the construction cost is reduced, and the operation time is saved.
Description
Technical field
The present invention relates to steel strand and lay field, specifically relate to a kind of semi-mechanization steel strand laying method for round silo.
Background technology
At present, steel strand construction generally adopts artificial laying in the industry, and when steel strand are laid, front needs a people to adjust steel strand and wears direction, and rear personnel hold steel strand pushed forward with hand-tight.This construction method not only labor intensive, for 30m diameter silo, per tour steel strand are laid at least needs 12 workmans not stop operation; And be difficult to when large silo of constructing, steel strand are arranged intensive ensure that steel strand laying progress meets the construction speed of barrel, often occur to lay because of steel strand to occur the situations such as the work holdup not in time.And adopt semimechanized laying laying method, the labour intensity of operating personnel can be greatly reduced, improve the laying efficiency of steel strand; And utilize semi-automatic steel strand laying apparatus, decrease operating personnel, reduce the load of slip form platform during silo construction, improve the safety of slip form platform, the risk that reduction accident greatly occurs.
Summary of the invention
For the technical problem existed in prior art, the object of the present invention is to provide a kind of semi-mechanization steel strand laying method for round silo.
To achieve these goals, the technical solution adopted in the present invention is: a kind of semi-mechanization steel strand laying method for round silo, comprises the following steps:
S1, slip form platform support body are reequiped:
In the some steel strand tip position near barrel place, selected hoist engine installation site, carries out repacking to the slip form platform support body of installation site and reinforces;
S2, hoist engine are installed:
Slip form platform support body after repacking is reinforced installs hoist engine, and the stability of hoist engine must meet the dilatory work of follow-up steel strand;
S3, barrel steel strand fixed mount are installed, centering:
First steel strand on the estimation need the track laid to install some steel strand fixed mounts, and utilize steel strand fixed mount to replace the vertical distributing bar of part barrel;
Wearing in advance of S4, steel wire rope of windlass:
By the steel strand fixed mount of the cable wire end on hoist engine through round silo, until steel strand tip position;
The connection of S5, steel strand and wire rope:
Utilize steel cable clamp, by parallel with steel strand termination for cable wire end connection, the rubber pad that buckle and steel strand contact position pad prevent steel strand in pulling to be damaged;
S6, regain wire rope with hoist engine, artificial fine setting is in place to steel strand, unties the connection between wire rope and steel strand, steel strand and steel strand fixed mount tied silk is tightened.
Beneficial effect of the present invention shows:
The laying method that the present invention proposes utilizes hoist engine to achieve the object of semi-mechanization laying steel strand, solve the steel strand when slding form operation and lay the problem that operating personnel consumes greatly, progress is slow, the device economical rationality of selecting, reduces construction cost, has saved operation holding time.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of step S4.
Fig. 2 is the schematic diagram of step S5.
Detailed description of the invention
For further describing the present invention, below in conjunction with embodiment, it is described further.
For a semi-mechanization steel strand laying method for round silo, comprise the following steps:
S1, slip form platform support body 1 are reequiped:
In some steel strand 2 tip position near barrel place, selected hoist engine 3 installation site, carries out repacking to the slip form platform support body 1 of installation site and reinforces.
S2, hoist engine 3 are installed:
Slip form platform support body 1 after repacking is reinforced installs hoist engine 3, and the stability of hoist engine 3 must meet the dilatory work of follow-up steel strand 2.
S3, barrel steel strand fixed mount 4 are installed, centering:
First steel strand 2 on the estimation need the track laid to install some steel strand fixed mounts 4, and utilize steel strand fixed mount 4 to replace the vertical distributing bar of part barrel.
Wearing in advance of S4, hoist engine 3 wire rope 5:
As Fig. 1, by the steel strand fixed mount 4 of wire rope 5 fag end on hoist engine 3 through round silo, until steel strand 2 tip position.
The connection of S5, steel strand 2 and wire rope 5:
As Fig. 2, utilize steel cable clamp 6, by wire rope 5 fag end and the parallel connection in steel strand 2 termination, the rubber pad 7 that buckle 6 and steel strand 2 contact position pad prevent steel strand in pulling to be damaged.
S6, regain wire rope 5 with hoist engine 3, artificial fine setting is in place to steel strand 2, unties the connection between wire rope 5 and steel strand 2, steel strand 2 and steel strand fixed mount 4 is tightened by tied silk.
The present invention proposes a kind of semi-mechanization steel strand laying method for round silo, principle of the present invention is exactly that former should utilization is laid steel strand personnel thrust in the wings and changed into hoist engine 3 and tighten up wire rope 5 in front and the pulling force that brings steel strand 2; Hoist engine 3 should slowly tighten up; When tightening up, steel strand 2 are other establishes operating personnel to guard, and prevents steel strand 2 from causing damage with steel strand fixed mount 4 is stuck, and after steel strand 2 are in place, personnel remove steel strand 2 and the connection of wire rope 5 immediately, steel strand 2 and steel strand fixed mount 4 are tightened by tied silk.
Above content is only to design example of the present invention and explanation; affiliated those skilled in the art make various amendment to described specific embodiment or supplement or adopt similar mode to substitute; only otherwise depart from the design of invention or surmount this scope as defined in the claims, protection scope of the present invention all should be belonged to.
Claims (1)
1., for a semi-mechanization steel strand laying method for round silo, it is characterized in that, comprise the following steps:
S1, slip form platform support body (1) are reequiped:
In some steel strand (2) tip position near barrel place, selected hoist engine (3) installation site, carries out repacking to the slip form platform support body (1) of installation site and reinforces;
S2, hoist engine (3) are installed:
Slip form platform support body (1) after repacking is reinforced installs hoist engine (3), and the stability of hoist engine (3) must meet the dilatory work of follow-up steel strand (2);
S3, barrel steel strand fixed mount (4) are installed, centering:
First steel strand (2) on the estimation need the track laid to install some steel strand fixed mounts (4), and utilize steel strand fixed mount (4) to replace the vertical distributing bar of part barrel;
S4, the wearing in advance of hoist engine (3) wire rope (5):
By the steel strand fixed mount (4) of wire rope (5) fag end on hoist engine (3) through round silo, until steel strand (2) tip position;
The connection of S5, steel strand (2) and wire rope (5):
Utilize steel cable clamp (6), by wire rope (5) fag end and the parallel connection in steel strand (2) termination, the rubber pad (7) that buckle (6) and steel strand (2) contact position pad prevent steel strand in pulling to be damaged;
S6, regain wire rope (5) with hoist engine (3), artificial fine setting is in place to steel strand (2), unties the connection between wire rope (5) and steel strand (2), steel strand (2) and steel strand fixed mount (4) is tightened by tied silk.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510687262.4A CN105350782B (en) | 2015-10-22 | 2015-10-22 | A kind of semi-mechanization steel strand wires laying method for round silo |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510687262.4A CN105350782B (en) | 2015-10-22 | 2015-10-22 | A kind of semi-mechanization steel strand wires laying method for round silo |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105350782A true CN105350782A (en) | 2016-02-24 |
CN105350782B CN105350782B (en) | 2017-12-05 |
Family
ID=55326830
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510687262.4A Active CN105350782B (en) | 2015-10-22 | 2015-10-22 | A kind of semi-mechanization steel strand wires laying method for round silo |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105350782B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112267688A (en) * | 2020-11-24 | 2021-01-26 | 江苏新筑同创土木工程有限公司 | Mechanical auxiliary penetrating method and system for annular unbonded prestressed tendon |
CN115538704A (en) * | 2022-09-19 | 2022-12-30 | 天津熙贝众合预应力工程有限公司 | An installation process of unbonded prestressed steel strands for large-diameter silos with slipform construction |
CN117605286A (en) * | 2024-01-23 | 2024-02-27 | 中国电建集团山东电力建设第一工程有限公司 | Wind power mixing tower prestress steel strand threading tool and method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561706A (en) * | 2012-03-19 | 2012-07-11 | 中冶天工集团有限公司 | Internal threading method for spatial large-span prestressed steel structure steel strand |
CN102635238A (en) * | 2012-05-03 | 2012-08-15 | 中国十九冶集团有限公司 | Large-scale coal bunker wall prestress anchor sealing construction method and structure |
CN103669214A (en) * | 2013-11-19 | 2014-03-26 | 中建三局建设工程股份有限公司 | Superlong prestress strand combing, binding and strand pulling integrated device |
JP2015101867A (en) * | 2013-11-22 | 2015-06-04 | 株式会社竹中工務店 | Manufacturing method for exterior panel unit |
CN204475874U (en) * | 2015-03-13 | 2015-07-15 | 中国土木工程集团有限公司 | A kind of novel pre-stressed steel strand draw-gear |
-
2015
- 2015-10-22 CN CN201510687262.4A patent/CN105350782B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561706A (en) * | 2012-03-19 | 2012-07-11 | 中冶天工集团有限公司 | Internal threading method for spatial large-span prestressed steel structure steel strand |
CN102635238A (en) * | 2012-05-03 | 2012-08-15 | 中国十九冶集团有限公司 | Large-scale coal bunker wall prestress anchor sealing construction method and structure |
CN103669214A (en) * | 2013-11-19 | 2014-03-26 | 中建三局建设工程股份有限公司 | Superlong prestress strand combing, binding and strand pulling integrated device |
JP2015101867A (en) * | 2013-11-22 | 2015-06-04 | 株式会社竹中工務店 | Manufacturing method for exterior panel unit |
CN204475874U (en) * | 2015-03-13 | 2015-07-15 | 中国土木工程集团有限公司 | A kind of novel pre-stressed steel strand draw-gear |
Non-Patent Citations (1)
Title |
---|
韩斯明: "储配仓混凝土结构中无粘结预应力施工技术", 《安徽建筑》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112267688A (en) * | 2020-11-24 | 2021-01-26 | 江苏新筑同创土木工程有限公司 | Mechanical auxiliary penetrating method and system for annular unbonded prestressed tendon |
CN115538704A (en) * | 2022-09-19 | 2022-12-30 | 天津熙贝众合预应力工程有限公司 | An installation process of unbonded prestressed steel strands for large-diameter silos with slipform construction |
CN117605286A (en) * | 2024-01-23 | 2024-02-27 | 中国电建集团山东电力建设第一工程有限公司 | Wind power mixing tower prestress steel strand threading tool and method |
Also Published As
Publication number | Publication date |
---|---|
CN105350782B (en) | 2017-12-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102444086B (en) | Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge | |
CN101967796B (en) | Method for arranging parallel steel wire stay cable | |
CN103441451B (en) | A kind of overhead transmission line crosses over wire laying device | |
CN104631329B (en) | A kind of suspension bridge continuous way cat road integral linear method of adjustment | |
CN105350782A (en) | Semi-mechanized steel strand laying method for circular silo | |
CN109973130B (en) | Construction system and method for realizing one-time traction of extra-long tunnel anchor narrow space by main cable strand | |
CN210003305U (en) | Construction system for achieving traction in place in narrow anchor space of ultra-long tunnel in modes | |
CN106401196A (en) | Steel strand tensioning device for pre-stressed anchorage device | |
CN102659043B (en) | Improved dismounting device for buttress rod of tower crane | |
CN105507149A (en) | Arrangement method for cable-hanging of single parallel steel strand wires | |
CN103708371B (en) | The Huan Sheng mechanism that rope drives | |
CN202412091U (en) | Fixing and clamping device used in installation and vulcanization of adhesive tape | |
CN201171147Y (en) | Clamp for vertically mounting ultra-high layer cable | |
CN204199734U (en) | A kind of safe blanket net of automatic control movement | |
CN208416535U (en) | A kind of coal-cutting machine towline protecting apparatus | |
CN107268439B (en) | It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture | |
CN107313786B (en) | Trolley trailer system | |
CN214660350U (en) | Split initial tunneling pipeline extension supporting device of shield tunneling machine | |
CN104505771A (en) | Overhead ground wire lifter | |
CN203602263U (en) | Engineering machine and amplitude-variable pulley block fixing device | |
CN103708370B (en) | The pneumatic lift rope supporting device of mining inclined tunnel | |
CN210238255U (en) | Pushing construction anti-slip reverse-pulling device | |
CN209818062U (en) | Cable dragging device of tunneling machine | |
CN207896560U (en) | A kind of skyscraper cable-laying gear | |
CN205202161U (en) | Rubber belt conveyor primer area laying apparatus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |