[go: up one dir, main page]

CN105337215A - Tool and method for replacing earth electrode circuit corner tension-resistant hardware fitting - Google Patents

Tool and method for replacing earth electrode circuit corner tension-resistant hardware fitting Download PDF

Info

Publication number
CN105337215A
CN105337215A CN201510838017.9A CN201510838017A CN105337215A CN 105337215 A CN105337215 A CN 105337215A CN 201510838017 A CN201510838017 A CN 201510838017A CN 105337215 A CN105337215 A CN 105337215A
Authority
CN
China
Prior art keywords
card
fixedly connected
hardware fitting
steel
rear card
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510838017.9A
Other languages
Chinese (zh)
Other versions
CN105337215B (en
Inventor
陶留海
刘红伟
姜国庆
杨朝锋
张建辉
李忠民
赵龙
樊建军
高嵩
孙惠涛
郭栋
刘阔
郭文博
杨东辉
陈雷
崔磊
李雪奎
尹飞
邵瑰玮
齐征
王洪涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Research Institute Co Ltd CEPRI
Maintenance Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Maintenance Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maintenance Co of State Grid Henan Electric Power Co Ltd filed Critical Maintenance Co of State Grid Henan Electric Power Co Ltd
Priority to CN201510838017.9A priority Critical patent/CN105337215B/en
Publication of CN105337215A publication Critical patent/CN105337215A/en
Application granted granted Critical
Publication of CN105337215B publication Critical patent/CN105337215B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Heat Treatment Of Articles (AREA)
  • Manufacture And Refinement Of Metals (AREA)

Abstract

本发明公开了一种更换接地极线路转角耐张金具的工具及方法,包括前卡、后卡和紧线丝杆,所述前卡设置为两个挂环,所述挂环设置为“U”形,所述挂环一端与横担固定连接,所述后卡一端与三角联板连接,所述紧线丝杠设置在挂环和后卡之间,所述紧线丝杠包括推力轴承、手柄、丝杠、棘轮套管和轴承座,所述推力轴承与挂环另一端固定连接,所述手柄设置在丝杠中部,所述棘轮套管设置在丝杠和轴承座之间并套接在所述丝杠外,所述棘轮套管与轴承座固定连接,所述轴承座与后卡另一端固定连接,所述挂环、后卡和紧线丝杆均采用高强钢材料制成。本发明不仅通用性强、作业方法简便,而且极大的减轻了塔上带电作业人员的工作量,提高了作业效率。

The invention discloses a tool and method for replacing the corner tension-resistant fittings of grounding pole lines, which include a front clamp, a rear clamp and a thread tightening screw rod, the front clamp is set as two hanging rings, and the hanging ring is set as "U "shape, one end of the hanging ring is fixedly connected with the cross arm, one end of the rear card is connected with the triangular connecting plate, the tightening screw is arranged between the hanging ring and the rear card, and the tightening screw includes a thrust bearing , a handle, a lead screw, a ratchet sleeve and a bearing seat, the thrust bearing is fixedly connected to the other end of the hanging ring, the handle is arranged in the middle of the lead screw, and the ratchet sleeve is arranged between the lead screw and the bearing seat Connected to the outside of the lead screw, the ratchet sleeve is fixedly connected to the bearing seat, and the bearing seat is fixedly connected to the other end of the rear card. The hanging ring, the rear card and the tightening screw are all made of high-strength steel . The invention not only has strong versatility and simple and convenient operation method, but also greatly reduces the workload of live workers on the tower and improves the operation efficiency.

Description

一种更换接地极线路转角耐张金具的工具及方法Tool and method for replacing grounding electrode line corner tension fittings

技术领域 technical field

本发明涉及电力作业工具,特别涉及一种更换接地极线路转角耐张金具的工具及方法。 The invention relates to an electric power working tool, in particular to a tool and a method for replacing a corner tension fitting of a ground electrode line.

背景技术 Background technique

随着我国经济的快速发展,特高压直流输电技术以其能够满足远距离、大容量的供电需求而备受关注。常见的直流输电系统有两种运行方式:以单极运行方式和双极运行方式,其中单极运行方式又分金属回线方式和大地(或海水)作为回路的单极大地回路方式,在单极大地回路方式下运行,大地回路流过全部系统电流;双极线路在正常的情况下,大地回路只有不平衡电流流过(其值大约为额定电流的1%左右),但当一根导线或一组换流阀发生故障时,直流系统任可利用大地作为回路作单极运行,为了降低入地电流对换流站电力设备等的影响,接地极一般布置在远离换流站的位置,距离可达数十到上百公里。接地极线路即为连接换流站与接地极线路(一般为架空线路),其安全稳定运行对整个直流系统至关重要。 With the rapid development of my country's economy, UHVDC transmission technology has attracted much attention because it can meet the long-distance and large-capacity power supply needs. Common DC transmission systems have two operating modes: unipolar operating mode and bipolar operating mode, in which the unipolar operating mode is divided into the metal loop mode and the earth (or seawater) as the unipolar-earth loop mode. When operating in the mode of extremely large earth loop, the entire system current flows through the earth loop; under normal conditions for bipolar lines, only unbalanced current flows through the earth loop (the value is about 1% of the rated current), but when a wire Or when a group of converter valves fails, the DC system can use the earth as a loop for unipolar operation. In order to reduce the impact of the ground current on the power equipment of the converter station, the ground electrode is generally arranged far away from the converter station. The distance can reach tens to hundreds of kilometers. The grounding pole line is the line connecting the converter station and the grounding pole line (usually an overhead line), and its safe and stable operation is crucial to the entire DC system.

接地极线路由于其线路结构特点,从换流站至接地极址间的架空线路一般无法沿直线达到,需要蜿蜒避开其他线路走廊,因此转角塔使用较多,而转角塔的金具结构与其他类型的杆塔差异较大,因此尚无专门的工具对其金具进行更换。 Due to the characteristics of the line structure of the grounding pole line, the overhead line from the converter station to the grounding pole site generally cannot be reached along a straight line, and needs to meander to avoid other line corridors, so corner towers are often used, and the fitting structure of the corner tower and Other types of towers are quite different, so there is no special tool to replace their hardware.

公告号CN103500961A公开了一种带电更换耐张绝缘子串专用工具,包括两根平行设置的绝缘绳,所述绝缘绳前后两端分别连接前卡及后卡,所述前卡左右两端通过直线防扭丝杠与绝缘绳前端连接,所述后卡左右两端与绝缘绳后端连,两根绝缘绳之间在后卡前方设有中卡,所述中卡左右两端分别设有一根收紧丝杠与后卡连接,所述前卡后侧通过联接板与耐张绝缘子连接,所述后卡前侧通过联接板与耐张绝缘子连接,这种专用工具在更换绝缘子的过程中无法进行角度的调整,更无法避免金具和横担对工具的干涉,而且这种专用工具结构复杂,不方便工作人员进行更换操作。 The notification number CN103500961A discloses a special tool for live replacement of tension insulator strings, which includes two insulating ropes arranged in parallel. The twisted lead screw is connected to the front end of the insulating rope, the left and right ends of the rear card are connected to the rear end of the insulating rope, and a middle card is arranged in front of the rear card between the two insulating ropes, and a receiving card is provided at the left and right ends of the middle card respectively. The tightening screw is connected to the rear card, the rear side of the front card is connected to the tension insulator through the connecting plate, and the front side of the rear card is connected to the tensile insulator through the connecting plate. This special tool cannot be used in the process of replacing the insulator. The adjustment of the angle can not avoid the interference of the hardware and the cross arm to the tool, and the structure of this special tool is complicated, which is inconvenient for the staff to perform the replacement operation.

发明内容 Contents of the invention

有鉴于此,本发明的目的是针对现有技术的不足,提供了一种更换接地极线路转角耐张金具的工具及方法,不仅通用性强、作业方法简便、轻便灵活,而且极大的减轻了塔上带电作业人员的工作量,提高了作业效率。 In view of this, the object of the present invention is to address the deficiencies of the prior art, and provide a tool and method for replacing the corner tension fittings of the ground electrode line, which not only has strong versatility, simple and convenient operation method, light and flexible, but also greatly reduces the It reduces the workload of live operators on the tower and improves the working efficiency.

为达到上述目的,本发明采用以下技术方案: To achieve the above object, the present invention adopts the following technical solutions:

一种更换接地极线路转角耐张金具的工具,包括前卡、后卡和紧线丝杆,所述前卡设置为两个挂环,所述挂环设置为“U”形,所述挂环一端与横担固定连接,所述后卡一端与三角联板连接,所述紧线丝杠设置在挂环和后卡之间,所述紧线丝杠包括推力轴承、手柄、丝杠、棘轮套管和轴承座,所述推力轴承与挂环另一端固定连接,所述手柄设置在丝杠中部,所述棘轮套管设置在丝杠和轴承座之间并套接在所述丝杠外,所述棘轮套管与轴承座固定连接,所述轴承座与后卡另一端固定连接,所述挂环、后卡和紧线丝杆均采用高强钢材料制成。 A tool for replacing the corner tension fittings of grounding electrode lines, including a front card, a rear card and a thread tightening screw rod, the front card is set as two hanging rings, the hanging ring is set in a "U" shape, and the hanging One end of the ring is fixedly connected with the cross arm, one end of the rear card is connected with the triangular connecting plate, the tightening screw is arranged between the hanging ring and the rear card, and the tightening screw includes a thrust bearing, a handle, a leading screw, A ratchet sleeve and a bearing seat, the thrust bearing is fixedly connected to the other end of the hanging ring, the handle is arranged in the middle of the screw, the ratchet sleeve is arranged between the screw and the bearing seat and is sleeved on the screw In addition, the ratchet sleeve is fixedly connected to the bearing seat, and the bearing seat is fixedly connected to the other end of the rear card. The hanging ring, the rear card and the tightening screw are all made of high-strength steel.

优选的,所述后卡设置为联板后卡,所述联板后卡通过直角挂板与三角联板固定连接。 Preferably, the rear card is set as a joint plate rear card, and the joint plate rear card is fixedly connected to the triangular joint plate through a right-angle hanging plate.

优选的,所述后卡设置为弯钩后卡,所述弯钩后卡一端与轴承座固定连接,另一端与三角联板活动连接。 Preferably, the rear clamp is configured as a hook rear clamp, one end of the hook rear clamp is fixedly connected to the bearing seat, and the other end is movably connected to the triangular connecting plate.

优选的,所述联板后卡两侧分别设置有用于与轴承座固定的第一安装孔,所述联板后卡中部设置有用于与直角挂板和三角联板固定的第二安装孔。 Preferably, first mounting holes for fixing to the bearing housing are respectively provided on both sides of the rear clamp of the connecting plate, and second mounting holes for fixing to the right-angle hanging plate and the triangular connecting plate are provided in the middle of the rear clamp of the connecting plate.

优选的,所述弯钩后卡一端设置有用于与轴承座固定的第三安装孔。 Preferably, one end of the rear clip of the hook is provided with a third installation hole for fixing with the bearing seat.

优选的,所述高强钢按照重量百分比计,包括以下组成成分:C=0.12~0.20%,Si=1.60~1.85%,Mn=0.85~2.3%,Cr=1.85~3.12%,Ni=0.72~1.86%,Mo=0.32~0.86%,Ti=0.08~0.12%,Nb=0.04~0.08%,V=0.12~0.19%,B=0.001~0.0022%,Tm=3.6~4.8%,S=0.002~0.010%,其余为铁和不可避免的杂质。 Preferably, the high-strength steel includes the following components in terms of weight percentage: C=0.12~0.20%, Si=1.60~1.85%, Mn=0.85~2.3%, Cr=1.85~3.12%, Ni=0.72~1.86 %, Mo=0.32~0.86%, Ti=0.08~0.12%, Nb=0.04~0.08%, V=0.12~0.19%, B=0.001~0.0022%, Tm=3.6~4.8%, S=0.002~0.010% , and the rest are iron and unavoidable impurities.

优选的,所述高强钢的制备方法包括以下步骤: Preferably, the preparation method of the high-strength steel comprises the following steps:

(1)称量各种原料,并对块状原料进行30~40min的破碎和研磨; (1) Weigh various raw materials, and crush and grind the bulk raw materials for 30-40 minutes;

(2)将所有原料混合在一起,强制式搅拌机内搅拌30~45min,得到混合原料; (2) Mix all raw materials together and stir in a forced mixer for 30-45 minutes to obtain mixed raw materials;

(3)将步骤(2)所述混合原料置于冶炼炉内于1800~2400℃冶炼35~50min,得到钢液; (3) Put the mixed raw material described in step (2) into a smelting furnace for smelting at 1800-2400°C for 35-50 minutes to obtain molten steel;

(4)将步骤(3)所得钢液倒入铸模中,860~910℃下锻造12~14道次,冷却速度为0.5~1℃/s的水冷降温至350~450℃,再空气冷却至常温,得到钢锭; (4) Pour the molten steel obtained in step (3) into the casting mold, forge at 860~910°C for 12~14 passes, cool down to 350~450°C with water at a cooling rate of 0.5~1°C/s, and then air cool to At room temperature, steel ingots are obtained;

(5)将步骤(4)所得钢锭进行淬火处理:将钢锭加热到800~900℃,保温3~5h,置于空气、水或油中进行冷却至室温; (5) Quenching the steel ingot obtained in step (4): heating the steel ingot to 800-900°C, keeping it warm for 3-5 hours, and cooling it to room temperature in air, water or oil;

(6)将步骤(5)所得钢锭进行回火处理:将淬火处理过的钢锭再加热到550~680℃,保温2~3h,置于空气、水或油中进行冷却至室温。 (6) Tempering the steel ingot obtained in step (5): reheat the quenched steel ingot to 550-680°C, keep it warm for 2-3 hours, and place it in air, water or oil to cool to room temperature.

一种更换接地极线路转角耐张金具的方法,包括以下步骤: A method for replacing a grounding electrode line corner tension fitting, comprising the following steps:

1)将前卡一端固定连接在横担的施工孔处,另一端与推力轴承固定连接,再将轴承座与后卡一端固定连接,后卡另一端与三角联板连接; 1) Fix one end of the front card to the construction hole of the cross arm, and the other end to the thrust bearing, then connect the bearing seat to one end of the rear card, and connect the other end of the rear card to the triangular joint plate;

2)通过手柄适当收紧紧线丝杠并确保工具前后端受力均匀以及紧线丝杠行程合适; 2) Properly tighten the tightening screw through the handle and ensure that the front and rear ends of the tool are evenly stressed and the travel of the tightening screw is appropriate;

3)收紧紧线丝杠使得线路转角耐张金具受力转移到更换工具上即可。 3) Tighten the lead screw so that the force of the line corner tension fitting is transferred to the replacement tool.

本发明的有益效果是: The beneficial effects of the present invention are:

1.本发明采用了紧线丝杆与前、后卡的活动设计,使的紧线丝杆在受到导线水平荷载时能不同角度的发生偏转,保证紧线丝杆所受应力为径向,从而从多个角度达到安全作业的要求,避免金具和横担对更换工具的干涉与影响;本发明采用联板后卡和弯钩后卡两种后卡,在同时保证操作方便和安全可靠的前提下,可以满足不同角度不同类型耐张金具的更换需求,大大增加了更换工具的通用性和实用性;通过在联板后卡和弯钩后卡上加设的安装孔,能使联板后卡和弯钩后卡固定在轴承座和三角联板上,使得联板后卡和弯钩后卡与紧线丝杆以及三角联板形成一体,能有效防止后卡松脱,保证了施工安全;本发明中前卡、后卡和紧线丝杆均采用高强钢材料制成,以高强钢替代普通金属材料提高了工件性能。 1. The present invention adopts the movable design of the tightening screw rod and the front and rear clamps, so that the tightening screw rod can be deflected at different angles when it is subjected to the horizontal load of the wire, ensuring that the stress on the tightening screw rod is radial, Thereby meeting the requirements of safe operation from multiple angles and avoiding the interference and influence of fittings and crossarms on tool replacement; the present invention adopts two types of rear clamps, the joint plate rear clamp and the hook rear clamp, while ensuring convenient operation, safety and reliability. Under the premise, it can meet the replacement requirements of different types of tension fittings at different angles, greatly increasing the versatility and practicability of the replacement tools; through the installation holes added on the rear clip of the connecting plate and the rear clip of the hook, the connecting plate can be The back clip and the hook are fixed on the bearing seat and the triangular link plate, so that the post clip of the link plate, the rear clip of the hook and the tightening screw and the triangular link plate are integrated, which can effectively prevent the back clip from loosening and ensure the construction. Safe; in the present invention, the front clamp, the rear clamp and the tightening screw are all made of high-strength steel materials, and the high-strength steel replaces ordinary metal materials to improve the performance of the workpiece.

2.本发明高强钢的原料中,C做为强化元素,固溶强化和通过低温回火后可以析出亚稳碳化物起到强化的目的;适量的Si可以溶入马氏体基体内,通过固溶强化提高钢的强度;Cr有利于提高钢的淬透性,并通过固溶强化提高钢的强度;Ti、Nb或B的添加能够有效提高钢的淬透性,使钢在经过淬火和回火后具有高的强度;Ni和V能够细化显微组织的尺寸,使晶粒变小,进一步提高钢的强韧度;Mo具有净化晶界、抑制回火脆性的作用,还可通过固溶强化提高钢的强度;稀土元素Tm可以用于脱氧,可防止氧对合金性能的危害,冶炼时可以以中间合金的形式加入;多道次锻造工艺细化了组织及晶粒,并通过中温回火工艺消除了组织内应力,有利于增加钢的强度。 2. In the raw material of the high-strength steel of the present invention, C is used as a strengthening element, solid solution strengthening and metastable carbides can be precipitated after low-temperature tempering to achieve the purpose of strengthening; an appropriate amount of Si can be dissolved in the martensite matrix, through Solid solution strengthening improves the strength of steel; Cr is beneficial to improve the hardenability of steel, and the strength of steel is improved through solid solution strengthening; the addition of Ti, Nb or B can effectively improve the hardenability of steel, so that the steel can be quenched and It has high strength after tempering; Ni and V can refine the size of the microstructure, make the grain smaller, and further improve the strength and toughness of the steel; Mo can purify the grain boundary and inhibit the temper brittleness. Solid solution strengthening improves the strength of steel; the rare earth element Tm can be used for deoxidation, which can prevent the damage of oxygen to the properties of the alloy, and can be added in the form of an intermediate alloy during smelting; the multi-pass forging process refines the structure and grains, and through The medium temperature tempering process eliminates the internal stress of the structure, which is beneficial to increase the strength of the steel.

附图说明 Description of drawings

图1为本发明实施例1的结构示意图; Fig. 1 is the structural representation of embodiment 1 of the present invention;

图2为本发明实施例2的结构示意图; Fig. 2 is the structural representation of embodiment 2 of the present invention;

图3为本发明紧线丝杠的结构示意图; Fig. 3 is the schematic structural view of the tightening lead screw of the present invention;

图4为本发明弯钩后卡的结构示意图; Fig. 4 is a structural schematic diagram of the hook rear card of the present invention;

其中,1-挂环,2-紧线丝杠,3-横担,4-三角联板,5-联板后卡,6-直角挂板,7-第一安装孔,8-第二安装孔,9-弯钩后卡,10-第三安装孔,21-推力轴承,22-手柄,23-丝杠,24-棘轮套管,25-轴承座。 Among them, 1-hanging ring, 2-tightening screw, 3-cross arm, 4-triangular connecting plate, 5-connecting plate rear clamp, 6-right angle hanging plate, 7-first installation hole, 8-second installation Hole, 9-curved hook rear card, 10-the third mounting hole, 21-thrust bearing, 22-handle, 23-leading screw, 24-ratchet sleeve, 25-bearing seat.

具体实施方式 detailed description

下面结合附图和实施例对本发明作进一步描述。 The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

其中本发明高强钢的制备方法中,O、S为有害元素,在高强钢的冶炼过程中须严格控制它们的含量,冶炼过程中除了加入Mn、稀土元素Tm等脱氧元素外,还应严格控制入转炉的钢水或原料中的S含量,采用转炉冶炼或电炉冶炼兑入铁水时,优选使用经预处理脱硫的铁水,在控制入炉原料S的含量的同时,采用LF炉精炼以获得目标O、S含量的钢液。 Among them, in the preparation method of the high-strength steel of the present invention, O and S are harmful elements, and their content must be strictly controlled in the smelting process of the high-strength steel. In the smelting process, in addition to adding deoxidizing elements such as Mn and rare earth elements Tm, the content should also be strictly controlled. The S content in molten steel or raw materials entering the converter, when using converter smelting or electric furnace smelting to add molten iron, preferably use pretreated desulfurized molten iron, while controlling the S content of the raw material into the furnace, use LF furnace refining to obtain the target O , Liquid steel with S content.

实施例1 Example 1

如图1和3所示,一种更换接地极线路转角耐张金具的工具及方法,包括前卡、后卡和紧线丝杆2,其中后卡设置为联板后卡5,其中前卡设置为两个“U”形挂环1,挂环1一端与横担3通过螺栓固定连接,联板后卡5通过设置的第二安装孔8与直角挂板6与三角联板4螺纹固定连接,通过在联板后卡5上加设第二安装孔8可以保证联板后卡5与紧线丝杆2以及三角联板4形成一体,能有效防止联板后卡5松脱,保证了施工安全。 As shown in Figures 1 and 3, a tool and method for replacing the corner tension fittings of the grounding electrode line, including a front clamp, a rear clamp and a thread tightening screw 2, wherein the rear clamp is set as a connecting plate rear clamp 5, wherein the front clamp It is set as two "U"-shaped hanging rings 1, one end of the hanging ring 1 is fixedly connected with the cross arm 3 by bolts, and the rear card 5 of the connecting plate is screwed with the right-angle hanging plate 6 and the triangular connecting plate 4 through the second installation hole 8 provided. Connection, by adding the second installation hole 8 on the back clamp 5 of the joint plate, it can be ensured that the rear clamp 5 of the joint plate is integrated with the tightening screw rod 2 and the triangular joint plate 4, which can effectively prevent the back clamp 5 of the joint plate from getting loose, ensuring construction safety.

紧线丝杠2设置在挂环1和联板后卡5之间,紧线丝杠2包括推力轴承21、手柄22、丝杠23、棘轮套管24和轴承座25,推力轴承21上设置有螺纹孔,通过螺栓固定与挂环1另一端连接,手柄22设置在丝杠23中部,棘轮套管24设置在丝杠23和轴承座25之间并套接在丝杠23外,棘轮套管24与轴承座25一端通过螺栓固定连接,轴承座25另一端设置有螺纹孔,通过螺栓固定联板后卡5上设置的第一安装孔7与联板后卡5固定连接。 The tightening lead screw 2 is arranged between the hanging ring 1 and the back clamp 5 of the connecting plate. The tightening lead screw 2 includes a thrust bearing 21, a handle 22, a leading screw 23, a ratchet sleeve 24 and a bearing seat 25, and the thrust bearing 21 is arranged There is a threaded hole, which is connected to the other end of the hanging ring 1 by bolts. The handle 22 is arranged in the middle of the screw 23. The ratchet sleeve 24 is arranged between the screw 23 and the bearing seat 25 and is sleeved outside the screw 23. The ratchet sleeve Pipe 24 is fixedly connected with bearing seat 25 one end by bolt, and bearing seat 25 other end is provided with threaded hole, and the first installation hole 7 that is provided with on the back card 5 of link plate is fixedly connected with link plate back card 5 by bolt.

挂环1、联板后卡5和紧线丝杆2均采用高强钢材料制成,紧线丝杆2与挂环1、联板后卡5的活动设计,使的紧线丝杆2在受到导线水平荷载时能不同角度的发生偏转,保证紧线丝杆2所受应力为径向,从而从多个角度达到安全作业的要求,避免金具和横担对更换工具的干涉与影响。 The hanging ring 1, the back clamp 5 of the connecting plate and the tightening screw rod 2 are all made of high-strength steel material. It can be deflected at different angles when subjected to the horizontal load of the wire, ensuring that the stress on the tightening screw 2 is radial, so as to meet the requirements of safe operation from multiple angles, and avoid the interference and influence of fittings and cross arms on the replacement tool.

本实施例在使用时: When this embodiment is in use:

首先将挂环1通过螺栓固定连接在横担3的施工孔处,通过推力轴承21上设置有螺纹孔与挂环1螺栓固定连接,通过轴承座25上设置有螺纹孔与联板后卡5上设置的第一安装孔7螺栓固定连接,再将联板后卡5通过设置的第二安装孔8与直角挂板6与三角联板4螺纹固定连接,然后通过手柄22适当收紧紧线丝杠2并确保卡具前后端受力均匀以及紧线丝杠2行程合适,最后只收紧紧线丝杠2使得线路转角耐张金具受力转移到本更换工具上即可。 First, the hanging ring 1 is fixedly connected to the construction hole of the cross arm 3 through bolts, and the threaded hole is provided on the thrust bearing 21 to be fixedly connected to the hanging ring 1 by bolts. The first mounting hole 7 set on the top is fixedly connected with bolts, and then the rear card 5 of the connecting plate is fixedly connected with the second mounting hole 8 provided with the right angle hanging plate 6 and the triangular connecting plate 4, and then the handle 22 is used to properly tighten the thread. Screw 2 and ensure that the front and rear ends of the fixture are evenly stressed and the stroke of the tightening screw 2 is appropriate. Finally, only the tightening screw 2 is tightened so that the force of the line corner tension fittings can be transferred to the replacement tool.

其中,高强钢按照重量百分比计,包括以下组成成分:C=0.12%,Si=1.60%,Mn=0.85~2.3%,Cr=1.85%,Ni=0.72%,Mo=0.32%,Ti=0.08%,Nb=0.04%,V=0.12%,B=0.001%,Tm=3.6%,S=0.002%,其余为铁和不可避免的杂质。 Among them, the high-strength steel includes the following components in terms of weight percentage: C=0.12%, Si=1.60%, Mn=0.85~2.3%, Cr=1.85%, Ni=0.72%, Mo=0.32%, Ti=0.08% , Nb=0.04%, V=0.12%, B=0.001%, Tm=3.6%, S=0.002%, and the rest are iron and unavoidable impurities.

高强钢的制备方法包括以下步骤: The preparation method of high-strength steel comprises the following steps:

(1)称量各种原料,并对块状原料进行30min的破碎和研磨; (1) Weigh various raw materials, and crush and grind the bulk raw materials for 30 minutes;

(2)将所有原料混合在一起,强制式搅拌机内搅拌30min,得到混合原料; (2) Mix all raw materials together and stir in a forced mixer for 30 minutes to obtain mixed raw materials;

(3)将步骤(2)所述混合原料置于冶炼炉内于1800℃冶炼35~50min,得到钢液; (3) Put the mixed raw materials in step (2) into a smelting furnace for smelting at 1800°C for 35-50 minutes to obtain molten steel;

(4)将步骤(3)所得钢液倒入铸模中,860℃下锻造12道次,冷却速度为0.5℃/s的水冷降温至350℃,再空气冷却至常温,得到钢锭; (4) Pour the molten steel obtained in step (3) into the casting mold, forge 12 passes at 860°C, cool down to 350°C by water cooling at a cooling rate of 0.5°C/s, and then air cool to room temperature to obtain a steel ingot;

(5)将步骤(4)所得钢锭进行淬火处理:将钢锭加热到800℃,保温3h,置于空气、水或油中进行冷却至室温; (5) Quenching the steel ingot obtained in step (4): heating the steel ingot to 800°C, keeping it warm for 3 hours, and cooling it to room temperature in air, water or oil;

(6)将步骤(5)所得钢锭进行回火处理:将淬火处理过的钢锭再加热到550℃,保温2h,置于空气、水或油中进行冷却至室温。 (6) Tempering the steel ingot obtained in step (5): reheat the quenched steel ingot to 550° C., keep it warm for 2 hours, and place it in air, water or oil to cool to room temperature.

实施例2 Example 2

实施例2中各部件与实施例1所用的高强钢材料相同,不同的是:如图2~4所示,后卡设置为弯钩后卡9,弯钩后卡9一端通过设置的第三安装孔10与轴承座25螺纹固定连接,通过在弯钩后卡9上加设第三安装孔10可以保证弯钩后卡9与紧线丝杆2以及三角联板4形成一体,能有效防止弯钩后卡9松脱,保证了施工安全,另一端直接勾住三角联板4的长边,这样可以避免了大角度旋转的三角联板4对卡具的影响。 The components in Embodiment 2 are the same as the high-strength steel materials used in Embodiment 1. The difference is that: as shown in Figures 2 to 4, the rear clamp is set as a hook rear clamp 9, and one end of the hook rear clamp 9 passes through the third set. Mounting hole 10 is threaded and fixedly connected with bearing seat 25. By adding a third mounting hole 10 on the hook rear clip 9, it can be ensured that the hook rear clip 9 is integrated with the tightening wire rod 2 and the triangular connecting plate 4, which can effectively prevent After the crotch, the card 9 is loosened, which ensures the construction safety, and the other end directly hooks the long side of the triangular connecting plate 4, which can avoid the influence of the large-angle rotating triangular connecting plate 4 on the fixture.

本实施例在使用时: When this embodiment is in use:

首先将挂环1通过螺栓固定连接在横担3的施工孔处,通过推力轴承21上设置有螺纹孔与挂环1螺栓固定连接,通过轴承座25上设置有螺纹孔与弯钩后卡9一端设置的第三安装孔10螺栓固定连接,再将弯钩后卡9另一端直接勾住三角联板4的长边,然后通过手柄22适当收紧紧线丝杠2并确保卡具前后端受力均匀以及紧线丝杠2行程合适,最后只收紧紧线丝杠2使得线路转角耐张金具受力转移到本更换工具上即可。 First, the hanging ring 1 is fixedly connected to the construction hole of the cross arm 3 through bolts, and the threaded hole is provided on the thrust bearing 21 to be fixedly connected to the hanging ring 1 by bolts. The third mounting hole 10 provided at one end is fixedly connected by bolts, and then the other end of the hook rear clamp 9 is directly hooked to the long side of the triangular joint plate 4, and then the thread screw 2 is properly tightened by the handle 22 to ensure that the front and rear ends of the clamp are The force is uniform and the stroke of the tightening lead screw 2 is suitable. Finally, only the tightening lead screw 2 is tightened so that the tension force of the line corner tension fittings can be transferred to the replacement tool.

实施例3 Example 3

实施例3与实施例1的结构以及使用方法大致形同,不同的是: The structure and method of use of embodiment 3 and embodiment 1 are roughly the same, the difference is:

其中,高强钢按照重量百分比计,包括以下组成成分:C=0.20%,Si=1.85%,Mn=0.85~2.3%,Cr=3.12%,Ni=1.86%,Mo=0.86%,Ti=0.12%,Nb=0.08%,V=0.19%,B=0.0022%,Tm=4.8%,S=0.010%,其余为铁和不可避免的杂质。 Among them, the high-strength steel includes the following components in terms of weight percentage: C=0.20%, Si=1.85%, Mn=0.85~2.3%, Cr=3.12%, Ni=1.86%, Mo=0.86%, Ti=0.12% , Nb=0.08%, V=0.19%, B=0.0022%, Tm=4.8%, S=0.010%, and the rest are iron and unavoidable impurities.

高强钢的制备方法包括以下步骤: The preparation method of high-strength steel comprises the following steps:

(1)称量各种原料,并对块状原料进行40min的破碎和研磨; (1) Weigh various raw materials, and crush and grind the bulk raw materials for 40 minutes;

(2)将所有原料混合在一起,强制式搅拌机内搅拌45min,得到混合原料; (2) Mix all raw materials together and stir in a forced mixer for 45 minutes to obtain mixed raw materials;

(3)将步骤(2)所述混合原料置于冶炼炉内于2400℃冶炼50min,得到钢液; (3) Put the mixed raw material described in step (2) into a smelting furnace and smelt at 2400°C for 50 minutes to obtain molten steel;

(4)将步骤(3)所得钢液倒入铸模中,910℃下锻造14道次,冷却速度为1℃/s的水冷降温至450℃,再空气冷却至常温,得到钢锭; (4) Pour the molten steel obtained in step (3) into the casting mold, forge 14 passes at 910°C, cool down to 450°C by water cooling at a cooling rate of 1°C/s, and then air cool to room temperature to obtain a steel ingot;

(5)将步骤(4)所得钢锭进行淬火处理:将钢锭加热到900℃,保温5h,置于空气、水或油中进行冷却至室温; (5) Quenching the steel ingot obtained in step (4): heating the steel ingot to 900°C, keeping it warm for 5 hours, and cooling it to room temperature in air, water or oil;

(6)将步骤(5)所得钢锭进行回火处理:将淬火处理过的钢锭再加热到680℃,保温3h,置于空气、水或油中进行冷却至室温。 (6) Tempering the steel ingot obtained in step (5): reheat the quenched steel ingot to 680° C., keep it warm for 3 hours, and place it in air, water or oil to cool to room temperature.

实施例4 Example 4

实施例4与实施例1的结构以及使用方法大致形同,不同的是: Embodiment 4 is roughly the same in structure and method of use as Embodiment 1, except that:

其中,高强钢按照重量百分比计,包括以下组成成分:C=0.18%,Si=1.68%,Mn=1.85%,Cr=2.12%,Ni=1.06%,Mo=0.53%,Ti=0.09%,Nb=0.06%,V=0.17%,B=0.0015%,Tm=3.9%,S=0.006%,其余为铁和不可避免的杂质。 Among them, the high-strength steel includes the following components in terms of weight percentage: C=0.18%, Si=1.68%, Mn=1.85%, Cr=2.12%, Ni=1.06%, Mo=0.53%, Ti=0.09%, Nb =0.06%, V=0.17%, B=0.0015%, Tm=3.9%, S=0.006%, and the rest are iron and unavoidable impurities.

高强钢的制备方法包括以下步骤: The preparation method of high-strength steel comprises the following steps:

(1)称量各种原料,并对块状原料进行36min的破碎和研磨; (1) Weigh various raw materials, and crush and grind the bulk raw materials for 36 minutes;

(2)将所有原料混合在一起,强制式搅拌机内搅拌38min,得到混合原料; (2) Mix all raw materials together and stir in a forced mixer for 38 minutes to obtain mixed raw materials;

(3)将步骤(2)所述混合原料置于冶炼炉内于1900℃冶炼40min,得到钢液; (3) Put the mixed raw material described in step (2) into a smelting furnace for smelting at 1900°C for 40 minutes to obtain molten steel;

(4)将步骤(3)所得钢液倒入铸模中,890℃下锻造13道次,冷却速度为0.8℃/s的水冷降温至380℃,再空气冷却至常温,得到钢锭; (4) Pour the molten steel obtained in step (3) into a casting mold, forge 13 passes at 890°C, cool down to 380°C with water at a cooling rate of 0.8°C/s, and then air cool to room temperature to obtain a steel ingot;

(5)将步骤(4)所得钢锭进行淬火处理:将钢锭加热到880℃,保温4h,置于空气、水或油中进行冷却至室温; (5) Quenching the steel ingot obtained in step (4): heating the steel ingot to 880°C, keeping it warm for 4 hours, and cooling it to room temperature in air, water or oil;

(6)将步骤(5)所得钢锭进行回火处理:将淬火处理过的钢锭再加热到590℃,保温2h,置于空气、水或油中进行冷却至室温。 (6) Tempering the steel ingot obtained in step (5): reheat the quenched steel ingot to 590° C., keep it warm for 2 hours, and place it in air, water or oil to cool to room temperature.

实施例5 Example 5

实施例5与实施例1的结构以及使用方法大致相同,不同的是: The structure and method of use of embodiment 5 and embodiment 1 are roughly the same, the difference is:

其中,高强钢按照重量百分比计,包括以下组成成分:C=0.15%,Si=1.77%,Mn=1.68%,Cr=2.64%,Ni=1.69%,Mo=0.72%,Ti=0.12%,Nb=0.07%,V=0.15%,B=0.0017%,Tm=4.3%,S=0.007%,其余为铁和不可避免的杂质。 Among them, the high-strength steel includes the following components in terms of weight percentage: C=0.15%, Si=1.77%, Mn=1.68%, Cr=2.64%, Ni=1.69%, Mo=0.72%, Ti=0.12%, Nb =0.07%, V=0.15%, B=0.0017%, Tm=4.3%, S=0.007%, and the rest are iron and unavoidable impurities.

高强钢的制备方法包括以下步骤: The preparation method of high-strength steel comprises the following steps:

(1)称量各种原料,并对块状原料进行32min的破碎和研磨; (1) Weigh various raw materials, and crush and grind the bulk raw materials for 32 minutes;

(2)将所有原料混合在一起,强制式搅拌机内搅拌38min,得到混合原料; (2) Mix all raw materials together and stir in a forced mixer for 38 minutes to obtain mixed raw materials;

(3)将步骤(2)所述混合原料置于冶炼炉内于2200℃冶炼46min,得到钢液; (3) Put the mixed raw material described in step (2) into a smelting furnace for smelting at 2200°C for 46 minutes to obtain molten steel;

(4)将步骤(3)所得钢液倒入铸模中,880℃下锻造14道次,冷却速度为0.8℃/s的水冷降温至425℃,再空气冷却至常温,得到钢锭; (4) Pour the molten steel obtained in step (3) into the casting mold, forge 14 passes at 880°C, cool down to 425°C by water cooling at a cooling rate of 0.8°C/s, and then air cool to room temperature to obtain a steel ingot;

(5)将步骤(4)所得钢锭进行淬火处理:将钢锭加热到860℃,保温3.5h,置于空气、水或油中进行冷却至室温; (5) Quenching the steel ingot obtained in step (4): heat the steel ingot to 860°C, keep it warm for 3.5 hours, and place it in air, water or oil to cool to room temperature;

(6)将步骤(5)所得钢锭进行回火处理:将淬火处理过的钢锭再加热到650℃,保温3h,置于空气、水或油中进行冷却至室温。 (6) Tempering the steel ingot obtained in step (5): reheat the quenched steel ingot to 650° C., keep it warm for 3 hours, and place it in air, water or oil to cool to room temperature.

实施例6 Example 6

实施例6与实施例1的结构以及使用方法大致相同,不同的是: The structure and method of use of embodiment 6 and embodiment 1 are roughly the same, the difference is:

其中,高强钢按照重量百分比计,包括以下组成成分:C=0.20%,Si=1.70%,Mn=2.2%,Cr=2.67%,Ni=1.34%,Mo=0.68%,Ti=0.09%,Nb=0.05%,V=0.17%,B=0.0019%,Tm=3.8%,S=0.0075%,其余为铁和不可避免的杂质。 Among them, the high-strength steel includes the following components in terms of weight percentage: C=0.20%, Si=1.70%, Mn=2.2%, Cr=2.67%, Ni=1.34%, Mo=0.68%, Ti=0.09%, Nb =0.05%, V=0.17%, B=0.0019%, Tm=3.8%, S=0.0075%, and the rest are iron and unavoidable impurities.

高强钢的制备方法包括以下步骤: The preparation method of high-strength steel comprises the following steps:

(1)称量各种原料,并对块状原料进行34min的破碎和研磨; (1) Weigh various raw materials, and crush and grind the bulk raw materials for 34 minutes;

(2)将所有原料混合在一起,强制式搅拌机内搅拌38min,得到混合原料; (2) Mix all raw materials together and stir in a forced mixer for 38 minutes to obtain mixed raw materials;

(3)将步骤(2)所述混合原料置于冶炼炉内于2300℃冶炼43min,得到钢液; (3) Put the mixed raw material described in step (2) into a smelting furnace for smelting at 2300°C for 43 minutes to obtain molten steel;

(4)将步骤(3)所得钢液倒入铸模中,890℃下锻造14道次,冷却速度为0.9℃/s的水冷降温至420℃,再空气冷却至常温,得到钢锭; (4) Pour the molten steel obtained in step (3) into the casting mold, forge 14 passes at 890°C, cool down to 420°C by water cooling at a cooling rate of 0.9°C/s, and then air cool to room temperature to obtain a steel ingot;

(5)将步骤(4)所得钢锭进行淬火处理:将钢锭加热到880℃,保温5h,置于空气、水或油中进行冷却至室温; (5) Quenching the steel ingot obtained in step (4): heating the steel ingot to 880°C, keeping it warm for 5 hours, and cooling it to room temperature in air, water or oil;

(6)将步骤(5)所得钢锭进行回火处理:将淬火处理过的钢锭再加热到680℃,保温3h,置于空气、水或油中进行冷却至室温。 (6) Tempering the steel ingot obtained in step (5): reheat the quenched steel ingot to 680° C., keep it warm for 3 hours, and place it in air, water or oil to cool to room temperature.

对本发明中实施例1~6制备的高强钢材料从抗拉强度Rm(MPa)、屈服强度RP0.2(MPa)、延伸率(%)和冲击功(-20℃,J)进行性能测试,测试结果见下表一。 The properties of the high-strength steel materials prepared in Examples 1-6 of the present invention are evaluated from tensile strength R m (MPa), yield strength R P0.2 (MPa), elongation (%) and impact energy (-20°C, J) The test results are shown in Table 1 below.

表一为不同实施例制备出的高强钢性能参数: Table 1 shows the performance parameters of high-strength steel prepared by different embodiments:

总之,本发明制造的高强钢具有高的强度和韧性,不容易发生断裂和塑性变形;另外由于钢的强度和韧性高,有利于减少构件中钢材的用量,进而降低了本发明更换接地极线路转角耐张金具的工具的制造成本和它的重量,大幅提高了更换工具的耐冲击性能和断裂韧性,同时,该钢具有优良的疲劳强度和耐磨性,极大提高了更换工具的使用寿命;而且,本发明更换接地极线路转角耐张金具的工具,不仅通用性强、作业方法简便、轻便灵活,而且极大的减轻了塔上带电作业人员的工作量,提高了作业效率。 In short, the high-strength steel produced by the present invention has high strength and toughness, and is not prone to fracture and plastic deformation; in addition, due to the high strength and toughness of the steel, it is beneficial to reduce the amount of steel used in the components, thereby reducing the cost of replacing the ground electrode circuit in the present invention. The manufacturing cost and weight of the tool of corner tension-resistant metal fittings greatly improve the impact resistance and fracture toughness of the replacement tool. At the same time, the steel has excellent fatigue strength and wear resistance, which greatly improves the service life of the replacement tool. ; And, the present invention replaces the tool of ground pole circuit corner tension-resistant fittings, not only versatility is strong, operation method is simple, light and flexible, and greatly alleviated the workload of live operator on the tower, improved operating efficiency.

最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,本领域普通技术人员对本发明的技术方案所做的其他修改或者等同替换,只要不脱离本发明技术方案的精神和范围,均应涵盖在本发明的权利要求范围当中。 Finally, it is noted that the above embodiments are only used to illustrate the technical solution of the present invention and not to limit it. Those of ordinary skill in the art may make other modifications or equivalent replacements to the technical solution of the present invention, as long as they do not depart from the spirit and spirit of the technical solution of the present invention. All should be included in the scope of the claims of the present invention.

Claims (8)

1. change the instrument of ground electrode circuit corner strain hardware fitting for one kind, it is characterized in that: comprise front card, rear card and thread-tightening lead screw, before described, card is set to two links, described link is set to " U " shape, described link one end is fixedly connected with cross-arm, described rear card one end is connected with triangle yoke plate, described Wire tensioning screw is arranged between link and rear card, described Wire tensioning screw comprises thrust bearing, handle, leading screw, ratchet casing tube and bearing pedestal, described thrust bearing is fixedly connected with the link other end, described handle is arranged in the middle part of leading screw, described ratchet casing tube to be arranged between leading screw and bearing pedestal and to be socketed in outside described leading screw, described ratchet casing tube is fixedly connected with bearing pedestal, described bearing pedestal is fixedly connected with the rear card other end, described link, rear card and thread-tightening lead screw all adopt high-strength steel material to make.
2. a kind of instrument changing ground electrode circuit corner strain hardware fitting as claimed in claim 1, is characterized in that: block after described rear card is set to yoke plate, and after described yoke plate, cartoon is crossed right angle link plate and is fixedly connected with triangle yoke plate.
3. a kind of instrument changing ground electrode circuit corner strain hardware fitting as claimed in claim 1, is characterized in that: block after described rear card is set to crotch, after described crotch, card one end is fixedly connected with bearing pedestal, and the other end is flexibly connected with triangle yoke plate.
4. a kind of instrument changing ground electrode circuit corner strain hardware fitting as claimed in claim 2, it is characterized in that: after described yoke plate, card both sides are respectively arranged with for first installing hole fixing with bearing pedestal, after described yoke plate card middle part be provided with for right angle link plate and fixing the second installing hole of triangle yoke plate.
5. a kind of instrument changing ground electrode circuit corner strain hardware fitting as claimed in claim 3, is characterized in that: after described crotch, card one end is provided with for three installing hole fixing with bearing pedestal.
6. a kind of instrument changing ground electrode circuit corner strain hardware fitting as claimed in claim 1, it is characterized in that: described high-strength steel is according to weight percent meter, comprise following constituent: C=0.12 ~ 0.20%, Si=1.60 ~ 1.85%, Mn=0.85 ~ 2.3%, Cr=1.85 ~ 3.12%, Ni=0.72 ~ 1.86%, Mo=0.32 ~ 0.86%, Ti=0.08 ~ 0.12%, Nb=0.04 ~ 0.08%, V=0.12 ~ 0.19%, B=0.001 ~ 0.0022%, Tm=3.6 ~ 4.8%, S=0.002 ~ 0.010%, all the other are iron and inevitable impurity.
7. a kind of instrument changing ground electrode circuit corner strain hardware fitting as described in claim 1 or 6, is characterized in that: the preparation method of described high-strength steel comprises the following steps:
(1) weigh various raw material, and fragmentation and the grinding of 30 ~ 40min are carried out to block stock;
(2) all raw materials are mixed, stir 30 ~ 45min in forced mixer, obtain mixed material;
(3) step (2) described mixed material is placed in smelting furnace and smelts 35 ~ 50min in 1800 ~ 2400 DEG C, obtain molten steel;
(4) pour in mold by step (3) gained molten steel, forge 12 ~ 14 passages at 860 ~ 910 DEG C, cooling rate is water-cooled cooling to 350 ~ 450 DEG C of 0.5 ~ 1 DEG C/s, then Air flow is to normal temperature, obtains steel ingot;
(5) step (4) gained steel ingot is carried out Quenching Treatment: by Heating Steel Ingots to 800 ~ 900 DEG C, insulation 3 ~ 5h, is placed in air, water or oil and carries out being cooled to room temperature;
(6) step (5) gained steel ingot is carried out temper: steel ingot Quenching Treatment crossed is heated to 550 ~ 680 DEG C again, insulation 2 ~ 3h, is placed in air, water or oil and carries out being cooled to room temperature.
8. the method changing ground electrode circuit corner strain hardware fitting as claimed in claim 1, is characterized in that: comprise the following steps:
1) front card one end is fixedly connected on the construction hole place of cross-arm, the other end is fixedly connected with thrust bearing, then is fixedly connected with rear card one end by bearing pedestal, and the rear card other end is connected with triangle yoke plate;
2) suitably tighten up Wire tensioning screw by handle and guarantee instrument front and back end uniform force and Wire tensioning screw stroke suitable;
3) tighten up Wire tensioning screw and make that circuit corner strain hardware fitting is stressed to be transferred on replacing instrument.
CN201510838017.9A 2015-11-26 2015-11-26 A kind of tool and method for replacing ground electrode circuit corner strain hardware fitting Active CN105337215B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510838017.9A CN105337215B (en) 2015-11-26 2015-11-26 A kind of tool and method for replacing ground electrode circuit corner strain hardware fitting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510838017.9A CN105337215B (en) 2015-11-26 2015-11-26 A kind of tool and method for replacing ground electrode circuit corner strain hardware fitting

Publications (2)

Publication Number Publication Date
CN105337215A true CN105337215A (en) 2016-02-17
CN105337215B CN105337215B (en) 2018-11-02

Family

ID=55287590

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510838017.9A Active CN105337215B (en) 2015-11-26 2015-11-26 A kind of tool and method for replacing ground electrode circuit corner strain hardware fitting

Country Status (1)

Country Link
CN (1) CN105337215B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106786172A (en) * 2017-03-28 2017-05-31 国网河南省电力公司检修公司 A kind of replacing device for insulator
CN107069542A (en) * 2017-03-28 2017-08-18 国网河南省电力公司检修公司 A kind of insulator steel cap fixture
CN108072950A (en) * 2016-11-16 2018-05-25 刘伟华 Optical fiber cable fitting replaces stent
CN108448488A (en) * 2018-05-25 2018-08-24 国网河南省电力公司检修公司 840kN grade tension quadruple cross-arm side insulator replacement tool and method
CN108711778A (en) * 2018-05-25 2018-10-26 国网河南省电力公司检修公司 Six strain insulator of 550kN grades replaces tool and method
CN113381340A (en) * 2021-06-16 2021-09-10 国网山西省电力公司检修分公司 A turn over board card for extra-high voltage line changes insulator
CN114123027A (en) * 2021-11-24 2022-03-01 国网江苏省电力有限公司检修分公司 Steel tube tower linear double-I-string clamp and operation method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102163827A (en) * 2011-01-30 2011-08-24 江苏捷凯电力器材有限公司 Strain insulator string for multi-division transmission line
CN103618251A (en) * 2013-11-27 2014-03-05 国家电网公司 Technology for electrified overhaul of +-800kV ultrahigh voltage direct-current transmission line
CN104682266A (en) * 2015-03-18 2015-06-03 湖北省超能超高压电力科技开发有限公司 Change tool and change technology for ultra-high-voltage strain insulator string
CN205159910U (en) * 2015-11-26 2016-04-13 国网河南省电力公司检修公司 A tool for replacing the corner tension fittings of grounding electrode lines

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102163827A (en) * 2011-01-30 2011-08-24 江苏捷凯电力器材有限公司 Strain insulator string for multi-division transmission line
CN103618251A (en) * 2013-11-27 2014-03-05 国家电网公司 Technology for electrified overhaul of +-800kV ultrahigh voltage direct-current transmission line
CN104682266A (en) * 2015-03-18 2015-06-03 湖北省超能超高压电力科技开发有限公司 Change tool and change technology for ultra-high-voltage strain insulator string
CN205159910U (en) * 2015-11-26 2016-04-13 国网河南省电力公司检修公司 A tool for replacing the corner tension fittings of grounding electrode lines

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108072950A (en) * 2016-11-16 2018-05-25 刘伟华 Optical fiber cable fitting replaces stent
CN106786172A (en) * 2017-03-28 2017-05-31 国网河南省电力公司检修公司 A kind of replacing device for insulator
CN107069542A (en) * 2017-03-28 2017-08-18 国网河南省电力公司检修公司 A kind of insulator steel cap fixture
CN107069542B (en) * 2017-03-28 2018-08-24 国网河南省电力公司检修公司 A kind of insulator steel cap fixture
CN108448488A (en) * 2018-05-25 2018-08-24 国网河南省电力公司检修公司 840kN grade tension quadruple cross-arm side insulator replacement tool and method
CN108711778A (en) * 2018-05-25 2018-10-26 国网河南省电力公司检修公司 Six strain insulator of 550kN grades replaces tool and method
CN113381340A (en) * 2021-06-16 2021-09-10 国网山西省电力公司检修分公司 A turn over board card for extra-high voltage line changes insulator
CN114123027A (en) * 2021-11-24 2022-03-01 国网江苏省电力有限公司检修分公司 Steel tube tower linear double-I-string clamp and operation method thereof
CN114123027B (en) * 2021-11-24 2024-03-01 国网江苏省电力有限公司检修分公司 Steel pipe tower straight line double-I-string clamp and operation method thereof

Also Published As

Publication number Publication date
CN105337215B (en) 2018-11-02

Similar Documents

Publication Publication Date Title
CN105337215B (en) A kind of tool and method for replacing ground electrode circuit corner strain hardware fitting
CN105063433B (en) A kind of high-conductivity heat-resistant aluminum alloy monofilament and preparation method thereof
CN111349820B (en) High-conductivity heat-resistant Al-Zr-Er alloy wire material and preparation method thereof
CN105609155B (en) A kind of high-conductivity hard aluminum wire monofilament and preparation method thereof
CN104532143A (en) Mining large-specification and high-strength chain steel and preparation method thereof
CN105803276A (en) a conductive monofilament
CN104894438B (en) A kind of high conductivity heat-resisting aluminium alloy monofilament material and preparation method thereof
CN104726783B (en) A kind of wind power yawing, pitch variable bearings lasso steel and preparation method thereof
CN108588555B (en) Alloy steel for overhead conductor, preparation method of alloy steel and overhead conductor
CN101988147A (en) Treatment method for welding zone of high-performance sulfur-resisting drill pipe body and joint
CN108559874A (en) A kind of heat-resistant aluminum alloy wire of high-strength highly-conductive and preparation method thereof
CN105695808A (en) Aluminum alloy wire
CN205159910U (en) A tool for replacing the corner tension fittings of grounding electrode lines
CN101109059A (en) A high resistivity and high magnetic permeability martensite-ferrite duplex stainless steel and its heat treatment process
CN104928590B (en) Mn-Si-Cr low carbon bainitic steel, and Mn-Si-Cr low carbon drill rod and preparation method thereof
CN104532067A (en) Non-heat treatment medium-strength aluminum alloy conductor material and preparation method thereof
CN102230134A (en) Quaternary marine mooring chain steel with large specification and high performance and machining process thereof
CN110578074A (en) Super heat-resistant aluminum alloy single wire and preparation method thereof
CN104862605B (en) A kind of low yield ratio weathering resistant wind-power tower steel and production method
CN104264003A (en) Stretch-proof energy-saving aluminum alloy conductor and preparation method thereof
CN107086487A (en) A hanging point device for transfer tackle
CN110373584A (en) Strength aluminium alloy monofilament and preparation method thereof in a kind of high conductivity
CN115572900A (en) Sulfide stress corrosion resistant oil casing and preparation method thereof
CN102108462A (en) Aluminium alloy material and preparation method and application thereof
CN103114249A (en) Method for producing medium-wall 20G seamless steel pipe by using controlled rolling instead of normalizing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Tao Liuhai

Inventor after: Gao Song

Inventor after: Sun Huitao

Inventor after: Guo Dong

Inventor after: Liu Kuo

Inventor after: Guo Wenbo

Inventor after: Yang Donghui

Inventor after: Chen Lei

Inventor after: Cui Lei

Inventor after: Li Xuekui

Inventor after: Yin Fei

Inventor after: Liu Hongwei

Inventor after: Shao Guiwei

Inventor after: Qi Zheng

Inventor after: Wang Hongtao

Inventor after: Jiang Guoqing

Inventor after: Yang Chaofeng

Inventor after: Zhang Jianhui

Inventor after: Li Zhongmin

Inventor after: Tang Pan

Inventor after: Zhao Long

Inventor after: Fan Jianjun

Inventor before: Tao Liuhai

Inventor before: Sun Huitao

Inventor before: Guo Dong

Inventor before: Liu Kuo

Inventor before: Guo Wenbo

Inventor before: Yang Donghui

Inventor before: Chen Lei

Inventor before: Cui Lei

Inventor before: Li Xuekui

Inventor before: Yin Fei

Inventor before: Shao Guiwei

Inventor before: Liu Hongwei

Inventor before: Qi Zheng

Inventor before: Wang Hongtao

Inventor before: Jiang Guoqing

Inventor before: Yang Chaofeng

Inventor before: Zhang Jianhui

Inventor before: Li Zhongmin

Inventor before: Zhao Long

Inventor before: Fan Jianjun

Inventor before: Gao Song

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160316

Address after: 450006 Huaihe Road, Zhongyuan District, Henan, China, No. 40, No.

Applicant after: MAINTENANCE COMPANY OF STATE GRID HENAN ELECTRIC POWER COMPANY

Applicant after: China Electric Power Research Institute

Address before: 450006 Huaihe Road, Zhongyuan District, Henan, China, No. 40, No.

Applicant before: MAINTENANCE COMPANY OF STATE GRID HENAN ELECTRIC POWER COMPANY

GR01 Patent grant